Perform Integrated
change Control
Chapter 5 –
Project Integration Management
PMP SIXTH EDITION
PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com)
4.6 Perform Integrated Change Control
Overview
Change request process
Perform Integrated Change Control definition
Perform Integrated Change Control - ITTO
What is Change Control board?
What is Configuration Management System?
Review
PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com)
Integration Management processes
Develop Project
Charter
Develop Project
Management plan
Direct and Manage
Project work
Manage Knowledge
Monitor & Control
Project Work
Perform Integrated
change Control
Close Project or
phase
I P EE
MC CMC
PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com)
Perform Integrated Change Control
Any stakeholder can request changes on the project
Project
sponsor
Perform Integrated
change Control
Always look at project
objective.
Coordinate changes
across the project.
Ensure changes are
controlled.
PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com)
Submit CR to PM
Evaluate CR
•Approve or Reject
Detailed evaluation
•Impact /Options Analysis
•Recommendations
Present in CCB
•Reject /Approve
•Defer
Update plan &
documents,
communicate
Implement Change
(Execution - D&M)
Communicate to
Stakeholder
Perform Integrated Change Control -> Change control Process
PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com)
Change Control
Board (CCB)
Change Control
System (CCS)
Change Control Tools
Configuration
Management System
Perform Integrated Change Control -> Key terms
PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com)
Change Control Board (CCB):
A formally chartered group responsible for reviewing, evaluating,
approving/rejecting changes to project. Also, responsible for recording
& communicating.
Perform Integrated Change Control -> Key terms -> CCB
Change Approver
(Matrix should be defined in
PMP-change control plan)
Change Control Board
Responsible Authority
Customer or Sponsor
Project Manager (small
changes as agreed in PMP)
Change Control
Board
Change Request can be:
Approved Denied Returned for info Delayed
PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com)
Change Control system (CCS):
• A set of procedures that describes how
modifications to the project deliverables and
documentation are managed and controlled.
• Includes Change control Policy, Setting up CCB.
Change Control Tools:
• Manual or automated tools to assist with
change & configuration management.
• At least tools should support activities of the
CCB.
Perform Integrated Change Control-> Key Terms
PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com)
Change Control Tools:
• Manual or automated tools to assist with change & configuration management.
HP- PPM (Project &
Portfolio Management)
Microsoft SharePoint
Perform Integrated Change Control-> Change Control Tools
Project Manager:
Define formal
change process
Ensure proper
documentation
Ensure changes are
introduced in a controlled
& coordinated manner.
PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com)
Configuration Management System (CMS):
• It is a set of procedures to identify & document changes to
product characteristics.
• functional & physical characteristics of a
product.
Identify & document
• Any changes to such characteristics.Control
• Each change & its implementation status.Record & report
• Product audit to verify conformance to
requirements.
Support
Perform Integrated Change Control-> CMS
PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com)
VSS – Visual Source
Safe
CVS- Concurrent
version system
Rational Clear Case
Perform Integrated Change Control-> CMS
Change Control
System (CCS)
Configuration
Management
System (CMS)
Other Project
Management
Systems/ Tools
PMIS
Configuration Management System (CMS):
• It It is a set of procedures to identify & document changes to product
characteristics.
PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com)
Configuration Management System (CMS) Example:
• Infrastructure upgrade project for Bank; Bank Locations : 20
• Upgrades : Servers, PC’s/Laptops, Operating Systems & Software's (Local Payroll
software, queuing software, Licenses etc),
• Different Bank locations has severs with different configurations
• Software's with different version.
• Some Customized software's
Challenges:
• To document existing functional & physical characteristics of a products
(Servers, PC’s, software versions etc)
• Record & report each change & its implementation status.
Team will
use CMS
• track different versions of the Hardware, software during the upgrade.
• Allow teams to work simultaneously on the multiple locations.
• Provide data for Auditing & reporting status.
CMS will
Perform Integrated Change Control-> CMS
PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com)
Configuration
identification.
•Configuration item are
identified
•Products and
documents are
labelled
•Accountability is
maintained.
Configuration status
accounting.
•Listing of approved
configuration
•Status of proposed
changes
•Implementation status
Configuration
verification and audit.
•Ensure corresponding
changes are registered
•Changes are assessed,
approved & tracked
•Changes correctly
implemented
Perform Integrated Change Control-> CMS
Configuration Management System (CMS):
• It is a set of procedures used to apply technical & administrative direction and
scrutiny to identify & document changes to product characteristics.
PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com)
Reviewing all CR’s, approving changes & managing changes to
deliverables, project documents & PMP
It allows documented changes within project to be considered in a
integrated fashion while reducing a project risk.
Perform Integrated Change Control
Reviewing &
approving CR’s
Managing
changes
Communicating
decisions
PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com)
Perform Integrated Change Control->ITTO
Expert Judgment
Change Control tools
Data analysis
Decision making
Meetings
Project Management
plan
Project documents
Work Performance
Reports
Change Requests
Enterprise
environmental factors
Organizational process
assets
Approved Change
Request
PMP updates
Project document
updates
Change Log
Inputs Tools & Techniques Outputs
PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com)
Perform Integrated Change Control-> Input
Project Management
plan
Project documents
Work Performance
Reports
Change Requests
Enterprise
environmental factors
Organizational
process assets
PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com)
Project management
plan
