SlideShare a Scribd company logo
1 of 4
Download to read offline
DEPARTMENT OF CONSTRUCTION MANAGEMENT
PROJECT COVER SHEET
STUDENT NAME: DC
STUDENT NUMBER: C 123
COURSE/ YEAR DT117/4
SUBJECT: Advanced Construction
Technology
PROJECT TITLE: Deep Basement Excavation
LECTURER:
FOR OFFICE USE ONLY:
DATE DUE: 10th
February 2016
DATE RECEIVED:
RECEIVED BY:
REPEAT PROJECT?
MARKS:
Introduction
The construction site for the prophase of the project will be a multi-story commercial dwelling with
deep basement carpark located in city centre at Smithfield where there is a high level of water content
as it is in close proximity to the river Liffey, lack of space due to other buildings, traffic level are high
and one way system is the only option. The design team have proposed ‘type C drained cavity’ basement
that will consist of ‘secant piling system that has to be delivered in accordance with the project schedule.
Project management has to plan for the following in relation to deep basement construction:
The first thing a CM will do is find out the ground conditions/cut-off points on the Smithfield project
determining the water levels below ground and depth of the required excavation. Also problems that
may be incurred during a city centre project are existing underground services such as water mains and
drainage. Cat-scan will be carried out to locate these services that will allow for additional measures
that may be necessary such as diversion of services. (DEEPEX, 2015)
Specific management plans
All basement projects are to include traffic management plan regards to impact on traffic surrounding
the site showing the impact for the construction schedule and surrounding services such as ambulances,
buses etc. and demolition management plan (CDMP) showing materials handling and storage,
establishment of welfare facilities for the workers on the site a clear construction sequence illustrated
with sketches and detailed diversion of working swears. (personal.cityu)
Project Scheduling
As time equals money quality of planning and scheduling of highly efficient working programme will
be vital for success of a safe on time project without any disturbances to works that may set back the
project to the completion date or require more resources that were not planned for. The project will
require layout and planning of the site accommodation and phasing/sectioning of the job. (teckrackher,
n.d.)
Associated risk and safety
(ADSC, 2015) Health and safety plan will have to be made stating the nature of the work, method
statement of the project, and risks associated with the project. Potential unforeseeable problems during
the construction process of deep basement construction are:
1. The effect of water ingress or pressure on the stability of bored pile walls and excavations
2. Collapse or failure of excavation walls
3. Disturbance of adjoining buildings and structures
Such risks will have to be eliminated by putting in place corrective measures such as:
1. To eliminate the effect of water egress predictability of conditions during the construction
period will be made. Temporary pumping and measures to prevent flooding will be installed.
Monitoring of water levels during construction period to predict potential risk.
2. To prevent the collapse of the basement wall anchors and tiebacks will be used to retain the
wall in place. Available expertise skill will be needed to calculate the vertical loads and lateral
loads to determine if the piles will be able to carry out their function additional shoring can be
placed against the excavated piles.
3. Disturbance to adjoining buildings can be eliminated through public relations and minimization
of the noise control during specified hours. Sprinkler systems will be used to eliminate
construction debris. (ADSC, 2015)
Introduction to Secant piles
The following section will focus on the construction methods used to
deliver Secant pile deep basement from site management perspective.
Secant pile walls are formed by drilling intersecting (one pile with
another) reinforced concrete piles. The research shows that secant
piles are reinforced with either steel rebar or with steel beams.
Primary (female) piles are installed first with secondary (male) piles
constructed in between primary (female) piles once the concrete
gains sufficient strength. Pile overlap is typically in the order of 8 cm
and can go in depths of up to 45 meters. (Baxter, 2012)
Construction procedures of secant pile wall
The secant pile wall will be set out with the piles distances centre-to-centre spacing and is drilled in two
stages. 1st
stage involves drilling and placing of primary piles and 2nd
stage will involve drilling the
secondary piles in-between the primary wall. (Concrete-group, 2016)
 The guide wall will be excavated which is a precast concrete wall to secure the wall alignment
but is not necessary.
 The male piles are bored through the female piles before the concrete has achieved its full
strength.
 Once the Rebar is placed and poured the levelling of the excavation can begin. First the guide
wall is removed.
 Once the wall is excavated to a depth of 2 meters ground anchors may be used.
Ground anchors
Ground anchors are used for installation that is capable of
transmitting an applied tensile load to a load bearing
section which may be a soil or rock to provide resistance to
structural movements. The advantage of ground anchors is
that excavation can stay unobstructed. The ground anchors
will be installed at an angle in the concrete pile. The hole
will be bored where the rebar will be placed and then
injected with concrete. The end of the anchor will be cut
and a cap put on top. (Ergun, 2008)
Ground water barriers
To achieve a water tightens it will be necessary for the CM
to build a skin wall to the sides of the piles. First step is by
cleaning the piles from any remaining spoil. Next shotcrete
will be pumped to the wall. Then waterproof membrane will
be placed on the wall by screwed to the main structure of
the wall. Once the membrane will be on polyethylene
studded sheets will be overlapped to seal the secant pile
wall. Then reinforced concrete levelled walls will be made
to cover the drainage system where it will be poured over
drainage pipe located 20cm from the wall. 50mm concrete
blinding will provide clean working surface for positioning
the mesh floor slab so the concrete can be poured pour.
Advantages of using secant piles
The main advantages of secant pile walls are:
1. Increased wall stiffness compared to sheet piles.
2. Can be installed in difficult ground.
3. Used in high water table conditions.
4. Columns can be as close as 5m from existing
buildings. (Wong, 2002)
The main disadvantages of secant pile walls are:
1. Verticality tolerances may be hard to achieve
for deep piles.
2. Total waterproofing is very difficult to obtain in
joints.
3. Increased cost compared to sheet pile.

