SlideShare a Scribd company logo
1 of 12
SCHOOL OF ARCHITECTURE, BUILDING &
DESIGN
BACHELOR OF QUANTITY SURVEYING (HONS)
PROFESSIONAL PRACTICE II
(QSB60904)
CHAN YI FUNG 0323057
FARAH AIDA BINTI SHAHAR SHAM 0322962
KIEW CHEE YUAN 0323297
LIEW WEI ZHEAN 0331225
NURAFIQAH HAJI ABD ZARIFUL 0321196
TAN KEN RIC 0318631
YEE JYH LIN 0322408
LECTURER : SR EDDIE LIM SEK CHEON
SUBMISSION DATE : 29th OCTOBER 2018
Question 1
The Letter of Award for the above works was issued for RM 81,200,000.00 based on
the tender sum submitted by the Contractor. As you were preparing the contract
documents for binding and signature, you found some errors in the rates for aluminium
windows works submitted by the Contractor, which were very low. Kindly advise the
actions that you will take.
Answer:
Clause 13.1 states that the Contract Sum shall not be adjusted or altered in any way
whatsoever, other than in accordance with the express provisions of the Contract. Any
arithmetical errors or any errors in the prices and rates shall be corrected and/or
rationalised by the Architect or Consultant without any change to the Contract Sum
before the signing of the Contract. This means that the arithmetical error or other human
errors can be altered under the circumstances that the contract sum doesn’t get
affected.
As a consultant QS i would advise to correct any errors done in the rates for aluminium
windows by the contractor. This is still possible before binding and signing of any
contract documents. After rationalizing the rate according to the market, and with the
consent of the contractor, the agreement should be fairly dealt to all parties. One of the
ways a contractor can make extra money is by a method call front loading. This method
will only reduce the risk of the supplier but increases the risk for employer if the
construction does not proceed. For this case of the errors in rates for the aluminium
windows works being slightly low, after rationalizing, the rates should fall into a
reasonable rate.
Based on a case law of Sist Construction v State Electricity Commission of Victoria
[1982] VR 597 of 606, the contractor priced lower rates on the item where they believe
that the actual quantities are likely to be less than the quantity stated in BQ. Court held
that the contractor has to act reasonable when pricing the BQ and it is necessary for the
consultant to rationalize the BQ. The reason for rationalizing the quantities is so that it
can avoid any intentional and unintentional errors of the rates by the QS.
Question 2 (a)(b)
In accordance with clause 30.10 of the contract, the contractor duly submitted his Final
Accounts within 6 months after the issuance of the Certificate of Practical Completion.
You are then required to assess this application and prepare the Final Account for the
apartment project based of the following valuations and adjustments made to the
Contract Sum:
The Architect had granted the Contractor’s first application for extension of time and
approved additional insurance premium amounting to RM 30,000.00 in accordance with
clause 24 of the contract due to the delay in the completion of the works caused by the
Employer’s late decision on the toilet design.
In his second application for extension of time, the Contractor submitted an an
application for extension of time due to exceptionally inclement weather and a loss and
expense claim for RM120,000.00 in his Final Accounts to you. The Architect approved
the extension of time as per Clause 23.8.
Answer:
Pam 2006 with quantities stated that contractor need to submit all necessary document
within 6 months after the issuance of the Certificate of Practical Completion for
preparation of final account. Quantity Surveyor and Architect shall complete the final
account within 6 months from the receipt of all document from contractor.
Contractor’s first application regarding additional insurance premium of RM 30,000.00
which accordance with clause 24.4(a) due to delay in the completion of the works
caused by the Employer’s late decision on the toilet design which is clearly employer’s
default, due to employer’s late decision architect will have to issue late Architect
Instruction to contractor regarding the toilet design. RM 30,000 of additional losses shall
be granted to contractor.
Contractor’s second application regarding exceptionally inclement weather which he
incurred losses of RM 120,000.00. Contractor’s second application will not be grant due
to it is not under clause 24.3. Exceptionally inclement weather is a neutral event which
is no either contractor or employer default which contractor and employer shall bared
their own losses.
Nominated sub-contractor’s final account such as lift services, air conditioning services
and electrical services, the nominated sub-contractor final account sum will be add into
the final account and the profit will be 2% of the final sum and the attendance will
remain the same as the original amount.
On the other hand, provisional sums for guard house are awarded to the nominated
sub-contractor therefore RM 1,250,000.00 of the nominated sub-contractor final account
sum will be added into the final account and profit and attendance are included as well.
For the amount of profit and attendance for guard house will be 2% each of the final
sum of nominated sub-contractor’s final account.
Question 2 (c)(i)
The contractor had priced RM130,000.00 for the Contractor All Risk Insurance policy in
the Preliminaries Bills. The contractor failed to purchase this insurance when the works
commence. The Employer, then, bought and paid for the said insurance for
RM180,000.00 on behalf of the Contractor, for which the Contractor agreed. The
employer wants to recover this cost.
Answer:
Under the contract, it is the contractor’s responsibility to provide and purchase the
insurance. The preliminaries have included this item to be priced by the contractor.
Insurance is one of the most important item in the preliminaries which covers indemnity
for injury to person or loss and/or damage of property and indemnity to the employer.
Based on Clause 18.0 of PAM Contract 2006 (with Quantities), it clearly states the
importance of insurance.
The insurance which must be purchase by the contractor is:
● Contractor’s All Risk commonly abbreviated as ‘CAR’
● and insurance for Workmen’s Compensation or commonly referred to as ‘WC’.
Based on Clause 20.A.1 The insurance policy should be valid up to the Completion
Date and the extended maintenance cover shall be for the Defect Liability Period plus a
further three (3) Months.
Under clauses 20.A.3 stated if contractor makes default in insuring or continuing the
insure as aforesaid, the employer may insure against any risks in respect of which the
defaults has occurred and the amount of premiums and any other cost incurred or paid
by the employer shall be set-off by the employer under clause 30.4.
For this case, the Contractor had priced the insurance for RM130,000.00. Due to some
circumstances, he had failed to secure the insurance on time. The employer then
purchased the insurance on the Contractor’s behalf , however the insurance for the
work as quoted by the insurance company which was agreed by both parties came to
RM180,000.00 which means the Contractor had underpriced for the Insurance
Premium.
In order for the employer to recover his cost, the employer may choose to pay the
Contractor RM130,000.00 during the progress payment first, but set off RM180,000.00
at any time the employer wishes to do so. This means the Contractor bears the extra
cost of RM50,000.00 and it cannot be claimed from the employer. The employer’s right
to set off against this item and any other items is mentioned on Clause 30.4.
However, this set off is not to be included in the Final Account. This is based on Clause
30.11(f) which states that this matter shall not be included in the Final Account and are
matters to be resolved separately between Employer and the Contractor.
Question 2 (c)(ii)
Under the Preliminaries, the Contractor is required to provide a black and white
photocopier machine on site for the Resident Engineer’s use but this item was left un-
priced, i.e. BQ item was left blank in the rate/amount column in the contract document.
During the progress, the Architect instructed the Contractor to provide a colour
photocopier machine costing RM8,000.00 instead of the black and white one as
specified. Contractor submitted a variation claim for RM8,000.00.
Answer:
According to this situation, the contractor must firstly consider several factors before
claiming for variations. In accordance to Clause 11.1 in the PAM Contract 2006,
“Variation” is defined as the alteration or modification of the design, quality or quantity of
Works. Therefore, in this sense, the Contractor’s claim may be considered a variation
as the change was requested by the Architect. Stated in Clause 11.1 (a) is “the addition,
omission or substitution of any work…” which thusly applies, as stated in the preliminary