It Provides subsidiary plans, baselines & project objectives to compare against CR.
Scope baseline Schedule baseline Cost baseline
Change Management plan:
•Provides the direction for managing the change
control process.
•Document roles & responsibilities of CCB.
Configuration management plan:
•Describes configurable items of the project.
•Identifies items that will be recorded &
updated.
Perform Integrated Change Control -> Input -> PMP
PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com)
Project documents
Following Project documents can be considered as inputs:
Basis of estimates:
• How the duration, cost & resource
estimations were derived.
Requirements traceability matrix:
• Help asses impact of change on project
scope.
Risk report:
• Report may have information on source of
project risks related to change request.
Perform Integrated Change Control -> Input -> Project documents
PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com)
Work Performance
Reports
WPR can provide current health of the project, which is vital for the CR evaluation and decision making.
Schedule reports Cost reports
Burn up or Burn down
Chart
Resource availability
Histograms
Earn value reports
Perform Integrated Change Control -> Input -> WPR
Monitor & Control
Project work
Perform Integrated
Change Control
WPR
Current health of
the project shown
in WPR can impact
the CR analysis &
decision making.
PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com)
Change Request
Formal proposal to modify any document, deliverables or baseline.
These are the requests that the Change Control Board will evaluate and either approve or reject as per CCP process.
Perform Integrated Change Control -> Input -> Change Request
Monitoring & Controlling PG-> Control Process
Validate Scope Control Scope Control Schedule Control Cost Manage Quality Control Communication Control Risks
Monitor Stakeholder
Eng.
Control Procurements
Direct & Manage
Project work
Change Request
Perform Integrated
Change Control
PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com)
Organizational process assets
Change Control
procedures.
Process of
approving &
issuing change
authorization.
Configuration
management
process.
Enterprise environmental factors - Project
Management Information System (PMIS)
Scheduling tool
Configuration
management
system
Information
collection &
distribution
system
Perform Integrated Change Control -> Input -> EEF & OPA
Organizational
process assets
Enterprise
environmental factors
PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com)
Perform Integrated Change Control-> Tools & Techniques
Change Control
tools
Data analysis Expert Judgment
Decision making Meetings
PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com)
Manual or automated tools to assist with change & configuration management.
Help record & Track change request via Change log.
At least, tools should support activities of the CCB.
Perform Integrated Change Control->T&T-> Change Control Tools
Change Control
tools
Microsoft SharePoint
HP Portfolio
Management
PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com)
Data analysis
•Change request must be analyzed with multiple alternatives.
•These alternatives are documented & discussed in the CCB
meetings.
Alternative
analysis
•Cost of requested changes will be analyzed against benefits
and presented in CCB.
Cost
benefit
analysis
Perform Integrated Change Control -> T&T -> Data analysis
Alternative analysis Cost benefit analysis
Following Data analysis techniques can be used:
PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com)
Experts discuss & analyze changes. They may be a part of CCB, who
decides the outcome of Change Request.
Analysis Decision Making Coordination
Perform Integrated Change Control -> T&T -> Expert Judgment
Expert
Judgment
PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com)
Change control related meetings are conducted by CCB (Analyze, Review, approve/Reject the Change)
CCB may also review Configuration Management activities.
CCB decisions are formally documented & shared.
Perform Integrated Change Control -> T&T -> Meetings
Decide on the
Change request
status (Approve /
Reject)
Discuss
Change
request
Meetings
PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com)
Decision
making
Following Decision making techniques can be used:
Perform Integrated Change Control -> T&T -> Decision making
Voting
Autocratic decision
making
Multi-criteria decision
analysis
• Unanimity, Majority, PluralityVoting
• one person takes the responsibility for making decision for the entire group
Autocratic
decision
making
• Its systematic analytical approach where decision matrix are used.
• Matrix will have predefined criteria's for accepting or rejecting change.
Multi-criteria
decision
analysis
PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com)
Perform Integrated Change Control-> Output
Approved Change
Request
Change Log PMP updates
Project document
updates
PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com)
Approved Change
request
Change Requests are processed according to Change Control System.
Approved CR will be implemented through Direct & Manage Project work process.
Perform Integrated CC->Output->Approved CR
Change Request
Perform Integrated
Change Control
Approved Change
request
Direct & Manage
Project work
PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com)
Change log
Document the changes that occur during a project including rejected changes.
It can provide the list of all changes with current status of each change request.
Change Request statuses :
Status accounting may differ as per company methodology
Entry is made when new change is initiated
Updated to reflected completion of analysis
Updated once shared with CCB
Updated with CCB decision
Updated when its under development/construction
Updated once quality control is completed
Updated as ‘Closed’ once change is completely implemented.
Perform Integrated Change Control -> Output
Manage Stakeholder
Engagement
PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com)
All documents subject to formal Change
control Process.
Any subsidiary planes and Baselines that are
subject to formal Change control Process.
Perform Integrated Change Control -> Output -> Project doc. & PMP
Project document
updates
PMP updates
PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com)
Perform Integrated Change Control -> Quick Review
What is Integrated change control?
What is Change Request?
What is configuration management?
How approved change request are implemented.
What is Change log?
What are change control tools?
Chap 4.6 Perform Integrated Change Control

