SlideShare a Scribd company logo
1
Prepared By:
Mr.Premanand Desai L/EE
B.L.D.E.A’s SHREE SANGANABASAVA
MAHA SWAMIJI POLYTECHNIC,
VIJAYAPUR-03
E-mail ID:ssmp.premananddesai@bldea.org
cell no : +91 7892881829
COURSE & CODE: ELECTRICAL ESTIMATION AND COSTING (15EE54T)
UNIT - 06
TRANSMISSION LINES AND SUBSTATIONS
2
COURSE & CODE: ELECTRICAL ESTIMATION AND COSTING (15EE54T)
UNIT - 06
TRANSMISSION LINES AND SUBSTATIONS
6.0 Transmission line:
The line bringing electrical supply from generating stations to secondary substations is called
transmission lines.
Examples - 400KV, 220KV, 110KV, 66KV, etc.
6.1 Code of practice for Transmission lines:
1) Preliminary surveying is carried out with respect to the following aspects to plot the toposheet.
i) The transmission line is to be taken along the road as far as possible to facilitate easy
transportation, maintenance and repair.
ii) Transmission lines are not to be taken on hill top to avoiding lightning effect.
iii) Lines to be drawn in straight path as far as possible to avoid excess of materials.
2) Minimum clearance (6.096 Meter) from conductor to ground must be kept according to IE rules.
3) Double insulator strings and guarding are to be provided in case of road crossing crossings,
railway, telephone line, highway, canal and river crossings, etc.
4) Conductor should be having high tensile strength in order to withstand mechanical load.
5) Towers should be having high mechanical strength to withstand the weight of the conductor,
insulators and high velocity wind load.
6) Continuous wire should be run on top of the towers for earthing in order to protect the
transmission line against the lightning discharge.
7) Phase plates, number plates, anti-climbing devices and danger boards should be provided for
each tower.
6.2 Images of Transmission line materials
Armoring rods Vibration dampers
Phase Plate Jumpers Parallel groove clamps
Suspension clamps Tension clamps Anti-climbing devices Arching horns
3
6.3 Transmission line materials
1. Towers : Lattice steel or painted or galvanised steel materials used for fabrication of towers. The
height of the line voltage length of the span and legs of the towers are set in special concrete
foundations.
Mainly there are two types of towers - 1.Tangent , 2.Anchor Towers.
1.Tangent Towers (suspension towers) :
These are straight line towers and are called as A type towers or suspension towers. The angle
of deviation is zero degree. They are withstanding vertical load.
2.Anchoring towers:
These are the deviation towers, starting or dead end towers. They are also called as B, C and
D type towers. Which are installed at an angle of deviation from 0 to 30 degree, 30 to 60
degree and 60 to below 90 degree respectively. These towers are withstanding the horizontal
load. Four pole structures are used at an angle exactly 90 degree deviation.
Extension Piece : Extension piece of fabricated steel structure of 3 meter or 6 meter may be used in
order to achieve the minimum clearance to ground as per I.E. rule.
Span Length:
1. 66KV line – 220m to 260m
2. 110KV line – 260m to 330m
3. 220KV line – 330m to 360m
Approximate height and weight of towers:
Sl.No. Line
Voltage
Height in
meters
Weight in Tons
Tangent Tower Anchor Tower
1 66KV 24 2 tons 3 tons
2 110KV 24 3.5 tons 4.5 tons
3 220KV 26 4 tons 5 tons
No. of 15KV disc insulators and their breaking strength:
Sl.No. Line
Voltage
No. of 15KV disc insulators Breaking
strength
Tangent Tower Anchor Tower
1 66KV 4Nos. 5 Nos. 70 KN
2 110KV 7Nos. 8 Nos. 90 KN
3 220KV 14Nos. 15 Nos. 120 KN
2. Types of conductor and their size:
Sl. No. Type of conductor size Application
1 Coyote Conductor 26/2.54mm + 7/1.9mm 66KV Line
2 Lynx Conductor 30/7/2.79mm 110KV Line
3 Drake Conductor 30/7/4.27mm 220KV Line
3. Armouring rods:
They consist of aluminium round rods of short length. These are wrapped around A.C.S.R conductors
at the point of support. It protects the A.C.S.R conductors from possible damage from vibration of
conductors due to high velocity wind action and tightening the clamps at the point of support.
4. Vibration dampers:
These are used to prevent occurrence of resonant vibration due to high velocity wind action.
Occasionally it has been found resulting in breaking of conductor strands at the point of support.
4
5.Arching horns:
These are placed near the ends of the insulator strings and connected to earth. This regulates the
potential gradient across the strings and takes care of the arc of the flash over. These are provided for
protection of insulators.
6. Numbering plates:
All the towers are fixed with number plate to find out the faulted place(distance) by means of
toposheet.
7. Phase plates:
These are fixed to each tower for indication the red yellow and blue phases.
8. Bolt and Nuts:
Standard bolt and nuts are used, common in size from 25mm to 225mm length and 16mm thickness.
9. Bird guards:
To avoid sitting of birds on supports, a stick of ebonite plate with zig zag cutting on top. It is fixed near
the insulator on the cross arms to prevent flash over between cross arm and conductor.
10.Parallel groove clamps:
These clamps are used for electrical connections between two conductors.
11. Suspension clamps:
These are used with arcing horns for holding insulator discs for suspension type or A type Towers.
12. Tension clamps:
These are provided with all types of anchoring towers (B,C and D type) to hold the group of disc
insulators with arching horns.
13. Danger boards:
A danger plate is provided for each tower as a warning measure indicating the working voltage, the
word DANGER and also bone and skull symbols. It is provided at a height of 3m from the ground level.
14. Anti-climbing devices:
GI Barbed wire is wrapped around the tower legs at a height of 2.5m from the ground level for at least
1m length. This is to prevent climbing of unauthorized persons.
15. Other accessories:
Such as Al paint, twisting joints, tubular compression joints, repair sleeves, etc.
5
6.4 Single circuit and double circuit transmission lines.
In single circuit transmission line three conductors corresponding to three phases i.e., R Y B phases
are run on the transmission towers.
Where as in double circuit transmission line total six conductors are provided to make two different
transmission circuits. Each circuit consisting of three conductors corresponding to three phases. This
method of transmission enables the transfer of more power over a particular distance. It is cheaper
and requires less conductor materials less land.
Suspension type insulators Strain string insulators
6
6.5 Method of calculating the quantity of transmission line materials:
1. Number of spans =
length of proposed line in meters
span length in meters
2. Total number of four legged fabricated steel structures = No. of spans +1
3. Number of anchoring towers=
Total number of towers
10
(assuming every 10th
tower is to be an anchoring)
4. Number of suspension towers = Total number of towers – Number of anchoring towers
5.Total weight of the towers= ( Total no. of suspension towers X weight of each
suspension towers) + ( Total no. of anchoring towers X weight of each anchoring towers)
6. Number of 15KV disc insulators
i. At suspension string for tangent towers
= Number of suspension towers X No of suspension strings/ tower X No of insulator/ suspension
string.
ii. At tension string for anchoring towers
= Number of anchoring towers X Number of tension strings/ tower X No of insulator / tension
string.
Total no. of disc insulators = (i+ii)
Add 5% breakage on total
7. Length of ACSR conductor allowing 3% sag = (total length of the line X No.of conductor) X 1.03
8. Length of the GI ground wire of size 7/3.15mm allowing 3% sag
= ( Total length of the line X no of ground wire) X 1.03
9. No. of suspension clamps for suitable conductor with arcing horns
= Total no of towers × No. of suspension strings/tower.
10. No of tension clamps for suitable conductor with arcing horns
= Total no of anchoring towers X No of tension strings/tower.
11. Armouring rods for suitable conductor = No of suspension clamps + No of tension clamps
12. PG clamps for suitable conductor
= No of anchoring towers X No of jumpers / tower X No of PG clamps / jumpers
13. Vibration dampers for suitable conductor = Total no of towers x 6 ( for single circuit)
14. Grounding materials including accessories = Total no of towers
15. Cement concrete for tower erection = Total no of towers X 12m3
16. Miscellaneous materials such as conductor accessories, ant climbing devices, danger
boards, phase plates, no. plates, bird guards, bolt nuts, and other unfortunate items.
7
6.6 Examples :
1. Prepare the quantity of materials required for running a 80km long 66kv single circuit
transmission line across a jungle terrain using four legged fabricated steel structures weighing
approximately 2 tones. Assume a span length of 300m. The conductor used is coyote ACSR.
Solution:
a) No. of spans =
length of proposed line in meters
span length in meters
=
80000
300
= 266.66 = 267 Nos.
b) Total no. of four legged fabricated steel structures = No. of spans +1
= 267+1=268 nos.
c) No. of anchoring towers, Assuming every 10th tower is to anchoring
=
Total No.of Towers
10
=
268
10
= 26.8 = 27 Nos.
Total No. of anchoring towers =27+1 at starting point = 28 nos.
d) No. of suspension towers = Total no. of towers – No. of anchoring towers
= 268-28 = 240 nos.
e) Total weight of the towers
= ( Total no. of suspension towers X weight of each suspension towers) + ( Total no. of
anchoring towers X weight of each anchoring towers)
= (240 X 2) + (28 X 2) = 536 Tones
f) No. of 15KV disc insulators, 70 KN grade,
i) At suspension string for tangent towers
= No.of suspension towers X No. of suspension strings/tower X No of insulator/suspension string.
= 240 X 3 X 4 = 2880 Nos.
ii) At tension string for anchoring towers
= No. of anchoring towers X No. of tension strings/tower X No of insulator/tension string.
= 28 X 6 X 5 = 840 nos.
Total no. of disc insulators= 2880+840 = 3720 nos.
Add 5% extra for breakage on total, i.e.,= 3720 X 0.05 = 186 nos.
Grand total = 3720 + 186 = 3906 nos.
g) Length of coyote ACSR conductor allowing 3% sag
