SlideShare a Scribd company logo
1 of 41
2. RECOMMONDATIONS
Treatment to avoid seepage in the basement
by providing seepage water sump.
 Treatment to avoid seepage in the basement by providing seepage water sump.
The seepage water sump generally provided to decrease the seepage pressure. Seepage pressure
is the main cause of bouncy effect or uplift of subbase/grade slab. Following are the procedure
to provide the seepage water sump. Seepage water sump may of rectangular or circular in shape.
Procedure for round type of sump.
• Excavate the square trench of size 2.5×2.5×2.5m in identified location (specifically the location
at higher pore pressure).
• Spread the 25mm aggregate at the bottom with a depth of 300mm and pour the sand over it and
level the surface.
• Pour the lean mix of 1:4:8 concrete with a thick ness of 100mm over the levelled surface.
• Place the precast ring of size 2m diameter and height of 150mm and thickness of 75mm to
100mm with weep holes.
• Place the ring one above the other as shown in fig.
• Fill the coarse sands and 20 mm aggregate with 1:2 ratio around the ring
• Provide proper chamber cover (precast slab) over the sump
• Provide sensor controlled submersible pump in the sump to pump-out the seepage water after
stored to specified depth.
2.1Treatment for cracked and uplifted floor in
the location.
View of cracked and uplifted floor in the location.
2.2 Treatment for Leakage/dampness/damp
patches/peeling of paint in RC members.
View of Leakage/dampness/damp patches/peeling of paint in RC members
 Treatment for Leakage/dampness/damp patches/peeling of paint in RC members.
• Existing concrete surface to be cleaned thoroughly to remove dust particles by air & water jet.
• 12 mm dia 75mm deep holes shall be drilled at 1000mm c/c spacing as in the damped areas to
fix grouting nozzles.
• 10 mm dia PVC/TEFLON nozzles/packers shall be fixed into the drilled holes using anchor
grout as per specification.
• Pressure grouting with low viscosity, elastic, solvent free, polyurethane resin grouting shall be
carried out until refusal is reached under a pressure not less than 3- 4kg/cm2.
• The grouting shall be carried out from bottom to top and alternate holes shall be grouted at a
time.
• Projected nozzles shall be cut in flush with the adjacent concrete surface.
2.3 Treatment for Crack in RC Member
View of crack in RC members
 Treatment for crack in RC members. (RC Slab and Retaining wall)
• Existing concrete surface to be cleaned thoroughly to remove dust particles by air & water jet.
• ‘U’ Grove shall be made along the crack and cleaned with air and water jet.
• 12 mm dia 50mm deep holes shall be drilled at 250mm c/c spacing as indicated in sketch to
fix grouting nozzles.
• 10 mm dia PVC/TEFLON nozzles/packers shall be fixed into the drilled holes using anchor
grout as per specification.
• Cleaned ‘U’ grooves along cracks shall be sealed with epoxy putty/mortar.
• Pressure grouting with low viscosity epoxy/monomer shall be carried out until refusal is
reached under a pressure not less than 3- 4kg/cm2.
2.4 View of separation cracks between
masonry walls and RC members
View of separation cracks between masonry walls and RC members
 Treatment for separation cracks between masonry walls and RC members.
• Plaster in this region about 20mm on either side of the crack to be removed and
loose particles shall be cleaned using wire brush.
• ‘U’ groove of 12 mm wide 6 mm deep shall be made all along the crack at the
interface of masonry wall and RC member junction and cleaned.
• The Groove shall be filled with flexible sealant like Tacksel / Polysulphate sealant
/ silicon sealant or any other equivalent.
2.5 Treatment for Cracks in Masonry walls.
View of cracks in Masonry walls.
 Treatment for cracks in Masonry walls.
• Existing plaster along the crack shall be removed on either side of the crack for a
width of about 300 mm (on either side of the wall) and cleaned.
• Mortar joints along the crack shall be deep raked and filled with cement mortar.
• Weld mesh of size 50 x 50 x 3 mm shall be fabricated and fixed across the crack
using ‘U’ nails.
• Re-plastering the region with CM 1:4 as per standard practice.
2.6 Treatment for Dampness/deteriorated
plaster in masonry walls.
View of dampness/deteriorated plaster in masonry walls
 Treatment for dampness/deteriorated plaster in masonry walls
• The deteriorated /debonded plaster on masonry walls & RC Members shall be
totally removed by gentle chipping.
• The mortar joints in walls shall be deep raked and repointed with C M 1:3 as per
standard practice followed by replastering in CM 1:4 mixed with water proofing
plasticizer.
2.7 Treatment for WPC by Polyurethane
coating
View of damaged WPC by Polyurethane coating
Treatment for WPC by Polyurethane coating.
• The existing roof slab shall be cleaned using wire brush followed by air and water jet.
• Existing cracks in WPC shall be filled with crack sealant after making “U” groove all around
the crack.
• Existing cavity/voids in WPC should be filled with polymer modified mortar and finished in
flush with the adjacent surface.
• Polyurethane based liquid waterproofing coating shall be provided over the cleaned surface as
per manufacturer’s specifications enduring adequate slope for effective disposal of rainwater
and cured.
Provision of Saucer drain along the length of
retaining wall
Provision of Saucer drain along the length of retaining wall
• This drain system is effective in drain the seep water from retaining wall. This type of drains
are preferred where the seepage is uncontrolled by the grouting treatment. The pressure has to
be released by allowing the seepage flow.
• The saucer drain is provided in some location in the lower basement but provision is not made
to connect to drainage chamber. Refer the drawing and detail of saucer drain and connect it to
nearby chamber.
Treatment for expansion joint in the (fresh
and hardened concrete) flooring.
 Treatment for expansion joint in the (fresh and hardened concrete) flooring.
The cracks will be developed due to thermal stresses induced in the flooring due to the non-
provision of expansion joint. The floor concrete to be done panel by panel with distinct
separation generally called as expansion joint by using elastic material. Following are the
procedure to be followed.
 Case. I. Providing of Expansion joint prior to the concrete pour.
• Mark the rectangular panel size of 2mX3m.
• Prepare the shuttering arrangement by using ISMC or runners.
• Place the rubber/neoprene /bitumen/mastic pad of 5to10 mm thickness and depth equal to depth
of concrete to be poured over the panel marking.
• Pour the concrete in the panel and compact it by using vibrators.
• Provide the proper slope on surface using float.
• Cut excess projection of pad above the surface.
 Case.II. Providing expansion joint in hardened concrete.
• Mark the panel over the hardened floor and Cut the groove of 5 to 10 mm width and depth of
half to one inch (25mm) by groove cut machine.
• Remove the particle and dust in the groove by scoops and blowers.
• Insert the baker /neoprene rod of 5 to 10 mm in the groove and press it till 05mm gap available
above it.
• Provide Polysulphate /polyurethane sealant (Nitoseal PU 40 /sika 106711 self levelling sealant
or equivalent) in the gap over the baker/neoprene rod and wipe it by straight edge.
• Allow some time for sealant to set after it laid (refer manufacturer’s instructions).
Case. I. Providing of Expansion joint prior to the concrete pour.
Case. I. Providing of Expansion joint in the hardened concrete.