More Related Content

What's hot

PMP Chap 8 - Project Quality Management
PMP Chap 8 - Project Quality ManagementPMP Chap 8 - Project Quality Management
PMP Chap 8 - Project Quality ManagementAnand Bobade
 
Chap 9.6 Control Resources
Chap 9.6  Control ResourcesChap 9.6  Control Resources
Chap 9.6 Control ResourcesAnand Bobade
 
Chap 7.3 Determine budget
Chap 7.3   Determine budgetChap 7.3   Determine budget
Chap 7.3 Determine budgetAnand Bobade
 
Chap 11.2 Identify Risks
Chap 11.2 Identify RisksChap 11.2 Identify Risks
Chap 11.2 Identify RisksAnand Bobade
 
Chap 4.5 Monitor and Control Project Work
Chap 4.5 Monitor and Control Project WorkChap 4.5 Monitor and Control Project Work
Chap 4.5 Monitor and Control Project WorkAnand Bobade
 
Chap 12.0 Procurement Management overview
Chap 12.0   Procurement Management overviewChap 12.0   Procurement Management overview
Chap 12.0 Procurement Management overviewAnand Bobade
 
Chap 12.1 Plan Procurement Management
Chap 12.1 Plan Procurement ManagementChap 12.1 Plan Procurement Management
Chap 12.1 Plan Procurement ManagementAnand Bobade
 
Chap 8.3 Control Quality
Chap 8.3  Control QualityChap 8.3  Control Quality
Chap 8.3 Control QualityAnand Bobade
 
PMP Chap4-Project Integration Management Details: Part-2
PMP Chap4-Project Integration Management Details: Part-2PMP Chap4-Project Integration Management Details: Part-2
PMP Chap4-Project Integration Management Details: Part-2Anand Bobade
 
Pmp chap 11 - project risk management v0.1
Pmp   chap 11 - project risk management v0.1Pmp   chap 11 - project risk management v0.1
Pmp chap 11 - project risk management v0.1Anand Bobade
 
Chap 6.4 Estimate Activity Duration
Chap 6.4 Estimate Activity DurationChap 6.4 Estimate Activity Duration
Chap 6.4 Estimate Activity DurationAnand Bobade
 
Project scope management
Project scope managementProject scope management
Project scope managementAnit Roy
 
Chap 9.1 Pan Resource Management
Chap 9.1   Pan Resource ManagementChap 9.1   Pan Resource Management
Chap 9.1 Pan Resource ManagementAnand Bobade
 
Chap 5.5 validate scope
Chap 5.5 validate scopeChap 5.5 validate scope
Chap 5.5 validate scopeAnand Bobade
 
Chap 9.5 Manage Team
Chap 9.5  Manage TeamChap 9.5  Manage Team
Chap 9.5 Manage TeamAnand Bobade
 
Pmbok 4th edition chapter 12 - Project Procurement Management
Pmbok 4th edition   chapter 12 - Project Procurement ManagementPmbok 4th edition   chapter 12 - Project Procurement Management
Pmbok 4th edition chapter 12 - Project Procurement ManagementAhmad Maharma, PMP,RMP
 
Chap 9.2 Estimate Activity Resource
Chap 9.2   Estimate Activity ResourceChap 9.2   Estimate Activity Resource
Chap 9.2 Estimate Activity ResourceAnand Bobade
 
PMP Chap 5.0 Scope Management Overview
PMP Chap 5.0 Scope Management OverviewPMP Chap 5.0 Scope Management Overview
PMP Chap 5.0 Scope Management OverviewAnand Bobade
 
Chap 6.1 Plan Schedule Management
Chap 6.1 Plan Schedule ManagementChap 6.1 Plan Schedule Management
Chap 6.1 Plan Schedule ManagementAnand Bobade
 
PMP 47 process definitions
PMP 47 process definitionsPMP 47 process definitions
PMP 47 process definitionsAnand Bobade
 

What's hot (20)

PMP Chap 8 - Project Quality Management
PMP Chap 8 - Project Quality ManagementPMP Chap 8 - Project Quality Management
PMP Chap 8 - Project Quality Management
 
Chap 9.6 Control Resources
Chap 9.6  Control ResourcesChap 9.6  Control Resources
Chap 9.6 Control Resources
 
Chap 7.3 Determine budget
Chap 7.3   Determine budgetChap 7.3   Determine budget
Chap 7.3 Determine budget
 
Chap 11.2 Identify Risks
Chap 11.2 Identify RisksChap 11.2 Identify Risks
Chap 11.2 Identify Risks
 
Chap 4.5 Monitor and Control Project Work
Chap 4.5 Monitor and Control Project WorkChap 4.5 Monitor and Control Project Work
Chap 4.5 Monitor and Control Project Work
 
Chap 12.0 Procurement Management overview
Chap 12.0   Procurement Management overviewChap 12.0   Procurement Management overview
Chap 12.0 Procurement Management overview
 
Chap 12.1 Plan Procurement Management
Chap 12.1 Plan Procurement ManagementChap 12.1 Plan Procurement Management
Chap 12.1 Plan Procurement Management
 
Chap 8.3 Control Quality
Chap 8.3  Control QualityChap 8.3  Control Quality
Chap 8.3 Control Quality
 
PMP Chap4-Project Integration Management Details: Part-2
PMP Chap4-Project Integration Management Details: Part-2PMP Chap4-Project Integration Management Details: Part-2
PMP Chap4-Project Integration Management Details: Part-2
 
Pmp chap 11 - project risk management v0.1
Pmp   chap 11 - project risk management v0.1Pmp   chap 11 - project risk management v0.1
Pmp chap 11 - project risk management v0.1
 
Chap 6.4 Estimate Activity Duration
Chap 6.4 Estimate Activity DurationChap 6.4 Estimate Activity Duration
Chap 6.4 Estimate Activity Duration
 
Project scope management
Project scope managementProject scope management
Project scope management
 
Chap 9.1 Pan Resource Management
Chap 9.1   Pan Resource ManagementChap 9.1   Pan Resource Management
Chap 9.1 Pan Resource Management
 
Chap 5.5 validate scope
Chap 5.5 validate scopeChap 5.5 validate scope
Chap 5.5 validate scope
 
Chap 9.5 Manage Team
Chap 9.5  Manage TeamChap 9.5  Manage Team
Chap 9.5 Manage Team
 
