SlideShare a Scribd company logo
1 of 37
CONSTRUCTION TECHNOLOGY 2
CHAPTER 1.1 DEEP EXCAVATION
GROUP MEMBERS:
LEE SU WEN
LIM JIA YI
CELINE CHONG
YAP SUK PING
KANG YING HONG
 You are an engineer in a construction company
which is awarded a tender in basement excavation
and construction using the diaphragm wall method.
The basement is designed for a three (3) storey car
park below a multi-storey office block. You are
assigned to prepare the method statements for this
project which involves the following matters:-
WHAT IS A DIAPHRAGM WALL?
 A reinforced concrete structure constructed in-situ panel by panel.
 Constructed using a narrow trench excavated in ground and supported by
an engineered fluid ( typically bentonite mud or polymer mud) until the
mud is replaced by the concrete
 Walls generally range from 600 to 1500 mm thickness, in wide between
2000 and 3500 mm and can be excavated to depths of 60m or more.
 Used for decades to provide cost-effective, long-term solutions for many
groundwater control problems
DIAPHRAGM WALL APPLICATIONS
Commonly used for
retention systems and
permanent retaining walls
of the basement
Used as deep
groundwater barriers
As a cut-off provision to
support deep excavation
Used in congested areas
As a separating structure
between major
underground facilities
As the final wall for
basement or other
underground structure
Q1. THE CONSTRUCTION OF A
PRE-TRENCH AT THE INITIAL
STAGE OF DIAPHRAGM WALL.
GUIDE WALL
 Construct two temporary parallel concrete beams -
guide the excavation tool and to stabilize the upper
 Maintain the horizontal alignment and wall
continuity of a diaphragm wall while are adopted
 Help guide the diaphragm wall grabs vertically and
aid in the positioning of the final structure
 The dimensions and shape - depending on the
nature of the surface soil
 Shall be 100 to 250 mm thick, 1-2m deep and made
of lightly reinforced concrete and shall represent the
reference lines
TRENCH EXCAVATION
 Excavation is done by digging technique using clamshell or
grabs to the desired depth.
 Sand and soft rock strata - excavation by cutting technique
using reverse circulation trench cutters can be used.
 Carried out with the aid of several pieces of equipment, such as
(in increasing order of cost):
 Mechanical clam-shell,
 Hydraulic clam-shell,
 Kelly bar
 Hydromill
 The choice of the equipment depends mainly on the
characteristics of the soil to be excavated and on the depth to
be reached.
EXCAVATION SUPPORT
 Prevented from collapsing - reinforcing and casting by
the use of supporting bentonite slurry
 supporting slurry fluid must be cleaned - it's
properties are within acceptable levels
 balances the inward hydraulic forces and prevents
water flow into the trench
 The mud is usually pumped to a storage tank where it
hydrates for up to 12 hours.
 The bentonite particles swell and absorb the water
before it’s used to support the excavation.
REINFORCEMENT
 A prefabricated reinforced
cage is then lowered into the
excavation between the stop
ends.
 Reinforcement cage must
have a sufficient transverse
and diagonal reinforcement
 to withstand lifting and
lowering handling forces
 Sufficient space must be left
for at least two or three tremie
pipes
CONCRETING
 Process of replacing the supporting slurry with the permanent
concrete with the use of vertical pipes - tremies.
 Prevent the segregation of concrete
 Lift the tremies progressively as the concrete level raises
 Maintain a minimum depth of 0.6 meters of tremie pipe into the
concrete.
 Overpouring might be required - make sure that all slurry is
displaced
 Poor tremieing can result in slurry pockets getting entraped within
the diaphragm wall concrete.
 Lead to excessive and costly groundwater leaks or even blowouts.
 Central Artery Project in Boston, MA (Big dig) and has led to
costly repairs and delays.
JOINING FOR THE DIAPHRAGM WALL PANEL
 Purpose: to protect the rubber water stop during the excavation of the trench for the
next panel
 It will be remove before the placing of reinforcement and concrete into the excavated
trench
• The steel pipes are installed at both panel
fronts before concreting
• The pipes rest on the excavation bottom
and match the circular shape of the panel
fronts
• Concrete injected takes the shape of the
stop end pipes
• The panel has concave fronts
1. Stop End Pipes
3. DISPOSABLE PIPES
 PVC
 Fixed to the cage and lowered to rest on
the bottom
 A panel with two holes
 When concrete is cast in the secondary
panel, it fills the recess and creates a joint
with the primary panel.
2. Sheet Piling
• Driven into the primary panel, before concrete is
cast
• Concrete on the fronts of the panel takes on the
shape of the sheet pile and a recess is created.
• Concrete has hardened - keep its shape, sheet
piles are extracted.
• Allows for the insertion of plastic elements - water
stops between the panels -guarantee increased
water tightness.
WHAT IS EXCAVATION SUPPORT SYSTEM?
