2. A diaphragm wall is a reinforced concrete wall that is
made in situ constructed in the ground using Under
slurry technique which was developed in Italy in 1948.
The slurry forms a thick deposit (the cake) on the
walls of the trench which balances the inward
hydraulic forces and prevents water flow into the
trench.
Walls of thickness between 500 and 1500 mm can be
formed in this way.
3. Commonly used in congested areas.
Can be Installed in close proximity to existing
structure.
Practically suited for deep basements.
Used in conjunction with “Top Down” construction
technique.
4. Very unstable soil profiles below the water table.
Limited construction time
Where deeper than normal cantilever support may be
required.
5. Can be Installed to considerable depth.
Formation of walls with substantial thickness.
Easily incorporated into Permanent works.
Designable to carry vertical loads.
Construction time of Basement can be lowered
considerably.
Minimizes settlement of adjacent buildings
Provides strong and watertight wall
No vibration during installation.
13. Trenching usually carried out under Poly mud slurry.
Poly mud Slurry - Key component.
This Slurry acts as shoring to prevent collapse by
hydraulic pressure and thyrotrophic property.
14. It is a supporting fluid
Poly Mud's molecular structure allows the polymer to
be completely soluble in water.
Readily available for the primary function of active
chemical bonding and stabilization of soil particles.
15. Forms jelly under positive pressure into the sides in
case of granular soils.
The Poly Mud suspension gets deposited on the sides
of the hole resulting in the formation of a filter cake in
contact with soil against which the fluid pressure acts.
In case of impervious clay, the Poly Mud does not
penetrate into the soil, but deposits only a thin film on
the surface of the hole.
23. Placing of concrete having slump 200/250 mm by
tremmie method.
Placed by metal hopper with plug at bottom.
Concrete displaces the slurry.
The concrete level will be measured at regular
intervals.
24.
25. Tremie pipe is made up of segments of 1 m in length. The tremie pipe is lifted up
by crane and goes ups and downs to compact the concrete. And this segments
are removed one by one after doing concreting to a certain depth.
28. Withdrawal of Stop ends just after the Initial setting of
concrete.
If retarders are not added, Stop End Pipes shall be
moved up & down not later than 45 minutes from the
time of placing of concrete.