SlideShare a Scribd company logo
1 of 14
Deep
excavation
Lee Siaw ChyI
0330451
Carolyn Low Sing Yee 0327652
Wan Yee Len
0330764
Wong Yong Le
0326478
List out the types of construction
method for deep excavation.
1. Open Cut
2. Bottom-Up
3. Top-down
Choose (1) type of
construction
method for deep
excavation and
explain the
sequence of
construction.
Top-down method
1) Install retaining wall, piles and basement
columns.
2) Struts are installed
3) Cast the basement top slab and beam.
4) Excavate the soil underneath and start construct
above.
5) Construct the 2nd basement slab while work above
ground continues.
Two (2) major
design
consideration
for deep
excavation.
• Planning of subsurface
investigation and laboratory testing
•Evaluation of foundation of
adjacent properties and their
tolerances
Two (2) importance of
implementing
excavation support
systems.
● To assess on the cost and time of
construction.
● To ensure that movements will not cause
damage to neighbouring structures or to
utilities in the surrounding ground.
This is a photo of excavation support system
for the Getty Center art museum garage in Los
Angeles, California. The excavation is about 75
feet deep. The sides of the excavation are
supported by soldier piles and lagging. The
soldier piles were driven before excavation
began, and the wood lagging were installed as
the excavation proceeded down. On the sides
of the excavation the soldier pile and lagging
wall is supported by post-tensioned anchors
drilled and grouted into the soil around the
excavation. The corners were supported by
corner braces.
Example
Explain
with a
sketch why
cantilever
wall is only
suitable for
shallow
excavation.
BASEMENT FLOOR LEVEL
GROUND LEVEL
ACTIVE EARTH
PRESSURE
- SOIL PRESSURE
- HYDROSTATIC
PRESSURE
PASSIVE
EARTH
PRESSURE
RETAINING
SIDE
EXCAVATED SIDE
Before excavation, the pressure is in
equilibrium state.
An imbalanced load situation is created when
the soil is unloaded on the excavated side.
EXCAVATED
SIDE
RETAINING SIDE
BASEMENT FLOOR LEVEL
GROUND LEVEL
ACTIVE EARTH
PRESSURE
- SOIL PRESSURE
- HYDROSTATIC
PRESSURE
PASSIVE EARTH
PRESSURE
RETAINING
SIDE
EXCAVATED SIDE
>18ft (6m) deep
Two types of additional support and their
advantages and disadvantages.
1. Ground Anchor
● Earth, percussion driven or mechanical anchors
● Hold, restrain and support building, civil engineering and other structures
Advantages
● Minimal disruption to surface
finishes while installing
● Able to hold capacity up to
3000kN
● Lightweight and corrosion
resistant
● Provides a clean area for the
construction of basement
Disadvantages
● Requires specific equipment and
professional engineers to
operate.
● Difficult to apply anchors in great
depth
● Great care must be taken to
prevent movement of ground
anchors and wall
2. Rakers
● Temporary support to unsafe
wall
● Also known as inclined shore,
varies with site condition
● Transfers floor and wall loads
to ground
● Difficult to assemble
● Must only rest against solid
masonry
● More secure compared to
other additionals supports
● Suitable for soft ground
area because the sole
piece area can be
increased
● Can be used for taller
houses
Advantages Disadvantages
Two (2) reasons for selecting interlocking steel sheet
piles as supporting system.
● Durable and Long lasting
○ Interlocks allow individual sections to be
connected continuously
○ Continuous steel wall that is earth tight
and water resistant
● Convenient and Easy to install
○ Readily available and transportable

More Related Content

What's hot (20)

Foundation
FoundationFoundation
Foundation
 
Cofferdam
CofferdamCofferdam
Cofferdam
 
Shoring
ShoringShoring
Shoring
 
Shoring
ShoringShoring
Shoring
 
BCT MODULE 2 - Caisson
BCT MODULE 2 - CaissonBCT MODULE 2 - Caisson
BCT MODULE 2 - Caisson
 
Solid Ground Floors
 Solid Ground Floors  Solid Ground Floors
Solid Ground Floors
 
DIFFERENT TYPE OF CRACKS AND PREVENTIVE MEASURE ON CRACKS
DIFFERENT TYPE OF CRACKS AND PREVENTIVE MEASURE ON CRACKS DIFFERENT TYPE OF CRACKS AND PREVENTIVE MEASURE ON CRACKS
DIFFERENT TYPE OF CRACKS AND PREVENTIVE MEASURE ON CRACKS
 
Diaphragm walls
Diaphragm wallsDiaphragm walls
Diaphragm walls
 
Deep excavation
Deep excavationDeep excavation
Deep excavation
 
Top Down Construction Presentation.
Top Down Construction Presentation.Top Down Construction Presentation.
Top Down Construction Presentation.
 
