SlideShare a Scribd company logo
1 of 30
Presented by
 Foundations are sub-structure that transmits the load of the building
along with its own weight into the soil.
 The main purpose of the foundation is to increase the stability of the
structure by distributing the structural load over a large bearing area
without causing bearing capacity failure and excessive settlement.
(1) BEARING CAPACITY FAILURE:
1. By error in estimation of Shear Strength parameters
2. By error in estimation of Type of Shear failure in SBC determination
(2) SETTLEMENT:
 Settlement of foundation is when the
weight of the structure is greater than
the bearing capacity of the soil.
(3) SHRINKAGE CRACK:
The basic reason for the development of
shrinkage cracks in concrete slab-on-
grade foundations is due to ground water
depletion.
Found on clay soil and cracks are
developed in foundation wall and floor slab.
(4) MOISTURE INSTRUSION:
Moisture penetrates the foundation
at the location of the shrinkage cracks.
It also penetrates the slab in the form of
water vapor and cause damage to floor
coverings and settles.
 Foundation is an integral structural part of a home and affects the
building from the basement to the roof if it is weekend or fail.
 If the foundation fails and no foundation repair is made, the rest of the
home will ultimately crumble.
 Rehabilitation is a process that strengthens foundations which have
been weakened by above discussed factors.
1. Concrete jacketing
2. Micropile technique
3. Push pier system
4. Jack up technique
 Commonly used method for widening and strengthening of existing
foundations.
 Carried out by constructing a “concrete jacket” to existing
foundation.
 With this method, axial strength, bending strength and stiffness of the
damaged column gets increased.
 The size of the jacket shall be selected such that the average
maximum foundation pressure does not exceed the recommended
allowable value.
 The new jacket should be properly anchored to the existing footing in
order to withstand transfer of loads.
STEP 1: Excavation around the
footing.
STEP 2: Cleaning and roughening the
concrete surface.
 STEP 3: Installing dowels at 25-30cm
spacing in both directions using an
appropriate epoxy material.
STEP 4: Fastening the new steel bars.
STEP 5: Pouring the new concrete.
INSTALLING DOWELS AND STEEL
RODS
JACKETING
 Micropiles are small-diameter (typically 2” to 8” diameter) piles that can be
drilled, sealed and injected with cement grout and incorporating steel
reinforcement elements that withstand a higher proportion of all the design
loads compared with conventional piles.
 Can be vertical or inclined.
 Can be installed in confined space and through any type of subsurface
condition from sand to clay.
 The load is mostly supported by the steel and transferred via the cement
grout to the surrounding ground through high lateral resistance.
1. Drilling and casing
2. Reinforcement placement
3. Injection (grouting)
4. Connecting to the superstructure.
PROBLEM:
The expansion of Michigan State University’s Spartan Stadium includes
construction of new sky boxes, press boxes, elevators and access ramps.
However, some of the new load from these improvements will be transferred to
existing columns and footings. MSU’s consultants determined that the existing
footings were too small to carry the additional load and that foundation
modifications would be necessary.
SOLUTION:
Micropiles were chosen to structurally support the existing footings and
to transfer the new loads to bedrock.
Push piers are hydraulically driven pier systems consisting of sections of
galvanized or epoxy-coated steel pipe.
These systems utilize high-strength round steel tube sections and a load
transfer bracket to stabilize and to lift sinking or settling foundations.
Push piers has its ability to penetrate various layers and strengths the soil
to achieve great depths. An important feature that makes this possible is called
a “friction reducing collar” which is simply a ring that is welded to the pier
segment.
The friction reducing collar slightly enlarged end creates a small annular
space around the pier shaft that can dramatically reduce skin friction as the
pier is advanced through the soil.
STEP 1: Footing is exposed for the bracket.
STEP 2: The bracket, driving equipment
and tubes are assembled at pier
location.
STEP 3: Steel tube sections are hydraulically
driven into soil.
STEP 4: Weight of the home is transferred to
the piers.
STEP 5: Lifting the structure back to its
original position is attempted.
STEP 6: Soil is backfilled and work area is
cleaned up.
PROBLEM:
The liberty middle school in Clifton is a single storey structure with exterior concrete block walls
and brick veneer. A bump-out area of the building approximately 100 feet long and 14-feet wide had
settled and rotated away from the main footprint of the structure. An interior block partition wall
intersected the long exterior wall at its mid-length. The settlement and rotation of the exterior wall
caused the two walls to separate with the crack wider at the top than the bottom. The movement
also raised concern that connections and adequate bearing of the roof joists to the top of the
exterior block wall had been compromised. A subsurface investigation encountered lean to fat clay
underlain by competent limestone.
SOLUTION:
A system of hydraulically-driven push piers was selected as the most economical
method to stabilize and potentially lift the settled area of the building. A total of 17 push piers were
installed at a 7 feet maximum center-to-center spacing. 15 piers were installed along the 100 feet
section of wall and 2 piers were installed at each of the 14 foot returns. A 50 kip drive load was
specified per pier with a minimum factor of safety of 1.5 after the lift. Excavation to site clean-up
was completed in just four days.
 Mud jacking is used when a foundation is so weak that piers or pilings
cannot be installed and where concrete slabs are lifted or moved using a
complex hydraulic system.
 Small holes are drilled and polyurethane resins are injected. When the
resins mix underneath a foundation, they form a gas bubbles and expands
which results in lifting of buildings.
 After lifting, the small hole are patched with concrete.
 It is a convenient and inexpensive way to lift pool decks, slabs, driveways
and other items made of concrete that is 3 to 6 inches thick.
 Mud jacking is cheaper and can often be completed in a day or two days.
PROBLEM:
In the 4 years since construction, the CNIM factory, Canjiang Industrial Park,
China , the floors had subsided up to 365mm, making some areas unproductive in last
12 months.
SOLUTION:
Soil stabilisation and compaction was carried out using the deep injection
technology of expanding resins at extremely high pressures at the weak locations and
levels as detected by the penetrometer testing. Floor slabs were lifted and voids beneath
the slabs filled by foam injected directly below the slab.
Rehabilitation of foundation
Rehabilitation of foundation
Rehabilitation of foundation

