SlideShare a Scribd company logo
1 of 31
www.heatflux.com
Improving Catalytic Reformer Heaters
Using New Technologies
Ashutosh Garg
Furnace Improvements Services
www.heatflux.com
FIS Patented
Catalytic Reforming Units
Catalytic Reforming Unit is an important unit in most
refineries
It converts Straight Run Naphtha from Low Octane to
High Octane in Presence of Hydrogen
The reaction occurs in the presence of catalyst.
The reaction is endothermic in nature.
The reaction is carried out in 3 or 4 stage reactors.
Feed needs to be heated in the charge heater and then to
the interheaters before reactors.
www.heatflux.com
Catalytic reforming units initially
operated at very high pressure and
over the last 50 years the pressure has
gradually reduced from 1000 psig to
almost 50 psig.
Feed volume increases substantially
as the pressure goes down.
Typical pressure drop across each
stage is only 3-4 psi.
Pressure drop is very critical as it
determines recycle gas compressors.
www.heatflux.com
Catalytic Reforming Heaters
Most of the heaters have charge in the radiant
section only
 Inlet all vapor, large manifolds provided
 Low pressure drop required, multiple passes
 High inlet temperature 850-900 F, outlet temperature-
950-1050 F
Convection section has waste heat recovery
 Mostly steam generation –bfw preheating, steam
generation and steam superheater
 Some have stripper and stabilizer reboilers coils
www.heatflux.com
Construction
Most heaters are natural draft
configuration
Tall stack providing draft in the
radiant section
Air preheating also installed in
some heaters
Typical heat flux
15,000-20,000 Btu/hr.ft2
Tubes are single fired or double
fired
www.heatflux.com
Convection Section
Stack
Damper
Most Clients
want to
Increase
Heater Duty
Clients are want to increase the
capacity of their units
Increase in charge rate means increase
of pressure drop in the heater
Limited in pressure drop and cannot
push more charge
Limited in firing rate/permit limit
www.heatflux.com
Conventional Approach
Increase tube size to reduce pressure drop
Upgrade tube metallurgy to increase TMT limits
Both options require complete radiant section
retubing including manifold
Increase heat transfer area in radiant section
 Extend existing radiant section
 Add new radiant section
Both these options are extremely expensive
www.heatflux.com
Process Feed In
Process Feed Out
Waste Heat
Recovery Unit
1,600°F
750°F
250°F
750°F
1000°F
Conventional Approach to Increasing Capacity
 Extend radiant cell and add more radiant coils & burners
 Provide additional radiant cells with new coils and burners
H-20
H-21
H-22
H-20
(NEW)
H-21
(NEW)
H-21
(NEW)
H-20 H-21 H-22
www.heatflux.com
Drawbacks of
Conventional
Approach
Real estate
requirement
New burners
& associated
changes
New civil
foundation
work
Higher firing
rates
Draft
limitation
Very High cost
www.heatflux.com
Split Flow* Fired Heater
www.heatflux.com10
*Patented
Feed In Feed Out
450 °F 600 °F
Radiant Section
Convection
Section - I
1,650 °FFlue gas 3,200 °FFlue gas
1,650 °FFlue gas
500 °F
Convection
Section- II
750 °FFlue gas
Flue gas
Flue gas
Split Flow in
Split Flow out
450 °F 600 °F
500 °F
Reformer Heater - Split Flow
Radiant Section
 Parallel Passes
 Heat 70% of process feed
Convection Section
 Heat 30% of Process Feed
 Waste heat recover
• HC Reboiler
• Steam Generation Service
 Pressure drop is maintained
11
Process Feed In Process Feed Out
Split
Flow in
Split Flow Out
Waste Heat
Recovery Unit
1,600°F
1,100°F
250°F
400°F
Reformer Heater – Flexible Split Flow
Radiant Section
 Parallel Passes
 Heat 70% + of process feed
Convection Section
 Heat up to 30% of Process Feed
 Waste heat recovery
• HC Reboiler
• Steam Generation Service
Pressure drop is kept same even
at increased charge rate.
www.heatflux.com
Split Flow with Flexibility
Split Flow Technology - Advantages
Low Cost Solution for:
 Increasing Capacity
 Improving Efficiency
Lower Pressure Drop
Lower Revamping Cost
Flexible Operation
 Maximum Process Duty
 Maximum Steam Generation
www.heatflux.com
Case Study 1