keep the sides of deep
excavations stable
1
To withstand soil
pressure and water
pressure (hydrostatic
pressure)
2
ensure that movements
will not cause damage
to neighbouring
structures
3
Preliminary analysis has
to be carried out for
many options of wall
and support system
4
TEMPORARY EXCAVATION SUPPORT:
• Only for temporary construction
• can be taken out after constructed
• Reused
• Example:
1. Cantilever wall
2. Soldier pile and lagging
3. Sheet pile- to provide safe access for construction
PERMANENT EXCAVATION SUPPORT:
• Remain in the site
• Example:
1. Diaphragm wall
2. Bore pile
3. Sheet pile- serve as permanent retaining structures
Q2. THE SELECTION OF
SUITABLE TEMPORARY
EXCAVATION SUPPORT
Cantilever wall
• one type of retaining
structure
• suitable for situation when
the excavation relatively
shallow and the ground is
stiff
• A structure to withstand the
soil pressure and water
pressure.
Soldier pile and lagging
• An earth retention technique that
retains soil, using vertical steel piles
with horizontal lagging
• pile can be from the UB (universal
beam) or UC (universal column)
• and are inserted into the pre-bored
holes at the perimeter of the
excavation site for basement
Interlocking sheet pile
• H-piles with infilling horizontal
sheeting have also been used
successfully
• Driven in side by side with interlocking
ends
• Light weight
• Can be reused serval times
CONSIDERATION OF EXCAVATION SUPPORT
Soil characteristic
Depth of the project
Cost management
Neighbourhood conditions of a site
Construction procedure
Soil characteristic
• Can be used in most type of soil
Depth
• Suitable for 3storey basement
Water table • Required dewatering
Costing • Cheap
Neighbour disturbance • Relatively quiet
Construction procedure • Easy and fast to construct
SOLDIER PILE AND LAGGING
Dewatering:
• A process to remove the over-saturated water in ground
• Keep the subsoil within a non-saturated condition.
Q3. LIST OUT 6 ADVANTAGES
OF THE DIAPHRAGM WALL
SUPPORT
ADVANTAGES OF THE DIAPHRAGM WALL SUPPORT
Reduced number of
joints in the wall
•Improves the walls water
tightness
•Little effects on adjacent
structure
Great depth
Lee Tunnel Project
Diaphragm wall with 98m depth
Quiet and little
vibration
Low environmental impact
* Sound pollution
* Land disturbance
Shorten working period
Saving Cost
Less temporary supports
Eg: Labour Cost, Specialist
Contractors
Take Heavy Loads
Used as permanent structure wall
Foundation of the superstructure
Time Management
Faster execution
Prevent liquidated damage
PRIMARY & SECONDARY & ENDING PANELS
DISADVANTAGES
OF DIAPHRAGM WALL SUPPORT
Less flexible
High cost for short term
project
Q4. STATE 2 OF EXCAVATOR
MACHINES
EXCAVATOR MACHINES
 Suitable for different kind of
works such as rock excavation,
trenching, etc.
 Suitable for hard surface and
soil
 Control high degree of
verticality
Hydraulic rock cutter
HYDRAULIC DIAPHRAGM WALL GRAB
 Suitable for most of soil
conditions
 Controlled by monitoring
system
 High accuracy to verticality
 Excavate over 50m depths
 Free of noise and vibration
Q5. WHAT ARE THE SUITABLE STEPS
AND PRECAUTIONS TO TAKE IF
RUBBER WATER STOPS ARE TO BE
CAST AT BOTH SIDES OF THE
DIAPHRAGM WALL?
• Mainly to block the passage of
liquid within concrete joints
• PVC is the most commonly used
material for water stops
• Copper and stainless steel and
natural rubber can also be used
• Fundamental object for
construction works to exclude water
RUBBER WATERSTOP
PRECAUTIONS
• Pay particular attention to the underside of horizontally
placed waterstops
• Intimate contact between the concrete and waterstop is
necessary for full performance of a waterstop
• Maintain adequate clearance between reinforcing steel and
the waterstop
• To promote the formation of voids due to aggregate bridging
• Waterstop should never be cut or modified to allow
reinforcement to pass through
Q6. THE SUITABLE TYPE OF
ADDITIONAL SUPPORT FOR THE
COMPLETED DIAPHRAGM WALL
ADDITIONAL DIAPHRAGM WALL SUPPORT
 Commonly used for the
stabilization of steep slopes
which consist of softer soils
 Tendon the steel rods is
connected to the bearing plate
 Help preventing excessive
erosion or landslide
GROUND ANCHOR
Q7. THE FUNCTION OF TREMIE
TUBE AND PRECAUTION TO BE
TAKEN WHEN USING THE TUBE
PRECAUTIONS
 Transfer concrete under bentonite
slurry which will displace bentonite
slurry when the concrete is filled from
the bottom
 Pour concrete underwater in a way
that avoids washout of cement from
the mix due to turbulent water contact
with the concrete while it is flowing
 Tremie tube has to be cleaned every time
after using, to prevent any excess concrete
to stick on to the tube, that will cause
blockage
 Concrete should be coherent, rich in
cement and of slump between 150 and
180mm
 Lower end of tremie tube should be kept
embedded in the wet concrete
 When a large number of concrete are
required to be placed over an extensive
area, it is advisable to use a number of
tremis
FUNCTION

