SUPERCRITICAL UNIT STARTUP
AND SHUTDOWN
INTRODUCTION
 INDIA’S FIRST 66O MW SUPER CRITICAL UNIT SYNCHRONISED BY ADANI
POWER LTD, MUNDRA IN OCT 2010 IN RECORD TIME OF 36 MONTHS.
 COMMISSIONED 4Nos. 660MW UNITS IN A YEAR.
 ADANI IS THE FIRST COMPANY IN INDIA TO EARN CARBON CREDIT.
START-UP SEQUENCE
 BOP SYSTEM READYNESS
 BOILER FLUSHING: COLD/HOT
 BOILER LINE UP AND LIGHT UP.
 TURBINE LINE UP.
 TURBINE ROLLING.
 SYNCHRONISATION
 PHASE CHANGE OVER
 FULL LOAD
START UP MODES
 COLD START UP:HP & IP SHAFT METAL
TEMP <204°C
 WARM START UP: HP & IP METAL TEMP
IN BETWEEN 204 TO 400°C
 HOT START UP :HP & IP METAL TEMP
>400°C
HP
T
IPT LPT A LPT B
CPP
GSC
Condensor
(HP) Condensor
(LP)
HPH-1HPH-2HPH-3
EXT From
CRH
LPH -5 LPH -6
LPH -7A
LPH -7B
LPH -8A
LPH -8B
3
Deaerator
Boiler
CEP
3x50%
FCS
5 56 6
Economiser
1482 TPH
1994 TPH
(MD BFBP
1x35%)
7
8
7
8 8
77
8
11+1 8 2x7 2x7
RH
1
TDBFP 2X50%
PRE STARTUP READYNESS
 HT/LT POWER SUPPLY READINESS
 WATER SYSTEM: FIRE WATER,SERVICE WATER,DMP,CW & ACW.
 CCCW SYSTEM
 COMPRESSOR SYSTEM
 AUXILIARY STEAM. (S/B UNIT OR AUX BOILER).
 START CEP AND MDBFP.
 CHECK THE BCP SYSTEM IS READY.
WHY BCP ?
 TO ASSIST CIRCULATION IN BOILER WATER WALL
 TO INCREASE THE CIRCULATION VELOCITY
 TO AVOID DNB (Departure from Nucleate Boiling) IN LOW LOAD.
 TO REDUCE THE OVER HEATING AND UNDUE STRESSES ON WATER
WALL TUBES.
 TO AVOID DRY OUT OF WATER WALL TUBES WHEN LOAD IS REDUCED.
BCP FILLING ,PURGING & FLUSHING
 PURPOSE-
- TO FILL THE MOTOR CAVITY.
 RECOMMENDED MOTOR FILLING WATER QUALITY
- CONDUCTIVITY <1 µs/cm
- BOILER FEED WATER
- TEMP.<= 45 O
C
- CL-
<= 50 PPM
- pH >= 6.5
- SUSPENDED SOLIDS <= 5 PPM
 FILLING,PURGING & FLUSHING WATER REQUIREMENT
- MOTOR INITIAL FILLING FLOW RATE : MAX. 5 L/MIN
PRE BOILER FLUSHING
 START CEP.
 FILL & DRAIN FROM DEAERATOR UNTIL
REQUIRED WATER QUALITY IS ACHIEVED.
( Fe<500 Ppb.)
 START MDBFP.
 START THE BOILER COLD/HOT FLUSHING TO
REDUCE THE Fe & SiO2 CONTENT IN FEED
WATER.
Sampling Fe+
Above
500ppb
Below
500ppbMIXER
Boiler flushing
HOTWELL
CW
LINE
BCP
START-UP
LINE
ECO
WW
SP SP
BOILER COLD FLUSHING
COLD FLUSHING
 WATER WALL TEMP REQUIRED 105-120 DEG.C (TEMP
MAINTAINED BY DEAERATOR PEGGING STEAM)
 COLD OPEN FLUSHING QUALIFIES Fe < 500PPB
SiO2 < 100PPB
 THEN CPU WILL BE TAKEN IN SERVICE TO REDUCE WATER LOSS AND
IMPROVE QUALITY.
 COLD CYCLIC FLUSHING QUALIFIES Fe < 100PPB
SIO2 < 50PPB
(ALL ANALYSIS FROM SEPARATOR DRAIN)
BOILER HOT FLUSHING
HOT FLUSHING
 WATER WALL TEMP REQUIRED 150-190 DEG.C (TAKE OIL GUNS
OF BC ELEVATION)
 HOT OPEN FLUSHING START UP CRITERIA FE > 100PPB
SIO2 > 50PPB
 IF HOT CYCLIC FLUSHING CRITERIA IF FE < 100PPB
SIO2 < 50PPB
 HOT CYCLIC FLUSHING QUALIFIES IF FE < 50PPB
SIO2 < 30PPB
 AFTER COLD FLUSHING START BCP WITH MINIMUM 30% FEED FLOW &
THROTTLE FRS VALVE.
BOILER LINE UP AND LIGHT UP
 FUEL OIL SYSTEM: LDO/HFO PUMPS
 ESP HEATERS & RAPPERS
 AIR FLUE GAS SYSTEM: APH,IDF, FDF & SCANNER FAN.
 MAINTAIN AIR FLOW : 30% - 40%.
 FURNACE PURGE: 300 Sec.
 LIGHT UP BOILER WITH OIL GUNS AT BC (LDO)
ELEVETION.
 CONTINUE HOT FLUSHING UNTIL REQD.WATER QUALITY
IS ACHIEVED
 THEN TAKE CD ELEVETION GUNS. IF REQUIRED TAKE 2
NO. GUNS IN AB ELEVETION.
BOILER LINE UP AND LIGHT UP
 CONTINUOUS APH SOOT BLOWING TO BE DONE AT THE TIME OF
OIL FIRING.
 PR RISING RATE- 0.05 MPA/MIN. BETWEEN 0-1 MPA
 PR RISING RATE 0.1 MPA/MIN. BETWEEN 1 – 2 MPA
 PR RISING RATE 0.2 MPA/MIN. ABOVE 2 MPA
 FURNACE EXIT GAS TEMP MUST BE BELOW 538°C FOR REHEATER
PROTECTION (UNTIL HP-LPBP IS CHARGED).
 CLOSE SH DRAINS AND VENTS AFTER ACHIEVING DEGREE OF SH 50
°C ( CLOSE IT AFTER CHARGING HP-LP BYPASS).
LDO/HFO GUN
Fuel Light Oil
Fuel Pressure 0.8MPa-2.0MPa
Fuel Flow 500kg/h -3000kg/h
Atomizing Air Pressure 0.6MPa-1.2MPa
Atomizing Air Flow 100-600kg/h
Ignition Method HESI (20 joules/spark)
Fuel Heavy Oil
Fuel Pressure 0.8MPa- 2.0MPa
Fuel Flow 1000-4000 kg/h
Atomizing Steam Pressure 0.8MPa-1.2MPa
Atomizing Steam Flow 100-400kg/h
Ignition Method HESI (20 joules/spark)
TURBINE LINE UP
 ENSURE:
 LUBE OIL SYSTEM: IN SERVICE (0.8 MPA)
 JACKING OIL SYSTEM:IN SERVICE ( 14 MPA)
 TURBINE BARRING GEAR: 3-4 RPM
 SEAL OIL SYSTEM: AIR & H2 SIDE. CHARGED
 STATOR AND H2 COOLING WATER SYSTEM:CHARGED TEMP CONTROL IN AUTO)
 H2 FILLED IN GENERATOR AND MAINTAIN PR 0.35 MPA.