More Related Content

What's hot

pile foundation and pile cap presentation
pile foundation and pile cap presentationpile foundation and pile cap presentation
pile foundation and pile cap presentationRahul bhatnagar
 
Modular Volumetric Construction
Modular Volumetric ConstructionModular Volumetric Construction
Modular Volumetric Constructionphilwdm
 
Type of structural joints
Type of structural joints Type of structural joints
Type of structural joints Hanzlahakhlaq
 
One Museum Park West (Post-Tensioning case study)
One Museum Park West (Post-Tensioning case study)One Museum Park West (Post-Tensioning case study)
One Museum Park West (Post-Tensioning case study)AMSYSCO Inc.
 
Case study iii 79&park
Case study iii 79&parkCase study iii 79&park
Case study iii 79&parkROHAN M JOSHI
 
Pre stressed concrete construction
Pre stressed concrete constructionPre stressed concrete construction
Pre stressed concrete constructionJenilPatel22
 
Prefabrication in construction
Prefabrication in constructionPrefabrication in construction
Prefabrication in constructionShailja km
 
Top down construction
Top down constructionTop down construction
Top down constructionANUPAM TIWARI
 
Expansion joints
Expansion jointsExpansion joints
Expansion jointsnamePPS
 
Scaffolding & underpinning
Scaffolding & underpinningScaffolding & underpinning
Scaffolding & underpinningJitesh Dhule
 
Precast concrete construction
Precast concrete constructionPrecast concrete construction
Precast concrete constructionMadan Mohan Jana
 
Prestressed Concrete
Prestressed ConcretePrestressed Concrete
Prestressed ConcreteRavi Savani
 
Defects and remedies of building
Defects and remedies of buildingDefects and remedies of building
Defects and remedies of buildingtoshi gupta
 
Modular construction
Modular constructionModular construction
Modular constructionKiran Gill
 

What's hot (20)

Table formwork
Table formwork Table formwork
Table formwork
 
pile foundation and pile cap presentation
pile foundation and pile cap presentationpile foundation and pile cap presentation
pile foundation and pile cap presentation
 
