Contents are sourced from different authors including PMBOK 5th Edition.
This is provided for free as part of our Continuing Practice in Project Management Professional Certification. You may download, share but please refrain from commercializing it or altering parts. Thanks.
For more on Innovations and Project Management, please visit www.facebook.com/SigmaProcessExcellence
The document discusses project cost management. It describes that project cost management includes processes to estimate, budget, and control project costs so the project can be completed within budget. It discusses estimating costs as developing an approximation of monetary resources needed to complete project activities. Different types of cost estimates like order of magnitude, conceptual, preliminary and definitive estimates are described along with their typical ranges.
Change occurs in almost every project. It may come in the form to increased project scope, decreased budgets, or accelerated timelines. With all of these opportunities for change, project managers must be prepared to adjust the project plan in response to change. Unfortunately, ineffective project change management practices is one of the most common sources of project failure. Project managers must become better equipped at responding to change in order to increase project success. In this presentation the need for project change management is identified and several tools and strategies for effectively dealing with project change are presented.
The document provides an overview of the role of a project manager. It discusses that a project manager plays a critical leadership role to achieve a project's objectives from initiation through closing. The role of a project manager is compared to that of an orchestra conductor who leads a team and has both management and technical knowledge. A project manager is defined as the person assigned by the organization to lead the team responsible for achieving the project's objectives and has influence within the project team.
Introduction to Project Management by Javid HamdardJavid Hamdard
This document provides an introduction to project management. It discusses key statistics about the project management industry and the benefits of qualified project managers. Common challenges that cause IT projects to fail are outlined, such as unclear objectives and unrealistic schedules. The five process groups of project management are introduced as well as typical project management methodologies like waterfall and agile. Popular project management software applications and certifications are also mentioned.
This document discusses project execution and control. It explains that project execution utilizes prior plans and preparations to deal with unanticipated events while minimizing impacts. The purpose of execution is to construct the facility as commissioned while applying most resources. Execution concludes when the product is fully built, tested, accepted and transitioned to the client. At the end, all deliverables documented in the plan have been produced and the facility is handed over.
Contents are sourced from different authors including PMBOK 5th Edition.
This is provided for free as part of our Continuing Practice in Project Management Professional Certification. You may download, share but please refrain from commercializing it or altering parts. Thanks.
For more on Innovations and Project Management, please visit www.facebook.com/SigmaProcessExcellence
The document discusses project cost management. It describes that project cost management includes processes to estimate, budget, and control project costs so the project can be completed within budget. It discusses estimating costs as developing an approximation of monetary resources needed to complete project activities. Different types of cost estimates like order of magnitude, conceptual, preliminary and definitive estimates are described along with their typical ranges.
Change occurs in almost every project. It may come in the form to increased project scope, decreased budgets, or accelerated timelines. With all of these opportunities for change, project managers must be prepared to adjust the project plan in response to change. Unfortunately, ineffective project change management practices is one of the most common sources of project failure. Project managers must become better equipped at responding to change in order to increase project success. In this presentation the need for project change management is identified and several tools and strategies for effectively dealing with project change are presented.
The document provides an overview of the role of a project manager. It discusses that a project manager plays a critical leadership role to achieve a project's objectives from initiation through closing. The role of a project manager is compared to that of an orchestra conductor who leads a team and has both management and technical knowledge. A project manager is defined as the person assigned by the organization to lead the team responsible for achieving the project's objectives and has influence within the project team.
Introduction to Project Management by Javid HamdardJavid Hamdard
This document provides an introduction to project management. It discusses key statistics about the project management industry and the benefits of qualified project managers. Common challenges that cause IT projects to fail are outlined, such as unclear objectives and unrealistic schedules. The five process groups of project management are introduced as well as typical project management methodologies like waterfall and agile. Popular project management software applications and certifications are also mentioned.
This document discusses project execution and control. It explains that project execution utilizes prior plans and preparations to deal with unanticipated events while minimizing impacts. The purpose of execution is to construct the facility as commissioned while applying most resources. Execution concludes when the product is fully built, tested, accepted and transitioned to the client. At the end, all deliverables documented in the plan have been produced and the facility is handed over.
In today's fast-paced business environment, successful project management has its place on the organizational hall-of-fame.
All major corporations have recognized that the future of their corporate success lies in their employees' abilities to effectively manage overlapping, complex projects.
The concepts and processes on how to perform project scope management according to PMBOK Guide 6th edition. You'll find key concepts and terms, plan scope management, collect requirements, define scope, create WBS, validate scope, and control scope.
This document discusses monitoring and controlling projects. It outlines three scenarios for projects: when they go as planned, when there are changes from stakeholders, and when risks occur. When projects go as planned, the project manager follows the plan, do, check, act cycle to monitor progress. When changes are requested, an integrated change management process is followed, involving change requests, a change control board, and adjusting baselines. Risks can also lead to change requests if their impacts require action. The overall goal is for the project manager to control changes and maintain the project plan.
Introduction to Project Management (workshop) - v.1Mena M. Eissa
This document provides an introduction to project management concepts. It begins with introductions from the presenter and the audience. It then defines key project management terms like project, project management, stakeholders, roles, scope, requirements, deliverables, change, risk and lessons learned. It discusses the triple constraints of scope, time and cost. It also outlines the typical project lifecycle phases of initiating, planning, executing, monitoring/controlling and closing. The document concludes with discussing next steps like certifications and tools to use in project management.
The document provides an overview of key components for an effective project charter, including objectives, scope, deliverables, timelines, budgets, resources, risks, and measures of success. An effective charter clearly defines the project goals, how it fits strategically, what work will be done, when it will be completed, who will work on it, potential challenges, and how success will be determined. The charter establishes a shared understanding and provides essential information to ensure project alignment, buy-in, and successful delivery.
HD version: http://1drv.ms/1i8AvZc
This is my publication on the introduction to project management. In this publication I overview important project management terms, definitions, project life cycles, and key project management software and tools
The document provides an overview of project scope management including:
- Abdullah Alkhdrawy is an instructor for project scope management. He has a civil engineering degree and project management certification and experience.
- Scope management involves planning, collecting requirements, defining, creating a work breakdown structure, validating, and controlling the scope. It aims to ensure all required work and only the required work is included.
- Collecting requirements involves determining, documenting, and managing stakeholder needs through techniques like interviews, workshops, prototypes, and document analysis to develop requirements documentation and a requirements traceability matrix.
The document introduces project execution and the need to develop a Project Execution Plan to outline responsibilities and procedures for delivering agreed upon project outputs, as the plan expands on the Project Business Plan by specifying day-to-day management controls. A Project Execution Plan is developed when a project proposal is approved, and requires knowledge of developing detailed project plans, schedules, quality procedures, reporting, purchasing if needed, risk management, and cost control. The main outputs of project planning include the project execution plan and controls, progress reports, action item logs, project cost control, training plans, risk logs, and lessons learned.
This document summarizes key aspects of project scope management according to the Project Management Body of Knowledge (PMBOK). It discusses the processes involved, including planning scope management, collecting requirements, defining scope, creating a work breakdown structure, validating scope, and controlling scope. For each process, it describes relevant inputs, tools and techniques, and outputs as defined by PMBOK. The overall purpose is to define and manage the scope of a project to meet stakeholder requirements and project objectives.
Project communication management involves planning, collecting, distributing, and managing project information. The key processes are:
1. Plan Communications Management - Developing a communication plan based on stakeholder needs and a communication requirements analysis.
2. Manage Communications - Creating, distributing, and storing project information according to the communication plan using various communication methods and technology.
3. Control Communications - Monitoring and controlling communications throughout the project to ensure stakeholder information needs are met. This includes reviewing performance reports, issues logs, and work performance data.