More Related Content

What's hot

types of cracks in building
types of cracks in buildingtypes of cracks in building
types of cracks in buildingMuhammad Sultan
 
Retrofitting case study of RCC structure
Retrofitting case study of RCC structureRetrofitting case study of RCC structure
Retrofitting case study of RCC structureManish Sharma
 
Prestressed Concrete
Prestressed ConcretePrestressed Concrete
Prestressed ConcreteRavi Savani
 
Chapter 4 repair, rehabilitation & retrofiiting
Chapter 4 repair, rehabilitation & retrofiitingChapter 4 repair, rehabilitation & retrofiiting
Chapter 4 repair, rehabilitation & retrofiitingAnkit Patel
 
Chapter 1 PILE FOUNDATIONS
Chapter 1 PILE FOUNDATIONSChapter 1 PILE FOUNDATIONS
Chapter 1 PILE FOUNDATIONSKHUSHBU SHAH
 
Earthquake resistance in buildings
Earthquake resistance in buildingsEarthquake resistance in buildings
Earthquake resistance in buildingsRithika Ravishankar
 
Deterioration of concrete
Deterioration of concreteDeterioration of concrete
Deterioration of concreteHarikrishna M.S
 
Causes and prevention of cracks in buildings
Causes and prevention of cracks in buildingsCauses and prevention of cracks in buildings
Causes and prevention of cracks in buildingsSUPREETH Suppi
 
Techniques for various structural repair
Techniques for various  structural repairTechniques for various  structural repair
Techniques for various structural repairUdayram Patil
 
Rehabilitation and strengthening of existing structures
Rehabilitation and strengthening of existing structuresRehabilitation and strengthening of existing structures
Rehabilitation and strengthening of existing structuresShahrukh Niaz
 
Grouting, guniting, jacketing
Grouting, guniting, jacketingGrouting, guniting, jacketing
Grouting, guniting, jacketingAditya Sanyal
 
Seismic Analysis
Seismic AnalysisSeismic Analysis
Seismic AnalysisKrishnagnr
 
Repair to overcome low member strength
Repair to overcome low member strength Repair to overcome low member strength
Repair to overcome low member strength RAMPRASAD KUMAWAT
 
Raft foundations
Raft foundationsRaft foundations
Raft foundationshatim ahmed
 
Retrofitting of concrete structure
Retrofitting of concrete structureRetrofitting of concrete structure
Retrofitting of concrete structureshlok patel
 
Chapter 3 shallow foundations
Chapter 3 shallow foundationsChapter 3 shallow foundations
Chapter 3 shallow foundationsKHUSHBU SHAH
 

What's hot (20)

types of cracks in building
types of cracks in buildingtypes of cracks in building
types of cracks in building
 
Retrofitting case study of RCC structure
Retrofitting case study of RCC structureRetrofitting case study of RCC structure
Retrofitting case study of RCC structure
 
