Trainer: Anand BobadePMBOK 6th Edition, 2019, All rights reserved.
Perform Integrated
change Control
Chapter 5 –
Project Integration Management
PMP SIXTH EDITION
PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com)
4.6 Perform Integrated Change Control
Overview
Change request process
Perform Integrated Change Control definition
Perform Integrated Change Control - ITTO
What is Change Control board?
What is Configuration Management System?
Review
PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com)
Integration Management processes
Develop Project
Charter
Develop Project
Management plan
Direct and Manage
Project work
Manage Knowledge
Monitor & Control
Project Work
Perform Integrated
change Control
Close Project or
phase
I P EE
MC CMC
PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com)
Perform Integrated Change Control
Any stakeholder can request changes on the project
Project
sponsor
Perform Integrated
change Control
Always look at project
objective.
Coordinate changes
across the project.
Ensure changes are
controlled.
PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com)
Submit CR to PM
Evaluate CR
•Approve or Reject
Detailed evaluation
•Impact /Options Analysis
•Recommendations
Present in CCB
•Reject /Approve
•Defer
Update plan &
documents,
communicate
Implement Change
(Execution - D&M)
Communicate to
Stakeholder
Perform Integrated Change Control -> Change control Process
PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com)
Change Control
Board (CCB)
Change Control
System (CCS)
Change Control Tools
Configuration
Management System
Perform Integrated Change Control -> Key terms
PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com)
Change Control Board (CCB):
A formally chartered group responsible for reviewing, evaluating,
approving/rejecting changes to project. Also, responsible for recording
& communicating.
Perform Integrated Change Control -> Key terms -> CCB
Change Approver
(Matrix should be defined in
PMP-change control plan)
Change Control Board
Responsible Authority
Customer or Sponsor
Project Manager (small
changes as agreed in PMP)
Change Control
Board
Change Request can be:
Approved Denied Returned for info Delayed
PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com)
Change Control system (CCS):
• A set of procedures that describes how
modifications to the project deliverables and
documentation are managed and controlled.
• Includes Change control Policy, Setting up CCB.
Change Control Tools:
• Manual or automated tools to assist with
change & configuration management.
• At least tools should support activities of the
CCB.
Perform Integrated Change Control-> Key Terms
PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com)
Change Control Tools:
• Manual or automated tools to assist with change & configuration management.
HP- PPM (Project &
Portfolio Management)
Microsoft SharePoint
Perform Integrated Change Control-> Change Control Tools
Project Manager:
Define formal
change process
Ensure proper
documentation
Ensure changes are
introduced in a controlled
& coordinated manner.
PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com)
Configuration Management System (CMS):
• It is a set of procedures to identify & document changes to
product characteristics.
• functional & physical characteristics of a
product.
Identify & document
• Any changes to such characteristics.Control
• Each change & its implementation status.Record & report
• Product audit to verify conformance to
requirements.
Support
Perform Integrated Change Control-> CMS
PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com)
VSS – Visual Source
Safe
CVS- Concurrent
version system
Rational Clear Case
Perform Integrated Change Control-> CMS
Change Control
System (CCS)
Configuration
Management
System (CMS)
Other Project
Management
Systems/ Tools
PMIS
Configuration Management System (CMS):
• It It is a set of procedures to identify & document changes to product
characteristics.
PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com)
Configuration Management System (CMS) Example:
• Infrastructure upgrade project for Bank; Bank Locations : 20
• Upgrades : Servers, PC’s/Laptops, Operating Systems & Software's (Local Payroll
software, queuing software, Licenses etc),
• Different Bank locations has severs with different configurations
• Software's with different version.
• Some Customized software's
Challenges:
• To document existing functional & physical characteristics of a products
(Servers, PC’s, software versions etc)
• Record & report each change & its implementation status.
Team will
use CMS
• track different versions of the Hardware, software during the upgrade.
• Allow teams to work simultaneously on the multiple locations.
• Provide data for Auditing & reporting status.
CMS will
Perform Integrated Change Control-> CMS
PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com)
Configuration
identification.
•Configuration item are
identified
•Products and
documents are
labelled
•Accountability is
maintained.
Configuration status
accounting.
•Listing of approved
configuration
•Status of proposed
changes
•Implementation status
Configuration
verification and audit.
