Strategic Projects Report – Q3
Content:
Term Shift, MC-LC Cooperation Customization
towards LCs potential, Financial Model,
Term Shift Mgmt Report
Q32013
Goals of the project
Optimizing timeline of organizational general
processes towards external, internal &
network realities to boost ELD long term
performance while maintaining members’
high quality AIESEC experience.
Milestones of the project
• Presentation of the idea during SumCo, gaining trust of AIESEC in
Poland towards possible change
• Data collection and preperations
• ST work
• Gathering BOA feedback
• Compendium correction preperation – I + II
• Voting for the change on General Assembly - I
• Presentation of the proposal to the LCPs with gathering topics to
work on
• Voting for the change on General Assembly - II
• Providing education towards change management
• Monitoring Implementation
I – term shift 13.14
II – term shift 2015
Overall Factors
• Well planned timeline - P
• SumCo shocking teraphy for the network – P
• LCPs highly open for changes, having trust in MC – P
• High-quality outcome of ST work - P
• Talking, talking, talking – P
Term Shift Mgmt in Q3 2013
Key Achievements:
• Completed decision
making process - Annual
Term will be
incorporated to AIESEC
in Poland from 2015!
• Trust of the network
towards the change
• AIESEC in Poland
(MC, LCs) has a calendar
for 2 years in advance ;]
Key Non-Achievements
• Lack of functional
feedback and analysis of
term shift impact for the
area
Term Shift Mgmt
in upcoming time
Priorities for October:
• Functional (MCVP)
analysis for LCs’ structure
recommendation
• Analysis consolidation
(OD)
• (!!!) Assuming initial
structure for MC 14.15
[crucial for creation LC
structures]
Priorities for Q4:
• Releasing MC
recommendations
towards 2014 local
structues (Virtually or
Physically)
• (!!!) Transition for EBs
[5W]
MC-LC Cooperation
Customization Report
August 2013
Goals of the project
Designing & providing strategic organizational
initiatives connecting MC and LC in a way to:
• enable LCs’ short-term growth
• enable LCs’ capitalization on own potential
• address diversity of LC realities
• maximize on the limited limeline & resources
Piliars of the project
Coaching
National
Conference
Cycle
LC Planning
Milestones of the
Coaching sub-project
• Current state analysis
• Desired state envisioning
• Coaching strategy creation
• Feedback gathering & correction
• Coaching application releasment
• LC Coaches allocation
• LC Coaches announcement
• Creation of coaching tools
• Coaches education
• Coaches and coaching timeline management
• Coaching round feedback gathering & evaluation
• Coaching strategy improvement
Overall Factors
1st part of the new coaching strategy is almost done—
creation of strategy and materials, education & visits (last
visits are already scheduled).
More than 70% of all coaching visits have been deliver to
the LCs.
Good response from the LCs and MC.
Better understanding of the local reality.
Coaching sub-project
in Q3 2013
Key Achievements:
• Current state analysis
• Desired state envisioning
• Coaching strategy creation
• Feedback gathering &
correction
• Coaching application
releasment
• LC Coaches allocation
• LC Coaches announcement
• Creation of coaching tools
• Coaches education
• Coaches and coaching
timeline management
Key Non-Achievements
• Materials in the teambox
are incomplete.
• Not all the areas that
were assigned are going
to deliver coaching.
Coaching sub-project
in upcoming time
Priorities for October:
• Send coaching evaluation
(part 1)
• GDC- 1st Monthly skype
meeting.
• Gathering of all outputs.
Priorities for Q4:
• General Tracking.
Milestones of the National
Conference Cycle sub-project
• Current state analysis
• Desired state envisioning
• National Conference Cycle creation
• Feedback gathering & correction
• Conference Cycle I + application releasment
• SumCo preperations & delivery management
• SumCo evaluation
• Organizing LCs allocation
Milestones of the National
Conference Cycle sub-project
• Summits preperations & delivery management
• Conference Cycle II + application releasment
• Summits preperations & delivery management
• Summits evaluation
• Winco preperations & delivery management
• Winco evaluation
• MultiTo preperations & delivery management
• Multito evaluation
• Further platforms preperations & delivery
management
• Further platforms evaluation
Overall Factors
• Querulous but soo talented MC Team!  Great SumCo
& ELD Summitt (!) Delivery - P
• Lack of LCPs responsibility for common good – late
selection or lack of hosting LC – N
• Lack of Conference Manager role assignment at the
beginning of the term - N
• Skip of Ewa as WinCo Conference Manager - N
National Conference Cycle
in Q3 2013
Key Achievements:
• Long term, refreshed
conference cycle creation
• SumCo delivery
• ELD Summitt delivery
Key Non-Achievements:
• No physical NPM ;(
• Lack of OD – TM – NET
rules of cooperation
establishment towards
WinCo
• No Conferenace
Managers for upcoming
conferences
National Conference Cycle
in upcoming time
Priorities for October:
• Conference Managers
Assignment!