Modular Volumetric Construction
Modular Volumetric ConstructionModular Volumetric Construction
Modular Volumetric Construction
 
Type of structural joints
Type of structural joints Type of structural joints
Type of structural joints
 
One Museum Park West (Post-Tensioning case study)
One Museum Park West (Post-Tensioning case study)One Museum Park West (Post-Tensioning case study)
One Museum Park West (Post-Tensioning case study)
 
Prefabrication
PrefabricationPrefabrication
Prefabrication
 
Case study iii 79&park
Case study iii 79&parkCase study iii 79&park
Case study iii 79&park
 
Pre stressed concrete construction
Pre stressed concrete constructionPre stressed concrete construction
Pre stressed concrete construction
 
Prefabrication in construction
Prefabrication in constructionPrefabrication in construction
Prefabrication in construction
 
Top down construction
Top down constructionTop down construction
Top down construction
 
Underpinning
UnderpinningUnderpinning
Underpinning
 
Prestressing ppt
Prestressing pptPrestressing ppt
Prestressing ppt
 
Expansion joints
Expansion jointsExpansion joints
Expansion joints
 
Scaffolding & underpinning
Scaffolding & underpinningScaffolding & underpinning
Scaffolding & underpinning
 
Precast concrete construction
Precast concrete constructionPrecast concrete construction
Precast concrete construction
 
Prestressed Concrete
Prestressed ConcretePrestressed Concrete
Prestressed Concrete
 
Defects and remedies of building
Defects and remedies of buildingDefects and remedies of building
Defects and remedies of building
 
Modular construction
Modular constructionModular construction
Modular construction
 
Post Tension
Post TensionPost Tension
Post Tension
 
Deep excavation
Deep excavationDeep excavation
Deep excavation
 

Viewers also liked

basement excavation, underpinning
basement excavation, underpinningbasement excavation, underpinning
basement excavation, underpinningOkwera David
 
Smart city proposal citizens initiative for smart portblair - final lite ver
Smart city proposal   citizens initiative for smart portblair - final lite verSmart city proposal   citizens initiative for smart portblair - final lite ver
Smart city proposal citizens initiative for smart portblair - final lite verANIRBAN CHOUDHURY
 

Viewers also liked (6)

EXCAVATIONS
EXCAVATIONSEXCAVATIONS
EXCAVATIONS
 
basement excavation, underpinning
basement excavation, underpinningbasement excavation, underpinning
basement excavation, underpinning
 
Smart city proposal citizens initiative for smart portblair - final lite ver
Smart city proposal   citizens initiative for smart portblair - final lite verSmart city proposal   citizens initiative for smart portblair - final lite ver
Smart city proposal citizens initiative for smart portblair - final lite ver
 
Deep excavations
Deep excavationsDeep excavations
Deep excavations
 
Deep carious lesions
Deep carious lesionsDeep carious lesions
Deep carious lesions
 
Excavations ppt
Excavations pptExcavations ppt
Excavations ppt
 

Similar to Deep basement excavation

CT III IBS Formwork System
CT III IBS Formwork System CT III IBS Formwork System
CT III IBS Formwork System ashleyyeap
 
accelerated bridge construction(ABC)
accelerated bridge construction(ABC)accelerated bridge construction(ABC)
accelerated bridge construction(ABC)varun km
 
Summer training report
Summer training reportSummer training report
Summer training reportaki8872233
 
Speedy construction- FORMS AND MATERIALS
Speedy construction- FORMS AND MATERIALSSpeedy construction- FORMS AND MATERIALS
Speedy construction- FORMS AND MATERIALSSOUMYA KHANDELWAL
 
