SlideShare a Scribd company logo
1 of 21
Download to read offline
ESTIMATING & COSTING
ARUN RAVI.K.R
Instructor, Draughtsman (Civil)
Part -2
Different Types of Sanctions01
LEARNING OBJECTIVES
Different Types of Estimates02
Estimate Sanction
Before the execution Three Sanctions are Required
Administrative Sanction
Financial Sanction (Expenditure sanction)
Technical sanction
Administrative Sanction (A.S)
For any project an approval or sanction of the competent authority
of the department is necessary at the first instance with respect of the cost
and work. (Sanction from Govt.)
Administrative approval denotes to formal acceptance of the
proposal. After A.S, the engineering department take up the work and
prepares detailed design, plans and estimates and then executes the work.
Financial Sanction (Expenditure sanction)
Financial sanction means allotment of fund or money for
a project from the finance department of Government
Technical Sanction (T.S)
The sanction of the detailed estimates,
design calculation, quantities of works,
rates and cost of the work by the
competent authority of the engineering
department is known as Technical
Sanction.
TYPES OF ESTIMATE
Preliminary or approximate or abstract estimate
This type of estimate is required for preliminary studies of
a project, to decide the financial position and policy for
administrative sanction by the competent administrative
authority.
The approximate estimate is prepared
with the practical knowledge and cost of the
similar works. This is also accompanied with
a site plan or layout plan. A percentage of
about 5% to 10% is added as contingencies.
Plinth area estimate (P.A. estimate)
This is prepared on the basis of plinth area of building, the
rate being deducted from the cost of similar building having
similar specification, heights and construction, in the locality.
Plinth area estimate is calculated
by finding the plinth area of the building
and multiplying by the plinth area rate.
Cubic rate estimate
This is prepared on the basis of the cubical contents of
the building. The cube rate being deducted from the cost of the
similar building having similar specifications and construction,
in the locality.
This is calculated by finding the
cubical content of the building (length
x breadth x height) and multiplied it by
the cube rate.
Cube rate estimate is most accurate
than to the plinth area estimate
Approximate quantity method
In this method approximate total length of work is found
in running metre and this total length multiplied by the rate per
running metre of wall gives a fairly accurate cost.
For this method the plan or line plan
of the structure should be available.
Detailed estimate
Detailed estimate is an accurate estimate consists of the
quantities of each item of works, and working the cost.
The dimensions, (length, breadth and height) of each item
are taken out correctly from drawing and quantities of each item
are calculated.
The detailed estimate is prepared in two stages.
1) Details of measurement and calculation of quantities
2) Abstract of estimate cost
1) Details of measurement and calculation of quantities
The details of measurement of each item of work are
taken out correctly from plan and drawings and quantities
under each item are computed or calculated in a tabular form
named as Details of Measurement Form (Table 1).
2) Abstract of estimate cost
The cost of each item of work is calculated in a tabular
form from the quantities already computed and total cost is
worked out in abstract of estimate form (Table 2). The rates of
different items of work are taken as per schedule of rates
Detailed Estimate Abstract estimate
Revised estimate
Revised Estimate is detailed estimate and is prepared
under any one of the following circumstances.
I. When the original sanctioned estimate is exceeds more than
5%.
II. When the expenditure on a work exceeds of administrative
sanction by more than 10%
III. When there are material deviation from the original proposal,
even though the cost may be met from the sanctioned
amount.
The revised estimate should be accompanied by a
comparative statement showing the variations of each
item of works
Supplementary estimate
Supplementary estimate is a detailed estimate and is
prepared when additional works are required to supplement the
original works, or when further developments is required during
the progress of work.
This is a fresh detailed estimate of the additional works in
addition to the original estimate.
Supplementary and revised estimate
 When a work is partially abandoned and the remaining
work is less than 95% of the original sanctioned estimate.
Or
 when there are material deviations and changes in the design
which may cause excess or saving in the estimate,
A supplementary and Revised Estimate is then prepared
and fresh technical sanction of the competent authority is
obtained.
Annual repair or annual maintenance estimate (A.R. or A.M. Estimate):
This estimate is a detailed estimate and is prepared to
maintain the structure or work in proper order and safe
condition.
For building: Includes white
washing, colour washing,
painting, minor repairs etc.
For road works: Tarring patch repairing,
renewals, repairs of bridges and culvert, etc.
Extension and improvement estimate
When some changes and
extensions are required to be made in
the old work, the cost of which cannot
be met by the annual
repair/maintenance estimate, a detailed
estimate is prepared for such work
which is called as extension and
improvement estimate.
ARUN RAVI.K.R
Instructor, Draughtsman (Civil)
arunravikr@gmail.com
9447622946

