Reasons to Reduce Project Durations:
 1.     To realize incentive pay
 2.     To fit within the contractually required time (influences
        Bid price).
 3.     To avoid paying Liquated Damages/Damage for delay
        causes (or avoid damaging the company’s
        relationship).
 4.     To complete a project early & move on to another
        project (Although the Job-specify profit may reduce,
        company profile may increase).
 5.     To complete a project when weather conditions make
        it less expensive (Avoid temporary Heating, avoid
        completing site work during raining season).

 Spring 2008,               Time-Cost-Trade-off                     1
 King Saud University       Dr. Khalid Al-Gahtani
Methods to reduce durations:
1.     Have the existing crew work overtime. This increase
       the labor costs due to increase pay rate and decrease
       productivity.
2.     Bring in additional workers to enlarge crew size. This
       increases labor costs due to overcrowding and poor
       learning curve.
3.     Use better/more advanced equipment. This will usually
       increase costs due to rental and transport fees. If labor
       costs (per unit) are reduced, this could reduce costs.
4.     Add subcontracted labor to the activity. This almost
       always increases the cost of an activity unless the
       subcontracted labor is for more efficient.

Spring 2008,              Time-Cost-Trade-off                  2
King Saud University      Dr. Khalid Al-Gahtani
Project Costs Definitions




Spring 2008,           Time-Cost-Trade-off     3
King Saud University   Dr. Khalid Al-Gahtani
Practices to Estimate the Project cost
• Some company assigns Overhead office as % of
  direct cost.
• Most companies don’t consider profit as a cost
  of the job. Instead, analysis are completed by
  using Direct costs + Indirect costs + Company
  overhead vs. Budgeted (estimated costs).
• Similar to each activity, the project as a whole
  has an ideal (Lease expensive) Duration.


Spring 2008,           Time-Cost-Trade-off       4
King Saud University   Dr. Khalid Al-Gahtani
Spring 2008,           Time-Cost-Trade-off     5
King Saud University   Dr. Khalid Al-Gahtani
Accelerating the Critical and
                Noncritical path




Spring 2008,           Time-Cost-Trade-off     6
King Saud University   Dr. Khalid Al-Gahtani
Network Compression Algorithm
•      Determine Normal project duration, and
       cost.
•      Identify Normal duration Critical Path.
•      For large network, using CRITICALITY
       THEORM to eliminate the noncritical
       paths that do not need to be crashed.
•      Compute the cost slop :
         co st slo pe =     crash co st - no rmal co st
                          no rmal duratio n- crash duratio n
Spring 2008,                    Time-Cost-Trade-off            7
King Saud University            Dr. Khalid Al-Gahtani
Network Compression Algorithm
• shortening the CRITICAL ACTIVITIES
  beginning with the activity having the
  lowest cost-slope
• Determine the compression limit (Nil)
                        - C rash L im it, or
 N il = M in            - Free F lo at o f any o f the no n crit ica l a ctivit ie s
                       in the para lle l paths co m pet ing fo r crit ica l path.*




Spring 2008,                         Time-Cost-Trade-off                               8
King Saud University                 Dr. Khalid Al-Gahtani
Network Compression Algorithm
• Organize the data as in the following table:
• yc le toAS ho rten S C artened N il S ho rtened C oDsta y CC yc le r T otal DPuratio n
C
  #
           ct ivit y
                       ho
                          n Be           D a ys           per o st fo
                                                                       C o st
                                                                                ro ject

  0
  1
  2
  3




• Update the project network


Spring 2008,                      Time-Cost-Trade-off                                9
King Saud University              Dr. Khalid Al-Gahtani
Network Compression Algorithm
• When a new Critical path is formed:
     – Shorten the combination of activity which
       Falls on Both Critical Paths, OR
     – Shorten one activity from each of the critical
       paths. Use the combined cost of shortening
       both activities when determining if it is cost
       effective to shorten the project.
• At each shortening cycle, compute the
  new project duration and project cost
Spring 2008,           Time-Cost-Trade-off              10
King Saud University   Dr. Khalid Al-Gahtani
Network Compression Algorithm
• Continue until no further shortening is possible
• Tabulate and Plot the Indirect project Cost on
  the same time-cost graph
              C yc le P ro ject        D irect        Ind ire ct   T otal
                 #    D uratio n        C o st          C o st     C o st
                  0
                  1
                  2
                  3

