SlideShare a Scribd company logo
1 of 57
Process
Engineering
IE550 -- Manufacturing Systems
Fall 2008
Chapter 6. PROCESS
ENGINEERING
• Process planning is also called: manufacturing planning, process
planning, material processing, process engineering, and machine
routing.
• Which machining processes and parameters are to be used (as well as
those machines capable of performing these processes) to convert
(machine) a piece part from its initial form to a final form predetermined
(usually by a design engineer) from an engineering drawing.
• The act of preparing detailed work instructions to produce a part.
• How to realize a given product design.
PRODUCT
REALIZATION
Product design
Process planning
Operation programming
Verification
Scheduling
Execution
Process,
machine
knowledge
Scheduling
knowledge
PROCESS
PLANNING
Design Machine
Tool
Scheduling and Production Control
Process
Planning
PROBLEMS FACING
MANUFACTURING INDUSTRY
Fact:
Only 11% of the machine tools in the U.S. are
programmable.
More than 53% of the metal-working plants in the
U.S. do not have even one computer-controlled
machine.
Potential benefits in reducing turnaround time by using
programmable machine tools have not been realized due to time,
complexity and costs of planning and programming.
DOMAIN
One-of-a-kind and Small batch
Objectives: Lead-time, Cost
Approaches: process selection, use
existing facilities.
Mass production
Objective: Cost
Approaches: process design, optimization,
materials selection, facilities
design
How do we process
engineer?
 How can we make it?
 How much does it cost?
 How long will it take us to complete it?
 How reliable will it be?
 How can we recycle it
How can we make
it?
 Is this like something else that we’ve done?
 Yes; What methods were used?
 No; Design a new process
What methods were
used?
 Machining methods
 Pressworking
 Welding/fabrication
 Casting
 Powder materials
 Layered deposition
 Others
Welding/fabrication
:
Additive
techniques
Initial
Stock
Weld
Add-on
Weld
Add-on
Final Product
Machining Methods:
Subtractive
techniques
Initial
Stock
Slotting Drilling
Final Product
Casting:
Form
Methods
ENGINEERING DESIGN
MODELING
10"+0.01
-0.01
1'-4" +0.01
-0.01
4"+0.01
-0.01
7"+0.05
-0.05
5"+0.01
-0.01
3"+0.01
-0.01
2"+0.01
-0.01 0.001 AB
A
B
S.F. 64uinch
U*
- *
CSG MODEL
Fa c e
Lo o p
Ed g e
V e rt e x
B-REP MODEL
INTERACTION OF
PLANNING FUNCTIONS
GEOMETRIC REASONING
PROCESS SELECTION
CUTTER SELECTION
MACHINE TOOL SELECTION
SETUP PLANNING
FIXTURE PLANNING
CUTTER PATH GENERATION
• global & local geometry
• process capability
• process cost
• available tools
• tool dimension and geometry
• geometric constraints
• machine availability, cost
• machine capability
• feature relationship
• approach directions
• process constraints
• fixture constraints
• fixture element function
• locating, supporting, and
clamping surfaces
• stability
• feature merging and split
• path optimization
• obstacle and interference
avoidance
PROCESS
PLAN
• Also called : operation sheet, route sheet, operation planning summary,
or another similar name.
• The detailed plan contains:
route
processes
process parameters
machine and tool selections
fixtures
• How detail the plan is depends on the application.
• Operation: a process
• Operation Plan (Op-plan): contains the description of an operation,
includes tools, machines to be used, process parameters, machining
time, etc.
• Op-plan sequence: Summary of a process plan.
EXAMPLE PROCESS
PLANS
Route Sheet
Part No. S1243
Part Name: Mounting Bracket
1. Mtl Rm
2. Mill02 5
3. Drl01 4
4. Insp 1
workstation Time(min)
by: T.C. Chang
P R O C E S S P L A N ACE Inc.
P a r t N o . S 0 1 2 5 - F
P a r t N a m e : H o u s in g
O r ig in a l: S .D . S m a r t D a te : 1 /1 /8 9
C h e c k e d : C .S . G o o d D a te : 2 /1 /8 9
M a te r ia l: s te e l 4 3 4 0 S i
C h a n g e s : D a te :
A p p r o v e d : T .C . C h a n g D a te : 2 /1 4 /8 9
N o . O p e ra tio n
D e s c rip tio n
W o r k s ta tio n S e tu p T o o l T im e
(M in )
1 0 M ill b o tto m su r fa c e 1 M I L L 0 1 se e a tta c h # 1
fo r illu str a tio n
F a c e m ill
6 te e th /4 " d ia
3 s e tu p
5 m a c h in in g
2 0 M ill to p su r fa c e M I L L 0 1 se e a tta c h # 1 F a c e m ill
6 te e th /4 " d ia
2 s e tu p
6 m a c h in in g
3 0 D r ill 4 h o le s D R L 0 2 se t o n s u rfa c e 1 tw ist d r ill
1 /2 " d ia
2 " lo n g
2 s e tu p
3 m a c h in in g
Detailed Process Plan
Oper. Routing Summary
FACTORS AFFECTING
PROCESS
PLAN SELECTION
• Shape
• Tolerance
• Surface finish
• Size
• Material type
• Quantity
• Value of the product
• Urgency
• Manufacturing system itself
PROCESS PLANNING
CLASSIFICATIONMANUAL
COMPUTER-AIDED
VARIANT
GT based
Computer aids for editing
Parameters selection
GENERATIVE
Some kind of decision logic
Decision tree/table
Artificial Intelligence
Objective-Oriented
Still experience based
AUTOMATIC
Design understanding
Geometric reasoning capability
REQUIREMENTS IN
MANUAL PROCESS
PLANNING• ability to interpret an engineering drawing.
• familiar with manufacturing processes and
practice.
• familiar with tooling and fixtures.
• know what resources are available in the
shop.
• know how to use reference books, such as
machinability data handbook.
• able to do computations on machining time
and cost.
INDUSTRIAL
SOLUTION
10"+0.01
-0.01
1'-4" +0.01
-0.01
4"+0.01
-0.01
7"+0.05
-0.05
5" +0.01
-0.01
3" +0.01
-0.01
2" +0.01
-0.01 0.001 AB
A
B
S.F. 64 uinch
PRODUCT
CONCEPT
CAD
CAM
CUTTER
PATH
HUMAN - decision making
COMPUTER - geometric computation, data handling
N0010 G70 G 90 T08 M06
N0020 G00 X2.125 Y-0.475 Z4.000 S3157