More Related Content

What's hot

1# introduction to Quantity Surveying
1# introduction to Quantity Surveying1# introduction to Quantity Surveying
1# introduction to Quantity Surveying
LIJI A
 
Estimating and-costing book
Estimating and-costing bookEstimating and-costing book
Estimating and-costing book
Thomas Britto
 

What's hot (20)

Terminology used in estimating and costing
Terminology used in estimating and costingTerminology used in estimating and costing
Terminology used in estimating and costing
 
Rate analysis
Rate analysisRate analysis
Rate analysis
 
Estimating & Costing - I
Estimating & Costing - IEstimating & Costing - I
Estimating & Costing - I
 
Analysis of rates
Analysis of ratesAnalysis of rates
Analysis of rates
 
Schedule of Rates
Schedule of RatesSchedule of Rates
Schedule of Rates
 
Types of estimate
Types of estimateTypes of estimate
Types of estimate
 
estimation and quantity surveying
estimation and quantity surveyingestimation and quantity surveying
estimation and quantity surveying
 
Estimating and-costing
Estimating and-costingEstimating and-costing
Estimating and-costing
 
Estimating and Costing
Estimating and CostingEstimating and Costing
Estimating and Costing
 
Types of estimates
Types of estimatesTypes of estimates
Types of estimates
 
ESTIMATING AND COSTING
ESTIMATING AND COSTINGESTIMATING AND COSTING
ESTIMATING AND COSTING
 
Estimation and Costing - Contracts
Estimation and Costing - ContractsEstimation and Costing - Contracts
Estimation and Costing - Contracts
 
1# introduction to Quantity Surveying
1# introduction to Quantity Surveying1# introduction to Quantity Surveying
1# introduction to Quantity Surveying
 
Estimating and costing
Estimating and costingEstimating and costing
Estimating and costing
 
Estimating and-costing book
Estimating and-costing bookEstimating and-costing book
Estimating and-costing book
 
BUILDING ESTIMATION (Details Estimate For G+2 Storied Building presentation ...
BUILDING ESTIMATION (Details Estimate For G+2  Storied Building presentation ...BUILDING ESTIMATION (Details Estimate For G+2  Storied Building presentation ...
BUILDING ESTIMATION (Details Estimate For G+2 Storied Building presentation ...
 
Specifications of buildings
Specifications of buildingsSpecifications of buildings
Specifications of buildings
 
Construction planning & management
Construction planning & managementConstruction planning & management
Construction planning & management
 
Approximate estimate
Approximate estimateApproximate estimate
Approximate estimate
 
Unit-4_Specification
Unit-4_SpecificationUnit-4_Specification
Unit-4_Specification
 

Similar to Estimating part 2

approximateestimate-200713090343.pdf
approximateestimate-200713090343.pdfapproximateestimate-200713090343.pdf
approximateestimate-200713090343.pdf
Deepak37004
 

Similar to Estimating part 2 (20)

Estimation and Costing
Estimation and CostingEstimation and Costing
Estimation and Costing
 
Unit 1 - General Items used for building
Unit 1 - General Items used for buildingUnit 1 - General Items used for building
Unit 1 - General Items used for building
 
EEEC pdf.pdf
EEEC pdf.pdfEEEC pdf.pdf
EEEC pdf.pdf
 
IV -I - EQS - .pptx
IV -I - EQS - .pptxIV -I - EQS - .pptx
IV -I - EQS - .pptx
 
Ecv
EcvEcv
Ecv
 
Lec05.pptx
Lec05.pptxLec05.pptx
Lec05.pptx
 
Aiet e&c lecture_notes
Aiet  e&c lecture_notesAiet  e&c lecture_notes
Aiet e&c lecture_notes
 