More Related Content

Similar to CASE STUDY. on Restoration and rehabilitation

GOOD CONSTRUCTION PRACTICE.pptx
GOOD CONSTRUCTION PRACTICE.pptxGOOD CONSTRUCTION PRACTICE.pptx
GOOD CONSTRUCTION PRACTICE.pptxHirenThakkar31
 
REPAIR REHABILITATION & RETROFITTING OF STRUCTURES.pptx
REPAIR REHABILITATION  & RETROFITTING OF STRUCTURES.pptxREPAIR REHABILITATION  & RETROFITTING OF STRUCTURES.pptx
REPAIR REHABILITATION & RETROFITTING OF STRUCTURES.pptxBasineniUdaykumar
 
SPECIFICATIONS FOR ADDL HOUSING PROJECT.pptx
SPECIFICATIONS FOR ADDL HOUSING PROJECT.pptxSPECIFICATIONS FOR ADDL HOUSING PROJECT.pptx
SPECIFICATIONS FOR ADDL HOUSING PROJECT.pptxswethasekhar5
 
Soldier Bored and Diaphragm
Soldier Bored and DiaphragmSoldier Bored and Diaphragm
Soldier Bored and DiaphragmYingHongKang
 
Diaphragm walls
Diaphragm wallsDiaphragm walls
Diaphragm wallsNguyen Bao
 
Construction and testing of sewer line
Construction and testing of sewer lineConstruction and testing of sewer line
Construction and testing of sewer lineRAMPRASAD KUMAWAT
 