Curing & prefabrication of concrete structures@hemadurgarao-IIIT Nuzvid
Curing & prefabrication of concrete structures@hemadurgarao-IIIT NuzvidCuring & prefabrication of concrete structures@hemadurgarao-IIIT Nuzvid
Curing & prefabrication of concrete structures@hemadurgarao-IIIT Nuzvid
 
Retaining walls
Retaining wallsRetaining walls
Retaining walls
 
DEMOLITION AND DISMANTLING TECHNIQUES
DEMOLITION AND DISMANTLING TECHNIQUESDEMOLITION AND DISMANTLING TECHNIQUES
DEMOLITION AND DISMANTLING TECHNIQUES
 
Diaphragm wall
Diaphragm wallDiaphragm wall
Diaphragm wall
 
R.C.C. STAIRS
R.C.C. STAIRSR.C.C. STAIRS
R.C.C. STAIRS
 
Pile foundation ppt
Pile foundation pptPile foundation ppt
Pile foundation ppt
 
Types of foundations.
Types of foundations.Types of foundations.
Types of foundations.
 
Bored piles production method
Bored piles   production methodBored piles   production method
Bored piles production method
 
GUNITING
GUNITINGGUNITING
GUNITING
 
Safety precautions during demolition
Safety precautions during demolitionSafety precautions during demolition
Safety precautions during demolition
 

Similar to Construction Technology II (Seminar) - Deep excavation

Construction site
Construction siteConstruction site
Construction siteTimun Loh
 
Demolition of building and blasting equipment
Demolition of building and blasting equipmentDemolition of building and blasting equipment
Demolition of building and blasting equipmentChetan Karwa
 
Bcon final
Bcon finalBcon final
Bcon finaldicky177
 
Building technology.pptx
Building technology.pptxBuilding technology.pptx
Building technology.pptxNeha569445
 
EVALUATION OF VIBRATION LIMITS
EVALUATION OF VIBRATION LIMITSEVALUATION OF VIBRATION LIMITS
EVALUATION OF VIBRATION LIMITSGhassanAboodHabeeb
 
Building construction ii report (1)
Building construction ii report  (1)Building construction ii report  (1)
Building construction ii report (1)Chong jiayi
 
Soldier Bored and Diaphragm
Soldier Bored and DiaphragmSoldier Bored and Diaphragm
Soldier Bored and DiaphragmYingHongKang
 
final report last.pdf
final report last.pdffinal report last.pdf
final report last.pdfwzhen77
 
Lecture_all.pdf
Lecture_all.pdfLecture_all.pdf
Lecture_all.pdfRanadita
 
Experiencing Construction
Experiencing ConstructionExperiencing Construction
Experiencing ConstructionSNLim125
 
Building Construction Report
Building Construction ReportBuilding Construction Report
Building Construction ReportSheau Hui Tan
 
Earthquake Resistant Building Construction
Earthquake Resistant Building ConstructionEarthquake Resistant Building Construction
Earthquake Resistant Building ConstructionRohan Narvekar
 
REPORT ON ANALYSIS OF CONSTRUCTION SEQUENCES
REPORT ON 	ANALYSIS OF CONSTRUCTION SEQUENCES REPORT ON 	ANALYSIS OF CONSTRUCTION SEQUENCES
REPORT ON ANALYSIS OF CONSTRUCTION SEQUENCES Saleh Ahmed
 
Building Construction II Report
Building Construction II ReportBuilding Construction II Report
Building Construction II ReportBolin Loong
 
foundation and structural system of the shard building
foundation and structural system  of the shard buildingfoundation and structural system  of the shard building
foundation and structural system of the shard buildingBirukYared3
 

Similar to Construction Technology II (Seminar) - Deep excavation (20)

