SlideShare a Scribd company logo
1 of 29
A diaphragm wall is a reinforced concrete wall that is
made in situ constructed in the ground using Under
slurry technique which was developed in Italy in 1948.
 The slurry forms a thick deposit (the cake) on the
walls of the trench which balances the inward
hydraulic forces and prevents water flow into the
trench.
Walls of thickness between 500 and 1500 mm can be
formed in this way.
Commonly used in congested areas.
Can be Installed in close proximity to existing
structure.
Practically suited for deep basements.
Used in conjunction with “Top Down” construction
technique.
Very unstable soil profiles below the water table.
Limited construction time
Where deeper than normal cantilever support may be
required.
Can be Installed to considerable depth.
Formation of walls with substantial thickness.
Easily incorporated into Permanent works.
Designable to carry vertical loads.
Construction time of Basement can be lowered
considerably.
Minimizes settlement of adjacent buildings
Provides strong and watertight wall
No vibration during installation.
High cost
Requires special Equipment
Utility impacts
Step-1: Fixing of Alignment
Step-2: Guide wall Construction
Step-3: Trenching
Step-4: Trench Cleaning
Step-5: Stop ends fixing
Step-6: Reinforcement Cage lowering
Step-7: Placing of Concrete
Step-8: Withdrawal of Stop ends
Guide wall is
Constructed to fix the
alignment of
Diaphragm Wall in the
field
r/f shuttering
curing
r/f
Excavation of panel
Trenching usually carried out under Poly mud slurry.
Poly mud Slurry - Key component.
This Slurry acts as shoring to prevent collapse by
hydraulic pressure and thyrotrophic property.
It is a supporting fluid
Poly Mud's molecular structure allows the polymer to
be completely soluble in water.
Readily available for the primary function of active
chemical bonding and stabilization of soil particles.
Forms jelly under positive pressure into the sides in
case of granular soils.
The Poly Mud suspension gets deposited on the sides
of the hole resulting in the formation of a filter cake in
contact with soil against which the fluid pressure acts.
In case of impervious clay, the Poly Mud does not
penetrate into the soil, but deposits only a thin film on
the surface of the hole.
Parameter Fresh Mix Reused slurry Before Concrete
Pour
Viscosity (seconds) 65-140 65-140 50-140
Density (kg/m3) 1.00-1.04 < 1.08 < 1.04
Sand Content (%) - < 2% < 2%
pH 11-12 11-12 9-12
Joints of adjacent panels to be cleaned to obtain
watertight bond.
Loose materials to be lifted by suitable air lifting
method.
Stop ends to be fixed at the proper position keeping it
truly vertical.
Distance between two Stop ends to be fixed as per
prefixed Panel Layout.
Stop End
Excavation of panel is followed by placing of steel
reinforcement cage in center of the panel.
Face Bar
R/f similar
to column
 Placing of concrete having slump 200/250 mm by
tremmie method.
 Placed by metal hopper with plug at bottom.
 Concrete displaces the slurry.
 The concrete level will be measured at regular
intervals.
Tremie pipe is made up of segments of 1 m in length. The tremie pipe is lifted up
by crane and goes ups and downs to compact the concrete. And this segments
are removed one by one after doing concreting to a certain depth.
Discharging of slurry through pump
Discharging Pipe Pump
After Concreting
 Withdrawal of Stop ends just after the Initial setting of
concrete.
 If retarders are not added, Stop End Pipes shall be
moved up & down not later than 45 minutes from the
time of placing of concrete.
THANK YOU

More Related Content

What's hot

footing
footingfooting
footing
illpa
 
Joints in concrete
Joints in concreteJoints in concrete
Joints in concrete
Aglaia Connect
 

What's hot (20)

