Rig Name/#: BENNEVIS JSA Number : MA 001 Person Approving JSA :
Work Activity (Job):Tanks &
Preloads Visual Inspection Date Raised : 04-OCT-2007
Work Team (Crew Members):
B.E/ ABE/ Lead Roustabout
Sequence of Basic Job Steps Potential Accidents or Hazards
Recommendation to Eliminate or Reduce Potential
Hazards
Who?
Initials
1. Hold pre-job meeting & work-permit 1. Procedures not known or not understood by crew member 1. Take time to read correctly JSA . Be sure everything is
understood. If not ask your Supervisor
BE
2 . Prepare and inspect tools needed for the
job : Lights ( torch or 24 v lights ) – Fall.
arrestor & Tripod support to go inside –
Harness - Gas detector – Air blower
2. Low batteries on lights ( no visibility ) – Using wrong voltage
(110 v/ 220 v) - Falling in tank from ladder – Poor atmosphere
condition can cause people to pass out or die
2. Inspect all tools needed for the job before to ensure
proper use
All
involved
3. Inspect atmospheric conditions of tank
before entering
3. Gas concentration – Poor atmospheric condition 3. Check gas detection. Ventilate the tank SAF-BE
4. Enter tank 4. Falling from ladder 4. Use fall arrestor & harness BE-ABE
5. Tank inspection 5. Lighting problem ( no visibility ) – Electric shock –
Tripping – Falling in tank compartment
5. Be sure there is enough batteries in torch – Be sure you
are using 24 volts lighting equipment – Good visibility in tank
Stand-by man outside tank all the time during inspection
BE-ABE-
Electrician
6. Exit tank 6. Same as step #4 6. Same as step #4
Safety Equipment To Do This Job
Page 1 of 2
Pyramid Drilling S.A
Manual Title: Personnel Safety Manual
Form Name: Job Safety Analysis
Issue Date
02-Sept-07
Revision No.
2
Revision Date
04-OCTOBER 07
Prepared By
QA/HSE
Approved By
HS
Level No.
2
Hard Hats x Cotton Gloves x Face Shield ( Fire Extinguishers (
Safety Boots x
Work Vest ( Goggles x Lockout/Tagout (
Safety Glasses x
Safety Harness x Barriers ( Work Permit Required x
Page 2 of 2
Pyramid Drilling S.A
Manual Title: Personnel Safety Manual
Form Name: Job Safety Analysis
Issue Date
02-Sept-07
Revision No.
2
Revision Date
04-OCTOBER 07
Prepared By
QA/HSE
Approved By
HS
Level No.
2

More Related Content

What's hot

Job safety Analysis
Job safety Analysis Job safety Analysis
Job safety Analysis Deepu Rajan
 
Ma 018 changing lifeboats wires
Ma 018 changing lifeboats wiresMa 018 changing lifeboats wires
Ma 018 changing lifeboats wiresYousif Fikry
 
Risk assessment for testing & commissioning of cranes
Risk assessment for  testing & commissioning of cranesRisk assessment for  testing & commissioning of cranes
Risk assessment for testing & commissioning of cranesAzmeel Contracting Company
 
Lifting Equipment
Lifting Equipment Lifting Equipment
Lifting Equipment Manish Yadav
 
A Part 6 Lifting Operations
A  Part 6 Lifting OperationsA  Part 6 Lifting Operations
A Part 6 Lifting OperationsJames McCann
 
Jha rock drill use and maintenance romo
Jha rock drill use and maintenance romoJha rock drill use and maintenance romo
Jha rock drill use and maintenance romonafable
 
Overhead Crane Safety and Inspection Requirements by NPCA
Overhead Crane Safety and Inspection Requirements by NPCAOverhead Crane Safety and Inspection Requirements by NPCA
Overhead Crane Safety and Inspection Requirements by NPCAAtlantic Training, LLC.
 