Special Concreting Techniques
Special Concreting Techniques Special Concreting Techniques
Special Concreting Techniques GAURAV. H .TANDON
 
494042554-White-Topping-Ppt.pptx
494042554-White-Topping-Ppt.pptx494042554-White-Topping-Ppt.pptx
494042554-White-Topping-Ppt.pptxPitambaramsrinivas
 
Building crack,types,causes & its repairing
Building crack,types,causes & its repairingBuilding crack,types,causes & its repairing
Building crack,types,causes & its repairingGAUTAMSWALA
 
Repair techniques : Grouting (RR&S)
Repair techniques : Grouting (RR&S)Repair techniques : Grouting (RR&S)
Repair techniques : Grouting (RR&S)RAMPRASAD KUMAWAT
 
Advanced construction technologies.pptx
Advanced construction technologies.pptxAdvanced construction technologies.pptx
Advanced construction technologies.pptxKalanaWijesinghe
 
MAINTENANCE OF CIVIL ENGINEERING STRCTURES.pptx
MAINTENANCE OF CIVIL ENGINEERING STRCTURES.pptxMAINTENANCE OF CIVIL ENGINEERING STRCTURES.pptx
MAINTENANCE OF CIVIL ENGINEERING STRCTURES.pptxNamanGhevariya
 
WATER LEAKEGE REMEDIES AND PRECAUTIONS IN RCC STRUCTURE
WATER LEAKEGE REMEDIES AND PRECAUTIONS IN RCC STRUCTUREWATER LEAKEGE REMEDIES AND PRECAUTIONS IN RCC STRUCTURE
WATER LEAKEGE REMEDIES AND PRECAUTIONS IN RCC STRUCTUREchintandomadiya
 
Sample copy of IT PPT.pptx
Sample copy of IT PPT.pptxSample copy of IT PPT.pptx
Sample copy of IT PPT.pptxHimanshumangal12
 
Grouting, guniting, jacketing
Grouting, guniting, jacketingGrouting, guniting, jacketing
Grouting, guniting, jacketingAditya Sanyal
 

Similar to CASE STUDY. on Restoration and rehabilitation (20)

sample.pptx
sample.pptxsample.pptx
sample.pptx
 
GOOD CONSTRUCTION PRACTICE.pptx
GOOD CONSTRUCTION PRACTICE.pptxGOOD CONSTRUCTION PRACTICE.pptx
GOOD CONSTRUCTION PRACTICE.pptx
 
REPAIR REHABILITATION & RETROFITTING OF STRUCTURES.pptx
REPAIR REHABILITATION  & RETROFITTING OF STRUCTURES.pptxREPAIR REHABILITATION  & RETROFITTING OF STRUCTURES.pptx
REPAIR REHABILITATION & RETROFITTING OF STRUCTURES.pptx
 
training1 (1).pptx
training1 (1).pptxtraining1 (1).pptx
training1 (1).pptx
 
SPECIFICATIONS FOR ADDL HOUSING PROJECT.pptx
SPECIFICATIONS FOR ADDL HOUSING PROJECT.pptxSPECIFICATIONS FOR ADDL HOUSING PROJECT.pptx
SPECIFICATIONS FOR ADDL HOUSING PROJECT.pptx
 
Soldier Bored and Diaphragm
Soldier Bored and DiaphragmSoldier Bored and Diaphragm
Soldier Bored and Diaphragm
 
Diaphragm walls
Diaphragm wallsDiaphragm walls
Diaphragm walls
 
Construction and testing of sewer line
Construction and testing of sewer lineConstruction and testing of sewer line
Construction and testing of sewer line
 
Soil Nailing
Soil NailingSoil Nailing
Soil Nailing
 
Special Concreting Techniques
Special Concreting Techniques Special Concreting Techniques
Special Concreting Techniques
 
494042554-White-Topping-Ppt.pptx
494042554-White-Topping-Ppt.pptx494042554-White-Topping-Ppt.pptx
494042554-White-Topping-Ppt.pptx
 
Building crack,types,causes & its repairing
Building crack,types,causes & its repairingBuilding crack,types,causes & its repairing
Building crack,types,causes & its repairing
 