• OD – TM – NET meeting
for WinCo
Priorities for Q4:
• External Summitt Delivery
• WinCo Preperations
Management & Delivery
Milestones of the LC Planning sub-
project
• Planning 2013 evaluation [MCVP OD, BOA, ST]
• Desired state envisioning
• Planning process creation
• Feedback gathering & correction
• Planning process elements delegating
• Providing feedback & correction
• Planning process consolidation
• Planning process educating [NMP]
• Planning process implementation monitoring
• LC plans gathering
• Feedback towards LC plans by MC team
• LC plans correction
• Final consolidation of LC plans
Overall Factors
• BOA advices – P
• DRAMATIC timeline for process creation & consolidation
– N
• Limited psychical platforms for contact with MC Team –
N
• Simply too much priorities in the same time of the whole
team - N
• Virtual Education – N
• Low alignment to the proces of LCPs - N
LC Planning in Q3 2013
Key Achievements:
• Planning 2014 being
released!
– Logic of the process
– Tools (AMS )
Key Non-Achievements
• Lack of process
importance
understanding among
LCs
• Virtual education
Key priorities in October:
• LCs progres monitoring
• Feedback process
creation
Key priorities in Q4:
• LCs progress monitoring
• Feedback process
delivery
• LC 2014 Plans gathering
• Plans Transition &
Review strategy creation
LC Planning in upcoming time
Financial Model Report
Q3 2013
Goals of the project
• Increasing financial sustainability of
organisation
• Filling income gap hole in MC budget
• Ensuring aligment of MoS between MC &
LC
Milestones of the project
• Collecting data from LCs – 09.09.13 - DONE
• Analysis done by FD – 30.09.13- in progress
• First WG meeting – 12-23.10.13 – to be done
• Second WG meeting – 14-16.11.13
• Output creation – 22.11.13
• Presentation to the network 12.12.13
• Voting new Financial Model – 26.01.14
Overall Factors
• Other priorities during this Quarter
• Timeline of the project is more focused on
work in Q4
• Great support from our BoA !
Financial Model in Q3 2013
Key Achievements:
• Understending of project
by @PLAD during
SumCo
• Data needed is gathered
from LCs
• Application released
Key Non-Achievements
• Lack of data analysys yet
• Timeline of the project
shifted
Financial Model in Q4
Key strategies for next
month:
• Work, work, work
• Meetings with WG
• Creation of redistribution
model
Key challenges for next
month:
• Application for WG
• A lot of strategic projects
for Finance area at the
same time

Q3 strategic projects report

  • 1.
    Strategic Projects Report– Q3 Content: Term Shift, MC-LC Cooperation Customization towards LCs potential, Financial Model,
  • 2.
    Term Shift MgmtReport Q32013
  • 3.
    Goals of theproject Optimizing timeline of organizational general processes towards external, internal & network realities to boost ELD long term performance while maintaining members’ high quality AIESEC experience.
  • 4.
    Milestones of theproject • Presentation of the idea during SumCo, gaining trust of AIESEC in Poland towards possible change • Data collection and preperations • ST work • Gathering BOA feedback • Compendium correction preperation – I + II • Voting for the change on General Assembly - I • Presentation of the proposal to the LCPs with gathering topics to work on • Voting for the change on General Assembly - II • Providing education towards change management • Monitoring Implementation I – term shift 13.14 II – term shift 2015
  • 5.
    Overall Factors • Wellplanned timeline - P • SumCo shocking teraphy for the network – P • LCPs highly open for changes, having trust in MC – P • High-quality outcome of ST work - P • Talking, talking, talking – P
  • 6.
    Term Shift Mgmtin Q3 2013 Key Achievements: • Completed decision making process - Annual Term will be incorporated to AIESEC in Poland from 2015! • Trust of the network towards the change • AIESEC in Poland (MC, LCs) has a calendar for 2 years in advance ;] Key Non-Achievements • Lack of functional feedback and analysis of term shift impact for the area
  • 7.
    Term Shift Mgmt inupcoming time Priorities for October: • Functional (MCVP) analysis for LCs’ structure recommendation • Analysis consolidation (OD) • (!!!) Assuming initial structure for MC 14.15 [crucial for creation LC structures] Priorities for Q4: • Releasing MC recommendations towards 2014 local structues (Virtually or Physically) • (!!!) Transition for EBs [5W]
  • 8.
  • 9.
    Goals of theproject Designing & providing strategic organizational initiatives connecting MC and LC in a way to: • enable LCs’ short-term growth • enable LCs’ capitalization on own potential • address diversity of LC realities • maximize on the limited limeline & resources
  • 10.
    Piliars of theproject Coaching National Conference Cycle LC Planning
  • 11.