252113184 method-statement-for-office-container-and-equipment-mobilization (1)
252113184 method-statement-for-office-container-and-equipment-mobilization (1)252113184 method-statement-for-office-container-and-equipment-mobilization (1)
252113184 method-statement-for-office-container-and-equipment-mobilization (1)DusanJankovic8
 
Lifting steam drum 72 ton by winch
Lifting steam drum 72 ton by winchLifting steam drum 72 ton by winch
Lifting steam drum 72 ton by winchHaGun Gunawan
 
Overhead crane risk assessment
Overhead crane risk assessmentOverhead crane risk assessment
Overhead crane risk assessmentSimba Zhao
 
LIFTING OPERATIONS BEST PRACTICES - SEMINAR 1
LIFTING OPERATIONS BEST PRACTICES - SEMINAR 1LIFTING OPERATIONS BEST PRACTICES - SEMINAR 1
LIFTING OPERATIONS BEST PRACTICES - SEMINAR 1Sreenath Pokkadavath
 
Ma 013 testing lifeboats capsules
Ma 013  testing  lifeboats  capsulesMa 013  testing  lifeboats  capsules
Ma 013 testing lifeboats capsulesYousif Fikry
 
Safety Tip: 10 Steps to Safer Crane Operation
Safety Tip: 10 Steps to Safer Crane OperationSafety Tip: 10 Steps to Safer Crane Operation
Safety Tip: 10 Steps to Safer Crane OperationComplianceSigns, LLC
 
Ma 016 unloading coiled tubing real from boat & install it on cantilever deck
Ma 016  unloading coiled tubing real from boat & install it on cantilever deckMa 016  unloading coiled tubing real from boat & install it on cantilever deck
Ma 016 unloading coiled tubing real from boat & install it on cantilever deckYousif Fikry
 

What's hot (20)

Job safety Analysis
Job safety Analysis Job safety Analysis
Job safety Analysis
 
Ma 018 changing lifeboats wires
Ma 018 changing lifeboats wiresMa 018 changing lifeboats wires
Ma 018 changing lifeboats wires
 
update 20feb1
update 20feb1update 20feb1
update 20feb1
 
Risk assessment for testing & commissioning of cranes
Risk assessment for  testing & commissioning of cranesRisk assessment for  testing & commissioning of cranes
Risk assessment for testing & commissioning of cranes
 
Lifting Equipment
Lifting Equipment Lifting Equipment
Lifting Equipment
 
A Part 6 Lifting Operations
A  Part 6 Lifting OperationsA  Part 6 Lifting Operations
A Part 6 Lifting Operations
 
SDV-20253 VALVE MOD 9 lift plan 1
SDV-20253 VALVE MOD 9 lift plan 1SDV-20253 VALVE MOD 9 lift plan 1
SDV-20253 VALVE MOD 9 lift plan 1
 
Jha rock drill use and maintenance romo
Jha rock drill use and maintenance romoJha rock drill use and maintenance romo
Jha rock drill use and maintenance romo
 
PA PIPE WORK 14 inch spool TH11177-06-PI-10-004-5
PA PIPE WORK 14 inch spool TH11177-06-PI-10-004-5PA PIPE WORK 14 inch spool TH11177-06-PI-10-004-5
PA PIPE WORK 14 inch spool TH11177-06-PI-10-004-5
 
Overhead Crane Safety and Inspection Requirements by NPCA
Overhead Crane Safety and Inspection Requirements by NPCAOverhead Crane Safety and Inspection Requirements by NPCA
Overhead Crane Safety and Inspection Requirements by NPCA
 
252113184 method-statement-for-office-container-and-equipment-mobilization (1)
252113184 method-statement-for-office-container-and-equipment-mobilization (1)252113184 method-statement-for-office-container-and-equipment-mobilization (1)
252113184 method-statement-for-office-container-and-equipment-mobilization (1)
 
Lifting steam drum 72 ton by winch
Lifting steam drum 72 ton by winchLifting steam drum 72 ton by winch
Lifting steam drum 72 ton by winch
 
Crane Operation - Lifting
Crane Operation -  LiftingCrane Operation -  Lifting
Crane Operation - Lifting
 
Overhead crane risk assessment
Overhead crane risk assessmentOverhead crane risk assessment
Overhead crane risk assessment
 
LIFTING OPERATIONS BEST PRACTICES - SEMINAR 1
LIFTING OPERATIONS BEST PRACTICES - SEMINAR 1LIFTING OPERATIONS BEST PRACTICES - SEMINAR 1
LIFTING OPERATIONS BEST PRACTICES - SEMINAR 1
 