More Related Content

What's hot

Building Technology 1 Construction Solutions Report
Building Technology 1 Construction Solutions ReportBuilding Technology 1 Construction Solutions Report
Building Technology 1 Construction Solutions Reportdouglasloon
 
Construction Contract in Malaysia
Construction Contract in MalaysiaConstruction Contract in Malaysia
Construction Contract in MalaysiaDayat Mohamad
 
Pp1 assignment group 8
Pp1 assignment group 8Pp1 assignment group 8
Pp1 assignment group 8lohwenjun
 
Mooc smm substructure_2
Mooc smm substructure_2Mooc smm substructure_2
Mooc smm substructure_2Azizan Supardi
 
Building services
Building services Building services
Building services Enoch Wong
 
BS 2 Group assignment example Building services-bangsar-village-1
BS 2 Group assignment example Building services-bangsar-village-1BS 2 Group assignment example Building services-bangsar-village-1
BS 2 Group assignment example Building services-bangsar-village-1Est
 
Building Technology Project 1
Building Technology Project 1Building Technology Project 1
Building Technology Project 1zerospaces_
 
Building Service Project 2 Year 2016 (Taylors University Lakeside Campus)
Building Service Project 2 Year 2016 (Taylors University Lakeside Campus)Building Service Project 2 Year 2016 (Taylors University Lakeside Campus)
Building Service Project 2 Year 2016 (Taylors University Lakeside Campus)Ong Seng Peng Jeff
 