that “the Architect instructed the Contractor to provide a Color Photocopier Machine”.
According to Clause 11.6 (c), “where work is not of a similar character to as set out in
the Contract documents, the Valuation shall be at fair market rates and prices
determined by the Quantity Surveyor”. The case is presented as such that the black and
white photocopier machine was not given a price in the Contract Documents; thus, in
order to omit the Black and White Photocopier Machine from the preliminary, the
assigned Quantity Surveyor must determine the price of said item based on fair market
rates and prices.
Moreover, as stated in Clause 11.6 (e), “the rates and prices in the Contract Documents
shall determine the valuation of items omitted. If omissions substantially vary the
conditions under which any remaining items a of work are carried out, the price of such
remaining items shall be valued by under Clause 11.6(a), (b) or (c)”. Since it was
discerned that the Black and White Photocopier Machine stated in the preliminaries
were not priced, the Quantity Surveyor shall omit said item and ascertain or establish
the price of the varied item, in this case the Color Photocopier Machine, with basis on
Clause 11.6(a), (b) or (c).
To summarize and finalize in conclusion, the concerned Quantity Surveyor shall exclude
the price of the Black and White Photocopier Machine as it was not thusly priced on the
preliminaries. Subsequently, the price of the replacement item which in this instance,
the Color Photocopier Machine (RM 8,000.00), must be added with emphasis on fair
market rates and price. The price difference between the two items, which are the Black
and White Photocopier Machine and the Color Photocopier Machine, shall delineate as
the Variation. Finally, the Final Account must include the omission and addition of items
in detail and in accordance to Clause 30.11 (a), the Final Account of Works shall show
all the adjustments engendered in the Contract Sum.
Question 2 (c)(iii)
The Contractor had delivered to site all marble floor tiles needed for the lift lobbies as
specified in the contract and construction drawings. However the Architect decided to
use granite floor instead and instructed the Contractor to remove all the marble tiles
from site. The Contractor paid RM50,000.00 for the marble tiles. The Contractor
returned the marble tiles to the supplier but only managed a refund of RM30,000.00.
The Contractor submitted a claim for the loss of RM20,000.00 that he suffered.
Answer:
Based on PAM Contract 2006 (With Quantities), Clause 11.1 the term “Variation” means
the alteration or modification of the design, quality or quantity of the works. Supported
with Clause 11.1(c) which states that the removal from the site of any work executed or
materials and goods brought thereon by the Contractor for the purpose of the works
other than work, materials and goods which are not in accordance with the Contract. In
this case, a variation occur because Architect instructed the contractor to remove all the
marble floor tiles as specified in the contract and replace granite floor tiles which means
contractor able to claim for loss and expenses under the Clause 11.1(c).
In order to claim for the loss of RM20,000.00 that he suffered, contractor able to claim
under Clause 11.7 where a Variation has directly caused or likely to cause the
contractor suffer additional expenses for which he would not be paid under any
provisions in Clause 11.6. However, the contractor must claim for such additional
expenses followed the procedure written under Clause 11.7(a) and (b).
Beside this, contractor need to follow Clause 11.8, stated contractor shall keep
contemporaneous records to substantiate all his claims for additional expenses under
Clause 11.7 and shall submit all particulars to the Architect and Quantity Surveyor. All
such documents shall remain available in accordance with this clause until all claims
have been resolved.
Based on Clause 11.9, after the architect certified the amount of Variations and/or
additional expenses claimed by the Contractor under Clause 11.7, the amount shall be
added to the Contract Sum. When an Interim Certificate is issued after the date of
ascertainment such amount shall be included in the certificate.
At the same times, contractor must use his endeavours to prevent further loss because
the duty to mitigate is on the part of the claimant to take all reasonable steps to reduce
the extent of damage or loss suffered as a result of breach of contract. A party cannot
recover for loss that he could have avoided. In our situation, Contractor had perform the
duty of mitigate because he returned the marble tiles to the supplier however only
managed to refund RM30,000.00.
In Final account, under variation work will Additional for the granite tiles price,
Omissions RM50,000 and Additional Expenses Rm20,000.
Question 2 (c)(iv)
Mistake was made in the price for excavation through rocks at RM50 per m3. Item was
not rationalized during contract documentation. However, original quantity in BQ is 10
m3 but re-measured as-built quantity was 100 m3. The Contractor submitted a claim for
RM55,000 based on a revised rates of RM550 per m3 for the total quantity of 100 m3.
Answer:
According to this case, the significant change of quantity allowed contractor entitled to
claim a valid variation order. Under PAM Contract 2006 Clause 11.1 defined variation
as the alteration or modification of the design, quality or quantity of the Works and
supporting with Clause 11.1(a) which stated that any addition, omission or substitution
of any Work.
For this case, the variation is valued under PAM Contract 2006 Clause 11.6(b) which
the work is carried out in a similar character as set out in the Contract which is to
excavate through rocks and is executed under similar conditions but there is a
significant change in the quantity of work carried out. According Clause 11.6(b) stated
that the rates and prices in the Contract Documents shall be the basis for determining
the valuation which shall include a fair adjustment rates, which mean the Contractor will
only be paid RM50 per m3 as agreed in the Contract Document. On the part of
quantities, Clause 11.6(f) stated in respect of Provisional Quantity, the quantities stated
in the Contract Documents shall be re-measured by the Quantity Surveyor based on the
actual quantities executed. Hence, the Quantity Surveyor shall use the re-measured of
100 m3 as the actual quantities executed to value the work.
Besides, PAM Contract 2006 Clause 13.1 stated that any arithmetical errors or any
errors in the prices and rates shall be corrected and/or rationalised by the Architect or
Consultant without any change to the Contract Sum before signing the Contract.
Comply with Clause 11.1 also mentioned the Contractor should bear the entirely cost of
work if there is any changes intended to rectify any negligence, omission, default and/or
breach of contract by the Contractor. Hence, the Contractor should bare for all the rates
and prices once signed the Contract which include those mistakes and the rates or
prices whether are rationalised or not. In the case of Henry Boot Construction Ltd v
Alstom Combined Cycles (2000), the English Court of Appeal held that the rates and
prices in the Contract should be given full effect notwithstanding that the Contractor has
made a mistake in his tender. Although the Contractor has made a mistake in his
tender, the Contractor is still should bear for all the rates and prices of the Contract
when he signed the Contract.
In this case, although the Contractor is bear for the rates and prices in the Contract
Document. The Contractor can still be able to claim for the additional expenses incurred
under Quantum Meruit or under Loss & Expenses claim to recover his loss. Quantity
Surveyor can consider to value this variation by the fair market rates. For Loss &
expenses claim, the Contractor can claim under PAM Contract 2006 Clause 11.7 stated
that the Contractor may make a claim for additional expenses if the Contractor is not be
paid for the variation under any provisions in Clause 11.6. Other than that, Contractor
can also claim under Clause 24.3(k) which stated in the opinion of the Architect is not
reasonably accurate forecast of the quantity of work required. The Contractor can claim
for loss & expenses as the quantities was not rationalised during Contract
Documentation.
As result, the concerned Quantity Surveyor shall value this variation with the rate of
RM50 per m3 for 100 m3 which is RM5,000. The revised claim should transfer into the
Final Account as an adjustment to the Contract Sum. The Quantity Surveyor should
omission the provisional sums of RM500 that stated in original BQ and made an
adjustment of addition RM5,000 into the Final Account as based on PAM Contract 2006
Clause 30.11. Hence, the revised claim for the excavation through rocks is valued as
RM4,500 into the Final Account.

