SlideShare a Scribd company logo
1 of 28
PROFESSIONAL
PRACTICE 1
TUTORIAL 7
FARAH SHAM | TAM ZHAO WEI | TAN JIA SAN
Contractor’s claims for loss and expense have long been a
contentious issue in many building contracts. These
claims are usually resolved during the final accounting
process but where negotiation fails, they usually become
disputes with the parties adopting legal route to resolve
their differences.
Discuss the matters below based on the PAM Form of
Contract 2006 (With Quantities):
Question a
The Contractor is granted an
Extension of Time. Is there an
automatic right to the recovery of loss
and expense?
“
NO
■ The claim for Extension of Time falls under Clause
23.0 and is deemed to refer to the relevant events
as stated in Clause 23.8
■ However, the claim for Loss and Expenses falls
under Clause 24.0 and is deemed to refer to the
matters materially affecting the regular progress
of the Works as stated in Clause 24.3
Question b
Explain the grounds for Claim of Loss
and Expense and describe how the
Contractor can register their claims.
“
Where the regular progress of the Works or any
section of the Works has been or is likely to be
materially affected by any of the matter expressly
referred to in Clause 24.3, and the Contractor has
incurred or is likely to incur loss and/or expense which
could not be reimbursed by a payment made under
any other provision in the Contract, the Contractor
may make a claim for such loss and/or expense.
- Clause 24.1 -
“
Matter materially affecting the regular progress of
the Works.
- Clause 24.3 -
Clause 24.1 (a)
Contractor Architect
with an initial estimate of his
claim duly supported with all
necessary calculations
Written notice
Within 28 days from the date of
AI, CAI or the start of the
occurrence of the matters
referred to in Clause 24.3
Clause 24.1 (b)
Contractor Architect &
Quantity Surveyor
Complete particulars of his
claim of loss and/or expense
together with all necessary
calculations to substantiate
his claims.
* If the contractor fails to submit the required particulars within the
stated time
(or within such longer period as may be agreed in writing by the
Architect), it shall be deemed that the contractor has waived his
rights for loss and/or expense.
Within 28 days after the matters referred to in Clause 24.3 have ended.
Question c
Claims are invariably initiated by the Contractor.
Contractual claims, Extra contractual claims and
Exgratia claims are the 3 types of claims in a
contract.
Give SIX (6) main reasons for claims and SIX (6)
common types of claims. How does the Quantity
Surveyor assess such claims?
REASONS
F O R
CLAIM
When instruction issued by architect or engineer is too
late because contractor already carried out the portion
of work so contractor entitled to claim for the
demolition or modification of work done, as well as the
cost needed for the new instruction.
1. LATE INSTRUCTIONS
2. POSTPONEMENT OF WORKS
When architect instruct that a part of the work is to be
postponed the contractor is entitled to claim additional
cost.
Postponement after the contract date
● Mobilization and demobilization of labour, plants
and tools.
Within the contract date
● Reduced output of work
Example :
Different floor finishes in BQ and Architectural Drawings.
3. LATE ISSUE OF MATERIALS
4. FAILURE OF EMPLOYER TO CARRY OUT
WORKS
Example :
Employer did not carry out the works, which affect
Contractor’s work.
- Time implication
- Clause 23 - EOT
- Clause 23.8 -Relevant Events
5. DIVERGENCE BETWEEN CONTRACT DOCUMENTS
Clause 3.1 Contract Documents
When discrepancies arise, the priority in the interpretation of such
documents shall be in the following descending order :
3.1 (a) the Letter of Award
3.1 (b) the Articles of Agreement
3.1 (c) the Conditions of Contract
3.1 (d) the Contract Drawings
3.1 (e) the Contract Bills
3.1 (f) other documents incorporated in the Contract Documents,
unless expressly stated to be excluded in any of the Contract
Document
6. VARIATIONS
Clause 11.7 Additional Expense caused by Variation
Clause 11.7 (a)
Contractor Architect
with an initial estimate of his
claim duly supported with all
necessary calculations
Written notice
Within 28 days from the date of
AI or CAI giving rise to his claim.
* If the contractor fails to submit the required particulars within the
stated time
(or within such longer period as may be agreed in writing by the
Architect), it shall be deemed that the contractor has waived his
rights to any such additional expenses.
6. VARIATIONS (cont’d)
Clause 11.7 Additional Expense caused by Variation
Clause 11.7 (b)
Contractor Architect &
Quantity Surveyor
Complete particulars of his
claim for additional expenses
together with all necessary
calculations to substantiate
his claims.
COMMON
TYPES OF
CLAIM
1. STANDING TIME OF PLANT & LABOUR
In the case where contractor is ready to start work
and has mobilize the plant and labor to the work
site, and the contractor is not allowed to start work
due to some circumstances.
The contractor in this case are entitled to claim for
the cost of the plant and labor which is idling for the
whole duration.
2. ADDITIONAL CONTRACT OVERHEAD COST
Contractor is instructed to carry out additional
work, normally in form of variation order and the
contract period is extended.
The contractor is entitled to claim for the overhead
cost which is the contract manager, site supervisor,
site quantity surveyor and some preliminaries
items (telephone, electricity bill, rent portable
toilets etc)
● Must be some obstruction
● Cannot carry out the works smoothly
● Time & cost implication
● How to justify it ?
( Photos and Job Measurement)
3. DISRUPTION OF WORK DUE TO VARIATION
Example :
Employer wants to change the door after installed.
● Based on initial plan
● Due to technical issue (not caused by Contractor)
● Must be under Clause 24.3
4. CONDITION DIFFERENT FROM PLANNED
5. CARRYING OUT WORK LATER THAN
ANTICIPATED
A head of claim that is often made by contractors
against employers for prolongation costs.
Example,
The costs sought by a contractor for having to remain on
site longer than its originally anticipated due to the
actions of the employer such as late handover of site
possession.
6. UNECONOMIC WORKING FOR PLANT AND
LABOUR
- Aka Loss of Productivity
This is a head of claim sometimes made where there has
been a delay in completion or disturbance of the
contractor’s regular and economic progress even
though, on occasion, the ultimate delay in completion is
small or does not occur.
HOW DOES QUANTITY
SURVEYOR ASSESS
SUCH CLAIMS?
Based on contractor’s disrupted output
- The qs have to look at the delay or disruption that took place.
- For example; due to late instruction by the architect the work is
delayed for a week. So the qs have to evaluate the idling of labours and
machineries.
Based on contract overheads
- When the contractor is granted an extension of time, they can claim for
the additional costs for the overheads.
- Example of overhead costs are; the staffs in charge of the project ie
project manager, site supervisor, qs, office rentals, telephone bills,
electricity bills.
- The claim is evaluated based on the salaries of the staff, for the
duration of the extension of time and also the cost incurred for the
office rental and associated bills.
Based on formula : - Hudson’s Formula.
Head Office % Contract Sum
Period of Delay
100 Contract Period
x x
THANK YOU!