Micropile
MicropileMicropile
Micropile
 
Construction site
Construction siteConstruction site
Construction site
 
Demolition of building and blasting equipment
Demolition of building and blasting equipmentDemolition of building and blasting equipment
Demolition of building and blasting equipment
 
Bcon final
Bcon finalBcon final
Bcon final
 
Building technology.pptx
Building technology.pptxBuilding technology.pptx
Building technology.pptx
 
EVALUATION OF VIBRATION LIMITS
EVALUATION OF VIBRATION LIMITSEVALUATION OF VIBRATION LIMITS
EVALUATION OF VIBRATION LIMITS
 
Building construction ii report (1)
Building construction ii report  (1)Building construction ii report  (1)
Building construction ii report (1)
 
Soldier Bored and Diaphragm
Soldier Bored and DiaphragmSoldier Bored and Diaphragm
Soldier Bored and Diaphragm
 
Final_ppt_puneeth.pptx
Final_ppt_puneeth.pptxFinal_ppt_puneeth.pptx
Final_ppt_puneeth.pptx
 
final report last.pdf
final report last.pdffinal report last.pdf
final report last.pdf
 
Lecture_all.pdf
Lecture_all.pdfLecture_all.pdf
Lecture_all.pdf
 
Experiencing Construction
Experiencing ConstructionExperiencing Construction
Experiencing Construction
 
muslim project ppt.pptx
muslim project ppt.pptxmuslim project ppt.pptx
muslim project ppt.pptx
 
Building Construction Report
Building Construction ReportBuilding Construction Report
Building Construction Report
 
Earthquake Resistant Building Construction
Earthquake Resistant Building ConstructionEarthquake Resistant Building Construction
Earthquake Resistant Building Construction
 
Retaining wall (1)
Retaining wall (1)Retaining wall (1)
Retaining wall (1)
 
REPORT ON ANALYSIS OF CONSTRUCTION SEQUENCES
REPORT ON 	ANALYSIS OF CONSTRUCTION SEQUENCES REPORT ON 	ANALYSIS OF CONSTRUCTION SEQUENCES
REPORT ON ANALYSIS OF CONSTRUCTION SEQUENCES
 
Deep excavation report
Deep excavation reportDeep excavation report
Deep excavation report
 
Building Construction II Report
Building Construction II ReportBuilding Construction II Report
Building Construction II Report
 
foundation and structural system of the shard building
foundation and structural system  of the shard buildingfoundation and structural system  of the shard building
foundation and structural system of the shard building
 

More from Yee Len Wan

Development Economics (Group Assignment) - Financial appraisal presentation
Development Economics (Group Assignment) - Financial appraisal presentationDevelopment Economics (Group Assignment) - Financial appraisal presentation
Development Economics (Group Assignment) - Financial appraisal presentationYee Len Wan
 
Project Management (Alternative Assessment) - Proposed development in Taylor'...
Project Management (Alternative Assessment) - Proposed development in Taylor'...Project Management (Alternative Assessment) - Proposed development in Taylor'...
Project Management (Alternative Assessment) - Proposed development in Taylor'...Yee Len Wan
 
Value Management (Alternative Assessment) - Understanding and Learning outcome
Value Management (Alternative Assessment) - Understanding and Learning outcomeValue Management (Alternative Assessment) - Understanding and Learning outcome
Value Management (Alternative Assessment) - Understanding and Learning outcomeYee Len Wan
 
Development Economics (Group Assignment) - Financial appraisal
Development Economics (Group Assignment) - Financial appraisalDevelopment Economics (Group Assignment) - Financial appraisal
Development Economics (Group Assignment) - Financial appraisalYee Len Wan
 
Development Economics (Individual Assessment) - Market Research
Development Economics (Individual Assessment) - Market ResearchDevelopment Economics (Individual Assessment) - Market Research
Development Economics (Individual Assessment) - Market ResearchYee Len Wan
 
Project Management (individual Assignment) - MCO
Project Management (individual Assignment) - MCO Project Management (individual Assignment) - MCO
Project Management (individual Assignment) - MCO Yee Len Wan
 
Dissertation - VIVA Presentation - Evolution of Women in the Construction Ind...
Dissertation - VIVA Presentation - Evolution of Women in the Construction Ind...Dissertation - VIVA Presentation - Evolution of Women in the Construction Ind...
Dissertation - VIVA Presentation - Evolution of Women in the Construction Ind...Yee Len Wan
 