Form Work
Form Work Form Work
Form Work
 
Repair techniques : Grouting (RR&S)
Repair techniques : Grouting (RR&S)Repair techniques : Grouting (RR&S)
Repair techniques : Grouting (RR&S)
 
Pavements PPT
 Pavements PPT  Pavements PPT
Pavements PPT
 
Advanced construction technologies.pptx
Advanced construction technologies.pptxAdvanced construction technologies.pptx
Advanced construction technologies.pptx
 
MAINTENANCE OF CIVIL ENGINEERING STRCTURES.pptx
MAINTENANCE OF CIVIL ENGINEERING STRCTURES.pptxMAINTENANCE OF CIVIL ENGINEERING STRCTURES.pptx
MAINTENANCE OF CIVIL ENGINEERING STRCTURES.pptx
 
WATER LEAKEGE REMEDIES AND PRECAUTIONS IN RCC STRUCTURE
WATER LEAKEGE REMEDIES AND PRECAUTIONS IN RCC STRUCTUREWATER LEAKEGE REMEDIES AND PRECAUTIONS IN RCC STRUCTURE
WATER LEAKEGE REMEDIES AND PRECAUTIONS IN RCC STRUCTURE
 
Sample copy of IT PPT.pptx
Sample copy of IT PPT.pptxSample copy of IT PPT.pptx
Sample copy of IT PPT.pptx
 
Grouting, guniting, jacketing
Grouting, guniting, jacketingGrouting, guniting, jacketing
Grouting, guniting, jacketing
 

More from KumarS250747

Road construction pavements flexible rigid
Road construction pavements flexible rigidRoad construction pavements flexible rigid
Road construction pavements flexible rigidKumarS250747
 
CASE STUDY of remedial measure of civil works
CASE STUDY of remedial measure of civil worksCASE STUDY of remedial measure of civil works
CASE STUDY of remedial measure of civil worksKumarS250747
 
presentation on retro fit and repair methods
presentation on retro fit and repair methodspresentation on retro fit and repair methods
presentation on retro fit and repair methodsKumarS250747
 
Introduction to Geotechnical engineering
Introduction to Geotechnical engineeringIntroduction to Geotechnical engineering
Introduction to Geotechnical engineeringKumarS250747
 
retrofitting and rehabilitation of structures
retrofitting and rehabilitation of structuresretrofitting and rehabilitation of structures
retrofitting and rehabilitation of structuresKumarS250747
 
Retrofitting rehabilitation and repair of structure
Retrofitting rehabilitation and repair of structureRetrofitting rehabilitation and repair of structure
Retrofitting rehabilitation and repair of structureKumarS250747
 
Civil construction and environmental engineering
Civil construction and environmental engineeringCivil construction and environmental engineering
Civil construction and environmental engineeringKumarS250747
 
Ground improvement technic and repair procedures.pdf
Ground improvement technic and repair procedures.pdfGround improvement technic and repair procedures.pdf
Ground improvement technic and repair procedures.pdfKumarS250747
 
Seismic Retrofitting and repairs and rehabilitations
Seismic Retrofitting and repairs and rehabilitationsSeismic Retrofitting and repairs and rehabilitations
Seismic Retrofitting and repairs and rehabilitationsKumarS250747
 

More from KumarS250747 (9)

Road construction pavements flexible rigid
Road construction pavements flexible rigidRoad construction pavements flexible rigid
Road construction pavements flexible rigid
 
CASE STUDY of remedial measure of civil works
CASE STUDY of remedial measure of civil worksCASE STUDY of remedial measure of civil works
CASE STUDY of remedial measure of civil works
 
presentation on retro fit and repair methods
presentation on retro fit and repair methodspresentation on retro fit and repair methods
presentation on retro fit and repair methods
 
Introduction to Geotechnical engineering
Introduction to Geotechnical engineeringIntroduction to Geotechnical engineering
Introduction to Geotechnical engineering
 
retrofitting and rehabilitation of structures
retrofitting and rehabilitation of structuresretrofitting and rehabilitation of structures
retrofitting and rehabilitation of structures
 
Retrofitting rehabilitation and repair of structure
Retrofitting rehabilitation and repair of structureRetrofitting rehabilitation and repair of structure
Retrofitting rehabilitation and repair of structure
 
Civil construction and environmental engineering
Civil construction and environmental engineeringCivil construction and environmental engineering
Civil construction and environmental engineering
 
