Manual Title: Personnel Safety Manual
Form Name: Job Safety Analysis
Issue Date
02-Sept-07
Revision No.
2
Revision Date
04-OCTOBER 07
Prepared By
QA/HSE
Approved By
HM
Level No.
2
Rig Name/#: BENNEVIS JSA Number : MA 004 Person Approving JSA:
Work Activity (Job Painting & cleaning inside tank Date Raised :
Work Team (Crew Members): ABE/ Roustabouts Date Last Amended :
Sequence of Basic Job Steps Potential Accidents or Hazards
Recommendation to Eliminate or Reduce Potential
Hazards
Who?
Initials
1. Hold pre-job meeting – Work-permit 1. Procedures not known or not understood by crew member 1. Take time to read correctly JSA . Be sure everything is
understood. If not ask your Supervisor
BE
2 . Prepare and inspect tools needed for the
job : Scaffolding condition – Harness – Paint
equipment
2. Falling from scaffolding – Scaffolding not erecting correctly
– Inhaling in skin – Hit by air hose paint spray gun
2. Inspect all tools & equipment needed for the job before to
ensure proper use – Erect scaffolding by competent person
– Wear proper PPE & protective equipment for paint jobs
ABE –
Roustabouts
- Painters
3. Erecting scaffolding Falling down during installation – Tools slipping or
falling during installation – pinch points –
Scaffolding falling down
Clean area before erecting – Secure tools during the
installation – Erect scaffolding by competent person
BE-ABE-
Electrician
Safety -
Roustabouts
4. Paint job 4. Falling down from scaffolding – Inhaling spray vapors – Poor
atmosphere and visibility due to spray paint -
6. Use harness and fix it correctly – Install enough 24 volts
lights – Stand-by man outside of tank all the time during job
– Ventilate tank all along the job – Continuous gas detection
– Wear proper PPE & protective equipment for paint jobs
Safety-ABE-
Painters
5. Removing tools and scaffolding 5. Tripping hazards – Same as step # 5 5 Same as step # 4 ABE –
Roustabouts
Safety Equipment To Do This Job(
Hard Hats x Gloves x Face Shield x Fire Extinguishers
Safety Boots x Work Vest Goggles x Lockout/Tagout
Safety Glasses x Safety Harness x Barriers Work Permit Required x
Page 1 of 1

More Related Content

Similar to Ma 004 paint jobs inside tanks

Ma 003 erecting & removing scaffolding in tanks
Ma 003  erecting & removing scaffolding in tanksMa 003  erecting & removing scaffolding in tanks
Ma 003 erecting & removing scaffolding in tanksYousif Fikry
 
Ma 002 welding in tanks
Ma 002  welding in tanksMa 002  welding in tanks
Ma 002 welding in tanksYousif Fikry
 
Ma 015 boom crane paint maintenance
Ma 015  boom crane paint maintenanceMa 015  boom crane paint maintenance
Ma 015 boom crane paint maintenanceYousif Fikry
 
Ma 005 cleaning front of main wall accomodations
Ma 005 cleaning front of main wall accomodationsMa 005 cleaning front of main wall accomodations
Ma 005 cleaning front of main wall accomodationsYousif Fikry
 
Ma 001 tanks & preloads visual inspection
Ma 001  tanks & preloads visual inspectionMa 001  tanks & preloads visual inspection
Ma 001 tanks & preloads visual inspectionYousif Fikry
 
Ma 019 preloads dump valves maintenance
Ma 019  preloads dump valves maintenanceMa 019  preloads dump valves maintenance
Ma 019 preloads dump valves maintenanceYousif Fikry
 
Ma 018 changing lifeboats wires
Ma 018 changing lifeboats wiresMa 018 changing lifeboats wires
Ma 018 changing lifeboats wiresYousif Fikry
 
Ma 016 unloading coiled tubing real from boat & install it on cantilever deck
Ma 016  unloading coiled tubing real from boat & install it on cantilever deckMa 016  unloading coiled tubing real from boat & install it on cantilever deck
Ma 016 unloading coiled tubing real from boat & install it on cantilever deckYousif Fikry
 
Ma 017 backloading coiled tubing real on boat
Ma 017  backloading coiled tubing real on boatMa 017  backloading coiled tubing real on boat
Ma 017 backloading coiled tubing real on boatYousif Fikry
 
Ma 021 backload flare boom on supply-boat
Ma 021 backload flare boom on supply-boatMa 021 backload flare boom on supply-boat
Ma 021 backload flare boom on supply-boatYousif Fikry
 
Ma 014 changing boom pendants on both cranes
Ma 014  changing boom pendants on both cranesMa 014  changing boom pendants on both cranes
Ma 014 changing boom pendants on both cranesYousif Fikry
 
