The document discusses key project management metrics like CPI, SPI and critical path. It defines CPI as the ratio of earned value to actual cost, which measures cost efficiency. SPI is defined as the ratio of earned value to planned value, which measures schedule efficiency. An example calculates the CPI and SPI for a project that is over budget and behind schedule after 3 months. The document also explains how to identify the critical path in a project network diagram as the longest path of activities requiring the total time to complete the project.