More Related Content

What's hot

Measuring tendering and estimating for CBE
Measuring tendering and estimating for CBEMeasuring tendering and estimating for CBE
Measuring tendering and estimating for CBESahl Buhary
 
Tenders and procedure of tendering
Tenders and procedure of tenderingTenders and procedure of tendering
Tenders and procedure of tenderingvvsasane
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008AYM1979
 
Types of Contract in Construction Management
Types of Contract in Construction ManagementTypes of Contract in Construction Management
Types of Contract in Construction ManagementShahin MB
 
Types of Tender and their Process
Types of Tender and their ProcessTypes of Tender and their Process
Types of Tender and their Processarpantripathi2
 
Contract Specifications, Bidding and Contractor Selection for Capital Replace...
Contract Specifications, Bidding and Contractor Selection for Capital Replace...Contract Specifications, Bidding and Contractor Selection for Capital Replace...
Contract Specifications, Bidding and Contractor Selection for Capital Replace...Kipcon Inc.
 
Estimating seminar 1 slides
Estimating seminar 1 slidesEstimating seminar 1 slides
Estimating seminar 1 slidesDoreen Yeo
 
Tenders in professional practice
Tenders in professional practiceTenders in professional practice
Tenders in professional practiceAditya Sanyal
 
Construction Documents
Construction DocumentsConstruction Documents
Construction DocumentsAllan Berry
 
Estimation and Costing - Contracts
Estimation and Costing - ContractsEstimation and Costing - Contracts
Estimation and Costing - Contractssrinivas2036
 
Civil tenders and contracts spce
Civil tenders and contracts spceCivil tenders and contracts spce
Civil tenders and contracts spceirkportal
 