Project Management Foundations Course 101 - Project Management ConceptsThink For A Change
This document provides an overview of an introductory project management course. The course covers three key segments: an introduction to project management concepts like the project lifecycle and how projects are organized; the typical project management lifecycle phases from initiation to closing; and how projects are organized through different structures and the roles involved like project managers. The goal is to provide students with little experience an overview of fundamental project management principles.
This document outlines the seven phases of the project life cycle: initiation, planning, execution, monitoring and control, and closeout. It describes the key activities and outputs for each phase. The initiation phase involves selecting a project manager and defining objectives. The planning phase develops detailed plans for tasks, schedule, budget, roles and communication. Execution involves executing the plans, and monitoring and control compares results to metrics and identifies variances. The closeout phase hands over the final product and archives lessons learned.
The document discusses the process of formally closing a project. It involves gaining acceptance of final products/services, reflecting on lessons learned, and creating project archives and reports. A Project Review and Closure Report is produced to tidy up any loose ends, review project outputs and success, outline outstanding issues/recommendations, and inform future projects. The report is developed towards the end of the project when all outputs have been delivered.
This document provides an overview of project management. It defines project management as applying knowledge, skills, tools, and techniques to project activities to meet requirements. The project management process involves 5 phases: initiating, planning, executing, monitoring and controlling, and closing. It also discusses the advantages of using project management, which include better efficiency, increased customer satisfaction, and enhanced effectiveness. Additionally, it covers the triple constraints of project management as scope, time and cost, and highlights important skills for project managers such as leadership, listening, and critical thinking.
The document discusses the key aspects of project integration management according to the Project Management Body of Knowledge (PMBOK). It describes the six main processes involved in project integration management: develop project charter, develop project management plan, direct and manage project work, monitor and control project work, perform integrated change control, and close project or phase. It provides details on the inputs, tools and techniques, and outputs of each process. It also discusses some components of the project management plan and charter.
This document provides an overview of project management certification and the Project Management Professional (PMP) designation. It discusses the requirements to become PMP certified, including education, experience, and passing a 200 question exam. The exam covers five process groups: initiation, planning, execution, monitoring and controlling, and closing. Maintaining the PMP certification requires ongoing professional development. The document also introduces key project management concepts like the project management lifecycle, differences between projects and operations, and the role of the project manager.
This document provides an overview of project management software and environments. It discusses project management frameworks and documents such as work breakdown structures, Gantt charts, and budgets. It then summarizes several popular desktop software options for project management including Microsoft Project, Open Workbench, and OmniPlan. Finally, it briefly mentions some web-based project management tools like Zoho Projects and Google Code, and provides additional learning materials on Microsoft Project.
Project portfolio management (PPM) aims to align projects with organizational strategy through assessing project proposals, allocating scarce resources, balancing project risk and size, and continually tracking projects. PPM is aimed at senior management who must ensure strategy and operations are integrated. It involves tasks like investment decision making, matching investments to objectives, and allocating assets. PPM helps improve project success rates and allows organizations to efficiently invest in opportunities critical to their future.
Project change management is important to (1) identify potential problems and take corrective action, (2) ensure an accurate understanding of project progress, and (3) carefully manage changes by rejecting or approving changes and incorporating them into revised baselines. It determines where the project currently stands compared to plans and helps get a project back on track if needed. A change management procedure typically involves identifying needed changes, analyzing feasibility, obtaining approvals, implementing, and reviewing changes.
CHANGE MANAGEMENT PLAN TEMPLATEIntroductionStart the developme.docxcravennichole326
CHANGE MANAGEMENT PLAN TEMPLATE
Introduction
Start the development of your Project Change Management Plan with this template. Download the Microsoft Word version by clicking on the icon below. This template is completely free and is intended to support your project change management process.
Change Management is an important part of any project. Changes must be vetted and managed to ensure that they are within the scope of the project and are communicated to all stakeholders if they are approved. The process for submitting, reviewing, and approving changes must also be communicated to all stakeholders in order to properly set expectations. If changes are allowed to be submitted or are implemented in and unorganized way, any project is sure to fail. All projects must include a Change Management Plan as part of the overall Project Plan, it can either be included as a section in the Project Plan or as an appendix as a subsidiary management plan.
The Change Management Plan was created for the Inventory Services (IS) Project in order to set expectations on how the approach to changes will be managed, what defines a change, the purpose and role of the change control board, and the overall change management process. All stakeholders will be expected to submit or request changes to the IS Project in accordance with this Change Management Plan and all requests and submissions will follow the process detailed herein.
Change Management Approach
This section of the Change Management Plan describes the approach the organization will use for managing change throughout the project. Throughout a project’s lifecycle there may be very few or very many submitted changes. The approach taken to manage these changes must be consistent and repeatable in order to provide a quality change management plan and process.
The Change Management approach for the IS Project will ensure that all proposed changes are defined, reviewed, and agreed upon so they can be properly implemented and communicated to all stakeholders. This approach will also ensure that only changes within the scope of this project are approved and implemented.
The Change Management approach is not to be confused with the Change Management Process which will be detailed later in this plan. The Change Management approach consists of three areas:
· Ensure changes are within scope and beneficial to the project
· Determine how the change will be implemented
· Manage the change as it is implemented
The Change Management process has been designed to make sure this approach is followed for all changes. By using this approach methodology, the IS Project Team will prevent unnecessary change from occurring and focus its resources only on beneficial changes within the project scope.
Definitions of Change
This section of the Change Management Plan defines the different types of changes that may be requested and considered for the project. These changes may include schedule change, budget change, scope change, or pro ...
In today's fast-paced business environment, successful project management has its place on the organizational hall-of-fame.
All major corporations have recognized that the future of their corporate success lies in their employees' abilities to effectively manage overlapping, complex projects.
The concepts and processes on how to perform project scope management according to PMBOK Guide 6th edition. You'll find key concepts and terms, plan scope management, collect requirements, define scope, create WBS, validate scope, and control scope.
This document discusses monitoring and controlling projects. It outlines three scenarios for projects: when they go as planned, when there are changes from stakeholders, and when risks occur. When projects go as planned, the project manager follows the plan, do, check, act cycle to monitor progress. When changes are requested, an integrated change management process is followed, involving change requests, a change control board, and adjusting baselines. Risks can also lead to change requests if their impacts require action. The overall goal is for the project manager to control changes and maintain the project plan.
Introduction to Project Management (workshop) - v.1Mena M. Eissa
This document provides an introduction to project management concepts. It begins with introductions from the presenter and the audience. It then defines key project management terms like project, project management, stakeholders, roles, scope, requirements, deliverables, change, risk and lessons learned. It discusses the triple constraints of scope, time and cost. It also outlines the typical project lifecycle phases of initiating, planning, executing, monitoring/controlling and closing. The document concludes with discussing next steps like certifications and tools to use in project management.
The document provides an overview of key components for an effective project charter, including objectives, scope, deliverables, timelines, budgets, resources, risks, and measures of success. An effective charter clearly defines the project goals, how it fits strategically, what work will be done, when it will be completed, who will work on it, potential challenges, and how success will be determined. The charter establishes a shared understanding and provides essential information to ensure project alignment, buy-in, and successful delivery.
HD version: http://1drv.ms/1i8AvZc
This is my publication on the introduction to project management. In this publication I overview important project management terms, definitions, project life cycles, and key project management software and tools
The document provides an overview of project scope management including:
- Abdullah Alkhdrawy is an instructor for project scope management. He has a civil engineering degree and project management certification and experience.
- Scope management involves planning, collecting requirements, defining, creating a work breakdown structure, validating, and controlling the scope. It aims to ensure all required work and only the required work is included.
