Rig Name/#: BENNEVIS JSA Number : MA 012 Person Approving JSA: H.M
Work Activity (Job): Using Working Basket Date Raised :
Work Team (Crew Members): Crane-Operators & All depts Date Last Amended :
Safety Equipment To Do This Job(
Hard Hats x Cotton Gloves x Face Shield Fire Extinguishers
Safety Boots x Work Vest x Goggles x Lockout/Tagout
Safety Glasses x Safety Harness x Barricades x Work Permit Required x
Uncontrolled When Printed Page 1 of 2
Sequence of Basic Job Steps Potential Accidents or Hazards
Recommendation to Eliminate or Reduce Potential
Hazards
Who?
Initials
1. Hold pre-job meeting – Work-permit 1. Procedures not known or not understood by crew members-
Persons involved in task becoming injured by incorrect procedure
compliance
1. Take time to read correctly JSA . Be sure everything is
understood . If not ask your Supervisor
Supervisors
2 . Prepare working basket – Harness –
Work vest if necessary - Tools
2. Basket in bad condition – Hands or fingers injuries - Falling
in water – Safety equipments in bad condition – Slings or
shackles damaged
2. Inspect basket , slings & shackles before use to make
sure they are in proper working condition – Check color code
& SWL – Be careful of hands placement
All
Involved
3. Moving personnel with working basket 3. Hands or fingers injuries being caught between basket &
equipment – Falling from basket – Swinging out of control –
Wrong crane signals done to crane operator
3. Be careful of hands placement – Fix harness correctly –
Use tag-line to keep basket steady – Secure basket during
job – Learn crane signals – Only one person doing signals –
Use work vest if necessary
All
Involved
4. End of job – Lowering basket 4. Falling from basket – Swinging out of control – Wrong crane
signals done to crane operator – Tools falling
4. Fix harness correctly – Use tag-line to keep basket
steady – Learn crane signals – Only one person doing
signals – Secure tools – Use work vest if necessary
All
Involved
Pyramid Drilling S.A
Manual Title: Personnel Safety Manual
Form Name: Job Safety Analysis
Issue Date
02-Sept-07
Revision No.
2
Revision Date
04-MAR 08
Prepared By
QA/HSE
Approved By
HM
Level No.
2
Uncontrolled When Printed Page 2 of 2
Pyramid Drilling S.A
Manual Title: Personnel Safety Manual
Form Name: Job Safety Analysis
Issue Date
02-Sept-07
Revision No.
2
Revision Date
04-MAR 08
Prepared By
QA/HSE
Approved By
HM
Level No.
2

More Related Content

Similar to Ma 012 using working personnel basket

Ma 018 changing lifeboats wires
Ma 018 changing lifeboats wiresMa 018 changing lifeboats wires
Ma 018 changing lifeboats wiresYousif Fikry
 
Ma 021 backload flare boom on supply-boat
Ma 021 backload flare boom on supply-boatMa 021 backload flare boom on supply-boat
Ma 021 backload flare boom on supply-boatYousif Fikry
 
Ma 015 boom crane paint maintenance
Ma 015  boom crane paint maintenanceMa 015  boom crane paint maintenance
Ma 015 boom crane paint maintenanceYousif Fikry
 
Ma 013 testing lifeboats capsules
Ma 013  testing  lifeboats  capsulesMa 013  testing  lifeboats  capsules
Ma 013 testing lifeboats capsulesYousif Fikry
 
Ma 016 unloading coiled tubing real from boat & install it on cantilever deck
Ma 016  unloading coiled tubing real from boat & install it on cantilever deckMa 016  unloading coiled tubing real from boat & install it on cantilever deck
Ma 016 unloading coiled tubing real from boat & install it on cantilever deckYousif Fikry
 
Ma 010 crane wire replacement ( whip line )
Ma 010  crane wire replacement ( whip line )Ma 010  crane wire replacement ( whip line )
Ma 010 crane wire replacement ( whip line )Yousif Fikry
 
Ma 115 boom crane cable tray repair
Ma 115  boom crane cable tray repairMa 115  boom crane cable tray repair
Ma 115 boom crane cable tray repairYousif Fikry
 
Ma 003 erecting & removing scaffolding in tanks
Ma 003  erecting & removing scaffolding in tanksMa 003  erecting & removing scaffolding in tanks
Ma 003 erecting & removing scaffolding in tanksYousif Fikry
 
Ma 040 emergency lowering of personnel lifting
Ma 040  emergency lowering of personnel liftingMa 040  emergency lowering of personnel lifting
Ma 040 emergency lowering of personnel liftingYousif Fikry
 
Ma 011 crane wire replacement ( main hook line )
Ma 011  crane wire replacement ( main hook line )Ma 011  crane wire replacement ( main hook line )
Ma 011 crane wire replacement ( main hook line )Yousif Fikry
 