 Spring 2008,                      Time-Cost-Trade-off                      11
 King Saud University              Dr. Khalid Al-Gahtani
Network Compression Algorithm
•      Add direct and indirect cost to find the
       project cost at each duration.
•      Use the total project cost-time curve to
       find the optimum time.




Spring 2008,           Time-Cost-Trade-off        12
King Saud University   Dr. Khalid Al-Gahtani
E xa m p le 1:
          T he duratio ns a nd d irect co sts fo r each activity in the netw o rk o f a sm a ll co nstructio n
co ntract under bo th no rm a l a nd crash co nd it io ns are g ive n in be lo w T able. E stablish the least
co st fo r exped iting the co ntract . D eterm ine the o ptim u m duratio n o f the co ntract assu m ing the
ind irect co st am o unts to S R 125/w eek.

                                                   N o rm a l                        C rash
        A ctivity     P receded by        D uratio n          C o st       D uratio n          C o st
                                          (w eeks)            (S R )       (w eeks)            (S R )
           A                —                12               7000             10             7200
           B                 A                8               5000              6             5300
           C                 A               15               4000             12             4600
           D                 B               23               5000             23             5000
           E                 B                5               1000              4             1050
           F                 C                5               3000              4             3300
           G               E ,C              20               6000             15             6300
           H                 F               13               2500             11             2580
           I              D, G, H            12               3000             10             3150
                                                              36,500

   Spring 2008,                             Time-Cost-Trade-off                                         13
   King Saud University                     Dr. Khalid Al-Gahtani
20    23     43
                                                    D                           4
                                              24     4     47
                                                     0


0    12   12       12    8        20          20     5     25        27    20       47         47      12       59
     A                   B                          E                      G                            I
0     0 12         14    2        22          22     2     27        27     0 47               47     0 59
    2@ 100             2@ 150                      1@ 50                  5@ 60                     2@ 75

                                                                                         2
                   12    15       27          27     5     32        32    13       45
                                                                                                ES       D      EF
                         C                           F                     H
                                                                                                      A ctivity
                   12 0 27                    29     2     34        34     2       47
                                                                                                LS          F   LF
                     3@ 200                    1@ 300                     2@ 40
                                                                                                 C rash lim it



C yc le A ct ivit y   Can Be                     D a ys C o st per C o st fo r            T otal         P ro ject
                                       N il
  #    to S ho rten S ho rtened               S ho rtened W e ek    C yc le               C o st        D uratio n
     0                                                                                   3 6 ,5 0 0             59
     1         G              5         2            2          60          120          3 6 ,6 2 0             57


Spring 2008,                                Time-Cost-Trade-off                                                      14
King Saud University                        Dr. Khalid Al-Gahtani
20    23     43
                                                        D
                                                  22     2     45
                                                         0


0     12   12          12   8        20           20     5     25        27    18    45        45       12      57
      A                     B                            E                     G                        I
0     0 12             14   2        22           22     2     27        27     0 47           45       0       55
    2@ 100              2@ 150                         1@ 50                  3@ 60                     0


                       12   15       27           27     5     32        32    13    45
                                                                                                   ES    D        EF
                            C                            F                     H
                                                                                                    A ctivity
                       12 0 27                    27 0 32                32     0 45
                         3@ 200                     1@ 300                    2@ 40                LS       F     LF
                                                                                                   C rash lim it