Tenders contract -arti
Tenders contract -artiTenders contract -arti
Tenders contract -artijagadish108
 
Tendering Document for the Procurement of Works
Tendering Document for the Procurement of WorksTendering Document for the Procurement of Works
Tendering Document for the Procurement of WorksMohammad Alimuzzaman Bappy
 
Tendering Bidding & Award of Contract Final Draft
Tendering Bidding & Award of Contract Final DraftTendering Bidding & Award of Contract Final Draft
Tendering Bidding & Award of Contract Final DraftMuneesh Methwani
 

What's hot (20)

Measuring tendering and estimating for CBE
Measuring tendering and estimating for CBEMeasuring tendering and estimating for CBE
Measuring tendering and estimating for CBE
 
Tenders and procedure of tendering
Tenders and procedure of tenderingTenders and procedure of tendering
Tenders and procedure of tendering
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008
 
Types of Contract in Construction Management
Types of Contract in Construction ManagementTypes of Contract in Construction Management
Types of Contract in Construction Management
 
TENDER DOCUMENT
TENDER DOCUMENTTENDER DOCUMENT
TENDER DOCUMENT
 
Chapter 2- Contract Management
Chapter 2- Contract ManagementChapter 2- Contract Management
Chapter 2- Contract Management
 
Types of Tender and their Process
Types of Tender and their ProcessTypes of Tender and their Process
Types of Tender and their Process
 
Contract Specifications, Bidding and Contractor Selection for Capital Replace...
Contract Specifications, Bidding and Contractor Selection for Capital Replace...Contract Specifications, Bidding and Contractor Selection for Capital Replace...
Contract Specifications, Bidding and Contractor Selection for Capital Replace...
 
Module 4 lecture 1
Module  4 lecture 1Module  4 lecture 1
Module 4 lecture 1
 
Estimating seminar 1 slides
Estimating seminar 1 slidesEstimating seminar 1 slides
Estimating seminar 1 slides
 
contract procedure
contract procedurecontract procedure
contract procedure
 
Tenders in professional practice
Tenders in professional practiceTenders in professional practice
Tenders in professional practice
 
Construction Documents
Construction DocumentsConstruction Documents
Construction Documents
 
Estimation and Costing - Contracts
Estimation and Costing - ContractsEstimation and Costing - Contracts
Estimation and Costing - Contracts
 
Tendering presenation
Tendering presenationTendering presenation
Tendering presenation
 
Civil tenders and contracts spce
Civil tenders and contracts spceCivil tenders and contracts spce
Civil tenders and contracts spce
 
Tendering-professional practices-jamia millia islamia
Tendering-professional practices-jamia millia islamiaTendering-professional practices-jamia millia islamia
Tendering-professional practices-jamia millia islamia
 
Tenders contract -arti
Tenders contract -artiTenders contract -arti
Tenders contract -arti
 
Tendering Document for the Procurement of Works
Tendering Document for the Procurement of WorksTendering Document for the Procurement of Works
Tendering Document for the Procurement of Works
 
Tendering Bidding & Award of Contract Final Draft
Tendering Bidding & Award of Contract Final DraftTendering Bidding & Award of Contract Final Draft
Tendering Bidding & Award of Contract Final Draft
 

Similar to Professional Practice 1 Tutorial 7 Claims Assessment

Seminar Presentation Slides (Chapter 2)
Seminar Presentation Slides (Chapter 2)Seminar Presentation Slides (Chapter 2)
Seminar Presentation Slides (Chapter 2)Melvin Lim
 
Professional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOTProfessional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOTYee Len Wan
 
Pp2 group assignment
Pp2 group assignmentPp2 group assignment
Pp2 group assignmentlohwenjun
 
Cbb512 examination november_2011
Cbb512 examination november_2011Cbb512 examination november_2011
Cbb512 examination november_2011Maatla Moadi
 
A Claim submitted by the contractor during for slides.pptx
A Claim submitted by the contractor during for slides.pptxA Claim submitted by the contractor during for slides.pptx
A Claim submitted by the contractor during for slides.pptxMahSobeh
 
A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006Melvin Lim
 
Lecture 8-determination-of-own-employment-by
Lecture 8-determination-of-own-employment-byLecture 8-determination-of-own-employment-by
Lecture 8-determination-of-own-employment-byseenyeeyong
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2ahmong4
 
Professional Practice II
Professional Practice IIProfessional Practice II
Professional Practice IIseenyeeyong
 
