SlideShare a Scribd company logo
1
Prepared By:
Mr.Premanand Desai L/EE
B.L.D.E.A’s SHREE SANGANABASAVA
MAHA SWAMIJI POLYTECHNIC,
VIJAYAPUR-03
E-mail ID:ssmp.premananddesai@bldea.org
cell no : +91 7892881829
COURSE & CODE : ELECTRICAL ESTIMATION AND COSTING (15EE54T)
UNIT - 01
INTRODUCTION
2
COURSE & CODE : ELECTRICAL ESTIMATION AND COSTING (15EE54T)
UNIT - 01
INTRODUCTION
1.1 Introduction
Before commissioning any work, it is important to know the clear picture of the
work, required materials, specification of the materials used and cost of the work.
1.2 Estimation
Estimation means an assessment of the quantity of the materials and its cost
required for any work. It includes listing of materials, stating their specifications
and Approximate cost.
OR
Estimation includes calculation of quantity involved and quality aspect of material ,
so estimation is the art of finding out the cost so that we can fix the budget for that
particular work.
1.3 Purpose/Need of Estimating
1. To Fix up the budget and complete details of the required materials for
carrying out the complete work.
2. To Exercise control over quality of materials required depending upon the
work to be executed.
3. To fix up the cost of various materials, including cost of labour ,
supervision , inspection ,transportation etc.
4. To find most economical procedure for the execution of work .
5. To keep the estimates in a systematic way for the future reference.
6. To ensure availability of all the materials required for execution of the
project.
7. To avoid the misuse of material and money.
8. To reduce the time required for completion of the project.
9. To complete the project uninterruptedly.
3
1.4 Importance of Estimation
1. It give approximate budget for carrying out the work
2. Its avoids wastage of material.
3. It helps to use correct material.
4. It helps to do the work according to the engineering principles without any
confusion in adopting different systems or methods.
1.5 Factors to be considered while preparing estimations
Before initiating any electrical project the following factors related to estimation
should be considered
1. Standard Performa for making estimation.
2. Specification of the materials.
3. Latest price list and Net prices of materials.
4. Overhead charges, Supervision charges and Labour charges.
5. Contingencies and stock incidental charges.
6. Inspection charges and Transportation charges.
7. Miscellaneous charges.
1.6 Qualities of good estimator:
1. He should have full practical experience and knowledge about preparing
estimation.
2. He should have complete knowledge about the latest designs.
3. He should have full knowledge about the specification of materials and
market prices.
4. He should have knowledge about the labour charges and other charges.
5. He should have good imagination and experimenting power because he should
keep provision for future extension.
4
1.7 Define specification.
Specification is a documented detailed description of materials, equipment’s and
machineries etc. suit to the requirements.
OR
Set of documented requirements to be satisfied by materials, equipment’s,
machineries, design etc. as per technical standard.
1.8 Importance of specification:
1. It provides clear details of the materials.
2. It gives quality and standards applied for materials.
3. It helps to purchase suitable materials.
4. It provides clear instructions about the quality of the materials.
5. It gives procedure for installation and using of materials.
1.9 Factors to be considered for specification:
1. Specification must be as per standards.
2. Economic factors to be considered.
3. Proper safety factor must be considered.
4. Specification must be as per the market availability of the materials.
1.10 standardization
It is a process to achieve interchangeability and quantity control so that mass
production is possible which reduces the cost. In India standards have been framed
by Bureau of Indian Standard.
1.11 Advantages or Need of standardization
1. Standardization minimizes the cost due to mass production.
2. It improves the quality of the material.
3. Standardization causes interchangeability due to which easy replacement of
material can be done.
4. Standardization avoids confusion to both supplier and user.
5
1.12. Charges
1.12.1 Overhead charges:
Overhead charges include office expenses, salary of administrative staff, rents for
office, lighting and heating expenses, travelling expenses, advertisements, insurance,
and water expenses, depreciation of furniture’s etc. Normally 10-15% of the total
estimated material and labour expenses are spent on overhead charges.
1.12.2 Labour charges:
Labour charge is the most difficult and variable item to assess. It is affected by so many
factors such as installation site condition, skill and technical training, physical fitness
etc. By vast experience and proper records of time sheets, an intelligent estimator will
be able to obtain labour values by the system of man-hour constant.
1.12.3 Contingencies:
During erection of the project, there can be certain emergency expenses which cannot
considered while calculating the material cost and labour expenses for the project.
These additional emergency expenses may be due to any reason such as increase in cost
of material or labour rates etc. Such additional expenses are called contingencies. For
this, 3-5% of the material cost and labour cost is estimated.
1.12.4 Stock incidental charges:
To cover the risk of damage during preservation, transportation, loading, unloading and
handling or theft of material extra charge is included. It is normally 5% of total cost.
1.12.5 Inspection/Inspectorate charges:
Inspection or testing of any electrical work (Generating station, substation, transmission
line, distribution line etc) is done by government body for this charge is to be paid. So
inspection charges are included in the estimation as per standard inspectorial charges.
1.12.6 Transportation charges:
The cost of transporting materials or goods for the execution of a particular electrical
installation or project work is called transportation charges.
6
1.12.7 Supervision charges:
These charges are paid for supervision of work to the licensee/contractor at 10% of the
estimated cost of the work.
1.12.8 Miscellaneous charges:
For purchasing of minor items like nuts, bolts, raw plugs, coal, salt etc which cannot be
mentioned in major works specification. The charges are paid in this head. The
miscellaneous charges included in the estimation are lump sum also rounded the cost of
estimation to a round figure.
1.12.9 Tender
A tender is a formal offer made by one to another to supply goods or to do a particular
job at certain specified cost. Generally business groups and Government departments’
issues notices for quotes for specified goods or services from other business or company
which known as tender. If a contract is put out to tender, formal offers are invited. If a
company wins a tender their offers is accepted.
1.12.10 Tender Notice
It is process to call venders for doing a certain job or provide certain service at a
competitive price. Usually done through the prominent newspaper of the region/official
e-procurement websites.
1.12.11 Quotation
An offer in terms of rates made by the supplier or manufacturer on a prescribed form
enclosed in a sealed envelope, in reply to a tender notice for supply of material on the
basis of some terms and a condition is called quotation.
1.12.12 Comparative statement
This is an important document to evaluate the offers received against an enquiry.
Utmost care must be exercised while preparing the comparative statement of tenders.
Any deviation from the tendered specifications, delivery conditions, assistance etc.
stipulated by the tenders should be highlight.
A sample of comparative price statement is as shown in Table below;
7
Comparative Price Statement (CPS)
No. of Tenders Received: Enquiry No:
No. of Enquiries Issued: Date:
Date of Opening of
Tenders: Due Date:
Sl No Description Quantity Previous purchases Current Offers
Received Ordered Date Unit 1 2 3 4 5 6
No. Price
1.12.13 Purchase order
A purchase order is legally binding document between a supplier and a buyer. It details
the items the buyer agrees to purchase at a certain price point. It also outlines the
delivery date and terms of payment for the buyer purchase order computer systems
have made the purchasing process more efficient and allow for better inventory and
payment tracking.
1.12.14 Work order
A work order is an order received by an organization from a customer or client or an
order created internally within the organization. A work order may before products or
services. A work order sometimes is used in place of an "invoice" or "statement" and
presented for payment requests.
1.13 Indian Electricity Act (I.E Act)
An Act to amend the law retaining to the supply and use of electrical energy, rights and
obligations of the licensees. Whereas it is expedient to amend the law relating to the
supply and use of electrical energy. This Act may be called the Indian Electricity Act;
1910.It extends to the whole of India.
The Electricity Supply Act, 1948 deals with the statutory powers and functions of the
Central Electricity Authority. State electricity boards and generating companies. The
electricity act 2003 is enacted to improve the backdrop of economic in power sector and
8