= (Total length of the line in km X No. of conductor) X 1.03
= 80 X 3 X 1.03
= 247.2 = 248 kms
h) Length of the GI ground wire of size 7/3.15mm allowing 3% sag
= (Total length of the line in km X No.of ground wires) X 1.03
= 80 X 1 X 1.03 = 82.4 = 83 kms
i) Number of suspension clamps suitable for coyote conductor with arcing horns
= Total No. of suspension towers X No of suspension strings/tower.
= 240 X 3 = 720 sets
j) Number of tension clamps suitable for coyote conductor with arcing horns
8
= Total no of anchoring towers X No of tension strings/tower.
= 28 X 6 = 168 sets.
k) Armoring rods suitable for coyote conductor
= No of suspension clamps + No of tension clamps
= 720 + 168 = 888 sets.
l) PG clamps suitable for coyote conductor
= No of anchoring towers X No of jumpers / tower X No of PG clamps / jumpers
= 28 X 3 X 2 = 168 nos.
m) Vibration dampers suitable for coyote conductor
= Total no of towers x 6 (for single circuit)
= 268 X 6 = 1608 nos.
n) Grounding materials including accessories = Total no of towers = 268 sets
o) Cement concrete for tower erection( 1:2:4) = Total no of towers X 12m3
= 268 X 12 = 3216 m3
p) Miscellaneous materials such as conductor accessories, ant climbing devices, danger boards,
phase plates, no. plates, bird guards, bolt nuts, and other unfortunate items.
2) Prepare a quantity of materials required for 60km, 110kv single circuit transmission line
across a jungle terrain using four legged fabricated steel structures.
Solution:
(Assuming Lynx ACSR conductor has to used and span length is 320m)
a) No. of spans=length of proposed line in meters/span length in meters = 60,000/320 = 188 nos
b) Total no. of four legged fabricated steel structures= No. of spans +1 = 188 + 1 = 189 nos.
c) No. of anchoring towers(Assuming every 10th tower is to be an anchoring)
= Total no.of towers /10
=189/10 = 19 nos
Total no of anchoring towers = 19 + 1 at starting point = 20 nos.
d) No. of suspension towers = total no. of towers – No. of anchoring towers
= 189 - 20 = 169 nos.
e) Total weight of the towers= ( Total no. of suspension towers X weight of each
suspension towers) + (Total no. of anchoring towers X weight of each anchoring towers)
= (169 X 3.5) +(20 X 4.5) = 682 Tons
f) No of 15KV disc insulators, 90 KN grade.
i) At suspension string for tangent towers=No of suspension towers X No of suspension
strings/tower X No of insulator / suspension string.
= 169 X 3 X 7 = 3549 nos.
ii) At tension string for anchoring towers=No of anchoring towers X No of
tension strings/ tower X No of insulator / tension string.
= 20 X 6 X 8 = 960 nos.
9
Total no. of disc insulators = 3549 + 960 = 4509 nos.
Add 5% extra for breakage on total i.e., = 4509 X 0.05 = 225nos
Grand total no. of disk insulator = 4509 + 225 = 4734 nos.
g) Length of lynx ACSR conductor allowing 3% sag = (total length of the line in km X
no of conductor) X 1.03
= 60 X 3 X 1.03 = 185.4 km = 186km
h) Length of the GI ground wire of size 7/3.15mm allowing 3% sag = (total length of the
line in km X no of ground wire) X 1.03
= 60 X 1 X 1.03 =61.8 = 62km
i) No of suspension clamps suitable for Lynx conductor with arcing horns = Total no of
suspension towers X No of suspension strings/tower.
= 169 X 3 = 507 sets
j) No of tension clamps suitable for Lynx conductor with arcing horns = Total no of
anchoring towers X No of tension strings/tower.
= 20 X 6 = 120 sets
k) Armoring rods suitable for Lynx conductor = No of suspension clamps + No of tension
clamps
= 507 + 120 = 627 sets
l) PG clamps suitable for Lynx conductor = No of anchoring towers X No of jumpers /
tower X No of PG clamps / jumpers
= 20 X 3 X 2 = 120
m) Vibration dampers suitable for Lynx conductor = Total no of towers x 6 ( for single
circuit)
= 189 X 6 = 1134 sets
n) Grounding materials including accessories = Total no of towers = 189 sets
o) Cement concrete for tower erection = Total no. of towers X 12m3
= 189 X 12 = 2268 m3
p) Miscellaneous materials such as conductor accessories, ant climbing devices, danger
boards, phase plates, no. plates, bird guards, bolt nuts, and other unfortunate items.
10
3) Prepare a detailed quantity of materials required for running a 120km, 220kv single circuit
transmission line across a jungle terrain using four legged fabricated steel structures. Assuming
average span length of 330m and conductor used is Drake ACSR.
Solution:
a) No. of spans = length of proposed line in meters/span length in meters
=120,000/330 = 363.6 = 364 nos.
b) Total no. of four legged fabricated steel structures = No. of spans +1
= 364 + 1= 365 nos
c) No. of anchoring towers(assuming every 10th tower is to be an anchoring)
= Total no. of towers /10
= 365/10 =36.5 nos = 37 nos
Total no of anchoring towers = 37 + 1 at starting point = 38
d) No. of suspension towers = Total no. of towers – No. of anchoring towers
= 365 – 38 = 327 nos.
e) Total weight of the towers= ( Total no. of suspension towers X weight of each
suspension towers) + ( Total no. of anchoring towers X weight of each anchoring towers)
= (327 X 4) +(38 X 5) = 1308 + 190 = 1498 Tons
f) No of 15KV disc insulators
i) At suspension string for tangent towers
=No of suspension towers X No of suspension strings/ tower X No of insulator / suspension string.
= 327 X 3 X 14 = 13734 nos.
ii) At tension string for anchoring towers
= No of anchoring towers X No of tension strings/ tower X No of insulator / tension string.
= 38 X 6 X 15 = 3420 nos.
Total no. of disc insulators=(13734 + 3420) = 17154 nos.
Add 5% extra for breakage on total, i.e.,=17154 X 0.05 = 858 nos.
g) Length of ACSR conductor allowing 3% sag
= (Total length of the line in km X no of conductor) X 1.03
= 120 X 3 X 1.03 = 371 km.
h) Length of the GI ground wire of size 7/3.15mm allowing 3% sag
= (Total length of the line in km X no of ground wire) X 1.03
= 120 X 1 X 1.03 = 124 km.
i) No. of suspension clamps suitable for Drake conductor with arcing horns
= Total no of suspension towers X No of suspension strings/tower.
= 327 X 3 = 981 sets.
j) No. of tension clamps suitable for Drake conductor with arcing horns
= Total no of anchoring towers X No of tension strings/tower.
= 38 X 6 = 228 sets.
11
k) Armoring rods suitable for Drake conductor
= No of suspension clamps + No of tension clamps
= 981+228= 1209 sets.
l) PG clamps suitable for Drake conductor
= No of anchoring towers X No of jumpers / tower X No of PG clamps / jumpers
= 38 X 3 X 2 = 22 nos.
m) Vibration dampers suitable for Drake conductor
= Total no of towers x 6 ( for single circuit)
= 365 x 6 = 2190 sets.
n) Grounding materials including accessories = Total no of towers = 365 sets.
o) Cement concrete for tower erection = Total no of towers X 12m3
= 365 X 12 = 4380 m3
p) Miscellaneous materials such as conductor accessories, ant climbing devices, danger boards,
phase plates, no. plates, bird guards, bolt nuts, and other unfortunate items.
12
6.7 SUB STATION:
A substation receives electrical power from generating stations through incoming transmission
lines and delivers electrical power through outgoing transmission lines. The electrical substation
is the part of a power system in which the voltage is transformed from high to low or low to high
for transmission, distribution, transformation and switching. The power transformer, circuit
breaker, bus-bar, insulator, lightning arrester are the main components of an electrical
substation.
6.7.1 - Single line diagram of 66/11KV, 5 MVA substation:
6.7.2 - Materials required for 66/11kV, 5MVA substations with specifications:
Example : Prepare a quantity of materials required for establishing a substation of capacity
5MVA, 66/11kv transformer. Assuming current market rates and as per K.P.T.C.L procedure.
Solution:
(Assuming two incoming lines as in above single line diagram)
Equipment’s on primary (66kv) side:
a) Lightning arresters metal oxide type, 66kv class
= 4 sets ( 2 for bus coupler and 2 for transformer)
b) Potential transformers 66kv class = 4 sets ( 2 for line and 2 for Bus bars)
c) Current transformers 800:1 ratio = 5 sets ( 2 for i/c line, 2 for o/g line, 1 for bus coupler) &
Current transformers 200:1 ratio = 2 sets ( 1 for each transformer)
d) Upright Isolators (G.O.S) double blade 800A, 66kv class with earth switch
= 4 sets (2 for i/c and 2 for o/g line)
13
e) Upright Isolators (G.O.S) double blade 800A, 66kv class without earth switch
= 14 sets (2 for bus coupler and 12 for bus bars)
f) Circuit breakers SF6 type, 66kv class
= 7 sets (2 for i/c line, 2 for o/g line, 2 for Transformers and 1 for bus coupler)
g) Bus bars expansion type using ACSR conductor = 2 sets.
h) Transformers 5MVA, 66/11kv, with OLTC and all accessories = 2 sets
i) Control and Relay panels for 66kv lines = 4 sets ( 2 for i/c line and 2 for o/g line)
j) Control and Relay panels for Transformers = 2 sets ( 1set for each transformer)
k) Control and Relay panels for bus coupler = 1 set.
l) Power and control cables in between different equipment’s and control and relay panels
= lump sum in meters
m) G.I mounting structures for mounting different equipment’s = lump sum in metric tonnes
Equipment’s on secondary side (11kv):
a) 11kv , 1200A outdoor switch gear with breaker, CT, PT etc., = 6 sets
b) G.O.S 11kv, 400A double blade = 6 sets (for outgoing 11kv lines)
c) Lightning arresters 11kv, thyrite type = 6 sets (for outgoing 11kv lines)
d) Distribution transformer for station auxiliary supply 100 KVA, 11KV / 440V = 1 set
e) Underground cable of size 1X1000mm2 from transformer to 11kv switch gear
= lumpsum in meters
f) Underground cable of size 3X250mm2 from outdoor switch gear take off structure
= lumpsum in meters
g) Take off structures 9m long double pole structure = 6 sets
h) 110V, 60AH, batteries with batteries charger = 2 sets
i) Earth mat including pipe earthing and plate earthing = lump sum
j) LT AC panel board indoor type =1 set
k) Outdoor type AC distribution boards = lumpsum
l) DC distribution board indoor type = 1 set
m) Miscellaneous materials such as ACSR conductors, 15kv disc insulators, stain insulators,
different types of clamps, bolt nuts, fire extinguishers, name plates, danger boards and other
unfortunate items.

