Rig Name/#: BENNEVIS JSA Number : MA 014 Person Approving JSA: H.M
Work Activity (Job):
Changing Boom Pendants on
Both Cranes Date Raised :
Work Team (Crew Members):
BE– ABE – Roustabouts –
Crane Operator Date Last Amended :
Uncontrolled When Printed Page 1 of 2
Pyramid Drilling S.A
Manual Title: Personnel Safety Manual
Form Name: Job Safety Analysis
Issue Date
02-Sept-07
Revision No.
2
Revision Date
04-MAR 08
Prepared By
QA/HSE
Approved By
HM
Level No.
2
Safety Equipment To Do This Job(
Hard Hats x Cotton Gloves x Face Shield Fire Extinguishers
Safety Boots x Work Vest Goggles x Lockout/Tagout
Safety Glasses x Safety Harness x Barriers x Work Permit Required x
Uncontrolled When Printed Page 2 of 2
Sequence of Basic Job Steps Potential Accidents or Hazards
Recommendation to Eliminate or Reduce Potential
Hazards
Who?
Initials
1. Hold pre-job meeting – Work-permit 1. Procedures not known or not understood by crew members-
Persons involved in task becoming injured by incorrect procedure
compliance
1. Take time to read correctly JSA . Be sure everything is
understood. If not ask your Supervisor
Supervisors
2. Prepare & inspect tools – Put crane boom
on cradle
2. Tools inadequate or in bad condition – Crane failure –
Damaged cradle
2. Ensure you will use proper tools for the job before going
on boom crane – Check safety harness – Operate crane
slowly
BE – ABE
Roustabouts
Crane
Operator
3. Disconnect old pendants 3. Safety pins falling down – Pendants falling down on people –
People falling down from boom crane – Hands injuries – Pinch
points – Safety walkway on boom crane broken
3. Slack completely & secure pendants on boom crane
before removing pins – Secure pins – Fix safety harness
correctly – Careful when hammering – Hook-up pendant to
opposite crane - Ensure that safety walkway on boom crane
is in good condition
BE - ABE
Crane
Operator
Roustabouts
4. Remove pendant with opposite crane 4. Pendant falling down – People falling down from boom crane
People struck by opposite crane sling hook
4. Ensure that pendant is secure correctly – Hook up
pendant slowly equalize lifting point ( middle of pendant ) &
release fastening ropes pendant 1 by 1 – Operate the crane
slowly – Do not stay below boom crane – Fasten harness
correctly
BE – ABE
Roustabouts
CraneOperator
5. Install new pendant 5. Pendant falling down – People falling down from boom crane –
People struck by pendant – Hands injuries – Pinch points –
Pendant safety pin falling on people – Tools falling
5. Lift up & position new pendant slowly with crane –
Equalize lifting point ( middle of pendant ) – Connect 1 side
of pendant on boom crane – Slack slowly pendant & secure
on boom crane – Connect 2nd
end of pendant on boom –
Operate crane slowly – Fix correctly harness – Do not stay
below boom crane during operation – Watch hands position
– Secure tools & pins
BE – ABE
Roustabouts
Crane
Operator
6. Crane boom up 6. Boom falling down – Tools falling down from boom crane 6. Ensure before raising boom that pendants are correctly
installed & secured – Check before raising boom that any
tools still on boom crane – Do not stay below boom crane –
Operate crane slowly
BE – ABE
Roustabouts
Crane
Operator
Pyramid Drilling S.A
Manual Title: Personnel Safety Manual
Form Name: Job Safety Analysis
Issue Date
02-Sept-07
Revision No.
2
Revision Date
04-MAR 08
Prepared By
QA/HSE
Approved By
HM
Level No.
2

More Related Content

Similar to Ma 014 changing boom pendants on both cranes

Ma 017 backloading coiled tubing real on boat
Ma 017  backloading coiled tubing real on boatMa 017  backloading coiled tubing real on boat
Ma 017 backloading coiled tubing real on boatYousif Fikry
 
Ma 010 crane wire replacement ( whip line )
Ma 010  crane wire replacement ( whip line )Ma 010  crane wire replacement ( whip line )
Ma 010 crane wire replacement ( whip line )Yousif Fikry
 