    C yc le A ct ivit y   Can Be                    D a ys C o st per C o st fo r         T otal      P ro ject
                                          N il
      #    to S ho rten S ho rtened              S ho rtened W e ek    C yc le            C o st     D uratio n
      0                                                                                   36,500             59
      1         G                5         2            2           60         120        36,620             57
      2         I                2         2            2           70         140        36,760             55

Spring 2008,                                   Time-Cost-Trade-off                                                   15
King Saud University                           Dr. Khalid Al-Gahtani
20    23       43
                                                       D
                                                 22     2       45
                                                        0


0    12   12           12   8        20          20     5       25         27    18   45      45     10       55
     A
               0            B                           E                        G                    I
0     0 12             14   2        22          22     2       27         27     0 45        45      0       55
    2@ 100              2@ 150                        1@ 50                     3@ 60                 0


                       12   15       27          27     5       32         32    13   45
                                                                                               ES      D      EF
                            C                           F                        H
                                                                                                    A ctivity
                       12 0 27                   27 0 32                   32     0 45
                                                                                               LS         F   LF
                         3@ 200                    1@ 300                       2@ 40
                                                                                               C rash lim it

 C yc le A ct ivit y   Can Be                       D a ys C o st per C o st fo r          T otal          P ro ject
                                          N il
   #    to S ho rten S ho rtened                 S ho rtened W e ek    C yc le             C o st         D uratio n
     0                                                                                     36,500             59
     1         G                 5         2                2        60              120   36,620             57
     2         I                 2                          2        70              140   36,760             55
     3         A                 2                          2        100             200   36,960             53
Spring 2008,                                Time-Cost-Trade-off                                                    16
King Saud University                        Dr. Khalid Al-Gahtani
18    23     41
                                                     D                               2
                                               20     2     43
                                                      0


0       10   10        10   8    18            20     5     25            25    18       43            43    10       53
        A                   B                         E                         G                             I
0       0    10        12   2    20            22     2     27            25     0 43                  43     0       53
        0               2@ 150                      1@ 50                      3@ 60                          0


                       10   15   25            25     5     30            30    13       43
                                                                                                        ES     D       EF
                            C                         F                         H
                                                                                                            A ctivity
                       10 0 25                 25 0 30                    30     0 43
                                                                                                        LS        F    LF
                         3@ 200                  1@ 300                        2@ 40
                                                                                                        C rash lim it

C yc le A ct ivit y   Can Be                     D a ys C o st per C o st fo r                T otal         P ro ject
                                      N il
  #    to S ho rten S ho rtened               S ho rtened W e ek    C yc le                   C o st        D uratio n
    0                                                                                         36 ,500             59
    1             G         5          2             2            60           1 20           36 ,620             57
    2             I         2                        2            70           140            36 ,760             55
    3          A            2                        2            100          200            36 ,960             53
    4         H, G          2          2             2           60+ 40        200            37 ,160             51
Spring 2008,                                 Time-Cost-Trade-off                                                           17
King Saud University                         Dr. Khalid Al-Gahtani
18     23     41
                                                        D
                                                 18      0     41
                                                         0


0       10   10        10   8    18              18      5     23        25    16   41            41    10       51
        A                   B             0              E                     G                         I
0       0    10        10 0 18                   20      2     25        25     0 41              41     0       51
        0                2@ 150                        1@ 50                  1@ 60                      0


                       10   15   25              25      5     30        30    11   41
                                                                                                  ES      D      EF
                            C                            F                     H
                                                                                                       A ctivity
                       10 0 25                   25 0 30                 30    0    41
                                                                                                  LS         F   LF
                         3@ 200                    1@ 300                      0
                                                                                                   C rash lim it