- Collecting requirements involves determining, documenting, and managing stakeholder needs through techniques like interviews, workshops, prototypes, and document analysis to develop requirements documentation and a requirements traceability matrix.
The document introduces project execution and the need to develop a Project Execution Plan to outline responsibilities and procedures for delivering agreed upon project outputs, as the plan expands on the Project Business Plan by specifying day-to-day management controls. A Project Execution Plan is developed when a project proposal is approved, and requires knowledge of developing detailed project plans, schedules, quality procedures, reporting, purchasing if needed, risk management, and cost control. The main outputs of project planning include the project execution plan and controls, progress reports, action item logs, project cost control, training plans, risk logs, and lessons learned.
This document summarizes key aspects of project scope management according to the Project Management Body of Knowledge (PMBOK). It discusses the processes involved, including planning scope management, collecting requirements, defining scope, creating a work breakdown structure, validating scope, and controlling scope. For each process, it describes relevant inputs, tools and techniques, and outputs as defined by PMBOK. The overall purpose is to define and manage the scope of a project to meet stakeholder requirements and project objectives.
Project communication management involves planning, collecting, distributing, and managing project information. The key processes are:
1. Plan Communications Management - Developing a communication plan based on stakeholder needs and a communication requirements analysis.
2. Manage Communications - Creating, distributing, and storing project information according to the communication plan using various communication methods and technology.
3. Control Communications - Monitoring and controlling communications throughout the project to ensure stakeholder information needs are met. This includes reviewing performance reports, issues logs, and work performance data.
Project Management Foundations Course 101 - Project Management ConceptsThink For A Change
This document provides an overview of an introductory project management course. The course covers three key segments: an introduction to project management concepts like the project lifecycle and how projects are organized; the typical project management lifecycle phases from initiation to closing; and how projects are organized through different structures and the roles involved like project managers. The goal is to provide students with little experience an overview of fundamental project management principles.
This document outlines the seven phases of the project life cycle: initiation, planning, execution, monitoring and control, and closeout. It describes the key activities and outputs for each phase. The initiation phase involves selecting a project manager and defining objectives. The planning phase develops detailed plans for tasks, schedule, budget, roles and communication. Execution involves executing the plans, and monitoring and control compares results to metrics and identifies variances. The closeout phase hands over the final product and archives lessons learned.
The document discusses the process of formally closing a project. It involves gaining acceptance of final products/services, reflecting on lessons learned, and creating project archives and reports. A Project Review and Closure Report is produced to tidy up any loose ends, review project outputs and success, outline outstanding issues/recommendations, and inform future projects. The report is developed towards the end of the project when all outputs have been delivered.
This document provides an overview of project management. It defines project management as applying knowledge, skills, tools, and techniques to project activities to meet requirements. The project management process involves 5 phases: initiating, planning, executing, monitoring and controlling, and closing. It also discusses the advantages of using project management, which include better efficiency, increased customer satisfaction, and enhanced effectiveness. Additionally, it covers the triple constraints of project management as scope, time and cost, and highlights important skills for project managers such as leadership, listening, and critical thinking.
The document discusses the key aspects of project integration management according to the Project Management Body of Knowledge (PMBOK). It describes the six main processes involved in project integration management: develop project charter, develop project management plan, direct and manage project work, monitor and control project work, perform integrated change control, and close project or phase. It provides details on the inputs, tools and techniques, and outputs of each process. It also discusses some components of the project management plan and charter.
This document provides an overview of project management certification and the Project Management Professional (PMP) designation. It discusses the requirements to become PMP certified, including education, experience, and passing a 200 question exam. The exam covers five process groups: initiation, planning, execution, monitoring and controlling, and closing. Maintaining the PMP certification requires ongoing professional development. The document also introduces key project management concepts like the project management lifecycle, differences between projects and operations, and the role of the project manager.
This document provides an overview of project management software and environments. It discusses project management frameworks and documents such as work breakdown structures, Gantt charts, and budgets. It then summarizes several popular desktop software options for project management including Microsoft Project, Open Workbench, and OmniPlan. Finally, it briefly mentions some web-based project management tools like Zoho Projects and Google Code, and provides additional learning materials on Microsoft Project.
Project portfolio management (PPM) aims to align projects with organizational strategy through assessing project proposals, allocating scarce resources, balancing project risk and size, and continually tracking projects. PPM is aimed at senior management who must ensure strategy and operations are integrated. It involves tasks like investment decision making, matching investments to objectives, and allocating assets. PPM helps improve project success rates and allows organizations to efficiently invest in opportunities critical to their future.
Project change management is important to (1) identify potential problems and take corrective action, (2) ensure an accurate understanding of project progress, and (3) carefully manage changes by rejecting or approving changes and incorporating them into revised baselines. It determines where the project currently stands compared to plans and helps get a project back on track if needed. A change management procedure typically involves identifying needed changes, analyzing feasibility, obtaining approvals, implementing, and reviewing changes.
CHANGE MANAGEMENT PLAN TEMPLATEIntroductionStart the developme.docxcravennichole326
CHANGE MANAGEMENT PLAN TEMPLATE
Introduction
Start the development of your Project Change Management Plan with this template. Download the Microsoft Word version by clicking on the icon below. This template is completely free and is intended to support your project change management process.
Change Management is an important part of any project. Changes must be vetted and managed to ensure that they are within the scope of the project and are communicated to all stakeholders if they are approved. The process for submitting, reviewing, and approving changes must also be communicated to all stakeholders in order to properly set expectations. If changes are allowed to be submitted or are implemented in and unorganized way, any project is sure to fail. All projects must include a Change Management Plan as part of the overall Project Plan, it can either be included as a section in the Project Plan or as an appendix as a subsidiary management plan.
The Change Management Plan was created for the Inventory Services (IS) Project in order to set expectations on how the approach to changes will be managed, what defines a change, the purpose and role of the change control board, and the overall change management process. All stakeholders will be expected to submit or request changes to the IS Project in accordance with this Change Management Plan and all requests and submissions will follow the process detailed herein.
Change Management Approach
This section of the Change Management Plan describes the approach the organization will use for managing change throughout the project. Throughout a project’s lifecycle there may be very few or very many submitted changes. The approach taken to manage these changes must be consistent and repeatable in order to provide a quality change management plan and process.
The Change Management approach for the IS Project will ensure that all proposed changes are defined, reviewed, and agreed upon so they can be properly implemented and communicated to all stakeholders. This approach will also ensure that only changes within the scope of this project are approved and implemented.
The Change Management approach is not to be confused with the Change Management Process which will be detailed later in this plan. The Change Management approach consists of three areas:
· Ensure changes are within scope and beneficial to the project
· Determine how the change will be implemented
· Manage the change as it is implemented
The Change Management process has been designed to make sure this approach is followed for all changes. By using this approach methodology, the IS Project Team will prevent unnecessary change from occurring and focus its resources only on beneficial changes within the project scope.
Definitions of Change
This section of the Change Management Plan defines the different types of changes that may be requested and considered for the project. These changes may include schedule change, budget change, scope change, or pro ...
Change Management is the process of monitoring and controlling changes within a project to reduce impacts, identify new issues and risks, ensure objectives are still achievable, and control costs. It begins with documenting change requests, which are then reviewed by the Project Manager to determine if the change is critical. Critical changes are approved by the Project Board and implemented according to the project schedule. Finally, the Project Manager reviews implemented changes to ensure desired outcomes were achieved before closing the change request.
How Implementing an effective Change Control process can have a positive impact on a project. This presentation will bring you through a step by step guide to accomplish this goal.