Ma 013 testing lifeboats capsules
Ma 013  testing  lifeboats  capsulesMa 013  testing  lifeboats  capsules
Ma 013 testing lifeboats capsulesYousif Fikry
 
Ma 008 removing mooring ropes from legs
Ma 008 removing mooring ropes from legsMa 008 removing mooring ropes from legs
Ma 008 removing mooring ropes from legsYousif Fikry
 
Ma 006 transfer by personnel basket
Ma 006  transfer by personnel basketMa 006  transfer by personnel basket
Ma 006 transfer by personnel basketYousif Fikry
 
Ma 07 installing mooring ropes on legs
Ma 07  installing mooring ropes on legsMa 07  installing mooring ropes on legs
Ma 07 installing mooring ropes on legsYousif Fikry
 
Job Safety Analyses For Energization of Substation..doc
Job Safety Analyses For Energization of Substation..docJob Safety Analyses For Energization of Substation..doc
Job Safety Analyses For Energization of Substation..docAtif767782
 
JSA-Piling or Concreting for Foundations & Building
JSA-Piling or Concreting for Foundations & Building JSA-Piling or Concreting for Foundations & Building
JSA-Piling or Concreting for Foundations & Building Alvin160771
 
Methodstatement welding
Methodstatement weldingMethodstatement welding
Methodstatement weldingAanand Subi
 
Assignment front sheet assignment 2
Assignment front sheet assignment 2Assignment front sheet assignment 2
Assignment front sheet assignment 2NeilOw87
 

Similar to Ma 004 paint jobs inside tanks (20)

Ma 003 erecting & removing scaffolding in tanks
Ma 003  erecting & removing scaffolding in tanksMa 003  erecting & removing scaffolding in tanks
Ma 003 erecting & removing scaffolding in tanks
 
Ma 002 welding in tanks
Ma 002  welding in tanksMa 002  welding in tanks
Ma 002 welding in tanks
 
Ma 015 boom crane paint maintenance
Ma 015  boom crane paint maintenanceMa 015  boom crane paint maintenance
Ma 015 boom crane paint maintenance
 
Ma 005 cleaning front of main wall accomodations
Ma 005 cleaning front of main wall accomodationsMa 005 cleaning front of main wall accomodations
Ma 005 cleaning front of main wall accomodations
 
Ma 001 tanks & preloads visual inspection
Ma 001  tanks & preloads visual inspectionMa 001  tanks & preloads visual inspection
Ma 001 tanks & preloads visual inspection
 
Ma 019 preloads dump valves maintenance
Ma 019  preloads dump valves maintenanceMa 019  preloads dump valves maintenance
Ma 019 preloads dump valves maintenance
 
Ma 018 changing lifeboats wires
Ma 018 changing lifeboats wiresMa 018 changing lifeboats wires
Ma 018 changing lifeboats wires
 
Ma 016 unloading coiled tubing real from boat & install it on cantilever deck
Ma 016  unloading coiled tubing real from boat & install it on cantilever deckMa 016  unloading coiled tubing real from boat & install it on cantilever deck
Ma 016 unloading coiled tubing real from boat & install it on cantilever deck
 
Ma 017 backloading coiled tubing real on boat
Ma 017  backloading coiled tubing real on boatMa 017  backloading coiled tubing real on boat
Ma 017 backloading coiled tubing real on boat
 
Ma 021 backload flare boom on supply-boat
Ma 021 backload flare boom on supply-boatMa 021 backload flare boom on supply-boat
Ma 021 backload flare boom on supply-boat
 
Ma 014 changing boom pendants on both cranes
Ma 014  changing boom pendants on both cranesMa 014  changing boom pendants on both cranes
Ma 014 changing boom pendants on both cranes
 
Ma 013 testing lifeboats capsules
Ma 013  testing  lifeboats  capsulesMa 013  testing  lifeboats  capsules
Ma 013 testing lifeboats capsules
 
Ma 008 removing mooring ropes from legs
Ma 008 removing mooring ropes from legsMa 008 removing mooring ropes from legs
Ma 008 removing mooring ropes from legs
 
Ma 022 preloading
Ma 022 preloadingMa 022 preloading
Ma 022 preloading
 
Ma 006 transfer by personnel basket
Ma 006  transfer by personnel basketMa 006  transfer by personnel basket
Ma 006 transfer by personnel basket
 
Ma 07 installing mooring ropes on legs
Ma 07  installing mooring ropes on legsMa 07  installing mooring ropes on legs
Ma 07 installing mooring ropes on legs
 