Jsa heat-treatment
Jsa  heat-treatmentJsa  heat-treatment
Jsa heat-treatment
 
Ma 013 testing lifeboats capsules
Ma 013  testing  lifeboats  capsulesMa 013  testing  lifeboats  capsules
Ma 013 testing lifeboats capsules
 
Safety Tip: 10 Steps to Safer Crane Operation
Safety Tip: 10 Steps to Safer Crane OperationSafety Tip: 10 Steps to Safer Crane Operation
Safety Tip: 10 Steps to Safer Crane Operation
 
Standards Regulations
Standards RegulationsStandards Regulations
Standards Regulations
 
Ma 016 unloading coiled tubing real from boat & install it on cantilever deck
Ma 016  unloading coiled tubing real from boat & install it on cantilever deckMa 016  unloading coiled tubing real from boat & install it on cantilever deck
Ma 016 unloading coiled tubing real from boat & install it on cantilever deck
 

Viewers also liked

Ma 020 launching lifeboats to sea
Ma 020 launching lifeboats to seaMa 020 launching lifeboats to sea
Ma 020 launching lifeboats to seaYousif Fikry
 
Ma 032 transfer water from or to supply boat
Ma 032 transfer water from or to supply boatMa 032 transfer water from or to supply boat
Ma 032 transfer water from or to supply boatYousif Fikry
 
Ma 024 working on ladder
Ma 024 working on ladderMa 024 working on ladder
Ma 024 working on ladderYousif Fikry
 
Ma 034 jsa general lifting on the deck
Ma 034   jsa general lifting on the deckMa 034   jsa general lifting on the deck
Ma 034 jsa general lifting on the deckYousif Fikry
 
Ma 038 painting on derrick set
Ma 038 painting on derrick setMa 038 painting on derrick set
Ma 038 painting on derrick setYousif Fikry
 
Ma 030 cleaning oil in 100 t crane
Ma 030 cleaning oil in 100 t craneMa 030 cleaning oil in 100 t crane
Ma 030 cleaning oil in 100 t craneYousif Fikry
 
Ma 035 jsa open seachest
Ma 035   jsa open seachestMa 035   jsa open seachest
Ma 035 jsa open seachestYousif Fikry
 
Ma 029 loading & offloading tubulars from a supply boat
Ma 029 loading & offloading tubulars from a supply boatMa 029 loading & offloading tubulars from a supply boat
Ma 029 loading & offloading tubulars from a supply boatYousif Fikry
 
Ma 028 jsa open seachest
Ma 028    jsa open seachestMa 028    jsa open seachest
Ma 028 jsa open seachestYousif Fikry
 
Ma 036 jsa check ballast 5p loading valve
Ma 036 jsa check ballast 5p loading valveMa 036 jsa check ballast 5p loading valve
Ma 036 jsa check ballast 5p loading valveYousif Fikry
 
Ma 026 offloading or backloading fuel, base oil, obm
Ma 026 offloading or backloading fuel, base oil, obmMa 026 offloading or backloading fuel, base oil, obm
Ma 026 offloading or backloading fuel, base oil, obmYousif Fikry
 
Ma 031 transfer brine from or to supply boat
Ma 031 transfer brine from or to supply boatMa 031 transfer brine from or to supply boat
Ma 031 transfer brine from or to supply boatYousif Fikry
 
Ma 027 jsa general lifting on the deck
Ma 027  jsa general lifting on the deckMa 027  jsa general lifting on the deck
Ma 027 jsa general lifting on the deckYousif Fikry
 
Ma 033 jsa rack pup joint in the stb rack
Ma 033 jsa rack pup joint in the stb rackMa 033 jsa rack pup joint in the stb rack
Ma 033 jsa rack pup joint in the stb rackYousif Fikry
 

Viewers also liked (14)

Ma 020 launching lifeboats to sea
Ma 020 launching lifeboats to seaMa 020 launching lifeboats to sea
Ma 020 launching lifeboats to sea
 
Ma 032 transfer water from or to supply boat
Ma 032 transfer water from or to supply boatMa 032 transfer water from or to supply boat
Ma 032 transfer water from or to supply boat
 