Vertical Drain
Vertical Drain Vertical Drain
Vertical Drain
 
Special Concretes
Special Concretes Special Concretes
Special Concretes
 
Grouting
GroutingGrouting
Grouting
 
Pile load test
Pile load testPile load test
Pile load test
 
Pile foundation ppt 2 (usefulsearch.org) (useful search)
Pile foundation ppt 2 (usefulsearch.org) (useful search)Pile foundation ppt 2 (usefulsearch.org) (useful search)
Pile foundation ppt 2 (usefulsearch.org) (useful search)
 
Pile foundations_Advanced Construction Technology
Pile foundations_Advanced Construction TechnologyPile foundations_Advanced Construction Technology
Pile foundations_Advanced Construction Technology
 
DEEP FOUNDATION
DEEP FOUNDATIONDEEP FOUNDATION
DEEP FOUNDATION
 
Reinforced earth structures
Reinforced earth structuresReinforced earth structures
Reinforced earth structures
 
Types of Retaining walls..
Types of Retaining walls..Types of Retaining walls..
Types of Retaining walls..
 
footing
footingfooting
footing
 
Foundation
FoundationFoundation
Foundation
 
Reinforced earth wall and its design parameters
Reinforced earth wall and its design parametersReinforced earth wall and its design parameters
Reinforced earth wall and its design parameters
 
Micropile
MicropileMicropile
Micropile
 
Foundation types
Foundation typesFoundation types
Foundation types
 
Damp proofing
Damp proofingDamp proofing
Damp proofing
 
Well foundation
Well foundationWell foundation
Well foundation
 
Grouting
Grouting Grouting
Grouting
 
Joints in concrete
Joints in concreteJoints in concrete
Joints in concrete
 
Diaphragm wall construction
Diaphragm wall constructionDiaphragm wall construction
Diaphragm wall construction
 
A PowerPoint Presentation On Superstructure
A PowerPoint Presentation On SuperstructureA PowerPoint Presentation On Superstructure
A PowerPoint Presentation On Superstructure
 

Viewers also liked

Top down final
Top down finalTop down final
Top down final
dngu022
 
grouting and guniting
grouting and gunitinggrouting and guniting
grouting and guniting
Vipul Kerni
 

Viewers also liked (20)

Diaphragm Wall Presentation By Gagan
Diaphragm Wall Presentation By GaganDiaphragm Wall Presentation By Gagan
Diaphragm Wall Presentation By Gagan
 
Diaphragm
DiaphragmDiaphragm
Diaphragm
 
Diaphragm Wall
 Diaphragm Wall Diaphragm Wall
Diaphragm Wall
 
Diaphragm
Diaphragm Diaphragm
Diaphragm
 
Diaphragm
DiaphragmDiaphragm
Diaphragm
 
Top down final
Top down finalTop down final
Top down final
 
Lecture 2 thoracic wall & Diaphragm
Lecture 2 thoracic wall & DiaphragmLecture 2 thoracic wall & Diaphragm
Lecture 2 thoracic wall & Diaphragm
 
The diaphragm anatomy & embryology
The diaphragm  anatomy & embryologyThe diaphragm  anatomy & embryology
The diaphragm anatomy & embryology
 
Construction dewatering
Construction dewateringConstruction dewatering
Construction dewatering
 
grouting and guniting
grouting and gunitinggrouting and guniting
grouting and guniting
 
High-rise structural systems
High-rise structural systemsHigh-rise structural systems
High-rise structural systems
 
slurywall
slurywallslurywall
slurywall
 
Lec.9 diaphragm pt&rt
Lec.9 diaphragm pt&rtLec.9 diaphragm pt&rt
Lec.9 diaphragm pt&rt
 
Structural systems in high rise buildings
Structural systems in high rise buildingsStructural systems in high rise buildings
Structural systems in high rise buildings
 
Diaphragm Anatomy
Diaphragm AnatomyDiaphragm Anatomy
Diaphragm Anatomy
 
Marine civil engineering and Gujarat
Marine civil engineering and GujaratMarine civil engineering and Gujarat
Marine civil engineering and Gujarat
 