More Related Content

What's hot

Traction system
Traction systemTraction system
Traction system
atul giri
 
Sag and tension
Sag and tensionSag and tension
Sag and tension
rajendrachoudhary123
 
Classification of transmission lines
Classification of transmission linesClassification of transmission lines
Classification of transmission lines
HamzaAbbas43
 
Substation
SubstationSubstation
Substation
AbassKhan
 
Ehv substation
Ehv substationEhv substation
Ehv substation
Demsew Mitiku
 
Overhead railway traction
Overhead railway tractionOverhead railway traction
Overhead railway traction
Probodh Mallick
 
Electrical Transmission Tower: Types, Design and Parts
Electrical Transmission Tower: Types, Design and  PartsElectrical Transmission Tower: Types, Design and  Parts
Electrical Transmission Tower: Types, Design and Parts
Dr.Raja R
 
Chapter 4 mechanical design of transmission lines
Chapter 4  mechanical design of transmission linesChapter 4  mechanical design of transmission lines
Chapter 4 mechanical design of transmission lines
firaoltemesgen1
 
report on electrical wiring
report on electrical wiringreport on electrical wiring
report on electrical wiring
Abhidada123
 
Sag calculation
Sag calculationSag calculation
Sag calculation
Darshil Shah
 
Sag in overhead transmission line, sag calculation & string chart
Sag in overhead transmission line, sag   calculation & string chartSag in overhead transmission line, sag   calculation & string chart
Sag in overhead transmission line, sag calculation & string chart
vishalgohel12195
 
Electricity distribution system in india
Electricity distribution system in indiaElectricity distribution system in india
Electricity distribution system in india
Jasgt Singh
 
EHVAC TRANSMISSION LINE MAINTENANCE TECHNIQUES IN INDIAN PERSPECTIVE-A REVIEW
EHVAC TRANSMISSION LINE MAINTENANCE TECHNIQUES IN INDIAN PERSPECTIVE-A REVIEWEHVAC TRANSMISSION LINE MAINTENANCE TECHNIQUES IN INDIAN PERSPECTIVE-A REVIEW
EHVAC TRANSMISSION LINE MAINTENANCE TECHNIQUES IN INDIAN PERSPECTIVE-A REVIEW
Dr. Babasaheb Ambedkar Technological University
 
Transmission and distribution system of nepal
Transmission and distribution system of nepalTransmission and distribution system of nepal
Transmission and distribution system of nepal
Bishal Rimal
 
Conductors used in transmission line
Conductors used in transmission lineConductors used in transmission line
Conductors used in transmission line
Sourabh sharma
 
Overhead Electrification
Overhead Electrification Overhead Electrification
Overhead Electrification
Suresh Sunny
 
UNIT - 05 DISTRIBUTION LINES AND TRANSFORMER CENTRE
UNIT - 05 DISTRIBUTION LINES AND TRANSFORMER CENTREUNIT - 05 DISTRIBUTION LINES AND TRANSFORMER CENTRE
UNIT - 05 DISTRIBUTION LINES AND TRANSFORMER CENTRE
PremanandDesai
 
Electrical transmission line
Electrical transmission lineElectrical transmission line
Electrical transmission line
Dhananjay Jha
 
Acsr moose conductor
Acsr moose conductorAcsr moose conductor
Acsr moose conductorDineshsenthil
 

What's hot (20)

Traction system
Traction systemTraction system
Traction system
 
Sag and tension
Sag and tensionSag and tension
Sag and tension
 
Classification of transmission lines
Classification of transmission linesClassification of transmission lines
Classification of transmission lines
 
Substation
SubstationSubstation
Substation
 
Types of-tower
Types of-towerTypes of-tower
Types of-tower
 
Ehv substation
Ehv substationEhv substation
Ehv substation
 
Overhead railway traction
Overhead railway tractionOverhead railway traction
Overhead railway traction
 
Electrical Transmission Tower: Types, Design and Parts
Electrical Transmission Tower: Types, Design and  PartsElectrical Transmission Tower: Types, Design and  Parts
Electrical Transmission Tower: Types, Design and Parts
 
Chapter 4 mechanical design of transmission lines
Chapter 4  mechanical design of transmission linesChapter 4  mechanical design of transmission lines
Chapter 4 mechanical design of transmission lines
 
report on electrical wiring
report on electrical wiringreport on electrical wiring
report on electrical wiring
 
Sag calculation
Sag calculationSag calculation
Sag calculation
 
Sag in overhead transmission line, sag calculation & string chart
Sag in overhead transmission line, sag   calculation & string chartSag in overhead transmission line, sag   calculation & string chart
Sag in overhead transmission line, sag calculation & string chart
 