Ma 021 backload flare boom on supply-boat
Ma 021 backload flare boom on supply-boatMa 021 backload flare boom on supply-boat
Ma 021 backload flare boom on supply-boatYousif Fikry
 
Ma 09 crane wire replacement ( boom )
Ma 09 crane wire replacement ( boom )Ma 09 crane wire replacement ( boom )
Ma 09 crane wire replacement ( boom )Yousif Fikry
 
Ma 011 crane wire replacement ( main hook line )
Ma 011  crane wire replacement ( main hook line )Ma 011  crane wire replacement ( main hook line )
Ma 011 crane wire replacement ( main hook line )Yousif Fikry
 
Ma 013 testing lifeboats capsules
Ma 013  testing  lifeboats  capsulesMa 013  testing  lifeboats  capsules
Ma 013 testing lifeboats capsulesYousif Fikry
 
Ma 008 removing mooring ropes from legs
Ma 008 removing mooring ropes from legsMa 008 removing mooring ropes from legs
Ma 008 removing mooring ropes from legsYousif Fikry
 
Ma 07 installing mooring ropes on legs
Ma 07  installing mooring ropes on legsMa 07  installing mooring ropes on legs
Ma 07 installing mooring ropes on legsYousif Fikry
 
Ma 040 emergency lowering of personnel lifting
Ma 040  emergency lowering of personnel liftingMa 040  emergency lowering of personnel lifting
Ma 040 emergency lowering of personnel liftingYousif Fikry
 
Ma 020 launching lifeboats to sea
Ma 020 launching lifeboats to seaMa 020 launching lifeboats to sea
Ma 020 launching lifeboats to seaYousif Fikry
 
Ma 005 cleaning front of main wall accomodations
Ma 005 cleaning front of main wall accomodationsMa 005 cleaning front of main wall accomodations
Ma 005 cleaning front of main wall accomodationsYousif Fikry
 
Ma 003 erecting & removing scaffolding in tanks
Ma 003  erecting & removing scaffolding in tanksMa 003  erecting & removing scaffolding in tanks
Ma 003 erecting & removing scaffolding in tanksYousif Fikry
 
Ma 015 boom crane paint maintenance
Ma 015  boom crane paint maintenanceMa 015  boom crane paint maintenance
Ma 015 boom crane paint maintenanceYousif Fikry
 
Ma 006 transfer by personnel basket
Ma 006  transfer by personnel basketMa 006  transfer by personnel basket
Ma 006 transfer by personnel basketYousif Fikry
 
Ma 019 preloads dump valves maintenance
Ma 019  preloads dump valves maintenanceMa 019  preloads dump valves maintenance
Ma 019 preloads dump valves maintenanceYousif Fikry
 
Ma 012 using working personnel basket
Ma 012 using working personnel basketMa 012 using working personnel basket
Ma 012 using working personnel basketYousif Fikry
 
Ma 004 paint jobs inside tanks
Ma 004  paint jobs inside tanksMa 004  paint jobs inside tanks
Ma 004 paint jobs inside tanksYousif Fikry
 
Ma 115 boom crane cable tray repair
Ma 115  boom crane cable tray repairMa 115  boom crane cable tray repair
Ma 115 boom crane cable tray repairYousif Fikry
 
Ma 001 tanks & preloads visual inspection
Ma 001  tanks & preloads visual inspectionMa 001  tanks & preloads visual inspection
Ma 001 tanks & preloads visual inspectionYousif Fikry
 

Similar to Ma 014 changing boom pendants on both cranes (20)

Ma 017 backloading coiled tubing real on boat
Ma 017  backloading coiled tubing real on boatMa 017  backloading coiled tubing real on boat
Ma 017 backloading coiled tubing real on boat
 
Ma 010 crane wire replacement ( whip line )
Ma 010  crane wire replacement ( whip line )Ma 010  crane wire replacement ( whip line )
Ma 010 crane wire replacement ( whip line )
 
Ma 021 backload flare boom on supply-boat
Ma 021 backload flare boom on supply-boatMa 021 backload flare boom on supply-boat
Ma 021 backload flare boom on supply-boat
 