SITE REPORT (PAD FOOTING)
SITE REPORT (PAD FOOTING)SITE REPORT (PAD FOOTING)
SITE REPORT (PAD FOOTING)I'mMiss Lily
 
Presentation ibs
Presentation ibsPresentation ibs
Presentation ibsUTHM
 
B.tech Project 1 - Industrialised Building Systems
B.tech Project 1 - Industrialised Building SystemsB.tech Project 1 - Industrialised Building Systems
B.tech Project 1 - Industrialised Building SystemsCarmen Chan
 
Final BUILDING CONSTRUCTION 1
Final BUILDING CONSTRUCTION 1 Final BUILDING CONSTRUCTION 1
Final BUILDING CONSTRUCTION 1 Dexter Ng
 
Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1Sow Wei Henn
 
CT III IBS Formwork System
CT III IBS Formwork System CT III IBS Formwork System
CT III IBS Formwork System ashleyyeap
 
Blockwork system
Blockwork systemBlockwork system
Blockwork systemWen Crystal
 
Final Bills of Quantity
Final Bills of QuantityFinal Bills of Quantity
Final Bills of QuantityArissa Loh
 
building services project 1
building services project 1building services project 1
building services project 1Baddy Peigun
 

What's hot (20)

Building Technology 1 Construction Solutions Report
Building Technology 1 Construction Solutions ReportBuilding Technology 1 Construction Solutions Report
Building Technology 1 Construction Solutions Report
 
Construction Contract in Malaysia
Construction Contract in MalaysiaConstruction Contract in Malaysia
Construction Contract in Malaysia
 
Pp1 assignment group 8
Pp1 assignment group 8Pp1 assignment group 8
Pp1 assignment group 8
 
Mooc smm substructure_2
Mooc smm substructure_2Mooc smm substructure_2
Mooc smm substructure_2
 
Building services
Building services Building services
Building services
 
BS 2 Group assignment example Building services-bangsar-village-1
BS 2 Group assignment example Building services-bangsar-village-1BS 2 Group assignment example Building services-bangsar-village-1
BS 2 Group assignment example Building services-bangsar-village-1
 
Building Technology Project 1
Building Technology Project 1Building Technology Project 1
Building Technology Project 1
 
Precast concrete
Precast concretePrecast concrete
Precast concrete
 
Building Service Project 2 Year 2016 (Taylors University Lakeside Campus)
Building Service Project 2 Year 2016 (Taylors University Lakeside Campus)Building Service Project 2 Year 2016 (Taylors University Lakeside Campus)
Building Service Project 2 Year 2016 (Taylors University Lakeside Campus)
 
SITE REPORT (PAD FOOTING)
SITE REPORT (PAD FOOTING)SITE REPORT (PAD FOOTING)
SITE REPORT (PAD FOOTING)
 
Presentation ibs
Presentation ibsPresentation ibs
Presentation ibs
 
B.tech Project 1 - Industrialised Building Systems
B.tech Project 1 - Industrialised Building SystemsB.tech Project 1 - Industrialised Building Systems
B.tech Project 1 - Industrialised Building Systems
 
Final BUILDING CONSTRUCTION 1
Final BUILDING CONSTRUCTION 1 Final BUILDING CONSTRUCTION 1
Final BUILDING CONSTRUCTION 1
 
bs:copbs101
bs:copbs101bs:copbs101
bs:copbs101
 
Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1
 
CT III IBS Formwork System
CT III IBS Formwork System CT III IBS Formwork System
CT III IBS Formwork System
 
Blockwork system
Blockwork systemBlockwork system
Blockwork system
 
Final Bills of Quantity
Final Bills of QuantityFinal Bills of Quantity
Final Bills of Quantity
 
Steel formwork
Steel formworkSteel formwork
Steel formwork
 
building services project 1
building services project 1building services project 1
building services project 1
 