GCC2015 Course_Day2
GCC2015 Course_Day2GCC2015 Course_Day2
GCC2015 Course_Day2JB Nartey
 
GCC2015 Course_Day2
GCC2015 Course_Day2GCC2015 Course_Day2
GCC2015 Course_Day2JB Nartey
 
Preserving Your Bottom Line
Preserving Your Bottom LinePreserving Your Bottom Line
Preserving Your Bottom LineCallPM
 
PP2 - Seminar Presentation
PP2 - Seminar Presentation PP2 - Seminar Presentation
PP2 - Seminar Presentation Lin Hui
 
Conditions of CPWD contract in INDIA
Conditions of CPWD contract in INDIAConditions of CPWD contract in INDIA
Conditions of CPWD contract in INDIAAvinash Kumar Gupta
 
Arbitration Dispute Cross Arguments: Asia NGPipeline -Substance of EPC contra...
Arbitration Dispute Cross Arguments: Asia NGPipeline -Substance of EPC contra...Arbitration Dispute Cross Arguments: Asia NGPipeline -Substance of EPC contra...
Arbitration Dispute Cross Arguments: Asia NGPipeline -Substance of EPC contra...César del Riego y Fuentes
 
PP2 final report
PP2 final reportPP2 final report
PP2 final reportArissa Loh
 

Similar to Professional Practice 1 Tutorial 7 Claims Assessment (20)

Claims and insolvencies (1)
Claims and insolvencies (1)Claims and insolvencies (1)
Claims and insolvencies (1)
 
Seminar Presentation Slides (Chapter 2)
Seminar Presentation Slides (Chapter 2)Seminar Presentation Slides (Chapter 2)
Seminar Presentation Slides (Chapter 2)
 
Professional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOTProfessional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOT
 
Pp2 group assignment
Pp2 group assignmentPp2 group assignment
Pp2 group assignment
 
Cbb512 examination november_2011
Cbb512 examination november_2011Cbb512 examination november_2011
Cbb512 examination november_2011
 
A Claim submitted by the contractor during for slides.pptx
A Claim submitted by the contractor during for slides.pptxA Claim submitted by the contractor during for slides.pptx
A Claim submitted by the contractor during for slides.pptx
 
A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006
 
Lecture 8-determination-of-own-employment-by
Lecture 8-determination-of-own-employment-byLecture 8-determination-of-own-employment-by
Lecture 8-determination-of-own-employment-by
 
Cl presentation
Cl presentationCl presentation
Cl presentation
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2
 
Professional Practice II
Professional Practice IIProfessional Practice II
Professional Practice II
 
GCC2015 Course_Day2
GCC2015 Course_Day2GCC2015 Course_Day2
GCC2015 Course_Day2
 
GCC2015 Course_Day2
GCC2015 Course_Day2GCC2015 Course_Day2
GCC2015 Course_Day2
 
Preserving Your Bottom Line
Preserving Your Bottom LinePreserving Your Bottom Line
Preserving Your Bottom Line
 
PP2 COMPILCATION
PP2 COMPILCATIONPP2 COMPILCATION
PP2 COMPILCATION
 
PP2 - Seminar Presentation
PP2 - Seminar Presentation PP2 - Seminar Presentation
PP2 - Seminar Presentation
 
Conditions of CPWD contract in INDIA
Conditions of CPWD contract in INDIAConditions of CPWD contract in INDIA
Conditions of CPWD contract in INDIA
 
Arbitration Dispute Cross Arguments: Asia NGPipeline -Substance of EPC contra...
Arbitration Dispute Cross Arguments: Asia NGPipeline -Substance of EPC contra...Arbitration Dispute Cross Arguments: Asia NGPipeline -Substance of EPC contra...
Arbitration Dispute Cross Arguments: Asia NGPipeline -Substance of EPC contra...
 