Three stage catalytic reformer ( reactor) unit
First cell – Feed heater, Rest 3 cells- interheater
Feed- Mixture of Naphtha and Recycle gas
Inlet Temperature- 842-990 °F
Outlet Temperature-1010 °F
Inlet Pressure-231 psig
Outlet Pressure- 228 psig
Pressure drop /stage- 3 psi
www.heatflux.com
Revamp Objectives
Improve Efficiency
 Stack temperature was 1100 ºF
 No steam generation
 No air preheater
Gas prices touched
$10/MSCF
www.heatflux.com
Arrangement - Original Heater
Process flow before revamp
StackStackStack
Stabilizer
Btms
Stabilizer
Btms
Stripper Btms
Stripper Btms
To Plat. RX To Plat. RX
From Plat. RX.
To Plat. RX
From Plat. RX
Stripper Btms
From Plat.
RX
To Plat. RX
Stripper Btms
BURNERS
428°F
840°F
459°F
1010°F
www.heatflux.com
Reformer Heater Conventional
Revamp
Increase heat transfer surface in
convection section
Pressure drop – more than twice
of existing
Large size piping requirement
Larger convection sections
Increased stack height
High cost ($6 Million) Reformer Heater
www.heatflux.com
Split-Flow Arrangement
Split Flow Technology Design
StackStackStack
Burners
#1 In
#1 Out
In
#2 In
#2 Out
#3 In
#3 Out
#4 In
#4 Out
In
Out
Out
www.heatflux.com
Heater Data Comparison
Heater after revamp
Reformer Heater Data Comparison
Item Units Before After
Capacity BPD 18,500 24,000
Heat Duty MMBtu/hr 158 194.5
Heat release MMBtu/hr 234 225
Stack temp. °F 1,092 478
Efficiency % 67.5 86.6
Fuel savings $/annum 5.8 Million
www.heatflux.com
Case Study-2
Process heating-all Radiant
Steam Generation in Convection
Natural Draft
Firing rates were very high
Heater efficiency lower than design
value by 10% to 15%
Stack temperature -650℉ (320 ℉
higher than design)
www.heatflux.com
Radiant Section
3 Cells
52/56/48 tubes in cells 1/2/3
P22 tubes
Inverted U tubes
Single fired design
Bottom inlet/outlet
2.5 inch tubes at 5 inch pitch
Total -23 Burners (7 , 9 and 7 in cell 1/2/3)
www.heatflux.com
Convection Section
Steam Generator Bank
BFW Preheater Bank
Steam Generation: 53,650 lbs/hr@300 psig
8 tubes per row
Eleven rows
Two future rows
www.heatflux.com
Revamp Objectives
Increase heater capacity from 12,000 to
18,000 BPD
Improve thermal efficiency
Maintain NOx emissions
Improve Reliability
www.heatflux.com
Proposed Process Heat Duties (MMBtu/hr)
at 18000 BPD
Heater Section
Existing Heat
Duty
Proposed
Duty
Extra Duty
Required
70-H-1 27.7 37.5 9.8
70-H-2 33.4 44.7 11.3
70-H-3 22.9 30.9 8.0
Stem Gen. 51.6 47.8 -
Total Process 84 113.1 29.1
www.heatflux.com
Split Flow for 70-H-1/70-H-2/70-H-3
70-H-1- 2 Bare Rows
70-H-2- 2 Finned Rows
70-H-3 – 2 Finned Rows
TFG = 1,717℉
TFG = 1,300℉
TFG = 350℉
TFG = 1,717℉www.heatflux.com
Final Revamp – Split Flow Control Scheme
www.heatflux.com
Proposed Revamp Solution
Lower Pressure drop in all heaters
 Allowable : 5 psi
 Calculated : 2-4 psi
No Modification to existing Radiant cells
Reduced Average Heat Flux
Lower Firing Rate – 180 MMBtu /hr
Lower Volumetric Heat Release
More efficient system - 89%
Flexibility to increase duty further
www.heatflux.com
Flexible Split Flow Technology
www.heatflux.com
Proposed Scheme Advantages
25-30% process feed of Cells 1 & 2 is heated in split flow coils
Heater to be operated at two modes:
 Normal operation/Maximum process absorbed duties
 Dry run operation/Maximum steam generation
To maximize steam production, process absorbed duties reduced
Split flow coils are run dry to shift convection heat duties for steam
generation
It gives flexibility in steam production and process duties as per
requirement
No change in firing rates
www.heatflux.com
General Advantages of FIS
Flexible Split Flow Technology
Improved Capacity and Flexible Operation
Higher Efficiency
Lower Pressure Drop (process)
Lower Firing Rate
Lower Fire Box Temperatures
Lower Radiant Heat Fluxes
Lower TMT
Lower Turnaround Time
Lower Installation Cost
www.heatflux.com
www.heatflux.com
Furnace Improvement Services Inc.
Low Cost Solutions for Fired Heaters and Boilers
1600 Hwy 6 South Ste. 480
Sugar Land, TX 77479
Tel: (281) 980-0325
www.heatflux.com
Thank you very much.
Questions and Comments are welcome.