More Related Content

What's hot

Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2ahmong4
 
Pp2 coursework 2 201808
Pp2 coursework 2   201808Pp2 coursework 2   201808
Pp2 coursework 2 201808Arissa Loh
 
Pp2 assignment-final
Pp2 assignment-finalPp2 assignment-final
Pp2 assignment-finalashleyyeap
 
Professional Practice 2: Group Assignment
Professional Practice 2: Group AssignmentProfessional Practice 2: Group Assignment
Professional Practice 2: Group Assignment마 이환
 
A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006Melvin Lim
 
Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017DarrenTofu
 
ECA Workshop - Brief
ECA Workshop - BriefECA Workshop - Brief
ECA Workshop - BriefKai Yun Pang
 
Eca presentation
Eca presentationEca presentation
Eca presentationKailyn Lee
 
Professional Practice 1 Assignment
Professional Practice 1 AssignmentProfessional Practice 1 Assignment
Professional Practice 1 AssignmentMelvin Lim
 
Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1Sow Wei Henn
 
Software presentation
Software presentationSoftware presentation
Software presentationTimun Loh
 
ECA Presentation
ECA PresentationECA Presentation
ECA PresentationLee Pei Gie
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2Shze Hwa Lee
 

What's hot (20)

Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2
 
Pp2 coursework 2 201808
Pp2 coursework 2   201808Pp2 coursework 2   201808
Pp2 coursework 2 201808
 
Pp2 assignment-final
Pp2 assignment-finalPp2 assignment-final
Pp2 assignment-final
 
Professional Practice 2: Group Assignment
Professional Practice 2: Group AssignmentProfessional Practice 2: Group Assignment
Professional Practice 2: Group Assignment
 
A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006
 
Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017
 
PP2 COMPILCATION
PP2 COMPILCATIONPP2 COMPILCATION
PP2 COMPILCATION
 
ECA Workshop - Brief
ECA Workshop - BriefECA Workshop - Brief
ECA Workshop - Brief
 