Pp2 final report
Pp2 final reportPp2 final report
Pp2 final report
 
PP2 final report
PP2 final reportPP2 final report
PP2 final report
 

More from Farah Sham

Conference Paper
Conference PaperConference Paper
Conference PaperFarah Sham
 
My Community Service Journal
My Community Service JournalMy Community Service Journal
My Community Service JournalFarah Sham
 
Orphanage Community Service Initiative
Orphanage Community Service InitiativeOrphanage Community Service Initiative
Orphanage Community Service InitiativeFarah Sham
 
Infographic Poster Report
Infographic Poster ReportInfographic Poster Report
Infographic Poster ReportFarah Sham
 
Hubungan Etnik Magazine Masyarakat India di Brickfiields
Hubungan Etnik Magazine Masyarakat India di BrickfiieldsHubungan Etnik Magazine Masyarakat India di Brickfiields
Hubungan Etnik Magazine Masyarakat India di BrickfiieldsFarah Sham
 
Strategic Management: Individual Assignment
Strategic Management: Individual AssignmentStrategic Management: Individual Assignment
Strategic Management: Individual AssignmentFarah Sham
 
Strategic Management Presentation
Strategic Management Presentation Strategic Management Presentation
Strategic Management Presentation Farah Sham
 
Strategic Management Group Report
Strategic Management Group ReportStrategic Management Group Report
Strategic Management Group ReportFarah Sham
 
Pp2 coursework 1 p10
Pp2 coursework 1 p10 Pp2 coursework 1 p10
Pp2 coursework 1 p10 Farah Sham
 
PP2 Assignment: Group
PP2 Assignment: GroupPP2 Assignment: Group
PP2 Assignment: GroupFarah Sham
 
Building Economics Tutorial
Building Economics TutorialBuilding Economics Tutorial
Building Economics TutorialFarah Sham
 
Building Economics Presentation
Building Economics PresentationBuilding Economics Presentation
Building Economics PresentationFarah Sham
 
A3 CONSTRUCTION METHODOLOGY
A3 CONSTRUCTION METHODOLOGYA3 CONSTRUCTION METHODOLOGY
A3 CONSTRUCTION METHODOLOGYFarah Sham
 
Building Economics Cost Data
Building Economics Cost Data Building Economics Cost Data
Building Economics Cost Data Farah Sham
 
Building Economics Cost Plan Report
Building Economics Cost Plan ReportBuilding Economics Cost Plan Report
Building Economics Cost Plan ReportFarah Sham
 
MEASUREMENT TENDER DOCUMENTATION
MEASUREMENT TENDER DOCUMENTATIONMEASUREMENT TENDER DOCUMENTATION
MEASUREMENT TENDER DOCUMENTATIONFarah Sham
 
Software application
Software application Software application
Software application Farah Sham
 
Project tender
Project tender Project tender
Project tender Farah Sham
 
Project tender
Project tenderProject tender
Project tenderFarah Sham
 
Software application for qs material standard rate
Software application for qs   material  standard rateSoftware application for qs   material  standard rate
Software application for qs material standard rateFarah Sham
 

More from Farah Sham (20)

Conference Paper
Conference PaperConference Paper
Conference Paper
 
My Community Service Journal
My Community Service JournalMy Community Service Journal
My Community Service Journal
 
Orphanage Community Service Initiative
Orphanage Community Service InitiativeOrphanage Community Service Initiative
Orphanage Community Service Initiative
 
Infographic Poster Report
Infographic Poster ReportInfographic Poster Report
Infographic Poster Report
 
Hubungan Etnik Magazine Masyarakat India di Brickfiields
Hubungan Etnik Magazine Masyarakat India di BrickfiieldsHubungan Etnik Magazine Masyarakat India di Brickfiields
Hubungan Etnik Magazine Masyarakat India di Brickfiields
 
Strategic Management: Individual Assignment
Strategic Management: Individual AssignmentStrategic Management: Individual Assignment
Strategic Management: Individual Assignment
 
Strategic Management Presentation
Strategic Management Presentation Strategic Management Presentation
Strategic Management Presentation
 
Strategic Management Group Report
Strategic Management Group ReportStrategic Management Group Report
Strategic Management Group Report
 
Pp2 coursework 1 p10
Pp2 coursework 1 p10 Pp2 coursework 1 p10
Pp2 coursework 1 p10
 
PP2 Assignment: Group
PP2 Assignment: GroupPP2 Assignment: Group
PP2 Assignment: Group
 
Building Economics Tutorial
Building Economics TutorialBuilding Economics Tutorial
Building Economics Tutorial
 
Building Economics Presentation
Building Economics PresentationBuilding Economics Presentation
Building Economics Presentation
 
