SlideShare a Scribd company logo
1 of 65
PROCESS PLANNING AND
COST ESTIMATION
INTRODUCTION TO PROCESS
PLANNING
PROCESS PLANNING DEFINITION:
• Set of instructions describes mfg product and its parts.
• Operations planning as systematic determination of engg processes
and systems to mfg a product competitively and economically.
• Prepare work instructions for mfg and assembly of components to
product in discrete mfg environments.
• Systematic determination of methods products to be
mfg,economically and competitively.
• Consists of selection of mfg processes and operations,production
equipment,tooling and jigs and fixtures,
• Determination of mfg parameters,specify selection criteria for quality
assurance ensure product quality.
IMPORTANCE OF PROCESS PLANNING:
• Link between engg design and shop floor mfg,product is how
mfg,production costs and profitability,indepth of knowledge,
equipment capabilities, tooling availability, material processing
characteristics, shop practices.
PRODUCT DESIGN AND MFG CYCLE:
• Intermediate stage b/w designing the product and mfg.
• Three main functions marketing and sales,design,mfg.
PROCESS PLANNING: LINK B/W DESIGN AND MFG:
• Cross functional teams are employed to design and mfg
functions,known as simultaneous or concurrent engg.
RESPOSIBILITIES OF PROCESS PLANNING ENGINEER:
• Part print analysis and symbols.
• Fundamentals of product design(rough stock, production
rate,finish,dimensional tolerances).
• Machining processes(setup time,quality,type and cost of tooling).
• Operations sequence,inspect the equipment,production
tolerances,cutting tools and cutting conditions,overall time by work
measurement techniques.
PROCESS PLANNING ACTIVITIES:
Drawing interpretation:
• Analyse finished part in engineering design.component
drawings(features,dimensions,geometric tolerances,surface
finish,material specification,part required).
Material evaluation and process selection:
• (Function,appearance,reliability,life,environment,compatibility,produc
tivity,cost).Evaluate the materials, (features,dimensions,geometric
tolerances transform rough state to finished state).Process
evolution(rough to finished).Part evolution(final state to initial state).
Selection of m/c,tooling,workholding devices:
• Economic considerations,production rate per unit cost,durability and
dependability,lower process rejection,minimum setup times,long life
of m/c,functional versatility.best m/c,make or buy,BEA .
Selecting process parameters:
• Machines selected,calculating operation setup time and cycle
time,tooling sequence,equipment capability,shop practice.
• Calculation of part processing time requires determination of
sequence of processing steps on each m/c as outplanning.
• Part loading,unloading,m/c indexing for 1 cycle.
• M/c cycle time allowances added to standard cycle time.Calculate
cycle time & m/c rates to find out cost.
Selecting quality assurance methods:
• Inspection criterias(dimensional,geometric,surface finish),tools and
techniques,increases costs&time.
Cost estimating:
• Process of determining the probable cost of product before
manufacture.
• Material,labour,overhead costs-profit.
• Material,mfg processes,batch size,make or buy.
Process planning documentation:
• Document clearly all the detail information.
• Documented as job routing or operating sheet.
• Production operations&associated m/c tools for component and
subassembly.
• Route sheet information as
part identification,processing,operation of m/c,std times,setup cycle
times,tooling requirements,production control information shows
planning lead time operation.
• Reasons: part process-design,job quote,cost estimate,std cost
systems,communication vehicle.
Communicate process knowledge:
• Mfg to shop floor,economy,consistent quality.
Inputs and outputs of process planning:
• Route sheet and operation sheet as single sheet.
PROCESS PLANNING METHODS(APPROACHES TO PROCESS
PLANNING):
• Manual process planning(traditional,workbook approaches).
• Computer aided process planning(retrieval,generative).
Manual process planning:
Traditional approach:
• Process plan prepared manually.
• Examine and interpret eg,m/c process,equipment selection,opns
sequence,shop practices,skill,judgement and experience,different
planners.
• Product opns,manual tools(feed,speed,setup time,opns
time),documented as routing sheet.
Workbook approach:
• Modified version uses developed workbook prepares route sheet.opns
sequence of products the drawing interpretation is carried by
workbook.
Uses of manual approach:
• Small scale companies,flexible,low investments.
Drawbacks of manual approach:
• Complex,time&data high,skill process,human error,skill,judgement
and experience,increases paper work,productivity down,no response
to mfg environment,process,tool,materials…
Computer aided process planning:
• Computers reduces clerical works,rational,consistent and optimal
plans,interface between cad and cam.
Benefits of capp:
• Process rationalization and standardization,productivity
improvement,product cost reduction,eliminate human error,time
reduction,reduces clerical and paper work,legibility improves,fast
response to engg changes,incorporation of application programs.
Retrieval or variant capp systems:
• Widely used in machining applications,similar parts have similar
plans,new part recalls,identifies,retrieves existing plan for similar
modified new parts.
Benefits of retrieval capp systems:
• Standard plan,variety of parts,simple programming and
installation,understandable,easy to learn and use.
Drawbacks of retrieval capp systems:
• Planned components limited to previous planned.
• Experiences modify standard plan.
Generative capp systems:
• Computers synthesize individual process plan automatically w ith or
without reference to prior plan.
• Decision logics and precoded algorithms,mfg using
equipment,specific process plan for specific part.
• Inputting GT code as part design,monitoring the functions.
Components:
• Part description,subsystem define m/c parameters&select and
sequence individual operations,database,report generators.
Advantages of generative capp:
• Consistent process plan,new components,integrating automated mfg
facility provides detailed control information.
Drawbacks of generative capp:
• Complex and very difficult
SELECTION OF PROCESS PLANNING SYSTEM:
• Numerous engg management decisions,identify,weight and compare
interrelated factors.
• Best process plan-general environment,organisational
structure,technical expertise,needs and objectives of MIS.
DRAWING INTERPRETATION:
• Prepares process plan for product,functional requirements of
design,assembled with dimensions and tolerances.
• Information such as material,designation,coding,no of
parts,weight,dimension of parts,geometric tolerances,size and
accuracy.
• Engineering drawing:Language of engg and
communication,orthographic projection(accurate mfg
design,2D&3D,pictorial gives more information).
Types of drawing:
• Detail drawings:single-part,collective.
• Assembly drawings:single-part,collective.
• Combined drawing.
Detail drawings:
• Provide all the information required for mfg of
product,(dimensions,tolerances,surface finish and material
specifications).
Types: single part,collective single part.
Single part drawings:
• Complete detail information single component mfg without reference
sources.shape,dimension,tolerances,size and locations,heat
treatment,surface finish.
Collective single part drawings:
• One or two dimensions of component are variable,others being
standard.
Assembly drawings:
• Machines and mechanisms consist of numerous parts and a drawing
shows complete product with all components in correct physical
relationship.
Sub-assembly drawings:
• Drawing gives small part of whole assembly.
Types:
• Single part,collective
Single part assembly drawings:
• Information to build single sub-assembly or assembly.
• Part list,quantity,overall dimensions,weight,mtrl specifications,design
data,operational details and instructions.
Collective assembly drawings:
• Range of products similar in appearances,differ in size,mfg and
assembled.
Combined detail and assembly drawings:
• Assembly with part list and details of these parts on one
drawing,small one-off reduces scheduling and printing.
INFORMATION ON THE DRAWING SHEET REQUIRED FOR
PROCESS PLANNING:(CRITICAL PROCESSING FACTORS):
• Dimensions: complete dimensions of the component design mfg.
• Functional: Influence operated part.
• Non-functional: Not influence operated part.
• Auxiliary: Not relate to operate and mfg part.
Material specifications:
• Parts evaluated,specified and manufactured.
Special material treatments:
• Material properties treated.
Tolerances,limits and fits:
• Component fit assembly,appropriate lower and upper limits.
• Accurate tolerance,cost high,good engg practice.
Dimensional tolerances:
• 10±0.02 as 9.98&10.02mm.