This document outlines a change control plan with the following key points:
- It provides two examples of a change control process - a simple process for smaller projects and a more complex process for larger projects.
- The simple process involves a project manager and sponsor, while the complex process adds a change control board.
- Both processes describe how a change request is submitted, analyzed for impact, approved or denied, and then implemented if approved.
- The complex process includes additional documentation like a change request form and impact statement, and more statuses for tracking changes.
- Roles, activities, and documentation requirements are clearly defined for transparently managing the change control workflow.
This document provides a change management plan template for the Inventory Services Project. It outlines the change management approach, definitions of change, roles of the Change Control Board, and the change control process. The change management approach ensures all proposed changes are properly defined, reviewed, approved, implemented, and communicated. The change control board reviews and approves or denies all change requests. The change control process involves identifying needs, logging requests, submitting to the board, obtaining a decision, and implementing any approved changes.
The document discusses key concepts in project integration management. It begins by explaining that integration management involves planning the work, ensuring the work is completed properly while managing changes, and closing the project. It then provides examples of integration processes and discusses how work should be integrated across the organization. It also covers topics like the project charter, schedule, change control, lessons learned system, and how stakeholders contribute to the project plan.
It is very important for a project to implement a robust project change request process to help manage succesful delivery.
This presentation provides an overview of the 5 core steps of the project change control process.
Ideal for a PMO or project team looking to implement their own change control process.
Project Management and Change Management - Sean LowPink Elephant
Project Management & Change Management: The Value & Challenges Of Integration & Alignment
Join Sean for a highly interactive discussion about the often challenging relationship between Project Management and Change Management. Come prepared to contribute your questions, insights and opinions to this session which will focus on various aspects of this highly engaging topic.
Sean will answer questions like:
1) Should change managers have the authority to say “NO” to project changes?
2) To what extent should projects be exempt from the Change Management process?
3) At what point in a Project Lifecycle should change managers expect project managers to submit requests for change?
4) What roles are designated in ITIL to coordinate change efforts between Project Management and Change Management?
The document discusses establishing an effective change control process for construction projects. It emphasizes that changes should be minimized but rigorously controlled. It outlines establishing a change control strategy early, defining the process, documenting it, establishing a log to track changes, agreeing whether changes are acceptable, and reporting costs with agreed changes. The key aspects of the change control process are defining the baseline, tracking changes, approving or rejecting changes, adjusting budgets and schedules, and regularly reporting on changes.
The document discusses establishing an effective change control process for construction projects. It emphasizes that changes should be minimized but rigorously controlled. It outlines establishing a change control strategy early, defining the process, documenting it, establishing a log to track changes, agreeing whether changes are acceptable, and reporting costs with agreed changes. The key aspects of the change control process are defining the baseline, tracking changes, approving or rejecting changes, adjusting budgets and schedules, and reporting on changes regularly.
The document discusses integration management and key project documents. It describes a project charter, project management plan, configuration management, and change control system. Integrated change control occurs throughout the project and involves identifying, approving, managing, and documenting all changes. Maintaining the project baseline is important when changes are made. Historical information and a project plan can help improve a new project manager's chances of success.
This document discusses maintaining a business continuity and disaster recovery (BC/DR) plan. It notes that maintaining the plan may be the biggest challenge after developing it. It outlines strategies for managing change to the plan, including monitoring for changes, evaluating proposed changes, and incorporating approved changes. Some key sources of change include technology changes, operational changes, corporate changes, and legal/regulatory changes. The document emphasizes the importance of auditing the plan during training and testing exercises to identify needed changes.
The document discusses project scope management. It defines scope management as defining and managing what is included and excluded from a project. Scope management involves planning, controlling, and closing processes. Planning involves determining project goals, tasks, deadlines and budgets. Controlling involves documenting and approving/disapproving changes. Closing examines completed deliverables against the original plan. Effective scope management provides clarity on project requirements, tasks, timelines and costs.
1. The document discusses managing changes during construction projects to reduce their negative impacts and improve productivity. Effective change management is essential.
2. Many factors can cause changes, including assumptions being proven wrong and external/internal influences. Changes must be identified, their impacts planned for, and coordination ensured across the project.
3. Tools like scheduling, modeling, and cost control systems can help construction managers monitor costs, identify deviations early, and take corrective actions to reduce overruns from changes. Close monitoring of activities and costs is important for change management.
1. The document discusses managing changes during construction projects to reduce their negative impacts and improve productivity. Effective change management is essential.
2. Many factors can cause changes, including assumptions being proven wrong and external/internal influences. Changes must be identified, their impacts planned for, and coordination ensured across the project.
3. Key aspects of change management are monitoring costs, controlling scope changes, and identifying causes of changes to mitigate negative effects like cost overruns. Change control systems help observe costs and allow timely corrective actions.
1. The document discusses managing changes during construction projects to reduce their negative impacts and improve productivity. Effective change management is essential.
2. Many factors can cause changes, including assumptions being proven wrong and external/internal influences. Changes must be identified, their impacts planned for, and coordination ensured across the project.
3. Tracking costs and taking immediate steps if overruns are detected are important for change control. Software tools can help monitor costs and provide early warnings to facilitate corrective actions.
Education is Fundamental to the Nation Building Process.
Right to Education is now a Fundamental Right of every child in India.
GST Law Recognizes this and provides Certain Exemption to Educational Institutions, providing Education
In this Presentation let's Discuss the Applicability of GST on Education Sector
Eliminating 8 Wastes For Improving Supplychain EfficacyMMR July 2022 SN Panigrahi, PMP
A supply chain is a Chain of Supplies -
is the network of all the individuals,
organizations, resources, activities and
technology involved in the creation and supply of a
product, from the delivery of source materials from
the Supplier to Manufacturer to Distributer to
Wholesaler to Retailer and Eventually Delivery to the
End User or Consumer. Lean is the concept of efficient
manufacturing/operations that grew out of
the Toyota Production System in the middle of the
20th century. Since then, “lean” which was started as
an important concept, in the world of manufacturing
first, has thrived in to other fields such as Supply Chain
Management (SCM). Lean management is an approach
to managing an organization that supports the concept
of continuous improvement, a long-term approach to
work that systematically seeks to achieve small,
incremental changes in the processes in order to
improve efficiency and quality by eliminating or
minimising the process waste and maximising the value
of the product or service to the customer.
In this article we shall discuss 8 types of wastes in the
entire value stream of supply chain and analyse Cause
- Effect & Solution for improving Supply Chain Efficacy.
Session - 2 Introduction to Customs Act & Procedures by SN PanigrahiSN Panigrahi, PMP
The document discusses the history and development of the internet over the past 50 years, from its origins as a US military program called ARPANET to the commercialization of the world wide web in the 1990s. It led to an explosion of new technologies and services over the following decades that have transformed how people live and work through communication, education, business and entertainment.
Session - 1 Overview of International Trade By SN Panigrahi ...SN Panigrahi, PMP
The document discusses the benefits of exercise for mental health. Regular physical activity can help reduce anxiety and depression and improve mood and cognitive function. Exercise stimulates the production of endorphins in the brain which elevate mood and reduce stress levels.
SUPPLY CHAIN DISRUPTIONS & RESILIENCE - By SN PanigrahiSN Panigrahi, PMP
SUPPLY CHAIN DISRUPTIONS & RESILIENCE
Article Published in Materials Management Review of IIMM
SN Panigrahi
#IIMM,
#materialsmanagement,
#supplychainmanagement,
#supplychaindisruptions,
#supplychainresilience,
Challenges of Apparel Exports from India - Presentation @ Indian Institute...SN Panigrahi, PMP
I had an Opportunity to Provide Training to the Officials of Directorate of MSME, Govt. of West Bengal on "Training of Master Trainers for Export Consultancy in the Gems and Jewellery & Apparel Sector of West Bengal“
Through Indian Institute of Foreign Trade (IIFT), Kolkata on Hybrid Mode on 1st Dec'2021.