A3 CONSTRUCTION METHODOLOGY
A3 CONSTRUCTION METHODOLOGYA3 CONSTRUCTION METHODOLOGY
A3 CONSTRUCTION METHODOLOGY
 
Building Economics Cost Data
Building Economics Cost Data Building Economics Cost Data
Building Economics Cost Data
 
Building Economics Cost Plan Report
Building Economics Cost Plan ReportBuilding Economics Cost Plan Report
Building Economics Cost Plan Report
 
MEASUREMENT TENDER DOCUMENTATION
MEASUREMENT TENDER DOCUMENTATIONMEASUREMENT TENDER DOCUMENTATION
MEASUREMENT TENDER DOCUMENTATION
 
Software application
Software application Software application
Software application
 
Project tender
Project tender Project tender
Project tender
 
Project tender
Project tenderProject tender
Project tender
 
Software application for qs material standard rate
Software application for qs   material  standard rateSoftware application for qs   material  standard rate
Software application for qs material standard rate
 

Recently uploaded

Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxNirmalaLoungPoorunde1
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...Marc Dusseiller Dusjagr
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
 
भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,Virag Sontakke
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformChameera Dedduwage
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsanshu789521
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxmanuelaromero2013
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon AUnboundStockton
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxSayali Powar
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxpboyjonauth
 
Final demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptxFinal demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptxAvyJaneVismanos
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdfSoniaTolstoy
 
internship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developerinternship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developerunnathinaik
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 
Class 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfClass 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfakmcokerachita
 
Painted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaPainted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaVirag Sontakke
 

Recently uploaded (20)

Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptx
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
 
भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy Reform
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha elections
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptx
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon A
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptx
 
Final demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptxFinal demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptx
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
 
internship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developerinternship ppt on smartinternz platform as salesforce developer
internship ppt on smartinternz platform as salesforce developer
 
Staff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSDStaff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSD
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdfTataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
 
Class 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfClass 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdf
 
Painted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaPainted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of India
 

