SlideShare a Scribd company logo
Using The Earned Value Method To
Calculate Project Delays In Terms Of
Time
By: Ahmed Elsayed
Experienced Planning Engineer with a demonstrated history of working in
the civil engineering industry. Certified Project Management Professional
(PMP®) Skilled in Primavera P6, Project Estimation, and Construction
Management. Have a Bachelor's degree (Bsc.) Civil Engineering focused
in Construction Management & Planning from Cairo University.
Reference Used
• “Practice Standard for Earned Value
Management”
ISBN: 1-930699-42-5
Published by: Project Management Institute, Inc.
Schedule Analysis & Forecasting 225 Oct.2015
Earned Value Method
• The Practice Standard “Practice Standard for
Earned Value Management” mentions two
methods to calculate Schedule Variance (SV) &
Schedule Performance Index (SPI).
• The two methods are:
1.Cost Based Method.
2.Time Based Method.
Schedule Analysis & Forecasting 325 Oct.2015
Cost Based Method
Schedule Analysis & Forecasting 425 Oct.2015
Cost Based Method
• The Cost Based Method is based on comparing
the Planned Value(PV) and the Earned Value(EV)
for work done at a certain moment of time.
• Based on Cost the SV & SPI are calculated as
follows:
SV= EV-PV SPI= EV/PV
Schedule Analysis & Forecasting 525 Oct.2015
Cost Based Method
• For example:
For a certain project , a progress report is
prepared at a certain date, It was found that
the Earned Value till the date is 32 M ($) & the
planned Value according to the schedule was
48 M ($). So the SV will be:
SV= EV-PV = 32 M – 48 M = -16 M ($)
Schedule Analysis & Forecasting 625 Oct.2015
Cost Based Method
• Schedule variance also can be represented as
a percentage by dividing it by the planned
Value:
SV= EV-PV = 32 M – 48 M = -16 M ($)
SV% = SV/PV = -16 M/48 M = -33%
Schedule Analysis & Forecasting 725 Oct.2015
Cost Based Method
• Schedule Performance is calculated by
dividing the Earned value by the Planned
Value, So the SPI will be:
SPI= EV/PV = 32 M / 48 M = 0.67
Schedule Analysis & Forecasting 825 Oct.2015
Cost Based Method
So from the example above:
• The SV indicates that a quantity
of work worth 16 M ($) was
supposed to be finished, but
actually it wasn’t:
• THE SV% & the SPI indicate that
33% of the planned work wasn’t
finished.
• But all these don’t refer to
delayed time.
SV = -16 M ($)
SV($)= -33%
SPI = 0.67
Schedule Analysis & Forecasting 925 Oct.2015
Why Cost based method cannot
be used to judge time?
Schedule Analysis & Forecasting 1025 Oct.2015
Cost Based Method
At the end of the Project, EV will be equal to the
planned value, So the SV & the SPI will be as
follows:
Which means that all work is done. But it neglects
the time delay, Even if the project stayed for 6
months later than it’s planned finish date.
SPI= EV/PV = 1
SV= EV - PV = zero
Schedule Analysis & Forecasting 1125 Oct.2015
Time Based Method
Schedule Analysis & Forecasting 1225 Oct.2015
Time Based Method
• The “Practice Standard for Earned Value
Management” states another method for
schedule analysis based on time.
• This method compares the Actual Time (AT)
vs the Planned Time (PT) for a fixed amount of
work (the work done till now)
Schedule Analysis & Forecasting 1325 Oct.2015
Time Based Method
• Based on Time the SV & SPI are calculated as
follows:
SPI(t)= PT/ATSV(t)= PT - AT
Schedule Analysis & Forecasting 1425 Oct.2015
Time Based Method
• For example:
• After four months of the project start, we
found that the amount of work done till now
was supposed to be done in three months
only. So the PT= 3 months & the AT= 4 months
SPI(t)= PT/AT = 3/4 = 0.75
SV(t)= PT – AT = 3 – 4 = -1 months
Schedule Analysis & Forecasting 1525 Oct.2015
Time Based Method
• The SV(t) means that the work has a delayed
time of one month and the SPI(t) means that
25% of work time is wasted.
SPI(t)= 0.75SV(t)= -1 months
Schedule Analysis & Forecasting 1625 Oct.2015
Time Based Method
• Let’s consider an example for a project which
was supposed to be finished within 12
months, it actually took 18 months to finish
work.