N0030 G01 Z1.500 F63 M03
N0040 G01 Y4.100
N0050 G01 X2.625
N0060 G01 Y1.375
N0070 G01 X3.000
N0080 G03 Y2.625 I3.000 J2.000
N0090 G01 Y2.000
N0100 G01 X2.625
N0110 G01 Y-0.100
N0120 G00 Z4.000 T02 M05
N0130 F9.16 S509 M06
N0140 G81 X0.750 Y1.000 Z-0.1 R2.100 M03
N0150 G81 X0.750 Y3.000 Z-0.1 R2.100
N0160 G00 X-1.000 Y-1.000 M30
.
Handbook
PROCESS PLANNING
STEPS Study the overall shape of the part. Use this
information to classify the part and determine
the type of workstation needed.
• Thoroughly study the drawing. Try to identify
every manufacturing features and notes.
 If raw stock is not given, determine the best raw
material shape to use.
 Identify datum surfaces. Use information on
datum surfaces to determine the setups.
• Select machines for each setup.
 For each setup determine the rough sequence
of operations necessary to create all the
PROCESS PLANNING
STEPS
(continue) Sequence the operations determined in the
previous step.
 Select tools for each operation. Try to use the
same tool for several operations if it is
possible. Keep in mind the trade off on tool
change time and estimated machining time.
 Select or design fixtures for each setup.
 Evaluate the plan generate thus far and make
necessary modifications.
 Select cutting parameters for each operation.
 Prepare the final process plan document.
COMPUTER-
AIDED
PROCESS
PLANNING
ADVANTAGES
1. It can reduce the skill required of a planner.
2. It can reduce the process planning time.
3. It can reduce both process planning and
manufacturing cost.
4. It can create more consistent plans.
5. It can produce more accurate plans.
6. It can increase productivity.
WHY AUTOMATED
PROCESS PLANNING
• Shortening the lead-time
• Manufacturability feedback
• Lowering the production cost
• Consistent process plans
PROCESS PLANNING
Machining featuresDesign
Workpiece Selection
Process Selection
Tool Selection
Feed, Speed Selection
Operation Sequencing
Setup Planning
Fixturing Planning
Part Programming
VARIANT PROCESS
PLANNING
Standard
process
plans &
individual
process
plans
process
plan
editing
part
coding
part
family
formation
standard
plan
preparation
part
coding
part
family
search
process
plan
retrieval
finished
process
plan
GROUP TECHNOLOGY BASED RETRIEVAL SYSTEM
PROBLEMS ASSOCIATED
WITH
THE VARIANT APPROACH
1. The components to be planned are
limited to similar components previously
planned.
2. Experienced process planners are still
required to modify the standard plan for
the specific component.
3. Details of the plan cannot be
generated.
4. Variant planning cannot be used in an
entirely automated manufacturing
system, without additional process
ADVANTAGES OF
THE
VARIANT
APPROACH
1. Once a standard plan has been written, a
variety of components can be planned.
2. Comparatively simple programming and
installation (compared with generative
systems) is required to implement a
planning system.
3. The system is understandable, and the
planner has control of the final plan.
4. It is easy to learn, and easy to use.
GENERATIVE
APPROACH
(i) part description
(ii) manufacturing databases
(iii) decision making logic and
algorithms
A system which automatically synthesizes a
process plan for a new component.
MAJOR COMPONENTS:
ADVANTAGES OF THE
GENERATIVE
APPROACH
1. Generate consistent process plans
rapidly;
2. New components can be planned as
easily as existing components;
3. It has potential for integrating with an
automated manufacturing facility to
provide detailed control information.
KEY
DEVELOPMENTS
1. The logic of process planning must be
identified and captured.
2. The part to be produced must be clearly
and precisely defined in a computer-
compatible format
3. The captured logic of process planning
and the part description
PRODUCT
REPRESENTATION
Geometrical information
Part shape
Design features
Technological information
Tolerances
Surface quality (surface finish, surface
integrity)
Special manufacturing notes
Etc.
INPUT REPRESENTATION
SELECTION
• How much information is needed?
• Data format required.
• Ease of use for the planning.
• Interface with other functions, such as, part
programming, design, etc.
• Easy recognition of manufacturing features.
• Easy extraction of planning information from
the representation.
WHAT INPUT
REPRESENTATIONS
GT CODE
Line drawing
Special language
Symbolic representation
Solid model
CSG
B-Rep
others?
Feature based model
SPECIAL
LANGUAGE
10CYLINDER/3,1/
11DFIT/K,5/
12CHAMFER/.2,2.6/
20CYLINDER/2.5,1.2/
21LTOL/+0.001,-0.001/
3
1
1.2
2.5
.2x2.6
K5
+.001
-.001
AUTAP
CIMS/PRO
REPRESENTATION
a1
a2 a3
a4
a5
a6
t
X
Y Z
sweep
direction
GARI
REPRESENTATION
(F1 (type face) (direction xp) (quality 120))
(F2 (type face) (direction yp) (quality 64))
(F3 (type face) (direction ym) (quality rough))
(H1 (type countersunk-hole) (diameter 1.0)
(countersik-diameter 3.0)
(starting-from F2) (opening-into F3))
(distance H1 F1 3.0)
(countersink-depth F2 H1 0.5)
0 3.0
2
.5
0 1.
X
Y3.0
F1
F2
F3
CONCEPT OF
FEATUREManufacturing is "feature" based.
Feature:
1 a: the structure, form, or appearance esp. of
a person
b: obs: physical beauty.
2 a: the makeup or appearance of the face or
its parts
b: a part of the face: LINEAMENT
3: a prominent part or characteristic
4: a special attraction
FEATURES IN DESIGN
AND
MANUFACTURING
A high level geometry which includes a
set of connected geometries. Its meaning
is dependent upon the application domain.
Boss
Pocket with an island
Design Feature vs Manufacturing Feature
DESIGN
FEATURES
• For creating a shape
• For providing a function
M o tio n Slot feature
MANUFACTURING