Professional Practice 1 Tutorial 7 Claims Assessment

  • 1. PROFESSIONAL PRACTICE 1 TUTORIAL 7 FARAH SHAM | TAM ZHAO WEI | TAN JIA SAN
  • 2. Contractor’s claims for loss and expense have long been a contentious issue in many building contracts. These claims are usually resolved during the final accounting process but where negotiation fails, they usually become disputes with the parties adopting legal route to resolve their differences. Discuss the matters below based on the PAM Form of Contract 2006 (With Quantities):
  • 3. Question a The Contractor is granted an Extension of Time. Is there an automatic right to the recovery of loss and expense?
  • 4. “ NO ■ The claim for Extension of Time falls under Clause 23.0 and is deemed to refer to the relevant events as stated in Clause 23.8 ■ However, the claim for Loss and Expenses falls under Clause 24.0 and is deemed to refer to the matters materially affecting the regular progress of the Works as stated in Clause 24.3
  • 5. Question b Explain the grounds for Claim of Loss and Expense and describe how the Contractor can register their claims.
  • 6. “ Where the regular progress of the Works or any section of the Works has been or is likely to be materially affected by any of the matter expressly referred to in Clause 24.3, and the Contractor has incurred or is likely to incur loss and/or expense which could not be reimbursed by a payment made under any other provision in the Contract, the Contractor may make a claim for such loss and/or expense. - Clause 24.1 -
  • 7. “ Matter materially affecting the regular progress of the Works. - Clause 24.3 -
  • 8. Clause 24.1 (a) Contractor Architect with an initial estimate of his claim duly supported with all necessary calculations Written notice Within 28 days from the date of AI, CAI or the start of the occurrence of the matters referred to in Clause 24.3
  • 9. Clause 24.1 (b) Contractor Architect & Quantity Surveyor Complete particulars of his claim of loss and/or expense together with all necessary calculations to substantiate his claims. * If the contractor fails to submit the required particulars within the stated time (or within such longer period as may be agreed in writing by the Architect), it shall be deemed that the contractor has waived his rights for loss and/or expense. Within 28 days after the matters referred to in Clause 24.3 have ended.
  • 10. Question c Claims are invariably initiated by the Contractor. Contractual claims, Extra contractual claims and Exgratia claims are the 3 types of claims in a contract. Give SIX (6) main reasons for claims and SIX (6) common types of claims. How does the Quantity Surveyor assess such claims?
  • 12. When instruction issued by architect or engineer is too late because contractor already carried out the portion of work so contractor entitled to claim for the demolition or modification of work done, as well as the cost needed for the new instruction. 1. LATE INSTRUCTIONS
  • 13. 2. POSTPONEMENT OF WORKS When architect instruct that a part of the work is to be postponed the contractor is entitled to claim additional cost. Postponement after the contract date ● Mobilization and demobilization of labour, plants and tools. Within the contract date ● Reduced output of work
  • 14. Example : Different floor finishes in BQ and Architectural Drawings. 3. LATE ISSUE OF MATERIALS
  • 15. 4. FAILURE OF EMPLOYER TO CARRY OUT WORKS Example : Employer did not carry out the works, which affect Contractor’s work. - Time implication - Clause 23 - EOT - Clause 23.8 -Relevant Events
  • 16. 5. DIVERGENCE BETWEEN CONTRACT DOCUMENTS Clause 3.1 Contract Documents When discrepancies arise, the priority in the interpretation of such documents shall be in the following descending order : 3.1 (a) the Letter of Award 3.1 (b) the Articles of Agreement 3.1 (c) the Conditions of Contract 3.1 (d) the Contract Drawings 3.1 (e) the Contract Bills 3.1 (f) other documents incorporated in the Contract Documents, unless expressly stated to be excluded in any of the Contract Document
  • 17. 6. VARIATIONS Clause 11.7 Additional Expense caused by Variation Clause 11.7 (a) Contractor Architect with an initial estimate of his claim duly supported with all necessary calculations Written notice Within 28 days from the date of AI or CAI giving rise to his claim.
  • 18. * If the contractor fails to submit the required particulars within the stated time (or within such longer period as may be agreed in writing by the Architect), it shall be deemed that the contractor has waived his rights to any such additional expenses. 6. VARIATIONS (cont’d) Clause 11.7 Additional Expense caused by Variation Clause 11.7 (b) Contractor Architect & Quantity Surveyor Complete particulars of his claim for additional expenses together with all necessary calculations to substantiate his claims.
  • 20. 1. STANDING TIME OF PLANT & LABOUR In the case where contractor is ready to start work and has mobilize the plant and labor to the work site, and the contractor is not allowed to start work due to some circumstances. The contractor in this case are entitled to claim for the cost of the plant and labor which is idling for the whole duration.
  • 21. 2. ADDITIONAL CONTRACT OVERHEAD COST Contractor is instructed to carry out additional work, normally in form of variation order and the contract period is extended. The contractor is entitled to claim for the overhead cost which is the contract manager, site supervisor, site quantity surveyor and some preliminaries items (telephone, electricity bill, rent portable toilets etc)
  • 22. ● Must be some obstruction ● Cannot carry out the works smoothly ● Time & cost implication ● How to justify it ? ( Photos and Job Measurement) 3. DISRUPTION OF WORK DUE TO VARIATION Example : Employer wants to change the door after installed.
  • 23. ● Based on initial plan ● Due to technical issue (not caused by Contractor) ● Must be under Clause 24.3 4. CONDITION DIFFERENT FROM PLANNED
  • 24. 5. CARRYING OUT WORK LATER THAN ANTICIPATED A head of claim that is often made by contractors against employers for prolongation costs. Example, The costs sought by a contractor for having to remain on site longer than its originally anticipated due to the actions of the employer such as late handover of site possession.
  • 25. 6. UNECONOMIC WORKING FOR PLANT AND LABOUR - Aka Loss of Productivity This is a head of claim sometimes made where there has been a delay in completion or disturbance of the contractor’s regular and economic progress even though, on occasion, the ultimate delay in completion is small or does not occur.
  • 26. HOW DOES QUANTITY SURVEYOR ASSESS SUCH CLAIMS?
  • 27. Based on contractor’s disrupted output - The qs have to look at the delay or disruption that took place. - For example; due to late instruction by the architect the work is delayed for a week. So the qs have to evaluate the idling of labours and machineries. Based on contract overheads - When the contractor is granted an extension of time, they can claim for the additional costs for the overheads. - Example of overhead costs are; the staffs in charge of the project ie project manager, site supervisor, qs, office rentals, telephone bills, electricity bills. - The claim is evaluated based on the salaries of the staff, for the duration of the extension of time and also the cost incurred for the office rental and associated bills. Based on formula : - Hudson’s Formula. Head Office % Contract Sum Period of Delay 100 Contract Period x x