This is Part of West Bengal Government's Strategy to Promote Exports from the State. West Bengal Government Targeted to Double the Apparel Exports from the State in next 3-5 Years.
SN Panigrahi
GST for Supply Chain Professionals Webinar of IIMM - Hyderabad SN Panigrahi, PMP
➢ GST is a comprehensive indirect tax on the supply of goods and services throughout India that replaced multiple cascading taxes levied by the central and state governments.
➢ It is a destination-based tax collected by the government based on where the consumption takes place rather than the origin of the goods or services.
➢ Under GST, a taxable person is required to register if their aggregate turnover exceeds ₹20 lakhs or ₹10 lakhs in special category states. They are issued a PAN-based 15-digit GST registration number.
What is Lean? Understanding Lean Principles by SN PanigrahiSN Panigrahi, PMP
What is Lean? Understanding Lean Principles by SN Panigrahi
Lean is a way of thinking about creating needed value with fewer resources and less waste. Lean is a practice consisting of continuous experimentation to achieve perfect value with zero waste.
RoDTEP Scheme - Manner to Issue & Utilization of Duty Credit for Goods Expor...SN Panigrahi, PMP
RoDTEP Scheme - Manner to Issue & Utilization of Duty Credit for Goods Exported - By SN Panigrahi
Remission of Duties or Taxes on Export Products (RoDTEP) was introduced for the Exporters to make Indian products cost-competitive and create a level playing field for them in the Global Market by Refund un-refunded Taxes or Duties / Levies, not Exempted or Rebated at Present by any other Mechanism.
Government Issued an Advisory on 1st Jan’2021, to implement the Scheme effective from 1st Jan’2021, and allowed the exporters to claim in the Shipping Bill, even though Rates were not announced. Subsequently the Rates range from 0.5% to 4.3% for various Sectors at 8 Digit Level as per Appendix – 4R of Hand Book of Procedures were announced by DGFT vide: Notification 19 / 2015-2020, dated 17th Aug’2021.
Now, CBIC announced the Manner of Issue Duty Credit for Goods Exported under the scheme vide Notification No: 76/2021-Customs (N.T.), 23rd September, 2021.
Enterprise Risk Assessment : A Pro-active Measure to Establish Strategic Prio...SN Panigrahi, PMP
Enterprise Risk Assessment : A Pro-active Measure to Establish Strategic Priorities & To Tackle Key Business Risks- By SN Panigrahi
Enterprise Risk Assessment Tool is used by organizations to Manage Risks Pro-actively and Seize Opportunities related to the achievement of their Objectives. Risk Assessment outcomes help Organizations to Establish Strategic Priorities and Activities to Tackle Key Risks. Increasing Awareness and Imbibing Risk Culture with Involvement of Top Management & Cross Functional Teams shall enhance the Organizations ability to Understand, Identify, and Develop Action Plans in Advance to Pro-Actively Manage Risks.
Re-Export of Warehoused Goods to Nepal & Bhutan - SN PanigrahiSN Panigrahi, PMP
SN Panigrahi is an experienced business consultant, trainer, and author with over 30 years of experience in fields like project management, supply chain management, procurement, and indirect taxes. He has conducted over 200 workshops globally and published over 500 articles. He holds certifications from various organizations including PMI, Lean Six Sigma, and the Government of India. Panigrahi shares his expertise as a speaker and has received awards for his writings and contributions to business. He provides his contact information at the end.
Hybrid Project Life Cycle - By SN Panigrahi,
Understanding Project Phase & Project Life Cycle,
Types of Project Life Cycle,
Predictive Life Cycle,
Iterative Life Cycle,
Incremental Life Cycle,
Adaptive Life Cycle,
Agile Life Cycle,
Hybrid Life Cycle,
Characteristics of Hybrid Life Cycles,
1.Agile Development Followed by a Predictive Model,
2. Combined Agile and Predictive Approaches,
3. Predominantly Predictive Approach with Some Agile Components,
4. Largely Agile Approach with a Predictive Component,
#HybridLifeCycle,
#PredictiveLifeCycle,
#AgileLifeCycle
#pmpexam,
#pmpcertification,
#pmptraining,
#pmpexamprep,
#pmpcertificationexam,
#pmp2021,
#pmpcommunity
#ProjectFundamentals
#SNPanigrahi,
#EssAnnPee Business Solutions
Export Logistics- A Critical Analysis By SN PanigrahiSN Panigrahi, PMP
The document discusses the history and development of the internet over the past 50 years, from its origins as a US military program called ARPANET to the commercialization of the world wide web in the 1990s. It grew exponentially from the 1980s onward and now billions of people use the internet for communication, information, commerce, and entertainment on a daily basis. The internet has fundamentally changed how society interacts and shares information on a global scale.
Choosing Right CHA & Freight Forwarders - By SN PanigrahiSN Panigrahi, PMP
Choosing Right CHA & Freight Forwarders - By SN Panigrahi,
Basic Understanding of Exports,
Incoterms – 2020 : Key Considerations to Avoid Risk,
Role of Logistic Intermediaries : CHAs / Forwarders /1PL, 2PL, 3PL, 4PL,
Selection of CHAs / Freight Forwarders / Shipping Lines,
#SN Panigrahi,
#EssAnnPee Business Solutions,
The APCO Geopolitical Radar - Q3 2024 The Global Operating Environment for Bu...APCO
The Radar reflects input from APCO’s teams located around the world. It distils a host of interconnected events and trends into insights to inform operational and strategic decisions. Issues covered in this edition include:
Best Competitive Marble Pricing in Dubai - ☎ 9928909666Stone Art Hub
Stone Art Hub offers the best competitive Marble Pricing in Dubai, ensuring affordability without compromising quality. With a wide range of exquisite marble options to choose from, you can enhance your spaces with elegance and sophistication. For inquiries or orders, contact us at ☎ 9928909666. Experience luxury at unbeatable prices.
[To download this presentation, visit:
https://www.oeconsulting.com.sg/training-presentations]
This presentation is a curated compilation of PowerPoint diagrams and templates designed to illustrate 20 different digital transformation frameworks and models. These frameworks are based on recent industry trends and best practices, ensuring that the content remains relevant and up-to-date.
Key highlights include Microsoft's Digital Transformation Framework, which focuses on driving innovation and efficiency, and McKinsey's Ten Guiding Principles, which provide strategic insights for successful digital transformation. Additionally, Forrester's framework emphasizes enhancing customer experiences and modernizing IT infrastructure, while IDC's MaturityScape helps assess and develop organizational digital maturity. MIT's framework explores cutting-edge strategies for achieving digital success.
These materials are perfect for enhancing your business or classroom presentations, offering visual aids to supplement your insights. Please note that while comprehensive, these slides are intended as supplementary resources and may not be complete for standalone instructional purposes.
Frameworks/Models included:
Microsoft’s Digital Transformation Framework
McKinsey’s Ten Guiding Principles of Digital Transformation
Forrester’s Digital Transformation Framework
IDC’s Digital Transformation MaturityScape
MIT’s Digital Transformation Framework
Gartner’s Digital Transformation Framework
Accenture’s Digital Strategy & Enterprise Frameworks
Deloitte’s Digital Industrial Transformation Framework
Capgemini’s Digital Transformation Framework
PwC’s Digital Transformation Framework
Cisco’s Digital Transformation Framework
Cognizant’s Digital Transformation Framework
DXC Technology’s Digital Transformation Framework
The BCG Strategy Palette
McKinsey’s Digital Transformation Framework
Digital Transformation Compass
Four Levels of Digital Maturity
Design Thinking Framework
Business Model Canvas
Customer Journey Map
Top mailing list providers in the USA.pptxJeremyPeirce1
Discover the top mailing list providers in the USA, offering targeted lists, segmentation, and analytics to optimize your marketing campaigns and drive engagement.