Eca presentation
Eca presentationEca presentation
Eca presentation
 
Professional Practice 1 Assignment
Professional Practice 1 AssignmentProfessional Practice 1 Assignment
Professional Practice 1 Assignment
 
Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1
 
Software presentation
Software presentationSoftware presentation
Software presentation
 
ECA Presentation
ECA PresentationECA Presentation
ECA Presentation
 
PP1 report
PP1 reportPP1 report
PP1 report
 
ECA presentation
ECA presentationECA presentation
ECA presentation
 
Cl compilation
Cl compilationCl compilation
Cl compilation
 
Elemental Cost Analysis
Elemental Cost AnalysisElemental Cost Analysis
Elemental Cost Analysis
 
ECA form
ECA formECA form
ECA form
 
Site Possession
Site PossessionSite Possession
Site Possession
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2
 

Similar to PP2 Assignment: Group

Pp2 assignment
Pp2 assignmentPp2 assignment
Pp2 assignmentfareezsham
 
PP2 - Group Assignment
PP2 - Group AssignmentPP2 - Group Assignment
PP2 - Group AssignmentLin Hui
 
Pp2 assignment-final
Pp2 assignment-finalPp2 assignment-final
Pp2 assignment-finalashleyyeap
 
Pp2 group assignment
Pp2 group assignmentPp2 group assignment
Pp2 group assignmentlohwenjun
 
Professional Practice II (Group Assignment)
Professional Practice II (Group Assignment)Professional Practice II (Group Assignment)
Professional Practice II (Group Assignment)Yee Len Wan
 
Pp2 coursework 2
Pp2 coursework  2Pp2 coursework  2
Pp2 coursework 2tfkc1212
 
Assignment - Report
Assignment - ReportAssignment - Report
Assignment - ReportKai Yun Pang
 
Professional Practice II
Professional Practice IIProfessional Practice II
Professional Practice IIseenyeeyong
 
Suspension and Termination by Contractor Presentation.pptx
Suspension and Termination by Contractor Presentation.pptxSuspension and Termination by Contractor Presentation.pptx
Suspension and Termination by Contractor Presentation.pptxNathannielGonzales1
 
Pp2 coursework 1 p10
Pp2 coursework 1 p10 Pp2 coursework 1 p10
Pp2 coursework 1 p10 Farah Sham
 
CE-CONTRACTS-REPORT.pdf
CE-CONTRACTS-REPORT.pdfCE-CONTRACTS-REPORT.pdf
CE-CONTRACTS-REPORT.pdfChelDems
 
Pp2 coursework 2 201808
Pp2 coursework 2   201808Pp2 coursework 2   201808
Pp2 coursework 2 201808ashleyyeap
 
CONTRACT FOR PROJECT MANAGEMENT SERVICE (PMS)_CLEAN DRAFT.docx
CONTRACT FOR PROJECT MANAGEMENT SERVICE (PMS)_CLEAN DRAFT.docxCONTRACT FOR PROJECT MANAGEMENT SERVICE (PMS)_CLEAN DRAFT.docx
CONTRACT FOR PROJECT MANAGEMENT SERVICE (PMS)_CLEAN DRAFT.docxMeneerGultom
 
PP Seminar Tutorial 7
PP Seminar Tutorial 7PP Seminar Tutorial 7
PP Seminar Tutorial 7Farah Sham
 
Construction law update august 2015 quarter 2 a
Construction law update august 2015 quarter 2 aConstruction law update august 2015 quarter 2 a
Construction law update august 2015 quarter 2 aColin Tomlinson
 
Commercial and Construction Law Update Q2 2015
Commercial and Construction Law Update Q2 2015Commercial and Construction Law Update Q2 2015
Commercial and Construction Law Update Q2 2015Colin Tomlinson
 

Similar to PP2 Assignment: Group (20)

Pp2 assignment
Pp2 assignmentPp2 assignment
Pp2 assignment
 
PP2 - Group Assignment
PP2 - Group AssignmentPP2 - Group Assignment
PP2 - Group Assignment
 
Pp2 final report
Pp2 final reportPp2 final report
Pp2 final report
 
Pp2 assignment-final
Pp2 assignment-finalPp2 assignment-final
Pp2 assignment-final
 
Pp2 group assignment
Pp2 group assignmentPp2 group assignment
Pp2 group assignment
 
Professional Practice II (Group Assignment)
Professional Practice II (Group Assignment)Professional Practice II (Group Assignment)
Professional Practice II (Group Assignment)
 
Cl report final
Cl report finalCl report final
Cl report final
 
Pp2 coursework 2
Pp2 coursework  2Pp2 coursework  2
Pp2 coursework 2
 
Pp2 chapter 1 cheeyong & yih shyang
Pp2 chapter 1 cheeyong & yih shyangPp2 chapter 1 cheeyong & yih shyang
Pp2 chapter 1 cheeyong & yih shyang
 
Assignment - Report
Assignment - ReportAssignment - Report
Assignment - Report
 
Pp2 asignment-1
Pp2 asignment-1Pp2 asignment-1
Pp2 asignment-1
 
Professional Practice II
Professional Practice IIProfessional Practice II
Professional Practice II
 
Suspension and Termination by Contractor Presentation.pptx
Suspension and Termination by Contractor Presentation.pptxSuspension and Termination by Contractor Presentation.pptx
Suspension and Termination by Contractor Presentation.pptx
 
Pp2 coursework 1 p10
Pp2 coursework 1 p10 Pp2 coursework 1 p10
Pp2 coursework 1 p10
 
CE-CONTRACTS-REPORT.pdf
CE-CONTRACTS-REPORT.pdfCE-CONTRACTS-REPORT.pdf
CE-CONTRACTS-REPORT.pdf
 
Pp2 coursework 2 201808
Pp2 coursework 2   201808Pp2 coursework 2   201808
Pp2 coursework 2 201808
 