FEATURES
Drilling Round hole
Turning Rotational
feature
End milling Plane surface,
Hole, profile, slot
pocket
Ball end mill Free form
surface
Boring Cylindrical shell
ReamingCylindrical shell
... ...
• For process selection
• For fixturing
End mill a slot
Manufacturing
is feature based.
MANUFACTURING FEATURES
(cont.)
?
DATA ASSOCIATED
WITH
DESIGN FEATURES
Mechanical Engineering Part Design
• Feature Type
• Dimension
• Location
• Tolerance
• Surface finish
• Function
A S lo t
DATA ASSOCIATED WITH
MANUFACTURING
FEATURES
• Feature type
• Dimension
• Location
• Tolerance
• Surface finish
• Relations with other features
• Approach directions
A p p ro a c h
A p p ro a ch
° Feature classifications are not the same.
FEATURE
RECOGNITION
Extract and decompose features from a
geometric model.
• Syntactic pattern recognition
• State transition diagram and automata
• Decomposition
• Logic
• Graph matching
• Face growing
DIFFICULTIES OF
FEATURE
RECOGNITION• Potentially large number of features.
• Features are domain and user specific.
• Lack of a theory in features.
• Input geometric model specific. Based
on incomplete models.
• Computational complexity of the
algorithms.
• Existing algorithms are limited to simple
features.
DESIGN WITH
MANUFACTURING
FEATURESMake the design process a simulation of the
manufacturing process. Features are tool
swept volumes and operators are
manufacturing processes.
Design
Process Planning
Bar stock - Profile - Bore hole
Turn profile Drill hole
Bore hole
PROS AND CONS OF DESIGN
WITH
MANUFACTURING FEATURES
• Concurrent engineering - designers are
forced to think about manufacturing
process.
• Simplify (eliminate) process planning.
• Hinder the creative thinking of designers.
• Use the wrong talent (designer doing
process planning).
• Interaction of features affects processes.
Pros
Cons
BACKWARD
PLANNING.
Bo rin g
D r i l l i n g
Mi l l i n g
Fin is h e d
p a rt
Wo rkp ie c e
P
la
n
n
in
g
M
a
c
h
in
in
g
o
p
e
ra
t
io
n
PROCESS
KNOWLEDGE
REPRESENTATION
• Predicate logic
• Production rules
• Semantic Nets
• Frames
• Object Oriented Programming
SOME RESEARCH
ISSUES
• Part design representation: information
contents, data format
• Geometric reasoning: feature recognition,
feature extraction, tool approach directions,
feature relations
• Process selection: backward planning,
tolerance analysis, geometric capability,
process knowledge, process mechanics
• Tool selection: size, length, cut length, shank
length, holder, materials, geometry, roughing,
and finishing tools
SOME RESEARCH
ISSUES
(continue)
• Fixture design: fixture element model,
fixturing knowledge modeling, stability
analysis, friction/cutting force
• Tool path planning: algorithms for features,
gauging and interference avoidance
algorithms, automated path generation
• Software engineering issues: data structure,
data base, knowledge base, planning
algorithms, user interface, software interface
A FEATURE BASED
DESIGN/
PROCESS PLANNING
SYSTEM
Geometric Reasoning
Application-Specific Features (e.g. manufacturing features)
blind slot, through slot, step, etc.
approach direction, feed direction
feature relations: precedence and intersection type
Manufacturing-Oriented Design Features
hole, straight slot, T-slot, circular slot, pocket
counterbore, sculptured surface cavity
Princple
Principle:
Provide designer with the freedom to describe shape -
avoid constraining manufacturing planning
or requiring detailed manufacturing knowledge.
SOME AUTOMATED PROCESS PLANNING EFFORTS
NIST : Automated process planning
CAM-I, UTRC: XPS-2, generative process
planning
U of Maryland, Nau: Semi-generative process
planning
GE R & D, Hines: Art to Part
Penn State, Wysk (Texas A&M): graph based
process planning
Stanford, Cutkosky: FirstCut, integrated design
and manufacturing system based on features.
CMI & CMU: IMW, feature based design, expert
operation planning.
U. of Twente, Holland, Kals: PARTS , feature
based input, feature recognition, operation
planning.
Allied Bendix, Hummel & Brooks: XCUT system
for cavity operation planning.
IPK Berlin & IPK Aachen
UMIST, B.J. Davies
U. of Leeds, de Pennington
U. Mass, Dixon: Features-based design for
manufacturing analysis of extrusions,
castings, injection molding
ASU, Shah: Theory of features study for
CAM-I; Feature-mapping shell
Stanford,Cutkosky: feature-based design,
process planning, fixturing systems.
Helsinki, Mantyla: systems for design &
process planning.
IBM, Rossignac:Editing & validation of
feature models; MAMOUR system.
SDRC, Chung, GE, Simmons: Feature-based
design and casting analysis.
Features in Process PlanningFeature in Design
QTC is one of the only efforts that
considers design through inspection
and the only one that uses deep
geometric reasoning to link design
and process planning.
SOME
APPROACHESCAD
CAM
2-D
Drafting
ProcessPlanner
•automaticdrawinginterpretation
•gen.typeplangeneration
Automaticpart
programming
3-D
SolidModel
canned/auto.cutter
pathcycle
Featurebased
solidmodel
automaticpart
programming
•featurerefinement
•limitedgeometricreasoning
•generativeplanning
•seqmaydictatedbydesign
2-D
Drafting
•drawinginterpretation
•varianttypeplangeneration
•interactivepartprogramming
NCcontrol
3-DCAD
Model
•interactivedrawinginterpretation
•gen./varianttypeplan
generation
cannedcutter
pathcycles
•geometricreasoning
•expertplanner
•nohumandecision
THE DEVELOPMENT OF
CAPP
1960 1970 1980 1990 2000
Intelligence of
the system
H um an
Expert
?
m anual
planning
Data
base
G T
variant
system
expert
system
geom etric
reasoning
elem entary
m achine
learning
? technology