• We are calculating the SV(t) & the SPI(t) at the
end of the project. It will be as follows:
SPI(t)= PT/AT = 12/18 = 0.67
SV(t)= PT – AT = 12 – 18 = -6 months
Schedule Analysis & Forecasting 1725 Oct.2015
Time Based Method
• The above information means that the project
had a 6 months delay & 33% of it’s planned
time was wasted.
SPI(t)= 0.67SV(t)= -6 months
Schedule Analysis & Forecasting 1825 Oct.2015
Cost Based vs. Time Based
Cost Based Time Based
Assumptions Compares Cost of planned
work at certain date to the
Cost of actual work done till
the same Date.
Compares the Actual time
elapsed to do a certain amount
of work to the planned time
supposed to be elapsed for the
same amount of work.
Schedule
variance (output)
The SV output indicates the
cost of delayed work till a
certain date
The SV output indicates the
amount of wasted time (Delay)
till date
Schedule
performance
Index (output)
The SPI output indicates the
efficiency of work based on
scope (or Cost)
The SPI output indicates the
efficiency of work based on time
At the End of the
Project
If time delay occurred
SV = 0 days
SPI = 1
If time delay occurred
SV = - (x) days
SPI < 1
Schedule Analysis & Forecasting 1925 Oct.2015
Cost Based vs. Time Based
At the same Date
At the same CostSchedule Analysis & Forecasting 2025 Oct.2015
Application to an example Project
• At the 13th of Oct. 2015 for the example project
• No. of Elapsed days (from project start) (AT) = 338 days
• Cost of Actual Work done (EV) = 30,045,060 $
• Cost of planned work at the same date (PV) = 69,915,599.05 $
• This amount of work done till that date was supposed to be
done by 9th of July 2015,
• So the planned time (PT) = 242 days
Schedule Analysis & Forecasting 2125 Oct.2015
Application to an example Project
• Based on Cost:
• Based on Time:
EV= 30,045,060 $
PV= 69,915,599.05 $
AT= 338 days
PT= 242 dayes
SV= EV- PV= 30,045,060 - 69,915,599
So, SV = -39,870,539 $
SPI = EV/PV = 30,045,060 / 69,915,599 = 0.4297
SV(t)= PT – AT = 242 – 338 = 96 days
SPI(t)= PT / AT = 242 / 338 = 0.716
Schedule Analysis & Forecasting 2225 Oct.2015
Application to an example Project
• For the equation =
• We actually don’t know a formal reference to
this equation. However we can deduce it’s
logic to a certain extent.
Delay= (1-SPI)*Elapsed days
Schedule Analysis & Forecasting 2325 Oct.2015
How to use this equation ??
Delay= (1-SPI)*Elapsed days
Schedule Analysis & Forecasting 2425 Oct.2015
Application to an example Project
• Based on the last calculations for SV(t) & SPI (t)
• Let’s apply the equation for the SPI:
We used the SPI calculated on time basis to recalculate the
delay time (which is the same as the SV)
SV(t)= PT – AT = 242 – 338 = -96 days
SPI(t)= PT / AT = 242 / 338 = 0.716
Delay= (1-SPI)*Elapsed days = (1- 0.716)*338= 96 days which is
exactly equal to the value of SV(t)
Schedule Analysis & Forecasting 2525 Oct.2015
Application to an example Project
• For the cost basis method:
• Let’s apply the equation for the SPI:
• But if applied like this:
SV= EV- PV= 30,045,060 - 69,915,599
So, SV = -39,870,539 $
SPI = EV/PV = 30,045,060 / 69,915,599.05 = 0.4297
Delay= (1-SPI)*Elapsed days = (1- 0.4297)*338= 192 days which
is not equal to the value of SV
Delay= (1-SPI)*PV = (1- 0.4297)*69,915,599.05= 39,870,539 $
which is exactly equal to the value of SV
Schedule Analysis & Forecasting 2625 Oct.2015
• Where is the Problem ??
Schedule Analysis & Forecasting 2725 Oct.2015
The Problem is:
• We can use the SPI (based on cost Basis)
to calculate the cost of delayed work, but
we cannot use it to calculate the amount
of delayed time.
• To calculate the delayed time we use the
SPI(t) (based on time basis).
Schedule Analysis & Forecasting 2825 Oct.2015
The Problem is:
• Based on all mentioned before, The equations
Are useless –but not wrong- as they are just another
method to calculate the Schedule variance (SV)
provided that the proper SPI is used in the proper
equation.
Delay= (1-SPI(t))*Elapsed days
Or
Delay= (1-SPI)*Planned Value
Schedule Analysis & Forecasting 2925 Oct.2015