Ma 014 changing boom pendants on both cranes
Ma 014  changing boom pendants on both cranesMa 014  changing boom pendants on both cranes
Ma 014 changing boom pendants on both cranesYousif Fikry
 
Ma 033 jsa rack pup joint in the stb rack
Ma 033 jsa rack pup joint in the stb rackMa 033 jsa rack pup joint in the stb rack
Ma 033 jsa rack pup joint in the stb rackYousif Fikry
 
Ma 07 installing mooring ropes on legs
Ma 07  installing mooring ropes on legsMa 07  installing mooring ropes on legs
Ma 07 installing mooring ropes on legsYousif Fikry
 
Ma 004 paint jobs inside tanks
Ma 004  paint jobs inside tanksMa 004  paint jobs inside tanks
Ma 004 paint jobs inside tanksYousif Fikry
 
Ma 09 crane wire replacement ( boom )
Ma 09 crane wire replacement ( boom )Ma 09 crane wire replacement ( boom )
Ma 09 crane wire replacement ( boom )Yousif Fikry
 
JHA Handling Materials in crane and hydra
JHA Handling Materials in crane and hydraJHA Handling Materials in crane and hydra
JHA Handling Materials in crane and hydraDebiprasadPradhan6
 
Job safety analysis
Job safety analysis Job safety analysis
Job safety analysis soumenmakar
 
Ma 023 change out butter fly valve for bulk system
Ma 023  change out butter fly valve for bulk systemMa 023  change out butter fly valve for bulk system
Ma 023 change out butter fly valve for bulk systemYousif Fikry
 
Ma 008 removing mooring ropes from legs
Ma 008 removing mooring ropes from legsMa 008 removing mooring ropes from legs
Ma 008 removing mooring ropes from legsYousif Fikry
 

Similar to Ma 012 using working personnel basket (20)

Ma 018 changing lifeboats wires
Ma 018 changing lifeboats wiresMa 018 changing lifeboats wires
Ma 018 changing lifeboats wires
 
Ma 021 backload flare boom on supply-boat
Ma 021 backload flare boom on supply-boatMa 021 backload flare boom on supply-boat
Ma 021 backload flare boom on supply-boat
 
Ma 015 boom crane paint maintenance
Ma 015  boom crane paint maintenanceMa 015  boom crane paint maintenance
Ma 015 boom crane paint maintenance
 
Ma 013 testing lifeboats capsules
Ma 013  testing  lifeboats  capsulesMa 013  testing  lifeboats  capsules
Ma 013 testing lifeboats capsules
 
Ma 016 unloading coiled tubing real from boat & install it on cantilever deck
Ma 016  unloading coiled tubing real from boat & install it on cantilever deckMa 016  unloading coiled tubing real from boat & install it on cantilever deck
Ma 016 unloading coiled tubing real from boat & install it on cantilever deck
 
Ma 010 crane wire replacement ( whip line )
Ma 010  crane wire replacement ( whip line )Ma 010  crane wire replacement ( whip line )
Ma 010 crane wire replacement ( whip line )
 
Ma 115 boom crane cable tray repair
Ma 115  boom crane cable tray repairMa 115  boom crane cable tray repair
Ma 115 boom crane cable tray repair
 
Ma 003 erecting & removing scaffolding in tanks
Ma 003  erecting & removing scaffolding in tanksMa 003  erecting & removing scaffolding in tanks
Ma 003 erecting & removing scaffolding in tanks
 
Ma 040 emergency lowering of personnel lifting
Ma 040  emergency lowering of personnel liftingMa 040  emergency lowering of personnel lifting
Ma 040 emergency lowering of personnel lifting
 
Ma 011 crane wire replacement ( main hook line )
Ma 011  crane wire replacement ( main hook line )Ma 011  crane wire replacement ( main hook line )
Ma 011 crane wire replacement ( main hook line )
 
Ma 014 changing boom pendants on both cranes
Ma 014  changing boom pendants on both cranesMa 014  changing boom pendants on both cranes
Ma 014 changing boom pendants on both cranes
 
Ma 033 jsa rack pup joint in the stb rack
Ma 033 jsa rack pup joint in the stb rackMa 033 jsa rack pup joint in the stb rack
Ma 033 jsa rack pup joint in the stb rack
 
Ma 07 installing mooring ropes on legs
Ma 07  installing mooring ropes on legsMa 07  installing mooring ropes on legs
Ma 07 installing mooring ropes on legs
 
Ma 004 paint jobs inside tanks
Ma 004  paint jobs inside tanksMa 004  paint jobs inside tanks
Ma 004 paint jobs inside tanks
 