Pmbok 4th edition chapter 12 - Project Procurement Management
Pmbok 4th edition   chapter 12 - Project Procurement ManagementPmbok 4th edition   chapter 12 - Project Procurement Management
Pmbok 4th edition chapter 12 - Project Procurement Management
 
Chap 9.2 Estimate Activity Resource
Chap 9.2   Estimate Activity ResourceChap 9.2   Estimate Activity Resource
Chap 9.2 Estimate Activity Resource
 
PMP Chap 5.0 Scope Management Overview
PMP Chap 5.0 Scope Management OverviewPMP Chap 5.0 Scope Management Overview
PMP Chap 5.0 Scope Management Overview
 
Chap 6.1 Plan Schedule Management
Chap 6.1 Plan Schedule ManagementChap 6.1 Plan Schedule Management
Chap 6.1 Plan Schedule Management
 
PMP 47 process definitions
PMP 47 process definitionsPMP 47 process definitions
PMP 47 process definitions
 

Similar to Chap 4.6 Perform Integrated Change Control

Chap 5.6 Control Scope
Chap 5.6 Control ScopeChap 5.6 Control Scope
Chap 5.6 Control ScopeAnand Bobade
 
Chap 4.3 Direct and Manage Project work
Chap 4.3 Direct and Manage Project workChap 4.3 Direct and Manage Project work
Chap 4.3 Direct and Manage Project workAnand Bobade
 
Chap 6.2 Define Activity
Chap 6.2 Define ActivityChap 6.2 Define Activity
Chap 6.2 Define ActivityAnand Bobade
 
Chap 6.6 Control Schedule
Chap 6.6 Control ScheduleChap 6.6 Control Schedule
Chap 6.6 Control ScheduleAnand Bobade
 
Chap 5.1 Plan Scope Management
Chap 5.1 Plan Scope ManagementChap 5.1 Plan Scope Management
Chap 5.1 Plan Scope ManagementAnand Bobade
 
Chap 7.1 Plan Cost Management
Chap 7.1  Plan Cost ManagementChap 7.1  Plan Cost Management
Chap 7.1 Plan Cost ManagementAnand Bobade
 
Chap 8.1 Plan quality management
Chap 8.1 Plan quality managementChap 8.1 Plan quality management
Chap 8.1 Plan quality managementAnand Bobade
 
Chap 5.2 Collect requirements
Chap 5.2 Collect requirementsChap 5.2 Collect requirements
Chap 5.2 Collect requirementsAnand Bobade
 
Chap 6.3 Sequence Activity
Chap 6.3 Sequence ActivityChap 6.3 Sequence Activity
Chap 6.3 Sequence ActivityAnand Bobade
 
PMP Chapter 5 of 6 M & C Process Group (12- Processes) (Based on PMBOK 6th e...
PMP Chapter 5 of 6  M & C Process Group (12- Processes) (Based on PMBOK 6th e...PMP Chapter 5 of 6  M & C Process Group (12- Processes) (Based on PMBOK 6th e...
PMP Chapter 5 of 6 M & C Process Group (12- Processes) (Based on PMBOK 6th e...Shamil Habet
 
Module 3 - IDP.ppt
Module 3 - IDP.pptModule 3 - IDP.ppt
Module 3 - IDP.pptRAJESH S
 
Chap 8.2 Manage Quality
Chap 8.2 Manage QualityChap 8.2 Manage Quality
Chap 8.2 Manage QualityAnand Bobade
 
Chap 11.7 Monitor Risks
Chap 11.7 Monitor RisksChap 11.7 Monitor Risks
Chap 11.7 Monitor RisksAnand Bobade
 
Software configuration management
Software configuration managementSoftware configuration management
Software configuration managementShivani Garg
 
5 itil v3 service transition 5 v1.8
5 itil v3 service transition 5 v1.85 itil v3 service transition 5 v1.8
5 itil v3 service transition 5 v1.8Karthik Arumugham
 
Software Engineering- Chapter 9.pptx
Software Engineering- Chapter 9.pptxSoftware Engineering- Chapter 9.pptx
Software Engineering- Chapter 9.pptxFarjanaParvin5
 
Project Control- Overview Presentation Tafseer
Project Control- Overview Presentation   TafseerProject Control- Overview Presentation   Tafseer
Project Control- Overview Presentation TafseerKishan Solankimbaccepmp
 

Similar to Chap 4.6 Perform Integrated Change Control (20)

Chap 5.6 Control Scope
Chap 5.6 Control ScopeChap 5.6 Control Scope
Chap 5.6 Control Scope
 
Chap 4.3 Direct and Manage Project work
Chap 4.3 Direct and Manage Project workChap 4.3 Direct and Manage Project work
Chap 4.3 Direct and Manage Project work
 
Chap 6.2 Define Activity
Chap 6.2 Define ActivityChap 6.2 Define Activity
Chap 6.2 Define Activity
 
Chap 6.6 Control Schedule
Chap 6.6 Control ScheduleChap 6.6 Control Schedule
Chap 6.6 Control Schedule
 
Chap 5.1 Plan Scope Management
Chap 5.1 Plan Scope ManagementChap 5.1 Plan Scope Management
Chap 5.1 Plan Scope Management
 
Chap 7.1 Plan Cost Management
Chap 7.1  Plan Cost ManagementChap 7.1  Plan Cost Management
Chap 7.1 Plan Cost Management
 
Chap 8.1 Plan quality management
Chap 8.1 Plan quality managementChap 8.1 Plan quality management
Chap 8.1 Plan quality management
 
Module 12 Monitoring and Control I
Module 12 Monitoring and Control IModule 12 Monitoring and Control I
Module 12 Monitoring and Control I
 
Chap 5.2 Collect requirements
Chap 5.2 Collect requirementsChap 5.2 Collect requirements
Chap 5.2 Collect requirements
 
Chap 6.3 Sequence Activity
Chap 6.3 Sequence ActivityChap 6.3 Sequence Activity
Chap 6.3 Sequence Activity
 
PMP Chapter 5 of 6 M & C Process Group (12- Processes) (Based on PMBOK 6th e...
PMP Chapter 5 of 6  M & C Process Group (12- Processes) (Based on PMBOK 6th e...PMP Chapter 5 of 6  M & C Process Group (12- Processes) (Based on PMBOK 6th e...
PMP Chapter 5 of 6 M & C Process Group (12- Processes) (Based on PMBOK 6th e...
 