More Related Content

What's hot

Project scheduling and resource levelling_Construction Management
Project scheduling and resource levelling_Construction Management Project scheduling and resource levelling_Construction Management
Project scheduling and resource levelling_Construction Management
A Makwana
 
Earned value analysis
Earned value analysisEarned value analysis
Earned value analysis
Nikhil Raj
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
Saqib Raza
 
3. construction planning. construction project management
3. construction planning. construction project management3. construction planning. construction project management
3. construction planning. construction project managementKabilan Kabi
 
PMP : Precedence Diagram Method : Relationship Types | iZenBridge
PMP : Precedence Diagram Method : Relationship Types | iZenBridgePMP : Precedence Diagram Method : Relationship Types | iZenBridge
PMP : Precedence Diagram Method : Relationship Types | iZenBridge
Saket Bansal
 
Scheduling by Primavera - Training
Scheduling by Primavera - TrainingScheduling by Primavera - Training
Scheduling by Primavera - TrainingMohammed Feroze
 
Earned value analysis (1)
Earned value analysis (1)Earned value analysis (1)
Earned value analysis (1)
Harshit Mahajan
 
PMP Chap 7 - Project Cost Management - Part 2
PMP Chap 7 - Project Cost Management - Part 2PMP Chap 7 - Project Cost Management - Part 2
PMP Chap 7 - Project Cost Management - Part 2
Anand Bobade
 
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)Allan Leyte
 
Project Control Practical Way by Herve Baron
Project Control Practical Way by Herve BaronProject Control Practical Way by Herve Baron
Project Control Practical Way by Herve Baron
ignitetribes
 
Cpm and pert
Cpm and pertCpm and pert
Cpm and pert
Vignesh Jayakumar
 
Chapter 1-Project and Construction project.pptx
Chapter 1-Project and Construction project.pptxChapter 1-Project and Construction project.pptx
Chapter 1-Project and Construction project.pptx
teshome eshetu
 
Project Control
Project ControlProject Control
Project Control
Martin Sillaots
 
Contract payment and variation
Contract payment and variationContract payment and variation
Contract payment and variation
Vj NiroSh
 
Pre Bid Risk Assessment
Pre Bid Risk AssessmentPre Bid Risk Assessment
Pre Bid Risk Assessment
Sukhdarshan Singh
 
Quantity Surveyor presentation
Quantity Surveyor presentationQuantity Surveyor presentation
Quantity Surveyor presentation
cynfang Fong
 
Time Impact Analysis
Time Impact AnalysisTime Impact Analysis
Time Impact Analysis
Chris Carson
 
Delay analysis ... wise after the event.
Delay analysis ... wise after the event.Delay analysis ... wise after the event.
Delay analysis ... wise after the event.
Tim Lloyd
 
Construction Monthly Progress Report - June 2011
Construction Monthly Progress Report - June 2011Construction Monthly Progress Report - June 2011
Construction Monthly Progress Report - June 2011Jamal Nelson, CCM
 
00 Introduction of project scheduling
00 Introduction of project scheduling00 Introduction of project scheduling
00 Introduction of project scheduling
Soe Naing Win
 

What's hot (20)

Project scheduling and resource levelling_Construction Management
Project scheduling and resource levelling_Construction Management Project scheduling and resource levelling_Construction Management
Project scheduling and resource levelling_Construction Management
 
Earned value analysis
Earned value analysisEarned value analysis
Earned value analysis
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
 
3. construction planning. construction project management
3. construction planning. construction project management3. construction planning. construction project management
3. construction planning. construction project management
 
PMP : Precedence Diagram Method : Relationship Types | iZenBridge
PMP : Precedence Diagram Method : Relationship Types | iZenBridgePMP : Precedence Diagram Method : Relationship Types | iZenBridge
PMP : Precedence Diagram Method : Relationship Types | iZenBridge
 