General tolerancing:
• Unspecified tolerances dimensions,saves time.
Limits and fits for shafts and holes:
• Basic size is shaft or hole size,limits the specified design.
• Basic hole system-basic hole size adjusts shaft size to fit.
• Basic shaft system-basic shaft size adjusts hole size to fit.
• Standard tools as drills,reamers for basic hole system.
Fit
• Tightness or looseness for application of tolerances to mating parts.
Clearance fit
• Assemble/dissemble by hand,running and sliding assemblies,low cost
to high temperature,minimum accuracy.
Transition fit
• Press tooling,close accuracy,no interference.
Interference fit
• Forced permanent assemblies,retain and locate.
Geometrical tolerancing
• Permissible variation of form,attitude.
Types:straightness,flatness,roundness,cylindricity,parallelism,squareness
angularity,concentricity,symmetry,position.
Surface finish:
• Irregularities depth of surface in mfg processes.
Form error:
• Longer wavelength deviations of surface to nominal surface,large
scale problems,errors in m/c tool ways,guides,inaccurate alignment of
w/p.
Roughness:
• Finest irregularities of surface,production process.
Waviness:
• Widely space deviations from norminal shape,m/c vibration.
• Surface texture=roughness+waviness.
• Surface roughness,surface textures(symbols), Surface
roughness,surface textures(components) used.
Material selection and evaluation:
• Component-material processing-mfg-design.
Metals and classification:
Ferrous materials:
• Materials of iron as prime constituent,steel(0.05-2%),iron(2-4.5%).
Steels:
• Alloys of iron and carbon,carbon steels and alloy steels.
• Low carbon steel 0.25%C,Medium carbon steel 0.60%C,
High carbon steel-0.60%C.
• Alloy steels-chromium,nickel,molybdenum,vanadium,tungsten,cobalt.
• Low alloy steels-3 to 4%,high alloy steels-5%(alloying elements).
• Important alloy steels-stainless steels,tool steels,HSLA
steels,maraging steels.
Cast iron:
• Ferrous alloys of iron 2 to 4.5%C,3.5% silicon.
• Grey cast iron-low cost,white cast iron-hard and brittle,malleable cast
iron-ductile,yield and tensile strength,spheroidal graphite cast iron.
Non-ferrous materials:
• Elements other than iron as chief constituent.
• Light weight,colour,ease fabrication, better resistant, electrical and
thermal conductivity.
• Important non-ferrous materials-C,Al,lead,Ni,Mg,Ti,Tn,Zn.
Polymers:
• Density, thermal and electrical insulation, resist to
chemical,fabrication,low cost.
Engineering ceramics:
• Grinding,deals,bearings,magnets,engines,pumps.
• Features-(melting temp,oxidation,corrosion,high temp).
• Alumina,SiC,Si3N4,PSZ,Sialons.
Composites:
• Composed of two or more different materials, resultant materials
superior to individual materials.
• Particle reinforced composites-Particles of one material dispersed in a
matrix of second material.
• Fibre reinforced composites-Dispersed phase as fibre.
MATERIAL SELECTION PROCESS:
• Appropriate material for product under consideration is complex task.
• Translation-design requirements as constraints,objectives,free
variables.
• Screening-constrained limits apply to subset of viable materials.
• Ranking-ordering material,excellence criteria,maximum or minimum.
• Supporting information-
top-ranked,history,behavior,availability,sufficient choice.
MATERIAL SELECTION METHODS:
• Computer aided databases,performance indices,decision
matrices,expert selection,value analysis,failure analysis,cost-benefit
analysis.
Material evaluation methods:
Shape or geometry considerations:
• Process-mfg-product.
• Size,complexity,dimensional tolerance,surface finish,wear
allowance,assembly,manufacturability.
• Material property requirements-Loading type,loading
magnitude,impact loading,cyclic loading,wear resistance,permissible
temp,material deformation.
• Physical property requirements-
electrical,magnetic,thermal,weight,aesthetic.
• Service requirements- temperatures operating,life span,most
extreme,maintanence,reliability,serviceability,recyclability.
Manufacturing considerations:
• Components,ease mfg,quantity,components rate,minimum&maximum
section thickness,quality level,inspection methods,assembly ease.
Process selection
• shaping, joining, finishing, mfg-design, size, shape and
precision,parts.
Factors
• Material form, size and weight, economic considerations, dimensional
and geometry accuracy, surface finish,batch size, production rate.
Guidelines
• Prototype validate mfg,compare mfg to assembly costs for different
processes.
Process selection methods(steps):
Mfg process,difficult,complex and systematic
Assumptions:
• Materials selected,specified.
• Design documents,information comprehensive.
Stages:
Drawing interpretation:
• Starting point for process selection.
• Material,shape,size,tolerance,roughness,process parameters.
• Three analysis and o/p-geometry analysis,mfg information,material
evaluation and o/p.
Identification of critical processing factors:
• Combined o/p from drawing interpretation analysed and correlated.
• Material-mfg-geometry.
Comparison of potential mfg processes:
• Correlate,appropriate,decision-making,economy data.
• (Labour,equipment,tooling cost,batch and production rates),costing
methods and comparisons.
Identification of suitable processes:
• Part-primary-secondary-critical processing.
Production equipment and tooling selection:
• Mfg-processes-production equipment.
Factors for equipment:
• Size,weight,physical size,construction,power and torque, no of tools,
type of tools.
• Equipment-tooling-operation.
Factors for tooling:
• Availability,w/p,type,part geometry,tool material,m/c data,m/c tool
characteristics,cutting tool materials,tool holding,quality,capability
requirements.
• Consumables tooling-cutting tools,workholding devices,jigs and
fixtures.
Factors in equipment selection:
• M/c-processes-mfg-decision making-performing.
Factors for m/c selection:
• Technical factors-physical size,m/c accuracy,surface finish,cutting
forces,power.
• Operational factors-batch size,.Capacity,availability.
Technical factors:
• M/c tool-mfg component/product, physical size,m/c accuracy,surface
finish,cutting forces,power.
Physical size:
• M/c tool-process-product-robust.
Machine accuracy:
• Capability-mfg-dimension&geometry-design.
Surface finish:Capability.
Cutting forces:Feed,speed,depth of cut,opns of m/c tool.
Machine power:Power=cutting forcexcutting speed.
Operational factors: Availability,cost effective,master production
schedule.[Important-batch size,capacity,availability].
Batch size: EBQ calculated,potential economical m/c tool.
Capacity:Production rate,acheives o/p,mps.
Availability:Proportion,performance,efficiency,reliability,
Availability.
Machine selection methods(steps):
First cut selection: Identify,specify,select mfg processes,physical
size,type of machine.
Power/force analysis: Specify.
Capability analysis: Dimensional,geometry accuracy,surface finish,m/c
short listings.
Final selection: More than 1 machine.
Factors in tooling selection:
• Constraints on tool selection- Mfg practice,mfg process,m/c tool
characteristics,capability,processing time, cutting tool availability.
• Operating requirements on tool selection-W/p material,operation,part
geometry, tooling data.
• Tooling performance affecting factors-Cutting tool materials, cutting
tool geometry, cutting fluids.
Constraints on tool selection- Mfg practice,mfg process,m/c tool
characteristics,capability,processing time, cutting tool availability.
Manufacturing practice:
• Tool actually fed to workpiece.
• Two categories(continuous cutting,intermittent cutting).
• Continuous cutting-cutting tool is continuously fed to w/p.
• Intermittent cutting-cutting tool not continuously fed to w/p.
Manufacturing process:
• M/c tools limit the selection of tooling.
M/c tool characteristics:
Work holding devices,Tool structure,Power o/p,
Feed and speed of m/c.
Capability:
• Dimensional and geometric accuracy,surface finish.
Machining time:
• Power,feed,speed,m/c,tooling.
Cutting tool availability:
• Selecting the available tools.
Tool selection operating requirements-W/p materials,operation,part
geometry,tooling data.
Workpiece material:
• Heat generation,cutting tool geometry material.
Operation:
• Specific cutting tool.
Part geometry:
• Specific geometry feature.
Tooling data:
• Mfg tooling data,suitable tools,specified operations.
Tooling performance factors- cutting tool materials,cutting tool
geometry,cutting fluids.
Cutting tool materials:
• Tool performance,hss,carbides,cast non-ferrous alloys,ceramics.
Cutting tool geometry:
• Tool angles,rake angles,cutting edge angles,tool nose radius.
• Influences w/p material and tool material.
Cutting fluids usage:
• Cools w/p,tool temperature,maintains hardness,avoid distortion.
• Friction b/w tool and w/p,wear resistance of tool,improves tool
performance.
INTRODUCTION TO PROCESS PLANNING
INTRODUCTION TO PROCESS PLANNING