•Ensure corresponding
changes are registered
•Changes are assessed,
approved & tracked
•Changes correctly
implemented
Perform Integrated Change Control-> CMS
Configuration Management System (CMS):
• It is a set of procedures used to apply technical & administrative direction and
scrutiny to identify & document changes to product characteristics.
PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com)
Reviewing all CR’s, approving changes & managing changes to
deliverables, project documents & PMP
It allows documented changes within project to be considered in a
integrated fashion while reducing a project risk.
Perform Integrated Change Control
Reviewing &
approving CR’s
Managing
changes
Communicating
decisions
PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com)
Perform Integrated Change Control->ITTO
Expert Judgment
Change Control tools
Data analysis
Decision making
Meetings
Project Management
plan
Project documents
Work Performance
Reports
Change Requests
Enterprise
environmental factors
Organizational process
assets
Approved Change
Request
PMP updates
Project document
updates
Change Log
Inputs Tools & Techniques Outputs
PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com)
Perform Integrated Change Control-> Input
Project Management
plan
Project documents
Work Performance
Reports
Change Requests
Enterprise
environmental factors
Organizational
process assets
PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com)
Project management
plan
It Provides subsidiary plans, baselines & project objectives to compare against CR.
Scope baseline Schedule baseline Cost baseline
Change Management plan:
•Provides the direction for managing the change
control process.
•Document roles & responsibilities of CCB.
Configuration management plan:
•Describes configurable items of the project.
•Identifies items that will be recorded &
updated.
Perform Integrated Change Control -> Input -> PMP
PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com)
Project documents
Following Project documents can be considered as inputs:
Basis of estimates:
• How the duration, cost & resource
estimations were derived.
Requirements traceability matrix:
• Help asses impact of change on project
scope.
Risk report:
• Report may have information on source of
project risks related to change request.
Perform Integrated Change Control -> Input -> Project documents
PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com)
Work Performance
Reports
WPR can provide current health of the project, which is vital for the CR evaluation and decision making.
Schedule reports Cost reports
Burn up or Burn down
Chart
Resource availability
Histograms
Earn value reports
Perform Integrated Change Control -> Input -> WPR
Monitor & Control
Project work
Perform Integrated
Change Control
WPR
Current health of
the project shown
in WPR can impact
the CR analysis &
decision making.
PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com)
Change Request
Formal proposal to modify any document, deliverables or baseline.
These are the requests that the Change Control Board will evaluate and either approve or reject as per CCP process.
Perform Integrated Change Control -> Input -> Change Request
Monitoring & Controlling PG-> Control Process
Validate Scope Control Scope Control Schedule Control Cost Manage Quality Control Communication Control Risks
Monitor Stakeholder
Eng.
Control Procurements
Direct & Manage
Project work
Change Request
Perform Integrated
Change Control
PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com)
Organizational process assets
Change Control
procedures.
Process of
approving &
issuing change
authorization.
Configuration
management
process.
Enterprise environmental factors - Project
Management Information System (PMIS)
Scheduling tool
Configuration
management
system
Information
collection &
distribution
system
Perform Integrated Change Control -> Input -> EEF & OPA
Organizational
process assets
Enterprise
environmental factors
PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com)
Perform Integrated Change Control-> Tools & Techniques
Change Control
tools
Data analysis Expert Judgment
Decision making Meetings
PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com)
Manual or automated tools to assist with change & configuration management.
Help record & Track change request via Change log.
At least, tools should support activities of the CCB.
Perform Integrated Change Control->T&T-> Change Control Tools
Change Control
tools
Microsoft SharePoint
HP Portfolio
Management
PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com)
Data analysis
•Change request must be analyzed with multiple alternatives.
•These alternatives are documented & discussed in the CCB
meetings.
Alternative
analysis
•Cost of requested changes will be analyzed against benefits
and presented in CCB.
Cost
benefit
analysis
Perform Integrated Change Control -> T&T -> Data analysis
Alternative analysis Cost benefit analysis
Following Data analysis techniques can be used:
PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com)
Experts discuss & analyze changes. They may be a part of CCB, who
decides the outcome of Change Request.
Analysis Decision Making Coordination
Perform Integrated Change Control -> T&T -> Expert Judgment
Expert
Judgment
PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com)
Change control related meetings are conducted by CCB (Analyze, Review, approve/Reject the Change)
CCB may also review Configuration Management activities.