performance of state electricity boards. This deals with uniform and unified law to take
care of the current needs of power sector in the areas of generation, transmission,
trading and distribution of electricity.
1.14 Importance of Indian Electricity Act
1. It is a single legislation which addresses all the key areas of electricity in the
country.
2. It provides a road map for overall and uniform development of electricity
sector in the country
3. It takes care of interests of consumers belonging to various sectors
4. It also aims to reform the sector to suit the needs of the present day
requirement in the light of globalization.
5. Through specific provisions it aims to bring in financial and commercial
viability for power sector utilities.
1.15 Purpose of Indian Electricity Act
1. To consolidate the laws relating to generation, transmission, distribution,
trading and use of electricity.
2. To take measures conducive for development of electricity sector.
3. To promote competition in the power sector.
4. To protect the interests of consumers.
5. To rationalize the electricity tariffs.
6. To establish regulatory commissions and appellate tribunal for electricity.
1.16 Indian electricity rules (IE Rules)
In exercise of the powers conferred by section 37 of the Indian electricity act,1910
the central electricity board frames the rules to regulate the generation,
transmission, supply and use of electrical energy. These rules called as Indian
electricity rules 1956.
1.17 Importance of Indian Electricity Rules
• They provides reliability and safety for electrical supply system
• They focus on protection of persons and property from injury.
9
• They supplement the various codes of bureau of Indian standards.
• They serve as a guideline for electrical practices in a country.
1.18 Purpose of Indian electricity rules
• To regulate the relation between the supplier and consumer.
• To make the generation, transmission and distribution of electricity as safe
as possible.
1.19 Earthing
The process of connecting metallic bodies of all the electrical apparatus and
equipment to huge mass of earth by a wire having negligible resistance is called
Earthing.
OR
The method of connecting noncurrent carrying parts of the electrical equipment or
accessories or neutral point of the supply, system to the earth through the wire
having negligible resistance is called electrical earthing.
1.19.1 Touch potential:
Touch potential is the potential difference between the energized object and the
feet of a person in contact with the object.
1.19.2 Step potential:
Step potential is the potential difference between the feet of a person standing
near an energized grounded object.
10
1.20 Necessity of earthing
• To provide a protection for the apparatus, equipment’s, devices etc.
against leakage current this may damage it.
• To provide safety to the operator or the person coming in touch with
electric supply.
• Tripping due to earthing in case faults save wastage of electric energy
excess current drawn during.
• Protection of large buildings and all machines fed from overhead lines
against lightning.
• To serve as a returned conductor in communication and traction work.
• To maintain the line voltage constant under unbalanced load condition
1.21 Points to be earthed:
1 Earth pin of sockets should be efficiently and permanently earthed.
2 All metallic covers of machines, starters and sheathing of wire should be
earthed.
3 Iron clad switches and iron clad distribution boards should be earthed.
4 Metallic coverings of any electrical supply line should be earthed.
5 Stay wires for overhead lines should be connected to earth.
6 In a dc 3-wire system, the middle conductors should be earthed at the
generating station.
1.22 Factors influencing earth resistance:
• Soil resistivity: The earth resistance of an earth pit depends on soil resistivity.
• Soil condition: Different soil gives different earth resistance.
• Moisture: Moisture content is one of the controlling factors in earth
resistivity.
• Dissolved salts: Small quantity of salt reduces the earth resistivity.
11
• Temperature: As the temperature changes the earth resistance also changes.
• The type of material used for earth electrode and earth wire.
• Size of earth electrode and earth wire.
1.23 Methods of reducing earth resistance
• Pour sufficient water in earth electrode periodically.
• By increasing the cross sectional area of electrode.
• By maintaining the temperature of the soil.
• By increasing depth of the plate.
• By installing number of electrodes in parallel.
• Using sufficient quantity of coal and salt in the earthing pit.
• Remove oxidation on joint and joints should be tightened.
1.24 Standard values of earth resistance for various installations.
• Large power station – 0.5 Ω
• Major Power Station – 1.0 Ω
• Small Substation – 2.0 Ω
• In all other cases – 5 Ω Maximum
Earth continuity inside an installation that is from the earth plate to any
point in the installation -1.0 Ω
12
1.25 Method of selecting the size of earth conductor.
• For domestic Installation : GI or Copper Wire no. 8 SWG will be required to run from
main distribution board to various submain distribution boards. Copper wire no.14
SWG will be required to run to three-pin socket outlets and connected to their earth
sleeve.
• For Motor Installation : In case of motor installation, the size of earth wire and earth
plate used will depend upon the rating of the motor for which it is to be used.
1.26 Types / Methods of Earthing
• Strip or Wire or Spiral Earthing
• Rod Earthing
• Mat Earthing
• Plate Earthing
• Pipe Earthing
1.27 Plate Earthing
The plate earthing is as shown in the Figure 2. In this method a copper plate of 60cm
x 60cm x 3mm or a GI plate of the size 60cm x 60cm x 6mm is used for earthing. The
plate is placed vertically down inside the ground at a depth of 3m and is embedded
in alternate layers of coal and salt for a thickness of 15 cm.
In addition, water is poured for keeping the earth electrode resistance value well
below a maximum of 5 ohms. The earth wire is securely bolted to the earth plate. A
cement masonry chamber is built with a cast iron cover for easy regular maintenance.
Capacity of motor /
Equipment
Size of earth wire in S W G
Copper G.I
Up to 10 hp No 8 No 8
Above 10 hp & up to 15 hp No 8 No 6
Above 15 hp & Up to 30 hp No 6 No 2
Above 30 hp & Up to 50 hp No 4 -
Above 50 hp & Up to 100 hp No 2 or Strip 13mm × 2.5mm -
Above 100 hp Strip 25 mm × 2.5mm -
13
1.27.1 Specification Plate Earthing
Sl No Description Specification
1 Earth pit 1mtr diameter 3mtr depth
2 Pipe for earth conductor GI 50mm dia, 2mtr length
3 Earth electrode plate size Copper plate of 600mm x 600mm x 3mm or
GI plate of 600mm x 600mm x 6mm
4 Earth strip for connection Copper earth strip of 25mm x 3mm
5 Filling of earth pit With charcoal and salt surrounding earth
plate about 150mm
6 Pipe for water pouring 19 mm dia GI pipe
7 Construction of masonry Masonry brick work of height 450mm x
work width 700mm with CI cover and CI frame
14
1.29 Pipe Earthing
Pipe earthing is done by G.I. pipe as shown in Figure.1. Here a 38mmdia G.I.pipe
2.5m in length, 3 mm thickness having alternate cross holes of 12.mmdia at each
300 mm distance buried in a pit of 340mm diameter with alternative layers of coal
and salt.
The top of this pipe is connected to the funnel through 19 mm GI, pipe with the
help of a reducer. At ground level a concrete bed is formed in such a way that a
hollow rectangular solid shape is formed (150mm X 150mm X 250mm) with the
insertion of GI pipe carrying the earth conductor.
The above hollow pit is closed by Cast Iron cover. Pipe is connected to the apparatus
by means of 8 SWG G I. wire with the help of bolts and nuts. To maintain the wetness
in pit periodically (After every eight days in summer and winter) water is poured
through the funnel. Always the earth resistance should be within 2 to 5 ohms, but
for rocky soil it can be more.
15
1.29.1 Specification Plate Earthing
Sl No Description Specification
1 Earth pit 1mtr diameter 4.5mtr depth
2 Pipe for earth conductor GI 40mm dia, 2.5mtr length, 3mm thickness
3 Pipe for water pouring 19 mm dia GI pipe
4 Filling of earth pit Alternative layer of charcoal and salt 2mtr
from the bottom of pipe.
5 Construction of masonry Masonry brick work of height 450mm x
work width 700mm with CI cover and CI frame
6 Identification of earth pit With suitable display board
16
MODEL QUESTIONS BANK
• Cognitive Level: REMEMBER
1. Define estimation. List the factors to be considered while estimating.
2. List the qualities of a good estimator.
3. List the importance of estimation.
4. Define specification. List the factors to be considered.
5. Mention the importance of specification.
6. Define standardization. List the advantages.
7. Define earthing?. List the points that need to be earthed.
8. Draw a neat diagram of pipe earthing and label the parts.
9. Draw a neat diagram of plate earthing and label the parts.
10.List the specification of pipe earthing
11.List the specifications of plate earthing.
12.List the factors on which earth resistance depends.
13.List the methods of reducing earth resistance.
• Cognitive level: Understanding/Analyse
1. Draw neat diagram of pipe earthing and label the parts with specifications.
2. Draw neat diagram of plate earthing and label the parts with specifications.
3. List the specifications of a) pipe earthing and b) plate earthing