CONTRACT FOR PROJECT MANAGEMENT SERVICE (PMS)_CLEAN DRAFT.docx
CONTRACT FOR PROJECT MANAGEMENT SERVICE (PMS)_CLEAN DRAFT.docxCONTRACT FOR PROJECT MANAGEMENT SERVICE (PMS)_CLEAN DRAFT.docx
CONTRACT FOR PROJECT MANAGEMENT SERVICE (PMS)_CLEAN DRAFT.docx
 
PP Seminar Tutorial 7
PP Seminar Tutorial 7PP Seminar Tutorial 7
PP Seminar Tutorial 7
 
Construction law update august 2015 quarter 2 a
Construction law update august 2015 quarter 2 aConstruction law update august 2015 quarter 2 a
Construction law update august 2015 quarter 2 a
 
Commercial and Construction Law Update Q2 2015
Commercial and Construction Law Update Q2 2015Commercial and Construction Law Update Q2 2015
Commercial and Construction Law Update Q2 2015
 

More from Farah Sham

Conference Paper
Conference PaperConference Paper
Conference PaperFarah Sham
 
My Community Service Journal
My Community Service JournalMy Community Service Journal
My Community Service JournalFarah Sham
 
Orphanage Community Service Initiative
Orphanage Community Service InitiativeOrphanage Community Service Initiative
Orphanage Community Service InitiativeFarah Sham
 
Infographic Poster Report
Infographic Poster ReportInfographic Poster Report
Infographic Poster ReportFarah Sham
 
Hubungan Etnik Magazine Masyarakat India di Brickfiields
Hubungan Etnik Magazine Masyarakat India di BrickfiieldsHubungan Etnik Magazine Masyarakat India di Brickfiields
Hubungan Etnik Magazine Masyarakat India di BrickfiieldsFarah Sham
 
Strategic Management: Individual Assignment
Strategic Management: Individual AssignmentStrategic Management: Individual Assignment
Strategic Management: Individual AssignmentFarah Sham
 
Strategic Management Presentation
Strategic Management Presentation Strategic Management Presentation
Strategic Management Presentation Farah Sham
 
Strategic Management Group Report
Strategic Management Group ReportStrategic Management Group Report
Strategic Management Group ReportFarah Sham
 
Building Economics Tutorial
Building Economics TutorialBuilding Economics Tutorial
Building Economics TutorialFarah Sham
 
Building Economics Presentation
Building Economics PresentationBuilding Economics Presentation
Building Economics PresentationFarah Sham
 
A3 CONSTRUCTION METHODOLOGY
A3 CONSTRUCTION METHODOLOGYA3 CONSTRUCTION METHODOLOGY
A3 CONSTRUCTION METHODOLOGYFarah Sham
 
Building Economics Cost Data
Building Economics Cost Data Building Economics Cost Data
Building Economics Cost Data Farah Sham
 
Building Economics Cost Plan Report
Building Economics Cost Plan ReportBuilding Economics Cost Plan Report
Building Economics Cost Plan ReportFarah Sham
 
MEASUREMENT TENDER DOCUMENTATION
MEASUREMENT TENDER DOCUMENTATIONMEASUREMENT TENDER DOCUMENTATION
MEASUREMENT TENDER DOCUMENTATIONFarah Sham
 
Software application
Software application Software application
Software application Farah Sham
 
Project tender
Project tender Project tender
Project tender Farah Sham
 
Project tender
Project tenderProject tender
Project tenderFarah Sham
 
Software application for qs material standard rate
Software application for qs   material  standard rateSoftware application for qs   material  standard rate
Software application for qs material standard rateFarah Sham
 

More from Farah Sham (20)

Conference Paper
Conference PaperConference Paper
Conference Paper
 
My Community Service Journal
My Community Service JournalMy Community Service Journal
My Community Service Journal
 
Orphanage Community Service Initiative
Orphanage Community Service InitiativeOrphanage Community Service Initiative
Orphanage Community Service Initiative
 
Infographic Poster Report
Infographic Poster ReportInfographic Poster Report
Infographic Poster Report
 
Hubungan Etnik Magazine Masyarakat India di Brickfiields
Hubungan Etnik Magazine Masyarakat India di BrickfiieldsHubungan Etnik Magazine Masyarakat India di Brickfiields
Hubungan Etnik Magazine Masyarakat India di Brickfiields
 
Strategic Management: Individual Assignment
Strategic Management: Individual AssignmentStrategic Management: Individual Assignment
Strategic Management: Individual Assignment
 
Strategic Management Presentation
Strategic Management Presentation Strategic Management Presentation
Strategic Management Presentation
 
Strategic Management Group Report
Strategic Management Group ReportStrategic Management Group Report
Strategic Management Group Report
 
Building Economics Tutorial
Building Economics TutorialBuilding Economics Tutorial
Building Economics Tutorial
 
Building Economics Presentation
Building Economics PresentationBuilding Economics Presentation
Building Economics Presentation
 
A3 CONSTRUCTION METHODOLOGY
A3 CONSTRUCTION METHODOLOGYA3 CONSTRUCTION METHODOLOGY
A3 CONSTRUCTION METHODOLOGY
 
Building Economics Cost Data
Building Economics Cost Data Building Economics Cost Data
Building Economics Cost Data
 
Building Economics Cost Plan Report
Building Economics Cost Plan ReportBuilding Economics Cost Plan Report
Building Economics Cost Plan Report
 
MEASUREMENT TENDER DOCUMENTATION
MEASUREMENT TENDER DOCUMENTATIONMEASUREMENT TENDER DOCUMENTATION
MEASUREMENT TENDER DOCUMENTATION
 
Software application
Software application Software application
Software application
 