 EH OIL SYSTEM: IN SERVICE (14 MPA)
TURBINE LINE UP
 ENSURE TDBFP IN BARRING.
 GLAND STEAM CHARGING: ENSURE STEAM TEMP. IS 56°C - 111
°C MORE THAN ROTOR TEMP & DEGREE OF SH > 50°C.
 CHARGE THE GLAND SEAL SYSTEM OF TDBFP.
 START THE VACUUM PULLING WITH VACUUM PUMP.
MAINTAIN VACUUM -0.9 KG/CM2.
 CHARGE THE HP-LP BYPASS SYSTEM .MAINTAIN THE MS STEAM
PRESSURE AND FIRING RATE FOR ACHIEVING TURBINE ROLLING
PARAMETERS.
COLD START UP CURVE
HOT ROLLING
MS TEMP
RH TEMP
SPEED
MS FLOW
LOAD
MS PRESS
PRE HEATING OF HP CASING.
 PREHEATING OF HPT REQUIRED WHEN INNER METAL TEMP <150°C.
 CRH PR 0.5-0.7 MPA/220-380°C.
 OPEN PRE HEATING VALVE (REVERSE FLOW VALVE) GRADUALLY.
 OPEN BDV VALVE FULLY.
 OPEN CRH DRAIN BEFORE NRV AND HPT-IPT CASING DRAINS.
 HEATING RATE SHOULD NOT BE MORE THAN 50°C PER HR.
 HP CASING TOP-BOTTOM & INNER-OUTER WALL METAL TEMP DIFFRENCE
SHOULD BE WITHIN 50°C.
 AFTER ATTAINING THE CASING TEMP > 150°C CLOSE THE RFV VALVE AND
OPEN HP CYLINDER VENTILATION VALVE TO CONDENSOR.
TURBINE WARM UP OPERATION
TURBINE STARUP PROCEDURE
RFV
CRH NRV
HPT
HPBP
CRH LINE
Ventilator valve
TO CONDENSER
IPT
BDV
TO CONDENSER
MS
TURBINE ROLLING
 AS PER REQUIREMENT OF START UP CURVE, FIRING TO BE INCREASED.
 REQUIRED STEAM PARAMETERS BEFORE ROLLING
 MS PR: 8.73 MPA, TEMP: 330-380 °C
 RH PR: 1.1 MPA , TEMP: 330°C
- THE DEGREE OF SUPER HEAT > 56°C.
 AFTER LATCHING THE TURBINE, START IP ROLLING WITH HP VENT TO
CONDENSER IN OPEN CONDITION TO KEEP THE HPT IN VACUUM.
 MSV 1&2 AND RSV 1&2 ARE IN OPEN CONDITION.
 GIVE THE SPEED SET POINT TO 600 RPM
 CHECK THE TURBINE SUPERVISORY INSTRUMENT PARAMETER.
 THE ECCENTRICITY SHOULD BE LESS THAN 0.076 MM.
TURBINE ROLLING
 SELECT TARGET SPEED 1500 RPM WITH RAMP RATE OF 100 RPM/MIN.
 ENSURE ALL HP CV’S OPENS TO 12% TO WARM UP THE HP CASING.
 WHEN HP CASING TEMP >320°C.CLOSE THE HP CV’S.
 SOAK THE TURBINE FOR 4 HRS ACCORDING TO THE START UP CURVE.
 CHARGE THE LP HEATER 5 & 6 BEFORE 3000 RPM
 SELECT TARGET SPEED TO 3000 RPM WITH RAMP RATE OF 100
RPM/MIN.SOAK IT FOR 30 MIN AS PER S/U CURVE.
 AS PER PROCEDURE SYNCHRONISE THE UNIT.
LOADING
 AFTER SYNCHRONISATION INITIAL LOAD WILL BE 30 MW.HOLD IT FOR 30 MIN AND
CHEK THE VIBRATION, BEARING TEMP, DIFF EXPANSION, CASING EXPANSION.
 CHARGE EXTRACTION STEAM TO DEAERATOR.
 TAKE MORE OIL GUNS IN EF/AB ELEVETION.
 TAKE PA FANS & SEAL AIR FAN.
 AFTER ACHIEVING FURNACE TEMP. MORE THEN 450°C. TAKE COAL MILL-B AT.
STEAM T/PR 380°C/8.7 MPA.
 INCREASE FUEL FLOW MAINTAINING STEAM TEMP.& RAISE LOAD
 AT 70 MW IP TO HP CHANGE OVER. CV’S WILL START OPENING, CLOSE THE BDV
AND VENTILATING VALVE.
 INCREASE THE LOAD AT 3MW/MIN
 CLOSE THE HP-LP BYPASS GRADULLY.
350 400 450 500 550 600 650
MINUTES
LOAD
(MW)
165
330
495
660
33MW
60MW
198MW
330MW
SYNCHRONISE
&CHARGED/A
MILL-BCUTIN
IPTOHPCHANGEOVER(70MW
MILL-CCUTINAT100MW
HPHCHARGED(150MW)
2ND
TDBFPCUTIN(180MW)
WETTODRYCHANGEOVER
MILL-ACUTIN(210MW)
OILGUNCUTOUT(260MW)
MILL-DCITIN(300MW)
MILL-ECUTIN(430MW)
MILL-FCUTIN(540MW)
660 MW
CONDENSER
LP HEATER 7A
LP HEATER 8A
CONDENSER
LP HEATER 7B
LP HEATER 8B
LPT A LPT B
HP HEATER 5
HP HEATER 6
LP HEATER 5
LP HEATER 6
2nd 2nd
4th 4th
5th
5th
5th
5th
6th
6th
6th
6th
FROM IPT EXHAUST
TDBFP START UP
 TAKE ONE TDBFP IN SERVICE( CHANGE OVER WITH MD BFP) WHILE DRIVING
STEAM IS AVAILABLE. SECOND TD BFP WILL BE TAKEN AT 180 MW.
 WARM UP THE TURBINE.
 SLOWLY OPEN THE AUX STEAM MOV TO TURBINE.
 PARAMETERS FOR ROLLING TDBFP.
STEAM PRESSURE: 0.6 ~ 1.3MPA, STEAM TEMP: 50 DEG C MORE THAN CASING
TEMP.
 ROLL THE TDBFP AS PER PROCEDURE.
 GIVE THE TARGET SPEED 500 RPM AND THAN TO 1000 HOLD FOR 40 MIN.CHECK
THE TSI PARAMETER
 WHEN SPEED REACHES 2840 RPM, GIVE REQUEST COMMAND FROM FW MENU.
THEN SELECT CCS CONTROL IN FROM MEH MENU.
IP
TDBFP-A
TDBFP-B
Aux. Steam
Header
To
CRH
HP
From
CRH
M
M M M
Deaerator
Booster
pumps
M M
M
E
E
To
Condenser
Aux. Steam
Header
M
M
M
M M
M M
E
E
Deaerator
1.3 MPa
350 ºC
1.12 Mpa
378 ºC
4 MPa
315.3 ºC
Changeover Valve
TDBFP STEAM SOURCES
LOADING
 TAKE THE MILL-C IN SERVICE AT 100 MW. STEAM T/PR:400°C/8.7 MPA.
 GRADUALLY WITH DRAW THE OIL SUPPORT AS PER THE FLAME
CONDITION.
 INCREASE THE LOAD TO 150 MW AND TAKE THE HPH-3, HPH-2 &
HPH-1 IN SERVICE. MS T/PR 410°C/8.7 MPA.
 AT 180 MW TAKE SECOND TDBFP IN SERVICE.