More Related Content

What's hot

EPC Solutions - All About Substation
EPC Solutions - All About Substation EPC Solutions - All About Substation
EPC Solutions - All About Substation
EPC Solutions LLP
 
TDU - Unit 01 Transmission system
TDU - Unit  01 Transmission system TDU - Unit  01 Transmission system
TDU - Unit 01 Transmission system
PremanandDesai
 
Basic power distribution system007
Basic power distribution system007Basic power distribution system007
Basic power distribution system007
Vaishnavee Patel
 
transmission line
transmission line transmission line
transmission line
singh1515
 
Overhead line work ppt
Overhead line work pptOverhead line work ppt
Overhead line work ppt
Demsew Mitiku
 
Classification of transmission lines
Classification of transmission linesClassification of transmission lines
Classification of transmission lines
HamzaAbbas43
 
Introduction to power transformers
Introduction to power transformersIntroduction to power transformers
Introduction to power transformers
Leonardo ENERGY
 
Transmission and distribution system of nepal
Transmission and distribution system of nepalTransmission and distribution system of nepal
Transmission and distribution system of nepal
Bishal Rimal
 
400kv sub-station-final-ppt-by-mohit
400kv sub-station-final-ppt-by-mohit400kv sub-station-final-ppt-by-mohit
400kv sub-station-final-ppt-by-mohitMohit Awasthi
 
ESTIMATION & COSTING OF DOMESTIC & INDUSTRIAL WIRING
ESTIMATION & COSTING OF DOMESTIC & INDUSTRIAL WIRINGESTIMATION & COSTING OF DOMESTIC & INDUSTRIAL WIRING
ESTIMATION & COSTING OF DOMESTIC & INDUSTRIAL WIRING
RanjitKumar Parmar
 
Electricity distribution system in india
Electricity distribution system in indiaElectricity distribution system in india
Electricity distribution system in india
Jasgt Singh
 
Equipments of power transmission
Equipments of power transmissionEquipments of power transmission
Equipments of power transmission
Rasika Ghongade
 
Underground cables
Underground cablesUnderground cables
Underground cables
Poonam Sarawgi
 
Electrical Power substation
Electrical Power substationElectrical Power substation
Electrical Power substation
Emran Ali
 
TDU Unit 03 Distribution Systems
TDU Unit  03 Distribution SystemsTDU Unit  03 Distribution Systems
TDU Unit 03 Distribution Systems
PremanandDesai
 
Transmission line Project
Transmission line ProjectTransmission line Project
Transmission line Project
Pankaj Kumar Dwivedi
 
Concept of energy transmission & distribution
Concept of energy transmission & distribution Concept of energy transmission & distribution
Concept of energy transmission & distribution
ZunAib Ali
 
Transformer Designing
Transformer Designing Transformer Designing
Transformer Designing
Praveen Sharma
 
Cable and laying
Cable and layingCable and laying
Cable and laying
BHAGWAN PRASAD
 
Underground cables
Underground cablesUnderground cables
Underground cables
Anu71
 

What's hot (20)

EPC Solutions - All About Substation
EPC Solutions - All About Substation EPC Solutions - All About Substation
EPC Solutions - All About Substation
 
TDU - Unit 01 Transmission system
TDU - Unit  01 Transmission system TDU - Unit  01 Transmission system
TDU - Unit 01 Transmission system
 
Basic power distribution system007
Basic power distribution system007Basic power distribution system007
Basic power distribution system007
 
transmission line
transmission line transmission line
transmission line
 
Overhead line work ppt
Overhead line work pptOverhead line work ppt
Overhead line work ppt
 
Classification of transmission lines
Classification of transmission linesClassification of transmission lines
Classification of transmission lines
 
Introduction to power transformers
Introduction to power transformersIntroduction to power transformers
Introduction to power transformers
 
Transmission and distribution system of nepal
Transmission and distribution system of nepalTransmission and distribution system of nepal
Transmission and distribution system of nepal
 
400kv sub-station-final-ppt-by-mohit
400kv sub-station-final-ppt-by-mohit400kv sub-station-final-ppt-by-mohit
400kv sub-station-final-ppt-by-mohit
 
ESTIMATION & COSTING OF DOMESTIC & INDUSTRIAL WIRING
ESTIMATION & COSTING OF DOMESTIC & INDUSTRIAL WIRINGESTIMATION & COSTING OF DOMESTIC & INDUSTRIAL WIRING
ESTIMATION & COSTING OF DOMESTIC & INDUSTRIAL WIRING
 
Electricity distribution system in india
Electricity distribution system in indiaElectricity distribution system in india
Electricity distribution system in india
 
Equipments of power transmission
Equipments of power transmissionEquipments of power transmission
Equipments of power transmission
 
Underground cables
Underground cablesUnderground cables
Underground cables
 
Electrical Power substation
Electrical Power substationElectrical Power substation
Electrical Power substation
 
TDU Unit 03 Distribution Systems
TDU Unit  03 Distribution SystemsTDU Unit  03 Distribution Systems
TDU Unit 03 Distribution Systems
 
Transmission line Project
Transmission line ProjectTransmission line Project
Transmission line Project
 
Concept of energy transmission & distribution
Concept of energy transmission & distribution Concept of energy transmission & distribution
Concept of energy transmission & distribution
 
Transformer Designing
Transformer Designing Transformer Designing
Transformer Designing
 
Cable and laying
Cable and layingCable and laying
Cable and laying
 
Underground cables
Underground cablesUnderground cables
Underground cables
 

Similar to UNIT - 01 INTRODUCTION

ESTIMATING and coasting of electrical equipment.
ESTIMATING and coasting of electrical equipment.ESTIMATING and coasting of electrical equipment.
ESTIMATING and coasting of electrical equipment.
subhamkumar01122000
 