Estimation Costing and Valuation Unit 2
Estimation Costing and Valuation Unit 2Estimation Costing and Valuation Unit 2
Estimation Costing and Valuation Unit 2
 
approximateestimate-200713090343.pdf
approximateestimate-200713090343.pdfapproximateestimate-200713090343.pdf
approximateestimate-200713090343.pdf
 
Construction Planning and Scheduling of Residential Building by MS Project by...
Construction Planning and Scheduling of Residential Building by MS Project by...Construction Planning and Scheduling of Residential Building by MS Project by...
Construction Planning and Scheduling of Residential Building by MS Project by...
 
chapter3-210122050220.pdf
chapter3-210122050220.pdfchapter3-210122050220.pdf
chapter3-210122050220.pdf
 
Fundamentals of estimating_and_costing
Fundamentals of estimating_and_costingFundamentals of estimating_and_costing
Fundamentals of estimating_and_costing
 
Introduction to estimation
Introduction to estimationIntroduction to estimation
Introduction to estimation
 
type of cost Estimation
type of cost Estimationtype of cost Estimation
type of cost Estimation
 
Estimation and costing of a commercial building
Estimation and costing of a commercial buildingEstimation and costing of a commercial building
Estimation and costing of a commercial building
 
Capital Expenditure Estimating Cost of Project
Capital Expenditure Estimating Cost of ProjectCapital Expenditure Estimating Cost of Project
Capital Expenditure Estimating Cost of Project
 
Capital Cost Expenditure Estimating .ppt
Capital Cost Expenditure Estimating .pptCapital Cost Expenditure Estimating .ppt
Capital Cost Expenditure Estimating .ppt
 
A brief on project cost management
A brief on project cost managementA brief on project cost management
A brief on project cost management
 
Quantity Survey and Estimation basic terms
Quantity Survey and Estimation basic termsQuantity Survey and Estimation basic terms
Quantity Survey and Estimation basic terms
 
Chapter 2 Approximate Estimates.pptx
Chapter 2 Approximate Estimates.pptxChapter 2 Approximate Estimates.pptx
Chapter 2 Approximate Estimates.pptx
 

Recently uploaded

Online crime reporting system project.pdf
Online crime reporting system project.pdfOnline crime reporting system project.pdf
Online crime reporting system project.pdf
Kamal Acharya
 
Activity Planning: Objectives, Project Schedule, Network Planning Model. Time...
Activity Planning: Objectives, Project Schedule, Network Planning Model. Time...Activity Planning: Objectives, Project Schedule, Network Planning Model. Time...
Activity Planning: Objectives, Project Schedule, Network Planning Model. Time...
Lovely Professional University
 

Recently uploaded (20)

Piping and instrumentation diagram p.pdf
Piping and instrumentation diagram p.pdfPiping and instrumentation diagram p.pdf
Piping and instrumentation diagram p.pdf
 
Quiz application system project report..pdf
Quiz application system project report..pdfQuiz application system project report..pdf
Quiz application system project report..pdf
 
Research Methodolgy & Intellectual Property Rights Series 1
Research Methodolgy & Intellectual Property Rights Series 1Research Methodolgy & Intellectual Property Rights Series 1
Research Methodolgy & Intellectual Property Rights Series 1
 
BRAKING SYSTEM IN INDIAN RAILWAY AutoCAD DRAWING
BRAKING SYSTEM IN INDIAN RAILWAY AutoCAD DRAWINGBRAKING SYSTEM IN INDIAN RAILWAY AutoCAD DRAWING
BRAKING SYSTEM IN INDIAN RAILWAY AutoCAD DRAWING
 
Online crime reporting system project.pdf
Online crime reporting system project.pdfOnline crime reporting system project.pdf
Online crime reporting system project.pdf
 