HP HEATER 3
DEAERATOR
HP HEATER 2
HP HEATER 1
CRH LINE
TDBFP A TDBFP B
MS LINE
9th
stage
5th stage
HP HEATER 1
HP HEATER 2
HP HEATER 3
HRH LINE
DEAERATOR
IP EXHAUST
PHASE CHANGE FROM WET TO DRY MODE
 DURING LOAD RAISING >25% BMCR, THE BCP FLOW AND FEED WATER
FLOW TO BE MONITORED CLOSELY.
 THE BCP FLOW NEED TO BE ADJUSTED W.R.T SEPERATOR TANK LEVEL AND
THE SAME FLOW TO BE ADJUSTED IN FEED WATER FLOW TO MAINTAIN
TOTAL FEED WATER FLOW TO ECONOMISER CONSTANT.
 WHEN BOILER STEAMING RATE RISES TO >30% BMCR, W.R.T FUEL FIRING, THE
SEPERATOR LEVEL REDUCES .
 ONCE THE CONDITION FULFILLS THE BCP STOPS AND FEED FLOW CONTROL
CHANGES OVER FRS.
 AFTER STOPPING BCP IT ACTS AS SUB-CRITICAL ONCE THROUGH“.
 WHEN THE STEAM PR REACHES 22.1 MPA IT IS IN “SUPERCRITICAL ZONE”
LOADING
 TAKE MILL-A AT 210 MW.
 CUT THE OIL SUPPORT AT 260 MW AS PER THE FLAME CONDITION.
 TAKE MILL-D AT 300 MW. MS T/PR 475°C/10 MPA.
 TAKE MILL-E AT 430 MW. MS T/PR 566°C/17 MPA.
 TAKE MILL-F AT 540 MW. MS T/PR 566°C/24.1 MPA.
 INCREASE THE LOAD TO “FULL LOAD 660 MW” GRADUALLY.
Boiler Design Parameters
NO.NO. ParametersParameters UnitUnit
11
100% BMCR Coal consumption (Design)100% BMCR Coal consumption (Design) 390.37390.37
t/ht/h
22 Design fuelDesign fuel Indian coalIndian coal
33 Superheated steam flowSuperheated steam flow 21112111 t/ht/h
44 Superheater outlet pressureSuperheater outlet pressure 25.425.4 MPaMPa
55 Superheater outlet temperatureSuperheater outlet temperature 569569 ℃℃
66 Reheated steam flowReheated steam flow 1749.11749.1 t/ht/h
77 Reheater inlet pressureReheater inlet pressure 4.734.73 MPaMPa
88 Reheater outlet pressureReheater outlet pressure 4.494.49 MPaMPa
99 Reheater inlet temperatureReheater inlet temperature 324324 ℃℃
1010 Reheater outlet temperatureReheater outlet temperature 569569 ℃℃
Feedwater pressureFeedwater pressure 28.828.8 MPa.gMPa.g
1111 Feedwater temperatureFeedwater temperature 280280 ℃℃
1212 Separator’s steam temperatureSeparator’s steam temperature 421421 ℃℃
1313
Air preheater’s outlet air temperature, uncorrectedAir preheater’s outlet air temperature, uncorrected
After correctingAfter correcting
153.3153.3 ℃℃
147.2147.2 ℃℃
1414 Calculating thermal efficiency of boilerCalculating thermal efficiency of boiler 87.19%87.19% (( BMCRBMCR ))
TURBINE PARAMETERS
HPT IPT LPT
Pressure (MPa) 24.2 3.961 1.12
I/L Temp (Deg C) 566 566 378
O/L Temp(deg C) 315.3 378
Steam Flow (tph) 1959.25 1649
TURBINE HEAT RATE( KCL/KWH) 1885
No of Stop valves 2 2
No of Control valves 4 4
Steam Admission Parameters at Turbine Inlet
TURBINEAT FULL LOAD
HPT IPT
RSV
LPT LPT #2 GEN
CRH
CRH
HRH
MS LINE
HRH
MS LINE
3.96MPa / 566°c
24.2MPa/566ºC
TO BLR RH
RCV
MSV
RCVRCV RCVCV CVCV
RSV
CVCV
CVCV
RSV
CVCVMSV
CV CV
LPT LPT #2LPT GEN#2LPTLPT #1
MSV CV CVMSV CVMSV CVMSV CVCVMSV CVMSV CVMSV CV CVMSV
MSV CVMSV CVCVMSV
RSV
CV CV
RSV
CV
RSV
CV
RSV
CVCV
RSV
1.12MPa / 378°c
CONDENSOR A CONDENSOR B
SHUT DOWN
 EXCEPT IN AN EMERGENCY, LOAD SHOULD BE REDUCED GRADUALLY.
 CUT THE MILL-F AT 540 MW.
 CUT THE MILL-E AT 470MW.
 CUT THE MILL-D AT 300 MW.
 TAKE OIL SUPPORT FOR FURNACE STABILITY ( AT THE TIME OF 3 MILL
OPERATION).
 CUT THE MILL-A AT 210 MW.
 TAKE THE HPH-1,2,3 OUT OF SERVICE.
 WHEN THE LOAD < 30% BOILER COMES IN WET MODE FROM DRY
MODE. START THE BCP AND MAINTAIN THE SEPEARTOR LEVEL.
SHUT DOWN
 WHEN THE LOAD HAS DECREASED TO 20% OF RATED LOAD TRIP THE
TURBINE ON TURBINE PROTECTION. THIS CLOSES THE THROTTLE VALVES,
GOVERNOR VALVES, REHEAT STOP VALVES AND INTERCEPTOR VALVES
 CHECK DRAIN VALVES OPENS IN AUTO.
 HP LP BYPASS VALVE OPENS TO MAINTAIN THE FLOW.
 REDUCE THE BOILER LOAD GRADULLY.
 TRIP THE BOILER.
 THE VACUUM BREAKER VALVES SHOULD NOT BE OPENED UNTIL THE
TURBINE UNIT HAS COASTED DOWN.
 VACUUM SHOULD BE KILLED BEFORE GLAND SEALING STEAM IS SHUT OFF.
 AUX OIL PUMP STARTS IN AUTO AT 2850 RPM.
 JOP START IN AUTO AT 1200 RPM.
SHUT DOWN
 WHEN THE VACUUM REACHES ZERO, SHUT OFF THE SEALING STEAM TO THE
GLAND STEAM CONTROL VALVES.
 SHUT DOWN THE GLAND STEAM CONDENSER EXHAUSTER. SHUT DOWN
CONDENSATE PUMP.
 SHUT DOWN THE VACUUM PUMP.
 SHUT OFF THE COOLING WATER SUPPLY TO THE GENERATOR HYDROGEN
COOLERS.
 ENSURE THAT BARRING GEAR HAS CUT IN.
SHUT DOWN CURVE
COOL DOWN CURVE
THANK YOU