More Related Content

What's hot

MANUFACTURING TECHNOLOGY-II
MANUFACTURING TECHNOLOGY-II MANUFACTURING TECHNOLOGY-II
MANUFACTURING TECHNOLOGY-II S. Sathishkumar
 
Process Planning & Cost Estimation
Process Planning & Cost Estimation Process Planning & Cost Estimation
Process Planning & Cost Estimation Prabhu Bose
 
Lecture # 09 Coordinate Measuring Machine (CMM)
Lecture # 09 Coordinate Measuring  Machine (CMM)Lecture # 09 Coordinate Measuring  Machine (CMM)
Lecture # 09 Coordinate Measuring Machine (CMM)Solomon Tekeste
 
Interchangeability & selective assembly
Interchangeability & selective assemblyInterchangeability & selective assembly
Interchangeability & selective assemblyKumar Chirra
 
Computer Aided Process Planning (CAPP)
Computer Aided Process Planning (CAPP)Computer Aided Process Planning (CAPP)
Computer Aided Process Planning (CAPP)Pratik Gandhi
 
GROUP TECHNOLOGY AND CAPP
GROUP TECHNOLOGY AND CAPPGROUP TECHNOLOGY AND CAPP
GROUP TECHNOLOGY AND CAPPmanimaran m
 
Group technology
Group technologyGroup technology
Group technologyjntuhcej
 
Design of Stage Progressive Die for a Sheet Metal Component
Design of Stage Progressive Die for a Sheet Metal Component Design of Stage Progressive Die for a Sheet Metal Component
Design of Stage Progressive Die for a Sheet Metal Component STAY CURIOUS
 
COMPUTER AIDED PROCESS PLANNING
COMPUTER AIDED PROCESS PLANNINGCOMPUTER AIDED PROCESS PLANNING
COMPUTER AIDED PROCESS PLANNINGjntuhcej
 
Chapter 3 CNC turning and machining centers
Chapter 3 CNC turning and machining centersChapter 3 CNC turning and machining centers
Chapter 3 CNC turning and machining centersRAHUL THAKER
 
COORDINATE MEASURING MACHINE
COORDINATE MEASURING MACHINECOORDINATE MEASURING MACHINE
COORDINATE MEASURING MACHINEarunkumar6836
 
Automatically programmed tool (ATP)
Automatically programmed  tool (ATP)Automatically programmed  tool (ATP)
Automatically programmed tool (ATP)Manoj Gowda K
 

What's hot (20)

Jigs and Fixture
Jigs and FixtureJigs and Fixture
Jigs and Fixture
 
MANUFACTURING TECHNOLOGY-II
MANUFACTURING TECHNOLOGY-II MANUFACTURING TECHNOLOGY-II
MANUFACTURING TECHNOLOGY-II
 
Process Planning & Cost Estimation
Process Planning & Cost Estimation Process Planning & Cost Estimation
Process Planning & Cost Estimation
 