More Related Content

What's hot

Furnace Improvements Sales Presentation
Furnace Improvements Sales PresentationFurnace Improvements Sales Presentation
Furnace Improvements Sales PresentationJonathan Morales
 
Fired Heaters-Key to Efficient Operation of Refineries and Petrochemicals
Fired Heaters-Key to Efficient Operation of Refineries and PetrochemicalsFired Heaters-Key to Efficient Operation of Refineries and Petrochemicals
Fired Heaters-Key to Efficient Operation of Refineries and PetrochemicalsAshutosh Garg
 
Furnace Improvements patented - Split Flow technology
Furnace Improvements patented - Split Flow technologyFurnace Improvements patented - Split Flow technology
Furnace Improvements patented - Split Flow technologyDisha Mangal
 
FIS Case Studies- Executed Projects Only
FIS Case Studies- Executed Projects OnlyFIS Case Studies- Executed Projects Only
FIS Case Studies- Executed Projects OnlyJonathan Morales
 
A new approach to improving heater efficiency
A new approach to improving heater efficiencyA new approach to improving heater efficiency
A new approach to improving heater efficiencyAshutosh Garg
 
Better Fired Heaters Specifications Pay Off- AFRC Meeting-2018 Salt Lake City
Better Fired Heaters Specifications Pay Off- AFRC Meeting-2018 Salt Lake CityBetter Fired Heaters Specifications Pay Off- AFRC Meeting-2018 Salt Lake City
Better Fired Heaters Specifications Pay Off- AFRC Meeting-2018 Salt Lake CityAbhinanda Das
 
Heater operation
Heater operationHeater operation
Heater operationJOMON M.C
 
Fired Heater and Combustion Optimization From Yokogawa
Fired Heater and Combustion Optimization From YokogawaFired Heater and Combustion Optimization From Yokogawa
Fired Heater and Combustion Optimization From YokogawaMiller Energy, Inc.
 
Process Heaters, Furnaces and Fired Heaters: Improving Efficiency and Reducin...
Process Heaters, Furnaces and Fired Heaters: Improving Efficiency and Reducin...Process Heaters, Furnaces and Fired Heaters: Improving Efficiency and Reducin...
Process Heaters, Furnaces and Fired Heaters: Improving Efficiency and Reducin...Belilove Company-Engineers
 
Coal fired electric power plants23
Coal fired electric power plants23Coal fired electric power plants23
Coal fired electric power plants23Munna Sagar
 
Burner Design, Operation and Maintenance on Ammonia Plants
Burner Design, Operation and Maintenance on Ammonia PlantsBurner Design, Operation and Maintenance on Ammonia Plants
Burner Design, Operation and Maintenance on Ammonia PlantsGerard B. Hawkins
 
Revamps for Modern Hydrogen Plants
Revamps for Modern Hydrogen PlantsRevamps for Modern Hydrogen Plants
Revamps for Modern Hydrogen PlantsGerard B. Hawkins
 
2003 ASME Power Conference Performance Evaluation of Feedwater Heaters for Nu...
2003 ASME Power Conference Performance Evaluation of Feedwater Heaters for Nu...2003 ASME Power Conference Performance Evaluation of Feedwater Heaters for Nu...
2003 ASME Power Conference Performance Evaluation of Feedwater Heaters for Nu...Komandur Sunder Raj, P.E.
 