CCB decisions are formally documented & shared.
Perform Integrated Change Control -> T&T -> Meetings
Decide on the
Change request
status (Approve /
Reject)
Discuss
Change
request
Meetings
PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com)
Decision
making
Following Decision making techniques can be used:
Perform Integrated Change Control -> T&T -> Decision making
Voting
Autocratic decision
making
Multi-criteria decision
analysis
• Unanimity, Majority, PluralityVoting
• one person takes the responsibility for making decision for the entire group
Autocratic
decision
making
• Its systematic analytical approach where decision matrix are used.
• Matrix will have predefined criteria's for accepting or rejecting change.
Multi-criteria
decision
analysis
PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com)
Perform Integrated Change Control-> Output
Approved Change
Request
Change Log PMP updates
Project document
updates
PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com)
Approved Change
request
Change Requests are processed according to Change Control System.
Approved CR will be implemented through Direct & Manage Project work process.
Perform Integrated CC->Output->Approved CR
Change Request
Perform Integrated
Change Control
Approved Change
request
Direct & Manage
Project work
PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com)
Change log
Document the changes that occur during a project including rejected changes.
It can provide the list of all changes with current status of each change request.
Change Request statuses :
Status accounting may differ as per company methodology
Entry is made when new change is initiated
Updated to reflected completion of analysis
Updated once shared with CCB
Updated with CCB decision
Updated when its under development/construction
Updated once quality control is completed
Updated as ‘Closed’ once change is completely implemented.
Perform Integrated Change Control -> Output
Manage Stakeholder
Engagement
PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com)
All documents subject to formal Change
control Process.
Any subsidiary planes and Baselines that are
subject to formal Change control Process.
Perform Integrated Change Control -> Output -> Project doc. & PMP
Project document
updates
PMP updates
PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com)
Perform Integrated Change Control -> Quick Review
What is Integrated change control?
What is Change Request?
What is configuration management?
How approved change request are implemented.
What is Change log?
What are change control tools?
Chap 4.6 Perform Integrated Change Control

Chap 4.6 Perform Integrated Change Control

  • 1.
    Trainer: Anand BobadePMBOK6th Edition, 2019, All rights reserved. Perform Integrated change Control Chapter 5 – Project Integration Management PMP SIXTH EDITION
  • 2.
    PMBOK 6 -All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com) 4.6 Perform Integrated Change Control Overview Change request process Perform Integrated Change Control definition Perform Integrated Change Control - ITTO What is Change Control board? What is Configuration Management System? Review
  • 3.
    PMBOK 6 -All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com) Integration Management processes Develop Project Charter Develop Project Management plan Direct and Manage Project work Manage Knowledge Monitor & Control Project Work Perform Integrated change Control Close Project or phase I P EE MC CMC
  • 4.
    PMBOK 6 -All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com) Perform Integrated Change Control Any stakeholder can request changes on the project Project sponsor Perform Integrated change Control Always look at project objective. Coordinate changes across the project. Ensure changes are controlled.
  • 5.
    PMBOK 6 -All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com) Submit CR to PM Evaluate CR •Approve or Reject Detailed evaluation •Impact /Options Analysis •Recommendations Present in CCB •Reject /Approve •Defer Update plan & documents, communicate Implement Change (Execution - D&M) Communicate to Stakeholder Perform Integrated Change Control -> Change control Process
  • 6.
    PMBOK 6 -All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com) Change Control Board (CCB) Change Control System (CCS) Change Control Tools Configuration Management System Perform Integrated Change Control -> Key terms
  • 7.
    PMBOK 6 -All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com) Change Control Board (CCB): A formally chartered group responsible for reviewing, evaluating, approving/rejecting changes to project. Also, responsible for recording & communicating. Perform Integrated Change Control -> Key terms -> CCB Change Approver (Matrix should be defined in PMP-change control plan) Change Control Board Responsible Authority Customer or Sponsor Project Manager (small changes as agreed in PMP) Change Control Board Change Request can be: Approved Denied Returned for info Delayed
  • 8.
    PMBOK 6 -All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com) Change Control system (CCS): • A set of procedures that describes how modifications to the project deliverables and documentation are managed and controlled. • Includes Change control Policy, Setting up CCB. Change Control Tools: • Manual or automated tools to assist with change & configuration management. • At least tools should support activities of the CCB. Perform Integrated Change Control-> Key Terms
  • 9.