Deep excavation
Deep excavationDeep excavation
Deep excavation
 
Top down construction
Top down constructionTop down construction
Top down construction
 
Cofferdam
CofferdamCofferdam
Cofferdam
 
Tunnelling methods
Tunnelling methodsTunnelling methods
Tunnelling methods
 

Similar to Diaphragm wall

Diaphragm walls
Diaphragm wallsDiaphragm walls
Diaphragm walls
Nguyen Bao
 
Upload a presentation to download Space frame
Upload a presentation to download Space frameUpload a presentation to download Space frame
Upload a presentation to download Space frame
BurkaDinka
 
Group 2 brick masonry- 0506,1706,3006,5207
Group 2 brick masonry- 0506,1706,3006,5207Group 2 brick masonry- 0506,1706,3006,5207
Group 2 brick masonry- 0506,1706,3006,5207
sharad_kadbhane
 

Similar to Diaphragm wall (20)

Deterioration in building
Deterioration in buildingDeterioration in building
Deterioration in building
 
02 FLOORING 08.06.2022.pptx
02 FLOORING 08.06.2022.pptx02 FLOORING 08.06.2022.pptx
02 FLOORING 08.06.2022.pptx
 
Concrete
ConcreteConcrete
Concrete
 
vacation work report 2
vacation work report 2vacation work report 2
vacation work report 2
 
Soldier Bored and Diaphragm
Soldier Bored and DiaphragmSoldier Bored and Diaphragm
Soldier Bored and Diaphragm
 
Rehabilitation of foundation
Rehabilitation of foundationRehabilitation of foundation
Rehabilitation of foundation
 
Lecture - Dampness.pptx
Lecture - Dampness.pptxLecture - Dampness.pptx
Lecture - Dampness.pptx
 
Diaphragm walls
Diaphragm wallsDiaphragm walls
Diaphragm walls
 
Upload a presentation to download Space frame
Upload a presentation to download Space frameUpload a presentation to download Space frame
Upload a presentation to download Space frame
 
CASE STUDY of remedial measure of civil works
CASE STUDY of remedial measure of civil worksCASE STUDY of remedial measure of civil works
CASE STUDY of remedial measure of civil works
 
CASE STUDY. on Restoration and rehabilitation
CASE STUDY. on Restoration and rehabilitationCASE STUDY. on Restoration and rehabilitation
CASE STUDY. on Restoration and rehabilitation
 
Advanced construction technologies.pptx
Advanced construction technologies.pptxAdvanced construction technologies.pptx
Advanced construction technologies.pptx
 
No finess concrete
No finess concreteNo finess concrete
No finess concrete
 
Rehabilitation and strengthening of existing structures
Rehabilitation and strengthening of existing structuresRehabilitation and strengthening of existing structures
Rehabilitation and strengthening of existing structures
 
presentation on retro fit and repair methods
presentation on retro fit and repair methodspresentation on retro fit and repair methods
presentation on retro fit and repair methods
 
diaphragm and basement construction.pptx
diaphragm and basement construction.pptxdiaphragm and basement construction.pptx
diaphragm and basement construction.pptx
 
Construction Sequence.pptx
Construction Sequence.pptxConstruction Sequence.pptx
Construction Sequence.pptx
 
special concrete and high performance concrete
special concrete and high performance concretespecial concrete and high performance concrete
special concrete and high performance concrete
 
Group 2 brick masonry- 0506,1706,3006,5207
Group 2 brick masonry- 0506,1706,3006,5207Group 2 brick masonry- 0506,1706,3006,5207
Group 2 brick masonry- 0506,1706,3006,5207
 
Water proofing in buildings
Water proofing in buildingsWater proofing in buildings
Water proofing in buildings
 

Recently uploaded

Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
ciinovamais
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
QucHHunhnh
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
heathfieldcps1
 

Recently uploaded (20)

Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
 
PROCESS RECORDING FORMAT.docx
PROCESS      RECORDING        FORMAT.docxPROCESS      RECORDING        FORMAT.docx
PROCESS RECORDING FORMAT.docx
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdf
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
 
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot Graph
 
SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...
SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...
SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17
 
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
 
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
 
This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and Mode
 
ICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptx
 
Unit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptxUnit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptx
 
Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across Sectors
 
Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 

Diaphragm wall

  • 1.
  • 2. A diaphragm wall is a reinforced concrete wall that is made in situ constructed in the ground using Under slurry technique which was developed in Italy in 1948.  The slurry forms a thick deposit (the cake) on the walls of the trench which balances the inward hydraulic forces and prevents water flow into the trench. Walls of thickness between 500 and 1500 mm can be formed in this way.
  • 3. Commonly used in congested areas. Can be Installed in close proximity to existing structure. Practically suited for deep basements. Used in conjunction with “Top Down” construction technique.
  • 4. Very unstable soil profiles below the water table. Limited construction time Where deeper than normal cantilever support may be required.
  • 5. Can be Installed to considerable depth. Formation of walls with substantial thickness. Easily incorporated into Permanent works. Designable to carry vertical loads. Construction time of Basement can be lowered considerably. Minimizes settlement of adjacent buildings Provides strong and watertight wall No vibration during installation.
  • 6. High cost Requires special Equipment Utility impacts
  • 7. Step-1: Fixing of Alignment Step-2: Guide wall Construction Step-3: Trenching Step-4: Trench Cleaning Step-5: Stop ends fixing Step-6: Reinforcement Cage lowering Step-7: Placing of Concrete Step-8: Withdrawal of Stop ends
  • 8. Guide wall is Constructed to fix the alignment of Diaphragm Wall in the field
  • 10.
  • 12.
  • 13. Trenching usually carried out under Poly mud slurry. Poly mud Slurry - Key component. This Slurry acts as shoring to prevent collapse by hydraulic pressure and thyrotrophic property.
  • 14. It is a supporting fluid Poly Mud's molecular structure allows the polymer to be completely soluble in water. Readily available for the primary function of active chemical bonding and stabilization of soil particles.
  • 15. Forms jelly under positive pressure into the sides in case of granular soils. The Poly Mud suspension gets deposited on the sides of the hole resulting in the formation of a filter cake in contact with soil against which the fluid pressure acts. In case of impervious clay, the Poly Mud does not penetrate into the soil, but deposits only a thin film on the surface of the hole.
  • 16. Parameter Fresh Mix Reused slurry Before Concrete Pour Viscosity (seconds) 65-140 65-140 50-140 Density (kg/m3) 1.00-1.04 < 1.08 < 1.04 Sand Content (%) - < 2% < 2% pH 11-12 11-12 9-12
  • 17. Joints of adjacent panels to be cleaned to obtain watertight bond. Loose materials to be lifted by suitable air lifting method.
  • 18. Stop ends to be fixed at the proper position keeping it truly vertical. Distance between two Stop ends to be fixed as per prefixed Panel Layout.
  • 20. Excavation of panel is followed by placing of steel reinforcement cage in center of the panel.
  • 22.
  • 23.  Placing of concrete having slump 200/250 mm by tremmie method.  Placed by metal hopper with plug at bottom.  Concrete displaces the slurry.  The concrete level will be measured at regular intervals.
  • 24.
  • 25. Tremie pipe is made up of segments of 1 m in length. The tremie pipe is lifted up by crane and goes ups and downs to compact the concrete. And this segments are removed one by one after doing concreting to a certain depth.
  • 26. Discharging of slurry through pump Discharging Pipe Pump
  • 28.  Withdrawal of Stop ends just after the Initial setting of concrete.  If retarders are not added, Stop End Pipes shall be moved up & down not later than 45 minutes from the time of placing of concrete.