Ma 09 crane wire replacement ( boom )
Ma 09 crane wire replacement ( boom )Ma 09 crane wire replacement ( boom )
Ma 09 crane wire replacement ( boom )
 
Ma 011 crane wire replacement ( main hook line )
Ma 011  crane wire replacement ( main hook line )Ma 011  crane wire replacement ( main hook line )
Ma 011 crane wire replacement ( main hook line )
 
Ma 013 testing lifeboats capsules
Ma 013  testing  lifeboats  capsulesMa 013  testing  lifeboats  capsules
Ma 013 testing lifeboats capsules
 
Ma 008 removing mooring ropes from legs
Ma 008 removing mooring ropes from legsMa 008 removing mooring ropes from legs
Ma 008 removing mooring ropes from legs
 
Ma 07 installing mooring ropes on legs
Ma 07  installing mooring ropes on legsMa 07  installing mooring ropes on legs
Ma 07 installing mooring ropes on legs
 
Ma 040 emergency lowering of personnel lifting
Ma 040  emergency lowering of personnel liftingMa 040  emergency lowering of personnel lifting
Ma 040 emergency lowering of personnel lifting
 
Ma 020 launching lifeboats to sea
Ma 020 launching lifeboats to seaMa 020 launching lifeboats to sea
Ma 020 launching lifeboats to sea
 
Ma 005 cleaning front of main wall accomodations
Ma 005 cleaning front of main wall accomodationsMa 005 cleaning front of main wall accomodations
Ma 005 cleaning front of main wall accomodations
 
Ma 003 erecting & removing scaffolding in tanks
Ma 003  erecting & removing scaffolding in tanksMa 003  erecting & removing scaffolding in tanks
Ma 003 erecting & removing scaffolding in tanks
 
Ma 015 boom crane paint maintenance
Ma 015  boom crane paint maintenanceMa 015  boom crane paint maintenance
Ma 015 boom crane paint maintenance
 
Ma 006 transfer by personnel basket
Ma 006  transfer by personnel basketMa 006  transfer by personnel basket
Ma 006 transfer by personnel basket
 
Ma 019 preloads dump valves maintenance
Ma 019  preloads dump valves maintenanceMa 019  preloads dump valves maintenance
Ma 019 preloads dump valves maintenance
 
Ma 012 using working personnel basket
Ma 012 using working personnel basketMa 012 using working personnel basket
Ma 012 using working personnel basket
 
Ma 022 preloading
Ma 022 preloadingMa 022 preloading
Ma 022 preloading
 
Ma 004 paint jobs inside tanks
Ma 004  paint jobs inside tanksMa 004  paint jobs inside tanks
Ma 004 paint jobs inside tanks
 
Ma 115 boom crane cable tray repair
Ma 115  boom crane cable tray repairMa 115  boom crane cable tray repair
Ma 115 boom crane cable tray repair
 
Ma 001 tanks & preloads visual inspection
Ma 001  tanks & preloads visual inspectionMa 001  tanks & preloads visual inspection
Ma 001 tanks & preloads visual inspection
 

More from Yousif Fikry

Ma 039 jsa emergency load lowering
Ma 039 jsa emergency load loweringMa 039 jsa emergency load lowering
Ma 039 jsa emergency load loweringYousif Fikry
 
Ma 038 painting on derrick set
Ma 038 painting on derrick setMa 038 painting on derrick set
Ma 038 painting on derrick setYousif Fikry
 
Ma 037 cleaning with air brush
Ma 037 cleaning with air brushMa 037 cleaning with air brush
Ma 037 cleaning with air brushYousif Fikry
 
Ma 036 jsa check ballast 5p loading valve
Ma 036 jsa check ballast 5p loading valveMa 036 jsa check ballast 5p loading valve
Ma 036 jsa check ballast 5p loading valveYousif Fikry
 
Ma 035 jsa open seachest
Ma 035   jsa open seachestMa 035   jsa open seachest
Ma 035 jsa open seachestYousif Fikry
 
Ma 034 jsa general lifting on the deck
Ma 034   jsa general lifting on the deckMa 034   jsa general lifting on the deck
Ma 034 jsa general lifting on the deckYousif Fikry
 