Underpinning
UnderpinningUnderpinning
Underpinning
 
Prestressed Concrete
Prestressed ConcretePrestressed Concrete
Prestressed Concrete
 
Concrete repair
Concrete repairConcrete repair
Concrete repair
 
Chapter 4 repair, rehabilitation & retrofiiting
Chapter 4 repair, rehabilitation & retrofiitingChapter 4 repair, rehabilitation & retrofiiting
Chapter 4 repair, rehabilitation & retrofiiting
 
Chapter 1 PILE FOUNDATIONS
Chapter 1 PILE FOUNDATIONSChapter 1 PILE FOUNDATIONS
Chapter 1 PILE FOUNDATIONS
 
Earthquake resistance in buildings
Earthquake resistance in buildingsEarthquake resistance in buildings
Earthquake resistance in buildings
 
Post Tension
Post TensionPost Tension
Post Tension
 
Deterioration of concrete
Deterioration of concreteDeterioration of concrete
Deterioration of concrete
 
Causes and prevention of cracks in buildings
Causes and prevention of cracks in buildingsCauses and prevention of cracks in buildings
Causes and prevention of cracks in buildings
 
Techniques for various structural repair
Techniques for various  structural repairTechniques for various  structural repair
Techniques for various structural repair
 
Rehabilitation and strengthening of existing structures
Rehabilitation and strengthening of existing structuresRehabilitation and strengthening of existing structures
Rehabilitation and strengthening of existing structures
 
Grouting, guniting, jacketing
Grouting, guniting, jacketingGrouting, guniting, jacketing
Grouting, guniting, jacketing
 
Seismic Analysis
Seismic AnalysisSeismic Analysis
Seismic Analysis
 
Shear wall
Shear wallShear wall
Shear wall
 
Repair to overcome low member strength
Repair to overcome low member strength Repair to overcome low member strength
Repair to overcome low member strength
 
Raft foundations
Raft foundationsRaft foundations
Raft foundations
 
Retrofitting of concrete structure
Retrofitting of concrete structureRetrofitting of concrete structure
Retrofitting of concrete structure
 
Chapter 3 shallow foundations
Chapter 3 shallow foundationsChapter 3 shallow foundations
Chapter 3 shallow foundations
 

Similar to Rehabilitation of foundation

Underpinning presentation chakamba
Underpinning presentation  chakambaUnderpinning presentation  chakamba
Underpinning presentation chakambaJohn Chakamba
 
REPORT ON ANALYSIS OF CONSTRUCTION SEQUENCES
REPORT ON 	ANALYSIS OF CONSTRUCTION SEQUENCES REPORT ON 	ANALYSIS OF CONSTRUCTION SEQUENCES
REPORT ON ANALYSIS OF CONSTRUCTION SEQUENCES Saleh Ahmed
 
bulding foundation for costruction (6).ppt
bulding foundation for costruction (6).pptbulding foundation for costruction (6).ppt
bulding foundation for costruction (6).pptAbdulwalimusemohamed
 
Tutorial 2 (1)
Tutorial 2 (1)Tutorial 2 (1)
Tutorial 2 (1)Daphne Tan
 
A technical seminar bubble deck slab.pptx
A technical seminar bubble deck slab.pptxA technical seminar bubble deck slab.pptx
A technical seminar bubble deck slab.pptxhkhemanth564
 
A technical seminar bubble deck slab.pptx
A technical seminar bubble deck slab.pptxA technical seminar bubble deck slab.pptx
A technical seminar bubble deck slab.pptxhkhemanth564
 
CHAPTER 5 DEEP FOUNDATION (2)7788788.ppt
CHAPTER 5 DEEP FOUNDATION (2)7788788.pptCHAPTER 5 DEEP FOUNDATION (2)7788788.ppt
CHAPTER 5 DEEP FOUNDATION (2)7788788.pptbryankalindo888
 
Btech compile 6 oct 4am
Btech compile 6 oct 4amBtech compile 6 oct 4am
Btech compile 6 oct 4amCeline Tan
 
Ishfaq Rashid.pptx
Ishfaq Rashid.pptxIshfaq Rashid.pptx
Ishfaq Rashid.pptxlovish34
 
Presentation on Mat Foundation
Presentation on Mat FoundationPresentation on Mat Foundation
Presentation on Mat FoundationSaif Ahmed
 
Construction Technology Report
Construction Technology ReportConstruction Technology Report
Construction Technology ReportShao Xun Sean Thun
 
An over view of the high rise buildings
An over view of the high rise buildingsAn over view of the high rise buildings
An over view of the high rise buildingshlksd
 