Kogent approach
Kogent approachKogent approach
Kogent approach
 
Module 3 - IDP.ppt
Module 3 - IDP.pptModule 3 - IDP.ppt
Module 3 - IDP.ppt
 
Software Configuration Management
Software Configuration ManagementSoftware Configuration Management
Software Configuration Management
 
Chap 8.2 Manage Quality
Chap 8.2 Manage QualityChap 8.2 Manage Quality
Chap 8.2 Manage Quality
 
Chap 11.7 Monitor Risks
Chap 11.7 Monitor RisksChap 11.7 Monitor Risks
Chap 11.7 Monitor Risks
 
Software configuration management
Software configuration managementSoftware configuration management
Software configuration management
 
5 itil v3 service transition 5 v1.8
5 itil v3 service transition 5 v1.85 itil v3 service transition 5 v1.8
5 itil v3 service transition 5 v1.8
 
Software Engineering- Chapter 9.pptx
Software Engineering- Chapter 9.pptxSoftware Engineering- Chapter 9.pptx
Software Engineering- Chapter 9.pptx
 
Project Control- Overview Presentation Tafseer
Project Control- Overview Presentation   TafseerProject Control- Overview Presentation   Tafseer
Project Control- Overview Presentation Tafseer
 

More from Anand Bobade

PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...Anand Bobade
 
Chap 12.3 Control Procurement
Chap 12.3 Control ProcurementChap 12.3 Control Procurement
Chap 12.3 Control ProcurementAnand Bobade
 
Chap 12.2 Conduct Procurement
Chap 12.2 Conduct ProcurementChap 12.2 Conduct Procurement
Chap 12.2 Conduct ProcurementAnand Bobade
 
Chap 10.3 Monitor Communication
Chap 10.3 Monitor CommunicationChap 10.3 Monitor Communication
Chap 10.3 Monitor CommunicationAnand Bobade
 
Chap 10.2 Manage Communication
Chap 10.2  Manage CommunicationChap 10.2  Manage Communication
Chap 10.2 Manage CommunicationAnand Bobade
 
Chap 10.1 Plan Communication Management
Chap 10.1  Plan Communication ManagementChap 10.1  Plan Communication Management
Chap 10.1 Plan Communication ManagementAnand Bobade
 
Chap 9.4 Develop Team
Chap 9.4  Develop TeamChap 9.4  Develop Team
Chap 9.4 Develop TeamAnand Bobade
 
Chap 9.3 Acquire Resources
Chap 9.3   Acquire ResourcesChap 9.3   Acquire Resources
Chap 9.3 Acquire ResourcesAnand Bobade
 
Chap 9.0 Project Resource Management overview
Chap 9.0   Project Resource Management overviewChap 9.0   Project Resource Management overview
Chap 9.0 Project Resource Management overviewAnand Bobade
 
Chap 7.4 Control Cost
Chap 7.4   Control CostChap 7.4   Control Cost
Chap 7.4 Control CostAnand Bobade
 
Chap 7.2 Estimate Cost
Chap 7.2 Estimate CostChap 7.2 Estimate Cost
Chap 7.2 Estimate CostAnand Bobade
 
Chap 7.0 Project Cost Management Overview
Chap 7.0 Project Cost Management OverviewChap 7.0 Project Cost Management Overview
Chap 7.0 Project Cost Management OverviewAnand Bobade
 
Chap 6.5 Define Schedule
Chap 6.5 Define ScheduleChap 6.5 Define Schedule
Chap 6.5 Define ScheduleAnand Bobade
 

More from Anand Bobade (13)

PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
 
Chap 12.3 Control Procurement
Chap 12.3 Control ProcurementChap 12.3 Control Procurement
Chap 12.3 Control Procurement
 
Chap 12.2 Conduct Procurement
Chap 12.2 Conduct ProcurementChap 12.2 Conduct Procurement
Chap 12.2 Conduct Procurement
 
Chap 10.3 Monitor Communication
Chap 10.3 Monitor CommunicationChap 10.3 Monitor Communication
Chap 10.3 Monitor Communication
 
Chap 10.2 Manage Communication
Chap 10.2  Manage CommunicationChap 10.2  Manage Communication
Chap 10.2 Manage Communication
 
Chap 10.1 Plan Communication Management
Chap 10.1  Plan Communication ManagementChap 10.1  Plan Communication Management
Chap 10.1 Plan Communication Management
 
Chap 9.4 Develop Team
Chap 9.4  Develop TeamChap 9.4  Develop Team
Chap 9.4 Develop Team
 
Chap 9.3 Acquire Resources
Chap 9.3   Acquire ResourcesChap 9.3   Acquire Resources
Chap 9.3 Acquire Resources
 
Chap 9.0 Project Resource Management overview
Chap 9.0   Project Resource Management overviewChap 9.0   Project Resource Management overview
Chap 9.0 Project Resource Management overview
 