Similar to Soldier Bored and Diaphragm

Diaphragm walls
Diaphragm wallsDiaphragm walls
Diaphragm wallsNeha Vivek
 
Diaphragm walls
Diaphragm wallsDiaphragm walls
Diaphragm wallsNguyen Bao
 
FERROCRETE - MATERIAL AND CONSTRUCTION METHODS
FERROCRETE - MATERIAL AND CONSTRUCTION METHODSFERROCRETE - MATERIAL AND CONSTRUCTION METHODS
FERROCRETE - MATERIAL AND CONSTRUCTION METHODSjagrutib22
 
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining Structures
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining StructuresEXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining Structures
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining StructuresShivananda Roy
 
diaphragmwall-141223040711-conversion-gate02.pdf
diaphragmwall-141223040711-conversion-gate02.pdfdiaphragmwall-141223040711-conversion-gate02.pdf
diaphragmwall-141223040711-conversion-gate02.pdfJeevanandanKanagavel1
 
WRE II construction of galleries in gravity dams
WRE II construction of galleries in gravity damsWRE II construction of galleries in gravity dams
WRE II construction of galleries in gravity damsMitaliShelke
 
D-wall Presentation - Rebar Cage.pdf
D-wall Presentation - Rebar Cage.pdfD-wall Presentation - Rebar Cage.pdf
D-wall Presentation - Rebar Cage.pdfAnonymousTxhyGf
 
Module on Special and high performance concrete
Module on Special and high performance concreteModule on Special and high performance concrete
Module on Special and high performance concreteErankajKumar
 
Diaphragm wall construction
Diaphragm wall constructionDiaphragm wall construction
Diaphragm wall constructionABHISHEK THAKKAE
 
Cut and cover_sections
Cut and cover_sectionsCut and cover_sections
Cut and cover_sectionsjuwes
 
Rehabilitation and strengthening of existing structures
Rehabilitation and strengthening of existing structuresRehabilitation and strengthening of existing structures
Rehabilitation and strengthening of existing structuresShahrukh Niaz
 
The construction method for surface drainage (housing)
The construction method for surface drainage (housing)The construction method for surface drainage (housing)
The construction method for surface drainage (housing)Adib Ramli
 
1619929813526_College Deep Well Foundation Project.pptx
1619929813526_College Deep Well Foundation Project.pptx1619929813526_College Deep Well Foundation Project.pptx
1619929813526_College Deep Well Foundation Project.pptxAkshayGhorpade19
 

Similar to Soldier Bored and Diaphragm (20)

Diaphragm walls
Diaphragm wallsDiaphragm walls
Diaphragm walls
 
Diaphragm walls
Diaphragm wallsDiaphragm walls
Diaphragm walls
 
Diaphragm Wall
 Diaphragm Wall Diaphragm Wall
Diaphragm Wall
 
1.2 Diaphragm walls.pptx
1.2 Diaphragm walls.pptx1.2 Diaphragm walls.pptx
1.2 Diaphragm walls.pptx
 
Micropile
MicropileMicropile
Micropile
 
FERROCRETE - MATERIAL AND CONSTRUCTION METHODS
FERROCRETE - MATERIAL AND CONSTRUCTION METHODSFERROCRETE - MATERIAL AND CONSTRUCTION METHODS
FERROCRETE - MATERIAL AND CONSTRUCTION METHODS
 
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining Structures
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining StructuresEXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining Structures
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining Structures
 
Diaphragm wall
Diaphragm wallDiaphragm wall
Diaphragm wall
 
diaphragmwall-141223040711-conversion-gate02.pdf
diaphragmwall-141223040711-conversion-gate02.pdfdiaphragmwall-141223040711-conversion-gate02.pdf
diaphragmwall-141223040711-conversion-gate02.pdf
 
WRE II construction of galleries in gravity dams
WRE II construction of galleries in gravity damsWRE II construction of galleries in gravity dams
WRE II construction of galleries in gravity dams
 
D-wall Presentation - Rebar Cage.pdf
D-wall Presentation - Rebar Cage.pdfD-wall Presentation - Rebar Cage.pdf
D-wall Presentation - Rebar Cage.pdf
 