Similar to Rehabilitation of foundation (20)

Underpinning
UnderpinningUnderpinning
Underpinning
 
Underpinning presentation chakamba
Underpinning presentation  chakambaUnderpinning presentation  chakamba
Underpinning presentation chakamba
 
Site report
Site reportSite report
Site report
 
REPORT ON ANALYSIS OF CONSTRUCTION SEQUENCES
REPORT ON 	ANALYSIS OF CONSTRUCTION SEQUENCES REPORT ON 	ANALYSIS OF CONSTRUCTION SEQUENCES
REPORT ON ANALYSIS OF CONSTRUCTION SEQUENCES
 
vacation work report 2
vacation work report 2vacation work report 2
vacation work report 2
 
bulding foundation for costruction (6).ppt
bulding foundation for costruction (6).pptbulding foundation for costruction (6).ppt
bulding foundation for costruction (6).ppt
 
Tutorial 2 (1)
Tutorial 2 (1)Tutorial 2 (1)
Tutorial 2 (1)
 
A technical seminar bubble deck slab.pptx
A technical seminar bubble deck slab.pptxA technical seminar bubble deck slab.pptx
A technical seminar bubble deck slab.pptx
 
A technical seminar bubble deck slab.pptx
A technical seminar bubble deck slab.pptxA technical seminar bubble deck slab.pptx
A technical seminar bubble deck slab.pptx
 
CHAPTER 5 DEEP FOUNDATION (2)7788788.ppt
CHAPTER 5 DEEP FOUNDATION (2)7788788.pptCHAPTER 5 DEEP FOUNDATION (2)7788788.ppt
CHAPTER 5 DEEP FOUNDATION (2)7788788.ppt
 
Btech compile 6 oct 4am
Btech compile 6 oct 4amBtech compile 6 oct 4am
Btech compile 6 oct 4am
 
Ishfaq Rashid.pptx
Ishfaq Rashid.pptxIshfaq Rashid.pptx
Ishfaq Rashid.pptx
 
Presentation on Mat Foundation
Presentation on Mat FoundationPresentation on Mat Foundation
Presentation on Mat Foundation
 
pile wall
pile wallpile wall
pile wall
 
Building construction
Building constructionBuilding construction
Building construction
 
Ct assignment
Ct assignmentCt assignment
Ct assignment
 
Construction Technology Report
Construction Technology ReportConstruction Technology Report
Construction Technology Report
 
Ct assignment
Ct assignmentCt assignment
Ct assignment
 
Deep excavation report
Deep excavation reportDeep excavation report
Deep excavation report
 
An over view of the high rise buildings
An over view of the high rise buildingsAn over view of the high rise buildings
An over view of the high rise buildings
 

Recently uploaded

Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxvipinkmenon1
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and usesDevarapalliHaritha
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacingjaychoudhary37
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 

Recently uploaded (20)

Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptx
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and uses
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacing
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 