Industrial Tech SW: Category Renewal and CreationChristian Dahlen
Every industrial revolution has created a new set of categories and a new set of players.
Multiple new technologies have emerged, but Samsara and C3.ai are only two companies which have gone public so far.
Manufacturing startups constitute the largest pipeline share of unicorns and IPO candidates in the SF Bay Area, and software startups dominate in Germany.
HOW TO START UP A COMPANY A STEP-BY-STEP GUIDE.pdf46adnanshahzad
How to Start Up a Company: A Step-by-Step Guide Starting a company is an exciting adventure that combines creativity, strategy, and hard work. It can seem overwhelming at first, but with the right guidance, anyone can transform a great idea into a successful business. Let's dive into how to start up a company, from the initial spark of an idea to securing funding and launching your startup.
Introduction
Have you ever dreamed of turning your innovative idea into a thriving business? Starting a company involves numerous steps and decisions, but don't worry—we're here to help. Whether you're exploring how to start a startup company or wondering how to start up a small business, this guide will walk you through the process, step by step.
The Steadfast and Reliable Bull: Taurus Zodiac Signmy Pandit
Explore the steadfast and reliable nature of the Taurus Zodiac Sign. Discover the personality traits, key dates, and horoscope insights that define the determined and practical Taurus, and learn how their grounded nature makes them the anchor of the zodiac.
Profiles of Iconic Fashion Personalities.pdfTTop Threads
The fashion industry is dynamic and ever-changing, continuously sculpted by trailblazing visionaries who challenge norms and redefine beauty. This document delves into the profiles of some of the most iconic fashion personalities whose impact has left a lasting impression on the industry. From timeless designers to modern-day influencers, each individual has uniquely woven their thread into the rich fabric of fashion history, contributing to its ongoing evolution.
Best practices for project execution and deliveryCLIVE MINCHIN
A select set of project management best practices to keep your project on-track, on-cost and aligned to scope. Many firms have don't have the necessary skills, diligence, methods and oversight of their projects; this leads to slippage, higher costs and longer timeframes. Often firms have a history of projects that simply failed to move the needle. These best practices will help your firm avoid these pitfalls but they require fortitude to apply.
The Genesis of BriansClub.cm Famous Dark WEb PlatformSabaaSudozai
BriansClub.cm, a famous platform on the dark web, has become one of the most infamous carding marketplaces, specializing in the sale of stolen credit card data.
Taurus Zodiac Sign: Unveiling the Traits, Dates, and Horoscope Insights of th...my Pandit
Dive into the steadfast world of the Taurus Zodiac Sign. Discover the grounded, stable, and logical nature of Taurus individuals, and explore their key personality traits, important dates, and horoscope insights. Learn how the determination and patience of the Taurus sign make them the rock-steady achievers and anchors of the zodiac.
Call8328958814 satta matka Kalyan result satta guessing➑➌➋➑➒➎➑➑➊➍
Satta Matka Kalyan Main Mumbai Fastest Results
Satta Matka ❋ Sattamatka ❋ New Mumbai Ratan Satta Matka ❋ Fast Matka ❋ Milan Market ❋ Kalyan Matka Results ❋ Satta Game ❋ Matka Game ❋ Satta Matka ❋ Kalyan Satta Matka ❋ Mumbai Main ❋ Online Matka Results ❋ Satta Matka Tips ❋ Milan Chart ❋ Satta Matka Boss❋ New Star Day ❋ Satta King ❋ Live Satta Matka Results ❋ Satta Matka Company ❋ Indian Matka ❋ Satta Matka 143❋ Kalyan Night Matka..
Navigating the world of forex trading can be challenging, especially for beginners. To help you make an informed decision, we have comprehensively compared the best forex brokers in India for 2024. This article, reviewed by Top Forex Brokers Review, will cover featured award winners, the best forex brokers, featured offers, the best copy trading platforms, the best forex brokers for beginners, the best MetaTrader brokers, and recently updated reviews. We will focus on FP Markets, Black Bull, EightCap, IC Markets, and Octa.
[To download this presentation, visit:
https://www.oeconsulting.com.sg/training-presentations]
This PowerPoint compilation offers a comprehensive overview of 20 leading innovation management frameworks and methodologies, selected for their broad applicability across various industries and organizational contexts. These frameworks are valuable resources for a wide range of users, including business professionals, educators, and consultants.
Each framework is presented with visually engaging diagrams and templates, ensuring the content is both informative and appealing. While this compilation is thorough, please note that the slides are intended as supplementary resources and may not be sufficient for standalone instructional purposes.
This compilation is ideal for anyone looking to enhance their understanding of innovation management and drive meaningful change within their organization. Whether you aim to improve product development processes, enhance customer experiences, or drive digital transformation, these frameworks offer valuable insights and tools to help you achieve your goals.
INCLUDED FRAMEWORKS/MODELS:
1. Stanford’s Design Thinking
2. IDEO’s Human-Centered Design
3. Strategyzer’s Business Model Innovation
4. Lean Startup Methodology
5. Agile Innovation Framework
6. Doblin’s Ten Types of Innovation
7. McKinsey’s Three Horizons of Growth
8. Customer Journey Map
9. Christensen’s Disruptive Innovation Theory
10. Blue Ocean Strategy
11. Strategyn’s Jobs-To-Be-Done (JTBD) Framework with Job Map
12. Design Sprint Framework
13. The Double Diamond
14. Lean Six Sigma DMAIC
15. TRIZ Problem-Solving Framework
16. Edward de Bono’s Six Thinking Hats
17. Stage-Gate Model
18. Toyota’s Six Steps of Kaizen
19. Microsoft’s Digital Transformation Framework
20. Design for Six Sigma (DFSS)
To download this presentation, visit:
https://www.oeconsulting.com.sg/training-presentations
Top 10 Free Accounting and Bookkeeping Apps for Small BusinessesYourLegal Accounting
Maintaining a proper record of your money is important for any business whether it is small or large. It helps you stay one step ahead in the financial race and be aware of your earnings and any tax obligations.
However, managing finances without an entire accounting staff can be challenging for small businesses.
Accounting apps can help with that! They resemble your private money manager.
They organize all of your transactions automatically as soon as you link them to your corporate bank account. Additionally, they are compatible with your phone, allowing you to monitor your finances from anywhere. Cool, right?
Thus, we’ll be looking at several fantastic accounting apps in this blog that will help you develop your business and save time.
Starting a business is like embarking on an unpredictable adventure. It’s a journey filled with highs and lows, victories and defeats. But what if I told you that those setbacks and failures could be the very stepping stones that lead you to fortune? Let’s explore how resilience, adaptability, and strategic thinking can transform adversity into opportunity.
How are Lilac French Bulldogs Beauty Charming the World and Capturing Hearts....Lacey Max
“After being the most listed dog breed in the United States for 31
years in a row, the Labrador Retriever has dropped to second place
in the American Kennel Club's annual survey of the country's most
popular canines. The French Bulldog is the new top dog in the
United States as of 2022. The stylish puppy has ascended the
rankings in rapid time despite having health concerns and limited
color choices.”
2. 2
Change is inevitable in any Project. Within your project, you will experience
change at some point.