C yc le A ct ivit y   Can Be            D a ys  C o st per C o st fo r                   T otal    P ro ject
                                N il
  #    to S ho rten S ho rtened      S ho rtened W e ek     C yc le                      C o st   D uratio n
    0                                                                                    36,500         59
    1             G         5         2            2                60    120            36,620         57
    2             I         2                      2                70    140            36,760         55
  3          A              2                       2         100         200            36,960         53
  4       G, H              2         2             2        60+ 40       200            37,160         51
Spring 2008,                                  Time-Cost-Trade-off                                          18
  5       B, C
King Saud University        2                       2       150+ 200
                                              Dr. Khalid Al-Gahtani       700            37,860         49
16    23     39
                                                  D
                                            16     0     39
                                                   0


     0   10   10         10   6    16       16     5     21          23     16    39      39    10       49
         A                    B                   E                         G                    I
     0   0    10         10   0    16       18     2     23          23      0 39         39     0       49
         0                    0                  1@ 50                     1@ 60                 0


                         10   13   23       23     5     28          28     11    39
                                                                                          ES      D      EF
                              C                    F                        H
                                                                                               A ctivity
                         10 0 23            23 0 28                  28     0     39
                           1@ 200             1@ 300                        0             LS         F   LF
                                                                                           C rash lim it

                       C yc le P ro ject     D irect          Ind ire ct         T otal
                          #    D uratio n     C o st            C o st           C o st
                         0          59       36500             7375             43875
                         1          57       36620             7125             43745
                         2          55       36760             6875             43635
                         3          53       36960             6625             43585
                         4          51       37160             6375             43535
                         5          49       37860             6125             43985
Spring 2008,                             Time-Cost-Trade-off                                                  19
King Saud University                     Dr. Khalid Al-Gahtani
Project Optimal Duration
            50000
            45000
            40000
            35000                                                                         Direct
                                                                                          Cost
Cost (SR)




            30000
                                                                                          Indirect
            25000
                                                                                          cost
            20000                                                                         Total
            15000                                                                         Cost

            10000
            5000
               0
                    48   49   50   51   52   53    54    55    56     57   58   59   60
                                        Project Duration (Week)

      Spring 2008,                            Time-Cost-Trade-off                             20
      King Saud University                    Dr. Khalid Al-Gahtani
C la ss W o rk #2

D ata o n sm a ll m a inte na nce pro ject is g ive n a s be lo w :

                         D epend s              N o rm a l                         C rash
           A ct ivit y       on           T im e         C o st        T im e               C o st
               A                          6 da ys        $700          4 da ys          $800
               B                          4 da ys            400       4 da ys              400
               C                          5 da ys            650       4 da ys              700
               D             A           8 da ys             625       5   da ys            700
               E             B           10 da ys            200       7   da ys            350
               F             B           7 da ys             500       5   da ys            700
               G             C           3 da ys             600       3   da ys            600
               H            D, E         6 da ys             300       5   da ys            400
               I            F, G         7 da ys             350       4   da ys            425


O n co m p let io n, the pro ject w ill g ive a return o f $110/da y. U sing t im e-co st trade-o ff m etho d,
ho w m u c h w o uld yo u like to co m press the pro ject fo r m a xim iz ing the return? S ho w all
ca lcu lat io ns.


    Spring 2008,                               Time-Cost-Trade-off                                     21
    King Saud University                       Dr. Khalid Al-Gahtani