More Related Content

What's hot

Industrial Engineering
Industrial EngineeringIndustrial Engineering
Industrial Engineeringvijay kumar
 
PPCE unit 2 (ME8793 – PROCESS PLANNING AND COST ESTIMATION )
PPCE unit 2 (ME8793 – PROCESS PLANNING AND COST ESTIMATION )PPCE unit 2 (ME8793 – PROCESS PLANNING AND COST ESTIMATION )
PPCE unit 2 (ME8793 – PROCESS PLANNING AND COST ESTIMATION )TAMILMECHKIT
 
Process Planning & Cost Estimation
Process Planning & Cost Estimation Process Planning & Cost Estimation
Process Planning & Cost Estimation Prabhu Bose
 
Machinability data syste
Machinability data systeMachinability data syste
Machinability data systeVenu Yadav
 
Chapter 3 CNC turning and machining centers
Chapter 3 CNC turning and machining centersChapter 3 CNC turning and machining centers
Chapter 3 CNC turning and machining centersRAHUL THAKER
 
Flexible Manufacturing System
Flexible Manufacturing SystemFlexible Manufacturing System
Flexible Manufacturing SystemVishal Jadhav
 
Chapter 1 introduction to manufacturing system
Chapter 1   introduction to manufacturing systemChapter 1   introduction to manufacturing system
Chapter 1 introduction to manufacturing systemN. A. Sutisna
 
Numerical control machines tool
Numerical control machines toolNumerical control machines tool
Numerical control machines tooljntuhcej
 
travel chart for plant layout
travel chart for plant layouttravel chart for plant layout
travel chart for plant layoutYash Patel
 
Unit ii process planning activities
Unit ii process planning activitiesUnit ii process planning activities
Unit ii process planning activitiesKarpaka Raj
 
Flexible manufacturing systems (FMS)
Flexible manufacturing systems (FMS)Flexible manufacturing systems (FMS)
Flexible manufacturing systems (FMS)SERCOD
 
PPCE unit 3 (ME8793 – PROCESS PLANNING AND COST ESTIMATION)
 PPCE  unit 3 (ME8793 – PROCESS PLANNING AND COST ESTIMATION)  PPCE  unit 3 (ME8793 – PROCESS PLANNING AND COST ESTIMATION)
PPCE unit 3 (ME8793 – PROCESS PLANNING AND COST ESTIMATION) TAMILMECHKIT
 
Computer numerical control (CNC)
Computer numerical control (CNC)Computer numerical control (CNC)
Computer numerical control (CNC)Sudip Phuyal
 
Flexible manufacturing systems (FMS)
Flexible manufacturing systems (FMS)Flexible manufacturing systems (FMS)
Flexible manufacturing systems (FMS)jntuhcej
 
FLEXIBLE MANUFACTURING SYSTEM
FLEXIBLE MANUFACTURING SYSTEMFLEXIBLE MANUFACTURING SYSTEM
FLEXIBLE MANUFACTURING SYSTEMAnand Khare
 
COMPUTER AIDED PROCESS PLANNING (CAPP)
COMPUTER AIDED PROCESS PLANNING (CAPP)COMPUTER AIDED PROCESS PLANNING (CAPP)
COMPUTER AIDED PROCESS PLANNING (CAPP)Victor Al
 
INTRODUCTION TO PROCESS PLANNING
INTRODUCTION TO PROCESS PLANNINGINTRODUCTION TO PROCESS PLANNING
INTRODUCTION TO PROCESS PLANNINGSathishkumarM89
 

What's hot (20)

Industrial Engineering
Industrial EngineeringIndustrial Engineering
Industrial Engineering
 
PPCE unit 2 (ME8793 – PROCESS PLANNING AND COST ESTIMATION )
PPCE unit 2 (ME8793 – PROCESS PLANNING AND COST ESTIMATION )PPCE unit 2 (ME8793 – PROCESS PLANNING AND COST ESTIMATION )
PPCE unit 2 (ME8793 – PROCESS PLANNING AND COST ESTIMATION )
 
Process Planning & Cost Estimation
Process Planning & Cost Estimation Process Planning & Cost Estimation
Process Planning & Cost Estimation
 
Machinability data syste
Machinability data systeMachinability data syste
Machinability data syste
 
Chapter 3 CNC turning and machining centers
Chapter 3 CNC turning and machining centersChapter 3 CNC turning and machining centers
Chapter 3 CNC turning and machining centers
 
Flexible Manufacturing System
Flexible Manufacturing SystemFlexible Manufacturing System
Flexible Manufacturing System
 
CNC Machines and its Components
CNC Machines and its ComponentsCNC Machines and its Components
CNC Machines and its Components
 
Chapter 1 introduction to manufacturing system
Chapter 1   introduction to manufacturing systemChapter 1   introduction to manufacturing system
Chapter 1 introduction to manufacturing system
 
Numerical control machines tool
Numerical control machines toolNumerical control machines tool
Numerical control machines tool
 
Numeric control
Numeric controlNumeric control
Numeric control
 
travel chart for plant layout
travel chart for plant layouttravel chart for plant layout
travel chart for plant layout
 
CNC MACHINE
CNC MACHINECNC MACHINE
CNC MACHINE
 
Unit ii process planning activities
Unit ii process planning activitiesUnit ii process planning activities
Unit ii process planning activities
 
Flexible manufacturing systems (FMS)
Flexible manufacturing systems (FMS)Flexible manufacturing systems (FMS)
Flexible manufacturing systems (FMS)
 
PPCE unit 3 (ME8793 – PROCESS PLANNING AND COST ESTIMATION)
 PPCE  unit 3 (ME8793 – PROCESS PLANNING AND COST ESTIMATION)  PPCE  unit 3 (ME8793 – PROCESS PLANNING AND COST ESTIMATION)
PPCE unit 3 (ME8793 – PROCESS PLANNING AND COST ESTIMATION)
 
Computer numerical control (CNC)
Computer numerical control (CNC)Computer numerical control (CNC)
Computer numerical control (CNC)
 
Flexible manufacturing systems (FMS)
Flexible manufacturing systems (FMS)Flexible manufacturing systems (FMS)
Flexible manufacturing systems (FMS)
 
FLEXIBLE MANUFACTURING SYSTEM
FLEXIBLE MANUFACTURING SYSTEMFLEXIBLE MANUFACTURING SYSTEM
FLEXIBLE MANUFACTURING SYSTEM
 
COMPUTER AIDED PROCESS PLANNING (CAPP)
COMPUTER AIDED PROCESS PLANNING (CAPP)COMPUTER AIDED PROCESS PLANNING (CAPP)
COMPUTER AIDED PROCESS PLANNING (CAPP)
 
INTRODUCTION TO PROCESS PLANNING
INTRODUCTION TO PROCESS PLANNINGINTRODUCTION TO PROCESS PLANNING
INTRODUCTION TO PROCESS PLANNING
 

Viewers also liked

Process planning (lesson 1)
Process planning (lesson 1)Process planning (lesson 1)
Process planning (lesson 1)Hari Vignesh R
 
Product Design
Product DesignProduct Design
Product Designajithsrc
 
Knowledge Engineering For Automated Planning
Knowledge Engineering For Automated PlanningKnowledge Engineering For Automated Planning
Knowledge Engineering For Automated Planningahmad bassiouny
 
Chapter 7 automation techniques
Chapter 7  automation techniquesChapter 7  automation techniques
Chapter 7 automation techniquesMohamad Sahiedan
 
Automated Planning as a Semantic Technology
Automated Planning as a Semantic TechnologyAutomated Planning as a Semantic Technology
Automated Planning as a Semantic TechnologyClark & Parsia LLC
 