Lab Manual Arduino UNO Microcontrollar.docx
Lab Manual Arduino UNO Microcontrollar.docxLab Manual Arduino UNO Microcontrollar.docx
Lab Manual Arduino UNO Microcontrollar.docx
 
Online book store management system project.pdf
Online book store management system project.pdfOnline book store management system project.pdf
Online book store management system project.pdf
 
EMPLOYEE MANAGEMENT SYSTEM FINAL presentation
EMPLOYEE MANAGEMENT SYSTEM FINAL presentationEMPLOYEE MANAGEMENT SYSTEM FINAL presentation
EMPLOYEE MANAGEMENT SYSTEM FINAL presentation
 
E-Commerce Shopping using MERN Stack where different modules are present
E-Commerce Shopping using MERN Stack where different modules are presentE-Commerce Shopping using MERN Stack where different modules are present
E-Commerce Shopping using MERN Stack where different modules are present
 
ChatGPT Prompt Engineering for project managers.pdf
ChatGPT Prompt Engineering for project managers.pdfChatGPT Prompt Engineering for project managers.pdf
ChatGPT Prompt Engineering for project managers.pdf
 
Circuit Breaker arc phenomenon.pdf engineering
Circuit Breaker arc phenomenon.pdf engineeringCircuit Breaker arc phenomenon.pdf engineering
Circuit Breaker arc phenomenon.pdf engineering
 
Artificial Intelligence Bayesian Reasoning
Artificial Intelligence Bayesian ReasoningArtificial Intelligence Bayesian Reasoning
Artificial Intelligence Bayesian Reasoning
 
Activity Planning: Objectives, Project Schedule, Network Planning Model. Time...
Activity Planning: Objectives, Project Schedule, Network Planning Model. Time...Activity Planning: Objectives, Project Schedule, Network Planning Model. Time...
Activity Planning: Objectives, Project Schedule, Network Planning Model. Time...
 
Electrostatic field in a coaxial transmission line
Electrostatic field in a coaxial transmission lineElectrostatic field in a coaxial transmission line
Electrostatic field in a coaxial transmission line
 
Fabrication Of Automatic Star Delta Starter Using Relay And GSM Module By Utk...
Fabrication Of Automatic Star Delta Starter Using Relay And GSM Module By Utk...Fabrication Of Automatic Star Delta Starter Using Relay And GSM Module By Utk...
Fabrication Of Automatic Star Delta Starter Using Relay And GSM Module By Utk...
 
Involute of a circle,Square, pentagon,HexagonInvolute_Engineering Drawing.pdf
Involute of a circle,Square, pentagon,HexagonInvolute_Engineering Drawing.pdfInvolute of a circle,Square, pentagon,HexagonInvolute_Engineering Drawing.pdf
Involute of a circle,Square, pentagon,HexagonInvolute_Engineering Drawing.pdf
 
Multivibrator and its types defination and usges.pptx
Multivibrator and its types defination and usges.pptxMultivibrator and its types defination and usges.pptx
Multivibrator and its types defination and usges.pptx
 
Insurance management system project report.pdf
Insurance management system project report.pdfInsurance management system project report.pdf
Insurance management system project report.pdf
 
Geometric constructions Engineering Drawing.pdf
Geometric constructions Engineering Drawing.pdfGeometric constructions Engineering Drawing.pdf
Geometric constructions Engineering Drawing.pdf
 
Introduction to Heat Exchangers: Principle, Types and Applications
Introduction to Heat Exchangers: Principle, Types and ApplicationsIntroduction to Heat Exchangers: Principle, Types and Applications
Introduction to Heat Exchangers: Principle, Types and Applications
 