    PMBOK 6 -All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com) Change Control Tools: • Manual or automated tools to assist with change & configuration management. HP- PPM (Project & Portfolio Management) Microsoft SharePoint Perform Integrated Change Control-> Change Control Tools Project Manager: Define formal change process Ensure proper documentation Ensure changes are introduced in a controlled & coordinated manner.
  • 10.
    PMBOK 6 -All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com) Configuration Management System (CMS): • It is a set of procedures to identify & document changes to product characteristics. • functional & physical characteristics of a product. Identify & document • Any changes to such characteristics.Control • Each change & its implementation status.Record & report • Product audit to verify conformance to requirements. Support Perform Integrated Change Control-> CMS
  • 11.
    PMBOK 6 -All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com) VSS – Visual Source Safe CVS- Concurrent version system Rational Clear Case Perform Integrated Change Control-> CMS Change Control System (CCS) Configuration Management System (CMS) Other Project Management Systems/ Tools PMIS Configuration Management System (CMS): • It It is a set of procedures to identify & document changes to product characteristics.
  • 12.
    PMBOK 6 -All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com) Configuration Management System (CMS) Example: • Infrastructure upgrade project for Bank; Bank Locations : 20 • Upgrades : Servers, PC’s/Laptops, Operating Systems & Software's (Local Payroll software, queuing software, Licenses etc), • Different Bank locations has severs with different configurations • Software's with different version. • Some Customized software's Challenges: • To document existing functional & physical characteristics of a products (Servers, PC’s, software versions etc) • Record & report each change & its implementation status. Team will use CMS • track different versions of the Hardware, software during the upgrade. • Allow teams to work simultaneously on the multiple locations. • Provide data for Auditing & reporting status. CMS will Perform Integrated Change Control-> CMS
  • 13.
    PMBOK 6 -All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com) Configuration identification. •Configuration item are identified •Products and documents are labelled •Accountability is maintained. Configuration status accounting. •Listing of approved configuration •Status of proposed changes •Implementation status Configuration verification and audit. •Ensure corresponding changes are registered •Changes are assessed, approved & tracked •Changes correctly implemented Perform Integrated Change Control-> CMS Configuration Management System (CMS): • It is a set of procedures used to apply technical & administrative direction and scrutiny to identify & document changes to product characteristics.
  • 14.
    PMBOK 6 -All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com) Reviewing all CR’s, approving changes & managing changes to deliverables, project documents & PMP It allows documented changes within project to be considered in a integrated fashion while reducing a project risk. Perform Integrated Change Control Reviewing & approving CR’s Managing changes Communicating decisions
  • 15.
    PMBOK 6 -All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com) Perform Integrated Change Control->ITTO Expert Judgment Change Control tools Data analysis Decision making Meetings Project Management plan Project documents Work Performance Reports Change Requests Enterprise environmental factors Organizational process assets Approved Change Request PMP updates Project document updates Change Log Inputs Tools & Techniques Outputs
  • 16.
    PMBOK 6 -All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com) Perform Integrated Change Control-> Input Project Management plan Project documents Work Performance Reports Change Requests Enterprise environmental factors Organizational process assets
  • 17.
    PMBOK 6 -All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com) Project management plan It Provides subsidiary plans, baselines & project objectives to compare against CR. Scope baseline Schedule baseline Cost baseline Change Management plan: •Provides the direction for managing the change control process. •Document roles & responsibilities of CCB. Configuration management plan: •Describes configurable items of the project. •Identifies items that will be recorded & updated. Perform Integrated Change Control -> Input -> PMP
  • 18.
    PMBOK 6 -All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com) Project documents Following Project documents can be considered as inputs: Basis of estimates: • How the duration, cost & resource estimations were derived. Requirements traceability matrix: • Help asses impact of change on project scope. Risk report: • Report may have information on source of project risks related to change request. Perform Integrated Change Control -> Input -> Project documents
  • 19.
    PMBOK 6 -All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com) Work Performance Reports WPR can provide current health of the project, which is vital for the CR evaluation and decision making. Schedule reports Cost reports Burn up or Burn down Chart Resource availability Histograms Earn value reports Perform Integrated Change Control -> Input -> WPR Monitor & Control Project work Perform Integrated Change Control WPR Current health of the project shown in WPR can impact the CR analysis & decision making.