Press work
Press workPress work
Press work
 
final project
final projectfinal project
final project
 
3 numerical control
3 numerical control3 numerical control
3 numerical control
 
Lecture # 09 Coordinate Measuring Machine (CMM)
Lecture # 09 Coordinate Measuring  Machine (CMM)Lecture # 09 Coordinate Measuring  Machine (CMM)
Lecture # 09 Coordinate Measuring Machine (CMM)
 
Tool wear and tool Life
Tool wear and tool LifeTool wear and tool Life
Tool wear and tool Life
 
3.cutting tools nomenclature
3.cutting tools nomenclature3.cutting tools nomenclature
3.cutting tools nomenclature
 
Interchangeability & selective assembly
Interchangeability & selective assemblyInterchangeability & selective assembly
Interchangeability & selective assembly
 
Computer Aided Process Planning (CAPP)
Computer Aided Process Planning (CAPP)Computer Aided Process Planning (CAPP)
Computer Aided Process Planning (CAPP)
 
GROUP TECHNOLOGY AND CAPP
GROUP TECHNOLOGY AND CAPPGROUP TECHNOLOGY AND CAPP
GROUP TECHNOLOGY AND CAPP
 
Group technology
Group technologyGroup technology
Group technology
 
Cutting tools
Cutting tools Cutting tools
Cutting tools
 
Design of Stage Progressive Die for a Sheet Metal Component
Design of Stage Progressive Die for a Sheet Metal Component Design of Stage Progressive Die for a Sheet Metal Component
Design of Stage Progressive Die for a Sheet Metal Component
 
COMPUTER AIDED PROCESS PLANNING
COMPUTER AIDED PROCESS PLANNINGCOMPUTER AIDED PROCESS PLANNING
COMPUTER AIDED PROCESS PLANNING
 
Drill bushes
Drill bushesDrill bushes
Drill bushes
 
Chapter 3 CNC turning and machining centers
Chapter 3 CNC turning and machining centersChapter 3 CNC turning and machining centers
Chapter 3 CNC turning and machining centers
 
COORDINATE MEASURING MACHINE
COORDINATE MEASURING MACHINECOORDINATE MEASURING MACHINE
COORDINATE MEASURING MACHINE
 
Automatically programmed tool (ATP)
Automatically programmed  tool (ATP)Automatically programmed  tool (ATP)
Automatically programmed tool (ATP)
 

Similar to INTRODUCTION TO PROCESS PLANNING

INTELLIGENT DECISION MAKING FOR REACTIVE SCHEDULING IN FMS
INTELLIGENT DECISION MAKING FOR REACTIVE SCHEDULING IN FMSINTELLIGENT DECISION MAKING FOR REACTIVE SCHEDULING IN FMS
INTELLIGENT DECISION MAKING FOR REACTIVE SCHEDULING IN FMSJyotiraman De
 
Cim presentation (1)
Cim presentation (1)Cim presentation (1)
Cim presentation (1)rajnitj19
 
1-unit(Introduction to process planning)-converted.docx
1-unit(Introduction to process planning)-converted.docx1-unit(Introduction to process planning)-converted.docx
1-unit(Introduction to process planning)-converted.docxprabaharjeevanananda
 
Unit ii Process Planning
Unit ii Process PlanningUnit ii Process Planning
Unit ii Process PlanningAsha A
 
Process Planning
Process PlanningProcess Planning
Process PlanningGuhan M
 
Chapter 7 automation techniques
Chapter 7  automation techniquesChapter 7  automation techniques
Chapter 7 automation techniquesMohamad Sahiedan
 
CADCAM CAE Notes
CADCAM CAE NotesCADCAM CAE Notes
CADCAM CAE NotesAbhay Gore
 
TMA Module 2........................................................
TMA Module 2........................................................TMA Module 2........................................................
TMA Module 2........................................................4PS19AU411SyedaSoubi
 
Production Planning & Control Book
Production Planning & Control BookProduction Planning & Control Book
Production Planning & Control BookLearn With GeekAlign
 
Group Technology
Group TechnologyGroup Technology
Group Technologysgrsoni45
 
Computer aided process planning
Computer aided process planningComputer aided process planning
Computer aided process planningsushma chinta
 
Production Planning & Control
Production Planning & ControlProduction Planning & Control
Production Planning & ControlKunalJagtap5
 
Introduction to Production Planning and control.
Introduction to Production Planning and control.Introduction to Production Planning and control.
Introduction to Production Planning and control.PraveenManickam2
 
Optimizing Parameters
Optimizing ParametersOptimizing Parameters
Optimizing ParametersAlan Smith
 
Computer Aided Design - Unit I Introduction
Computer Aided Design - Unit I IntroductionComputer Aided Design - Unit I Introduction
Computer Aided Design - Unit I IntroductionJayavendhanJ
 
PPCE Unit-2.pptx
PPCE Unit-2.pptxPPCE Unit-2.pptx
PPCE Unit-2.pptxDJAGADEESH1
 

Similar to INTRODUCTION TO PROCESS PLANNING (20)

INTELLIGENT DECISION MAKING FOR REACTIVE SCHEDULING IN FMS
INTELLIGENT DECISION MAKING FOR REACTIVE SCHEDULING IN FMSINTELLIGENT DECISION MAKING FOR REACTIVE SCHEDULING IN FMS
INTELLIGENT DECISION MAKING FOR REACTIVE SCHEDULING IN FMS
 
Cim presentation (1)
Cim presentation (1)Cim presentation (1)
Cim presentation (1)
 
1-unit(Introduction to process planning)-converted.docx
1-unit(Introduction to process planning)-converted.docx1-unit(Introduction to process planning)-converted.docx
1-unit(Introduction to process planning)-converted.docx
 
Unit ii Process Planning
Unit ii Process PlanningUnit ii Process Planning
Unit ii Process Planning
 
Process Planning
Process PlanningProcess Planning
Process Planning
 
Chapter 7 automation techniques
Chapter 7  automation techniquesChapter 7  automation techniques
Chapter 7 automation techniques
 
CADCAM CAE Notes
CADCAM CAE NotesCADCAM CAE Notes
CADCAM CAE Notes
 
TMA Module 2........................................................
TMA Module 2........................................................TMA Module 2........................................................
TMA Module 2........................................................
 