Ma 024 working on ladder
Ma 024 working on ladderMa 024 working on ladder
Ma 024 working on ladder
 
Ma 034 jsa general lifting on the deck
Ma 034   jsa general lifting on the deckMa 034   jsa general lifting on the deck
Ma 034 jsa general lifting on the deck
 
Ma 038 painting on derrick set
Ma 038 painting on derrick setMa 038 painting on derrick set
Ma 038 painting on derrick set
 
Ma 030 cleaning oil in 100 t crane
Ma 030 cleaning oil in 100 t craneMa 030 cleaning oil in 100 t crane
Ma 030 cleaning oil in 100 t crane
 
Ma 035 jsa open seachest
Ma 035   jsa open seachestMa 035   jsa open seachest
Ma 035 jsa open seachest
 
Ma 029 loading & offloading tubulars from a supply boat
Ma 029 loading & offloading tubulars from a supply boatMa 029 loading & offloading tubulars from a supply boat
Ma 029 loading & offloading tubulars from a supply boat
 
Ma 028 jsa open seachest
Ma 028    jsa open seachestMa 028    jsa open seachest
Ma 028 jsa open seachest
 
Ma 036 jsa check ballast 5p loading valve
Ma 036 jsa check ballast 5p loading valveMa 036 jsa check ballast 5p loading valve
Ma 036 jsa check ballast 5p loading valve
 
Ma 026 offloading or backloading fuel, base oil, obm
Ma 026 offloading or backloading fuel, base oil, obmMa 026 offloading or backloading fuel, base oil, obm
Ma 026 offloading or backloading fuel, base oil, obm
 
Ma 031 transfer brine from or to supply boat
Ma 031 transfer brine from or to supply boatMa 031 transfer brine from or to supply boat
Ma 031 transfer brine from or to supply boat
 
Ma 027 jsa general lifting on the deck
Ma 027  jsa general lifting on the deckMa 027  jsa general lifting on the deck
Ma 027 jsa general lifting on the deck
 
Ma 033 jsa rack pup joint in the stb rack
Ma 033 jsa rack pup joint in the stb rackMa 033 jsa rack pup joint in the stb rack
Ma 033 jsa rack pup joint in the stb rack
 

Similar to Ma 001 tanks & preloads visual inspection

Ma 019 preloads dump valves maintenance
Ma 019  preloads dump valves maintenanceMa 019  preloads dump valves maintenance
Ma 019 preloads dump valves maintenanceYousif Fikry
 
Ma 021 backload flare boom on supply-boat
Ma 021 backload flare boom on supply-boatMa 021 backload flare boom on supply-boat
Ma 021 backload flare boom on supply-boatYousif Fikry
 
Ma 005 cleaning front of main wall accomodations
Ma 005 cleaning front of main wall accomodationsMa 005 cleaning front of main wall accomodations
Ma 005 cleaning front of main wall accomodationsYousif Fikry
 
Ma 017 backloading coiled tubing real on boat
Ma 017  backloading coiled tubing real on boatMa 017  backloading coiled tubing real on boat
Ma 017 backloading coiled tubing real on boatYousif Fikry
 
Ma 006 transfer by personnel basket
Ma 006  transfer by personnel basketMa 006  transfer by personnel basket
Ma 006 transfer by personnel basketYousif Fikry
 
Dr047 confined space entry
Dr047 confined space entryDr047 confined space entry
Dr047 confined space entryYousif Fikry
 
Ma 015 boom crane paint maintenance
Ma 015  boom crane paint maintenanceMa 015  boom crane paint maintenance
Ma 015 boom crane paint maintenanceYousif Fikry
 
Ma 040 emergency lowering of personnel lifting
Ma 040  emergency lowering of personnel liftingMa 040  emergency lowering of personnel lifting
Ma 040 emergency lowering of personnel liftingYousif Fikry
 
Ma 008 removing mooring ropes from legs
Ma 008 removing mooring ropes from legsMa 008 removing mooring ropes from legs
Ma 008 removing mooring ropes from legsYousif Fikry
 