Structures (Group Assignment) - Structural Design and Analysis of a RC Bungalow
Structures (Group Assignment) - Structural Design and Analysis of a RC BungalowStructures (Group Assignment) - Structural Design and Analysis of a RC Bungalow
Structures (Group Assignment) - Structural Design and Analysis of a RC BungalowYee Len Wan
 
Integrated Assignment - Site Visit Report
Integrated Assignment - Site Visit ReportIntegrated Assignment - Site Visit Report
Integrated Assignment - Site Visit ReportYee Len Wan
 
Leading in the 21st Century (Group Presentation) - Mark Zuckerberg
Leading in the 21st Century (Group Presentation) - Mark ZuckerbergLeading in the 21st Century (Group Presentation) - Mark Zuckerberg
Leading in the 21st Century (Group Presentation) - Mark ZuckerbergYee Len Wan
 
Professional Practice I (Group Assignment) - Professional Ethics
Professional Practice I (Group Assignment) - Professional EthicsProfessional Practice I (Group Assignment) - Professional Ethics
Professional Practice I (Group Assignment) - Professional EthicsYee Len Wan
 
Construction Technology II (Seminar) - Scaffolding
Construction Technology II (Seminar) - ScaffoldingConstruction Technology II (Seminar) - Scaffolding
Construction Technology II (Seminar) - ScaffoldingYee Len Wan
 
Building Services & Civil Engineering Quantities (M5) - (Group Assignment) - BIM
Building Services & Civil Engineering Quantities (M5) - (Group Assignment) - BIMBuilding Services & Civil Engineering Quantities (M5) - (Group Assignment) - BIM
Building Services & Civil Engineering Quantities (M5) - (Group Assignment) - BIMYee Len Wan
 
Financial Management (Group Assignment) - Financial Analysis
Financial Management (Group Assignment) - Financial AnalysisFinancial Management (Group Assignment) - Financial Analysis
Financial Management (Group Assignment) - Financial AnalysisYee Len Wan
 
Professional Practice II (Group Assignment)
Professional Practice II (Group Assignment)Professional Practice II (Group Assignment)
Professional Practice II (Group Assignment)Yee Len Wan
 
Professional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOTProfessional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOTYee Len Wan
 
Building Economics Assignment - Preliminary Cost Appraisal - Presentation
Building Economics Assignment - Preliminary Cost Appraisal - PresentationBuilding Economics Assignment - Preliminary Cost Appraisal - Presentation
Building Economics Assignment - Preliminary Cost Appraisal - PresentationYee Len Wan
 
ECA: Elemental Cost Analysis (Measurement Workshop)
ECA: Elemental Cost Analysis (Measurement Workshop)ECA: Elemental Cost Analysis (Measurement Workshop)
ECA: Elemental Cost Analysis (Measurement Workshop)Yee Len Wan
 
Value Management - Tutorial - VM Practice: Enhancing value or cost cutting
Value Management - Tutorial - VM Practice: Enhancing value or cost cuttingValue Management - Tutorial - VM Practice: Enhancing value or cost cutting
Value Management - Tutorial - VM Practice: Enhancing value or cost cuttingYee Len Wan
 
Construction Law - Presentation - Construction Contractual Claims
Construction Law - Presentation - Construction Contractual ClaimsConstruction Law - Presentation - Construction Contractual Claims
Construction Law - Presentation - Construction Contractual ClaimsYee Len Wan
 

More from Yee Len Wan (20)

Development Economics (Group Assignment) - Financial appraisal presentation
Development Economics (Group Assignment) - Financial appraisal presentationDevelopment Economics (Group Assignment) - Financial appraisal presentation
Development Economics (Group Assignment) - Financial appraisal presentation
 
Project Management (Alternative Assessment) - Proposed development in Taylor'...
Project Management (Alternative Assessment) - Proposed development in Taylor'...Project Management (Alternative Assessment) - Proposed development in Taylor'...
Project Management (Alternative Assessment) - Proposed development in Taylor'...
 