Estimating part 2

  • 1. ESTIMATING & COSTING ARUN RAVI.K.R Instructor, Draughtsman (Civil) Part -2
  • 2. Different Types of Sanctions01 LEARNING OBJECTIVES Different Types of Estimates02
  • 3. Estimate Sanction Before the execution Three Sanctions are Required Administrative Sanction Financial Sanction (Expenditure sanction) Technical sanction
  • 4. Administrative Sanction (A.S) For any project an approval or sanction of the competent authority of the department is necessary at the first instance with respect of the cost and work. (Sanction from Govt.) Administrative approval denotes to formal acceptance of the proposal. After A.S, the engineering department take up the work and prepares detailed design, plans and estimates and then executes the work.
  • 5. Financial Sanction (Expenditure sanction) Financial sanction means allotment of fund or money for a project from the finance department of Government
  • 6. Technical Sanction (T.S) The sanction of the detailed estimates, design calculation, quantities of works, rates and cost of the work by the competent authority of the engineering department is known as Technical Sanction.
  • 8. Preliminary or approximate or abstract estimate This type of estimate is required for preliminary studies of a project, to decide the financial position and policy for administrative sanction by the competent administrative authority. The approximate estimate is prepared with the practical knowledge and cost of the similar works. This is also accompanied with a site plan or layout plan. A percentage of about 5% to 10% is added as contingencies.
  • 9. Plinth area estimate (P.A. estimate) This is prepared on the basis of plinth area of building, the rate being deducted from the cost of similar building having similar specification, heights and construction, in the locality. Plinth area estimate is calculated by finding the plinth area of the building and multiplying by the plinth area rate.
  • 10. Cubic rate estimate This is prepared on the basis of the cubical contents of the building. The cube rate being deducted from the cost of the similar building having similar specifications and construction, in the locality. This is calculated by finding the cubical content of the building (length x breadth x height) and multiplied it by the cube rate. Cube rate estimate is most accurate than to the plinth area estimate
  • 11. Approximate quantity method In this method approximate total length of work is found in running metre and this total length multiplied by the rate per running metre of wall gives a fairly accurate cost. For this method the plan or line plan of the structure should be available.
  • 12. Detailed estimate Detailed estimate is an accurate estimate consists of the quantities of each item of works, and working the cost. The dimensions, (length, breadth and height) of each item are taken out correctly from drawing and quantities of each item are calculated. The detailed estimate is prepared in two stages. 1) Details of measurement and calculation of quantities 2) Abstract of estimate cost
  • 13. 1) Details of measurement and calculation of quantities The details of measurement of each item of work are taken out correctly from plan and drawings and quantities under each item are computed or calculated in a tabular form named as Details of Measurement Form (Table 1).
  • 14. 2) Abstract of estimate cost The cost of each item of work is calculated in a tabular form from the quantities already computed and total cost is worked out in abstract of estimate form (Table 2). The rates of different items of work are taken as per schedule of rates
  • 16. Revised estimate Revised Estimate is detailed estimate and is prepared under any one of the following circumstances. I. When the original sanctioned estimate is exceeds more than 5%. II. When the expenditure on a work exceeds of administrative sanction by more than 10% III. When there are material deviation from the original proposal, even though the cost may be met from the sanctioned amount. The revised estimate should be accompanied by a comparative statement showing the variations of each item of works
  • 17. Supplementary estimate Supplementary estimate is a detailed estimate and is prepared when additional works are required to supplement the original works, or when further developments is required during the progress of work. This is a fresh detailed estimate of the additional works in addition to the original estimate.
  • 18. Supplementary and revised estimate  When a work is partially abandoned and the remaining work is less than 95% of the original sanctioned estimate. Or  when there are material deviations and changes in the design which may cause excess or saving in the estimate, A supplementary and Revised Estimate is then prepared and fresh technical sanction of the competent authority is obtained.
  • 19. Annual repair or annual maintenance estimate (A.R. or A.M. Estimate): This estimate is a detailed estimate and is prepared to maintain the structure or work in proper order and safe condition. For building: Includes white washing, colour washing, painting, minor repairs etc. For road works: Tarring patch repairing, renewals, repairs of bridges and culvert, etc.
  • 20. Extension and improvement estimate When some changes and extensions are required to be made in the old work, the cost of which cannot be met by the annual repair/maintenance estimate, a detailed estimate is prepared for such work which is called as extension and improvement estimate.
  • 21. ARUN RAVI.K.R Instructor, Draughtsman (Civil) arunravikr@gmail.com 9447622946