Ma 032 transfer water from or to supply boat
Ma 032 transfer water from or to supply boatMa 032 transfer water from or to supply boat
Ma 032 transfer water from or to supply boatYousif Fikry
 
Ma 031 transfer brine from or to supply boat
Ma 031 transfer brine from or to supply boatMa 031 transfer brine from or to supply boat
Ma 031 transfer brine from or to supply boatYousif Fikry
 
Ma 030 cleaning oil in 100 t crane
Ma 030 cleaning oil in 100 t craneMa 030 cleaning oil in 100 t crane
Ma 030 cleaning oil in 100 t craneYousif Fikry
 
Ma 029 loading & offloading tubulars from a supply boat
Ma 029 loading & offloading tubulars from a supply boatMa 029 loading & offloading tubulars from a supply boat
Ma 029 loading & offloading tubulars from a supply boatYousif Fikry
 
Ma 028 jsa open seachest
Ma 028    jsa open seachestMa 028    jsa open seachest
Ma 028 jsa open seachestYousif Fikry
 
Ma 027 jsa general lifting on the deck
Ma 027  jsa general lifting on the deckMa 027  jsa general lifting on the deck
Ma 027 jsa general lifting on the deckYousif Fikry
 
Ma 026 offloading or backloading fuel, base oil, obm
Ma 026 offloading or backloading fuel, base oil, obmMa 026 offloading or backloading fuel, base oil, obm
Ma 026 offloading or backloading fuel, base oil, obmYousif Fikry
 
Ma 025 transfer casing
Ma 025 transfer casingMa 025 transfer casing
Ma 025 transfer casingYousif Fikry
 
Ma 024 working on ladder
Ma 024 working on ladderMa 024 working on ladder
Ma 024 working on ladderYousif Fikry
 
Ma 023 change out butter fly valve for bulk system
Ma 023  change out butter fly valve for bulk systemMa 023  change out butter fly valve for bulk system
Ma 023 change out butter fly valve for bulk systemYousif Fikry
 

More from Yousif Fikry (17)

Welding operation
Welding operationWelding operation
Welding operation
 
Ma 039 jsa emergency load lowering
Ma 039 jsa emergency load loweringMa 039 jsa emergency load lowering
Ma 039 jsa emergency load lowering
 
Ma 038 painting on derrick set
Ma 038 painting on derrick setMa 038 painting on derrick set
Ma 038 painting on derrick set
 
Ma 037 cleaning with air brush
Ma 037 cleaning with air brushMa 037 cleaning with air brush
Ma 037 cleaning with air brush
 
Ma 036 jsa check ballast 5p loading valve
Ma 036 jsa check ballast 5p loading valveMa 036 jsa check ballast 5p loading valve
Ma 036 jsa check ballast 5p loading valve
 
Ma 035 jsa open seachest
Ma 035   jsa open seachestMa 035   jsa open seachest
Ma 035 jsa open seachest
 
Ma 034 jsa general lifting on the deck
Ma 034   jsa general lifting on the deckMa 034   jsa general lifting on the deck
Ma 034 jsa general lifting on the deck
 
Ma 032 transfer water from or to supply boat
Ma 032 transfer water from or to supply boatMa 032 transfer water from or to supply boat
Ma 032 transfer water from or to supply boat
 
Ma 031 transfer brine from or to supply boat
Ma 031 transfer brine from or to supply boatMa 031 transfer brine from or to supply boat
Ma 031 transfer brine from or to supply boat
 
Ma 030 cleaning oil in 100 t crane
Ma 030 cleaning oil in 100 t craneMa 030 cleaning oil in 100 t crane
Ma 030 cleaning oil in 100 t crane
 
Ma 029 loading & offloading tubulars from a supply boat
Ma 029 loading & offloading tubulars from a supply boatMa 029 loading & offloading tubulars from a supply boat
Ma 029 loading & offloading tubulars from a supply boat
 
Ma 028 jsa open seachest
Ma 028    jsa open seachestMa 028    jsa open seachest
Ma 028 jsa open seachest
 
Ma 027 jsa general lifting on the deck
Ma 027  jsa general lifting on the deckMa 027  jsa general lifting on the deck
Ma 027 jsa general lifting on the deck
 