Job Safety Analyses For Energization of Substation..doc
Job Safety Analyses For Energization of Substation..docJob Safety Analyses For Energization of Substation..doc
Job Safety Analyses For Energization of Substation..doc
 
JSA-Piling or Concreting for Foundations & Building
JSA-Piling or Concreting for Foundations & Building JSA-Piling or Concreting for Foundations & Building
JSA-Piling or Concreting for Foundations & Building
 
Methodstatement welding
Methodstatement weldingMethodstatement welding
Methodstatement welding
 
Assignment front sheet assignment 2
Assignment front sheet assignment 2Assignment front sheet assignment 2
Assignment front sheet assignment 2
 

More from Yousif Fikry

Ma 039 jsa emergency load lowering
Ma 039 jsa emergency load loweringMa 039 jsa emergency load lowering
Ma 039 jsa emergency load loweringYousif Fikry
 
Ma 038 painting on derrick set
Ma 038 painting on derrick setMa 038 painting on derrick set
Ma 038 painting on derrick setYousif Fikry
 
Ma 037 cleaning with air brush
Ma 037 cleaning with air brushMa 037 cleaning with air brush
Ma 037 cleaning with air brushYousif Fikry
 
Ma 036 jsa check ballast 5p loading valve
Ma 036 jsa check ballast 5p loading valveMa 036 jsa check ballast 5p loading valve
Ma 036 jsa check ballast 5p loading valveYousif Fikry
 
Ma 035 jsa open seachest
Ma 035   jsa open seachestMa 035   jsa open seachest
Ma 035 jsa open seachestYousif Fikry
 
Ma 034 jsa general lifting on the deck
Ma 034   jsa general lifting on the deckMa 034   jsa general lifting on the deck
Ma 034 jsa general lifting on the deckYousif Fikry
 
Ma 033 jsa rack pup joint in the stb rack
Ma 033 jsa rack pup joint in the stb rackMa 033 jsa rack pup joint in the stb rack
Ma 033 jsa rack pup joint in the stb rackYousif Fikry
 
Ma 032 transfer water from or to supply boat
Ma 032 transfer water from or to supply boatMa 032 transfer water from or to supply boat
Ma 032 transfer water from or to supply boatYousif Fikry
 
Ma 031 transfer brine from or to supply boat
Ma 031 transfer brine from or to supply boatMa 031 transfer brine from or to supply boat
Ma 031 transfer brine from or to supply boatYousif Fikry
 
Ma 030 cleaning oil in 100 t crane
Ma 030 cleaning oil in 100 t craneMa 030 cleaning oil in 100 t crane
Ma 030 cleaning oil in 100 t craneYousif Fikry
 
Ma 029 loading & offloading tubulars from a supply boat
Ma 029 loading & offloading tubulars from a supply boatMa 029 loading & offloading tubulars from a supply boat
Ma 029 loading & offloading tubulars from a supply boatYousif Fikry
 
Ma 028 jsa open seachest
Ma 028    jsa open seachestMa 028    jsa open seachest
Ma 028 jsa open seachestYousif Fikry
 
Ma 027 jsa general lifting on the deck
Ma 027  jsa general lifting on the deckMa 027  jsa general lifting on the deck
Ma 027 jsa general lifting on the deckYousif Fikry
 
Ma 026 offloading or backloading fuel, base oil, obm
Ma 026 offloading or backloading fuel, base oil, obmMa 026 offloading or backloading fuel, base oil, obm
Ma 026 offloading or backloading fuel, base oil, obmYousif Fikry
 
Ma 025 transfer casing
Ma 025 transfer casingMa 025 transfer casing
Ma 025 transfer casingYousif Fikry
 
Ma 024 working on ladder
Ma 024 working on ladderMa 024 working on ladder
Ma 024 working on ladderYousif Fikry
 
Ma 023 change out butter fly valve for bulk system
Ma 023  change out butter fly valve for bulk systemMa 023  change out butter fly valve for bulk system
Ma 023 change out butter fly valve for bulk systemYousif Fikry
 

More from Yousif Fikry (18)

Welding operation
Welding operationWelding operation
Welding operation
 
Ma 039 jsa emergency load lowering
Ma 039 jsa emergency load loweringMa 039 jsa emergency load lowering
Ma 039 jsa emergency load lowering
 
Ma 038 painting on derrick set
Ma 038 painting on derrick setMa 038 painting on derrick set
Ma 038 painting on derrick set
 
Ma 037 cleaning with air brush
Ma 037 cleaning with air brushMa 037 cleaning with air brush
Ma 037 cleaning with air brush
 
Ma 036 jsa check ballast 5p loading valve
Ma 036 jsa check ballast 5p loading valveMa 036 jsa check ballast 5p loading valve
Ma 036 jsa check ballast 5p loading valve
 