Scheduling by Primavera - Training
Scheduling by Primavera - TrainingScheduling by Primavera - Training
Scheduling by Primavera - Training
 
Earned value analysis (1)
Earned value analysis (1)Earned value analysis (1)
Earned value analysis (1)
 
PMP Chap 7 - Project Cost Management - Part 2
PMP Chap 7 - Project Cost Management - Part 2PMP Chap 7 - Project Cost Management - Part 2
PMP Chap 7 - Project Cost Management - Part 2
 
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)
 
Project Control Practical Way by Herve Baron
Project Control Practical Way by Herve BaronProject Control Practical Way by Herve Baron
Project Control Practical Way by Herve Baron
 
Cpm and pert
Cpm and pertCpm and pert
Cpm and pert
 
Chapter 1-Project and Construction project.pptx
Chapter 1-Project and Construction project.pptxChapter 1-Project and Construction project.pptx
Chapter 1-Project and Construction project.pptx
 
Project Control
Project ControlProject Control
Project Control
 
Contract payment and variation
Contract payment and variationContract payment and variation
Contract payment and variation
 
Pre Bid Risk Assessment
Pre Bid Risk AssessmentPre Bid Risk Assessment
Pre Bid Risk Assessment
 
Quantity Surveyor presentation
Quantity Surveyor presentationQuantity Surveyor presentation
Quantity Surveyor presentation
 
Time Impact Analysis
Time Impact AnalysisTime Impact Analysis
Time Impact Analysis
 
Delay analysis ... wise after the event.
Delay analysis ... wise after the event.Delay analysis ... wise after the event.
Delay analysis ... wise after the event.
 
Construction Monthly Progress Report - June 2011
Construction Monthly Progress Report - June 2011Construction Monthly Progress Report - June 2011
Construction Monthly Progress Report - June 2011
 
00 Introduction of project scheduling
00 Introduction of project scheduling00 Introduction of project scheduling
00 Introduction of project scheduling
 

Similar to Using The Earned Value Method To Calculate Project Delays In Terms Of Time

Lecture 5- Monitoring and Controlling Projects.ppt
Lecture 5- Monitoring and Controlling Projects.pptLecture 5- Monitoring and Controlling Projects.ppt
Lecture 5- Monitoring and Controlling Projects.ppt
vitumbikokhoswe1
 
IT Park - Earned Value ppt.ppt
IT Park - Earned Value ppt.pptIT Park - Earned Value ppt.ppt
IT Park - Earned Value ppt.ppt
DILIP KUMAR M.Tech (ACT)
 
Earned value management for Beginners
Earned value management for Beginners Earned value management for Beginners
Earned value management for Beginners Shenin Hassan
 
CAPM study session 4
CAPM study session 4CAPM study session 4
CAPM study session 4
Kinetic Potential
 
Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value Analysis
BECM, RUET, Bangladesh
 
Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting Projects Performance Analysis & Forecasting
Project Management EVM & SCBA
Project Management EVM & SCBAProject Management EVM & SCBA
Unit 3 PERT.pptx in related to supply chain
Unit 3 PERT.pptx in related to supply chainUnit 3 PERT.pptx in related to supply chain
Unit 3 PERT.pptx in related to supply chain
tanishkagupta907
 
1612170840-s-curve.pptx.................
1612170840-s-curve.pptx.................1612170840-s-curve.pptx.................
1612170840-s-curve.pptx.................
sukherafareed
 
07 projectcostmanagement
07 projectcostmanagement07 projectcostmanagement
07 projectcostmanagement
Dhamo daran
 
Module 06 Adv PM Budget Mgmt.ppt
Module 06 Adv PM Budget Mgmt.pptModule 06 Adv PM Budget Mgmt.ppt
Module 06 Adv PM Budget Mgmt.ppt
SandeepChauhan334237
 
Module 06 Adv Project Manager Budget Mgmt.ppt
Module 06 Adv Project Manager Budget Mgmt.pptModule 06 Adv Project Manager Budget Mgmt.ppt
Module 06 Adv Project Manager Budget Mgmt.ppt
AsBali1
 
project monitoring_and_control in project mgt
project monitoring_and_control in project mgtproject monitoring_and_control in project mgt
project monitoring_and_control in project mgt
debmahuya
 