Operational Risk Management & Strategic Planning
Operational Risk Management & Strategic PlanningOperational Risk Management & Strategic Planning
Operational Risk Management & Strategic PlanningEneni Oduwole
 
ORM Operational Risks Management
ORM Operational Risks ManagementORM Operational Risks Management
ORM Operational Risks ManagementTariq minhas
 
Operational risk & business continuity management
Operational risk & business continuity managementOperational risk & business continuity management
Operational risk & business continuity managementUjjwal 'Shanu'
 
Operational Risk & Basel Ii
Operational Risk & Basel IiOperational Risk & Basel Ii
Operational Risk & Basel Iijhsiddiqi2003
 
Risk management ppt 111p (training module)
Risk management ppt 111p (training module)Risk management ppt 111p (training module)
Risk management ppt 111p (training module)Sadia Razzaq
 
June event - Operational risk management - IT Career
June event - Operational risk management - IT CareerJune event - Operational risk management - IT Career
June event - Operational risk management - IT CareerFriends4Growth Group
 
Operational risk management and measurement
Operational risk management and measurementOperational risk management and measurement
Operational risk management and measurementRahmat Mulyana
 
Operation Risk Management in Banking Sector
Operation Risk Management in Banking SectorOperation Risk Management in Banking Sector
Operation Risk Management in Banking SectorSanjay Kumbhar
 
Operational risk management (orm)
Operational risk management (orm)Operational risk management (orm)
Operational risk management (orm)Bushra Angbeen
 
Operational Risk Management
Operational Risk ManagementOperational Risk Management
Operational Risk Managementarsqureshi
 

Viewers also liked (20)

Process planning (lesson 1)
Process planning (lesson 1)Process planning (lesson 1)
Process planning (lesson 1)
 
Product Design
Product DesignProduct Design
Product Design
 
Knowledge Engineering For Automated Planning
Knowledge Engineering For Automated PlanningKnowledge Engineering For Automated Planning
Knowledge Engineering For Automated Planning
 
Chapter 7 automation techniques
Chapter 7  automation techniquesChapter 7  automation techniques
Chapter 7 automation techniques
 
Automated Planning as a Semantic Technology
Automated Planning as a Semantic TechnologyAutomated Planning as a Semantic Technology
Automated Planning as a Semantic Technology
 
Operational Risk Management & Strategic Planning
Operational Risk Management & Strategic PlanningOperational Risk Management & Strategic Planning
Operational Risk Management & Strategic Planning
 
6184 7 tn05
6184 7 tn056184 7 tn05
6184 7 tn05
 
ORM Operational Risks Management
ORM Operational Risks ManagementORM Operational Risks Management
ORM Operational Risks Management
 
Operational risk & business continuity management
Operational risk & business continuity managementOperational risk & business continuity management
Operational risk & business continuity management
 
Operational Risk & Basel Ii
Operational Risk & Basel IiOperational Risk & Basel Ii
Operational Risk & Basel Ii
 
Enterprise Risk Management 2015 PDF
Enterprise Risk Management 2015 PDFEnterprise Risk Management 2015 PDF
Enterprise Risk Management 2015 PDF
 
Risk management ppt 111p (training module)
Risk management ppt 111p (training module)Risk management ppt 111p (training module)
Risk management ppt 111p (training module)
 
June event - Operational risk management - IT Career
June event - Operational risk management - IT CareerJune event - Operational risk management - IT Career
June event - Operational risk management - IT Career
 
Operational risk management and measurement
Operational risk management and measurementOperational risk management and measurement
Operational risk management and measurement
 
Operation Risk Management in Banking Sector
Operation Risk Management in Banking SectorOperation Risk Management in Banking Sector
Operation Risk Management in Banking Sector
 
The Planning Process
The Planning ProcessThe Planning Process
The Planning Process
 
Operational risk management (orm)
Operational risk management (orm)Operational risk management (orm)
Operational risk management (orm)
 
Operational Risk Management
Operational Risk ManagementOperational Risk Management
Operational Risk Management
 
Project Manufacturing
Project ManufacturingProject Manufacturing
Project Manufacturing
 
Product design concept
Product design conceptProduct design concept
Product design concept
 

Similar to Processs planning

ie550cappie550cappie550cappie550capp.ppt
ie550cappie550cappie550cappie550capp.pptie550cappie550cappie550cappie550capp.ppt
ie550cappie550cappie550cappie550capp.pptBasemAbdo4
 
1-unit(Introduction to process planning)-converted.docx
1-unit(Introduction to process planning)-converted.docx1-unit(Introduction to process planning)-converted.docx
1-unit(Introduction to process planning)-converted.docxprabaharjeevanananda
 
Process planning with an example
Process planning with an exampleProcess planning with an example
Process planning with an exampleHiran Gabriel
 
INTELLIGENT DECISION MAKING FOR REACTIVE SCHEDULING IN FMS
INTELLIGENT DECISION MAKING FOR REACTIVE SCHEDULING IN FMSINTELLIGENT DECISION MAKING FOR REACTIVE SCHEDULING IN FMS
INTELLIGENT DECISION MAKING FOR REACTIVE SCHEDULING IN FMSJyotiraman De
 
PROCESS PLANNING 1.pptx
PROCESS PLANNING 1.pptxPROCESS PLANNING 1.pptx
PROCESS PLANNING 1.pptxmurugarajan001
 
Product and process planning
Product and process planningProduct and process planning
Product and process planningzimbar
 
Process planning unit two
Process planning  unit twoProcess planning  unit two
Process planning unit twoZELALEMGIRMAW
 
INTRODUCTION TO PROCESS PLANNING
INTRODUCTION TO PROCESS PLANNINGINTRODUCTION TO PROCESS PLANNING
INTRODUCTION TO PROCESS PLANNINGSathishkumarM89
 
Cim presentation (1)
Cim presentation (1)Cim presentation (1)
Cim presentation (1)rajnitj19
 
CADCAM CAE Notes
CADCAM CAE NotesCADCAM CAE Notes
CADCAM CAE NotesAbhay Gore
 
TMA Module 2........................................................
TMA Module 2........................................................TMA Module 2........................................................
TMA Module 2........................................................4PS19AU411SyedaSoubi
 
Process planning approaches
Process planning approaches Process planning approaches
Process planning approaches chethan kumar
 

Similar to Processs planning (20)

ie550cappie550cappie550cappie550capp.ppt
ie550cappie550cappie550cappie550capp.pptie550cappie550cappie550cappie550capp.ppt
ie550cappie550cappie550cappie550capp.ppt
 