Energy adudit methodology for boiler
Energy adudit methodology for boilerEnergy adudit methodology for boiler
Energy adudit methodology for boilerKongkiert Tankayura
 
Performance calculation for feed water heater
Performance calculation  for feed water heaterPerformance calculation  for feed water heater
Performance calculation for feed water heaterSHIVAJI CHOUDHURY
 
Feed water and condensate heaters
Feed water and condensate heatersFeed water and condensate heaters
Feed water and condensate heatersManohar Tatwawadi
 

What's hot (20)

Furnace Improvements Sales Presentation
Furnace Improvements Sales PresentationFurnace Improvements Sales Presentation
Furnace Improvements Sales Presentation
 
Fired Heaters-Key to Efficient Operation of Refineries and Petrochemicals
Fired Heaters-Key to Efficient Operation of Refineries and PetrochemicalsFired Heaters-Key to Efficient Operation of Refineries and Petrochemicals
Fired Heaters-Key to Efficient Operation of Refineries and Petrochemicals
 
Furnace Improvements patented - Split Flow technology
Furnace Improvements patented - Split Flow technologyFurnace Improvements patented - Split Flow technology
Furnace Improvements patented - Split Flow technology
 
FIS Case Studies- Executed Projects Only
FIS Case Studies- Executed Projects OnlyFIS Case Studies- Executed Projects Only
FIS Case Studies- Executed Projects Only
 
A new approach to improving heater efficiency
A new approach to improving heater efficiencyA new approach to improving heater efficiency
A new approach to improving heater efficiency
 
Better Fired Heaters Specifications Pay Off- AFRC Meeting-2018 Salt Lake City
Better Fired Heaters Specifications Pay Off- AFRC Meeting-2018 Salt Lake CityBetter Fired Heaters Specifications Pay Off- AFRC Meeting-2018 Salt Lake City
Better Fired Heaters Specifications Pay Off- AFRC Meeting-2018 Salt Lake City
 
Introduction of Fired heaters
Introduction of Fired heatersIntroduction of Fired heaters
Introduction of Fired heaters
 
Heater operation
Heater operationHeater operation
Heater operation
 
Fired Heater and Combustion Optimization From Yokogawa
Fired Heater and Combustion Optimization From YokogawaFired Heater and Combustion Optimization From Yokogawa
Fired Heater and Combustion Optimization From Yokogawa
 
Process Heaters, Furnaces and Fired Heaters: Improving Efficiency and Reducin...
Process Heaters, Furnaces and Fired Heaters: Improving Efficiency and Reducin...Process Heaters, Furnaces and Fired Heaters: Improving Efficiency and Reducin...
Process Heaters, Furnaces and Fired Heaters: Improving Efficiency and Reducin...
 
Coal fired electric power plants23
Coal fired electric power plants23Coal fired electric power plants23
Coal fired electric power plants23
 
Burner Design, Operation and Maintenance on Ammonia Plants
Burner Design, Operation and Maintenance on Ammonia PlantsBurner Design, Operation and Maintenance on Ammonia Plants
Burner Design, Operation and Maintenance on Ammonia Plants
 
New Technologies in Process Heating
New Technologies in Process HeatingNew Technologies in Process Heating
New Technologies in Process Heating
 
Minimum Energy Performance Standards for Boilers in India
Minimum Energy Performance Standards for Boilers in IndiaMinimum Energy Performance Standards for Boilers in India
Minimum Energy Performance Standards for Boilers in India
 
Developments in Industrial Boilers, WHR and Power Boilers
Developments in Industrial Boilers, WHR and Power BoilersDevelopments in Industrial Boilers, WHR and Power Boilers
Developments in Industrial Boilers, WHR and Power Boilers
 
Revamps for Modern Hydrogen Plants
Revamps for Modern Hydrogen PlantsRevamps for Modern Hydrogen Plants
Revamps for Modern Hydrogen Plants
 
2003 ASME Power Conference Performance Evaluation of Feedwater Heaters for Nu...
2003 ASME Power Conference Performance Evaluation of Feedwater Heaters for Nu...2003 ASME Power Conference Performance Evaluation of Feedwater Heaters for Nu...
2003 ASME Power Conference Performance Evaluation of Feedwater Heaters for Nu...
 