Change is never easy, especially in a context of Managing Projects, as it
affects a lot of aspects. In order to ensure a smooth transition from the current
state to the desired state in projects, you need the correct change management
tools and resources at hand.
Having a well thought out plan on how to handle change when it is requested is
critical to your success.
Change Management is necessary to successfully implement changes in the
Project.
Change management has become one of the most critical success factors for
any Project and therefore "Change management is key to the project.“
3. 3
What is Change Management?
In the simplest of terms, change management is a systematic approach towards dealing with
change. It’s a structured way of applying tools, knowledge, and resources to effectively drive and
ensuring that changes are thoroughly and smoothly implemented, and that the lasting benefits of
change are achieved.
The underlying principle is that change does not happen in Isolation – it may impact the whole
Project, particularly on Six Constraints namely Scope, Schedule, Cost, Quality, Resources & Risk, as
the Project move from the Current Situation to the New one. Change Management is, therefore, a
very broad field, and approaches to managing change vary widely, from project to project.
For every project you should create a well thought out change management plan, because as we
said above, change is inevitable, so we have to plan for it.
Change management is a part of the Integration Management knowledge area and contains
processes within the Planning and Monitor and Control process groups.
4. 4
The change Management process is the sequence of steps or activities that a change
management team or project leader follow to apply change management to a change in order
to drive individual transitions and ensure the project meets its intended outcomes.
The below elements have been identified from research as key elements of a successful
change management process.
The activities involved in managing change can include:
➢ Is there is clear expression of the Reasons for Change
➢ “Why are we Making this change?”
➢ How big is this change?
➢ “What is Impact on Scope, Schedule, Cost, Quality, Resources & Risk due to Proposed
Changes?
➢ What are the Root Causes of Change?
➢ What Planning Activities Needed to Address the Impacts of the Change.
➢ “Who are the Sponsors we need to involve to make this successful?”
➢ How to implement the Changes
5. 5
➢ A Change Request is a Formal Proposal to modify any document, deliverable or baseline.
➢ Several Project Management Processes may Involve a Change Request.
➢ Changes may or may not impact the project baselines - sometimes only the performance
against the baseline is affected. Decisions on those changes are usually made by the project
manager.
➢ Change Requests that have an impact on the project baselines should be approved by the
CCB (if it exists) and by the customer or sponsor, unless they are part of the CCB.
➢ Change requests may include corrective action, preventive action, defect repairs, as well as
updates to formally controlled documents or deliverables to reflect modified or additional ideas or
content.
➢ Following are Change Management Activities :
❖ Identify changes. Identifying and selecting a change item for processes or project documents.
❖ Document changes. Documenting the change into a proper change request.
❖ Decide on changes. Reviewing the changes; approving, rejecting, deferring, or making any
other decision about changes to the project documents, deliverables, or baselines.
❖ Track changes. Verifying that the changes are registered, assessed, approved, and tracked
and communicating final results to stakeholders.
6. 6
Change
Request
Changes may or may not
impact the project baselines—
sometimes only the
performance against the
baseline is affected. Decisions
on those changes are usually
made by the project manager.
Change Requests that have an
impact on the project baselines
should be approved by the CCB
(if it exists) and by the customer
or sponsor, unless they are part
of the CCB.
Identify
Change
Document
Changes
Decide on
Changes
Track
Changes
Corrective Action
Preventive Action
Defect Repairs
May Include
Updates
A Change Request is a
Formal Proposal to modify
any document, deliverable
or baseline.
Several Project
Management Processes
may Involve a Change
Request.
7. 7
➢ Many Processes Produce Change Requests as an output.
➢ The Perform Integrated Change Control Process is conducted from Project Start through
Completion.
➢ It is the ultimate Responsibility of the Project Manager.
➢ Change Requests can Impact the Project Scope and the Product scope, as well as any
Project Management Plan (Baselines – Scope, Schedule, Cost) component or any Project
Document.
➢ Changes may be Requested by any Stakeholder involved with the project and may occur at
any time throughout the project life cycle.
➢ Before the Baselines are established, changes are not required to be formally controlled
by the Perform Integrated Change Control process.
➢ Once the Project is Baselined, change requests go through this process.
➢ As a general rule, each project’s configuration management plan should define which project
artifacts need to be placed under configuration control. Any change in a configuration
element should be formally controlled and will require a change request.
8. 8
❖ Although changes may be initiated verbally, they should be Recorded in Written Form and
entered into the change management and/or configuration management system.
❖ Change Requests may require information on estimated schedule impacts and estimated
cost impacts prior to approval.
❖ Whenever a change request may impact any of the project baselines, a formal integrated
change control process is always required.
❖ Every documented change request needs to be either approved, deferred, or rejected by a
responsible individual, usually the project sponsor or project manager.
❖ The Responsible Individual will be identified in the project management plan or by
organizational procedures.
❖ When required, the Perform Integrated Change Control process includes a change control
board (CCB), which is a formally chartered group responsible for reviewing, evaluating,
approving, deferring, or rejecting changes to the project and for recording and
communicating such decisions.
❖ Only approved changes should be incorporated into a revised baseline.
9. 9
❖ A Change Request (CR) is an Output of most Executing and all M&C Processes.
❖ A CR is an Input (only) to the PICC Process.
❖ A Decision for CR is taken by the Change Control Board (CCB) in PICC process.
❖ A CR can be Approved, Partially Approved, Rejected, or kept in abeyance by CCB.
❖ Approved changes and Change Log is Output of PICCC.
❖ Only Approved Changes should be incorporated into a Revised Baseline.
❖ Approved changes are Input to the Direct & Manage Project Work (D&MPW) process,
where they are Implemented after Updating the Project Management Plan (Mainly
Baselines – Scope Baseline, Schedule Baseline, Cost Baseline) & Project Documents.
10. 10
Process
Perform
Integrated
Change
Control
(PICC)
is the process
of Reviewing all
Change
Requests &
Deciding on
Change.
Process Group
Monitor & Control
Knowledge Area
Integration
Management
Input
Change Requests
Executing
Processes
Monitor &
Control
Processes
Output
Direct &
Manage
Project Work
Change Log
Approved
Change
Requests
Many Processes
Produce Change
Requests as an Output. Control
Quality
Control
Procurement
11. 11
Identify New Change Request
Impact Analysis of CR
Document CR
Present / Submit CR to the
CCB
Decision to Accept or Reject
CR
Update Change Log, Project Mgt
Plan & other Documents +
Communicate to Stakeholder(s)
Implement Approved
Changes
A CR can be Identified by Any Stakeholder.
She/he can be part of project team or
outside the project team.
PM and/or Project Team members analyze
the impact of CR on various project
objectives e.g. Scope, Schedule, Cost etc.
PM and/or Project Team members
documents the CR. They also document
suggested alternatives and possible
solutions.
PM and/or Project Team members presents
the documented CR to CCB members. They
explain its impact on various project
objectives.
CCB takes a decision on CR. It can approve,
reject, or partially approve the CR. It can
also ask PM to re-document it or postpone
the decision to a later date.
PM and/or Project Team members Update
Project Plan & Documents and
communicates the decision taken by CCB to
the Concerned stakeholders.
PM and/or Project Team members
implement the approved changes
Any Stakeholder
Project Manager
Project Manager
Project Manager
PM could be a Member of CCB
Change Control Board
(CCB)
Project Manager
Project Manager
12. Whether
Change is
Required?
Changes Requested by
Many Stakeholders
Changes may be
Required from Various
Process
Reject Change
Yes
No
Raise
Change Request
Record Change Request in
Change Log
Analyse Impact of
Change Request
Submit Change Request
with the Proposal to CCB
CCB has
Authority to
Accept or
Reject the
Change
Request
Change
Request
Accepted by
CCB?