Electricity distribution system in india
Electricity distribution system in indiaElectricity distribution system in india
Electricity distribution system in india
 
EHVAC TRANSMISSION LINE MAINTENANCE TECHNIQUES IN INDIAN PERSPECTIVE-A REVIEW
EHVAC TRANSMISSION LINE MAINTENANCE TECHNIQUES IN INDIAN PERSPECTIVE-A REVIEWEHVAC TRANSMISSION LINE MAINTENANCE TECHNIQUES IN INDIAN PERSPECTIVE-A REVIEW
EHVAC TRANSMISSION LINE MAINTENANCE TECHNIQUES IN INDIAN PERSPECTIVE-A REVIEW
 
Transmission and distribution system of nepal
Transmission and distribution system of nepalTransmission and distribution system of nepal
Transmission and distribution system of nepal
 
Conductors used in transmission line
Conductors used in transmission lineConductors used in transmission line
Conductors used in transmission line
 
Overhead Electrification
Overhead Electrification Overhead Electrification
Overhead Electrification
 
UNIT - 05 DISTRIBUTION LINES AND TRANSFORMER CENTRE
UNIT - 05 DISTRIBUTION LINES AND TRANSFORMER CENTREUNIT - 05 DISTRIBUTION LINES AND TRANSFORMER CENTRE
UNIT - 05 DISTRIBUTION LINES AND TRANSFORMER CENTRE
 
Electrical transmission line
Electrical transmission lineElectrical transmission line
Electrical transmission line
 
Acsr moose conductor
Acsr moose conductorAcsr moose conductor
Acsr moose conductor
 

Similar to UNIT - 06 TRANSMISSION LINES AND SUBSTATIONS

SOUMADIP-FACT.pptx
SOUMADIP-FACT.pptxSOUMADIP-FACT.pptx
SOUMADIP-FACT.pptx
SOUMADIPGHARA
 
Extra High voltage AC transmission line.pptx
Extra High voltage AC transmission line.pptxExtra High voltage AC transmission line.pptx
Extra High voltage AC transmission line.pptx
AnirbanSarkar943417
 
Installation, testing and jointing of lt and ht power cables up to 33 kv
Installation, testing and jointing of lt and ht power cables up to 33 kvInstallation, testing and jointing of lt and ht power cables up to 33 kv
Installation, testing and jointing of lt and ht power cables up to 33 kv
Alexander Decker
 
Sonali ppt.pptx
Sonali ppt.pptxSonali ppt.pptx
Sonali ppt.pptx
RBTV1
 
Analysis and Design of Power Transmission Lines Steel Towers.docx
Analysis and Design of Power Transmission Lines Steel Towers.docxAnalysis and Design of Power Transmission Lines Steel Towers.docx
Analysis and Design of Power Transmission Lines Steel Towers.docx
Adnan Lazem
 
Electrical Design of Overhead Lines.ppt
Electrical Design of Overhead Lines.pptElectrical Design of Overhead Lines.ppt
Electrical Design of Overhead Lines.ppt
AkdDeshmukh
 
Transmission Line presentation______.ppt
Transmission Line presentation______.pptTransmission Line presentation______.ppt
Transmission Line presentation______.ppt
ssuserc3b807
 
Akt tl design01
Akt tl design01Akt tl design01
Akt tl design01
Dr Ashok Tiwari
 
01 guidelines for electrical work ace 9632136976
01 guidelines for electrical work ace 963213697601 guidelines for electrical work ace 9632136976
01 guidelines for electrical work ace 9632136976
Southern Railway
 
Case study sterlite deadend grip
Case study  sterlite deadend gripCase study  sterlite deadend grip
Case study sterlite deadend grip
Harish Agarwal
 
SERVICE MAINS.pdf
SERVICE MAINS.pdfSERVICE MAINS.pdf
SERVICE MAINS.pdf
vaasuchetu
 
main content
main contentmain content
main contentRaj Kumar
 
Distribution system 2
Distribution system  2Distribution system  2
Distribution system 2
Engr Numan Sarwar
 
Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...
Rajesh Prasad
 
Basics of electrical engineering
Basics of electrical engineeringBasics of electrical engineering
Basics of electrical engineering
Nishkam Dhiman
 
Analysis-And-Design-Of-220kv-Transmission-Line-Tower-In-Different-Zones-I-&-V...
Analysis-And-Design-Of-220kv-Transmission-Line-Tower-In-Different-Zones-I-&-V...Analysis-And-Design-Of-220kv-Transmission-Line-Tower-In-Different-Zones-I-&-V...
Analysis-And-Design-Of-220kv-Transmission-Line-Tower-In-Different-Zones-I-&-V...Deepak Saxena
 
Supports of overhead line
Supports of overhead lineSupports of overhead line
Supports of overhead line
Shreyansha Sonwane
 
Electrical Transmission Tower Types - Design & Parts
Electrical Transmission Tower  Types - Design & PartsElectrical Transmission Tower  Types - Design & Parts
Electrical Transmission Tower Types - Design & Parts
Power System Operation
 
Calculation note suez canal cable stayed bridge
Calculation note suez canal cable stayed bridgeCalculation note suez canal cable stayed bridge
Calculation note suez canal cable stayed bridgeMohammed Abdelkawy
 

Similar to UNIT - 06 TRANSMISSION LINES AND SUBSTATIONS (20)

2581
25812581
2581
 
SOUMADIP-FACT.pptx
SOUMADIP-FACT.pptxSOUMADIP-FACT.pptx
SOUMADIP-FACT.pptx
 
Extra High voltage AC transmission line.pptx
Extra High voltage AC transmission line.pptxExtra High voltage AC transmission line.pptx
Extra High voltage AC transmission line.pptx
 
Installation, testing and jointing of lt and ht power cables up to 33 kv
Installation, testing and jointing of lt and ht power cables up to 33 kvInstallation, testing and jointing of lt and ht power cables up to 33 kv
Installation, testing and jointing of lt and ht power cables up to 33 kv
 
Sonali ppt.pptx
Sonali ppt.pptxSonali ppt.pptx
Sonali ppt.pptx
 
Analysis and Design of Power Transmission Lines Steel Towers.docx
Analysis and Design of Power Transmission Lines Steel Towers.docxAnalysis and Design of Power Transmission Lines Steel Towers.docx
Analysis and Design of Power Transmission Lines Steel Towers.docx
 
Electrical Design of Overhead Lines.ppt
Electrical Design of Overhead Lines.pptElectrical Design of Overhead Lines.ppt
Electrical Design of Overhead Lines.ppt
 
Transmission Line presentation______.ppt
Transmission Line presentation______.pptTransmission Line presentation______.ppt
Transmission Line presentation______.ppt
 
Akt tl design01
Akt tl design01Akt tl design01
Akt tl design01
 
01 guidelines for electrical work ace 9632136976
01 guidelines for electrical work ace 963213697601 guidelines for electrical work ace 9632136976
01 guidelines for electrical work ace 9632136976
 
Case study sterlite deadend grip
Case study  sterlite deadend gripCase study  sterlite deadend grip
Case study sterlite deadend grip
 
SERVICE MAINS.pdf
SERVICE MAINS.pdfSERVICE MAINS.pdf
SERVICE MAINS.pdf
 
main content
main contentmain content
main content
 
Distribution system 2
Distribution system  2Distribution system  2
Distribution system 2
 
Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...
 
Basics of electrical engineering
Basics of electrical engineeringBasics of electrical engineering
Basics of electrical engineering
 
Analysis-And-Design-Of-220kv-Transmission-Line-Tower-In-Different-Zones-I-&-V...
Analysis-And-Design-Of-220kv-Transmission-Line-Tower-In-Different-Zones-I-&-V...Analysis-And-Design-Of-220kv-Transmission-Line-Tower-In-Different-Zones-I-&-V...
Analysis-And-Design-Of-220kv-Transmission-Line-Tower-In-Different-Zones-I-&-V...
 