Value Management (Alternative Assessment) - Understanding and Learning outcome
Value Management (Alternative Assessment) - Understanding and Learning outcomeValue Management (Alternative Assessment) - Understanding and Learning outcome
Value Management (Alternative Assessment) - Understanding and Learning outcome
 
Development Economics (Group Assignment) - Financial appraisal
Development Economics (Group Assignment) - Financial appraisalDevelopment Economics (Group Assignment) - Financial appraisal
Development Economics (Group Assignment) - Financial appraisal
 
Development Economics (Individual Assessment) - Market Research
Development Economics (Individual Assessment) - Market ResearchDevelopment Economics (Individual Assessment) - Market Research
Development Economics (Individual Assessment) - Market Research
 
Project Management (individual Assignment) - MCO
Project Management (individual Assignment) - MCO Project Management (individual Assignment) - MCO
Project Management (individual Assignment) - MCO
 
Dissertation - VIVA Presentation - Evolution of Women in the Construction Ind...
Dissertation - VIVA Presentation - Evolution of Women in the Construction Ind...Dissertation - VIVA Presentation - Evolution of Women in the Construction Ind...
Dissertation - VIVA Presentation - Evolution of Women in the Construction Ind...
 
Structures (Group Assignment) - Structural Design and Analysis of a RC Bungalow
Structures (Group Assignment) - Structural Design and Analysis of a RC BungalowStructures (Group Assignment) - Structural Design and Analysis of a RC Bungalow
Structures (Group Assignment) - Structural Design and Analysis of a RC Bungalow
 
Integrated Assignment - Site Visit Report
Integrated Assignment - Site Visit ReportIntegrated Assignment - Site Visit Report
Integrated Assignment - Site Visit Report
 
Leading in the 21st Century (Group Presentation) - Mark Zuckerberg
Leading in the 21st Century (Group Presentation) - Mark ZuckerbergLeading in the 21st Century (Group Presentation) - Mark Zuckerberg
Leading in the 21st Century (Group Presentation) - Mark Zuckerberg
 
Professional Practice I (Group Assignment) - Professional Ethics
Professional Practice I (Group Assignment) - Professional EthicsProfessional Practice I (Group Assignment) - Professional Ethics
Professional Practice I (Group Assignment) - Professional Ethics
 
Construction Technology II (Seminar) - Scaffolding
Construction Technology II (Seminar) - ScaffoldingConstruction Technology II (Seminar) - Scaffolding
Construction Technology II (Seminar) - Scaffolding
 
Building Services & Civil Engineering Quantities (M5) - (Group Assignment) - BIM
Building Services & Civil Engineering Quantities (M5) - (Group Assignment) - BIMBuilding Services & Civil Engineering Quantities (M5) - (Group Assignment) - BIM
Building Services & Civil Engineering Quantities (M5) - (Group Assignment) - BIM
 
Financial Management (Group Assignment) - Financial Analysis
Financial Management (Group Assignment) - Financial AnalysisFinancial Management (Group Assignment) - Financial Analysis
Financial Management (Group Assignment) - Financial Analysis
 
Professional Practice II (Group Assignment)
Professional Practice II (Group Assignment)Professional Practice II (Group Assignment)
Professional Practice II (Group Assignment)
 
Professional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOTProfessional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOT
 
Building Economics Assignment - Preliminary Cost Appraisal - Presentation
Building Economics Assignment - Preliminary Cost Appraisal - PresentationBuilding Economics Assignment - Preliminary Cost Appraisal - Presentation
Building Economics Assignment - Preliminary Cost Appraisal - Presentation
 
ECA: Elemental Cost Analysis (Measurement Workshop)
ECA: Elemental Cost Analysis (Measurement Workshop)ECA: Elemental Cost Analysis (Measurement Workshop)
ECA: Elemental Cost Analysis (Measurement Workshop)
 
Value Management - Tutorial - VM Practice: Enhancing value or cost cutting
Value Management - Tutorial - VM Practice: Enhancing value or cost cuttingValue Management - Tutorial - VM Practice: Enhancing value or cost cutting
Value Management - Tutorial - VM Practice: Enhancing value or cost cutting
 
Construction Law - Presentation - Construction Contractual Claims
Construction Law - Presentation - Construction Contractual ClaimsConstruction Law - Presentation - Construction Contractual Claims
Construction Law - Presentation - Construction Contractual Claims
 

Recently uploaded

Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactPECB
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3JemimahLaneBuaron
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfciinovamais
 
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991RKavithamani
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformChameera Dedduwage
 