More Related Content

What's hot

210 mw LMZ Turbine rolling and its GOVERNING
210 mw LMZ Turbine rolling and its GOVERNING 210 mw LMZ Turbine rolling and its GOVERNING
210 mw LMZ Turbine rolling and its GOVERNING Nitin Patel
 
Handling of turbine during emergencies
Handling of turbine during emergenciesHandling of turbine during emergencies
Handling of turbine during emergenciesManohar Tatwawadi
 
HP LP Bypass system of 110 MW Steam Turbine
HP LP Bypass system of 110 MW Steam TurbineHP LP Bypass system of 110 MW Steam Turbine
HP LP Bypass system of 110 MW Steam TurbineRAVI PAL SINGH
 
210 mw turbine cycle heat rate
210 mw turbine cycle heat rate210 mw turbine cycle heat rate
210 mw turbine cycle heat rateManohar Tatwawadi
 
Turbine cycle heat rate calculation
Turbine  cycle heat rate calculationTurbine  cycle heat rate calculation
Turbine cycle heat rate calculationSHIVAJI CHOUDHURY
 
Boiler Reheater protection
Boiler Reheater  protectionBoiler Reheater  protection
Boiler Reheater protectionanujkumarsingh79
 
Furnace Guard Supervisory System (FSSS)
Furnace Guard Supervisory System (FSSS)Furnace Guard Supervisory System (FSSS)
Furnace Guard Supervisory System (FSSS)Jigyasa Singh
 
Electrohydraulic governing system
Electrohydraulic governing systemElectrohydraulic governing system
Electrohydraulic governing systemAshvani Shukla
 
Power Plant Simulator Day 3 Part 5
Power Plant Simulator Day 3 Part 5Power Plant Simulator Day 3 Part 5
Power Plant Simulator Day 3 Part 5Manohar Tatwawadi
 
Starting & Recommended Interlocks for AH,ID,FD,PA Fans & BD Valves for 270 MW...
Starting & Recommended Interlocks for AH,ID,FD,PA Fans & BD Valves for 270 MW...Starting & Recommended Interlocks for AH,ID,FD,PA Fans & BD Valves for 270 MW...
Starting & Recommended Interlocks for AH,ID,FD,PA Fans & BD Valves for 270 MW...Manohar Tatwawadi
 
660 mw supercritical boiler
660 mw supercritical boiler660 mw supercritical boiler
660 mw supercritical boilerAshvani Shukla
 
Boiler feed pump recirculation valve problem
Boiler feed pump recirculation valve problemBoiler feed pump recirculation valve problem
Boiler feed pump recirculation valve problemVudugundla Kodandapani
 
Air Heater and PF Boiler Performance Indices
Air Heater and PF Boiler Performance IndicesAir Heater and PF Boiler Performance Indices
Air Heater and PF Boiler Performance IndicesManohar Tatwawadi
 
210 mw turbine cycle heat rate
210 mw turbine cycle heat rate210 mw turbine cycle heat rate
210 mw turbine cycle heat rateManohar Tatwawadi
 

What's hot (20)

210 mw LMZ Turbine rolling and its GOVERNING
210 mw LMZ Turbine rolling and its GOVERNING 210 mw LMZ Turbine rolling and its GOVERNING
210 mw LMZ Turbine rolling and its GOVERNING
 
FURNACE SAFEGUARD SUPERVISORY SYSTEM (FSSS)
FURNACE SAFEGUARD SUPERVISORY SYSTEM (FSSS)FURNACE SAFEGUARD SUPERVISORY SYSTEM (FSSS)
FURNACE SAFEGUARD SUPERVISORY SYSTEM (FSSS)
 
Handling of turbine during emergencies
Handling of turbine during emergenciesHandling of turbine during emergencies
Handling of turbine during emergencies
 
HP LP Bypass system of 110 MW Steam Turbine
HP LP Bypass system of 110 MW Steam TurbineHP LP Bypass system of 110 MW Steam Turbine
HP LP Bypass system of 110 MW Steam Turbine
 
210 mw turbine cycle heat rate
210 mw turbine cycle heat rate210 mw turbine cycle heat rate
210 mw turbine cycle heat rate
 
Turbine cycle heat rate calculation
Turbine  cycle heat rate calculationTurbine  cycle heat rate calculation
Turbine cycle heat rate calculation
 
Unit protection scheme
Unit protection schemeUnit protection scheme
Unit protection scheme
 
Boiler Reheater protection
Boiler Reheater  protectionBoiler Reheater  protection
Boiler Reheater protection
 
boiler turbine emergency
boiler turbine emergencyboiler turbine emergency
boiler turbine emergency
 
Hplpbp
HplpbpHplpbp
Hplpbp
 
Furnace Guard Supervisory System (FSSS)
Furnace Guard Supervisory System (FSSS)Furnace Guard Supervisory System (FSSS)
Furnace Guard Supervisory System (FSSS)
 
Cmc philosophy
Cmc philosophyCmc philosophy
Cmc philosophy
 
Electrohydraulic governing system
Electrohydraulic governing systemElectrohydraulic governing system
Electrohydraulic governing system
 
Power Plant Simulator Day 3 Part 5
Power Plant Simulator Day 3 Part 5Power Plant Simulator Day 3 Part 5
Power Plant Simulator Day 3 Part 5
 
Starting & Recommended Interlocks for AH,ID,FD,PA Fans & BD Valves for 270 MW...
Starting & Recommended Interlocks for AH,ID,FD,PA Fans & BD Valves for 270 MW...Starting & Recommended Interlocks for AH,ID,FD,PA Fans & BD Valves for 270 MW...
Starting & Recommended Interlocks for AH,ID,FD,PA Fans & BD Valves for 270 MW...
 
660 mw supercritical boiler
660 mw supercritical boiler660 mw supercritical boiler
660 mw supercritical boiler
 
Boiler feed pump recirculation valve problem
Boiler feed pump recirculation valve problemBoiler feed pump recirculation valve problem
Boiler feed pump recirculation valve problem
 
Air Heater and PF Boiler Performance Indices
Air Heater and PF Boiler Performance IndicesAir Heater and PF Boiler Performance Indices
Air Heater and PF Boiler Performance Indices
 
Turbine safety protection
Turbine safety protectionTurbine safety protection
Turbine safety protection
 
210 mw turbine cycle heat rate
210 mw turbine cycle heat rate210 mw turbine cycle heat rate
210 mw turbine cycle heat rate
 

Similar to Unit lightup synchronisation &amp; shutdown

660 mw turbo generator &amp; its auxiliaries
660 mw turbo generator &amp; its auxiliaries660 mw turbo generator &amp; its auxiliaries
660 mw turbo generator &amp; its auxiliariesAshvani Shukla
 
Thermal Power plant familarisation & its Auxillaries
Thermal Power plant familarisation & its AuxillariesThermal Power plant familarisation & its Auxillaries
Thermal Power plant familarisation & its AuxillariesVaibhav Paydelwar
 
Turbo Generator & Its auxiliaries.ppt
Turbo Generator & Its auxiliaries.pptTurbo Generator & Its auxiliaries.ppt
Turbo Generator & Its auxiliaries.pptNarhari1
 
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...haxxo24
 
Ntpc (national thermal power corporation) sipat boiler haxxo24 i~i
Ntpc (national thermal power corporation) sipat boiler haxxo24 i~iNtpc (national thermal power corporation) sipat boiler haxxo24 i~i
Ntpc (national thermal power corporation) sipat boiler haxxo24 i~ihaxxo24
 
Cfbc boiler startup and shutdown
Cfbc boiler startup and shutdownCfbc boiler startup and shutdown
Cfbc boiler startup and shutdownAshvani Shukla
 
Vapour power 4 by RANA SAIFULLAH KHAN
Vapour power 4 by RANA SAIFULLAH KHANVapour power 4 by RANA SAIFULLAH KHAN
Vapour power 4 by RANA SAIFULLAH KHANRana Saif Khan
 