Module on Special and high performance concrete
Module on Special and high performance concreteModule on Special and high performance concrete
Module on Special and high performance concrete
 
Diaphragm wall construction
Diaphragm wall constructionDiaphragm wall construction
Diaphragm wall construction
 
Soil Nailing
Soil NailingSoil Nailing
Soil Nailing
 
Cut and cover_sections
Cut and cover_sectionsCut and cover_sections
Cut and cover_sections
 
Rehabilitation and strengthening of existing structures
Rehabilitation and strengthening of existing structuresRehabilitation and strengthening of existing structures
Rehabilitation and strengthening of existing structures
 
Deep excavation report
Deep excavation reportDeep excavation report
Deep excavation report
 
Cofferdam
CofferdamCofferdam
Cofferdam
 
The construction method for surface drainage (housing)
The construction method for surface drainage (housing)The construction method for surface drainage (housing)
The construction method for surface drainage (housing)
 
1619929813526_College Deep Well Foundation Project.pptx
1619929813526_College Deep Well Foundation Project.pptx1619929813526_College Deep Well Foundation Project.pptx
1619929813526_College Deep Well Foundation Project.pptx
 

Recently uploaded

Effects of rheological properties on mixing
Effects of rheological properties on mixingEffects of rheological properties on mixing
Effects of rheological properties on mixingviprabot1
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)Dr SOUNDIRARAJ N
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptSAURABHKUMAR892774
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHC Sai Kiran
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfme23b1001
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 

Recently uploaded (20)

Effects of rheological properties on mixing
Effects of rheological properties on mixingEffects of rheological properties on mixing
Effects of rheological properties on mixing
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.ppt
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECH
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdf
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 