Supports of overhead line
Supports of overhead lineSupports of overhead line
Supports of overhead line
 
Electrical Transmission Tower Types - Design & Parts
Electrical Transmission Tower  Types - Design & PartsElectrical Transmission Tower  Types - Design & Parts
Electrical Transmission Tower Types - Design & Parts
 
Calculation note suez canal cable stayed bridge
Calculation note suez canal cable stayed bridgeCalculation note suez canal cable stayed bridge
Calculation note suez canal cable stayed bridge
 

More from PremanandDesai

Week-11 - Assembly drawing - Synchronous Motor
Week-11 - Assembly drawing -  Synchronous Motor Week-11 - Assembly drawing -  Synchronous Motor
Week-11 - Assembly drawing - Synchronous Motor
PremanandDesai
 
Week-10 - Assembly drawing - Alternators
Week-10 - Assembly drawing - AlternatorsWeek-10 - Assembly drawing - Alternators
Week-10 - Assembly drawing - Alternators
PremanandDesai
 
Week-09 - Assembly drawing-Induction Motor
Week-09 - Assembly drawing-Induction Motor Week-09 - Assembly drawing-Induction Motor
Week-09 - Assembly drawing-Induction Motor
PremanandDesai
 
Week-08 - Transformer Assembly-Threephase
Week-08 - Transformer Assembly-ThreephaseWeek-08 - Transformer Assembly-Threephase
Week-08 - Transformer Assembly-Threephase
PremanandDesai
 
Week-07- Developed Winding Diagrams - 1 phase--.pptx
Week-07- Developed Winding Diagrams - 1 phase--.pptxWeek-07- Developed Winding Diagrams - 1 phase--.pptx
Week-07- Developed Winding Diagrams - 1 phase--.pptx
PremanandDesai
 
Week-06 - Developed Winding Diagrams - 3 phase--.pptx
Week-06 - Developed Winding Diagrams - 3 phase--.pptxWeek-06 - Developed Winding Diagrams - 3 phase--.pptx
Week-06 - Developed Winding Diagrams - 3 phase--.pptx
PremanandDesai
 
Week-05 -Design a GA LT panel wiring--.pptx
Week-05 -Design a GA LT panel wiring--.pptxWeek-05 -Design a GA LT panel wiring--.pptx
Week-05 -Design a GA LT panel wiring--.pptx
PremanandDesai
 
Week-04 -Motor control Panel board
Week-04 -Motor control Panel boardWeek-04 -Motor control Panel board
Week-04 -Motor control Panel board
PremanandDesai
 
Week-03 - Electrical wiring of Residential, Hospital , small workshop
Week-03 - Electrical wiring of  Residential, Hospital , small workshopWeek-03 - Electrical wiring of  Residential, Hospital , small workshop
Week-03 - Electrical wiring of Residential, Hospital , small workshop
PremanandDesai
 
Week-02 - Single line diagram of Substations
Week-02 - Single line diagram of SubstationsWeek-02 - Single line diagram of Substations
Week-02 - Single line diagram of Substations
PremanandDesai
 
Week-01 - INTRODUCTION to CAD
Week-01  - INTRODUCTION to CADWeek-01  - INTRODUCTION to CAD
Week-01 - INTRODUCTION to CAD
PremanandDesai
 
Week- 13 - APFC , AMF & STP
Week- 13 - APFC , AMF & STP Week- 13 - APFC , AMF & STP
Week- 13 - APFC , AMF & STP
PremanandDesai
 
Week - 12 - Motor control centre (MCC)
Week - 12 - Motor control centre (MCC) Week - 12 - Motor control centre (MCC)
Week - 12 - Motor control centre (MCC)
PremanandDesai
 
Week - 11 - Metering section and Auxiliary Relays
Week  - 11 - Metering section  and Auxiliary RelaysWeek  - 11 - Metering section  and Auxiliary Relays
Week - 11 - Metering section and Auxiliary Relays
PremanandDesai
 
Week 10 - Control Panel & Power gears
Week  10 - Control Panel &  Power gearsWeek  10 - Control Panel &  Power gears
Week 10 - Control Panel & Power gears
PremanandDesai
 
Switchgear and protection - lab
Switchgear and protection - labSwitchgear and protection - lab
Switchgear and protection - lab
PremanandDesai
 
Week - 09 - Testing of CB & Substation Earthing
Week - 09 - Testing of CB & Substation Earthing Week - 09 - Testing of CB & Substation Earthing
Week - 09 - Testing of CB & Substation Earthing
PremanandDesai
 
Week- 08 - Feeder protection and Bus–Bar Protection.
Week- 08 - Feeder protection and  Bus–Bar Protection.Week- 08 - Feeder protection and  Bus–Bar Protection.
Week- 08 - Feeder protection and Bus–Bar Protection.
PremanandDesai
 
Week 07 - Alternator Protection
Week   07 - Alternator Protection Week   07 - Alternator Protection
Week 07 - Alternator Protection
PremanandDesai
 
WEEK- 06/ UNIT – 06 Transformer Protection
WEEK- 06/ UNIT – 06 Transformer Protection WEEK- 06/ UNIT – 06 Transformer Protection
WEEK- 06/ UNIT – 06 Transformer Protection
PremanandDesai
 

More from PremanandDesai (20)

Week-11 - Assembly drawing - Synchronous Motor
Week-11 - Assembly drawing -  Synchronous Motor Week-11 - Assembly drawing -  Synchronous Motor
Week-11 - Assembly drawing - Synchronous Motor
 
Week-10 - Assembly drawing - Alternators
Week-10 - Assembly drawing - AlternatorsWeek-10 - Assembly drawing - Alternators
Week-10 - Assembly drawing - Alternators
 
Week-09 - Assembly drawing-Induction Motor
Week-09 - Assembly drawing-Induction Motor Week-09 - Assembly drawing-Induction Motor
Week-09 - Assembly drawing-Induction Motor
 
Week-08 - Transformer Assembly-Threephase
Week-08 - Transformer Assembly-ThreephaseWeek-08 - Transformer Assembly-Threephase
Week-08 - Transformer Assembly-Threephase
 
Week-07- Developed Winding Diagrams - 1 phase--.pptx
Week-07- Developed Winding Diagrams - 1 phase--.pptxWeek-07- Developed Winding Diagrams - 1 phase--.pptx
Week-07- Developed Winding Diagrams - 1 phase--.pptx
 
Week-06 - Developed Winding Diagrams - 3 phase--.pptx
Week-06 - Developed Winding Diagrams - 3 phase--.pptxWeek-06 - Developed Winding Diagrams - 3 phase--.pptx
Week-06 - Developed Winding Diagrams - 3 phase--.pptx
 
Week-05 -Design a GA LT panel wiring--.pptx
Week-05 -Design a GA LT panel wiring--.pptxWeek-05 -Design a GA LT panel wiring--.pptx
Week-05 -Design a GA LT panel wiring--.pptx
 
Week-04 -Motor control Panel board
Week-04 -Motor control Panel boardWeek-04 -Motor control Panel board
Week-04 -Motor control Panel board
 
Week-03 - Electrical wiring of Residential, Hospital , small workshop
Week-03 - Electrical wiring of  Residential, Hospital , small workshopWeek-03 - Electrical wiring of  Residential, Hospital , small workshop
Week-03 - Electrical wiring of Residential, Hospital , small workshop
 
Week-02 - Single line diagram of Substations
Week-02 - Single line diagram of SubstationsWeek-02 - Single line diagram of Substations
Week-02 - Single line diagram of Substations
 
Week-01 - INTRODUCTION to CAD
Week-01  - INTRODUCTION to CADWeek-01  - INTRODUCTION to CAD
Week-01 - INTRODUCTION to CAD
 
Week- 13 - APFC , AMF & STP
Week- 13 - APFC , AMF & STP Week- 13 - APFC , AMF & STP
Week- 13 - APFC , AMF & STP
 
Week - 12 - Motor control centre (MCC)
Week - 12 - Motor control centre (MCC) Week - 12 - Motor control centre (MCC)
Week - 12 - Motor control centre (MCC)
 
Week - 11 - Metering section and Auxiliary Relays
Week  - 11 - Metering section  and Auxiliary RelaysWeek  - 11 - Metering section  and Auxiliary Relays
Week - 11 - Metering section and Auxiliary Relays
 
Week 10 - Control Panel & Power gears
Week  10 - Control Panel &  Power gearsWeek  10 - Control Panel &  Power gears
Week 10 - Control Panel & Power gears
 
Switchgear and protection - lab
Switchgear and protection - labSwitchgear and protection - lab
Switchgear and protection - lab
 
Week - 09 - Testing of CB & Substation Earthing
Week - 09 - Testing of CB & Substation Earthing Week - 09 - Testing of CB & Substation Earthing
Week - 09 - Testing of CB & Substation Earthing
 
Week- 08 - Feeder protection and Bus–Bar Protection.
Week- 08 - Feeder protection and  Bus–Bar Protection.Week- 08 - Feeder protection and  Bus–Bar Protection.
Week- 08 - Feeder protection and Bus–Bar Protection.
 