Ma 09 crane wire replacement ( boom )
Ma 09 crane wire replacement ( boom )Ma 09 crane wire replacement ( boom )
Ma 09 crane wire replacement ( boom )
 
JHA Handling Materials in crane and hydra
JHA Handling Materials in crane and hydraJHA Handling Materials in crane and hydra
JHA Handling Materials in crane and hydra
 
Job safety analysis
Job safety analysis Job safety analysis
Job safety analysis
 
Ma 023 change out butter fly valve for bulk system
Ma 023  change out butter fly valve for bulk systemMa 023  change out butter fly valve for bulk system
Ma 023 change out butter fly valve for bulk system
 
Ma 008 removing mooring ropes from legs
Ma 008 removing mooring ropes from legsMa 008 removing mooring ropes from legs
Ma 008 removing mooring ropes from legs
 
JSA for Hydrotesting.pdf
JSA for Hydrotesting.pdfJSA for Hydrotesting.pdf
JSA for Hydrotesting.pdf
 

More from Yousif Fikry

Ma 039 jsa emergency load lowering
Ma 039 jsa emergency load loweringMa 039 jsa emergency load lowering
Ma 039 jsa emergency load loweringYousif Fikry
 
Ma 038 painting on derrick set
Ma 038 painting on derrick setMa 038 painting on derrick set
Ma 038 painting on derrick setYousif Fikry
 
Ma 037 cleaning with air brush
Ma 037 cleaning with air brushMa 037 cleaning with air brush
Ma 037 cleaning with air brushYousif Fikry
 
Ma 036 jsa check ballast 5p loading valve
Ma 036 jsa check ballast 5p loading valveMa 036 jsa check ballast 5p loading valve
Ma 036 jsa check ballast 5p loading valveYousif Fikry
 
Ma 035 jsa open seachest
Ma 035   jsa open seachestMa 035   jsa open seachest
Ma 035 jsa open seachestYousif Fikry
 
Ma 034 jsa general lifting on the deck
Ma 034   jsa general lifting on the deckMa 034   jsa general lifting on the deck
Ma 034 jsa general lifting on the deckYousif Fikry
 
Ma 032 transfer water from or to supply boat
Ma 032 transfer water from or to supply boatMa 032 transfer water from or to supply boat
Ma 032 transfer water from or to supply boatYousif Fikry
 
Ma 031 transfer brine from or to supply boat
Ma 031 transfer brine from or to supply boatMa 031 transfer brine from or to supply boat
Ma 031 transfer brine from or to supply boatYousif Fikry
 
Ma 030 cleaning oil in 100 t crane
Ma 030 cleaning oil in 100 t craneMa 030 cleaning oil in 100 t crane
Ma 030 cleaning oil in 100 t craneYousif Fikry
 
Ma 029 loading & offloading tubulars from a supply boat
Ma 029 loading & offloading tubulars from a supply boatMa 029 loading & offloading tubulars from a supply boat
Ma 029 loading & offloading tubulars from a supply boatYousif Fikry
 
Ma 028 jsa open seachest
Ma 028    jsa open seachestMa 028    jsa open seachest
Ma 028 jsa open seachestYousif Fikry
 
Ma 027 jsa general lifting on the deck
Ma 027  jsa general lifting on the deckMa 027  jsa general lifting on the deck
Ma 027 jsa general lifting on the deckYousif Fikry
 
Ma 026 offloading or backloading fuel, base oil, obm
Ma 026 offloading or backloading fuel, base oil, obmMa 026 offloading or backloading fuel, base oil, obm
Ma 026 offloading or backloading fuel, base oil, obmYousif Fikry
 
Ma 025 transfer casing
Ma 025 transfer casingMa 025 transfer casing
Ma 025 transfer casingYousif Fikry
 
Ma 024 working on ladder
Ma 024 working on ladderMa 024 working on ladder
Ma 024 working on ladderYousif Fikry
 
Ma 020 launching lifeboats to sea
Ma 020 launching lifeboats to seaMa 020 launching lifeboats to sea
Ma 020 launching lifeboats to seaYousif Fikry
 

More from Yousif Fikry (18)

Welding operation
Welding operationWelding operation
Welding operation
 
Ma 039 jsa emergency load lowering
Ma 039 jsa emergency load loweringMa 039 jsa emergency load lowering
Ma 039 jsa emergency load lowering
 
Ma 038 painting on derrick set
Ma 038 painting on derrick setMa 038 painting on derrick set
Ma 038 painting on derrick set
 
Ma 037 cleaning with air brush
Ma 037 cleaning with air brushMa 037 cleaning with air brush
Ma 037 cleaning with air brush
 
Ma 036 jsa check ballast 5p loading valve
Ma 036 jsa check ballast 5p loading valveMa 036 jsa check ballast 5p loading valve
Ma 036 jsa check ballast 5p loading valve
 