160155061 project-monitoring-control
160155061 project-monitoring-control160155061 project-monitoring-control
160155061 project-monitoring-control
eidalin95
 
Back to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinarBack to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinar
Association for Project Management
 
Earned value Project Management (evpm)
Earned value Project Management (evpm)Earned value Project Management (evpm)
Earned value Project Management (evpm)
Ejaz Bhatti
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost ManagementSerdar Temiz
 
Day 2 Revision
Day 2 RevisionDay 2 Revision
Day 2 Revision
Joyce Wong
 
Performing against the wall - SPI after completion
Performing against the wall - SPI after completionPerforming against the wall - SPI after completion
Performing against the wall - SPI after completion
M Maged Hegazy, LLM, MBA, CCP, P3O
 

Similar to Using The Earned Value Method To Calculate Project Delays In Terms Of Time (20)

Lecture 5- Monitoring and Controlling Projects.ppt
Lecture 5- Monitoring and Controlling Projects.pptLecture 5- Monitoring and Controlling Projects.ppt
Lecture 5- Monitoring and Controlling Projects.ppt
 
IT Park - Earned Value ppt.ppt
IT Park - Earned Value ppt.pptIT Park - Earned Value ppt.ppt
IT Park - Earned Value ppt.ppt
 
Earned value management for Beginners
Earned value management for Beginners Earned value management for Beginners
Earned value management for Beginners
 
CAPM study session 4
CAPM study session 4CAPM study session 4
CAPM study session 4
 
Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value Analysis
 
Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting
 
Project Management EVM & SCBA
Project Management EVM & SCBAProject Management EVM & SCBA
Project Management EVM & SCBA
 
cpmpertmy (1)
cpmpertmy (1)cpmpertmy (1)
cpmpertmy (1)
 
Unit 3 PERT.pptx in related to supply chain
Unit 3 PERT.pptx in related to supply chainUnit 3 PERT.pptx in related to supply chain
Unit 3 PERT.pptx in related to supply chain
 
1612170840-s-curve.pptx.................
1612170840-s-curve.pptx.................1612170840-s-curve.pptx.................
1612170840-s-curve.pptx.................
 
07 projectcostmanagement
07 projectcostmanagement07 projectcostmanagement
07 projectcostmanagement
 
Module 06 Adv PM Budget Mgmt.ppt
Module 06 Adv PM Budget Mgmt.pptModule 06 Adv PM Budget Mgmt.ppt
Module 06 Adv PM Budget Mgmt.ppt
 
Module 06 Adv Project Manager Budget Mgmt.ppt
Module 06 Adv Project Manager Budget Mgmt.pptModule 06 Adv Project Manager Budget Mgmt.ppt
Module 06 Adv Project Manager Budget Mgmt.ppt
 
project monitoring_and_control in project mgt
project monitoring_and_control in project mgtproject monitoring_and_control in project mgt
project monitoring_and_control in project mgt
 
160155061 project-monitoring-control
160155061 project-monitoring-control160155061 project-monitoring-control
160155061 project-monitoring-control
 
Back to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinarBack to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinar
 
Earned value Project Management (evpm)
Earned value Project Management (evpm)Earned value Project Management (evpm)
Earned value Project Management (evpm)
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Day 2 Revision
Day 2 RevisionDay 2 Revision
Day 2 Revision
 
Performing against the wall - SPI after completion
Performing against the wall - SPI after completionPerforming against the wall - SPI after completion
Performing against the wall - SPI after completion
 

Recently uploaded

Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.
PrashantGoswami42
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
Kamal Acharya
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Arya
abh.arya
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
Intella Parts
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
Pipe Restoration Solutions
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 

Recently uploaded (20)

Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Arya
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 