Production Planning & Control Book
Production Planning & Control BookProduction Planning & Control Book
Production Planning & Control Book
 
Group Technology
Group TechnologyGroup Technology
Group Technology
 
Computer aided process planning
Computer aided process planningComputer aided process planning
Computer aided process planning
 
Production Planning & Control
Production Planning & ControlProduction Planning & Control
Production Planning & Control
 
Introduction to Production Planning and control.
Introduction to Production Planning and control.Introduction to Production Planning and control.
Introduction to Production Planning and control.
 
TEST 2.pptx
TEST 2.pptxTEST 2.pptx
TEST 2.pptx
 
TEST 2.pdf
TEST 2.pdfTEST 2.pdf
TEST 2.pdf
 
Processs planning
Processs planningProcesss planning
Processs planning
 
Optimizing Parameters
Optimizing ParametersOptimizing Parameters
Optimizing Parameters
 
Computer Aided Design - Unit I Introduction
Computer Aided Design - Unit I IntroductionComputer Aided Design - Unit I Introduction
Computer Aided Design - Unit I Introduction
 
PPCE Unit-2.pptx
PPCE Unit-2.pptxPPCE Unit-2.pptx
PPCE Unit-2.pptx
 
PPCE Unit-2.pptx
PPCE Unit-2.pptxPPCE Unit-2.pptx
PPCE Unit-2.pptx
 

More from SathishkumarM89

UNIT-V- SLUDGE TREATMENT AND DISPOSAL.pptx
UNIT-V- SLUDGE TREATMENT AND DISPOSAL.pptxUNIT-V- SLUDGE TREATMENT AND DISPOSAL.pptx
UNIT-V- SLUDGE TREATMENT AND DISPOSAL.pptxSathishkumarM89
 
UNIT-1-INTRODUCTION.pptx
UNIT-1-INTRODUCTION.pptxUNIT-1-INTRODUCTION.pptx
UNIT-1-INTRODUCTION.pptxSathishkumarM89
 
UNIT-II-WASTE WATER TREATMENT PROCESSES.pptx
UNIT-II-WASTE WATER TREATMENT PROCESSES.pptxUNIT-II-WASTE WATER TREATMENT PROCESSES.pptx
UNIT-II-WASTE WATER TREATMENT PROCESSES.pptxSathishkumarM89
 
UNIT-IV-BIOLOGICAL WASTE WATER TREATMENT PROCESS.pptx
UNIT-IV-BIOLOGICAL WASTE WATER TREATMENT PROCESS.pptxUNIT-IV-BIOLOGICAL WASTE WATER TREATMENT PROCESS.pptx
UNIT-IV-BIOLOGICAL WASTE WATER TREATMENT PROCESS.pptxSathishkumarM89
 
UNIT-III-POLLUTION FROM MAJOR INDUSTRIES.pptx
UNIT-III-POLLUTION FROM MAJOR INDUSTRIES.pptxUNIT-III-POLLUTION FROM MAJOR INDUSTRIES.pptx
UNIT-III-POLLUTION FROM MAJOR INDUSTRIES.pptxSathishkumarM89
 
Unit 1--VEHICLE STRUCTURE AND ENGINES
Unit 1--VEHICLE STRUCTURE AND ENGINESUnit 1--VEHICLE STRUCTURE AND ENGINES
Unit 1--VEHICLE STRUCTURE AND ENGINESSathishkumarM89
 
Unit ii engine auxiliary systems
Unit ii engine auxiliary systemsUnit ii engine auxiliary systems
Unit ii engine auxiliary systemsSathishkumarM89
 
Unit--v---ALTERNATIVE FUELS
Unit--v---ALTERNATIVE FUELS   Unit--v---ALTERNATIVE FUELS
Unit--v---ALTERNATIVE FUELS SathishkumarM89
 
Unit iii--TRANSMISSION SYSTEMS
Unit iii--TRANSMISSION SYSTEMSUnit iii--TRANSMISSION SYSTEMS
Unit iii--TRANSMISSION SYSTEMSSathishkumarM89
 
STEADY STRESSES AND VARIABLE STRESSES IN MACHINE MEMBERS
STEADY STRESSES AND VARIABLE STRESSES IN MACHINE MEMBERSSTEADY STRESSES AND VARIABLE STRESSES IN MACHINE MEMBERS
STEADY STRESSES AND VARIABLE STRESSES IN MACHINE MEMBERSSathishkumarM89
 
MACHINING TIME CALCULATION
MACHINING TIME CALCULATIONMACHINING TIME CALCULATION
MACHINING TIME CALCULATIONSathishkumarM89
 
PRODUCTION COST ESTIMATION
PRODUCTION COST ESTIMATIONPRODUCTION COST ESTIMATION
PRODUCTION COST ESTIMATIONSathishkumarM89
 
INTRODUCTION TO COST ESTIMATION
INTRODUCTION TO COST ESTIMATIONINTRODUCTION TO COST ESTIMATION
INTRODUCTION TO COST ESTIMATIONSathishkumarM89
 
INTRODUCTION TO PROCESS PLANNING
INTRODUCTION TO PROCESS PLANNINGINTRODUCTION TO PROCESS PLANNING
INTRODUCTION TO PROCESS PLANNINGSathishkumarM89
 
PROCESS PLANNING ACTIVITIES
PROCESS PLANNING ACTIVITIESPROCESS PLANNING ACTIVITIES
PROCESS PLANNING ACTIVITIESSathishkumarM89
 

More from SathishkumarM89 (19)

UNIT-V- SLUDGE TREATMENT AND DISPOSAL.pptx
UNIT-V- SLUDGE TREATMENT AND DISPOSAL.pptxUNIT-V- SLUDGE TREATMENT AND DISPOSAL.pptx
UNIT-V- SLUDGE TREATMENT AND DISPOSAL.pptx
 
UNIT-1-INTRODUCTION.pptx
UNIT-1-INTRODUCTION.pptxUNIT-1-INTRODUCTION.pptx
UNIT-1-INTRODUCTION.pptx
 
UNIT-II-WASTE WATER TREATMENT PROCESSES.pptx
UNIT-II-WASTE WATER TREATMENT PROCESSES.pptxUNIT-II-WASTE WATER TREATMENT PROCESSES.pptx
UNIT-II-WASTE WATER TREATMENT PROCESSES.pptx
 
UNIT-IV-BIOLOGICAL WASTE WATER TREATMENT PROCESS.pptx
UNIT-IV-BIOLOGICAL WASTE WATER TREATMENT PROCESS.pptxUNIT-IV-BIOLOGICAL WASTE WATER TREATMENT PROCESS.pptx
UNIT-IV-BIOLOGICAL WASTE WATER TREATMENT PROCESS.pptx
 