Update Change Log;
Update Project Mgt. Plan;
- Update Baselines
Update Project Documents
Communicate to
Concerned Stakeholders
Approved Change Request
Yes
Update Change Log;
Communicate to
Initiator
After Updates
Implement Changes
as per the Revised Project
Management Plan &
Project Documents
Direct & Manage
Project Work
Control
Quality
No
Control
Procurement
Execute
13. 13
➢A modification to any formally controlled deliverable, project management plan component, or
project document.Change
❖Change Management is a systematic approach towards dealing with change. It’s a structured way
of applying tools, knowledge, and resources to effectively drive and ensuring that changes are
thoroughly and smoothly implemented, and that the lasting benefits of change are achieved.
Change
Management
➢A Component of the Project Management Plan that establishes the change control board,
documents the extent of its authority, and describes how the change control system will be
implemented.
Change
Management Plan
❖A Process whereby Modifications to Documents, Deliverables, or Baselines Associated with the
Project are Identified, Documented, Approved, or Rejected.
Change
Control
➢Perform Integrated Change Control (PICC) is the process of Reviewing all Change Requests &
Deciding on Change.
Perform Integrated
Change Control
(PICC)
14. 14
❖The approved version of a work product that can be changed only through formal change control
procedures and is used as a basis for comparison to actual results.Baseline
➢A Formal Proposal to Modify a Document, Deliverable, or Baseline. This request is submitted to the
Change Control Board.Change Request
❖A comprehensive list of changes submitted during the project and their current status.Change Log
➢A formally chartered group responsible for reviewing, evaluating, approving, delaying, or rejecting
changes to the project, and for recording and communicating such decisions.
• The CCB should be Created during the Planning Process Group.
Change Control
Board (CCB)
❖Approved change requests are an output of the Perform Integrated Change Control process, and
include those requests reviewed and approved for implementation by the project manager or by the
change control board (CCB) when applicable.
Approved Change
Requests
16. 16
Question:
Before the baselines of your IT development project are established, the
project sponsor requires a major change in the project. You assessed him on
the impacts that change would have in the project. Which of the following
statements is true about this situation?
A. That change does not have to be formally controlled by the
Perform Integrated Change Control process.
B. Any change in a configuration element should be formally
controlled and will require a change request.
C. Formal integrated change control process is always required.
D. That change must be communicated to all stakeholders previously.
17. 17
Answer : A
Once the project is baselined, change requests go through this process.
As a general rule, each project’s configuration management plan should
define which project artifacts need to be placed under configuration
control. Any change in a configuration element should be formally
controlled and will require a change request.
But this is not the case since the baselines are not yet established.
Before the baselines are established, changes are not required to be
formally controlled by the Perform Integrated Change Control
process. Therefore, the right choice for this question is A. [PMBOK 6th
edition, Page 115] [Project Integration Management]
18. 18
Question :
You have just received a change from customer. Customer has
analysed that it does not impact the schedule and easy to implement.
What should you do first?
A. Request Permission from Project Sponsor
B. Send the Change to Change Control Board for Approval
C. Implement the Change as soon as Possible
D. Ask the Customer to Raise Change Request & then
Evaluate the impact on the project
19. 19
Answer : D
Look at the basic principles and change management process to analyze the question. Basic principles
says it is only project team that should do impact analysis. Customer analysis is not required and not
sufficient. Irrespective of customer has done the analysis or not, project team must do impact analysis. Let’s
analyze the options:
A - Request permission from project sponsor: You need permission from change control board
to implement a change and not from sponsor.
B - Send the change to change control board for approval: If you look at the change
management process, you can send the change request to change control board only after
impact analysis. Customer impact analysis is neither valid not sufficient.
C - Implement the change as soon as possible: If you follow the process, you can implement a
change request only after CCB approval.
D - Ask the Customer to Raise Change Request & then Evaluate the impact on the
project: You should evaluate the impact i.e. do impact analysis. So the answer is D. A question
may arise how we can do impact analysis when a formal change request is not created and not
gone through qualification test yet as per process. The answer is, these two steps are not
available in the options. If either of them was available, I would have chosen it. We have to
choose best out of available options.
So the answer is D.
20. 20
You are a member of Change Control Board (CCB) where you can
approve or reject change requests. A change request has been
rejected by CCB, it means that change request will not be added to
scope of work. In case of rejection of a change request, which of
following document is updated?
A. Issue log
B. Change log
C. Project Management Plan
D. Requirements traceability matrix
Ans: B.
All change requests whether approved or rejected must be recorded in the
change log.
21. 21
Question :
You are developing an application. In the last week, you have made the first
delivery to your customer. Looking at the delivery, your customer has requested
a change in the application and customer ask you to urgently respond on the
change What is the BEST way for you to handle it?
A. Analyze the impact of the change on the project
B. Immediately ask your team to start work on the change and
meanwhile you will do the impact analysis and take the approval from
change control board
C. Create a formal change request
D. Call a team meeting to decide next step
22. 22
Answer : C
A- Analyze the impact of the change on the project: You should analyze the impact of the change on the
project but let us see if there is any option in B, C or D that comes before this step.
B- Immediately ask your team to start work on the change and meanwhile you will do the impact analysis
and take the approval from change control board: Asking your team to immediately start working on the
change will be a total violation of change management process and also dangerous for you as you do not
know the impact. By start working without understanding impact, you probably delay it instead of delivering
it early.
C- Create a Formal Change Request: Yes, you should first create a formal change request. This should
be preferred over A as it comes first in the Integrated Change Control Process.
D- Call a team meeting to decide next step: Calling a team meeting to decide next step shows that you
either do not have a change management process or you do not have inclination to follow it or you are
unaware of it. If you have a change management process, next step is defined there, just follow it, there is
no need to call a meeting.
So the answer is C as it is preferred over A.
23. 23
A. Get the list of changes from the customer and ask your team to work on the changes
immediately
B. Schedule a call with customer and tell the customer that all requirements have been
fulfilled as per the scope of the project and hence changes cannot be made
C. Ask the customer to file a change request
D. Estimate cost and time needed to finish the suggested changes and get it approved by
the customer
You are a project manager working in IT industry, your team is working on a
web application which is in user acceptance phase. You are satisfied the
project is ahead of schedule. Your customer suggests some changes in the
deliverables. The changes requested by the customer are minor and can be
accomplished within the deadline. What you should do next?
Answer : C.
All changes have to go through the Change Control Board (CCB).
24. 24
Question
Your project is half way. It is running on time and within budget. A team
member comes to you and informs that he has added an Extra Features to
the Project Scope that customer would like. The Customer and Team
Member do not want to Raise Change Request since there is no impact on
time and cost. What should be your NEXT step after hearing this
information?
A. Send this information to change control board to take a decision
B. Issue a change request and get it approved as soon as possible
C. Instruct the team member to remove the extra functionality
D. Present it to the customer as a value add
25. 25
Answer : C
A- Send this information to change control board to take a decision: It is not right as this is not
correct change control process. You should send the change request to CCB only when we have
completed impact analysis.
B- Issue a change request and get it approved as soon as possible: Change request is to be issued
before implementation of change and not after its implementation. It is violation of the process.
C- Instruct the team member to remove the extra functionality : You can instruct the team
member to remove it as it is not in the scope. Adding an extra feature which is not in
the scope is called Gold Platting and not required at all.
D- Present it to the customer as a value add: Presenting it as value add is not only violation of
Integrated Change Control Process but also risky as it was implemented without the knowledge of
customer.
So the answer is C. Explain to your team member that he/she is not expected to work on features out of
scope and ask him/her to remove it.