Using The Earned Value Method To Calculate Project Delays In Terms Of Time

  • 1. Using The Earned Value Method To Calculate Project Delays In Terms Of Time By: Ahmed Elsayed Experienced Planning Engineer with a demonstrated history of working in the civil engineering industry. Certified Project Management Professional (PMP®) Skilled in Primavera P6, Project Estimation, and Construction Management. Have a Bachelor's degree (Bsc.) Civil Engineering focused in Construction Management & Planning from Cairo University.
  • 2. Reference Used • “Practice Standard for Earned Value Management” ISBN: 1-930699-42-5 Published by: Project Management Institute, Inc. Schedule Analysis & Forecasting 225 Oct.2015
  • 3. Earned Value Method • The Practice Standard “Practice Standard for Earned Value Management” mentions two methods to calculate Schedule Variance (SV) & Schedule Performance Index (SPI). • The two methods are: 1.Cost Based Method. 2.Time Based Method. Schedule Analysis & Forecasting 325 Oct.2015
  • 4. Cost Based Method Schedule Analysis & Forecasting 425 Oct.2015
  • 5. Cost Based Method • The Cost Based Method is based on comparing the Planned Value(PV) and the Earned Value(EV) for work done at a certain moment of time. • Based on Cost the SV & SPI are calculated as follows: SV= EV-PV SPI= EV/PV Schedule Analysis & Forecasting 525 Oct.2015
  • 6. Cost Based Method • For example: For a certain project , a progress report is prepared at a certain date, It was found that the Earned Value till the date is 32 M ($) & the planned Value according to the schedule was 48 M ($). So the SV will be: SV= EV-PV = 32 M – 48 M = -16 M ($) Schedule Analysis & Forecasting 625 Oct.2015
  • 7. Cost Based Method • Schedule variance also can be represented as a percentage by dividing it by the planned Value: SV= EV-PV = 32 M – 48 M = -16 M ($) SV% = SV/PV = -16 M/48 M = -33% Schedule Analysis & Forecasting 725 Oct.2015
  • 8. Cost Based Method • Schedule Performance is calculated by dividing the Earned value by the Planned Value, So the SPI will be: SPI= EV/PV = 32 M / 48 M = 0.67 Schedule Analysis & Forecasting 825 Oct.2015
  • 9. Cost Based Method So from the example above: • The SV indicates that a quantity of work worth 16 M ($) was supposed to be finished, but actually it wasn’t: • THE SV% & the SPI indicate that 33% of the planned work wasn’t finished. • But all these don’t refer to delayed time. SV = -16 M ($) SV($)= -33% SPI = 0.67 Schedule Analysis & Forecasting 925 Oct.2015
  • 10. Why Cost based method cannot be used to judge time? Schedule Analysis & Forecasting 1025 Oct.2015
  • 11. Cost Based Method At the end of the Project, EV will be equal to the planned value, So the SV & the SPI will be as follows: Which means that all work is done. But it neglects the time delay, Even if the project stayed for 6 months later than it’s planned finish date. SPI= EV/PV = 1 SV= EV - PV = zero Schedule Analysis & Forecasting 1125 Oct.2015
  • 12. Time Based Method Schedule Analysis & Forecasting 1225 Oct.2015
  • 13. Time Based Method • The “Practice Standard for Earned Value Management” states another method for schedule analysis based on time. • This method compares the Actual Time (AT) vs the Planned Time (PT) for a fixed amount of work (the work done till now) Schedule Analysis & Forecasting 1325 Oct.2015
  • 14. Time Based Method • Based on Time the SV & SPI are calculated as follows: SPI(t)= PT/ATSV(t)= PT - AT Schedule Analysis & Forecasting 1425 Oct.2015
  • 15. Time Based Method • For example: • After four months of the project start, we found that the amount of work done till now was supposed to be done in three months only. So the PT= 3 months & the AT= 4 months SPI(t)= PT/AT = 3/4 = 0.75 SV(t)= PT – AT = 3 – 4 = -1 months Schedule Analysis & Forecasting 1525 Oct.2015
  • 16. Time Based Method • The SV(t) means that the work has a delayed time of one month and the SPI(t) means that 25% of work time is wasted. SPI(t)= 0.75SV(t)= -1 months Schedule Analysis & Forecasting 1625 Oct.2015