Time cost-trade-off

  • 1.
    Reasons to ReduceProject Durations: 1. To realize incentive pay 2. To fit within the contractually required time (influences Bid price). 3. To avoid paying Liquated Damages/Damage for delay causes (or avoid damaging the company’s relationship). 4. To complete a project early & move on to another project (Although the Job-specify profit may reduce, company profile may increase). 5. To complete a project when weather conditions make it less expensive (Avoid temporary Heating, avoid completing site work during raining season). Spring 2008, Time-Cost-Trade-off 1 King Saud University Dr. Khalid Al-Gahtani
  • 2.
    Methods to reducedurations: 1. Have the existing crew work overtime. This increase the labor costs due to increase pay rate and decrease productivity. 2. Bring in additional workers to enlarge crew size. This increases labor costs due to overcrowding and poor learning curve. 3. Use better/more advanced equipment. This will usually increase costs due to rental and transport fees. If labor costs (per unit) are reduced, this could reduce costs. 4. Add subcontracted labor to the activity. This almost always increases the cost of an activity unless the subcontracted labor is for more efficient. Spring 2008, Time-Cost-Trade-off 2 King Saud University Dr. Khalid Al-Gahtani
  • 3.
    Project Costs Definitions Spring2008, Time-Cost-Trade-off 3 King Saud University Dr. Khalid Al-Gahtani
  • 4.
    Practices to Estimatethe Project cost • Some company assigns Overhead office as % of direct cost. • Most companies don’t consider profit as a cost of the job. Instead, analysis are completed by using Direct costs + Indirect costs + Company overhead vs. Budgeted (estimated costs). • Similar to each activity, the project as a whole has an ideal (Lease expensive) Duration. Spring 2008, Time-Cost-Trade-off 4 King Saud University Dr. Khalid Al-Gahtani
  • 5.
    Spring 2008, Time-Cost-Trade-off 5 King Saud University Dr. Khalid Al-Gahtani
  • 6.
    Accelerating the Criticaland Noncritical path Spring 2008, Time-Cost-Trade-off 6 King Saud University Dr. Khalid Al-Gahtani
  • 7.
    Network Compression Algorithm • Determine Normal project duration, and cost. • Identify Normal duration Critical Path. • For large network, using CRITICALITY THEORM to eliminate the noncritical paths that do not need to be crashed. • Compute the cost slop : co st slo pe = crash co st - no rmal co st no rmal duratio n- crash duratio n Spring 2008, Time-Cost-Trade-off 7 King Saud University Dr. Khalid Al-Gahtani
  • 8.
    Network Compression Algorithm •shortening the CRITICAL ACTIVITIES beginning with the activity having the lowest cost-slope • Determine the compression limit (Nil) - C rash L im it, or N il = M in - Free F lo at o f any o f the no n crit ica l a ctivit ie s in the para lle l paths co m pet ing fo r crit ica l path.* Spring 2008, Time-Cost-Trade-off 8 King Saud University Dr. Khalid Al-Gahtani
  • 9.
    Network Compression Algorithm •Organize the data as in the following table: • yc le toAS ho rten S C artened N il S ho rtened C oDsta y CC yc le r T otal DPuratio n C # ct ivit y ho n Be D a ys per o st fo C o st ro ject 0 1 2 3 • Update the project network Spring 2008, Time-Cost-Trade-off 9 King Saud University Dr. Khalid Al-Gahtani