Purpose of estimation
Purpose of estimationPurpose of estimation
Purpose of estimation
ADARSH KUMAR
 
Project cost stimating
Project cost stimatingProject cost stimating
Project cost stimating
hatim ahmed
 
A systematic study on site overhead costs in construction industry
A systematic study on site overhead costs in construction industryA systematic study on site overhead costs in construction industry
A systematic study on site overhead costs in construction industry
eSAT Journals
 
15ee553.docx
15ee553.docx15ee553.docx
15ee553.docx
vaasuchetu
 
10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation Steps10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation Steps
SHAZEBALIKHAN1
 
Preparation and approaches of cost estimates
Preparation and approaches of cost estimatesPreparation and approaches of cost estimates
Preparation and approaches of cost estimates
nagashree123
 
UNIT-3.pptx
UNIT-3.pptxUNIT-3.pptx
UNIT-3.pptx
PChakravarthyMECH
 
construction project managment_civileng
construction project managment_civilengconstruction project managment_civileng
construction project managment_civileng
sulaiman khan
 
Cac Machinewel
Cac MachinewelCac Machinewel
Cac Machinewel
Puneet_Piyush
 
Cost records and audit rules 2014
Cost records and audit rules 2014Cost records and audit rules 2014
Cost records and audit rules 2014
Kameswara Rao
 
E.c.v Introduction
E.c.v IntroductionE.c.v Introduction
E.c.v Introduction
Yusuf Challawala
 
Construction & Civil Engineering: Operational Aspects
Construction & Civil Engineering: Operational AspectsConstruction & Civil Engineering: Operational Aspects
Construction & Civil Engineering: Operational Aspects
sathish sak
 
Need of bio medical engineer lekshmi g nadh 2015
Need of  bio medical engineer lekshmi g nadh 2015Need of  bio medical engineer lekshmi g nadh 2015
Need of bio medical engineer lekshmi g nadh 2015
lekshmibaba
 
Chetan Sharma - Mechanical Engineer
Chetan Sharma - Mechanical EngineerChetan Sharma - Mechanical Engineer
Chetan Sharma - Mechanical EngineerCHETAN SHARMA
 
Estimation and costing
Estimation and costingEstimation and costing
Estimation and costing
Ganesh Murugan
 
China Factory Location Analysis & Sourcing Case Study
China Factory Location Analysis & Sourcing Case StudyChina Factory Location Analysis & Sourcing Case Study
China Factory Location Analysis & Sourcing Case Study
Dragon Sourcing
 
Case Study-China Factory Location Analysis and Sourcing
Case Study-China Factory Location Analysis and SourcingCase Study-China Factory Location Analysis and Sourcing
Case Study-China Factory Location Analysis and Sourcing
John William
 
Case Study - China Factory Location Analysis & Sourcing Example
Case Study - China Factory Location Analysis & Sourcing ExampleCase Study - China Factory Location Analysis & Sourcing Example
Case Study - China Factory Location Analysis & Sourcing Example
Dragon Sourcing
 
Cost records and audit rules 2014
Cost records and audit rules 2014Cost records and audit rules 2014
Cost records and audit rules 2014
Kameswara Rao
 

Similar to UNIT - 01 INTRODUCTION (20)

ESTIMATING and coasting of electrical equipment.
ESTIMATING and coasting of electrical equipment.ESTIMATING and coasting of electrical equipment.
ESTIMATING and coasting of electrical equipment.
 
Purpose of estimation
Purpose of estimationPurpose of estimation
Purpose of estimation
 
Project cost stimating
Project cost stimatingProject cost stimating
Project cost stimating
 
A systematic study on site overhead costs in construction industry
A systematic study on site overhead costs in construction industryA systematic study on site overhead costs in construction industry
A systematic study on site overhead costs in construction industry
 
15ee553.docx
15ee553.docx15ee553.docx
15ee553.docx
 
10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation Steps10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation Steps
 
Preparation and approaches of cost estimates
Preparation and approaches of cost estimatesPreparation and approaches of cost estimates
Preparation and approaches of cost estimates
 
UNIT-3.pptx
UNIT-3.pptxUNIT-3.pptx
UNIT-3.pptx
 
construction project managment_civileng
construction project managment_civilengconstruction project managment_civileng
construction project managment_civileng
 
Cac Machinewel
Cac MachinewelCac Machinewel
Cac Machinewel
 
Cost records and audit rules 2014
Cost records and audit rules 2014Cost records and audit rules 2014
Cost records and audit rules 2014
 
E.c.v Introduction
E.c.v IntroductionE.c.v Introduction
E.c.v Introduction
 
Construction & Civil Engineering: Operational Aspects
Construction & Civil Engineering: Operational AspectsConstruction & Civil Engineering: Operational Aspects
Construction & Civil Engineering: Operational Aspects
 
Need of bio medical engineer lekshmi g nadh 2015
Need of  bio medical engineer lekshmi g nadh 2015Need of  bio medical engineer lekshmi g nadh 2015
Need of bio medical engineer lekshmi g nadh 2015
 
Chetan Sharma - Mechanical Engineer
Chetan Sharma - Mechanical EngineerChetan Sharma - Mechanical Engineer
Chetan Sharma - Mechanical Engineer
 
Estimation and costing
Estimation and costingEstimation and costing
Estimation and costing
 
China Factory Location Analysis & Sourcing Case Study
China Factory Location Analysis & Sourcing Case StudyChina Factory Location Analysis & Sourcing Case Study
China Factory Location Analysis & Sourcing Case Study
 
Case Study-China Factory Location Analysis and Sourcing
Case Study-China Factory Location Analysis and SourcingCase Study-China Factory Location Analysis and Sourcing
Case Study-China Factory Location Analysis and Sourcing
 
Case Study - China Factory Location Analysis & Sourcing Example
Case Study - China Factory Location Analysis & Sourcing ExampleCase Study - China Factory Location Analysis & Sourcing Example
Case Study - China Factory Location Analysis & Sourcing Example
 
Cost records and audit rules 2014
Cost records and audit rules 2014Cost records and audit rules 2014
Cost records and audit rules 2014
 

More from PremanandDesai

Week-11 - Assembly drawing - Synchronous Motor
Week-11 - Assembly drawing -  Synchronous Motor Week-11 - Assembly drawing -  Synchronous Motor
Week-11 - Assembly drawing - Synchronous Motor
PremanandDesai
 
Week-10 - Assembly drawing - Alternators
Week-10 - Assembly drawing - AlternatorsWeek-10 - Assembly drawing - Alternators
Week-10 - Assembly drawing - Alternators
PremanandDesai
 
Week-09 - Assembly drawing-Induction Motor
Week-09 - Assembly drawing-Induction Motor Week-09 - Assembly drawing-Induction Motor
Week-09 - Assembly drawing-Induction Motor
PremanandDesai
 
Week-08 - Transformer Assembly-Threephase
Week-08 - Transformer Assembly-ThreephaseWeek-08 - Transformer Assembly-Threephase
Week-08 - Transformer Assembly-Threephase
PremanandDesai
 