Ma 010 crane wire replacement ( whip line )
Ma 010  crane wire replacement ( whip line )Ma 010  crane wire replacement ( whip line )
Ma 010 crane wire replacement ( whip line )Yousif Fikry
 
Ma 011 crane wire replacement ( main hook line )
Ma 011  crane wire replacement ( main hook line )Ma 011  crane wire replacement ( main hook line )
Ma 011 crane wire replacement ( main hook line )Yousif Fikry
 
Ma 07 installing mooring ropes on legs
Ma 07  installing mooring ropes on legsMa 07  installing mooring ropes on legs
Ma 07 installing mooring ropes on legsYousif Fikry
 
Ma 014 changing boom pendants on both cranes
Ma 014  changing boom pendants on both cranesMa 014  changing boom pendants on both cranes
Ma 014 changing boom pendants on both cranesYousif Fikry
 
Ma 012 using working personnel basket
Ma 012 using working personnel basketMa 012 using working personnel basket
Ma 012 using working personnel basketYousif Fikry
 
Ma 023 change out butter fly valve for bulk system
Ma 023  change out butter fly valve for bulk systemMa 023  change out butter fly valve for bulk system
Ma 023 change out butter fly valve for bulk systemYousif Fikry
 
Atf marketing segment sorc meeting 14.05.2020 atf rev01
Atf marketing segment sorc meeting  14.05.2020   atf rev01Atf marketing segment sorc meeting  14.05.2020   atf rev01
Atf marketing segment sorc meeting 14.05.2020 atf rev01Amardeep Jadeja
 
Hazard Assessment Methodology of Liquid Hydrocarbon Tank | Risk Assessment of...
Hazard Assessment Methodology of Liquid Hydrocarbon Tank | Risk Assessment of...Hazard Assessment Methodology of Liquid Hydrocarbon Tank | Risk Assessment of...
Hazard Assessment Methodology of Liquid Hydrocarbon Tank | Risk Assessment of...Gaurav Singh Rajput
 

Similar to Ma 001 tanks & preloads visual inspection (20)

Ma 019 preloads dump valves maintenance
Ma 019  preloads dump valves maintenanceMa 019  preloads dump valves maintenance
Ma 019 preloads dump valves maintenance
 
Ma 022 preloading
Ma 022 preloadingMa 022 preloading
Ma 022 preloading
 
Ma 021 backload flare boom on supply-boat
Ma 021 backload flare boom on supply-boatMa 021 backload flare boom on supply-boat
Ma 021 backload flare boom on supply-boat
 
Ma 005 cleaning front of main wall accomodations
Ma 005 cleaning front of main wall accomodationsMa 005 cleaning front of main wall accomodations
Ma 005 cleaning front of main wall accomodations
 
Ma 017 backloading coiled tubing real on boat
Ma 017  backloading coiled tubing real on boatMa 017  backloading coiled tubing real on boat
Ma 017 backloading coiled tubing real on boat
 
Ma 006 transfer by personnel basket
Ma 006  transfer by personnel basketMa 006  transfer by personnel basket
Ma 006 transfer by personnel basket
 
Dr047 confined space entry
Dr047 confined space entryDr047 confined space entry
Dr047 confined space entry
 
Ma 015 boom crane paint maintenance
Ma 015  boom crane paint maintenanceMa 015  boom crane paint maintenance
Ma 015 boom crane paint maintenance
 
Ma 040 emergency lowering of personnel lifting
Ma 040  emergency lowering of personnel liftingMa 040  emergency lowering of personnel lifting
Ma 040 emergency lowering of personnel lifting
 
Ma 008 removing mooring ropes from legs
Ma 008 removing mooring ropes from legsMa 008 removing mooring ropes from legs
Ma 008 removing mooring ropes from legs
 
Ma 010 crane wire replacement ( whip line )
Ma 010  crane wire replacement ( whip line )Ma 010  crane wire replacement ( whip line )
Ma 010 crane wire replacement ( whip line )
 
Ma 011 crane wire replacement ( main hook line )
Ma 011  crane wire replacement ( main hook line )Ma 011  crane wire replacement ( main hook line )
Ma 011 crane wire replacement ( main hook line )
 