Energy adudit methodology for boiler
Energy adudit methodology for boilerEnergy adudit methodology for boiler
Energy adudit methodology for boilerKongkiert Tankayura
 
Amardeep jadeja copy.ppt [autosaved]
Amardeep jadeja   copy.ppt [autosaved]Amardeep jadeja   copy.ppt [autosaved]
Amardeep jadeja copy.ppt [autosaved]Amardeep Jadeja
 
SIP Presentation
SIP PresentationSIP Presentation
SIP PresentationAmay Jain
 
Design Project Presentation
Design Project PresentationDesign Project Presentation
Design Project PresentationRobert Cote
 
Bhushan powers and steels thalkuli,regali
Bhushan powers and steels thalkuli,regaliBhushan powers and steels thalkuli,regali
Bhushan powers and steels thalkuli,regaliBaroda
 
EMERSON Power plant applications
EMERSON Power plant applicationsEMERSON Power plant applications
EMERSON Power plant applicationsmirfanm
 
Emerson Power plant applications
Emerson Power plant applicationsEmerson Power plant applications
Emerson Power plant applicationsmirfanm
 
AIChE 2018 improving catalytic reformer heaters using split flow technology rev2
AIChE 2018 improving catalytic reformer heaters using split flow technology rev2AIChE 2018 improving catalytic reformer heaters using split flow technology rev2
AIChE 2018 improving catalytic reformer heaters using split flow technology rev2Ashutosh Garg
 

Similar to Unit lightup synchronisation &amp; shutdown (20)

660 mw turbo generator &amp; its auxiliaries
660 mw turbo generator &amp; its auxiliaries660 mw turbo generator &amp; its auxiliaries
660 mw turbo generator &amp; its auxiliaries
 
Turbo generator & its auxiliaries
Turbo generator & its auxiliariesTurbo generator & its auxiliaries
Turbo generator & its auxiliaries
 
Thermal Power plant familarisation & its Auxillaries
Thermal Power plant familarisation & its AuxillariesThermal Power plant familarisation & its Auxillaries
Thermal Power plant familarisation & its Auxillaries
 
Turbo Generator & Its auxiliaries.ppt
Turbo Generator & Its auxiliaries.pptTurbo Generator & Its auxiliaries.ppt
Turbo Generator & Its auxiliaries.ppt
 
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
 
Ntpc (national thermal power corporation) sipat boiler haxxo24 i~i
Ntpc (national thermal power corporation) sipat boiler haxxo24 i~iNtpc (national thermal power corporation) sipat boiler haxxo24 i~i
Ntpc (national thermal power corporation) sipat boiler haxxo24 i~i
 
Cfbc boiler startup and shutdown
Cfbc boiler startup and shutdownCfbc boiler startup and shutdown
Cfbc boiler startup and shutdown
 
ammoniautility operator
ammoniautility operatorammoniautility operator
ammoniautility operator
 
ammonia&utility operator
ammonia&utility operatorammonia&utility operator
ammonia&utility operator
 
Vapour power 4 by RANA SAIFULLAH KHAN
Vapour power 4 by RANA SAIFULLAH KHANVapour power 4 by RANA SAIFULLAH KHAN
Vapour power 4 by RANA SAIFULLAH KHAN
 
Energy adudit methodology for boiler
Energy adudit methodology for boilerEnergy adudit methodology for boiler
Energy adudit methodology for boiler
 
ntpc unchahar
ntpc unchaharntpc unchahar
ntpc unchahar
 
Pintu raj
Pintu rajPintu raj
Pintu raj
 
Amardeep jadeja copy.ppt [autosaved]
Amardeep jadeja   copy.ppt [autosaved]Amardeep jadeja   copy.ppt [autosaved]
Amardeep jadeja copy.ppt [autosaved]
 
SIP Presentation
SIP PresentationSIP Presentation
SIP Presentation
 
Design Project Presentation
Design Project PresentationDesign Project Presentation
Design Project Presentation
 
Bhushan powers and steels thalkuli,regali
Bhushan powers and steels thalkuli,regaliBhushan powers and steels thalkuli,regali
Bhushan powers and steels thalkuli,regali
 
EMERSON Power plant applications
EMERSON Power plant applicationsEMERSON Power plant applications
EMERSON Power plant applications
 
Emerson Power plant applications
Emerson Power plant applicationsEmerson Power plant applications
Emerson Power plant applications
 
AIChE 2018 improving catalytic reformer heaters using split flow technology rev2
AIChE 2018 improving catalytic reformer heaters using split flow technology rev2AIChE 2018 improving catalytic reformer heaters using split flow technology rev2
AIChE 2018 improving catalytic reformer heaters using split flow technology rev2
 

More from Ashvani Shukla

Adc.pptx ashvani 151503
Adc.pptx ashvani 151503Adc.pptx ashvani 151503
Adc.pptx ashvani 151503Ashvani Shukla
 
Pin photodiode.pptx ashvani
Pin photodiode.pptx ashvaniPin photodiode.pptx ashvani
Pin photodiode.pptx ashvaniAshvani Shukla
 
Furnace safegaurd supervisory system logic-1
Furnace safegaurd supervisory system logic-1Furnace safegaurd supervisory system logic-1
Furnace safegaurd supervisory system logic-1Ashvani Shukla
 
Temperature measurement
Temperature measurementTemperature measurement
Temperature measurementAshvani Shukla
 
Pressure measuring devices
Pressure measuring devicesPressure measuring devices
Pressure measuring devicesAshvani Shukla
 
Urea manufacturing process
Urea manufacturing processUrea manufacturing process
Urea manufacturing processAshvani Shukla
 
Amonia manufacturing process
Amonia manufacturing process Amonia manufacturing process
Amonia manufacturing process Ashvani Shukla
 
Paper production process
Paper production processPaper production process
Paper production processAshvani Shukla
 
Steel manufacturing process
Steel manufacturing processSteel manufacturing process
Steel manufacturing processAshvani Shukla
 
Cement manufacturing process new
Cement manufacturing process newCement manufacturing process new
Cement manufacturing process newAshvani Shukla
 
Pulverized coal fired boiler startup procedure
Pulverized coal fired boiler startup procedurePulverized coal fired boiler startup procedure
Pulverized coal fired boiler startup procedureAshvani Shukla
 
Combined ff and iec applications
Combined ff and iec applications  Combined ff and iec applications
Combined ff and iec applications Ashvani Shukla
 
Device exchange and calibration
Device exchange and calibration Device exchange and calibration
Device exchange and calibration Ashvani Shukla
 

More from Ashvani Shukla (20)

Adc.pptx ashvani 151503
Adc.pptx ashvani 151503Adc.pptx ashvani 151503
Adc.pptx ashvani 151503
 
Pin photodiode.pptx ashvani
Pin photodiode.pptx ashvaniPin photodiode.pptx ashvani
Pin photodiode.pptx ashvani
 
Furnace safegaurd supervisory system logic-1
Furnace safegaurd supervisory system logic-1Furnace safegaurd supervisory system logic-1
Furnace safegaurd supervisory system logic-1
 
Temperature measurement
Temperature measurementTemperature measurement
Temperature measurement
 
Modern coupling
Modern couplingModern coupling
Modern coupling
 
Mechanical coupling
Mechanical couplingMechanical coupling
Mechanical coupling
 
Pressure measuring devices
Pressure measuring devicesPressure measuring devices
Pressure measuring devices
 
Urea manufacturing process
Urea manufacturing processUrea manufacturing process
Urea manufacturing process
 