  • 17. Time Based Method • Let’s consider an example for a project which was supposed to be finished within 12 months, it actually took 18 months to finish work. • We are calculating the SV(t) & the SPI(t) at the end of the project. It will be as follows: SPI(t)= PT/AT = 12/18 = 0.67 SV(t)= PT – AT = 12 – 18 = -6 months Schedule Analysis & Forecasting 1725 Oct.2015
  • 18. Time Based Method • The above information means that the project had a 6 months delay & 33% of it’s planned time was wasted. SPI(t)= 0.67SV(t)= -6 months Schedule Analysis & Forecasting 1825 Oct.2015
  • 19. Cost Based vs. Time Based Cost Based Time Based Assumptions Compares Cost of planned work at certain date to the Cost of actual work done till the same Date. Compares the Actual time elapsed to do a certain amount of work to the planned time supposed to be elapsed for the same amount of work. Schedule variance (output) The SV output indicates the cost of delayed work till a certain date The SV output indicates the amount of wasted time (Delay) till date Schedule performance Index (output) The SPI output indicates the efficiency of work based on scope (or Cost) The SPI output indicates the efficiency of work based on time At the End of the Project If time delay occurred SV = 0 days SPI = 1 If time delay occurred SV = - (x) days SPI < 1 Schedule Analysis & Forecasting 1925 Oct.2015
  • 20. Cost Based vs. Time Based At the same Date At the same CostSchedule Analysis & Forecasting 2025 Oct.2015
  • 21. Application to an example Project • At the 13th of Oct. 2015 for the example project • No. of Elapsed days (from project start) (AT) = 338 days • Cost of Actual Work done (EV) = 30,045,060 $ • Cost of planned work at the same date (PV) = 69,915,599.05 $ • This amount of work done till that date was supposed to be done by 9th of July 2015, • So the planned time (PT) = 242 days Schedule Analysis & Forecasting 2125 Oct.2015
  • 22. Application to an example Project • Based on Cost: • Based on Time: EV= 30,045,060 $ PV= 69,915,599.05 $ AT= 338 days PT= 242 dayes SV= EV- PV= 30,045,060 - 69,915,599 So, SV = -39,870,539 $ SPI = EV/PV = 30,045,060 / 69,915,599 = 0.4297 SV(t)= PT – AT = 242 – 338 = 96 days SPI(t)= PT / AT = 242 / 338 = 0.716 Schedule Analysis & Forecasting 2225 Oct.2015
  • 23. Application to an example Project • For the equation = • We actually don’t know a formal reference to this equation. However we can deduce it’s logic to a certain extent. Delay= (1-SPI)*Elapsed days Schedule Analysis & Forecasting 2325 Oct.2015
  • 24. How to use this equation ?? Delay= (1-SPI)*Elapsed days Schedule Analysis & Forecasting 2425 Oct.2015
  • 25. Application to an example Project • Based on the last calculations for SV(t) & SPI (t) • Let’s apply the equation for the SPI: We used the SPI calculated on time basis to recalculate the delay time (which is the same as the SV) SV(t)= PT – AT = 242 – 338 = -96 days SPI(t)= PT / AT = 242 / 338 = 0.716 Delay= (1-SPI)*Elapsed days = (1- 0.716)*338= 96 days which is exactly equal to the value of SV(t) Schedule Analysis & Forecasting 2525 Oct.2015
  • 26. Application to an example Project • For the cost basis method: • Let’s apply the equation for the SPI: • But if applied like this: SV= EV- PV= 30,045,060 - 69,915,599 So, SV = -39,870,539 $ SPI = EV/PV = 30,045,060 / 69,915,599.05 = 0.4297 Delay= (1-SPI)*Elapsed days = (1- 0.4297)*338= 192 days which is not equal to the value of SV Delay= (1-SPI)*PV = (1- 0.4297)*69,915,599.05= 39,870,539 $ which is exactly equal to the value of SV Schedule Analysis & Forecasting 2625 Oct.2015
  • 27. • Where is the Problem ?? Schedule Analysis & Forecasting 2725 Oct.2015
  • 28. The Problem is: • We can use the SPI (based on cost Basis) to calculate the cost of delayed work, but we cannot use it to calculate the amount of delayed time. • To calculate the delayed time we use the SPI(t) (based on time basis). Schedule Analysis & Forecasting 2825 Oct.2015
  • 29. The Problem is: • Based on all mentioned before, The equations Are useless –but not wrong- as they are just another method to calculate the Schedule variance (SV) provided that the proper SPI is used in the proper equation. Delay= (1-SPI(t))*Elapsed days Or Delay= (1-SPI)*Planned Value Schedule Analysis & Forecasting 2925 Oct.2015