UNIT-III-POLLUTION FROM MAJOR INDUSTRIES.pptx
UNIT-III-POLLUTION FROM MAJOR INDUSTRIES.pptxUNIT-III-POLLUTION FROM MAJOR INDUSTRIES.pptx
UNIT-III-POLLUTION FROM MAJOR INDUSTRIES.pptx
 
Unit 1--VEHICLE STRUCTURE AND ENGINES
Unit 1--VEHICLE STRUCTURE AND ENGINESUnit 1--VEHICLE STRUCTURE AND ENGINES
Unit 1--VEHICLE STRUCTURE AND ENGINES
 
Unit ii engine auxiliary systems
Unit ii engine auxiliary systemsUnit ii engine auxiliary systems
Unit ii engine auxiliary systems
 
Unit--v---ALTERNATIVE FUELS
Unit--v---ALTERNATIVE FUELS   Unit--v---ALTERNATIVE FUELS
Unit--v---ALTERNATIVE FUELS
 
Unit iii--TRANSMISSION SYSTEMS
Unit iii--TRANSMISSION SYSTEMSUnit iii--TRANSMISSION SYSTEMS
Unit iii--TRANSMISSION SYSTEMS
 
Knuckle joint
Knuckle jointKnuckle joint
Knuckle joint
 
Coupling
CouplingCoupling
Coupling
 
Bearings
BearingsBearings
Bearings
 
Springs
SpringsSprings
Springs
 
STEADY STRESSES AND VARIABLE STRESSES IN MACHINE MEMBERS
STEADY STRESSES AND VARIABLE STRESSES IN MACHINE MEMBERSSTEADY STRESSES AND VARIABLE STRESSES IN MACHINE MEMBERS
STEADY STRESSES AND VARIABLE STRESSES IN MACHINE MEMBERS
 
MACHINING TIME CALCULATION
MACHINING TIME CALCULATIONMACHINING TIME CALCULATION
MACHINING TIME CALCULATION
 
PRODUCTION COST ESTIMATION
PRODUCTION COST ESTIMATIONPRODUCTION COST ESTIMATION
PRODUCTION COST ESTIMATION
 
INTRODUCTION TO COST ESTIMATION
INTRODUCTION TO COST ESTIMATIONINTRODUCTION TO COST ESTIMATION
INTRODUCTION TO COST ESTIMATION
 
INTRODUCTION TO PROCESS PLANNING
INTRODUCTION TO PROCESS PLANNINGINTRODUCTION TO PROCESS PLANNING
INTRODUCTION TO PROCESS PLANNING
 
PROCESS PLANNING ACTIVITIES
PROCESS PLANNING ACTIVITIESPROCESS PLANNING ACTIVITIES
PROCESS PLANNING ACTIVITIES
 

Recently uploaded

APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .Satyam Kumar
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfme23b1001
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 

Recently uploaded (20)

APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdf
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 