PP Seminar
PP SeminarPP Seminar
PP Seminar
 
Mega project
Mega projectMega project
Mega project
 
Project tender
Project tender Project tender
Project tender
 
Project tender
Project tenderProject tender
Project tender
 
Software application for qs material standard rate
Software application for qs   material  standard rateSoftware application for qs   material  standard rate
Software application for qs material standard rate
 

Recently uploaded

ICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxAreebaZafar22
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdfQucHHunhnh
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17Celine George
 
SOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning PresentationSOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning Presentationcamerronhm
 
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...ZurliaSoop
 
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17  How to Extend Models Using Mixin ClassesMixin Classes in Odoo 17  How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17 How to Extend Models Using Mixin ClassesCeline George
 
On National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsOn National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsMebane Rash
 
PROCESS RECORDING FORMAT.docx
PROCESS      RECORDING        FORMAT.docxPROCESS      RECORDING        FORMAT.docx
PROCESS RECORDING FORMAT.docxPoojaSen20
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfAdmir Softic
 
Spellings Wk 3 English CAPS CARES Please Practise
Spellings Wk 3 English CAPS CARES Please PractiseSpellings Wk 3 English CAPS CARES Please Practise
Spellings Wk 3 English CAPS CARES Please PractiseAnaAcapella
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdfQucHHunhnh
 
Micro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdfMicro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdfPoh-Sun Goh
 
Unit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptxUnit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptxVishalSingh1417
 
How to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POSHow to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POSCeline George
 
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...christianmathematics
 
The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxheathfieldcps1
 
Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)Jisc
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxVishalSingh1417
 
Food safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdfFood safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdfSherif Taha
 

Recently uploaded (20)

ICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptx
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17
 
Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024
 
SOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning PresentationSOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning Presentation
 
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
 
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17  How to Extend Models Using Mixin ClassesMixin Classes in Odoo 17  How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
 
On National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsOn National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan Fellows
 
PROCESS RECORDING FORMAT.docx
PROCESS      RECORDING        FORMAT.docxPROCESS      RECORDING        FORMAT.docx
PROCESS RECORDING FORMAT.docx
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdf
 
Spellings Wk 3 English CAPS CARES Please Practise
Spellings Wk 3 English CAPS CARES Please PractiseSpellings Wk 3 English CAPS CARES Please Practise
Spellings Wk 3 English CAPS CARES Please Practise
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
 
Micro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdfMicro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdf
 
Unit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptxUnit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptx
 
How to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POSHow to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POS
 
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
 
The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptx
 
Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptx
 
Food safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdfFood safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdf
 