Ma 026 offloading or backloading fuel, base oil, obm
Ma 026 offloading or backloading fuel, base oil, obmMa 026 offloading or backloading fuel, base oil, obm
Ma 026 offloading or backloading fuel, base oil, obm
 
Ma 025 transfer casing
Ma 025 transfer casingMa 025 transfer casing
Ma 025 transfer casing
 
Ma 024 working on ladder
Ma 024 working on ladderMa 024 working on ladder
Ma 024 working on ladder
 
Ma 023 change out butter fly valve for bulk system
Ma 023  change out butter fly valve for bulk systemMa 023  change out butter fly valve for bulk system
Ma 023 change out butter fly valve for bulk system
 

Ma 014 changing boom pendants on both cranes

  • 1. Rig Name/#: BENNEVIS JSA Number : MA 014 Person Approving JSA: H.M Work Activity (Job): Changing Boom Pendants on Both Cranes Date Raised : Work Team (Crew Members): BE– ABE – Roustabouts – Crane Operator Date Last Amended : Uncontrolled When Printed Page 1 of 2 Pyramid Drilling S.A Manual Title: Personnel Safety Manual Form Name: Job Safety Analysis Issue Date 02-Sept-07 Revision No. 2 Revision Date 04-MAR 08 Prepared By QA/HSE Approved By HM Level No. 2
  • 2. Safety Equipment To Do This Job( Hard Hats x Cotton Gloves x Face Shield Fire Extinguishers Safety Boots x Work Vest Goggles x Lockout/Tagout Safety Glasses x Safety Harness x Barriers x Work Permit Required x Uncontrolled When Printed Page 2 of 2 Sequence of Basic Job Steps Potential Accidents or Hazards Recommendation to Eliminate or Reduce Potential Hazards Who? Initials 1. Hold pre-job meeting – Work-permit 1. Procedures not known or not understood by crew members- Persons involved in task becoming injured by incorrect procedure compliance 1. Take time to read correctly JSA . Be sure everything is understood. If not ask your Supervisor Supervisors 2. Prepare & inspect tools – Put crane boom on cradle 2. Tools inadequate or in bad condition – Crane failure – Damaged cradle 2. Ensure you will use proper tools for the job before going on boom crane – Check safety harness – Operate crane slowly BE – ABE Roustabouts Crane Operator 3. Disconnect old pendants 3. Safety pins falling down – Pendants falling down on people – People falling down from boom crane – Hands injuries – Pinch points – Safety walkway on boom crane broken 3. Slack completely & secure pendants on boom crane before removing pins – Secure pins – Fix safety harness correctly – Careful when hammering – Hook-up pendant to opposite crane - Ensure that safety walkway on boom crane is in good condition BE - ABE Crane Operator Roustabouts 4. Remove pendant with opposite crane 4. Pendant falling down – People falling down from boom crane People struck by opposite crane sling hook 4. Ensure that pendant is secure correctly – Hook up pendant slowly equalize lifting point ( middle of pendant ) & release fastening ropes pendant 1 by 1 – Operate the crane slowly – Do not stay below boom crane – Fasten harness correctly BE – ABE Roustabouts CraneOperator 5. Install new pendant 5. Pendant falling down – People falling down from boom crane – People struck by pendant – Hands injuries – Pinch points – Pendant safety pin falling on people – Tools falling 5. Lift up & position new pendant slowly with crane – Equalize lifting point ( middle of pendant ) – Connect 1 side of pendant on boom crane – Slack slowly pendant & secure on boom crane – Connect 2nd end of pendant on boom – Operate crane slowly – Fix correctly harness – Do not stay below boom crane during operation – Watch hands position – Secure tools & pins BE – ABE Roustabouts Crane Operator 6. Crane boom up 6. Boom falling down – Tools falling down from boom crane 6. Ensure before raising boom that pendants are correctly installed & secured – Check before raising boom that any tools still on boom crane – Do not stay below boom crane – Operate crane slowly BE – ABE Roustabouts Crane Operator Pyramid Drilling S.A Manual Title: Personnel Safety Manual Form Name: Job Safety Analysis Issue Date 02-Sept-07 Revision No. 2 Revision Date 04-MAR 08 Prepared By QA/HSE Approved By HM Level No. 2