INTRODUCTION TO PROCESS PLANNING

  • 3. PROCESS PLANNING DEFINITION: • Set of instructions describes mfg product and its parts. • Operations planning as systematic determination of engg processes and systems to mfg a product competitively and economically. • Prepare work instructions for mfg and assembly of components to product in discrete mfg environments. • Systematic determination of methods products to be mfg,economically and competitively. • Consists of selection of mfg processes and operations,production equipment,tooling and jigs and fixtures,
  • 4. • Determination of mfg parameters,specify selection criteria for quality assurance ensure product quality. IMPORTANCE OF PROCESS PLANNING: • Link between engg design and shop floor mfg,product is how mfg,production costs and profitability,indepth of knowledge, equipment capabilities, tooling availability, material processing characteristics, shop practices. PRODUCT DESIGN AND MFG CYCLE: • Intermediate stage b/w designing the product and mfg. • Three main functions marketing and sales,design,mfg.
  • 5.
  • 6. PROCESS PLANNING: LINK B/W DESIGN AND MFG: • Cross functional teams are employed to design and mfg functions,known as simultaneous or concurrent engg.
  • 7.
  • 8. RESPOSIBILITIES OF PROCESS PLANNING ENGINEER: • Part print analysis and symbols. • Fundamentals of product design(rough stock, production rate,finish,dimensional tolerances). • Machining processes(setup time,quality,type and cost of tooling). • Operations sequence,inspect the equipment,production tolerances,cutting tools and cutting conditions,overall time by work measurement techniques.
  • 9.
  • 10.
  • 11.
  • 12.
  • 13.
  • 14. PROCESS PLANNING ACTIVITIES: Drawing interpretation: • Analyse finished part in engineering design.component drawings(features,dimensions,geometric tolerances,surface finish,material specification,part required). Material evaluation and process selection: • (Function,appearance,reliability,life,environment,compatibility,produc tivity,cost).Evaluate the materials, (features,dimensions,geometric tolerances transform rough state to finished state).Process evolution(rough to finished).Part evolution(final state to initial state).
  • 15. Selection of m/c,tooling,workholding devices: • Economic considerations,production rate per unit cost,durability and dependability,lower process rejection,minimum setup times,long life of m/c,functional versatility.best m/c,make or buy,BEA . Selecting process parameters: • Machines selected,calculating operation setup time and cycle time,tooling sequence,equipment capability,shop practice. • Calculation of part processing time requires determination of sequence of processing steps on each m/c as outplanning. • Part loading,unloading,m/c indexing for 1 cycle. • M/c cycle time allowances added to standard cycle time.Calculate cycle time & m/c rates to find out cost.
  • 16. Selecting quality assurance methods: • Inspection criterias(dimensional,geometric,surface finish),tools and techniques,increases costs&time. Cost estimating: • Process of determining the probable cost of product before manufacture. • Material,labour,overhead costs-profit. • Material,mfg processes,batch size,make or buy.
  • 17. Process planning documentation: • Document clearly all the detail information. • Documented as job routing or operating sheet. • Production operations&associated m/c tools for component and subassembly. • Route sheet information as part identification,processing,operation of m/c,std times,setup cycle times,tooling requirements,production control information shows planning lead time operation. • Reasons: part process-design,job quote,cost estimate,std cost systems,communication vehicle.
  • 18. Communicate process knowledge: • Mfg to shop floor,economy,consistent quality. Inputs and outputs of process planning: • Route sheet and operation sheet as single sheet.
  • 19. PROCESS PLANNING METHODS(APPROACHES TO PROCESS PLANNING): • Manual process planning(traditional,workbook approaches). • Computer aided process planning(retrieval,generative). Manual process planning: Traditional approach: • Process plan prepared manually. • Examine and interpret eg,m/c process,equipment selection,opns sequence,shop practices,skill,judgement and experience,different planners. • Product opns,manual tools(feed,speed,setup time,opns time),documented as routing sheet.
  • 20. Workbook approach: • Modified version uses developed workbook prepares route sheet.opns sequence of products the drawing interpretation is carried by workbook. Uses of manual approach: • Small scale companies,flexible,low investments. Drawbacks of manual approach: • Complex,time&data high,skill process,human error,skill,judgement and experience,increases paper work,productivity down,no response to mfg environment,process,tool,materials… Computer aided process planning: • Computers reduces clerical works,rational,consistent and optimal plans,interface between cad and cam.
  • 21. Benefits of capp: • Process rationalization and standardization,productivity improvement,product cost reduction,eliminate human error,time reduction,reduces clerical and paper work,legibility improves,fast response to engg changes,incorporation of application programs. Retrieval or variant capp systems: • Widely used in machining applications,similar parts have similar plans,new part recalls,identifies,retrieves existing plan for similar modified new parts. Benefits of retrieval capp systems: • Standard plan,variety of parts,simple programming and installation,understandable,easy to learn and use. Drawbacks of retrieval capp systems: • Planned components limited to previous planned. • Experiences modify standard plan.
  • 22. Generative capp systems: • Computers synthesize individual process plan automatically w ith or without reference to prior plan. • Decision logics and precoded algorithms,mfg using equipment,specific process plan for specific part. • Inputting GT code as part design,monitoring the functions. Components: • Part description,subsystem define m/c parameters&select and sequence individual operations,database,report generators. Advantages of generative capp: • Consistent process plan,new components,integrating automated mfg facility provides detailed control information. Drawbacks of generative capp: • Complex and very difficult
  • 23.
  • 24.
  • 25. SELECTION OF PROCESS PLANNING SYSTEM: • Numerous engg management decisions,identify,weight and compare interrelated factors. • Best process plan-general environment,organisational structure,technical expertise,needs and objectives of MIS.
  • 26.
  • 27.
  • 28.
  • 29.
  • 30. DRAWING INTERPRETATION: • Prepares process plan for product,functional requirements of design,assembled with dimensions and tolerances. • Information such as material,designation,coding,no of parts,weight,dimension of parts,geometric tolerances,size and accuracy. • Engineering drawing:Language of engg and communication,orthographic projection(accurate mfg design,2D&3D,pictorial gives more information). Types of drawing: • Detail drawings:single-part,collective. • Assembly drawings:single-part,collective. • Combined drawing. Detail drawings: • Provide all the information required for mfg of product,(dimensions,tolerances,surface finish and material specifications).
  • 31. Types: single part,collective single part. Single part drawings: • Complete detail information single component mfg without reference sources.shape,dimension,tolerances,size and locations,heat treatment,surface finish. Collective single part drawings: • One or two dimensions of component are variable,others being standard. Assembly drawings: • Machines and mechanisms consist of numerous parts and a drawing shows complete product with all components in correct physical relationship. Sub-assembly drawings: • Drawing gives small part of whole assembly. Types: • Single part,collective
  • 32. Single part assembly drawings: • Information to build single sub-assembly or assembly. • Part list,quantity,overall dimensions,weight,mtrl specifications,design data,operational details and instructions. Collective assembly drawings: • Range of products similar in appearances,differ in size,mfg and assembled. Combined detail and assembly drawings: • Assembly with part list and details of these parts on one drawing,small one-off reduces scheduling and printing. INFORMATION ON THE DRAWING SHEET REQUIRED FOR PROCESS PLANNING:(CRITICAL PROCESSING FACTORS): • Dimensions: complete dimensions of the component design mfg. • Functional: Influence operated part. • Non-functional: Not influence operated part. • Auxiliary: Not relate to operate and mfg part.
  • 33. Material specifications: • Parts evaluated,specified and manufactured. Special material treatments: • Material properties treated. Tolerances,limits and fits: • Component fit assembly,appropriate lower and upper limits. • Accurate tolerance,cost high,good engg practice. Dimensional tolerances: • 10±0.02 as 9.98&10.02mm. General tolerancing: • Unspecified tolerances dimensions,saves time. Limits and fits for shafts and holes: • Basic size is shaft or hole size,limits the specified design. • Basic hole system-basic hole size adjusts shaft size to fit. • Basic shaft system-basic shaft size adjusts hole size to fit.