PP2 Assignment: Group

  • 1. SCHOOL OF ARCHITECTURE, BUILDING & DESIGN BACHELOR OF QUANTITY SURVEYING (HONS) PROFESSIONAL PRACTICE II (QSB60904) CHAN YI FUNG 0323057 FARAH AIDA BINTI SHAHAR SHAM 0322962 KIEW CHEE YUAN 0323297 LIEW WEI ZHEAN 0331225 NURAFIQAH HAJI ABD ZARIFUL 0321196 TAN KEN RIC 0318631 YEE JYH LIN 0322408 LECTURER : SR EDDIE LIM SEK CHEON SUBMISSION DATE : 29th OCTOBER 2018 Question 1
  • 2. The Letter of Award for the above works was issued for RM 81,200,000.00 based on the tender sum submitted by the Contractor. As you were preparing the contract documents for binding and signature, you found some errors in the rates for aluminium windows works submitted by the Contractor, which were very low. Kindly advise the actions that you will take. Answer: Clause 13.1 states that the Contract Sum shall not be adjusted or altered in any way whatsoever, other than in accordance with the express provisions of the Contract. Any arithmetical errors or any errors in the prices and rates shall be corrected and/or rationalised by the Architect or Consultant without any change to the Contract Sum before the signing of the Contract. This means that the arithmetical error or other human errors can be altered under the circumstances that the contract sum doesn’t get affected. As a consultant QS i would advise to correct any errors done in the rates for aluminium windows by the contractor. This is still possible before binding and signing of any contract documents. After rationalizing the rate according to the market, and with the consent of the contractor, the agreement should be fairly dealt to all parties. One of the ways a contractor can make extra money is by a method call front loading. This method will only reduce the risk of the supplier but increases the risk for employer if the construction does not proceed. For this case of the errors in rates for the aluminium windows works being slightly low, after rationalizing, the rates should fall into a reasonable rate. Based on a case law of Sist Construction v State Electricity Commission of Victoria [1982] VR 597 of 606, the contractor priced lower rates on the item where they believe that the actual quantities are likely to be less than the quantity stated in BQ. Court held that the contractor has to act reasonable when pricing the BQ and it is necessary for the consultant to rationalize the BQ. The reason for rationalizing the quantities is so that it can avoid any intentional and unintentional errors of the rates by the QS. Question 2 (a)(b)
  • 3. In accordance with clause 30.10 of the contract, the contractor duly submitted his Final Accounts within 6 months after the issuance of the Certificate of Practical Completion. You are then required to assess this application and prepare the Final Account for the apartment project based of the following valuations and adjustments made to the Contract Sum: The Architect had granted the Contractor’s first application for extension of time and approved additional insurance premium amounting to RM 30,000.00 in accordance with clause 24 of the contract due to the delay in the completion of the works caused by the Employer’s late decision on the toilet design. In his second application for extension of time, the Contractor submitted an an application for extension of time due to exceptionally inclement weather and a loss and expense claim for RM120,000.00 in his Final Accounts to you. The Architect approved the extension of time as per Clause 23.8. Answer: Pam 2006 with quantities stated that contractor need to submit all necessary document within 6 months after the issuance of the Certificate of Practical Completion for preparation of final account. Quantity Surveyor and Architect shall complete the final account within 6 months from the receipt of all document from contractor. Contractor’s first application regarding additional insurance premium of RM 30,000.00 which accordance with clause 24.4(a) due to delay in the completion of the works caused by the Employer’s late decision on the toilet design which is clearly employer’s default, due to employer’s late decision architect will have to issue late Architect Instruction to contractor regarding the toilet design. RM 30,000 of additional losses shall be granted to contractor. Contractor’s second application regarding exceptionally inclement weather which he incurred losses of RM 120,000.00. Contractor’s second application will not be grant due to it is not under clause 24.3. Exceptionally inclement weather is a neutral event which is no either contractor or employer default which contractor and employer shall bared their own losses. Nominated sub-contractor’s final account such as lift services, air conditioning services and electrical services, the nominated sub-contractor final account sum will be add into
  • 4. the final account and the profit will be 2% of the final sum and the attendance will remain the same as the original amount. On the other hand, provisional sums for guard house are awarded to the nominated sub-contractor therefore RM 1,250,000.00 of the nominated sub-contractor final account sum will be added into the final account and profit and attendance are included as well. For the amount of profit and attendance for guard house will be 2% each of the final sum of nominated sub-contractor’s final account. Question 2 (c)(i) The contractor had priced RM130,000.00 for the Contractor All Risk Insurance policy in the Preliminaries Bills. The contractor failed to purchase this insurance when the works
  • 5. commence. The Employer, then, bought and paid for the said insurance for RM180,000.00 on behalf of the Contractor, for which the Contractor agreed. The employer wants to recover this cost. Answer: Under the contract, it is the contractor’s responsibility to provide and purchase the insurance. The preliminaries have included this item to be priced by the contractor. Insurance is one of the most important item in the preliminaries which covers indemnity for injury to person or loss and/or damage of property and indemnity to the employer. Based on Clause 18.0 of PAM Contract 2006 (with Quantities), it clearly states the importance of insurance. The insurance which must be purchase by the contractor is: ● Contractor’s All Risk commonly abbreviated as ‘CAR’ ● and insurance for Workmen’s Compensation or commonly referred to as ‘WC’. Based on Clause 20.A.1 The insurance policy should be valid up to the Completion Date and the extended maintenance cover shall be for the Defect Liability Period plus a further three (3) Months. Under clauses 20.A.3 stated if contractor makes default in insuring or continuing the insure as aforesaid, the employer may insure against any risks in respect of which the defaults has occurred and the amount of premiums and any other cost incurred or paid by the employer shall be set-off by the employer under clause 30.4. For this case, the Contractor had priced the insurance for RM130,000.00. Due to some circumstances, he had failed to secure the insurance on time. The employer then purchased the insurance on the Contractor’s behalf , however the insurance for the work as quoted by the insurance company which was agreed by both parties came to RM180,000.00 which means the Contractor had underpriced for the Insurance Premium. In order for the employer to recover his cost, the employer may choose to pay the Contractor RM130,000.00 during the progress payment first, but set off RM180,000.00 at any time the employer wishes to do so. This means the Contractor bears the extra cost of RM50,000.00 and it cannot be claimed from the employer. The employer’s right to set off against this item and any other items is mentioned on Clause 30.4.
  • 6. However, this set off is not to be included in the Final Account. This is based on Clause 30.11(f) which states that this matter shall not be included in the Final Account and are matters to be resolved separately between Employer and the Contractor. Question 2 (c)(ii) Under the Preliminaries, the Contractor is required to provide a black and white photocopier machine on site for the Resident Engineer’s use but this item was left un- priced, i.e. BQ item was left blank in the rate/amount column in the contract document. During the progress, the Architect instructed the Contractor to provide a colour