Week 07 - Alternator Protection
Week   07 - Alternator Protection Week   07 - Alternator Protection
Week 07 - Alternator Protection
 
WEEK- 06/ UNIT – 06 Transformer Protection
WEEK- 06/ UNIT – 06 Transformer Protection WEEK- 06/ UNIT – 06 Transformer Protection
WEEK- 06/ UNIT – 06 Transformer Protection
 

Recently uploaded

Palestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptxPalestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptx
RaedMohamed3
 
Introduction to Quality Improvement Essentials
Introduction to Quality Improvement EssentialsIntroduction to Quality Improvement Essentials
Introduction to Quality Improvement Essentials
Excellence Foundation for South Sudan
 
PART A. Introduction to Costumer Service
PART A. Introduction to Costumer ServicePART A. Introduction to Costumer Service
PART A. Introduction to Costumer Service
PedroFerreira53928
 
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCECLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
BhavyaRajput3
 
How to Break the cycle of negative Thoughts
How to Break the cycle of negative ThoughtsHow to Break the cycle of negative Thoughts
How to Break the cycle of negative Thoughts
Col Mukteshwar Prasad
 
Model Attribute Check Company Auto Property
Model Attribute  Check Company Auto PropertyModel Attribute  Check Company Auto Property
Model Attribute Check Company Auto Property
Celine George
 
Home assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdfHome assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdf
Tamralipta Mahavidyalaya
 
1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx
JosvitaDsouza2
 
GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...
GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...
GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...
Nguyen Thanh Tu Collection
 
Thesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.pptThesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.ppt
EverAndrsGuerraGuerr
 
Sectors of the Indian Economy - Class 10 Study Notes pdf
Sectors of the Indian Economy - Class 10 Study Notes pdfSectors of the Indian Economy - Class 10 Study Notes pdf
Sectors of the Indian Economy - Class 10 Study Notes pdf
Vivekanand Anglo Vedic Academy
 
Additional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdfAdditional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdf
joachimlavalley1
 
Supporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptxSupporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptx
Jisc
 
ESC Beyond Borders _From EU to You_ InfoPack general.pdf
ESC Beyond Borders _From EU to You_ InfoPack general.pdfESC Beyond Borders _From EU to You_ InfoPack general.pdf
ESC Beyond Borders _From EU to You_ InfoPack general.pdf
Fundacja Rozwoju Społeczeństwa Przedsiębiorczego
 
2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...
Sandy Millin
 
Unit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdfUnit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdf
Thiyagu K
 
Overview on Edible Vaccine: Pros & Cons with Mechanism
Overview on Edible Vaccine: Pros & Cons with MechanismOverview on Edible Vaccine: Pros & Cons with Mechanism
Overview on Edible Vaccine: Pros & Cons with Mechanism
DeeptiGupta154
 
The geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideasThe geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideas
GeoBlogs
 
How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...
Jisc
 
special B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdfspecial B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdf
Special education needs
 

Recently uploaded (20)

Palestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptxPalestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptx
 
Introduction to Quality Improvement Essentials
Introduction to Quality Improvement EssentialsIntroduction to Quality Improvement Essentials
Introduction to Quality Improvement Essentials
 
PART A. Introduction to Costumer Service
PART A. Introduction to Costumer ServicePART A. Introduction to Costumer Service
PART A. Introduction to Costumer Service
 
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCECLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
 
How to Break the cycle of negative Thoughts
How to Break the cycle of negative ThoughtsHow to Break the cycle of negative Thoughts
How to Break the cycle of negative Thoughts
 
Model Attribute Check Company Auto Property
Model Attribute  Check Company Auto PropertyModel Attribute  Check Company Auto Property
Model Attribute Check Company Auto Property
 
Home assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdfHome assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdf
 
1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx
 
GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...
GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...
GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...
 
Thesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.pptThesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.ppt
 
Sectors of the Indian Economy - Class 10 Study Notes pdf
Sectors of the Indian Economy - Class 10 Study Notes pdfSectors of the Indian Economy - Class 10 Study Notes pdf
Sectors of the Indian Economy - Class 10 Study Notes pdf
 
Additional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdfAdditional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdf
 
Supporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptxSupporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptx
 
ESC Beyond Borders _From EU to You_ InfoPack general.pdf
ESC Beyond Borders _From EU to You_ InfoPack general.pdfESC Beyond Borders _From EU to You_ InfoPack general.pdf
ESC Beyond Borders _From EU to You_ InfoPack general.pdf
 
2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...
 
Unit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdfUnit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdf
 
Overview on Edible Vaccine: Pros & Cons with Mechanism
Overview on Edible Vaccine: Pros & Cons with MechanismOverview on Edible Vaccine: Pros & Cons with Mechanism
Overview on Edible Vaccine: Pros & Cons with Mechanism
 
The geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideasThe geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideas
 
How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...
 
special B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdfspecial B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdf
 