Ma 07 installing mooring ropes on legs
Ma 07  installing mooring ropes on legsMa 07  installing mooring ropes on legs
Ma 07 installing mooring ropes on legs
 
COMPL OF WORKS1
COMPL OF WORKS1COMPL OF WORKS1
COMPL OF WORKS1
 
Ma 014 changing boom pendants on both cranes
Ma 014  changing boom pendants on both cranesMa 014  changing boom pendants on both cranes
Ma 014 changing boom pendants on both cranes
 
Ma 012 using working personnel basket
Ma 012 using working personnel basketMa 012 using working personnel basket
Ma 012 using working personnel basket
 
Ma 023 change out butter fly valve for bulk system
Ma 023  change out butter fly valve for bulk systemMa 023  change out butter fly valve for bulk system
Ma 023 change out butter fly valve for bulk system
 
JSA for Hydrotesting.pdf
JSA for Hydrotesting.pdfJSA for Hydrotesting.pdf
JSA for Hydrotesting.pdf
 
Atf marketing segment sorc meeting 14.05.2020 atf rev01
Atf marketing segment sorc meeting  14.05.2020   atf rev01Atf marketing segment sorc meeting  14.05.2020   atf rev01
Atf marketing segment sorc meeting 14.05.2020 atf rev01
 
Hazard Assessment Methodology of Liquid Hydrocarbon Tank | Risk Assessment of...
Hazard Assessment Methodology of Liquid Hydrocarbon Tank | Risk Assessment of...Hazard Assessment Methodology of Liquid Hydrocarbon Tank | Risk Assessment of...
Hazard Assessment Methodology of Liquid Hydrocarbon Tank | Risk Assessment of...
 

Ma 001 tanks & preloads visual inspection

  • 1. Rig Name/#: BENNEVIS JSA Number : MA 001 Person Approving JSA : Work Activity (Job):Tanks & Preloads Visual Inspection Date Raised : 04-OCT-2007 Work Team (Crew Members): B.E/ ABE/ Lead Roustabout Sequence of Basic Job Steps Potential Accidents or Hazards Recommendation to Eliminate or Reduce Potential Hazards Who? Initials 1. Hold pre-job meeting & work-permit 1. Procedures not known or not understood by crew member 1. Take time to read correctly JSA . Be sure everything is understood. If not ask your Supervisor BE 2 . Prepare and inspect tools needed for the job : Lights ( torch or 24 v lights ) – Fall. arrestor & Tripod support to go inside – Harness - Gas detector – Air blower 2. Low batteries on lights ( no visibility ) – Using wrong voltage (110 v/ 220 v) - Falling in tank from ladder – Poor atmosphere condition can cause people to pass out or die 2. Inspect all tools needed for the job before to ensure proper use All involved 3. Inspect atmospheric conditions of tank before entering 3. Gas concentration – Poor atmospheric condition 3. Check gas detection. Ventilate the tank SAF-BE 4. Enter tank 4. Falling from ladder 4. Use fall arrestor & harness BE-ABE 5. Tank inspection 5. Lighting problem ( no visibility ) – Electric shock – Tripping – Falling in tank compartment 5. Be sure there is enough batteries in torch – Be sure you are using 24 volts lighting equipment – Good visibility in tank Stand-by man outside tank all the time during inspection BE-ABE- Electrician 6. Exit tank 6. Same as step #4 6. Same as step #4 Safety Equipment To Do This Job Page 1 of 2 Pyramid Drilling S.A Manual Title: Personnel Safety Manual Form Name: Job Safety Analysis Issue Date 02-Sept-07 Revision No. 2 Revision Date 04-OCTOBER 07 Prepared By QA/HSE Approved By HS Level No. 2
  • 2. Hard Hats x Cotton Gloves x Face Shield ( Fire Extinguishers ( Safety Boots x Work Vest ( Goggles x Lockout/Tagout ( Safety Glasses x Safety Harness x Barriers ( Work Permit Required x Page 2 of 2 Pyramid Drilling S.A Manual Title: Personnel Safety Manual Form Name: Job Safety Analysis Issue Date 02-Sept-07 Revision No. 2 Revision Date 04-OCTOBER 07 Prepared By QA/HSE Approved By HS Level No. 2