Soldier Bored and Diaphragm

  • 1. CONSTRUCTION TECHNOLOGY 2 CHAPTER 1.1 DEEP EXCAVATION GROUP MEMBERS: LEE SU WEN LIM JIA YI CELINE CHONG YAP SUK PING KANG YING HONG
  • 2.  You are an engineer in a construction company which is awarded a tender in basement excavation and construction using the diaphragm wall method. The basement is designed for a three (3) storey car park below a multi-storey office block. You are assigned to prepare the method statements for this project which involves the following matters:-
  • 3. WHAT IS A DIAPHRAGM WALL?  A reinforced concrete structure constructed in-situ panel by panel.  Constructed using a narrow trench excavated in ground and supported by an engineered fluid ( typically bentonite mud or polymer mud) until the mud is replaced by the concrete  Walls generally range from 600 to 1500 mm thickness, in wide between 2000 and 3500 mm and can be excavated to depths of 60m or more.  Used for decades to provide cost-effective, long-term solutions for many groundwater control problems
  • 4. DIAPHRAGM WALL APPLICATIONS Commonly used for retention systems and permanent retaining walls of the basement Used as deep groundwater barriers As a cut-off provision to support deep excavation Used in congested areas As a separating structure between major underground facilities As the final wall for basement or other underground structure
  • 5. Q1. THE CONSTRUCTION OF A PRE-TRENCH AT THE INITIAL STAGE OF DIAPHRAGM WALL.
  • 6. GUIDE WALL  Construct two temporary parallel concrete beams - guide the excavation tool and to stabilize the upper  Maintain the horizontal alignment and wall continuity of a diaphragm wall while are adopted  Help guide the diaphragm wall grabs vertically and aid in the positioning of the final structure  The dimensions and shape - depending on the nature of the surface soil  Shall be 100 to 250 mm thick, 1-2m deep and made of lightly reinforced concrete and shall represent the reference lines
  • 7. TRENCH EXCAVATION  Excavation is done by digging technique using clamshell or grabs to the desired depth.  Sand and soft rock strata - excavation by cutting technique using reverse circulation trench cutters can be used.  Carried out with the aid of several pieces of equipment, such as (in increasing order of cost):  Mechanical clam-shell,  Hydraulic clam-shell,  Kelly bar  Hydromill  The choice of the equipment depends mainly on the characteristics of the soil to be excavated and on the depth to be reached.
  • 8. EXCAVATION SUPPORT  Prevented from collapsing - reinforcing and casting by the use of supporting bentonite slurry  supporting slurry fluid must be cleaned - it's properties are within acceptable levels  balances the inward hydraulic forces and prevents water flow into the trench  The mud is usually pumped to a storage tank where it hydrates for up to 12 hours.  The bentonite particles swell and absorb the water before it’s used to support the excavation.
  • 9.
  • 10. REINFORCEMENT  A prefabricated reinforced cage is then lowered into the excavation between the stop ends.  Reinforcement cage must have a sufficient transverse and diagonal reinforcement  to withstand lifting and lowering handling forces  Sufficient space must be left for at least two or three tremie pipes
  • 11. CONCRETING  Process of replacing the supporting slurry with the permanent concrete with the use of vertical pipes - tremies.  Prevent the segregation of concrete  Lift the tremies progressively as the concrete level raises  Maintain a minimum depth of 0.6 meters of tremie pipe into the concrete.  Overpouring might be required - make sure that all slurry is displaced  Poor tremieing can result in slurry pockets getting entraped within the diaphragm wall concrete.  Lead to excessive and costly groundwater leaks or even blowouts.  Central Artery Project in Boston, MA (Big dig) and has led to costly repairs and delays.
  • 12. JOINING FOR THE DIAPHRAGM WALL PANEL  Purpose: to protect the rubber water stop during the excavation of the trench for the next panel  It will be remove before the placing of reinforcement and concrete into the excavated trench • The steel pipes are installed at both panel fronts before concreting • The pipes rest on the excavation bottom and match the circular shape of the panel fronts • Concrete injected takes the shape of the stop end pipes • The panel has concave fronts 1. Stop End Pipes
  • 13. 3. DISPOSABLE PIPES  PVC  Fixed to the cage and lowered to rest on the bottom  A panel with two holes  When concrete is cast in the secondary panel, it fills the recess and creates a joint with the primary panel. 2. Sheet Piling • Driven into the primary panel, before concrete is cast • Concrete on the fronts of the panel takes on the shape of the sheet pile and a recess is created. • Concrete has hardened - keep its shape, sheet piles are extracted. • Allows for the insertion of plastic elements - water stops between the panels -guarantee increased water tightness.