UNIT - 06 TRANSMISSION LINES AND SUBSTATIONS

  • 1. 1 Prepared By: Mr.Premanand Desai L/EE B.L.D.E.A’s SHREE SANGANABASAVA MAHA SWAMIJI POLYTECHNIC, VIJAYAPUR-03 E-mail ID:ssmp.premananddesai@bldea.org cell no : +91 7892881829 COURSE & CODE: ELECTRICAL ESTIMATION AND COSTING (15EE54T) UNIT - 06 TRANSMISSION LINES AND SUBSTATIONS
  • 2. 2 COURSE & CODE: ELECTRICAL ESTIMATION AND COSTING (15EE54T) UNIT - 06 TRANSMISSION LINES AND SUBSTATIONS 6.0 Transmission line: The line bringing electrical supply from generating stations to secondary substations is called transmission lines. Examples - 400KV, 220KV, 110KV, 66KV, etc. 6.1 Code of practice for Transmission lines: 1) Preliminary surveying is carried out with respect to the following aspects to plot the toposheet. i) The transmission line is to be taken along the road as far as possible to facilitate easy transportation, maintenance and repair. ii) Transmission lines are not to be taken on hill top to avoiding lightning effect. iii) Lines to be drawn in straight path as far as possible to avoid excess of materials. 2) Minimum clearance (6.096 Meter) from conductor to ground must be kept according to IE rules. 3) Double insulator strings and guarding are to be provided in case of road crossing crossings, railway, telephone line, highway, canal and river crossings, etc. 4) Conductor should be having high tensile strength in order to withstand mechanical load. 5) Towers should be having high mechanical strength to withstand the weight of the conductor, insulators and high velocity wind load. 6) Continuous wire should be run on top of the towers for earthing in order to protect the transmission line against the lightning discharge. 7) Phase plates, number plates, anti-climbing devices and danger boards should be provided for each tower. 6.2 Images of Transmission line materials Armoring rods Vibration dampers Phase Plate Jumpers Parallel groove clamps Suspension clamps Tension clamps Anti-climbing devices Arching horns
  • 3. 3 6.3 Transmission line materials 1. Towers : Lattice steel or painted or galvanised steel materials used for fabrication of towers. The height of the line voltage length of the span and legs of the towers are set in special concrete foundations. Mainly there are two types of towers - 1.Tangent , 2.Anchor Towers. 1.Tangent Towers (suspension towers) : These are straight line towers and are called as A type towers or suspension towers. The angle of deviation is zero degree. They are withstanding vertical load. 2.Anchoring towers: These are the deviation towers, starting or dead end towers. They are also called as B, C and D type towers. Which are installed at an angle of deviation from 0 to 30 degree, 30 to 60 degree and 60 to below 90 degree respectively. These towers are withstanding the horizontal load. Four pole structures are used at an angle exactly 90 degree deviation. Extension Piece : Extension piece of fabricated steel structure of 3 meter or 6 meter may be used in order to achieve the minimum clearance to ground as per I.E. rule. Span Length: 1. 66KV line – 220m to 260m 2. 110KV line – 260m to 330m 3. 220KV line – 330m to 360m Approximate height and weight of towers: Sl.No. Line Voltage Height in meters Weight in Tons Tangent Tower Anchor Tower 1 66KV 24 2 tons 3 tons 2 110KV 24 3.5 tons 4.5 tons 3 220KV 26 4 tons 5 tons No. of 15KV disc insulators and their breaking strength: Sl.No. Line Voltage No. of 15KV disc insulators Breaking strength Tangent Tower Anchor Tower 1 66KV 4Nos. 5 Nos. 70 KN 2 110KV 7Nos. 8 Nos. 90 KN 3 220KV 14Nos. 15 Nos. 120 KN 2. Types of conductor and their size: Sl. No. Type of conductor size Application 1 Coyote Conductor 26/2.54mm + 7/1.9mm 66KV Line 2 Lynx Conductor 30/7/2.79mm 110KV Line 3 Drake Conductor 30/7/4.27mm 220KV Line 3. Armouring rods: They consist of aluminium round rods of short length. These are wrapped around A.C.S.R conductors at the point of support. It protects the A.C.S.R conductors from possible damage from vibration of conductors due to high velocity wind action and tightening the clamps at the point of support. 4. Vibration dampers: These are used to prevent occurrence of resonant vibration due to high velocity wind action. Occasionally it has been found resulting in breaking of conductor strands at the point of support.
  • 4. 4 5.Arching horns: These are placed near the ends of the insulator strings and connected to earth. This regulates the potential gradient across the strings and takes care of the arc of the flash over. These are provided for protection of insulators. 6. Numbering plates: All the towers are fixed with number plate to find out the faulted place(distance) by means of toposheet. 7. Phase plates: These are fixed to each tower for indication the red yellow and blue phases. 8. Bolt and Nuts: Standard bolt and nuts are used, common in size from 25mm to 225mm length and 16mm thickness. 9. Bird guards: To avoid sitting of birds on supports, a stick of ebonite plate with zig zag cutting on top. It is fixed near the insulator on the cross arms to prevent flash over between cross arm and conductor. 10.Parallel groove clamps: These clamps are used for electrical connections between two conductors. 11. Suspension clamps: These are used with arcing horns for holding insulator discs for suspension type or A type Towers. 12. Tension clamps: These are provided with all types of anchoring towers (B,C and D type) to hold the group of disc insulators with arching horns. 13. Danger boards: A danger plate is provided for each tower as a warning measure indicating the working voltage, the word DANGER and also bone and skull symbols. It is provided at a height of 3m from the ground level. 14. Anti-climbing devices: GI Barbed wire is wrapped around the tower legs at a height of 2.5m from the ground level for at least 1m length. This is to prevent climbing of unauthorized persons. 15. Other accessories: Such as Al paint, twisting joints, tubular compression joints, repair sleeves, etc.
  • 5. 5 6.4 Single circuit and double circuit transmission lines. In single circuit transmission line three conductors corresponding to three phases i.e., R Y B phases are run on the transmission towers. Where as in double circuit transmission line total six conductors are provided to make two different transmission circuits. Each circuit consisting of three conductors corresponding to three phases. This method of transmission enables the transfer of more power over a particular distance. It is cheaper and requires less conductor materials less land. Suspension type insulators Strain string insulators
  • 6. 6 6.5 Method of calculating the quantity of transmission line materials: 1. Number of spans = length of proposed line in meters span length in meters 2. Total number of four legged fabricated steel structures = No. of spans +1 3. Number of anchoring towers= Total number of towers 10 (assuming every 10th tower is to be an anchoring) 4. Number of suspension towers = Total number of towers – Number of anchoring towers 5.Total weight of the towers= ( Total no. of suspension towers X weight of each suspension towers) + ( Total no. of anchoring towers X weight of each anchoring towers) 6. Number of 15KV disc insulators i. At suspension string for tangent towers = Number of suspension towers X No of suspension strings/ tower X No of insulator/ suspension string. ii. At tension string for anchoring towers = Number of anchoring towers X Number of tension strings/ tower X No of insulator / tension string. Total no. of disc insulators = (i+ii) Add 5% breakage on total 7. Length of ACSR conductor allowing 3% sag = (total length of the line X No.of conductor) X 1.03 8. Length of the GI ground wire of size 7/3.15mm allowing 3% sag = ( Total length of the line X no of ground wire) X 1.03 9. No. of suspension clamps for suitable conductor with arcing horns = Total no of towers × No. of suspension strings/tower. 10. No of tension clamps for suitable conductor with arcing horns = Total no of anchoring towers X No of tension strings/tower. 11. Armouring rods for suitable conductor = No of suspension clamps + No of tension clamps 12. PG clamps for suitable conductor = No of anchoring towers X No of jumpers / tower X No of PG clamps / jumpers 13. Vibration dampers for suitable conductor = Total no of towers x 6 ( for single circuit) 14. Grounding materials including accessories = Total no of towers 15. Cement concrete for tower erection = Total no of towers X 12m3 16. Miscellaneous materials such as conductor accessories, ant climbing devices, danger boards, phase plates, no. plates, bird guards, bolt nuts, and other unfortunate items.
  • 7. 7 6.6 Examples : 1. Prepare the quantity of materials required for running a 80km long 66kv single circuit transmission line across a jungle terrain using four legged fabricated steel structures weighing approximately 2 tones. Assume a span length of 300m. The conductor used is coyote ACSR. Solution: a) No. of spans = length of proposed line in meters span length in meters = 80000 300 = 266.66 = 267 Nos. b) Total no. of four legged fabricated steel structures = No. of spans +1 = 267+1=268 nos. c) No. of anchoring towers, Assuming every 10th tower is to anchoring = Total No.of Towers 10 = 268 10 = 26.8 = 27 Nos. Total No. of anchoring towers =27+1 at starting point = 28 nos. d) No. of suspension towers = Total no. of towers – No. of anchoring towers = 268-28 = 240 nos. e) Total weight of the towers = ( Total no. of suspension towers X weight of each suspension towers) + ( Total no. of anchoring towers X weight of each anchoring towers) = (240 X 2) + (28 X 2) = 536 Tones f) No. of 15KV disc insulators, 70 KN grade, i) At suspension string for tangent towers = No.of suspension towers X No. of suspension strings/tower X No of insulator/suspension string. = 240 X 3 X 4 = 2880 Nos. ii) At tension string for anchoring towers = No. of anchoring towers X No. of tension strings/tower X No of insulator/tension string. = 28 X 6 X 5 = 840 nos. Total no. of disc insulators= 2880+840 = 3720 nos. Add 5% extra for breakage on total, i.e.,= 3720 X 0.05 = 186 nos. Grand total = 3720 + 186 = 3906 nos. g) Length of coyote ACSR conductor allowing 3% sag = (Total length of the line in km X No. of conductor) X 1.03 = 80 X 3 X 1.03 = 247.2 = 248 kms h) Length of the GI ground wire of size 7/3.15mm allowing 3% sag = (Total length of the line in km X No.of ground wires) X 1.03 = 80 X 1 X 1.03 = 82.4 = 83 kms i) Number of suspension clamps suitable for coyote conductor with arcing horns = Total No. of suspension towers X No of suspension strings/tower. = 240 X 3 = 720 sets j) Number of tension clamps suitable for coyote conductor with arcing horns