Week-07- Developed Winding Diagrams - 1 phase--.pptx
Week-07- Developed Winding Diagrams - 1 phase--.pptxWeek-07- Developed Winding Diagrams - 1 phase--.pptx
Week-07- Developed Winding Diagrams - 1 phase--.pptx
PremanandDesai
 
Week-06 - Developed Winding Diagrams - 3 phase--.pptx
Week-06 - Developed Winding Diagrams - 3 phase--.pptxWeek-06 - Developed Winding Diagrams - 3 phase--.pptx
Week-06 - Developed Winding Diagrams - 3 phase--.pptx
PremanandDesai
 
Week-05 -Design a GA LT panel wiring--.pptx
Week-05 -Design a GA LT panel wiring--.pptxWeek-05 -Design a GA LT panel wiring--.pptx
Week-05 -Design a GA LT panel wiring--.pptx
PremanandDesai
 
Week-04 -Motor control Panel board
Week-04 -Motor control Panel boardWeek-04 -Motor control Panel board
Week-04 -Motor control Panel board
PremanandDesai
 
Week-03 - Electrical wiring of Residential, Hospital , small workshop
Week-03 - Electrical wiring of  Residential, Hospital , small workshopWeek-03 - Electrical wiring of  Residential, Hospital , small workshop
Week-03 - Electrical wiring of Residential, Hospital , small workshop
PremanandDesai
 
Week-02 - Single line diagram of Substations
Week-02 - Single line diagram of SubstationsWeek-02 - Single line diagram of Substations
Week-02 - Single line diagram of Substations
PremanandDesai
 
Week-01 - INTRODUCTION to CAD
Week-01  - INTRODUCTION to CADWeek-01  - INTRODUCTION to CAD
Week-01 - INTRODUCTION to CAD
PremanandDesai
 
Week- 13 - APFC , AMF & STP
Week- 13 - APFC , AMF & STP Week- 13 - APFC , AMF & STP
Week- 13 - APFC , AMF & STP
PremanandDesai
 
Week - 12 - Motor control centre (MCC)
Week - 12 - Motor control centre (MCC) Week - 12 - Motor control centre (MCC)
Week - 12 - Motor control centre (MCC)
PremanandDesai
 
Week - 11 - Metering section and Auxiliary Relays
Week  - 11 - Metering section  and Auxiliary RelaysWeek  - 11 - Metering section  and Auxiliary Relays
Week - 11 - Metering section and Auxiliary Relays
PremanandDesai
 
Week 10 - Control Panel & Power gears
Week  10 - Control Panel &  Power gearsWeek  10 - Control Panel &  Power gears
Week 10 - Control Panel & Power gears
PremanandDesai
 
Switchgear and protection - lab
Switchgear and protection - labSwitchgear and protection - lab
Switchgear and protection - lab
PremanandDesai
 
Week - 09 - Testing of CB & Substation Earthing
Week - 09 - Testing of CB & Substation Earthing Week - 09 - Testing of CB & Substation Earthing
Week - 09 - Testing of CB & Substation Earthing
PremanandDesai
 
Week- 08 - Feeder protection and Bus–Bar Protection.
Week- 08 - Feeder protection and  Bus–Bar Protection.Week- 08 - Feeder protection and  Bus–Bar Protection.
Week- 08 - Feeder protection and Bus–Bar Protection.
PremanandDesai
 
Week 07 - Alternator Protection
Week   07 - Alternator Protection Week   07 - Alternator Protection
Week 07 - Alternator Protection
PremanandDesai
 
WEEK- 06/ UNIT – 06 Transformer Protection
WEEK- 06/ UNIT – 06 Transformer Protection WEEK- 06/ UNIT – 06 Transformer Protection
WEEK- 06/ UNIT – 06 Transformer Protection
PremanandDesai
 

More from PremanandDesai (20)

Week-11 - Assembly drawing - Synchronous Motor
Week-11 - Assembly drawing -  Synchronous Motor Week-11 - Assembly drawing -  Synchronous Motor
Week-11 - Assembly drawing - Synchronous Motor
 
Week-10 - Assembly drawing - Alternators
Week-10 - Assembly drawing - AlternatorsWeek-10 - Assembly drawing - Alternators
Week-10 - Assembly drawing - Alternators
 
Week-09 - Assembly drawing-Induction Motor
Week-09 - Assembly drawing-Induction Motor Week-09 - Assembly drawing-Induction Motor
Week-09 - Assembly drawing-Induction Motor
 
Week-08 - Transformer Assembly-Threephase
Week-08 - Transformer Assembly-ThreephaseWeek-08 - Transformer Assembly-Threephase
Week-08 - Transformer Assembly-Threephase
 
Week-07- Developed Winding Diagrams - 1 phase--.pptx
Week-07- Developed Winding Diagrams - 1 phase--.pptxWeek-07- Developed Winding Diagrams - 1 phase--.pptx
Week-07- Developed Winding Diagrams - 1 phase--.pptx
 
Week-06 - Developed Winding Diagrams - 3 phase--.pptx
Week-06 - Developed Winding Diagrams - 3 phase--.pptxWeek-06 - Developed Winding Diagrams - 3 phase--.pptx
Week-06 - Developed Winding Diagrams - 3 phase--.pptx
 
Week-05 -Design a GA LT panel wiring--.pptx
Week-05 -Design a GA LT panel wiring--.pptxWeek-05 -Design a GA LT panel wiring--.pptx
Week-05 -Design a GA LT panel wiring--.pptx
 
Week-04 -Motor control Panel board
Week-04 -Motor control Panel boardWeek-04 -Motor control Panel board
Week-04 -Motor control Panel board
 
Week-03 - Electrical wiring of Residential, Hospital , small workshop
Week-03 - Electrical wiring of  Residential, Hospital , small workshopWeek-03 - Electrical wiring of  Residential, Hospital , small workshop
Week-03 - Electrical wiring of Residential, Hospital , small workshop
 
Week-02 - Single line diagram of Substations
Week-02 - Single line diagram of SubstationsWeek-02 - Single line diagram of Substations
Week-02 - Single line diagram of Substations
 
Week-01 - INTRODUCTION to CAD
Week-01  - INTRODUCTION to CADWeek-01  - INTRODUCTION to CAD
Week-01 - INTRODUCTION to CAD
 
Week- 13 - APFC , AMF & STP
Week- 13 - APFC , AMF & STP Week- 13 - APFC , AMF & STP
Week- 13 - APFC , AMF & STP
 
Week - 12 - Motor control centre (MCC)
Week - 12 - Motor control centre (MCC) Week - 12 - Motor control centre (MCC)
Week - 12 - Motor control centre (MCC)
 
Week - 11 - Metering section and Auxiliary Relays
Week  - 11 - Metering section  and Auxiliary RelaysWeek  - 11 - Metering section  and Auxiliary Relays
Week - 11 - Metering section and Auxiliary Relays
 
Week 10 - Control Panel & Power gears
Week  10 - Control Panel &  Power gearsWeek  10 - Control Panel &  Power gears
Week 10 - Control Panel & Power gears
 
Switchgear and protection - lab
Switchgear and protection - labSwitchgear and protection - lab
Switchgear and protection - lab
 
Week - 09 - Testing of CB & Substation Earthing
Week - 09 - Testing of CB & Substation Earthing Week - 09 - Testing of CB & Substation Earthing
Week - 09 - Testing of CB & Substation Earthing
 
Week- 08 - Feeder protection and Bus–Bar Protection.
Week- 08 - Feeder protection and  Bus–Bar Protection.Week- 08 - Feeder protection and  Bus–Bar Protection.
Week- 08 - Feeder protection and Bus–Bar Protection.
 