  • 20.
    PMBOK 6 -All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com) Change Request Formal proposal to modify any document, deliverables or baseline. These are the requests that the Change Control Board will evaluate and either approve or reject as per CCP process. Perform Integrated Change Control -> Input -> Change Request Monitoring & Controlling PG-> Control Process Validate Scope Control Scope Control Schedule Control Cost Manage Quality Control Communication Control Risks Monitor Stakeholder Eng. Control Procurements Direct & Manage Project work Change Request Perform Integrated Change Control
  • 21.
    PMBOK 6 -All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com) Organizational process assets Change Control procedures. Process of approving & issuing change authorization. Configuration management process. Enterprise environmental factors - Project Management Information System (PMIS) Scheduling tool Configuration management system Information collection & distribution system Perform Integrated Change Control -> Input -> EEF & OPA Organizational process assets Enterprise environmental factors
  • 22.
    PMBOK 6 -All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com) Perform Integrated Change Control-> Tools & Techniques Change Control tools Data analysis Expert Judgment Decision making Meetings
  • 23.
    PMBOK 6 -All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com) Manual or automated tools to assist with change & configuration management. Help record & Track change request via Change log. At least, tools should support activities of the CCB. Perform Integrated Change Control->T&T-> Change Control Tools Change Control tools Microsoft SharePoint HP Portfolio Management
  • 24.
    PMBOK 6 -All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com) Data analysis •Change request must be analyzed with multiple alternatives. •These alternatives are documented & discussed in the CCB meetings. Alternative analysis •Cost of requested changes will be analyzed against benefits and presented in CCB. Cost benefit analysis Perform Integrated Change Control -> T&T -> Data analysis Alternative analysis Cost benefit analysis Following Data analysis techniques can be used:
  • 25.
    PMBOK 6 -All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com) Experts discuss & analyze changes. They may be a part of CCB, who decides the outcome of Change Request. Analysis Decision Making Coordination Perform Integrated Change Control -> T&T -> Expert Judgment Expert Judgment
  • 26.
    PMBOK 6 -All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com) Change control related meetings are conducted by CCB (Analyze, Review, approve/Reject the Change) CCB may also review Configuration Management activities. CCB decisions are formally documented & shared. Perform Integrated Change Control -> T&T -> Meetings Decide on the Change request status (Approve / Reject) Discuss Change request Meetings
  • 27.
    PMBOK 6 -All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com) Decision making Following Decision making techniques can be used: Perform Integrated Change Control -> T&T -> Decision making Voting Autocratic decision making Multi-criteria decision analysis • Unanimity, Majority, PluralityVoting • one person takes the responsibility for making decision for the entire group Autocratic decision making • Its systematic analytical approach where decision matrix are used. • Matrix will have predefined criteria's for accepting or rejecting change. Multi-criteria decision analysis
  • 28.
    PMBOK 6 -All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com) Perform Integrated Change Control-> Output Approved Change Request Change Log PMP updates Project document updates
  • 29.
    PMBOK 6 -All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com) Approved Change request Change Requests are processed according to Change Control System. Approved CR will be implemented through Direct & Manage Project work process. Perform Integrated CC->Output->Approved CR Change Request Perform Integrated Change Control Approved Change request Direct & Manage Project work
  • 30.
    PMBOK 6 -All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com) Change log Document the changes that occur during a project including rejected changes. It can provide the list of all changes with current status of each change request. Change Request statuses : Status accounting may differ as per company methodology Entry is made when new change is initiated Updated to reflected completion of analysis Updated once shared with CCB Updated with CCB decision Updated when its under development/construction Updated once quality control is completed Updated as ‘Closed’ once change is completely implemented. Perform Integrated Change Control -> Output Manage Stakeholder Engagement
  • 31.
    PMBOK 6 -All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com) All documents subject to formal Change control Process. Any subsidiary planes and Baselines that are subject to formal Change control Process. Perform Integrated Change Control -> Output -> Project doc. & PMP Project document updates PMP updates
  • 32.
    PMBOK 6 -All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com) Perform Integrated Change Control -> Quick Review What is Integrated change control? What is Change Request? What is configuration management? How approved change request are implemented. What is Change log? What are change control tools?