  • 10.
    Network Compression Algorithm •When a new Critical path is formed: – Shorten the combination of activity which Falls on Both Critical Paths, OR – Shorten one activity from each of the critical paths. Use the combined cost of shortening both activities when determining if it is cost effective to shorten the project. • At each shortening cycle, compute the new project duration and project cost Spring 2008, Time-Cost-Trade-off 10 King Saud University Dr. Khalid Al-Gahtani
  • 11.
    Network Compression Algorithm •Continue until no further shortening is possible • Tabulate and Plot the Indirect project Cost on the same time-cost graph C yc le P ro ject D irect Ind ire ct T otal # D uratio n C o st C o st C o st 0 1 2 3 Spring 2008, Time-Cost-Trade-off 11 King Saud University Dr. Khalid Al-Gahtani
  • 12.
    Network Compression Algorithm • Add direct and indirect cost to find the project cost at each duration. • Use the total project cost-time curve to find the optimum time. Spring 2008, Time-Cost-Trade-off 12 King Saud University Dr. Khalid Al-Gahtani
  • 13.
    E xa mp le 1: T he duratio ns a nd d irect co sts fo r each activity in the netw o rk o f a sm a ll co nstructio n co ntract under bo th no rm a l a nd crash co nd it io ns are g ive n in be lo w T able. E stablish the least co st fo r exped iting the co ntract . D eterm ine the o ptim u m duratio n o f the co ntract assu m ing the ind irect co st am o unts to S R 125/w eek. N o rm a l C rash A ctivity P receded by D uratio n C o st D uratio n C o st (w eeks) (S R ) (w eeks) (S R ) A — 12 7000 10 7200 B A 8 5000 6 5300 C A 15 4000 12 4600 D B 23 5000 23 5000 E B 5 1000 4 1050 F C 5 3000 4 3300 G E ,C 20 6000 15 6300 H F 13 2500 11 2580 I D, G, H 12 3000 10 3150 36,500 Spring 2008, Time-Cost-Trade-off 13 King Saud University Dr. Khalid Al-Gahtani
  • 14.
    20 23 43 D 4 24 4 47 0 0 12 12 12 8 20 20 5 25 27 20 47 47 12 59 A B E G I 0 0 12 14 2 22 22 2 27 27 0 47 47 0 59 2@ 100 2@ 150 1@ 50 5@ 60 2@ 75 2 12 15 27 27 5 32 32 13 45 ES D EF C F H A ctivity 12 0 27 29 2 34 34 2 47 LS F LF 3@ 200 1@ 300 2@ 40 C rash lim it C yc le A ct ivit y Can Be D a ys C o st per C o st fo r T otal P ro ject N il # to S ho rten S ho rtened S ho rtened W e ek C yc le C o st D uratio n 0 3 6 ,5 0 0 59 1 G 5 2 2 60 120 3 6 ,6 2 0 57 Spring 2008, Time-Cost-Trade-off 14 King Saud University Dr. Khalid Al-Gahtani
  • 15.
    20 23 43 D 22 2 45 0 0 12 12 12 8 20 20 5 25 27 18 45 45 12 57 A B E G I 0 0 12 14 2 22 22 2 27 27 0 47 45 0 55 2@ 100 2@ 150 1@ 50 3@ 60 0 12 15 27 27 5 32 32 13 45 ES D EF C F H A ctivity 12 0 27 27 0 32 32 0 45 3@ 200 1@ 300 2@ 40 LS F LF C rash lim it C yc le A ct ivit y Can Be D a ys C o st per C o st fo r T otal P ro ject N il # to S ho rten S ho rtened S ho rtened W e ek C yc le C o st D uratio n 0 36,500 59 1 G 5 2 2 60 120 36,620 57 2 I 2 2 2 70 140 36,760 55 Spring 2008, Time-Cost-Trade-off 15 King Saud University Dr. Khalid Al-Gahtani
  • 16.