Energy adudit methodology for boiler
Energy adudit methodology for boilerEnergy adudit methodology for boiler
Energy adudit methodology for boiler
 
Performance calculation for feed water heater
Performance calculation  for feed water heaterPerformance calculation  for feed water heater
Performance calculation for feed water heater
 
Feed water and condensate heaters
Feed water and condensate heatersFeed water and condensate heaters
Feed water and condensate heaters
 

Similar to Increase catalytic reformer capacity and efficiency with split flow technology

Steam Reforming - Practical Operations
Steam Reforming - Practical OperationsSteam Reforming - Practical Operations
Steam Reforming - Practical OperationsGerard B. Hawkins
 
Air to Water Low Temperature Heat Pump
Air to Water Low Temperature Heat PumpAir to Water Low Temperature Heat Pump
Air to Water Low Temperature Heat PumpCCSE Host
 
nitrogen_syngas_article_controlling_the_stresses_of-the_primary_reformer_may_...
nitrogen_syngas_article_controlling_the_stresses_of-the_primary_reformer_may_...nitrogen_syngas_article_controlling_the_stresses_of-the_primary_reformer_may_...
nitrogen_syngas_article_controlling_the_stresses_of-the_primary_reformer_may_...Shubham Mishra
 
Steam_Boiler_Basics_tim_powell_hughes.pdf
Steam_Boiler_Basics_tim_powell_hughes.pdfSteam_Boiler_Basics_tim_powell_hughes.pdf
Steam_Boiler_Basics_tim_powell_hughes.pdfGaluhAjeng26
 
EMERSON Power plant applications
EMERSON Power plant applicationsEMERSON Power plant applications
EMERSON Power plant applicationsmirfanm
 
Emerson Power plant applications
Emerson Power plant applicationsEmerson Power plant applications
Emerson Power plant applicationsmirfanm
 
Load Match Next Generation
Load Match Next GenerationLoad Match Next Generation
Load Match Next Generationkiakaha
 
Feedwater heaters in thermal power plants
Feedwater heaters in thermal power plantsFeedwater heaters in thermal power plants
Feedwater heaters in thermal power plantsSHIVAJI CHOUDHURY
 
Heat exchange technology explained
Heat exchange technology explainedHeat exchange technology explained
Heat exchange technology explainedSpirax Sarco UK
 
thermal power plant PTTP Parichha
thermal power plant PTTP Parichhathermal power plant PTTP Parichha
thermal power plant PTTP ParichhaGagandeep Maan
 
GSHP Training for Plumbcenter - Delivered by Kensa Heat Pumps - November 2011
GSHP Training for Plumbcenter - Delivered by Kensa Heat Pumps - November 2011GSHP Training for Plumbcenter - Delivered by Kensa Heat Pumps - November 2011
GSHP Training for Plumbcenter - Delivered by Kensa Heat Pumps - November 2011kensaheatpumps
 
Ntpc (national thermal power corporation) sipat boiler haxxo24 i~i
Ntpc (national thermal power corporation) sipat boiler haxxo24 i~iNtpc (national thermal power corporation) sipat boiler haxxo24 i~i
Ntpc (national thermal power corporation) sipat boiler haxxo24 i~ihaxxo24
 
Ppt of internship at dccpp
Ppt of internship at dccppPpt of internship at dccpp
Ppt of internship at dccppDurgSingh
 
AmbiRad general presentation
AmbiRad general presentationAmbiRad general presentation
AmbiRad general presentationLee Herbert
 
660 mw supercritical boiler
660 mw supercritical boiler660 mw supercritical boiler
660 mw supercritical boilerAshvani Shukla
 
Thermal system design 3
Thermal system design 3Thermal system design 3
Thermal system design 3shehryar23
 

Similar to Increase catalytic reformer capacity and efficiency with split flow technology (20)

Steam Reforming - Practical Operations
Steam Reforming - Practical OperationsSteam Reforming - Practical Operations
Steam Reforming - Practical Operations
 
Air to Water Low Temperature Heat Pump
Air to Water Low Temperature Heat PumpAir to Water Low Temperature Heat Pump
Air to Water Low Temperature Heat Pump
 
nitrogen_syngas_article_controlling_the_stresses_of-the_primary_reformer_may_...
nitrogen_syngas_article_controlling_the_stresses_of-the_primary_reformer_may_...nitrogen_syngas_article_controlling_the_stresses_of-the_primary_reformer_may_...
nitrogen_syngas_article_controlling_the_stresses_of-the_primary_reformer_may_...
 