Week 07 - Alternator Protection
Week   07 - Alternator Protection Week   07 - Alternator Protection
Week 07 - Alternator Protection
 
WEEK- 06/ UNIT – 06 Transformer Protection
WEEK- 06/ UNIT – 06 Transformer Protection WEEK- 06/ UNIT – 06 Transformer Protection
WEEK- 06/ UNIT – 06 Transformer Protection
 

Recently uploaded

How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17
Celine George
 
MARUTI SUZUKI- A Successful Joint Venture in India.pptx
MARUTI SUZUKI- A Successful Joint Venture in India.pptxMARUTI SUZUKI- A Successful Joint Venture in India.pptx
MARUTI SUZUKI- A Successful Joint Venture in India.pptx
bennyroshan06
 
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptxStudents, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
EduSkills OECD
 
1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx
JosvitaDsouza2
 
Sectors of the Indian Economy - Class 10 Study Notes pdf
Sectors of the Indian Economy - Class 10 Study Notes pdfSectors of the Indian Economy - Class 10 Study Notes pdf
Sectors of the Indian Economy - Class 10 Study Notes pdf
Vivekanand Anglo Vedic Academy
 
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup   New Member Orientation and Q&A (May 2024).pdfWelcome to TechSoup   New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
TechSoup
 
Additional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdfAdditional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdf
joachimlavalley1
 
How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...
Jisc
 
The Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official PublicationThe Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official Publication
Delapenabediema
 
Synthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptxSynthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptx
Pavel ( NSTU)
 
The approach at University of Liverpool.pptx
The approach at University of Liverpool.pptxThe approach at University of Liverpool.pptx
The approach at University of Liverpool.pptx
Jisc
 
Home assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdfHome assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdf
Tamralipta Mahavidyalaya
 
Cambridge International AS A Level Biology Coursebook - EBook (MaryFosbery J...
Cambridge International AS  A Level Biology Coursebook - EBook (MaryFosbery J...Cambridge International AS  A Level Biology Coursebook - EBook (MaryFosbery J...
Cambridge International AS A Level Biology Coursebook - EBook (MaryFosbery J...
AzmatAli747758
 
Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345
beazzy04
 
Template Jadual Bertugas Kelas (Boleh Edit)
Template Jadual Bertugas Kelas (Boleh Edit)Template Jadual Bertugas Kelas (Boleh Edit)
Template Jadual Bertugas Kelas (Boleh Edit)
rosedainty
 
Operation Blue Star - Saka Neela Tara
Operation Blue Star   -  Saka Neela TaraOperation Blue Star   -  Saka Neela Tara
Operation Blue Star - Saka Neela Tara
Balvir Singh
 
Model Attribute Check Company Auto Property
Model Attribute  Check Company Auto PropertyModel Attribute  Check Company Auto Property
Model Attribute Check Company Auto Property
Celine George
 
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCECLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
BhavyaRajput3
 
ESC Beyond Borders _From EU to You_ InfoPack general.pdf
ESC Beyond Borders _From EU to You_ InfoPack general.pdfESC Beyond Borders _From EU to You_ InfoPack general.pdf
ESC Beyond Borders _From EU to You_ InfoPack general.pdf
Fundacja Rozwoju Społeczeństwa Przedsiębiorczego
 
2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...
Sandy Millin
 

Recently uploaded (20)

How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17
 
MARUTI SUZUKI- A Successful Joint Venture in India.pptx
MARUTI SUZUKI- A Successful Joint Venture in India.pptxMARUTI SUZUKI- A Successful Joint Venture in India.pptx
MARUTI SUZUKI- A Successful Joint Venture in India.pptx
 
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptxStudents, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
 
1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx
 
Sectors of the Indian Economy - Class 10 Study Notes pdf
Sectors of the Indian Economy - Class 10 Study Notes pdfSectors of the Indian Economy - Class 10 Study Notes pdf
Sectors of the Indian Economy - Class 10 Study Notes pdf
 
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup   New Member Orientation and Q&A (May 2024).pdfWelcome to TechSoup   New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
 
Additional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdfAdditional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdf
 
How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...
 
The Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official PublicationThe Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official Publication
 
Synthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptxSynthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptx
 
The approach at University of Liverpool.pptx
The approach at University of Liverpool.pptxThe approach at University of Liverpool.pptx
The approach at University of Liverpool.pptx
 
Home assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdfHome assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdf
 
Cambridge International AS A Level Biology Coursebook - EBook (MaryFosbery J...
Cambridge International AS  A Level Biology Coursebook - EBook (MaryFosbery J...Cambridge International AS  A Level Biology Coursebook - EBook (MaryFosbery J...
Cambridge International AS A Level Biology Coursebook - EBook (MaryFosbery J...
 
Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345
 
Template Jadual Bertugas Kelas (Boleh Edit)
Template Jadual Bertugas Kelas (Boleh Edit)Template Jadual Bertugas Kelas (Boleh Edit)
Template Jadual Bertugas Kelas (Boleh Edit)
 
Operation Blue Star - Saka Neela Tara
Operation Blue Star   -  Saka Neela TaraOperation Blue Star   -  Saka Neela Tara
Operation Blue Star - Saka Neela Tara
 
Model Attribute Check Company Auto Property
Model Attribute  Check Company Auto PropertyModel Attribute  Check Company Auto Property
Model Attribute Check Company Auto Property
 
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCECLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
 
ESC Beyond Borders _From EU to You_ InfoPack general.pdf
ESC Beyond Borders _From EU to You_ InfoPack general.pdfESC Beyond Borders _From EU to You_ InfoPack general.pdf
ESC Beyond Borders _From EU to You_ InfoPack general.pdf
 
2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...
 