Chap 7.4 Control Cost
Chap 7.4   Control CostChap 7.4   Control Cost
Chap 7.4 Control Cost
 
Chap 7.2 Estimate Cost
Chap 7.2 Estimate CostChap 7.2 Estimate Cost
Chap 7.2 Estimate Cost
 
Chap 7.0 Project Cost Management Overview
Chap 7.0 Project Cost Management OverviewChap 7.0 Project Cost Management Overview
Chap 7.0 Project Cost Management Overview
 
Chap 6.5 Define Schedule
Chap 6.5 Define ScheduleChap 6.5 Define Schedule
Chap 6.5 Define Schedule
 

Recently uploaded

Project Management Professional (PMP)® from PMI
Project Management Professional (PMP)® from PMIProject Management Professional (PMP)® from PMI
Project Management Professional (PMP)® from PMITasnur Tonoy
 
Create the recognition your teams deserve.pptx
Create the recognition your teams deserve.pptxCreate the recognition your teams deserve.pptx
Create the recognition your teams deserve.pptxStephen Sitton
 
Risk Management in Banks - Overview (May 2024)
Risk Management in Banks - Overview (May 2024)Risk Management in Banks - Overview (May 2024)
Risk Management in Banks - Overview (May 2024)Kristi Rohtsalu
 
Founder-Game Director Workshop (Session 1)
Founder-Game Director  Workshop (Session 1)Founder-Game Director  Workshop (Session 1)
Founder-Game Director Workshop (Session 1)Amir H. Fassihi
 
ANIn Delhi Feb 2022 | Design the Future with Technology Disruption by N Kisho...
ANIn Delhi Feb 2022 | Design the Future with Technology Disruption by N Kisho...ANIn Delhi Feb 2022 | Design the Future with Technology Disruption by N Kisho...
ANIn Delhi Feb 2022 | Design the Future with Technology Disruption by N Kisho...AgileNetwork
 
Travis Hills of Minnesota Leads Livestock Water and Energy in Sustainable Inn...
Travis Hills of Minnesota Leads Livestock Water and Energy in Sustainable Inn...Travis Hills of Minnesota Leads Livestock Water and Energy in Sustainable Inn...
Travis Hills of Minnesota Leads Livestock Water and Energy in Sustainable Inn...Travis Hills MN
 
Principles of Management analyze how Zara manage
Principles of Management analyze how Zara managePrinciples of Management analyze how Zara manage
Principles of Management analyze how Zara managessuser4899c8
 
Flexi time, Flexi work, QWL and Role Effectiveness
Flexi time, Flexi  work, QWL and  Role EffectivenessFlexi time, Flexi  work, QWL and  Role Effectiveness
Flexi time, Flexi work, QWL and Role EffectivenessSana Fatima
 
Organization design fashion or fit by Henry Mintzberg
Organization design fashion or fit by Henry MintzbergOrganization design fashion or fit by Henry Mintzberg
Organization design fashion or fit by Henry MintzbergSana Fatima
 
Presentation On "Yusuf Ibn Tashfin" a true leader (1061 to 1106)_ prepared by...
Presentation On "Yusuf Ibn Tashfin" a true leader (1061 to 1106)_ prepared by...Presentation On "Yusuf Ibn Tashfin" a true leader (1061 to 1106)_ prepared by...
Presentation On "Yusuf Ibn Tashfin" a true leader (1061 to 1106)_ prepared by...kamrulShuva
 
Oprah Winfrey: A Leader in Media, Philanthropy, and Empowerment | CIO Women M...
Oprah Winfrey: A Leader in Media, Philanthropy, and Empowerment | CIO Women M...Oprah Winfrey: A Leader in Media, Philanthropy, and Empowerment | CIO Women M...
Oprah Winfrey: A Leader in Media, Philanthropy, and Empowerment | CIO Women M...CIOWomenMagazine
 

Recently uploaded (11)

Project Management Professional (PMP)® from PMI
Project Management Professional (PMP)® from PMIProject Management Professional (PMP)® from PMI
Project Management Professional (PMP)® from PMI
 
Create the recognition your teams deserve.pptx
Create the recognition your teams deserve.pptxCreate the recognition your teams deserve.pptx
Create the recognition your teams deserve.pptx
 
Risk Management in Banks - Overview (May 2024)
Risk Management in Banks - Overview (May 2024)Risk Management in Banks - Overview (May 2024)
Risk Management in Banks - Overview (May 2024)
 
Founder-Game Director Workshop (Session 1)
Founder-Game Director  Workshop (Session 1)Founder-Game Director  Workshop (Session 1)
Founder-Game Director Workshop (Session 1)
 
ANIn Delhi Feb 2022 | Design the Future with Technology Disruption by N Kisho...
ANIn Delhi Feb 2022 | Design the Future with Technology Disruption by N Kisho...ANIn Delhi Feb 2022 | Design the Future with Technology Disruption by N Kisho...
ANIn Delhi Feb 2022 | Design the Future with Technology Disruption by N Kisho...
 
Travis Hills of Minnesota Leads Livestock Water and Energy in Sustainable Inn...
Travis Hills of Minnesota Leads Livestock Water and Energy in Sustainable Inn...Travis Hills of Minnesota Leads Livestock Water and Energy in Sustainable Inn...
Travis Hills of Minnesota Leads Livestock Water and Energy in Sustainable Inn...
 
