xxxx Group
Finance Dep staff presentation
2015.6.24
Work in Progress
Understand Stage Of Completion
Measurability (Quantifiable)
Understand the value addition of
each cost element at each stage of
completion
UNDERSTAND COST ELEMENTS
Cycle time
Relation of
WIP Vs Cycle time
Short the Cycle time  Lower the WIP
Longer the Cycle  Higher the WIP
Location which Creates the WIP
RM
Factory
Finish Goods
Stores WIP
What is WIP
• WIP stands for Work In Progress
• DEFINITION of 'Work In Progress - WIP'
Material that has entered the production process but is not
yet a finished product.
Work in progress (WIP) therefore refers to all materials and
partly finished products that are at various stages of the
production process.
WIP excludes inventory of raw materials at the start of the
production cycle and finished products inventory at the end
of the production cycle.
Read more: http://www.investopedia.com/terms/w/workinprogress.asp#ixzz3dxra5T7p
Simple Process Map
Production Process
Work Center 1 Work Center 3Work Center 2
Op 4Op 3Op 1
Op 2
Op 9Op 8
Op 7
Op 6
Op 5
WC 1
Operation 2
5 activities
Method of Valuation
Raw
Material
VOH
Direct
Labour
RM
VOH
DL
25% Completed
RM
VOH
DL
50% Completed
RM
VOH
DL
75% Completed
If Product
Cost is 100/=
WIP value is
now 25/=
If Product
Cost is 100/=
WIP value is
now 50/=
If Product
Cost is 100/=
WIP value is
now 75/=
When the WIP is 100% completed
WIP Valuation is
FullCostisFinishGood
WIP Vs SFG (Semi Finish Goods)
Work Center 1
Op 3Op 1
Op 2
Operation 1 – 50%
completed 85pcs
Operation 2 – 75%
completed 85pcs
Operation 3 – 25%
completed 85pcs
Organization should plan to minimize
WIP value at any given time…
How the production techniques
optimize the cost of production
• PULL-KANBAN.avi.flv
Thank You for the listenership
Sugeeshwara Sirimanne
sugee@skillsholdings.com
+94(0)772375595
Colombo – Sri Lanka

WIP

  • 1.
    xxxx Group Finance Depstaff presentation 2015.6.24
  • 2.
    Work in Progress UnderstandStage Of Completion Measurability (Quantifiable) Understand the value addition of each cost element at each stage of completion UNDERSTAND COST ELEMENTS
  • 3.
  • 4.
    Relation of WIP VsCycle time Short the Cycle time  Lower the WIP Longer the Cycle  Higher the WIP
  • 6.
    Location which Createsthe WIP RM Factory Finish Goods Stores WIP
  • 7.
    What is WIP •WIP stands for Work In Progress • DEFINITION of 'Work In Progress - WIP' Material that has entered the production process but is not yet a finished product. Work in progress (WIP) therefore refers to all materials and partly finished products that are at various stages of the production process. WIP excludes inventory of raw materials at the start of the production cycle and finished products inventory at the end of the production cycle. Read more: http://www.investopedia.com/terms/w/workinprogress.asp#ixzz3dxra5T7p
  • 9.
  • 10.
    Production Process Work Center1 Work Center 3Work Center 2 Op 4Op 3Op 1 Op 2 Op 9Op 8 Op 7 Op 6 Op 5 WC 1 Operation 2 5 activities
  • 11.
    Method of Valuation Raw Material VOH Direct Labour RM VOH DL 25%Completed RM VOH DL 50% Completed RM VOH DL 75% Completed If Product Cost is 100/= WIP value is now 25/= If Product Cost is 100/= WIP value is now 50/= If Product Cost is 100/= WIP value is now 75/=
  • 12.
    When the WIPis 100% completed WIP Valuation is FullCostisFinishGood
  • 13.
    WIP Vs SFG(Semi Finish Goods) Work Center 1 Op 3Op 1 Op 2 Operation 1 – 50% completed 85pcs Operation 2 – 75% completed 85pcs Operation 3 – 25% completed 85pcs Organization should plan to minimize WIP value at any given time…
  • 14.
    How the productiontechniques optimize the cost of production • PULL-KANBAN.avi.flv Thank You for the listenership Sugeeshwara Sirimanne sugee@skillsholdings.com +94(0)772375595 Colombo – Sri Lanka