UNIT - 01 INTRODUCTION

  • 1. 1 Prepared By: Mr.Premanand Desai L/EE B.L.D.E.A’s SHREE SANGANABASAVA MAHA SWAMIJI POLYTECHNIC, VIJAYAPUR-03 E-mail ID:ssmp.premananddesai@bldea.org cell no : +91 7892881829 COURSE & CODE : ELECTRICAL ESTIMATION AND COSTING (15EE54T) UNIT - 01 INTRODUCTION
  • 2. 2 COURSE & CODE : ELECTRICAL ESTIMATION AND COSTING (15EE54T) UNIT - 01 INTRODUCTION 1.1 Introduction Before commissioning any work, it is important to know the clear picture of the work, required materials, specification of the materials used and cost of the work. 1.2 Estimation Estimation means an assessment of the quantity of the materials and its cost required for any work. It includes listing of materials, stating their specifications and Approximate cost. OR Estimation includes calculation of quantity involved and quality aspect of material , so estimation is the art of finding out the cost so that we can fix the budget for that particular work. 1.3 Purpose/Need of Estimating 1. To Fix up the budget and complete details of the required materials for carrying out the complete work. 2. To Exercise control over quality of materials required depending upon the work to be executed. 3. To fix up the cost of various materials, including cost of labour , supervision , inspection ,transportation etc. 4. To find most economical procedure for the execution of work . 5. To keep the estimates in a systematic way for the future reference. 6. To ensure availability of all the materials required for execution of the project. 7. To avoid the misuse of material and money. 8. To reduce the time required for completion of the project. 9. To complete the project uninterruptedly.
  • 3. 3 1.4 Importance of Estimation 1. It give approximate budget for carrying out the work 2. Its avoids wastage of material. 3. It helps to use correct material. 4. It helps to do the work according to the engineering principles without any confusion in adopting different systems or methods. 1.5 Factors to be considered while preparing estimations Before initiating any electrical project the following factors related to estimation should be considered 1. Standard Performa for making estimation. 2. Specification of the materials. 3. Latest price list and Net prices of materials. 4. Overhead charges, Supervision charges and Labour charges. 5. Contingencies and stock incidental charges. 6. Inspection charges and Transportation charges. 7. Miscellaneous charges. 1.6 Qualities of good estimator: 1. He should have full practical experience and knowledge about preparing estimation. 2. He should have complete knowledge about the latest designs. 3. He should have full knowledge about the specification of materials and market prices. 4. He should have knowledge about the labour charges and other charges. 5. He should have good imagination and experimenting power because he should keep provision for future extension.
  • 4. 4 1.7 Define specification. Specification is a documented detailed description of materials, equipment’s and machineries etc. suit to the requirements. OR Set of documented requirements to be satisfied by materials, equipment’s, machineries, design etc. as per technical standard. 1.8 Importance of specification: 1. It provides clear details of the materials. 2. It gives quality and standards applied for materials. 3. It helps to purchase suitable materials. 4. It provides clear instructions about the quality of the materials. 5. It gives procedure for installation and using of materials. 1.9 Factors to be considered for specification: 1. Specification must be as per standards. 2. Economic factors to be considered. 3. Proper safety factor must be considered. 4. Specification must be as per the market availability of the materials. 1.10 standardization It is a process to achieve interchangeability and quantity control so that mass production is possible which reduces the cost. In India standards have been framed by Bureau of Indian Standard. 1.11 Advantages or Need of standardization 1. Standardization minimizes the cost due to mass production. 2. It improves the quality of the material. 3. Standardization causes interchangeability due to which easy replacement of material can be done. 4. Standardization avoids confusion to both supplier and user.
  • 5. 5 1.12. Charges 1.12.1 Overhead charges: Overhead charges include office expenses, salary of administrative staff, rents for office, lighting and heating expenses, travelling expenses, advertisements, insurance, and water expenses, depreciation of furniture’s etc. Normally 10-15% of the total estimated material and labour expenses are spent on overhead charges. 1.12.2 Labour charges: Labour charge is the most difficult and variable item to assess. It is affected by so many factors such as installation site condition, skill and technical training, physical fitness etc. By vast experience and proper records of time sheets, an intelligent estimator will be able to obtain labour values by the system of man-hour constant. 1.12.3 Contingencies: During erection of the project, there can be certain emergency expenses which cannot considered while calculating the material cost and labour expenses for the project. These additional emergency expenses may be due to any reason such as increase in cost of material or labour rates etc. Such additional expenses are called contingencies. For this, 3-5% of the material cost and labour cost is estimated. 1.12.4 Stock incidental charges: To cover the risk of damage during preservation, transportation, loading, unloading and handling or theft of material extra charge is included. It is normally 5% of total cost. 1.12.5 Inspection/Inspectorate charges: Inspection or testing of any electrical work (Generating station, substation, transmission line, distribution line etc) is done by government body for this charge is to be paid. So inspection charges are included in the estimation as per standard inspectorial charges. 1.12.6 Transportation charges: The cost of transporting materials or goods for the execution of a particular electrical installation or project work is called transportation charges.
  • 6. 6 1.12.7 Supervision charges: These charges are paid for supervision of work to the licensee/contractor at 10% of the estimated cost of the work. 1.12.8 Miscellaneous charges: For purchasing of minor items like nuts, bolts, raw plugs, coal, salt etc which cannot be mentioned in major works specification. The charges are paid in this head. The miscellaneous charges included in the estimation are lump sum also rounded the cost of estimation to a round figure. 1.12.9 Tender A tender is a formal offer made by one to another to supply goods or to do a particular job at certain specified cost. Generally business groups and Government departments’ issues notices for quotes for specified goods or services from other business or company which known as tender. If a contract is put out to tender, formal offers are invited. If a company wins a tender their offers is accepted. 1.12.10 Tender Notice It is process to call venders for doing a certain job or provide certain service at a competitive price. Usually done through the prominent newspaper of the region/official e-procurement websites. 1.12.11 Quotation An offer in terms of rates made by the supplier or manufacturer on a prescribed form enclosed in a sealed envelope, in reply to a tender notice for supply of material on the basis of some terms and a condition is called quotation. 1.12.12 Comparative statement This is an important document to evaluate the offers received against an enquiry. Utmost care must be exercised while preparing the comparative statement of tenders. Any deviation from the tendered specifications, delivery conditions, assistance etc. stipulated by the tenders should be highlight. A sample of comparative price statement is as shown in Table below;
  • 7. 7 Comparative Price Statement (CPS) No. of Tenders Received: Enquiry No: No. of Enquiries Issued: Date: Date of Opening of Tenders: Due Date: Sl No Description Quantity Previous purchases Current Offers Received Ordered Date Unit 1 2 3 4 5 6 No. Price 1.12.13 Purchase order A purchase order is legally binding document between a supplier and a buyer. It details the items the buyer agrees to purchase at a certain price point. It also outlines the delivery date and terms of payment for the buyer purchase order computer systems have made the purchasing process more efficient and allow for better inventory and payment tracking. 1.12.14 Work order A work order is an order received by an organization from a customer or client or an order created internally within the organization. A work order may before products or services. A work order sometimes is used in place of an "invoice" or "statement" and presented for payment requests. 1.13 Indian Electricity Act (I.E Act) An Act to amend the law retaining to the supply and use of electrical energy, rights and obligations of the licensees. Whereas it is expedient to amend the law relating to the supply and use of electrical energy. This Act may be called the Indian Electricity Act; 1910.It extends to the whole of India. The Electricity Supply Act, 1948 deals with the statutory powers and functions of the Central Electricity Authority. State electricity boards and generating companies. The electricity act 2003 is enacted to improve the backdrop of economic in power sector and