  • 14. WHAT IS EXCAVATION SUPPORT SYSTEM? keep the sides of deep excavations stable 1 To withstand soil pressure and water pressure (hydrostatic pressure) 2 ensure that movements will not cause damage to neighbouring structures 3 Preliminary analysis has to be carried out for many options of wall and support system 4
  • 15. TEMPORARY EXCAVATION SUPPORT: • Only for temporary construction • can be taken out after constructed • Reused • Example: 1. Cantilever wall 2. Soldier pile and lagging 3. Sheet pile- to provide safe access for construction PERMANENT EXCAVATION SUPPORT: • Remain in the site • Example: 1. Diaphragm wall 2. Bore pile 3. Sheet pile- serve as permanent retaining structures
  • 16. Q2. THE SELECTION OF SUITABLE TEMPORARY EXCAVATION SUPPORT
  • 17. Cantilever wall • one type of retaining structure • suitable for situation when the excavation relatively shallow and the ground is stiff • A structure to withstand the soil pressure and water pressure.
  • 18. Soldier pile and lagging • An earth retention technique that retains soil, using vertical steel piles with horizontal lagging • pile can be from the UB (universal beam) or UC (universal column) • and are inserted into the pre-bored holes at the perimeter of the excavation site for basement
  • 19. Interlocking sheet pile • H-piles with infilling horizontal sheeting have also been used successfully • Driven in side by side with interlocking ends • Light weight • Can be reused serval times
  • 20. CONSIDERATION OF EXCAVATION SUPPORT Soil characteristic Depth of the project Cost management Neighbourhood conditions of a site Construction procedure
  • 21. Soil characteristic • Can be used in most type of soil Depth • Suitable for 3storey basement Water table • Required dewatering Costing • Cheap Neighbour disturbance • Relatively quiet Construction procedure • Easy and fast to construct SOLDIER PILE AND LAGGING Dewatering: • A process to remove the over-saturated water in ground • Keep the subsoil within a non-saturated condition.
  • 22. Q3. LIST OUT 6 ADVANTAGES OF THE DIAPHRAGM WALL SUPPORT
  • 23. ADVANTAGES OF THE DIAPHRAGM WALL SUPPORT Reduced number of joints in the wall •Improves the walls water tightness •Little effects on adjacent structure Great depth Lee Tunnel Project Diaphragm wall with 98m depth Quiet and little vibration Low environmental impact * Sound pollution * Land disturbance Shorten working period
  • 24.
  • 25. Saving Cost Less temporary supports Eg: Labour Cost, Specialist Contractors Take Heavy Loads Used as permanent structure wall Foundation of the superstructure Time Management Faster execution Prevent liquidated damage
  • 26. PRIMARY & SECONDARY & ENDING PANELS
  • 27. DISADVANTAGES OF DIAPHRAGM WALL SUPPORT Less flexible High cost for short term project
  • 28. Q4. STATE 2 OF EXCAVATOR MACHINES
  • 29. EXCAVATOR MACHINES  Suitable for different kind of works such as rock excavation, trenching, etc.  Suitable for hard surface and soil  Control high degree of verticality Hydraulic rock cutter
  • 30. HYDRAULIC DIAPHRAGM WALL GRAB  Suitable for most of soil conditions  Controlled by monitoring system  High accuracy to verticality  Excavate over 50m depths  Free of noise and vibration
  • 31. Q5. WHAT ARE THE SUITABLE STEPS AND PRECAUTIONS TO TAKE IF RUBBER WATER STOPS ARE TO BE CAST AT BOTH SIDES OF THE DIAPHRAGM WALL?
  • 32. • Mainly to block the passage of liquid within concrete joints • PVC is the most commonly used material for water stops • Copper and stainless steel and natural rubber can also be used • Fundamental object for construction works to exclude water RUBBER WATERSTOP
  • 33. PRECAUTIONS • Pay particular attention to the underside of horizontally placed waterstops • Intimate contact between the concrete and waterstop is necessary for full performance of a waterstop • Maintain adequate clearance between reinforcing steel and the waterstop • To promote the formation of voids due to aggregate bridging • Waterstop should never be cut or modified to allow reinforcement to pass through
  • 34. Q6. THE SUITABLE TYPE OF ADDITIONAL SUPPORT FOR THE COMPLETED DIAPHRAGM WALL
  • 35. ADDITIONAL DIAPHRAGM WALL SUPPORT  Commonly used for the stabilization of steep slopes which consist of softer soils  Tendon the steel rods is connected to the bearing plate  Help preventing excessive erosion or landslide GROUND ANCHOR
  • 36. Q7. THE FUNCTION OF TREMIE TUBE AND PRECAUTION TO BE TAKEN WHEN USING THE TUBE
  • 37. PRECAUTIONS  Transfer concrete under bentonite slurry which will displace bentonite slurry when the concrete is filled from the bottom  Pour concrete underwater in a way that avoids washout of cement from the mix due to turbulent water contact with the concrete while it is flowing  Tremie tube has to be cleaned every time after using, to prevent any excess concrete to stick on to the tube, that will cause blockage  Concrete should be coherent, rich in cement and of slump between 150 and 180mm  Lower end of tremie tube should be kept embedded in the wet concrete  When a large number of concrete are required to be placed over an extensive area, it is advisable to use a number of tremis FUNCTION