Lecture_all.pdf
Lecture_all.pdfLecture_all.pdf
Lecture_all.pdfRanadita
 
GROUP PROJECT: PROPOSAL FOR THE FINISHED/ EXISTING BUILDING CONSTRUCTION (CAS...
GROUP PROJECT: PROPOSAL FOR THE FINISHED/ EXISTING BUILDING CONSTRUCTION (CAS...GROUP PROJECT: PROPOSAL FOR THE FINISHED/ EXISTING BUILDING CONSTRUCTION (CAS...
GROUP PROJECT: PROPOSAL FOR THE FINISHED/ EXISTING BUILDING CONSTRUCTION (CAS...Firdaurs Abdullah
 
Pre-Cast Technology: An Initial Step to Sustainable Development
Pre-Cast Technology: An Initial Step to Sustainable DevelopmentPre-Cast Technology: An Initial Step to Sustainable Development
Pre-Cast Technology: An Initial Step to Sustainable Developmentijsrd.com
 
Precast Concrete is the most prominent structure
Precast Concrete is the most prominent structurePrecast Concrete is the most prominent structure
Precast Concrete is the most prominent structureNisshantSinghSaud
 
Bubble deck & hollow core slab
Bubble deck & hollow core slabBubble deck & hollow core slab
Bubble deck & hollow core slabErik Ong
 
Bubble deck&hollow core slab
Bubble deck&hollow core slabBubble deck&hollow core slab
Bubble deck&hollow core slabPenny3688
 
Continuous rigid PC frame box girder cantilever pouring construction reasonab...
Continuous rigid PC frame box girder cantilever pouring construction reasonab...Continuous rigid PC frame box girder cantilever pouring construction reasonab...
Continuous rigid PC frame box girder cantilever pouring construction reasonab...IJERA Editor
 
Ct bm measurement report
Ct bm measurement reportCt bm measurement report
Ct bm measurement reportKailyn Lee
 
02_Precast-and-Cast-in-Place.ppt
02_Precast-and-Cast-in-Place.ppt02_Precast-and-Cast-in-Place.ppt
02_Precast-and-Cast-in-Place.pptssusera0ac221
 
Essential Design Criteria for Safe Braced Cuts in Excavation Projects
Essential Design Criteria for Safe Braced Cuts in Excavation ProjectsEssential Design Criteria for Safe Braced Cuts in Excavation Projects
Essential Design Criteria for Safe Braced Cuts in Excavation ProjectsErbil Polytechnic University
 
Methodology for Prevention and Repair of Cracks in Building
Methodology for Prevention and Repair of Cracks in BuildingMethodology for Prevention and Repair of Cracks in Building
Methodology for Prevention and Repair of Cracks in BuildingGRD Journals
 

Similar to Deep basement excavation (20)

Mod. 1.pptx
Mod. 1.pptxMod. 1.pptx
Mod. 1.pptx
 
JEEVA.pptx
JEEVA.pptxJEEVA.pptx
JEEVA.pptx
 
CT III IBS Formwork System
CT III IBS Formwork System CT III IBS Formwork System
CT III IBS Formwork System
 
vacation work report 2
vacation work report 2vacation work report 2
vacation work report 2
 
accelerated bridge construction(ABC)
accelerated bridge construction(ABC)accelerated bridge construction(ABC)
accelerated bridge construction(ABC)
 
Summer training report
Summer training reportSummer training report
Summer training report
 
Site report 1
Site report 1Site report 1
Site report 1
 
Speedy construction- FORMS AND MATERIALS
Speedy construction- FORMS AND MATERIALSSpeedy construction- FORMS AND MATERIALS
Speedy construction- FORMS AND MATERIALS
 
Lecture_all.pdf
Lecture_all.pdfLecture_all.pdf
Lecture_all.pdf
 
GROUP PROJECT: PROPOSAL FOR THE FINISHED/ EXISTING BUILDING CONSTRUCTION (CAS...
GROUP PROJECT: PROPOSAL FOR THE FINISHED/ EXISTING BUILDING CONSTRUCTION (CAS...GROUP PROJECT: PROPOSAL FOR THE FINISHED/ EXISTING BUILDING CONSTRUCTION (CAS...
GROUP PROJECT: PROPOSAL FOR THE FINISHED/ EXISTING BUILDING CONSTRUCTION (CAS...
 