Ma 035 jsa open seachest
Ma 035   jsa open seachestMa 035   jsa open seachest
Ma 035 jsa open seachest
 
Ma 034 jsa general lifting on the deck
Ma 034   jsa general lifting on the deckMa 034   jsa general lifting on the deck
Ma 034 jsa general lifting on the deck
 
Ma 032 transfer water from or to supply boat
Ma 032 transfer water from or to supply boatMa 032 transfer water from or to supply boat
Ma 032 transfer water from or to supply boat
 
Ma 031 transfer brine from or to supply boat
Ma 031 transfer brine from or to supply boatMa 031 transfer brine from or to supply boat
Ma 031 transfer brine from or to supply boat
 
Ma 030 cleaning oil in 100 t crane
Ma 030 cleaning oil in 100 t craneMa 030 cleaning oil in 100 t crane
Ma 030 cleaning oil in 100 t crane
 
Ma 029 loading & offloading tubulars from a supply boat
Ma 029 loading & offloading tubulars from a supply boatMa 029 loading & offloading tubulars from a supply boat
Ma 029 loading & offloading tubulars from a supply boat
 
Ma 028 jsa open seachest
Ma 028    jsa open seachestMa 028    jsa open seachest
Ma 028 jsa open seachest
 
Ma 027 jsa general lifting on the deck
Ma 027  jsa general lifting on the deckMa 027  jsa general lifting on the deck
Ma 027 jsa general lifting on the deck
 
Ma 026 offloading or backloading fuel, base oil, obm
Ma 026 offloading or backloading fuel, base oil, obmMa 026 offloading or backloading fuel, base oil, obm
Ma 026 offloading or backloading fuel, base oil, obm
 
Ma 025 transfer casing
Ma 025 transfer casingMa 025 transfer casing
Ma 025 transfer casing
 
Ma 024 working on ladder
Ma 024 working on ladderMa 024 working on ladder
Ma 024 working on ladder
 
Ma 022 preloading
Ma 022 preloadingMa 022 preloading
Ma 022 preloading
 
Ma 020 launching lifeboats to sea
Ma 020 launching lifeboats to seaMa 020 launching lifeboats to sea
Ma 020 launching lifeboats to sea
 

Ma 012 using working personnel basket

  • 1. Rig Name/#: BENNEVIS JSA Number : MA 012 Person Approving JSA: H.M Work Activity (Job): Using Working Basket Date Raised : Work Team (Crew Members): Crane-Operators & All depts Date Last Amended : Safety Equipment To Do This Job( Hard Hats x Cotton Gloves x Face Shield Fire Extinguishers Safety Boots x Work Vest x Goggles x Lockout/Tagout Safety Glasses x Safety Harness x Barricades x Work Permit Required x Uncontrolled When Printed Page 1 of 2 Sequence of Basic Job Steps Potential Accidents or Hazards Recommendation to Eliminate or Reduce Potential Hazards Who? Initials 1. Hold pre-job meeting – Work-permit 1. Procedures not known or not understood by crew members- Persons involved in task becoming injured by incorrect procedure compliance 1. Take time to read correctly JSA . Be sure everything is understood . If not ask your Supervisor Supervisors 2 . Prepare working basket – Harness – Work vest if necessary - Tools 2. Basket in bad condition – Hands or fingers injuries - Falling in water – Safety equipments in bad condition – Slings or shackles damaged 2. Inspect basket , slings & shackles before use to make sure they are in proper working condition – Check color code & SWL – Be careful of hands placement All Involved 3. Moving personnel with working basket 3. Hands or fingers injuries being caught between basket & equipment – Falling from basket – Swinging out of control – Wrong crane signals done to crane operator 3. Be careful of hands placement – Fix harness correctly – Use tag-line to keep basket steady – Secure basket during job – Learn crane signals – Only one person doing signals – Use work vest if necessary All Involved 4. End of job – Lowering basket 4. Falling from basket – Swinging out of control – Wrong crane signals done to crane operator – Tools falling 4. Fix harness correctly – Use tag-line to keep basket steady – Learn crane signals – Only one person doing signals – Secure tools – Use work vest if necessary All Involved Pyramid Drilling S.A Manual Title: Personnel Safety Manual Form Name: Job Safety Analysis Issue Date 02-Sept-07 Revision No. 2 Revision Date 04-MAR 08 Prepared By QA/HSE Approved By HM Level No. 2
  • 2. Uncontrolled When Printed Page 2 of 2 Pyramid Drilling S.A Manual Title: Personnel Safety Manual Form Name: Job Safety Analysis Issue Date 02-Sept-07 Revision No. 2 Revision Date 04-MAR 08 Prepared By QA/HSE Approved By HM Level No. 2