    20 23 43 D 22 2 45 0 0 12 12 12 8 20 20 5 25 27 18 45 45 10 55 A 0 B E G I 0 0 12 14 2 22 22 2 27 27 0 45 45 0 55 2@ 100 2@ 150 1@ 50 3@ 60 0 12 15 27 27 5 32 32 13 45 ES D EF C F H A ctivity 12 0 27 27 0 32 32 0 45 LS F LF 3@ 200 1@ 300 2@ 40 C rash lim it C yc le A ct ivit y Can Be D a ys C o st per C o st fo r T otal P ro ject N il # to S ho rten S ho rtened S ho rtened W e ek C yc le C o st D uratio n 0 36,500 59 1 G 5 2 2 60 120 36,620 57 2 I 2 2 70 140 36,760 55 3 A 2 2 100 200 36,960 53 Spring 2008, Time-Cost-Trade-off 16 King Saud University Dr. Khalid Al-Gahtani
  • 17.
    18 23 41 D 2 20 2 43 0 0 10 10 10 8 18 20 5 25 25 18 43 43 10 53 A B E G I 0 0 10 12 2 20 22 2 27 25 0 43 43 0 53 0 2@ 150 1@ 50 3@ 60 0 10 15 25 25 5 30 30 13 43 ES D EF C F H A ctivity 10 0 25 25 0 30 30 0 43 LS F LF 3@ 200 1@ 300 2@ 40 C rash lim it C yc le A ct ivit y Can Be D a ys C o st per C o st fo r T otal P ro ject N il # to S ho rten S ho rtened S ho rtened W e ek C yc le C o st D uratio n 0 36 ,500 59 1 G 5 2 2 60 1 20 36 ,620 57 2 I 2 2 70 140 36 ,760 55 3 A 2 2 100 200 36 ,960 53 4 H, G 2 2 2 60+ 40 200 37 ,160 51 Spring 2008, Time-Cost-Trade-off 17 King Saud University Dr. Khalid Al-Gahtani
  • 18.
    18 23 41 D 18 0 41 0 0 10 10 10 8 18 18 5 23 25 16 41 41 10 51 A B 0 E G I 0 0 10 10 0 18 20 2 25 25 0 41 41 0 51 0 2@ 150 1@ 50 1@ 60 0 10 15 25 25 5 30 30 11 41 ES D EF C F H A ctivity 10 0 25 25 0 30 30 0 41 LS F LF 3@ 200 1@ 300 0 C rash lim it C yc le A ct ivit y Can Be D a ys C o st per C o st fo r T otal P ro ject N il # to S ho rten S ho rtened S ho rtened W e ek C yc le C o st D uratio n 0 36,500 59 1 G 5 2 2 60 120 36,620 57 2 I 2 2 70 140 36,760 55 3 A 2 2 100 200 36,960 53 4 G, H 2 2 2 60+ 40 200 37,160 51 Spring 2008, Time-Cost-Trade-off 18 5 B, C King Saud University 2 2 150+ 200 Dr. Khalid Al-Gahtani 700 37,860 49
  • 19.
    16 23 39 D 16 0 39 0 0 10 10 10 6 16 16 5 21 23 16 39 39 10 49 A B E G I 0 0 10 10 0 16 18 2 23 23 0 39 39 0 49 0 0 1@ 50 1@ 60 0 10 13 23 23 5 28 28 11 39 ES D EF C F H A ctivity 10 0 23 23 0 28 28 0 39 1@ 200 1@ 300 0 LS F LF C rash lim it C yc le P ro ject D irect Ind ire ct T otal # D uratio n C o st C o st C o st 0 59 36500 7375 43875 1 57 36620 7125 43745 2 55 36760 6875 43635 3 53 36960 6625 43585 4 51 37160 6375 43535 5 49 37860 6125 43985 Spring 2008, Time-Cost-Trade-off 19 King Saud University Dr. Khalid Al-Gahtani
  • 20.
    Project Optimal Duration 50000 45000 40000 35000 Direct Cost Cost (SR) 30000 Indirect 25000 cost 20000 Total 15000 Cost 10000 5000 0 48 49 50 51 52 53 54 55 56 57 58 59 60 Project Duration (Week) Spring 2008, Time-Cost-Trade-off 20 King Saud University Dr. Khalid Al-Gahtani
  • 21.
    C la ssW o rk #2 D ata o n sm a ll m a inte na nce pro ject is g ive n a s be lo w : D epend s N o rm a l C rash A ct ivit y on T im e C o st T im e C o st A 6 da ys $700 4 da ys $800 B 4 da ys 400 4 da ys 400 C 5 da ys 650 4 da ys 700 D A 8 da ys 625 5 da ys 700 E B 10 da ys 200 7 da ys 350 F B 7 da ys 500 5 da ys 700 G C 3 da ys 600 3 da ys 600 H D, E 6 da ys 300 5 da ys 400 I F, G 7 da ys 350 4 da ys 425 O n co m p let io n, the pro ject w ill g ive a return o f $110/da y. U sing t im e-co st trade-o ff m etho d, ho w m u c h w o uld yo u like to co m press the pro ject fo r m a xim iz ing the return? S ho w all ca lcu lat io ns. Spring 2008, Time-Cost-Trade-off 21 King Saud University Dr. Khalid Al-Gahtani