    Milestones of the Coachingsub-project • Current state analysis • Desired state envisioning • Coaching strategy creation • Feedback gathering & correction • Coaching application releasment • LC Coaches allocation • LC Coaches announcement • Creation of coaching tools • Coaches education • Coaches and coaching timeline management • Coaching round feedback gathering & evaluation • Coaching strategy improvement
  • 12.
    Overall Factors 1st partof the new coaching strategy is almost done— creation of strategy and materials, education & visits (last visits are already scheduled). More than 70% of all coaching visits have been deliver to the LCs. Good response from the LCs and MC. Better understanding of the local reality.
  • 13.
    Coaching sub-project in Q32013 Key Achievements: • Current state analysis • Desired state envisioning • Coaching strategy creation • Feedback gathering & correction • Coaching application releasment • LC Coaches allocation • LC Coaches announcement • Creation of coaching tools • Coaches education • Coaches and coaching timeline management Key Non-Achievements • Materials in the teambox are incomplete. • Not all the areas that were assigned are going to deliver coaching.
  • 14.
    Coaching sub-project in upcomingtime Priorities for October: • Send coaching evaluation (part 1) • GDC- 1st Monthly skype meeting. • Gathering of all outputs. Priorities for Q4: • General Tracking.
  • 15.
    Milestones of theNational Conference Cycle sub-project • Current state analysis • Desired state envisioning • National Conference Cycle creation • Feedback gathering & correction • Conference Cycle I + application releasment • SumCo preperations & delivery management • SumCo evaluation • Organizing LCs allocation
  • 16.
    Milestones of theNational Conference Cycle sub-project • Summits preperations & delivery management • Conference Cycle II + application releasment • Summits preperations & delivery management • Summits evaluation • Winco preperations & delivery management • Winco evaluation • MultiTo preperations & delivery management • Multito evaluation • Further platforms preperations & delivery management • Further platforms evaluation
  • 17.
    Overall Factors • Querulousbut soo talented MC Team!  Great SumCo & ELD Summitt (!) Delivery - P • Lack of LCPs responsibility for common good – late selection or lack of hosting LC – N • Lack of Conference Manager role assignment at the beginning of the term - N • Skip of Ewa as WinCo Conference Manager - N
  • 18.
    National Conference Cycle inQ3 2013 Key Achievements: • Long term, refreshed conference cycle creation • SumCo delivery • ELD Summitt delivery Key Non-Achievements: • No physical NPM ;( • Lack of OD – TM – NET rules of cooperation establishment towards WinCo • No Conferenace Managers for upcoming conferences
  • 19.
    National Conference Cycle inupcoming time Priorities for October: • Conference Managers Assignment! • OD – TM – NET meeting for WinCo Priorities for Q4: • External Summitt Delivery • WinCo Preperations Management & Delivery
  • 20.
    Milestones of theLC Planning sub- project • Planning 2013 evaluation [MCVP OD, BOA, ST] • Desired state envisioning • Planning process creation • Feedback gathering & correction • Planning process elements delegating • Providing feedback & correction • Planning process consolidation • Planning process educating [NMP] • Planning process implementation monitoring • LC plans gathering • Feedback towards LC plans by MC team • LC plans correction • Final consolidation of LC plans
  • 21.
    Overall Factors • BOAadvices – P • DRAMATIC timeline for process creation & consolidation – N • Limited psychical platforms for contact with MC Team – N • Simply too much priorities in the same time of the whole team - N • Virtual Education – N • Low alignment to the proces of LCPs - N
  • 22.
    LC Planning inQ3 2013 Key Achievements: • Planning 2014 being released! – Logic of the process – Tools (AMS ) Key Non-Achievements • Lack of process importance understanding among LCs • Virtual education
  • 23.
    Key priorities inOctober: • LCs progres monitoring • Feedback process creation Key priorities in Q4: • LCs progress monitoring • Feedback process delivery • LC 2014 Plans gathering • Plans Transition & Review strategy creation LC Planning in upcoming time
  • 24.
  • 25.
    Goals of theproject • Increasing financial sustainability of organisation • Filling income gap hole in MC budget • Ensuring aligment of MoS between MC & LC
  • 26.
    Milestones of theproject • Collecting data from LCs – 09.09.13 - DONE • Analysis done by FD – 30.09.13- in progress • First WG meeting – 12-23.10.13 – to be done • Second WG meeting – 14-16.11.13 • Output creation – 22.11.13 • Presentation to the network 12.12.13 • Voting new Financial Model – 26.01.14
  • 27.
    Overall Factors • Otherpriorities during this Quarter • Timeline of the project is more focused on work in Q4 • Great support from our BoA !
  • 28.
    Financial Model inQ3 2013 Key Achievements: • Understending of project by @PLAD during SumCo • Data needed is gathered from LCs • Application released Key Non-Achievements • Lack of data analysys yet • Timeline of the project shifted
  • 29.
    Financial Model inQ4 Key strategies for next month: • Work, work, work • Meetings with WG • Creation of redistribution model Key challenges for next month: • Application for WG • A lot of strategic projects for Finance area at the same time