Ma 035 jsa open seachest
Ma 035   jsa open seachestMa 035   jsa open seachest
Ma 035 jsa open seachest
 
Ma 034 jsa general lifting on the deck
Ma 034   jsa general lifting on the deckMa 034   jsa general lifting on the deck
Ma 034 jsa general lifting on the deck
 
Ma 033 jsa rack pup joint in the stb rack
Ma 033 jsa rack pup joint in the stb rackMa 033 jsa rack pup joint in the stb rack
Ma 033 jsa rack pup joint in the stb rack
 
Ma 032 transfer water from or to supply boat
Ma 032 transfer water from or to supply boatMa 032 transfer water from or to supply boat
Ma 032 transfer water from or to supply boat
 
Ma 031 transfer brine from or to supply boat
Ma 031 transfer brine from or to supply boatMa 031 transfer brine from or to supply boat
Ma 031 transfer brine from or to supply boat
 
Ma 030 cleaning oil in 100 t crane
Ma 030 cleaning oil in 100 t craneMa 030 cleaning oil in 100 t crane
Ma 030 cleaning oil in 100 t crane
 
Ma 029 loading & offloading tubulars from a supply boat
Ma 029 loading & offloading tubulars from a supply boatMa 029 loading & offloading tubulars from a supply boat
Ma 029 loading & offloading tubulars from a supply boat
 
Ma 028 jsa open seachest
Ma 028    jsa open seachestMa 028    jsa open seachest
Ma 028 jsa open seachest
 
Ma 027 jsa general lifting on the deck
Ma 027  jsa general lifting on the deckMa 027  jsa general lifting on the deck
Ma 027 jsa general lifting on the deck
 
Ma 026 offloading or backloading fuel, base oil, obm
Ma 026 offloading or backloading fuel, base oil, obmMa 026 offloading or backloading fuel, base oil, obm
Ma 026 offloading or backloading fuel, base oil, obm
 
Ma 025 transfer casing
Ma 025 transfer casingMa 025 transfer casing
Ma 025 transfer casing
 
Ma 024 working on ladder
Ma 024 working on ladderMa 024 working on ladder
Ma 024 working on ladder
 
Ma 023 change out butter fly valve for bulk system
Ma 023  change out butter fly valve for bulk systemMa 023  change out butter fly valve for bulk system
Ma 023 change out butter fly valve for bulk system
 

Ma 004 paint jobs inside tanks

  • 1. Pyramid Drilling S.A Manual Title: Personnel Safety Manual Form Name: Job Safety Analysis Issue Date 02-Sept-07 Revision No. 2 Revision Date 04-OCTOBER 07 Prepared By QA/HSE Approved By HM Level No. 2 Rig Name/#: BENNEVIS JSA Number : MA 004 Person Approving JSA: Work Activity (Job Painting & cleaning inside tank Date Raised : Work Team (Crew Members): ABE/ Roustabouts Date Last Amended : Sequence of Basic Job Steps Potential Accidents or Hazards Recommendation to Eliminate or Reduce Potential Hazards Who? Initials 1. Hold pre-job meeting – Work-permit 1. Procedures not known or not understood by crew member 1. Take time to read correctly JSA . Be sure everything is understood. If not ask your Supervisor BE 2 . Prepare and inspect tools needed for the job : Scaffolding condition – Harness – Paint equipment 2. Falling from scaffolding – Scaffolding not erecting correctly – Inhaling in skin – Hit by air hose paint spray gun 2. Inspect all tools & equipment needed for the job before to ensure proper use – Erect scaffolding by competent person – Wear proper PPE & protective equipment for paint jobs ABE – Roustabouts - Painters 3. Erecting scaffolding Falling down during installation – Tools slipping or falling during installation – pinch points – Scaffolding falling down Clean area before erecting – Secure tools during the installation – Erect scaffolding by competent person BE-ABE- Electrician Safety - Roustabouts 4. Paint job 4. Falling down from scaffolding – Inhaling spray vapors – Poor atmosphere and visibility due to spray paint - 6. Use harness and fix it correctly – Install enough 24 volts lights – Stand-by man outside of tank all the time during job – Ventilate tank all along the job – Continuous gas detection – Wear proper PPE & protective equipment for paint jobs Safety-ABE- Painters 5. Removing tools and scaffolding 5. Tripping hazards – Same as step # 5 5 Same as step # 4 ABE – Roustabouts Safety Equipment To Do This Job( Hard Hats x Gloves x Face Shield x Fire Extinguishers Safety Boots x Work Vest Goggles x Lockout/Tagout Safety Glasses x Safety Harness x Barriers Work Permit Required x Page 1 of 1