  • 8. 8 = Total no of anchoring towers X No of tension strings/tower. = 28 X 6 = 168 sets. k) Armoring rods suitable for coyote conductor = No of suspension clamps + No of tension clamps = 720 + 168 = 888 sets. l) PG clamps suitable for coyote conductor = No of anchoring towers X No of jumpers / tower X No of PG clamps / jumpers = 28 X 3 X 2 = 168 nos. m) Vibration dampers suitable for coyote conductor = Total no of towers x 6 (for single circuit) = 268 X 6 = 1608 nos. n) Grounding materials including accessories = Total no of towers = 268 sets o) Cement concrete for tower erection( 1:2:4) = Total no of towers X 12m3 = 268 X 12 = 3216 m3 p) Miscellaneous materials such as conductor accessories, ant climbing devices, danger boards, phase plates, no. plates, bird guards, bolt nuts, and other unfortunate items. 2) Prepare a quantity of materials required for 60km, 110kv single circuit transmission line across a jungle terrain using four legged fabricated steel structures. Solution: (Assuming Lynx ACSR conductor has to used and span length is 320m) a) No. of spans=length of proposed line in meters/span length in meters = 60,000/320 = 188 nos b) Total no. of four legged fabricated steel structures= No. of spans +1 = 188 + 1 = 189 nos. c) No. of anchoring towers(Assuming every 10th tower is to be an anchoring) = Total no.of towers /10 =189/10 = 19 nos Total no of anchoring towers = 19 + 1 at starting point = 20 nos. d) No. of suspension towers = total no. of towers – No. of anchoring towers = 189 - 20 = 169 nos. e) Total weight of the towers= ( Total no. of suspension towers X weight of each suspension towers) + (Total no. of anchoring towers X weight of each anchoring towers) = (169 X 3.5) +(20 X 4.5) = 682 Tons f) No of 15KV disc insulators, 90 KN grade. i) At suspension string for tangent towers=No of suspension towers X No of suspension strings/tower X No of insulator / suspension string. = 169 X 3 X 7 = 3549 nos. ii) At tension string for anchoring towers=No of anchoring towers X No of tension strings/ tower X No of insulator / tension string. = 20 X 6 X 8 = 960 nos.
  • 9. 9 Total no. of disc insulators = 3549 + 960 = 4509 nos. Add 5% extra for breakage on total i.e., = 4509 X 0.05 = 225nos Grand total no. of disk insulator = 4509 + 225 = 4734 nos. g) Length of lynx ACSR conductor allowing 3% sag = (total length of the line in km X no of conductor) X 1.03 = 60 X 3 X 1.03 = 185.4 km = 186km h) Length of the GI ground wire of size 7/3.15mm allowing 3% sag = (total length of the line in km X no of ground wire) X 1.03 = 60 X 1 X 1.03 =61.8 = 62km i) No of suspension clamps suitable for Lynx conductor with arcing horns = Total no of suspension towers X No of suspension strings/tower. = 169 X 3 = 507 sets j) No of tension clamps suitable for Lynx conductor with arcing horns = Total no of anchoring towers X No of tension strings/tower. = 20 X 6 = 120 sets k) Armoring rods suitable for Lynx conductor = No of suspension clamps + No of tension clamps = 507 + 120 = 627 sets l) PG clamps suitable for Lynx conductor = No of anchoring towers X No of jumpers / tower X No of PG clamps / jumpers = 20 X 3 X 2 = 120 m) Vibration dampers suitable for Lynx conductor = Total no of towers x 6 ( for single circuit) = 189 X 6 = 1134 sets n) Grounding materials including accessories = Total no of towers = 189 sets o) Cement concrete for tower erection = Total no. of towers X 12m3 = 189 X 12 = 2268 m3 p) Miscellaneous materials such as conductor accessories, ant climbing devices, danger boards, phase plates, no. plates, bird guards, bolt nuts, and other unfortunate items.
  • 10. 10 3) Prepare a detailed quantity of materials required for running a 120km, 220kv single circuit transmission line across a jungle terrain using four legged fabricated steel structures. Assuming average span length of 330m and conductor used is Drake ACSR. Solution: a) No. of spans = length of proposed line in meters/span length in meters =120,000/330 = 363.6 = 364 nos. b) Total no. of four legged fabricated steel structures = No. of spans +1 = 364 + 1= 365 nos c) No. of anchoring towers(assuming every 10th tower is to be an anchoring) = Total no. of towers /10 = 365/10 =36.5 nos = 37 nos Total no of anchoring towers = 37 + 1 at starting point = 38 d) No. of suspension towers = Total no. of towers – No. of anchoring towers = 365 – 38 = 327 nos. e) Total weight of the towers= ( Total no. of suspension towers X weight of each suspension towers) + ( Total no. of anchoring towers X weight of each anchoring towers) = (327 X 4) +(38 X 5) = 1308 + 190 = 1498 Tons f) No of 15KV disc insulators i) At suspension string for tangent towers =No of suspension towers X No of suspension strings/ tower X No of insulator / suspension string. = 327 X 3 X 14 = 13734 nos. ii) At tension string for anchoring towers = No of anchoring towers X No of tension strings/ tower X No of insulator / tension string. = 38 X 6 X 15 = 3420 nos. Total no. of disc insulators=(13734 + 3420) = 17154 nos. Add 5% extra for breakage on total, i.e.,=17154 X 0.05 = 858 nos. g) Length of ACSR conductor allowing 3% sag = (Total length of the line in km X no of conductor) X 1.03 = 120 X 3 X 1.03 = 371 km. h) Length of the GI ground wire of size 7/3.15mm allowing 3% sag = (Total length of the line in km X no of ground wire) X 1.03 = 120 X 1 X 1.03 = 124 km. i) No. of suspension clamps suitable for Drake conductor with arcing horns = Total no of suspension towers X No of suspension strings/tower. = 327 X 3 = 981 sets. j) No. of tension clamps suitable for Drake conductor with arcing horns = Total no of anchoring towers X No of tension strings/tower. = 38 X 6 = 228 sets.
  • 11. 11 k) Armoring rods suitable for Drake conductor = No of suspension clamps + No of tension clamps = 981+228= 1209 sets. l) PG clamps suitable for Drake conductor = No of anchoring towers X No of jumpers / tower X No of PG clamps / jumpers = 38 X 3 X 2 = 22 nos. m) Vibration dampers suitable for Drake conductor = Total no of towers x 6 ( for single circuit) = 365 x 6 = 2190 sets. n) Grounding materials including accessories = Total no of towers = 365 sets. o) Cement concrete for tower erection = Total no of towers X 12m3 = 365 X 12 = 4380 m3 p) Miscellaneous materials such as conductor accessories, ant climbing devices, danger boards, phase plates, no. plates, bird guards, bolt nuts, and other unfortunate items.
  • 12. 12 6.7 SUB STATION: A substation receives electrical power from generating stations through incoming transmission lines and delivers electrical power through outgoing transmission lines. The electrical substation is the part of a power system in which the voltage is transformed from high to low or low to high for transmission, distribution, transformation and switching. The power transformer, circuit breaker, bus-bar, insulator, lightning arrester are the main components of an electrical substation. 6.7.1 - Single line diagram of 66/11KV, 5 MVA substation: 6.7.2 - Materials required for 66/11kV, 5MVA substations with specifications: Example : Prepare a quantity of materials required for establishing a substation of capacity 5MVA, 66/11kv transformer. Assuming current market rates and as per K.P.T.C.L procedure. Solution: (Assuming two incoming lines as in above single line diagram) Equipment’s on primary (66kv) side: a) Lightning arresters metal oxide type, 66kv class = 4 sets ( 2 for bus coupler and 2 for transformer) b) Potential transformers 66kv class = 4 sets ( 2 for line and 2 for Bus bars) c) Current transformers 800:1 ratio = 5 sets ( 2 for i/c line, 2 for o/g line, 1 for bus coupler) & Current transformers 200:1 ratio = 2 sets ( 1 for each transformer) d) Upright Isolators (G.O.S) double blade 800A, 66kv class with earth switch = 4 sets (2 for i/c and 2 for o/g line)
  • 13. 13 e) Upright Isolators (G.O.S) double blade 800A, 66kv class without earth switch = 14 sets (2 for bus coupler and 12 for bus bars) f) Circuit breakers SF6 type, 66kv class = 7 sets (2 for i/c line, 2 for o/g line, 2 for Transformers and 1 for bus coupler) g) Bus bars expansion type using ACSR conductor = 2 sets. h) Transformers 5MVA, 66/11kv, with OLTC and all accessories = 2 sets i) Control and Relay panels for 66kv lines = 4 sets ( 2 for i/c line and 2 for o/g line) j) Control and Relay panels for Transformers = 2 sets ( 1set for each transformer) k) Control and Relay panels for bus coupler = 1 set. l) Power and control cables in between different equipment’s and control and relay panels = lump sum in meters m) G.I mounting structures for mounting different equipment’s = lump sum in metric tonnes Equipment’s on secondary side (11kv): a) 11kv , 1200A outdoor switch gear with breaker, CT, PT etc., = 6 sets b) G.O.S 11kv, 400A double blade = 6 sets (for outgoing 11kv lines) c) Lightning arresters 11kv, thyrite type = 6 sets (for outgoing 11kv lines) d) Distribution transformer for station auxiliary supply 100 KVA, 11KV / 440V = 1 set e) Underground cable of size 1X1000mm2 from transformer to 11kv switch gear = lumpsum in meters f) Underground cable of size 3X250mm2 from outdoor switch gear take off structure = lumpsum in meters g) Take off structures 9m long double pole structure = 6 sets h) 110V, 60AH, batteries with batteries charger = 2 sets i) Earth mat including pipe earthing and plate earthing = lump sum j) LT AC panel board indoor type =1 set k) Outdoor type AC distribution boards = lumpsum l) DC distribution board indoor type = 1 set m) Miscellaneous materials such as ACSR conductors, 15kv disc insulators, stain insulators, different types of clamps, bolt nuts, fire extinguishers, name plates, danger boards and other unfortunate items.