Pre-Cast Technology: An Initial Step to Sustainable Development
Pre-Cast Technology: An Initial Step to Sustainable DevelopmentPre-Cast Technology: An Initial Step to Sustainable Development
Pre-Cast Technology: An Initial Step to Sustainable Development
 
Precast Concrete is the most prominent structure
Precast Concrete is the most prominent structurePrecast Concrete is the most prominent structure
Precast Concrete is the most prominent structure
 
Bubble deck & hollow core slab
Bubble deck & hollow core slabBubble deck & hollow core slab
Bubble deck & hollow core slab
 
Bubble deck&hollow core slab
Bubble deck&hollow core slabBubble deck&hollow core slab
Bubble deck&hollow core slab
 
Continuous rigid PC frame box girder cantilever pouring construction reasonab...
Continuous rigid PC frame box girder cantilever pouring construction reasonab...Continuous rigid PC frame box girder cantilever pouring construction reasonab...
Continuous rigid PC frame box girder cantilever pouring construction reasonab...
 
Ct bm measurement report
Ct bm measurement reportCt bm measurement report
Ct bm measurement report
 
02_Precast-and-Cast-in-Place.ppt
02_Precast-and-Cast-in-Place.ppt02_Precast-and-Cast-in-Place.ppt
02_Precast-and-Cast-in-Place.ppt
 
Essential Design Criteria for Safe Braced Cuts in Excavation Projects
Essential Design Criteria for Safe Braced Cuts in Excavation ProjectsEssential Design Criteria for Safe Braced Cuts in Excavation Projects
Essential Design Criteria for Safe Braced Cuts in Excavation Projects
 
Methodology for Prevention and Repair of Cracks in Building
Methodology for Prevention and Repair of Cracks in BuildingMethodology for Prevention and Repair of Cracks in Building
Methodology for Prevention and Repair of Cracks in Building
 
Connstruction engg ppt 2016
Connstruction engg ppt 2016Connstruction engg ppt 2016
Connstruction engg ppt 2016
 

Recently uploaded

Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxvipinkmenon1
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 

Recently uploaded (20)

Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptx
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 