Amonia manufacturing process
Amonia manufacturing process Amonia manufacturing process
Amonia manufacturing process
 
Control valve
Control valveControl valve
Control valve
 
Paper production process
Paper production processPaper production process
Paper production process
 
Steel manufacturing process
Steel manufacturing processSteel manufacturing process
Steel manufacturing process
 
Cement manufacturing process new
Cement manufacturing process newCement manufacturing process new
Cement manufacturing process new
 
Pulverized coal fired boiler startup procedure
Pulverized coal fired boiler startup procedurePulverized coal fired boiler startup procedure
Pulverized coal fired boiler startup procedure
 
Nuclear reactor
Nuclear reactorNuclear reactor
Nuclear reactor
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
Flow measurement
Flow measurementFlow measurement
Flow measurement
 
Orifice plate
Orifice plateOrifice plate
Orifice plate
 
Combined ff and iec applications
Combined ff and iec applications  Combined ff and iec applications
Combined ff and iec applications
 
Device exchange and calibration
Device exchange and calibration Device exchange and calibration
Device exchange and calibration
 

Recently uploaded

College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAbhinavSharma374939
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 

Recently uploaded (20)

College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog Converter
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 

Unit lightup synchronisation &amp; shutdown

  • 2. INTRODUCTION  INDIA’S FIRST 66O MW SUPER CRITICAL UNIT SYNCHRONISED BY ADANI POWER LTD, MUNDRA IN OCT 2010 IN RECORD TIME OF 36 MONTHS.  COMMISSIONED 4Nos. 660MW UNITS IN A YEAR.  ADANI IS THE FIRST COMPANY IN INDIA TO EARN CARBON CREDIT.
  • 3.
  • 4. START-UP SEQUENCE  BOP SYSTEM READYNESS  BOILER FLUSHING: COLD/HOT  BOILER LINE UP AND LIGHT UP.  TURBINE LINE UP.  TURBINE ROLLING.  SYNCHRONISATION  PHASE CHANGE OVER  FULL LOAD
  • 5. START UP MODES  COLD START UP:HP & IP SHAFT METAL TEMP <204°C  WARM START UP: HP & IP METAL TEMP IN BETWEEN 204 TO 400°C  HOT START UP :HP & IP METAL TEMP >400°C
  • 6. HP T IPT LPT A LPT B CPP GSC Condensor (HP) Condensor (LP) HPH-1HPH-2HPH-3 EXT From CRH LPH -5 LPH -6 LPH -7A LPH -7B LPH -8A LPH -8B 3 Deaerator Boiler CEP 3x50% FCS 5 56 6 Economiser 1482 TPH 1994 TPH (MD BFBP 1x35%) 7 8 7 8 8 77 8 11+1 8 2x7 2x7 RH 1 TDBFP 2X50%
  • 7. PRE STARTUP READYNESS  HT/LT POWER SUPPLY READINESS  WATER SYSTEM: FIRE WATER,SERVICE WATER,DMP,CW & ACW.  CCCW SYSTEM  COMPRESSOR SYSTEM  AUXILIARY STEAM. (S/B UNIT OR AUX BOILER).  START CEP AND MDBFP.  CHECK THE BCP SYSTEM IS READY.
  • 8. WHY BCP ?  TO ASSIST CIRCULATION IN BOILER WATER WALL  TO INCREASE THE CIRCULATION VELOCITY  TO AVOID DNB (Departure from Nucleate Boiling) IN LOW LOAD.  TO REDUCE THE OVER HEATING AND UNDUE STRESSES ON WATER WALL TUBES.  TO AVOID DRY OUT OF WATER WALL TUBES WHEN LOAD IS REDUCED.
  • 9. BCP FILLING ,PURGING & FLUSHING  PURPOSE- - TO FILL THE MOTOR CAVITY.  RECOMMENDED MOTOR FILLING WATER QUALITY - CONDUCTIVITY <1 µs/cm - BOILER FEED WATER - TEMP.<= 45 O C - CL- <= 50 PPM - pH >= 6.5 - SUSPENDED SOLIDS <= 5 PPM  FILLING,PURGING & FLUSHING WATER REQUIREMENT - MOTOR INITIAL FILLING FLOW RATE : MAX. 5 L/MIN
  • 10. PRE BOILER FLUSHING  START CEP.  FILL & DRAIN FROM DEAERATOR UNTIL REQUIRED WATER QUALITY IS ACHIEVED. ( Fe<500 Ppb.)  START MDBFP.  START THE BOILER COLD/HOT FLUSHING TO REDUCE THE Fe & SiO2 CONTENT IN FEED WATER.
  • 12. BOILER COLD FLUSHING COLD FLUSHING  WATER WALL TEMP REQUIRED 105-120 DEG.C (TEMP MAINTAINED BY DEAERATOR PEGGING STEAM)  COLD OPEN FLUSHING QUALIFIES Fe < 500PPB SiO2 < 100PPB  THEN CPU WILL BE TAKEN IN SERVICE TO REDUCE WATER LOSS AND IMPROVE QUALITY.  COLD CYCLIC FLUSHING QUALIFIES Fe < 100PPB SIO2 < 50PPB (ALL ANALYSIS FROM SEPARATOR DRAIN)
  • 13. BOILER HOT FLUSHING HOT FLUSHING  WATER WALL TEMP REQUIRED 150-190 DEG.C (TAKE OIL GUNS OF BC ELEVATION)  HOT OPEN FLUSHING START UP CRITERIA FE > 100PPB SIO2 > 50PPB  IF HOT CYCLIC FLUSHING CRITERIA IF FE < 100PPB SIO2 < 50PPB  HOT CYCLIC FLUSHING QUALIFIES IF FE < 50PPB SIO2 < 30PPB  AFTER COLD FLUSHING START BCP WITH MINIMUM 30% FEED FLOW & THROTTLE FRS VALVE.
  • 14. BOILER LINE UP AND LIGHT UP  FUEL OIL SYSTEM: LDO/HFO PUMPS  ESP HEATERS & RAPPERS  AIR FLUE GAS SYSTEM: APH,IDF, FDF & SCANNER FAN.  MAINTAIN AIR FLOW : 30% - 40%.  FURNACE PURGE: 300 Sec.  LIGHT UP BOILER WITH OIL GUNS AT BC (LDO) ELEVETION.  CONTINUE HOT FLUSHING UNTIL REQD.WATER QUALITY IS ACHIEVED  THEN TAKE CD ELEVETION GUNS. IF REQUIRED TAKE 2 NO. GUNS IN AB ELEVETION.