Principles of Management analyze how Zara manage
Principles of Management analyze how Zara managePrinciples of Management analyze how Zara manage
Principles of Management analyze how Zara manage
 
Flexi time, Flexi work, QWL and Role Effectiveness
Flexi time, Flexi  work, QWL and  Role EffectivenessFlexi time, Flexi  work, QWL and  Role Effectiveness
Flexi time, Flexi work, QWL and Role Effectiveness
 
Organization design fashion or fit by Henry Mintzberg
Organization design fashion or fit by Henry MintzbergOrganization design fashion or fit by Henry Mintzberg
Organization design fashion or fit by Henry Mintzberg
 
Presentation On "Yusuf Ibn Tashfin" a true leader (1061 to 1106)_ prepared by...
Presentation On "Yusuf Ibn Tashfin" a true leader (1061 to 1106)_ prepared by...Presentation On "Yusuf Ibn Tashfin" a true leader (1061 to 1106)_ prepared by...
Presentation On "Yusuf Ibn Tashfin" a true leader (1061 to 1106)_ prepared by...
 
Oprah Winfrey: A Leader in Media, Philanthropy, and Empowerment | CIO Women M...
Oprah Winfrey: A Leader in Media, Philanthropy, and Empowerment | CIO Women M...Oprah Winfrey: A Leader in Media, Philanthropy, and Empowerment | CIO Women M...
Oprah Winfrey: A Leader in Media, Philanthropy, and Empowerment | CIO Women M...
 