Steam_Boiler_Basics_tim_powell_hughes.pdf
Steam_Boiler_Basics_tim_powell_hughes.pdfSteam_Boiler_Basics_tim_powell_hughes.pdf
Steam_Boiler_Basics_tim_powell_hughes.pdf
 
EMERSON Power plant applications
EMERSON Power plant applicationsEMERSON Power plant applications
EMERSON Power plant applications
 
Emerson Power plant applications
Emerson Power plant applicationsEmerson Power plant applications
Emerson Power plant applications
 
Load Match Next Generation
Load Match Next GenerationLoad Match Next Generation
Load Match Next Generation
 
Methanol Reformer Designs
Methanol Reformer DesignsMethanol Reformer Designs
Methanol Reformer Designs
 
Feedwater heaters in thermal power plants
Feedwater heaters in thermal power plantsFeedwater heaters in thermal power plants
Feedwater heaters in thermal power plants
 
ammoniautility operator
ammoniautility operatorammoniautility operator
ammoniautility operator
 
ammonia&utility operator
ammonia&utility operatorammonia&utility operator
ammonia&utility operator
 
Heat exchange technology explained
Heat exchange technology explainedHeat exchange technology explained
Heat exchange technology explained
 
thermal power plant PTTP Parichha
thermal power plant PTTP Parichhathermal power plant PTTP Parichha
thermal power plant PTTP Parichha
 
GSHP Training for Plumbcenter - Delivered by Kensa Heat Pumps - November 2011
GSHP Training for Plumbcenter - Delivered by Kensa Heat Pumps - November 2011GSHP Training for Plumbcenter - Delivered by Kensa Heat Pumps - November 2011
GSHP Training for Plumbcenter - Delivered by Kensa Heat Pumps - November 2011
 
Ntpc (national thermal power corporation) sipat boiler haxxo24 i~i
Ntpc (national thermal power corporation) sipat boiler haxxo24 i~iNtpc (national thermal power corporation) sipat boiler haxxo24 i~i
Ntpc (national thermal power corporation) sipat boiler haxxo24 i~i
 
Ppt of internship at dccpp
Ppt of internship at dccppPpt of internship at dccpp
Ppt of internship at dccpp
 
AmbiRad general presentation
AmbiRad general presentationAmbiRad general presentation
AmbiRad general presentation
 
660 mw supercritical boiler
660 mw supercritical boiler660 mw supercritical boiler
660 mw supercritical boiler
 
Thermal system design 3
Thermal system design 3Thermal system design 3
Thermal system design 3
 
O&m of boiler
O&m of boilerO&m of boiler
O&m of boiler
 

Recently uploaded

Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
DATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage exampleDATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage examplePragyanshuParadkar1
 
EduAI - E learning Platform integrated with AI
EduAI - E learning Platform integrated with AIEduAI - E learning Platform integrated with AI
EduAI - E learning Platform integrated with AIkoyaldeepu123
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfme23b1001
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptSAURABHKUMAR892774
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEroselinkalist12
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
pipeline in computer architecture design
pipeline in computer architecture  designpipeline in computer architecture  design
pipeline in computer architecture designssuser87fa0c1
 

Recently uploaded (20)

Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
DATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage exampleDATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage example
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
EduAI - E learning Platform integrated with AI
EduAI - E learning Platform integrated with AIEduAI - E learning Platform integrated with AI
EduAI - E learning Platform integrated with AI
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdf
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.ppt
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
pipeline in computer architecture design
pipeline in computer architecture  designpipeline in computer architecture  design
pipeline in computer architecture design
 