Ground improvement technic and repair procedures.pdf
Ground improvement technic and repair procedures.pdfGround improvement technic and repair procedures.pdf
Ground improvement technic and repair procedures.pdf
 
Seismic Retrofitting and repairs and rehabilitations
Seismic Retrofitting and repairs and rehabilitationsSeismic Retrofitting and repairs and rehabilitations
Seismic Retrofitting and repairs and rehabilitations
 

Recently uploaded

Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvLewisJB
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 
pipeline in computer architecture design
pipeline in computer architecture  designpipeline in computer architecture  design
pipeline in computer architecture designssuser87fa0c1
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHC Sai Kiran
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptSAURABHKUMAR892774
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEroselinkalist12
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
Effects of rheological properties on mixing
Effects of rheological properties on mixingEffects of rheological properties on mixing
Effects of rheological properties on mixingviprabot1
 

Recently uploaded (20)

Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvv
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 
pipeline in computer architecture design
pipeline in computer architecture  designpipeline in computer architecture  design
pipeline in computer architecture design
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECH
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.ppt
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
Effects of rheological properties on mixing
Effects of rheological properties on mixingEffects of rheological properties on mixing
Effects of rheological properties on mixing
 

CASE STUDY. on Restoration and rehabilitation

  • 2. Treatment to avoid seepage in the basement by providing seepage water sump.
  • 3.
  • 4.
  • 5.  Treatment to avoid seepage in the basement by providing seepage water sump. The seepage water sump generally provided to decrease the seepage pressure. Seepage pressure is the main cause of bouncy effect or uplift of subbase/grade slab. Following are the procedure to provide the seepage water sump. Seepage water sump may of rectangular or circular in shape. Procedure for round type of sump. • Excavate the square trench of size 2.5×2.5×2.5m in identified location (specifically the location at higher pore pressure). • Spread the 25mm aggregate at the bottom with a depth of 300mm and pour the sand over it and level the surface.
  • 6. • Pour the lean mix of 1:4:8 concrete with a thick ness of 100mm over the levelled surface. • Place the precast ring of size 2m diameter and height of 150mm and thickness of 75mm to 100mm with weep holes. • Place the ring one above the other as shown in fig. • Fill the coarse sands and 20 mm aggregate with 1:2 ratio around the ring • Provide proper chamber cover (precast slab) over the sump • Provide sensor controlled submersible pump in the sump to pump-out the seepage water after stored to specified depth.
  • 7. 2.1Treatment for cracked and uplifted floor in the location.
  • 8. View of cracked and uplifted floor in the location.
  • 9.
  • 10. 2.2 Treatment for Leakage/dampness/damp patches/peeling of paint in RC members.
  • 11. View of Leakage/dampness/damp patches/peeling of paint in RC members
  • 12.
  • 13.  Treatment for Leakage/dampness/damp patches/peeling of paint in RC members. • Existing concrete surface to be cleaned thoroughly to remove dust particles by air & water jet. • 12 mm dia 75mm deep holes shall be drilled at 1000mm c/c spacing as in the damped areas to fix grouting nozzles. • 10 mm dia PVC/TEFLON nozzles/packers shall be fixed into the drilled holes using anchor grout as per specification. • Pressure grouting with low viscosity, elastic, solvent free, polyurethane resin grouting shall be carried out until refusal is reached under a pressure not less than 3- 4kg/cm2. • The grouting shall be carried out from bottom to top and alternate holes shall be grouted at a time. • Projected nozzles shall be cut in flush with the adjacent concrete surface.
  • 14. 2.3 Treatment for Crack in RC Member
  • 15. View of crack in RC members
  • 16.  Treatment for crack in RC members. (RC Slab and Retaining wall) • Existing concrete surface to be cleaned thoroughly to remove dust particles by air & water jet. • ‘U’ Grove shall be made along the crack and cleaned with air and water jet. • 12 mm dia 50mm deep holes shall be drilled at 250mm c/c spacing as indicated in sketch to fix grouting nozzles. • 10 mm dia PVC/TEFLON nozzles/packers shall be fixed into the drilled holes using anchor grout as per specification. • Cleaned ‘U’ grooves along cracks shall be sealed with epoxy putty/mortar. • Pressure grouting with low viscosity epoxy/monomer shall be carried out until refusal is reached under a pressure not less than 3- 4kg/cm2.