Student login on Anyboli platform.helpin
Student login on Anyboli platform.helpinStudent login on Anyboli platform.helpin
Student login on Anyboli platform.helpinRaunakKeshri1
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...Marc Dusseiller Dusjagr
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxNirmalaLoungPoorunde1
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docxPoojaSen20
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingTechSoup
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppCeline George
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdfSoniaTolstoy
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...EduSkills OECD
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxiammrhaywood
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionSafetyChain Software
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeThiyagu K
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdfQucHHunhnh
 

Recently uploaded (20)

Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global Impact
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
 
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
 
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptxINDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy Reform
 
Student login on Anyboli platform.helpin
Student login on Anyboli platform.helpinStudent login on Anyboli platform.helpin
Student login on Anyboli platform.helpin
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
 
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdfTataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptx
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docx
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy Consulting
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website App
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory Inspection
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and Mode
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
 

Construction Technology II (Seminar) - Deep excavation

  • 1. Deep excavation Lee Siaw ChyI 0330451 Carolyn Low Sing Yee 0327652 Wan Yee Len 0330764 Wong Yong Le 0326478
  • 2. List out the types of construction method for deep excavation. 1. Open Cut 2. Bottom-Up 3. Top-down
  • 3. Choose (1) type of construction method for deep excavation and explain the sequence of construction. Top-down method 1) Install retaining wall, piles and basement columns. 2) Struts are installed 3) Cast the basement top slab and beam. 4) Excavate the soil underneath and start construct above. 5) Construct the 2nd basement slab while work above ground continues.
  • 4. Two (2) major design consideration for deep excavation. • Planning of subsurface investigation and laboratory testing •Evaluation of foundation of adjacent properties and their tolerances
  • 5. Two (2) importance of implementing excavation support systems. ● To assess on the cost and time of construction. ● To ensure that movements will not cause damage to neighbouring structures or to utilities in the surrounding ground.
  • 6. This is a photo of excavation support system for the Getty Center art museum garage in Los Angeles, California. The excavation is about 75 feet deep. The sides of the excavation are supported by soldier piles and lagging. The soldier piles were driven before excavation began, and the wood lagging were installed as the excavation proceeded down. On the sides of the excavation the soldier pile and lagging wall is supported by post-tensioned anchors drilled and grouted into the soil around the excavation. The corners were supported by corner braces. Example
  • 7. Explain with a sketch why cantilever wall is only suitable for shallow excavation. BASEMENT FLOOR LEVEL GROUND LEVEL ACTIVE EARTH PRESSURE - SOIL PRESSURE - HYDROSTATIC PRESSURE PASSIVE EARTH PRESSURE RETAINING SIDE EXCAVATED SIDE
  • 8. Before excavation, the pressure is in equilibrium state. An imbalanced load situation is created when the soil is unloaded on the excavated side. EXCAVATED SIDE RETAINING SIDE
  • 9. BASEMENT FLOOR LEVEL GROUND LEVEL ACTIVE EARTH PRESSURE - SOIL PRESSURE - HYDROSTATIC PRESSURE PASSIVE EARTH PRESSURE RETAINING SIDE EXCAVATED SIDE >18ft (6m) deep
  • 10. Two types of additional support and their advantages and disadvantages. 1. Ground Anchor ● Earth, percussion driven or mechanical anchors ● Hold, restrain and support building, civil engineering and other structures
  • 11. Advantages ● Minimal disruption to surface finishes while installing ● Able to hold capacity up to 3000kN ● Lightweight and corrosion resistant ● Provides a clean area for the construction of basement Disadvantages ● Requires specific equipment and professional engineers to operate. ● Difficult to apply anchors in great depth ● Great care must be taken to prevent movement of ground anchors and wall
  • 12. 2. Rakers ● Temporary support to unsafe wall ● Also known as inclined shore, varies with site condition ● Transfers floor and wall loads to ground
  • 13. ● Difficult to assemble ● Must only rest against solid masonry ● More secure compared to other additionals supports ● Suitable for soft ground area because the sole piece area can be increased ● Can be used for taller houses Advantages Disadvantages
  • 14. Two (2) reasons for selecting interlocking steel sheet piles as supporting system. ● Durable and Long lasting ○ Interlocks allow individual sections to be connected continuously ○ Continuous steel wall that is earth tight and water resistant ● Convenient and Easy to install ○ Readily available and transportable