  • 15. BOILER LINE UP AND LIGHT UP  CONTINUOUS APH SOOT BLOWING TO BE DONE AT THE TIME OF OIL FIRING.  PR RISING RATE- 0.05 MPA/MIN. BETWEEN 0-1 MPA  PR RISING RATE 0.1 MPA/MIN. BETWEEN 1 – 2 MPA  PR RISING RATE 0.2 MPA/MIN. ABOVE 2 MPA  FURNACE EXIT GAS TEMP MUST BE BELOW 538°C FOR REHEATER PROTECTION (UNTIL HP-LPBP IS CHARGED).  CLOSE SH DRAINS AND VENTS AFTER ACHIEVING DEGREE OF SH 50 °C ( CLOSE IT AFTER CHARGING HP-LP BYPASS).
  • 16. LDO/HFO GUN Fuel Light Oil Fuel Pressure 0.8MPa-2.0MPa Fuel Flow 500kg/h -3000kg/h Atomizing Air Pressure 0.6MPa-1.2MPa Atomizing Air Flow 100-600kg/h Ignition Method HESI (20 joules/spark) Fuel Heavy Oil Fuel Pressure 0.8MPa- 2.0MPa Fuel Flow 1000-4000 kg/h Atomizing Steam Pressure 0.8MPa-1.2MPa Atomizing Steam Flow 100-400kg/h Ignition Method HESI (20 joules/spark)
  • 17. TURBINE LINE UP  ENSURE:  LUBE OIL SYSTEM: IN SERVICE (0.8 MPA)  JACKING OIL SYSTEM:IN SERVICE ( 14 MPA)  TURBINE BARRING GEAR: 3-4 RPM  SEAL OIL SYSTEM: AIR & H2 SIDE. CHARGED  STATOR AND H2 COOLING WATER SYSTEM:CHARGED TEMP CONTROL IN AUTO)  H2 FILLED IN GENERATOR AND MAINTAIN PR 0.35 MPA.  EH OIL SYSTEM: IN SERVICE (14 MPA)
  • 18. TURBINE LINE UP  ENSURE TDBFP IN BARRING.  GLAND STEAM CHARGING: ENSURE STEAM TEMP. IS 56°C - 111 °C MORE THAN ROTOR TEMP & DEGREE OF SH > 50°C.  CHARGE THE GLAND SEAL SYSTEM OF TDBFP.  START THE VACUUM PULLING WITH VACUUM PUMP. MAINTAIN VACUUM -0.9 KG/CM2.  CHARGE THE HP-LP BYPASS SYSTEM .MAINTAIN THE MS STEAM PRESSURE AND FIRING RATE FOR ACHIEVING TURBINE ROLLING PARAMETERS.
  • 19. COLD START UP CURVE
  • 20. HOT ROLLING MS TEMP RH TEMP SPEED MS FLOW LOAD MS PRESS
  • 21. PRE HEATING OF HP CASING.  PREHEATING OF HPT REQUIRED WHEN INNER METAL TEMP <150°C.  CRH PR 0.5-0.7 MPA/220-380°C.  OPEN PRE HEATING VALVE (REVERSE FLOW VALVE) GRADUALLY.  OPEN BDV VALVE FULLY.  OPEN CRH DRAIN BEFORE NRV AND HPT-IPT CASING DRAINS.  HEATING RATE SHOULD NOT BE MORE THAN 50°C PER HR.  HP CASING TOP-BOTTOM & INNER-OUTER WALL METAL TEMP DIFFRENCE SHOULD BE WITHIN 50°C.  AFTER ATTAINING THE CASING TEMP > 150°C CLOSE THE RFV VALVE AND OPEN HP CYLINDER VENTILATION VALVE TO CONDENSOR.
  • 22. TURBINE WARM UP OPERATION TURBINE STARUP PROCEDURE RFV CRH NRV HPT HPBP CRH LINE Ventilator valve TO CONDENSER IPT BDV TO CONDENSER MS
  • 23. TURBINE ROLLING  AS PER REQUIREMENT OF START UP CURVE, FIRING TO BE INCREASED.  REQUIRED STEAM PARAMETERS BEFORE ROLLING  MS PR: 8.73 MPA, TEMP: 330-380 °C  RH PR: 1.1 MPA , TEMP: 330°C - THE DEGREE OF SUPER HEAT > 56°C.  AFTER LATCHING THE TURBINE, START IP ROLLING WITH HP VENT TO CONDENSER IN OPEN CONDITION TO KEEP THE HPT IN VACUUM.  MSV 1&2 AND RSV 1&2 ARE IN OPEN CONDITION.  GIVE THE SPEED SET POINT TO 600 RPM  CHECK THE TURBINE SUPERVISORY INSTRUMENT PARAMETER.  THE ECCENTRICITY SHOULD BE LESS THAN 0.076 MM.
  • 24. TURBINE ROLLING  SELECT TARGET SPEED 1500 RPM WITH RAMP RATE OF 100 RPM/MIN.  ENSURE ALL HP CV’S OPENS TO 12% TO WARM UP THE HP CASING.  WHEN HP CASING TEMP >320°C.CLOSE THE HP CV’S.  SOAK THE TURBINE FOR 4 HRS ACCORDING TO THE START UP CURVE.  CHARGE THE LP HEATER 5 & 6 BEFORE 3000 RPM  SELECT TARGET SPEED TO 3000 RPM WITH RAMP RATE OF 100 RPM/MIN.SOAK IT FOR 30 MIN AS PER S/U CURVE.  AS PER PROCEDURE SYNCHRONISE THE UNIT.
  • 25. LOADING  AFTER SYNCHRONISATION INITIAL LOAD WILL BE 30 MW.HOLD IT FOR 30 MIN AND CHEK THE VIBRATION, BEARING TEMP, DIFF EXPANSION, CASING EXPANSION.  CHARGE EXTRACTION STEAM TO DEAERATOR.  TAKE MORE OIL GUNS IN EF/AB ELEVETION.  TAKE PA FANS & SEAL AIR FAN.  AFTER ACHIEVING FURNACE TEMP. MORE THEN 450°C. TAKE COAL MILL-B AT. STEAM T/PR 380°C/8.7 MPA.  INCREASE FUEL FLOW MAINTAINING STEAM TEMP.& RAISE LOAD  AT 70 MW IP TO HP CHANGE OVER. CV’S WILL START OPENING, CLOSE THE BDV AND VENTILATING VALVE.  INCREASE THE LOAD AT 3MW/MIN  CLOSE THE HP-LP BYPASS GRADULLY.
  • 26. 350 400 450 500 550 600 650 MINUTES LOAD (MW) 165 330 495 660 33MW 60MW 198MW 330MW SYNCHRONISE &CHARGED/A MILL-BCUTIN IPTOHPCHANGEOVER(70MW MILL-CCUTINAT100MW HPHCHARGED(150MW) 2ND TDBFPCUTIN(180MW) WETTODRYCHANGEOVER MILL-ACUTIN(210MW) OILGUNCUTOUT(260MW) MILL-DCITIN(300MW) MILL-ECUTIN(430MW) MILL-FCUTIN(540MW) 660 MW
  • 27. CONDENSER LP HEATER 7A LP HEATER 8A CONDENSER LP HEATER 7B LP HEATER 8B LPT A LPT B HP HEATER 5 HP HEATER 6 LP HEATER 5 LP HEATER 6 2nd 2nd 4th 4th 5th 5th 5th 5th 6th 6th 6th 6th FROM IPT EXHAUST
  • 28. TDBFP START UP  TAKE ONE TDBFP IN SERVICE( CHANGE OVER WITH MD BFP) WHILE DRIVING STEAM IS AVAILABLE. SECOND TD BFP WILL BE TAKEN AT 180 MW.  WARM UP THE TURBINE.  SLOWLY OPEN THE AUX STEAM MOV TO TURBINE.  PARAMETERS FOR ROLLING TDBFP. STEAM PRESSURE: 0.6 ~ 1.3MPA, STEAM TEMP: 50 DEG C MORE THAN CASING TEMP.  ROLL THE TDBFP AS PER PROCEDURE.  GIVE THE TARGET SPEED 500 RPM AND THAN TO 1000 HOLD FOR 40 MIN.CHECK THE TSI PARAMETER  WHEN SPEED REACHES 2840 RPM, GIVE REQUEST COMMAND FROM FW MENU. THEN SELECT CCS CONTROL IN FROM MEH MENU.