  • 17.
  • 18. 2.4 View of separation cracks between masonry walls and RC members
  • 19. View of separation cracks between masonry walls and RC members
  • 20.  Treatment for separation cracks between masonry walls and RC members. • Plaster in this region about 20mm on either side of the crack to be removed and loose particles shall be cleaned using wire brush. • ‘U’ groove of 12 mm wide 6 mm deep shall be made all along the crack at the interface of masonry wall and RC member junction and cleaned. • The Groove shall be filled with flexible sealant like Tacksel / Polysulphate sealant / silicon sealant or any other equivalent.
  • 21.
  • 22. 2.5 Treatment for Cracks in Masonry walls.
  • 23. View of cracks in Masonry walls.
  • 24.  Treatment for cracks in Masonry walls. • Existing plaster along the crack shall be removed on either side of the crack for a width of about 300 mm (on either side of the wall) and cleaned. • Mortar joints along the crack shall be deep raked and filled with cement mortar. • Weld mesh of size 50 x 50 x 3 mm shall be fabricated and fixed across the crack using ‘U’ nails. • Re-plastering the region with CM 1:4 as per standard practice.
  • 25.
  • 26. 2.6 Treatment for Dampness/deteriorated plaster in masonry walls.
  • 27. View of dampness/deteriorated plaster in masonry walls
  • 28.  Treatment for dampness/deteriorated plaster in masonry walls • The deteriorated /debonded plaster on masonry walls & RC Members shall be totally removed by gentle chipping. • The mortar joints in walls shall be deep raked and repointed with C M 1:3 as per standard practice followed by replastering in CM 1:4 mixed with water proofing plasticizer.
  • 29.
  • 30. 2.7 Treatment for WPC by Polyurethane coating
  • 31. View of damaged WPC by Polyurethane coating
  • 32. Treatment for WPC by Polyurethane coating. • The existing roof slab shall be cleaned using wire brush followed by air and water jet. • Existing cracks in WPC shall be filled with crack sealant after making “U” groove all around the crack. • Existing cavity/voids in WPC should be filled with polymer modified mortar and finished in flush with the adjacent surface. • Polyurethane based liquid waterproofing coating shall be provided over the cleaned surface as per manufacturer’s specifications enduring adequate slope for effective disposal of rainwater and cured.
  • 33.
  • 34. Provision of Saucer drain along the length of retaining wall
  • 35.
  • 36. Provision of Saucer drain along the length of retaining wall • This drain system is effective in drain the seep water from retaining wall. This type of drains are preferred where the seepage is uncontrolled by the grouting treatment. The pressure has to be released by allowing the seepage flow. • The saucer drain is provided in some location in the lower basement but provision is not made to connect to drainage chamber. Refer the drawing and detail of saucer drain and connect it to nearby chamber.
  • 37. Treatment for expansion joint in the (fresh and hardened concrete) flooring.
  • 38.  Treatment for expansion joint in the (fresh and hardened concrete) flooring. The cracks will be developed due to thermal stresses induced in the flooring due to the non- provision of expansion joint. The floor concrete to be done panel by panel with distinct separation generally called as expansion joint by using elastic material. Following are the procedure to be followed.  Case. I. Providing of Expansion joint prior to the concrete pour. • Mark the rectangular panel size of 2mX3m. • Prepare the shuttering arrangement by using ISMC or runners. • Place the rubber/neoprene /bitumen/mastic pad of 5to10 mm thickness and depth equal to depth of concrete to be poured over the panel marking. • Pour the concrete in the panel and compact it by using vibrators.
  • 39. • Provide the proper slope on surface using float. • Cut excess projection of pad above the surface.  Case.II. Providing expansion joint in hardened concrete. • Mark the panel over the hardened floor and Cut the groove of 5 to 10 mm width and depth of half to one inch (25mm) by groove cut machine. • Remove the particle and dust in the groove by scoops and blowers. • Insert the baker /neoprene rod of 5 to 10 mm in the groove and press it till 05mm gap available above it. • Provide Polysulphate /polyurethane sealant (Nitoseal PU 40 /sika 106711 self levelling sealant or equivalent) in the gap over the baker/neoprene rod and wipe it by straight edge. • Allow some time for sealant to set after it laid (refer manufacturer’s instructions).
  • 40. Case. I. Providing of Expansion joint prior to the concrete pour.
  • 41. Case. I. Providing of Expansion joint in the hardened concrete.