  • 34. • Standard tools as drills,reamers for basic hole system. Fit • Tightness or looseness for application of tolerances to mating parts. Clearance fit • Assemble/dissemble by hand,running and sliding assemblies,low cost to high temperature,minimum accuracy. Transition fit • Press tooling,close accuracy,no interference. Interference fit • Forced permanent assemblies,retain and locate. Geometrical tolerancing • Permissible variation of form,attitude. Types:straightness,flatness,roundness,cylindricity,parallelism,squareness angularity,concentricity,symmetry,position.
  • 35. Surface finish: • Irregularities depth of surface in mfg processes. Form error: • Longer wavelength deviations of surface to nominal surface,large scale problems,errors in m/c tool ways,guides,inaccurate alignment of w/p. Roughness: • Finest irregularities of surface,production process. Waviness: • Widely space deviations from norminal shape,m/c vibration. • Surface texture=roughness+waviness. • Surface roughness,surface textures(symbols), Surface roughness,surface textures(components) used.
  • 36.
  • 37.
  • 38.
  • 39.
  • 40.
  • 41. Material selection and evaluation: • Component-material processing-mfg-design. Metals and classification: Ferrous materials: • Materials of iron as prime constituent,steel(0.05-2%),iron(2-4.5%). Steels: • Alloys of iron and carbon,carbon steels and alloy steels. • Low carbon steel 0.25%C,Medium carbon steel 0.60%C, High carbon steel-0.60%C. • Alloy steels-chromium,nickel,molybdenum,vanadium,tungsten,cobalt. • Low alloy steels-3 to 4%,high alloy steels-5%(alloying elements). • Important alloy steels-stainless steels,tool steels,HSLA steels,maraging steels. Cast iron: • Ferrous alloys of iron 2 to 4.5%C,3.5% silicon.
  • 42. • Grey cast iron-low cost,white cast iron-hard and brittle,malleable cast iron-ductile,yield and tensile strength,spheroidal graphite cast iron. Non-ferrous materials: • Elements other than iron as chief constituent. • Light weight,colour,ease fabrication, better resistant, electrical and thermal conductivity. • Important non-ferrous materials-C,Al,lead,Ni,Mg,Ti,Tn,Zn. Polymers: • Density, thermal and electrical insulation, resist to chemical,fabrication,low cost. Engineering ceramics: • Grinding,deals,bearings,magnets,engines,pumps. • Features-(melting temp,oxidation,corrosion,high temp). • Alumina,SiC,Si3N4,PSZ,Sialons.
  • 43. Composites: • Composed of two or more different materials, resultant materials superior to individual materials. • Particle reinforced composites-Particles of one material dispersed in a matrix of second material. • Fibre reinforced composites-Dispersed phase as fibre.
  • 44.
  • 45. MATERIAL SELECTION PROCESS: • Appropriate material for product under consideration is complex task. • Translation-design requirements as constraints,objectives,free variables. • Screening-constrained limits apply to subset of viable materials. • Ranking-ordering material,excellence criteria,maximum or minimum. • Supporting information- top-ranked,history,behavior,availability,sufficient choice. MATERIAL SELECTION METHODS: • Computer aided databases,performance indices,decision matrices,expert selection,value analysis,failure analysis,cost-benefit analysis.
  • 46.
  • 47. Material evaluation methods: Shape or geometry considerations: • Process-mfg-product. • Size,complexity,dimensional tolerance,surface finish,wear allowance,assembly,manufacturability. • Material property requirements-Loading type,loading magnitude,impact loading,cyclic loading,wear resistance,permissible temp,material deformation. • Physical property requirements- electrical,magnetic,thermal,weight,aesthetic. • Service requirements- temperatures operating,life span,most extreme,maintanence,reliability,serviceability,recyclability. Manufacturing considerations: • Components,ease mfg,quantity,components rate,minimum&maximum section thickness,quality level,inspection methods,assembly ease.
  • 48.
  • 49. Process selection • shaping, joining, finishing, mfg-design, size, shape and precision,parts. Factors • Material form, size and weight, economic considerations, dimensional and geometry accuracy, surface finish,batch size, production rate. Guidelines • Prototype validate mfg,compare mfg to assembly costs for different processes.
  • 50.
  • 51.
  • 52.
  • 53.
  • 54. Process selection methods(steps): Mfg process,difficult,complex and systematic Assumptions: • Materials selected,specified. • Design documents,information comprehensive. Stages: Drawing interpretation: • Starting point for process selection. • Material,shape,size,tolerance,roughness,process parameters. • Three analysis and o/p-geometry analysis,mfg information,material evaluation and o/p. Identification of critical processing factors: • Combined o/p from drawing interpretation analysed and correlated. • Material-mfg-geometry. Comparison of potential mfg processes:
  • 55. • Correlate,appropriate,decision-making,economy data. • (Labour,equipment,tooling cost,batch and production rates),costing methods and comparisons. Identification of suitable processes: • Part-primary-secondary-critical processing. Production equipment and tooling selection: • Mfg-processes-production equipment. Factors for equipment: • Size,weight,physical size,construction,power and torque, no of tools, type of tools. • Equipment-tooling-operation. Factors for tooling: • Availability,w/p,type,part geometry,tool material,m/c data,m/c tool characteristics,cutting tool materials,tool holding,quality,capability requirements.
  • 56. • Consumables tooling-cutting tools,workholding devices,jigs and fixtures. Factors in equipment selection: • M/c-processes-mfg-decision making-performing. Factors for m/c selection: • Technical factors-physical size,m/c accuracy,surface finish,cutting forces,power. • Operational factors-batch size,.Capacity,availability. Technical factors: • M/c tool-mfg component/product, physical size,m/c accuracy,surface finish,cutting forces,power. Physical size: • M/c tool-process-product-robust. Machine accuracy: • Capability-mfg-dimension&geometry-design.
  • 57. Surface finish:Capability. Cutting forces:Feed,speed,depth of cut,opns of m/c tool. Machine power:Power=cutting forcexcutting speed. Operational factors: Availability,cost effective,master production schedule.[Important-batch size,capacity,availability]. Batch size: EBQ calculated,potential economical m/c tool. Capacity:Production rate,acheives o/p,mps. Availability:Proportion,performance,efficiency,reliability, Availability.
  • 58.
  • 59. Machine selection methods(steps): First cut selection: Identify,specify,select mfg processes,physical size,type of machine. Power/force analysis: Specify. Capability analysis: Dimensional,geometry accuracy,surface finish,m/c short listings. Final selection: More than 1 machine.
  • 60.
  • 61. Factors in tooling selection: • Constraints on tool selection- Mfg practice,mfg process,m/c tool characteristics,capability,processing time, cutting tool availability. • Operating requirements on tool selection-W/p material,operation,part geometry, tooling data. • Tooling performance affecting factors-Cutting tool materials, cutting tool geometry, cutting fluids. Constraints on tool selection- Mfg practice,mfg process,m/c tool characteristics,capability,processing time, cutting tool availability. Manufacturing practice: • Tool actually fed to workpiece. • Two categories(continuous cutting,intermittent cutting). • Continuous cutting-cutting tool is continuously fed to w/p. • Intermittent cutting-cutting tool not continuously fed to w/p. Manufacturing process: • M/c tools limit the selection of tooling.
  • 62. M/c tool characteristics: Work holding devices,Tool structure,Power o/p, Feed and speed of m/c. Capability: • Dimensional and geometric accuracy,surface finish. Machining time: • Power,feed,speed,m/c,tooling. Cutting tool availability: • Selecting the available tools. Tool selection operating requirements-W/p materials,operation,part geometry,tooling data. Workpiece material: • Heat generation,cutting tool geometry material. Operation: • Specific cutting tool.
  • 63. Part geometry: • Specific geometry feature. Tooling data: • Mfg tooling data,suitable tools,specified operations. Tooling performance factors- cutting tool materials,cutting tool geometry,cutting fluids. Cutting tool materials: • Tool performance,hss,carbides,cast non-ferrous alloys,ceramics. Cutting tool geometry: • Tool angles,rake angles,cutting edge angles,tool nose radius. • Influences w/p material and tool material. Cutting fluids usage: • Cools w/p,tool temperature,maintains hardness,avoid distortion. • Friction b/w tool and w/p,wear resistance of tool,improves tool performance.