  • 8. 8 performance of state electricity boards. This deals with uniform and unified law to take care of the current needs of power sector in the areas of generation, transmission, trading and distribution of electricity. 1.14 Importance of Indian Electricity Act 1. It is a single legislation which addresses all the key areas of electricity in the country. 2. It provides a road map for overall and uniform development of electricity sector in the country 3. It takes care of interests of consumers belonging to various sectors 4. It also aims to reform the sector to suit the needs of the present day requirement in the light of globalization. 5. Through specific provisions it aims to bring in financial and commercial viability for power sector utilities. 1.15 Purpose of Indian Electricity Act 1. To consolidate the laws relating to generation, transmission, distribution, trading and use of electricity. 2. To take measures conducive for development of electricity sector. 3. To promote competition in the power sector. 4. To protect the interests of consumers. 5. To rationalize the electricity tariffs. 6. To establish regulatory commissions and appellate tribunal for electricity. 1.16 Indian electricity rules (IE Rules) In exercise of the powers conferred by section 37 of the Indian electricity act,1910 the central electricity board frames the rules to regulate the generation, transmission, supply and use of electrical energy. These rules called as Indian electricity rules 1956. 1.17 Importance of Indian Electricity Rules • They provides reliability and safety for electrical supply system • They focus on protection of persons and property from injury.
  • 9. 9 • They supplement the various codes of bureau of Indian standards. • They serve as a guideline for electrical practices in a country. 1.18 Purpose of Indian electricity rules • To regulate the relation between the supplier and consumer. • To make the generation, transmission and distribution of electricity as safe as possible. 1.19 Earthing The process of connecting metallic bodies of all the electrical apparatus and equipment to huge mass of earth by a wire having negligible resistance is called Earthing. OR The method of connecting noncurrent carrying parts of the electrical equipment or accessories or neutral point of the supply, system to the earth through the wire having negligible resistance is called electrical earthing. 1.19.1 Touch potential: Touch potential is the potential difference between the energized object and the feet of a person in contact with the object. 1.19.2 Step potential: Step potential is the potential difference between the feet of a person standing near an energized grounded object.
  • 10. 10 1.20 Necessity of earthing • To provide a protection for the apparatus, equipment’s, devices etc. against leakage current this may damage it. • To provide safety to the operator or the person coming in touch with electric supply. • Tripping due to earthing in case faults save wastage of electric energy excess current drawn during. • Protection of large buildings and all machines fed from overhead lines against lightning. • To serve as a returned conductor in communication and traction work. • To maintain the line voltage constant under unbalanced load condition 1.21 Points to be earthed: 1 Earth pin of sockets should be efficiently and permanently earthed. 2 All metallic covers of machines, starters and sheathing of wire should be earthed. 3 Iron clad switches and iron clad distribution boards should be earthed. 4 Metallic coverings of any electrical supply line should be earthed. 5 Stay wires for overhead lines should be connected to earth. 6 In a dc 3-wire system, the middle conductors should be earthed at the generating station. 1.22 Factors influencing earth resistance: • Soil resistivity: The earth resistance of an earth pit depends on soil resistivity. • Soil condition: Different soil gives different earth resistance. • Moisture: Moisture content is one of the controlling factors in earth resistivity. • Dissolved salts: Small quantity of salt reduces the earth resistivity.
  • 11. 11 • Temperature: As the temperature changes the earth resistance also changes. • The type of material used for earth electrode and earth wire. • Size of earth electrode and earth wire. 1.23 Methods of reducing earth resistance • Pour sufficient water in earth electrode periodically. • By increasing the cross sectional area of electrode. • By maintaining the temperature of the soil. • By increasing depth of the plate. • By installing number of electrodes in parallel. • Using sufficient quantity of coal and salt in the earthing pit. • Remove oxidation on joint and joints should be tightened. 1.24 Standard values of earth resistance for various installations. • Large power station – 0.5 Ω • Major Power Station – 1.0 Ω • Small Substation – 2.0 Ω • In all other cases – 5 Ω Maximum Earth continuity inside an installation that is from the earth plate to any point in the installation -1.0 Ω
  • 12. 12 1.25 Method of selecting the size of earth conductor. • For domestic Installation : GI or Copper Wire no. 8 SWG will be required to run from main distribution board to various submain distribution boards. Copper wire no.14 SWG will be required to run to three-pin socket outlets and connected to their earth sleeve. • For Motor Installation : In case of motor installation, the size of earth wire and earth plate used will depend upon the rating of the motor for which it is to be used. 1.26 Types / Methods of Earthing • Strip or Wire or Spiral Earthing • Rod Earthing • Mat Earthing • Plate Earthing • Pipe Earthing 1.27 Plate Earthing The plate earthing is as shown in the Figure 2. In this method a copper plate of 60cm x 60cm x 3mm or a GI plate of the size 60cm x 60cm x 6mm is used for earthing. The plate is placed vertically down inside the ground at a depth of 3m and is embedded in alternate layers of coal and salt for a thickness of 15 cm. In addition, water is poured for keeping the earth electrode resistance value well below a maximum of 5 ohms. The earth wire is securely bolted to the earth plate. A cement masonry chamber is built with a cast iron cover for easy regular maintenance. Capacity of motor / Equipment Size of earth wire in S W G Copper G.I Up to 10 hp No 8 No 8 Above 10 hp & up to 15 hp No 8 No 6 Above 15 hp & Up to 30 hp No 6 No 2 Above 30 hp & Up to 50 hp No 4 - Above 50 hp & Up to 100 hp No 2 or Strip 13mm × 2.5mm - Above 100 hp Strip 25 mm × 2.5mm -
  • 13. 13 1.27.1 Specification Plate Earthing Sl No Description Specification 1 Earth pit 1mtr diameter 3mtr depth 2 Pipe for earth conductor GI 50mm dia, 2mtr length 3 Earth electrode plate size Copper plate of 600mm x 600mm x 3mm or GI plate of 600mm x 600mm x 6mm 4 Earth strip for connection Copper earth strip of 25mm x 3mm 5 Filling of earth pit With charcoal and salt surrounding earth plate about 150mm 6 Pipe for water pouring 19 mm dia GI pipe 7 Construction of masonry Masonry brick work of height 450mm x work width 700mm with CI cover and CI frame
  • 14. 14 1.29 Pipe Earthing Pipe earthing is done by G.I. pipe as shown in Figure.1. Here a 38mmdia G.I.pipe 2.5m in length, 3 mm thickness having alternate cross holes of 12.mmdia at each 300 mm distance buried in a pit of 340mm diameter with alternative layers of coal and salt. The top of this pipe is connected to the funnel through 19 mm GI, pipe with the help of a reducer. At ground level a concrete bed is formed in such a way that a hollow rectangular solid shape is formed (150mm X 150mm X 250mm) with the insertion of GI pipe carrying the earth conductor. The above hollow pit is closed by Cast Iron cover. Pipe is connected to the apparatus by means of 8 SWG G I. wire with the help of bolts and nuts. To maintain the wetness in pit periodically (After every eight days in summer and winter) water is poured through the funnel. Always the earth resistance should be within 2 to 5 ohms, but for rocky soil it can be more.
  • 15. 15 1.29.1 Specification Plate Earthing Sl No Description Specification 1 Earth pit 1mtr diameter 4.5mtr depth 2 Pipe for earth conductor GI 40mm dia, 2.5mtr length, 3mm thickness 3 Pipe for water pouring 19 mm dia GI pipe 4 Filling of earth pit Alternative layer of charcoal and salt 2mtr from the bottom of pipe. 5 Construction of masonry Masonry brick work of height 450mm x work width 700mm with CI cover and CI frame 6 Identification of earth pit With suitable display board
  • 16. 16 MODEL QUESTIONS BANK • Cognitive Level: REMEMBER 1. Define estimation. List the factors to be considered while estimating. 2. List the qualities of a good estimator. 3. List the importance of estimation. 4. Define specification. List the factors to be considered. 5. Mention the importance of specification. 6. Define standardization. List the advantages. 7. Define earthing?. List the points that need to be earthed. 8. Draw a neat diagram of pipe earthing and label the parts. 9. Draw a neat diagram of plate earthing and label the parts. 10.List the specification of pipe earthing 11.List the specifications of plate earthing. 12.List the factors on which earth resistance depends. 13.List the methods of reducing earth resistance. • Cognitive level: Understanding/Analyse 1. Draw neat diagram of pipe earthing and label the parts with specifications. 2. Draw neat diagram of plate earthing and label the parts with specifications. 3. List the specifications of a) pipe earthing and b) plate earthing