  • 7. photocopier machine costing RM8,000.00 instead of the black and white one as specified. Contractor submitted a variation claim for RM8,000.00. Answer: According to this situation, the contractor must firstly consider several factors before claiming for variations. In accordance to Clause 11.1 in the PAM Contract 2006, “Variation” is defined as the alteration or modification of the design, quality or quantity of Works. Therefore, in this sense, the Contractor’s claim may be considered a variation as the change was requested by the Architect. Stated in Clause 11.1 (a) is “the addition, omission or substitution of any work…” which thusly applies, as stated in the preliminary that “the Architect instructed the Contractor to provide a Color Photocopier Machine”. According to Clause 11.6 (c), “where work is not of a similar character to as set out in the Contract documents, the Valuation shall be at fair market rates and prices determined by the Quantity Surveyor”. The case is presented as such that the black and white photocopier machine was not given a price in the Contract Documents; thus, in order to omit the Black and White Photocopier Machine from the preliminary, the assigned Quantity Surveyor must determine the price of said item based on fair market rates and prices. Moreover, as stated in Clause 11.6 (e), “the rates and prices in the Contract Documents shall determine the valuation of items omitted. If omissions substantially vary the conditions under which any remaining items a of work are carried out, the price of such remaining items shall be valued by under Clause 11.6(a), (b) or (c)”. Since it was discerned that the Black and White Photocopier Machine stated in the preliminaries were not priced, the Quantity Surveyor shall omit said item and ascertain or establish the price of the varied item, in this case the Color Photocopier Machine, with basis on Clause 11.6(a), (b) or (c). To summarize and finalize in conclusion, the concerned Quantity Surveyor shall exclude the price of the Black and White Photocopier Machine as it was not thusly priced on the preliminaries. Subsequently, the price of the replacement item which in this instance, the Color Photocopier Machine (RM 8,000.00), must be added with emphasis on fair market rates and price. The price difference between the two items, which are the Black and White Photocopier Machine and the Color Photocopier Machine, shall delineate as the Variation. Finally, the Final Account must include the omission and addition of items in detail and in accordance to Clause 30.11 (a), the Final Account of Works shall show all the adjustments engendered in the Contract Sum.
  • 8. Question 2 (c)(iii) The Contractor had delivered to site all marble floor tiles needed for the lift lobbies as specified in the contract and construction drawings. However the Architect decided to use granite floor instead and instructed the Contractor to remove all the marble tiles from site. The Contractor paid RM50,000.00 for the marble tiles. The Contractor returned the marble tiles to the supplier but only managed a refund of RM30,000.00. The Contractor submitted a claim for the loss of RM20,000.00 that he suffered.
  • 9. Answer: Based on PAM Contract 2006 (With Quantities), Clause 11.1 the term “Variation” means the alteration or modification of the design, quality or quantity of the works. Supported with Clause 11.1(c) which states that the removal from the site of any work executed or materials and goods brought thereon by the Contractor for the purpose of the works other than work, materials and goods which are not in accordance with the Contract. In this case, a variation occur because Architect instructed the contractor to remove all the marble floor tiles as specified in the contract and replace granite floor tiles which means contractor able to claim for loss and expenses under the Clause 11.1(c). In order to claim for the loss of RM20,000.00 that he suffered, contractor able to claim under Clause 11.7 where a Variation has directly caused or likely to cause the contractor suffer additional expenses for which he would not be paid under any provisions in Clause 11.6. However, the contractor must claim for such additional expenses followed the procedure written under Clause 11.7(a) and (b). Beside this, contractor need to follow Clause 11.8, stated contractor shall keep contemporaneous records to substantiate all his claims for additional expenses under Clause 11.7 and shall submit all particulars to the Architect and Quantity Surveyor. All such documents shall remain available in accordance with this clause until all claims have been resolved. Based on Clause 11.9, after the architect certified the amount of Variations and/or additional expenses claimed by the Contractor under Clause 11.7, the amount shall be added to the Contract Sum. When an Interim Certificate is issued after the date of ascertainment such amount shall be included in the certificate. At the same times, contractor must use his endeavours to prevent further loss because the duty to mitigate is on the part of the claimant to take all reasonable steps to reduce the extent of damage or loss suffered as a result of breach of contract. A party cannot recover for loss that he could have avoided. In our situation, Contractor had perform the duty of mitigate because he returned the marble tiles to the supplier however only managed to refund RM30,000.00. In Final account, under variation work will Additional for the granite tiles price, Omissions RM50,000 and Additional Expenses Rm20,000.
  • 10. Question 2 (c)(iv) Mistake was made in the price for excavation through rocks at RM50 per m3. Item was not rationalized during contract documentation. However, original quantity in BQ is 10 m3 but re-measured as-built quantity was 100 m3. The Contractor submitted a claim for RM55,000 based on a revised rates of RM550 per m3 for the total quantity of 100 m3. Answer:
  • 11. According to this case, the significant change of quantity allowed contractor entitled to claim a valid variation order. Under PAM Contract 2006 Clause 11.1 defined variation as the alteration or modification of the design, quality or quantity of the Works and supporting with Clause 11.1(a) which stated that any addition, omission or substitution of any Work. For this case, the variation is valued under PAM Contract 2006 Clause 11.6(b) which the work is carried out in a similar character as set out in the Contract which is to excavate through rocks and is executed under similar conditions but there is a significant change in the quantity of work carried out. According Clause 11.6(b) stated that the rates and prices in the Contract Documents shall be the basis for determining the valuation which shall include a fair adjustment rates, which mean the Contractor will only be paid RM50 per m3 as agreed in the Contract Document. On the part of quantities, Clause 11.6(f) stated in respect of Provisional Quantity, the quantities stated in the Contract Documents shall be re-measured by the Quantity Surveyor based on the actual quantities executed. Hence, the Quantity Surveyor shall use the re-measured of 100 m3 as the actual quantities executed to value the work. Besides, PAM Contract 2006 Clause 13.1 stated that any arithmetical errors or any errors in the prices and rates shall be corrected and/or rationalised by the Architect or Consultant without any change to the Contract Sum before signing the Contract. Comply with Clause 11.1 also mentioned the Contractor should bear the entirely cost of work if there is any changes intended to rectify any negligence, omission, default and/or breach of contract by the Contractor. Hence, the Contractor should bare for all the rates and prices once signed the Contract which include those mistakes and the rates or prices whether are rationalised or not. In the case of Henry Boot Construction Ltd v Alstom Combined Cycles (2000), the English Court of Appeal held that the rates and prices in the Contract should be given full effect notwithstanding that the Contractor has made a mistake in his tender. Although the Contractor has made a mistake in his tender, the Contractor is still should bear for all the rates and prices of the Contract when he signed the Contract. In this case, although the Contractor is bear for the rates and prices in the Contract Document. The Contractor can still be able to claim for the additional expenses incurred under Quantum Meruit or under Loss & Expenses claim to recover his loss. Quantity Surveyor can consider to value this variation by the fair market rates. For Loss & expenses claim, the Contractor can claim under PAM Contract 2006 Clause 11.7 stated that the Contractor may make a claim for additional expenses if the Contractor is not be paid for the variation under any provisions in Clause 11.6. Other than that, Contractor
  • 12. can also claim under Clause 24.3(k) which stated in the opinion of the Architect is not reasonably accurate forecast of the quantity of work required. The Contractor can claim for loss & expenses as the quantities was not rationalised during Contract Documentation. As result, the concerned Quantity Surveyor shall value this variation with the rate of RM50 per m3 for 100 m3 which is RM5,000. The revised claim should transfer into the Final Account as an adjustment to the Contract Sum. The Quantity Surveyor should omission the provisional sums of RM500 that stated in original BQ and made an adjustment of addition RM5,000 into the Final Account as based on PAM Contract 2006 Clause 30.11. Hence, the revised claim for the excavation through rocks is valued as RM4,500 into the Final Account.