Deep basement excavation

  • 1. DEPARTMENT OF CONSTRUCTION MANAGEMENT PROJECT COVER SHEET STUDENT NAME: DC STUDENT NUMBER: C 123 COURSE/ YEAR DT117/4 SUBJECT: Advanced Construction Technology PROJECT TITLE: Deep Basement Excavation LECTURER: FOR OFFICE USE ONLY: DATE DUE: 10th February 2016 DATE RECEIVED: RECEIVED BY: REPEAT PROJECT? MARKS:
  • 2. Introduction The construction site for the prophase of the project will be a multi-story commercial dwelling with deep basement carpark located in city centre at Smithfield where there is a high level of water content as it is in close proximity to the river Liffey, lack of space due to other buildings, traffic level are high and one way system is the only option. The design team have proposed ‘type C drained cavity’ basement that will consist of ‘secant piling system that has to be delivered in accordance with the project schedule. Project management has to plan for the following in relation to deep basement construction: The first thing a CM will do is find out the ground conditions/cut-off points on the Smithfield project determining the water levels below ground and depth of the required excavation. Also problems that may be incurred during a city centre project are existing underground services such as water mains and drainage. Cat-scan will be carried out to locate these services that will allow for additional measures that may be necessary such as diversion of services. (DEEPEX, 2015) Specific management plans All basement projects are to include traffic management plan regards to impact on traffic surrounding the site showing the impact for the construction schedule and surrounding services such as ambulances, buses etc. and demolition management plan (CDMP) showing materials handling and storage, establishment of welfare facilities for the workers on the site a clear construction sequence illustrated with sketches and detailed diversion of working swears. (personal.cityu) Project Scheduling As time equals money quality of planning and scheduling of highly efficient working programme will be vital for success of a safe on time project without any disturbances to works that may set back the project to the completion date or require more resources that were not planned for. The project will require layout and planning of the site accommodation and phasing/sectioning of the job. (teckrackher, n.d.) Associated risk and safety (ADSC, 2015) Health and safety plan will have to be made stating the nature of the work, method statement of the project, and risks associated with the project. Potential unforeseeable problems during the construction process of deep basement construction are: 1. The effect of water ingress or pressure on the stability of bored pile walls and excavations 2. Collapse or failure of excavation walls 3. Disturbance of adjoining buildings and structures Such risks will have to be eliminated by putting in place corrective measures such as: 1. To eliminate the effect of water egress predictability of conditions during the construction period will be made. Temporary pumping and measures to prevent flooding will be installed. Monitoring of water levels during construction period to predict potential risk. 2. To prevent the collapse of the basement wall anchors and tiebacks will be used to retain the wall in place. Available expertise skill will be needed to calculate the vertical loads and lateral loads to determine if the piles will be able to carry out their function additional shoring can be placed against the excavated piles. 3. Disturbance to adjoining buildings can be eliminated through public relations and minimization of the noise control during specified hours. Sprinkler systems will be used to eliminate construction debris. (ADSC, 2015)
  • 3. Introduction to Secant piles The following section will focus on the construction methods used to deliver Secant pile deep basement from site management perspective. Secant pile walls are formed by drilling intersecting (one pile with another) reinforced concrete piles. The research shows that secant piles are reinforced with either steel rebar or with steel beams. Primary (female) piles are installed first with secondary (male) piles constructed in between primary (female) piles once the concrete gains sufficient strength. Pile overlap is typically in the order of 8 cm and can go in depths of up to 45 meters. (Baxter, 2012) Construction procedures of secant pile wall The secant pile wall will be set out with the piles distances centre-to-centre spacing and is drilled in two stages. 1st stage involves drilling and placing of primary piles and 2nd stage will involve drilling the secondary piles in-between the primary wall. (Concrete-group, 2016)  The guide wall will be excavated which is a precast concrete wall to secure the wall alignment but is not necessary.  The male piles are bored through the female piles before the concrete has achieved its full strength.  Once the Rebar is placed and poured the levelling of the excavation can begin. First the guide wall is removed.  Once the wall is excavated to a depth of 2 meters ground anchors may be used. Ground anchors Ground anchors are used for installation that is capable of transmitting an applied tensile load to a load bearing section which may be a soil or rock to provide resistance to structural movements. The advantage of ground anchors is that excavation can stay unobstructed. The ground anchors will be installed at an angle in the concrete pile. The hole will be bored where the rebar will be placed and then injected with concrete. The end of the anchor will be cut and a cap put on top. (Ergun, 2008) Ground water barriers To achieve a water tightens it will be necessary for the CM to build a skin wall to the sides of the piles. First step is by cleaning the piles from any remaining spoil. Next shotcrete will be pumped to the wall. Then waterproof membrane will be placed on the wall by screwed to the main structure of the wall. Once the membrane will be on polyethylene studded sheets will be overlapped to seal the secant pile wall. Then reinforced concrete levelled walls will be made to cover the drainage system where it will be poured over drainage pipe located 20cm from the wall. 50mm concrete blinding will provide clean working surface for positioning the mesh floor slab so the concrete can be poured pour.
  • 4. Advantages of using secant piles The main advantages of secant pile walls are: 1. Increased wall stiffness compared to sheet piles. 2. Can be installed in difficult ground. 3. Used in high water table conditions. 4. Columns can be as close as 5m from existing buildings. (Wong, 2002) The main disadvantages of secant pile walls are: 1. Verticality tolerances may be hard to achieve for deep piles. 2. Total waterproofing is very difficult to obtain in joints. 3. Increased cost compared to sheet pile.