Rehabilitation of foundation

  • 2.  Foundations are sub-structure that transmits the load of the building along with its own weight into the soil.  The main purpose of the foundation is to increase the stability of the structure by distributing the structural load over a large bearing area without causing bearing capacity failure and excessive settlement.
  • 3. (1) BEARING CAPACITY FAILURE: 1. By error in estimation of Shear Strength parameters 2. By error in estimation of Type of Shear failure in SBC determination
  • 4. (2) SETTLEMENT:  Settlement of foundation is when the weight of the structure is greater than the bearing capacity of the soil.
  • 5. (3) SHRINKAGE CRACK: The basic reason for the development of shrinkage cracks in concrete slab-on- grade foundations is due to ground water depletion. Found on clay soil and cracks are developed in foundation wall and floor slab.
  • 6. (4) MOISTURE INSTRUSION: Moisture penetrates the foundation at the location of the shrinkage cracks. It also penetrates the slab in the form of water vapor and cause damage to floor coverings and settles.
  • 7.  Foundation is an integral structural part of a home and affects the building from the basement to the roof if it is weekend or fail.  If the foundation fails and no foundation repair is made, the rest of the home will ultimately crumble.  Rehabilitation is a process that strengthens foundations which have been weakened by above discussed factors.
  • 8. 1. Concrete jacketing 2. Micropile technique 3. Push pier system 4. Jack up technique
  • 9.  Commonly used method for widening and strengthening of existing foundations.  Carried out by constructing a “concrete jacket” to existing foundation.  With this method, axial strength, bending strength and stiffness of the damaged column gets increased.  The size of the jacket shall be selected such that the average maximum foundation pressure does not exceed the recommended allowable value.  The new jacket should be properly anchored to the existing footing in order to withstand transfer of loads.
  • 10. STEP 1: Excavation around the footing. STEP 2: Cleaning and roughening the concrete surface.
  • 11.  STEP 3: Installing dowels at 25-30cm spacing in both directions using an appropriate epoxy material. STEP 4: Fastening the new steel bars. STEP 5: Pouring the new concrete.
  • 12. INSTALLING DOWELS AND STEEL RODS JACKETING
  • 13.  Micropiles are small-diameter (typically 2” to 8” diameter) piles that can be drilled, sealed and injected with cement grout and incorporating steel reinforcement elements that withstand a higher proportion of all the design loads compared with conventional piles.  Can be vertical or inclined.  Can be installed in confined space and through any type of subsurface condition from sand to clay.  The load is mostly supported by the steel and transferred via the cement grout to the surrounding ground through high lateral resistance.
  • 14. 1. Drilling and casing 2. Reinforcement placement 3. Injection (grouting) 4. Connecting to the superstructure.
  • 15.
  • 16. PROBLEM: The expansion of Michigan State University’s Spartan Stadium includes construction of new sky boxes, press boxes, elevators and access ramps. However, some of the new load from these improvements will be transferred to existing columns and footings. MSU’s consultants determined that the existing footings were too small to carry the additional load and that foundation modifications would be necessary. SOLUTION: Micropiles were chosen to structurally support the existing footings and to transfer the new loads to bedrock.
  • 17.
  • 18. Push piers are hydraulically driven pier systems consisting of sections of galvanized or epoxy-coated steel pipe. These systems utilize high-strength round steel tube sections and a load transfer bracket to stabilize and to lift sinking or settling foundations. Push piers has its ability to penetrate various layers and strengths the soil to achieve great depths. An important feature that makes this possible is called a “friction reducing collar” which is simply a ring that is welded to the pier segment. The friction reducing collar slightly enlarged end creates a small annular space around the pier shaft that can dramatically reduce skin friction as the pier is advanced through the soil.
  • 19.
  • 20. STEP 1: Footing is exposed for the bracket. STEP 2: The bracket, driving equipment and tubes are assembled at pier location.
  • 21. STEP 3: Steel tube sections are hydraulically driven into soil. STEP 4: Weight of the home is transferred to the piers.
  • 22.
  • 23. STEP 5: Lifting the structure back to its original position is attempted. STEP 6: Soil is backfilled and work area is cleaned up.
  • 24. PROBLEM: The liberty middle school in Clifton is a single storey structure with exterior concrete block walls and brick veneer. A bump-out area of the building approximately 100 feet long and 14-feet wide had settled and rotated away from the main footprint of the structure. An interior block partition wall intersected the long exterior wall at its mid-length. The settlement and rotation of the exterior wall caused the two walls to separate with the crack wider at the top than the bottom. The movement also raised concern that connections and adequate bearing of the roof joists to the top of the exterior block wall had been compromised. A subsurface investigation encountered lean to fat clay underlain by competent limestone. SOLUTION: A system of hydraulically-driven push piers was selected as the most economical method to stabilize and potentially lift the settled area of the building. A total of 17 push piers were installed at a 7 feet maximum center-to-center spacing. 15 piers were installed along the 100 feet section of wall and 2 piers were installed at each of the 14 foot returns. A 50 kip drive load was specified per pier with a minimum factor of safety of 1.5 after the lift. Excavation to site clean-up was completed in just four days.
  • 25.  Mud jacking is used when a foundation is so weak that piers or pilings cannot be installed and where concrete slabs are lifted or moved using a complex hydraulic system.  Small holes are drilled and polyurethane resins are injected. When the resins mix underneath a foundation, they form a gas bubbles and expands which results in lifting of buildings.  After lifting, the small hole are patched with concrete.  It is a convenient and inexpensive way to lift pool decks, slabs, driveways and other items made of concrete that is 3 to 6 inches thick.  Mud jacking is cheaper and can often be completed in a day or two days.
  • 26.
  • 27. PROBLEM: In the 4 years since construction, the CNIM factory, Canjiang Industrial Park, China , the floors had subsided up to 365mm, making some areas unproductive in last 12 months. SOLUTION: Soil stabilisation and compaction was carried out using the deep injection technology of expanding resins at extremely high pressures at the weak locations and levels as detected by the penetrometer testing. Floor slabs were lifted and voids beneath the slabs filled by foam injected directly below the slab.