Increase catalytic reformer capacity and efficiency with split flow technology

  • 1. www.heatflux.com Improving Catalytic Reformer Heaters Using New Technologies Ashutosh Garg Furnace Improvements Services www.heatflux.com FIS Patented
  • 2. Catalytic Reforming Units Catalytic Reforming Unit is an important unit in most refineries It converts Straight Run Naphtha from Low Octane to High Octane in Presence of Hydrogen The reaction occurs in the presence of catalyst. The reaction is endothermic in nature. The reaction is carried out in 3 or 4 stage reactors. Feed needs to be heated in the charge heater and then to the interheaters before reactors. www.heatflux.com
  • 3. Catalytic reforming units initially operated at very high pressure and over the last 50 years the pressure has gradually reduced from 1000 psig to almost 50 psig. Feed volume increases substantially as the pressure goes down. Typical pressure drop across each stage is only 3-4 psi. Pressure drop is very critical as it determines recycle gas compressors. www.heatflux.com
  • 4. Catalytic Reforming Heaters Most of the heaters have charge in the radiant section only  Inlet all vapor, large manifolds provided  Low pressure drop required, multiple passes  High inlet temperature 850-900 F, outlet temperature- 950-1050 F Convection section has waste heat recovery  Mostly steam generation –bfw preheating, steam generation and steam superheater  Some have stripper and stabilizer reboilers coils www.heatflux.com
  • 5. Construction Most heaters are natural draft configuration Tall stack providing draft in the radiant section Air preheating also installed in some heaters Typical heat flux 15,000-20,000 Btu/hr.ft2 Tubes are single fired or double fired www.heatflux.com Convection Section Stack Damper
  • 6. Most Clients want to Increase Heater Duty Clients are want to increase the capacity of their units Increase in charge rate means increase of pressure drop in the heater Limited in pressure drop and cannot push more charge Limited in firing rate/permit limit www.heatflux.com
  • 7. Conventional Approach Increase tube size to reduce pressure drop Upgrade tube metallurgy to increase TMT limits Both options require complete radiant section retubing including manifold Increase heat transfer area in radiant section  Extend existing radiant section  Add new radiant section Both these options are extremely expensive www.heatflux.com Process Feed In Process Feed Out Waste Heat Recovery Unit 1,600°F 750°F 250°F 750°F 1000°F
  • 8. Conventional Approach to Increasing Capacity  Extend radiant cell and add more radiant coils & burners  Provide additional radiant cells with new coils and burners H-20 H-21 H-22 H-20 (NEW) H-21 (NEW) H-21 (NEW) H-20 H-21 H-22 www.heatflux.com
  • 9. Drawbacks of Conventional Approach Real estate requirement New burners & associated changes New civil foundation work Higher firing rates Draft limitation Very High cost www.heatflux.com
  • 10. Split Flow* Fired Heater www.heatflux.com10 *Patented Feed In Feed Out 450 °F 600 °F Radiant Section Convection Section - I 1,650 °FFlue gas 3,200 °FFlue gas 1,650 °FFlue gas 500 °F Convection Section- II 750 °FFlue gas Flue gas Flue gas Split Flow in Split Flow out 450 °F 600 °F 500 °F
  • 11. Reformer Heater - Split Flow Radiant Section  Parallel Passes  Heat 70% of process feed Convection Section  Heat 30% of Process Feed  Waste heat recover • HC Reboiler • Steam Generation Service  Pressure drop is maintained 11 Process Feed In Process Feed Out Split Flow in Split Flow Out Waste Heat Recovery Unit 1,600°F 1,100°F 250°F 400°F
  • 12. Reformer Heater – Flexible Split Flow Radiant Section  Parallel Passes  Heat 70% + of process feed Convection Section  Heat up to 30% of Process Feed  Waste heat recovery • HC Reboiler • Steam Generation Service Pressure drop is kept same even at increased charge rate. www.heatflux.com Split Flow with Flexibility
  • 13. Split Flow Technology - Advantages Low Cost Solution for:  Increasing Capacity  Improving Efficiency Lower Pressure Drop Lower Revamping Cost Flexible Operation  Maximum Process Duty  Maximum Steam Generation www.heatflux.com