1-unit(Introduction to process planning)-converted.docx
1-unit(Introduction to process planning)-converted.docx1-unit(Introduction to process planning)-converted.docx
1-unit(Introduction to process planning)-converted.docx
 
ie550capp.ppt
ie550capp.pptie550capp.ppt
ie550capp.ppt
 
Process planning with an example
Process planning with an exampleProcess planning with an example
Process planning with an example
 
ie550capp.ppt
ie550capp.pptie550capp.ppt
ie550capp.ppt
 
INTELLIGENT DECISION MAKING FOR REACTIVE SCHEDULING IN FMS
INTELLIGENT DECISION MAKING FOR REACTIVE SCHEDULING IN FMSINTELLIGENT DECISION MAKING FOR REACTIVE SCHEDULING IN FMS
INTELLIGENT DECISION MAKING FOR REACTIVE SCHEDULING IN FMS
 
PROCESS PLANNING 1.pptx
PROCESS PLANNING 1.pptxPROCESS PLANNING 1.pptx
PROCESS PLANNING 1.pptx
 
Product and process planning
Product and process planningProduct and process planning
Product and process planning
 
ie550capp.ppt
ie550capp.pptie550capp.ppt
ie550capp.ppt
 
Process planning unit two
Process planning  unit twoProcess planning  unit two
Process planning unit two
 
Process planning
Process planningProcess planning
Process planning
 
INTRODUCTION TO PROCESS PLANNING
INTRODUCTION TO PROCESS PLANNINGINTRODUCTION TO PROCESS PLANNING
INTRODUCTION TO PROCESS PLANNING
 
Cim presentation (1)
Cim presentation (1)Cim presentation (1)
Cim presentation (1)
 
UNIT 1 PPCE.ppt
UNIT 1 PPCE.pptUNIT 1 PPCE.ppt
UNIT 1 PPCE.ppt
 
CADCAM CAE Notes
CADCAM CAE NotesCADCAM CAE Notes
CADCAM CAE Notes
 
Unit 2 cim
Unit 2 cimUnit 2 cim
Unit 2 cim
 
Unit 1 manufacturing system design
Unit   1 manufacturing system designUnit   1 manufacturing system design
Unit 1 manufacturing system design
 
TMA Module 2........................................................
TMA Module 2........................................................TMA Module 2........................................................
TMA Module 2........................................................
 
Process planning approaches
Process planning approaches Process planning approaches
Process planning approaches
 
Chapter-3-PROCESS-PLANNING.pptx
Chapter-3-PROCESS-PLANNING.pptxChapter-3-PROCESS-PLANNING.pptx
Chapter-3-PROCESS-PLANNING.pptx
 

Recently uploaded

Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best ServiceTamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Servicemeghakumariji156
 
kiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal loadkiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal loadhamedmustafa094
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptxJIT KUMAR GUPTA
 
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARKOUSTAV SARKAR
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdfKamal Acharya
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTbhaskargani46
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxSCMS School of Architecture
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdfKamal Acharya
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VDineshKumar4165
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdfAldoGarca30
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startQuintin Balsdon
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationBhangaleSonal
 
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...drmkjayanthikannan
 
AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsvanyagupta248
 
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLEGEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLEselvakumar948
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayEpec Engineered Technologies
 
Computer Networks Basics of Network Devices
Computer Networks  Basics of Network DevicesComputer Networks  Basics of Network Devices
Computer Networks Basics of Network DevicesChandrakantDivate1
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxJuliansyahHarahap1
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.Kamal Acharya
 

Recently uploaded (20)

Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best ServiceTamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
 
kiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal loadkiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal load
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdf
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdf
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equation
 
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
 
AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech students
 
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLEGEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
 
Computer Networks Basics of Network Devices
Computer Networks  Basics of Network DevicesComputer Networks  Basics of Network Devices
Computer Networks Basics of Network Devices
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptx
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.
 