Chap 4.6 Perform Integrated Change Control

  • 1. Trainer: Anand BobadePMBOK 6th Edition, 2019, All rights reserved. Perform Integrated change Control Chapter 5 – Project Integration Management PMP SIXTH EDITION
  • 2. PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com) 4.6 Perform Integrated Change Control Overview Change request process Perform Integrated Change Control definition Perform Integrated Change Control - ITTO What is Change Control board? What is Configuration Management System? Review
  • 3. PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com) Integration Management processes Develop Project Charter Develop Project Management plan Direct and Manage Project work Manage Knowledge Monitor & Control Project Work Perform Integrated change Control Close Project or phase I P EE MC CMC
  • 4. PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com) Perform Integrated Change Control Any stakeholder can request changes on the project Project sponsor Perform Integrated change Control Always look at project objective. Coordinate changes across the project. Ensure changes are controlled.
  • 5. PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com) Submit CR to PM Evaluate CR •Approve or Reject Detailed evaluation •Impact /Options Analysis •Recommendations Present in CCB •Reject /Approve •Defer Update plan & documents, communicate Implement Change (Execution - D&M) Communicate to Stakeholder Perform Integrated Change Control -> Change control Process
  • 6. PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com) Change Control Board (CCB) Change Control System (CCS) Change Control Tools Configuration Management System Perform Integrated Change Control -> Key terms
  • 7. PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com) Change Control Board (CCB): A formally chartered group responsible for reviewing, evaluating, approving/rejecting changes to project. Also, responsible for recording & communicating. Perform Integrated Change Control -> Key terms -> CCB Change Approver (Matrix should be defined in PMP-change control plan) Change Control Board Responsible Authority Customer or Sponsor Project Manager (small changes as agreed in PMP) Change Control Board Change Request can be: Approved Denied Returned for info Delayed
  • 8. PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com) Change Control system (CCS): • A set of procedures that describes how modifications to the project deliverables and documentation are managed and controlled. • Includes Change control Policy, Setting up CCB. Change Control Tools: • Manual or automated tools to assist with change & configuration management. • At least tools should support activities of the CCB. Perform Integrated Change Control-> Key Terms
  • 9. PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com) Change Control Tools: • Manual or automated tools to assist with change & configuration management. HP- PPM (Project & Portfolio Management) Microsoft SharePoint Perform Integrated Change Control-> Change Control Tools Project Manager: Define formal change process Ensure proper documentation Ensure changes are introduced in a controlled & coordinated manner.
  • 10. PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com) Configuration Management System (CMS): • It is a set of procedures to identify & document changes to product characteristics. • functional & physical characteristics of a product. Identify & document • Any changes to such characteristics.Control • Each change & its implementation status.Record & report • Product audit to verify conformance to requirements. Support Perform Integrated Change Control-> CMS
  • 11. PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com) VSS – Visual Source Safe CVS- Concurrent version system Rational Clear Case Perform Integrated Change Control-> CMS Change Control System (CCS) Configuration Management System (CMS) Other Project Management Systems/ Tools PMIS Configuration Management System (CMS): • It It is a set of procedures to identify & document changes to product characteristics.
  • 12. PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com) Configuration Management System (CMS) Example: • Infrastructure upgrade project for Bank; Bank Locations : 20 • Upgrades : Servers, PC’s/Laptops, Operating Systems & Software's (Local Payroll software, queuing software, Licenses etc), • Different Bank locations has severs with different configurations • Software's with different version. • Some Customized software's Challenges: • To document existing functional & physical characteristics of a products (Servers, PC’s, software versions etc) • Record & report each change & its implementation status. Team will use CMS • track different versions of the Hardware, software during the upgrade. • Allow teams to work simultaneously on the multiple locations. • Provide data for Auditing & reporting status. CMS will Perform Integrated Change Control-> CMS
  • 13. PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com) Configuration identification. •Configuration item are identified •Products and documents are labelled •Accountability is maintained. Configuration status accounting. •Listing of approved configuration •Status of proposed changes •Implementation status Configuration verification and audit. •Ensure corresponding changes are registered •Changes are assessed, approved & tracked •Changes correctly implemented Perform Integrated Change Control-> CMS Configuration Management System (CMS): • It is a set of procedures used to apply technical & administrative direction and scrutiny to identify & document changes to product characteristics.
  • 14. PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com) Reviewing all CR’s, approving changes & managing changes to deliverables, project documents & PMP It allows documented changes within project to be considered in a integrated fashion while reducing a project risk. Perform Integrated Change Control Reviewing & approving CR’s Managing changes Communicating decisions
  • 15. PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com) Perform Integrated Change Control->ITTO Expert Judgment Change Control tools Data analysis Decision making Meetings Project Management plan Project documents Work Performance Reports Change Requests Enterprise environmental factors Organizational process assets Approved Change Request PMP updates Project document updates Change Log Inputs Tools & Techniques Outputs
  • 16. PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com) Perform Integrated Change Control-> Input Project Management plan Project documents Work Performance Reports Change Requests Enterprise environmental factors Organizational process assets
  • 17. PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com) Project management plan It Provides subsidiary plans, baselines & project objectives to compare against CR. Scope baseline Schedule baseline Cost baseline Change Management plan: •Provides the direction for managing the change control process. •Document roles & responsibilities of CCB. Configuration management plan: •Describes configurable items of the project. •Identifies items that will be recorded & updated. Perform Integrated Change Control -> Input -> PMP
  • 18. PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com) Project documents Following Project documents can be considered as inputs: Basis of estimates: • How the duration, cost & resource estimations were derived. Requirements traceability matrix: • Help asses impact of change on project scope. Risk report: • Report may have information on source of project risks related to change request. Perform Integrated Change Control -> Input -> Project documents
  • 19. PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com) Work Performance Reports WPR can provide current health of the project, which is vital for the CR evaluation and decision making. Schedule reports Cost reports Burn up or Burn down Chart Resource availability Histograms Earn value reports Perform Integrated Change Control -> Input -> WPR Monitor & Control Project work Perform Integrated Change Control WPR Current health of the project shown in WPR can impact the CR analysis & decision making.
  • 20. PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com) Change Request Formal proposal to modify any document, deliverables or baseline. These are the requests that the Change Control Board will evaluate and either approve or reject as per CCP process. Perform Integrated Change Control -> Input -> Change Request Monitoring & Controlling PG-> Control Process Validate Scope Control Scope Control Schedule Control Cost Manage Quality Control Communication Control Risks Monitor Stakeholder Eng. Control Procurements Direct & Manage Project work Change Request Perform Integrated Change Control
  • 21. PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com) Organizational process assets Change Control procedures. Process of approving & issuing change authorization. Configuration management process. Enterprise environmental factors - Project Management Information System (PMIS) Scheduling tool Configuration management system Information collection & distribution system Perform Integrated Change Control -> Input -> EEF & OPA Organizational process assets Enterprise environmental factors
  • 22. PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com) Perform Integrated Change Control-> Tools & Techniques Change Control tools Data analysis Expert Judgment Decision making Meetings
  • 23. PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com) Manual or automated tools to assist with change & configuration management. Help record & Track change request via Change log. At least, tools should support activities of the CCB. Perform Integrated Change Control->T&T-> Change Control Tools Change Control tools Microsoft SharePoint HP Portfolio Management
  • 24. PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com) Data analysis •Change request must be analyzed with multiple alternatives. •These alternatives are documented & discussed in the CCB meetings. Alternative analysis •Cost of requested changes will be analyzed against benefits and presented in CCB. Cost benefit analysis Perform Integrated Change Control -> T&T -> Data analysis Alternative analysis Cost benefit analysis Following Data analysis techniques can be used:
  • 25. PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com) Experts discuss & analyze changes. They may be a part of CCB, who decides the outcome of Change Request. Analysis Decision Making Coordination Perform Integrated Change Control -> T&T -> Expert Judgment Expert Judgment
  • 26. PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com) Change control related meetings are conducted by CCB (Analyze, Review, approve/Reject the Change) CCB may also review Configuration Management activities. CCB decisions are formally documented & shared. Perform Integrated Change Control -> T&T -> Meetings Decide on the Change request status (Approve / Reject) Discuss Change request Meetings
  • 27. PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com) Decision making Following Decision making techniques can be used: Perform Integrated Change Control -> T&T -> Decision making Voting Autocratic decision making Multi-criteria decision analysis • Unanimity, Majority, PluralityVoting • one person takes the responsibility for making decision for the entire group Autocratic decision making • Its systematic analytical approach where decision matrix are used. • Matrix will have predefined criteria's for accepting or rejecting change. Multi-criteria decision analysis
  • 28. PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com) Perform Integrated Change Control-> Output Approved Change Request Change Log PMP updates Project document updates
  • 29. PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com) Approved Change request Change Requests are processed according to Change Control System. Approved CR will be implemented through Direct & Manage Project work process. Perform Integrated CC->Output->Approved CR Change Request Perform Integrated Change Control Approved Change request Direct & Manage Project work
  • 30. PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com) Change log Document the changes that occur during a project including rejected changes. It can provide the list of all changes with current status of each change request. Change Request statuses : Status accounting may differ as per company methodology Entry is made when new change is initiated Updated to reflected completion of analysis Updated once shared with CCB Updated with CCB decision Updated when its under development/construction Updated once quality control is completed Updated as ‘Closed’ once change is completely implemented. Perform Integrated Change Control -> Output Manage Stakeholder Engagement
  • 31. PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com) All documents subject to formal Change control Process. Any subsidiary planes and Baselines that are subject to formal Change control Process. Perform Integrated Change Control -> Output -> Project doc. & PMP Project document updates PMP updates
  • 32. PMBOK 6 - All rights reserved 2019; By: Anand Bobade (nmbobade@gmail.com) Perform Integrated Change Control -> Quick Review What is Integrated change control? What is Change Request? What is configuration management? How approved change request are implemented. What is Change log? What are change control tools?