  • 29. IP TDBFP-A TDBFP-B Aux. Steam Header To CRH HP From CRH M M M M Deaerator Booster pumps M M M E E To Condenser Aux. Steam Header M M M M M M M E E Deaerator 1.3 MPa 350 ºC 1.12 Mpa 378 ºC 4 MPa 315.3 ºC Changeover Valve TDBFP STEAM SOURCES
  • 30. LOADING  TAKE THE MILL-C IN SERVICE AT 100 MW. STEAM T/PR:400°C/8.7 MPA.  GRADUALLY WITH DRAW THE OIL SUPPORT AS PER THE FLAME CONDITION.  INCREASE THE LOAD TO 150 MW AND TAKE THE HPH-3, HPH-2 & HPH-1 IN SERVICE. MS T/PR 410°C/8.7 MPA.  AT 180 MW TAKE SECOND TDBFP IN SERVICE.
  • 31. HP HEATER 3 DEAERATOR HP HEATER 2 HP HEATER 1 CRH LINE TDBFP A TDBFP B MS LINE 9th stage 5th stage HP HEATER 1 HP HEATER 2 HP HEATER 3 HRH LINE DEAERATOR IP EXHAUST
  • 32. PHASE CHANGE FROM WET TO DRY MODE  DURING LOAD RAISING >25% BMCR, THE BCP FLOW AND FEED WATER FLOW TO BE MONITORED CLOSELY.  THE BCP FLOW NEED TO BE ADJUSTED W.R.T SEPERATOR TANK LEVEL AND THE SAME FLOW TO BE ADJUSTED IN FEED WATER FLOW TO MAINTAIN TOTAL FEED WATER FLOW TO ECONOMISER CONSTANT.  WHEN BOILER STEAMING RATE RISES TO >30% BMCR, W.R.T FUEL FIRING, THE SEPERATOR LEVEL REDUCES .  ONCE THE CONDITION FULFILLS THE BCP STOPS AND FEED FLOW CONTROL CHANGES OVER FRS.  AFTER STOPPING BCP IT ACTS AS SUB-CRITICAL ONCE THROUGH“.  WHEN THE STEAM PR REACHES 22.1 MPA IT IS IN “SUPERCRITICAL ZONE”
  • 33. LOADING  TAKE MILL-A AT 210 MW.  CUT THE OIL SUPPORT AT 260 MW AS PER THE FLAME CONDITION.  TAKE MILL-D AT 300 MW. MS T/PR 475°C/10 MPA.  TAKE MILL-E AT 430 MW. MS T/PR 566°C/17 MPA.  TAKE MILL-F AT 540 MW. MS T/PR 566°C/24.1 MPA.  INCREASE THE LOAD TO “FULL LOAD 660 MW” GRADUALLY.
  • 34. Boiler Design Parameters NO.NO. ParametersParameters UnitUnit 11 100% BMCR Coal consumption (Design)100% BMCR Coal consumption (Design) 390.37390.37 t/ht/h 22 Design fuelDesign fuel Indian coalIndian coal 33 Superheated steam flowSuperheated steam flow 21112111 t/ht/h 44 Superheater outlet pressureSuperheater outlet pressure 25.425.4 MPaMPa 55 Superheater outlet temperatureSuperheater outlet temperature 569569 ℃℃ 66 Reheated steam flowReheated steam flow 1749.11749.1 t/ht/h 77 Reheater inlet pressureReheater inlet pressure 4.734.73 MPaMPa 88 Reheater outlet pressureReheater outlet pressure 4.494.49 MPaMPa 99 Reheater inlet temperatureReheater inlet temperature 324324 ℃℃ 1010 Reheater outlet temperatureReheater outlet temperature 569569 ℃℃ Feedwater pressureFeedwater pressure 28.828.8 MPa.gMPa.g 1111 Feedwater temperatureFeedwater temperature 280280 ℃℃ 1212 Separator’s steam temperatureSeparator’s steam temperature 421421 ℃℃ 1313 Air preheater’s outlet air temperature, uncorrectedAir preheater’s outlet air temperature, uncorrected After correctingAfter correcting 153.3153.3 ℃℃ 147.2147.2 ℃℃ 1414 Calculating thermal efficiency of boilerCalculating thermal efficiency of boiler 87.19%87.19% (( BMCRBMCR ))
  • 35. TURBINE PARAMETERS HPT IPT LPT Pressure (MPa) 24.2 3.961 1.12 I/L Temp (Deg C) 566 566 378 O/L Temp(deg C) 315.3 378 Steam Flow (tph) 1959.25 1649 TURBINE HEAT RATE( KCL/KWH) 1885 No of Stop valves 2 2 No of Control valves 4 4 Steam Admission Parameters at Turbine Inlet
  • 36. TURBINEAT FULL LOAD HPT IPT RSV LPT LPT #2 GEN CRH CRH HRH MS LINE HRH MS LINE 3.96MPa / 566°c 24.2MPa/566ºC TO BLR RH RCV MSV RCVRCV RCVCV CVCV RSV CVCV CVCV RSV CVCVMSV CV CV LPT LPT #2LPT GEN#2LPTLPT #1 MSV CV CVMSV CVMSV CVMSV CVCVMSV CVMSV CVMSV CV CVMSV MSV CVMSV CVCVMSV RSV CV CV RSV CV RSV CV RSV CVCV RSV 1.12MPa / 378°c CONDENSOR A CONDENSOR B
  • 37. SHUT DOWN  EXCEPT IN AN EMERGENCY, LOAD SHOULD BE REDUCED GRADUALLY.  CUT THE MILL-F AT 540 MW.  CUT THE MILL-E AT 470MW.  CUT THE MILL-D AT 300 MW.  TAKE OIL SUPPORT FOR FURNACE STABILITY ( AT THE TIME OF 3 MILL OPERATION).  CUT THE MILL-A AT 210 MW.  TAKE THE HPH-1,2,3 OUT OF SERVICE.  WHEN THE LOAD < 30% BOILER COMES IN WET MODE FROM DRY MODE. START THE BCP AND MAINTAIN THE SEPEARTOR LEVEL.
  • 38. SHUT DOWN  WHEN THE LOAD HAS DECREASED TO 20% OF RATED LOAD TRIP THE TURBINE ON TURBINE PROTECTION. THIS CLOSES THE THROTTLE VALVES, GOVERNOR VALVES, REHEAT STOP VALVES AND INTERCEPTOR VALVES  CHECK DRAIN VALVES OPENS IN AUTO.  HP LP BYPASS VALVE OPENS TO MAINTAIN THE FLOW.  REDUCE THE BOILER LOAD GRADULLY.  TRIP THE BOILER.  THE VACUUM BREAKER VALVES SHOULD NOT BE OPENED UNTIL THE TURBINE UNIT HAS COASTED DOWN.  VACUUM SHOULD BE KILLED BEFORE GLAND SEALING STEAM IS SHUT OFF.  AUX OIL PUMP STARTS IN AUTO AT 2850 RPM.  JOP START IN AUTO AT 1200 RPM.
  • 39. SHUT DOWN  WHEN THE VACUUM REACHES ZERO, SHUT OFF THE SEALING STEAM TO THE GLAND STEAM CONTROL VALVES.  SHUT DOWN THE GLAND STEAM CONDENSER EXHAUSTER. SHUT DOWN CONDENSATE PUMP.  SHUT DOWN THE VACUUM PUMP.  SHUT OFF THE COOLING WATER SUPPLY TO THE GENERATOR HYDROGEN COOLERS.  ENSURE THAT BARRING GEAR HAS CUT IN.