Processs planning

  • 2. Chapter 6. PROCESS ENGINEERING • Process planning is also called: manufacturing planning, process planning, material processing, process engineering, and machine routing. • Which machining processes and parameters are to be used (as well as those machines capable of performing these processes) to convert (machine) a piece part from its initial form to a final form predetermined (usually by a design engineer) from an engineering drawing. • The act of preparing detailed work instructions to produce a part. • How to realize a given product design.
  • 3. PRODUCT REALIZATION Product design Process planning Operation programming Verification Scheduling Execution Process, machine knowledge Scheduling knowledge
  • 4. PROCESS PLANNING Design Machine Tool Scheduling and Production Control Process Planning
  • 5. PROBLEMS FACING MANUFACTURING INDUSTRY Fact: Only 11% of the machine tools in the U.S. are programmable. More than 53% of the metal-working plants in the U.S. do not have even one computer-controlled machine. Potential benefits in reducing turnaround time by using programmable machine tools have not been realized due to time, complexity and costs of planning and programming.
  • 6. DOMAIN One-of-a-kind and Small batch Objectives: Lead-time, Cost Approaches: process selection, use existing facilities. Mass production Objective: Cost Approaches: process design, optimization, materials selection, facilities design
  • 7. How do we process engineer?  How can we make it?  How much does it cost?  How long will it take us to complete it?  How reliable will it be?  How can we recycle it
  • 8. How can we make it?  Is this like something else that we’ve done?  Yes; What methods were used?  No; Design a new process
  • 9. What methods were used?  Machining methods  Pressworking  Welding/fabrication  Casting  Powder materials  Layered deposition  Others
  • 13. ENGINEERING DESIGN MODELING 10"+0.01 -0.01 1'-4" +0.01 -0.01 4"+0.01 -0.01 7"+0.05 -0.05 5"+0.01 -0.01 3"+0.01 -0.01 2"+0.01 -0.01 0.001 AB A B S.F. 64uinch U* - * CSG MODEL Fa c e Lo o p Ed g e V e rt e x B-REP MODEL
  • 14. INTERACTION OF PLANNING FUNCTIONS GEOMETRIC REASONING PROCESS SELECTION CUTTER SELECTION MACHINE TOOL SELECTION SETUP PLANNING FIXTURE PLANNING CUTTER PATH GENERATION • global & local geometry • process capability • process cost • available tools • tool dimension and geometry • geometric constraints • machine availability, cost • machine capability • feature relationship • approach directions • process constraints • fixture constraints • fixture element function • locating, supporting, and clamping surfaces • stability • feature merging and split • path optimization • obstacle and interference avoidance
  • 15. PROCESS PLAN • Also called : operation sheet, route sheet, operation planning summary, or another similar name. • The detailed plan contains: route processes process parameters machine and tool selections fixtures • How detail the plan is depends on the application. • Operation: a process • Operation Plan (Op-plan): contains the description of an operation, includes tools, machines to be used, process parameters, machining time, etc. • Op-plan sequence: Summary of a process plan.
  • 16. EXAMPLE PROCESS PLANS Route Sheet Part No. S1243 Part Name: Mounting Bracket 1. Mtl Rm 2. Mill02 5 3. Drl01 4 4. Insp 1 workstation Time(min) by: T.C. Chang P R O C E S S P L A N ACE Inc. P a r t N o . S 0 1 2 5 - F P a r t N a m e : H o u s in g O r ig in a l: S .D . S m a r t D a te : 1 /1 /8 9 C h e c k e d : C .S . G o o d D a te : 2 /1 /8 9 M a te r ia l: s te e l 4 3 4 0 S i C h a n g e s : D a te : A p p r o v e d : T .C . C h a n g D a te : 2 /1 4 /8 9 N o . O p e ra tio n D e s c rip tio n W o r k s ta tio n S e tu p T o o l T im e (M in ) 1 0 M ill b o tto m su r fa c e 1 M I L L 0 1 se e a tta c h # 1 fo r illu str a tio n F a c e m ill 6 te e th /4 " d ia 3 s e tu p 5 m a c h in in g 2 0 M ill to p su r fa c e M I L L 0 1 se e a tta c h # 1 F a c e m ill 6 te e th /4 " d ia 2 s e tu p 6 m a c h in in g 3 0 D r ill 4 h o le s D R L 0 2 se t o n s u rfa c e 1 tw ist d r ill 1 /2 " d ia 2 " lo n g 2 s e tu p 3 m a c h in in g Detailed Process Plan Oper. Routing Summary
  • 17. FACTORS AFFECTING PROCESS PLAN SELECTION • Shape • Tolerance • Surface finish • Size • Material type • Quantity • Value of the product • Urgency • Manufacturing system itself
  • 18. PROCESS PLANNING CLASSIFICATIONMANUAL COMPUTER-AIDED VARIANT GT based Computer aids for editing Parameters selection GENERATIVE Some kind of decision logic Decision tree/table Artificial Intelligence Objective-Oriented Still experience based AUTOMATIC Design understanding Geometric reasoning capability
  • 19. REQUIREMENTS IN MANUAL PROCESS PLANNING• ability to interpret an engineering drawing. • familiar with manufacturing processes and practice. • familiar with tooling and fixtures. • know what resources are available in the shop. • know how to use reference books, such as machinability data handbook. • able to do computations on machining time and cost.
  • 20. INDUSTRIAL SOLUTION 10"+0.01 -0.01 1'-4" +0.01 -0.01 4"+0.01 -0.01 7"+0.05 -0.05 5" +0.01 -0.01 3" +0.01 -0.01 2" +0.01 -0.01 0.001 AB A B S.F. 64 uinch PRODUCT CONCEPT CAD CAM CUTTER PATH HUMAN - decision making COMPUTER - geometric computation, data handling N0010 G70 G 90 T08 M06 N0020 G00 X2.125 Y-0.475 Z4.000 S3157 N0030 G01 Z1.500 F63 M03 N0040 G01 Y4.100 N0050 G01 X2.625 N0060 G01 Y1.375 N0070 G01 X3.000 N0080 G03 Y2.625 I3.000 J2.000 N0090 G01 Y2.000 N0100 G01 X2.625 N0110 G01 Y-0.100 N0120 G00 Z4.000 T02 M05 N0130 F9.16 S509 M06 N0140 G81 X0.750 Y1.000 Z-0.1 R2.100 M03 N0150 G81 X0.750 Y3.000 Z-0.1 R2.100 N0160 G00 X-1.000 Y-1.000 M30 . Handbook
  • 21. PROCESS PLANNING STEPS Study the overall shape of the part. Use this information to classify the part and determine the type of workstation needed. • Thoroughly study the drawing. Try to identify every manufacturing features and notes.  If raw stock is not given, determine the best raw material shape to use.  Identify datum surfaces. Use information on datum surfaces to determine the setups. • Select machines for each setup.  For each setup determine the rough sequence of operations necessary to create all the
  • 22. PROCESS PLANNING STEPS (continue) Sequence the operations determined in the previous step.  Select tools for each operation. Try to use the same tool for several operations if it is possible. Keep in mind the trade off on tool change time and estimated machining time.  Select or design fixtures for each setup.  Evaluate the plan generate thus far and make necessary modifications.  Select cutting parameters for each operation.  Prepare the final process plan document.
  • 23. COMPUTER- AIDED PROCESS PLANNING ADVANTAGES 1. It can reduce the skill required of a planner. 2. It can reduce the process planning time. 3. It can reduce both process planning and manufacturing cost. 4. It can create more consistent plans. 5. It can produce more accurate plans. 6. It can increase productivity.
  • 24. WHY AUTOMATED PROCESS PLANNING • Shortening the lead-time • Manufacturability feedback • Lowering the production cost • Consistent process plans
  • 25. PROCESS PLANNING Machining featuresDesign Workpiece Selection Process Selection Tool Selection Feed, Speed Selection Operation Sequencing Setup Planning Fixturing Planning Part Programming
  • 27. PROBLEMS ASSOCIATED WITH THE VARIANT APPROACH 1. The components to be planned are limited to similar components previously planned. 2. Experienced process planners are still required to modify the standard plan for the specific component. 3. Details of the plan cannot be generated. 4. Variant planning cannot be used in an entirely automated manufacturing system, without additional process