  • 14. Case Study 1 Three stage catalytic reformer ( reactor) unit First cell – Feed heater, Rest 3 cells- interheater Feed- Mixture of Naphtha and Recycle gas Inlet Temperature- 842-990 °F Outlet Temperature-1010 °F Inlet Pressure-231 psig Outlet Pressure- 228 psig Pressure drop /stage- 3 psi www.heatflux.com
  • 15. Revamp Objectives Improve Efficiency  Stack temperature was 1100 ºF  No steam generation  No air preheater Gas prices touched $10/MSCF www.heatflux.com
  • 16. Arrangement - Original Heater Process flow before revamp StackStackStack Stabilizer Btms Stabilizer Btms Stripper Btms Stripper Btms To Plat. RX To Plat. RX From Plat. RX. To Plat. RX From Plat. RX Stripper Btms From Plat. RX To Plat. RX Stripper Btms BURNERS 428°F 840°F 459°F 1010°F www.heatflux.com
  • 17. Reformer Heater Conventional Revamp Increase heat transfer surface in convection section Pressure drop – more than twice of existing Large size piping requirement Larger convection sections Increased stack height High cost ($6 Million) Reformer Heater www.heatflux.com
  • 18. Split-Flow Arrangement Split Flow Technology Design StackStackStack Burners #1 In #1 Out In #2 In #2 Out #3 In #3 Out #4 In #4 Out In Out Out www.heatflux.com
  • 19. Heater Data Comparison Heater after revamp Reformer Heater Data Comparison Item Units Before After Capacity BPD 18,500 24,000 Heat Duty MMBtu/hr 158 194.5 Heat release MMBtu/hr 234 225 Stack temp. °F 1,092 478 Efficiency % 67.5 86.6 Fuel savings $/annum 5.8 Million www.heatflux.com
  • 20. Case Study-2 Process heating-all Radiant Steam Generation in Convection Natural Draft Firing rates were very high Heater efficiency lower than design value by 10% to 15% Stack temperature -650℉ (320 ℉ higher than design) www.heatflux.com
  • 21. Radiant Section 3 Cells 52/56/48 tubes in cells 1/2/3 P22 tubes Inverted U tubes Single fired design Bottom inlet/outlet 2.5 inch tubes at 5 inch pitch Total -23 Burners (7 , 9 and 7 in cell 1/2/3) www.heatflux.com
  • 22. Convection Section Steam Generator Bank BFW Preheater Bank Steam Generation: 53,650 lbs/hr@300 psig 8 tubes per row Eleven rows Two future rows www.heatflux.com
  • 23. Revamp Objectives Increase heater capacity from 12,000 to 18,000 BPD Improve thermal efficiency Maintain NOx emissions Improve Reliability www.heatflux.com
  • 24. Proposed Process Heat Duties (MMBtu/hr) at 18000 BPD Heater Section Existing Heat Duty Proposed Duty Extra Duty Required 70-H-1 27.7 37.5 9.8 70-H-2 33.4 44.7 11.3 70-H-3 22.9 30.9 8.0 Stem Gen. 51.6 47.8 - Total Process 84 113.1 29.1 www.heatflux.com
  • 25. Split Flow for 70-H-1/70-H-2/70-H-3 70-H-1- 2 Bare Rows 70-H-2- 2 Finned Rows 70-H-3 – 2 Finned Rows TFG = 1,717℉ TFG = 1,300℉ TFG = 350℉ TFG = 1,717℉www.heatflux.com
  • 26. Final Revamp – Split Flow Control Scheme www.heatflux.com
  • 27. Proposed Revamp Solution Lower Pressure drop in all heaters  Allowable : 5 psi  Calculated : 2-4 psi No Modification to existing Radiant cells Reduced Average Heat Flux Lower Firing Rate – 180 MMBtu /hr Lower Volumetric Heat Release More efficient system - 89% Flexibility to increase duty further www.heatflux.com
  • 28. Flexible Split Flow Technology www.heatflux.com
  • 29. Proposed Scheme Advantages 25-30% process feed of Cells 1 & 2 is heated in split flow coils Heater to be operated at two modes:  Normal operation/Maximum process absorbed duties  Dry run operation/Maximum steam generation To maximize steam production, process absorbed duties reduced Split flow coils are run dry to shift convection heat duties for steam generation It gives flexibility in steam production and process duties as per requirement No change in firing rates www.heatflux.com
  • 30. General Advantages of FIS Flexible Split Flow Technology Improved Capacity and Flexible Operation Higher Efficiency Lower Pressure Drop (process) Lower Firing Rate Lower Fire Box Temperatures Lower Radiant Heat Fluxes Lower TMT Lower Turnaround Time Lower Installation Cost www.heatflux.com www.heatflux.com
  • 31. Furnace Improvement Services Inc. Low Cost Solutions for Fired Heaters and Boilers 1600 Hwy 6 South Ste. 480 Sugar Land, TX 77479 Tel: (281) 980-0325 www.heatflux.com Thank you very much. Questions and Comments are welcome.