  • 28. ADVANTAGES OF THE VARIANT APPROACH 1. Once a standard plan has been written, a variety of components can be planned. 2. Comparatively simple programming and installation (compared with generative systems) is required to implement a planning system. 3. The system is understandable, and the planner has control of the final plan. 4. It is easy to learn, and easy to use.
  • 29. GENERATIVE APPROACH (i) part description (ii) manufacturing databases (iii) decision making logic and algorithms A system which automatically synthesizes a process plan for a new component. MAJOR COMPONENTS:
  • 30. ADVANTAGES OF THE GENERATIVE APPROACH 1. Generate consistent process plans rapidly; 2. New components can be planned as easily as existing components; 3. It has potential for integrating with an automated manufacturing facility to provide detailed control information.
  • 31. KEY DEVELOPMENTS 1. The logic of process planning must be identified and captured. 2. The part to be produced must be clearly and precisely defined in a computer- compatible format 3. The captured logic of process planning and the part description
  • 32. PRODUCT REPRESENTATION Geometrical information Part shape Design features Technological information Tolerances Surface quality (surface finish, surface integrity) Special manufacturing notes Etc.
  • 33. INPUT REPRESENTATION SELECTION • How much information is needed? • Data format required. • Ease of use for the planning. • Interface with other functions, such as, part programming, design, etc. • Easy recognition of manufacturing features. • Easy extraction of planning information from the representation.
  • 34. WHAT INPUT REPRESENTATIONS GT CODE Line drawing Special language Symbolic representation Solid model CSG B-Rep others? Feature based model
  • 37. GARI REPRESENTATION (F1 (type face) (direction xp) (quality 120)) (F2 (type face) (direction yp) (quality 64)) (F3 (type face) (direction ym) (quality rough)) (H1 (type countersunk-hole) (diameter 1.0) (countersik-diameter 3.0) (starting-from F2) (opening-into F3)) (distance H1 F1 3.0) (countersink-depth F2 H1 0.5) 0 3.0 2 .5 0 1. X Y3.0 F1 F2 F3
  • 38. CONCEPT OF FEATUREManufacturing is "feature" based. Feature: 1 a: the structure, form, or appearance esp. of a person b: obs: physical beauty. 2 a: the makeup or appearance of the face or its parts b: a part of the face: LINEAMENT 3: a prominent part or characteristic 4: a special attraction
  • 39. FEATURES IN DESIGN AND MANUFACTURING A high level geometry which includes a set of connected geometries. Its meaning is dependent upon the application domain. Boss Pocket with an island Design Feature vs Manufacturing Feature
  • 40. DESIGN FEATURES • For creating a shape • For providing a function M o tio n Slot feature
  • 41. MANUFACTURING FEATURES Drilling Round hole Turning Rotational feature End milling Plane surface, Hole, profile, slot pocket Ball end mill Free form surface Boring Cylindrical shell ReamingCylindrical shell ... ... • For process selection • For fixturing End mill a slot Manufacturing is feature based.
  • 43. DATA ASSOCIATED WITH DESIGN FEATURES Mechanical Engineering Part Design • Feature Type • Dimension • Location • Tolerance • Surface finish • Function A S lo t
  • 44. DATA ASSOCIATED WITH MANUFACTURING FEATURES • Feature type • Dimension • Location • Tolerance • Surface finish • Relations with other features • Approach directions A p p ro a c h A p p ro a ch ° Feature classifications are not the same.
  • 45. FEATURE RECOGNITION Extract and decompose features from a geometric model. • Syntactic pattern recognition • State transition diagram and automata • Decomposition • Logic • Graph matching • Face growing
  • 46. DIFFICULTIES OF FEATURE RECOGNITION• Potentially large number of features. • Features are domain and user specific. • Lack of a theory in features. • Input geometric model specific. Based on incomplete models. • Computational complexity of the algorithms. • Existing algorithms are limited to simple features.
  • 47. DESIGN WITH MANUFACTURING FEATURESMake the design process a simulation of the manufacturing process. Features are tool swept volumes and operators are manufacturing processes. Design Process Planning Bar stock - Profile - Bore hole Turn profile Drill hole Bore hole
  • 48. PROS AND CONS OF DESIGN WITH MANUFACTURING FEATURES • Concurrent engineering - designers are forced to think about manufacturing process. • Simplify (eliminate) process planning. • Hinder the creative thinking of designers. • Use the wrong talent (designer doing process planning). • Interaction of features affects processes. Pros Cons
  • 49. BACKWARD PLANNING. Bo rin g D r i l l i n g Mi l l i n g Fin is h e d p a rt Wo rkp ie c e P la n n in g M a c h in in g o p e ra t io n
  • 50. PROCESS KNOWLEDGE REPRESENTATION • Predicate logic • Production rules • Semantic Nets • Frames • Object Oriented Programming
  • 51. SOME RESEARCH ISSUES • Part design representation: information contents, data format • Geometric reasoning: feature recognition, feature extraction, tool approach directions, feature relations • Process selection: backward planning, tolerance analysis, geometric capability, process knowledge, process mechanics • Tool selection: size, length, cut length, shank length, holder, materials, geometry, roughing, and finishing tools
  • 52. SOME RESEARCH ISSUES (continue) • Fixture design: fixture element model, fixturing knowledge modeling, stability analysis, friction/cutting force • Tool path planning: algorithms for features, gauging and interference avoidance algorithms, automated path generation • Software engineering issues: data structure, data base, knowledge base, planning algorithms, user interface, software interface
  • 53. A FEATURE BASED DESIGN/ PROCESS PLANNING SYSTEM Geometric Reasoning Application-Specific Features (e.g. manufacturing features) blind slot, through slot, step, etc. approach direction, feed direction feature relations: precedence and intersection type Manufacturing-Oriented Design Features hole, straight slot, T-slot, circular slot, pocket counterbore, sculptured surface cavity
  • 54. Princple Principle: Provide designer with the freedom to describe shape - avoid constraining manufacturing planning or requiring detailed manufacturing knowledge.
  • 55. SOME AUTOMATED PROCESS PLANNING EFFORTS NIST : Automated process planning CAM-I, UTRC: XPS-2, generative process planning U of Maryland, Nau: Semi-generative process planning GE R & D, Hines: Art to Part Penn State, Wysk (Texas A&M): graph based process planning Stanford, Cutkosky: FirstCut, integrated design and manufacturing system based on features. CMI & CMU: IMW, feature based design, expert operation planning. U. of Twente, Holland, Kals: PARTS , feature based input, feature recognition, operation planning. Allied Bendix, Hummel & Brooks: XCUT system for cavity operation planning. IPK Berlin & IPK Aachen UMIST, B.J. Davies U. of Leeds, de Pennington U. Mass, Dixon: Features-based design for manufacturing analysis of extrusions, castings, injection molding ASU, Shah: Theory of features study for CAM-I; Feature-mapping shell Stanford,Cutkosky: feature-based design, process planning, fixturing systems. Helsinki, Mantyla: systems for design & process planning. IBM, Rossignac:Editing & validation of feature models; MAMOUR system. SDRC, Chung, GE, Simmons: Feature-based design and casting analysis. Features in Process PlanningFeature in Design QTC is one of the only efforts that considers design through inspection and the only one that uses deep geometric reasoning to link design and process planning.
  • 57. THE DEVELOPMENT OF CAPP 1960 1970 1980 1990 2000 Intelligence of the system H um an Expert ? m anual planning Data base G T variant system expert system geom etric reasoning elem entary m achine learning ? technology