SlideShare a Scribd company logo
1 of 26
Updating Construction Schedules
•       Procedure:
      – Change the duration of all completed activities
        to zeros.
      – Identify all activities on which work is currently
        proceeding as live activities.
      – Put early start time of live activities equals the
        update time and their durations equal the
        remaining duration given by the update report.
      – Change durations of future activities as given in
        the update report.
      – Carry out network analysis in the normal way
        and prepare a new activity schedule.
    Spring 2008,           Time and Cost Control        1
    King Saud University    Dr. Khalid Al-Gahtani
Example




Spring   Time and Cost Control    2
2008,     Dr. Khalid Al-Gahtani
Example
• The position of the activities at the end of the fifth
  week is as follows:
   – Activities B, C, D and E have been completed.
   – Activity F is ready to start at beginning of week 6.
   – Remaining duration of activity H is 4 weeks.
   – Remaining duration of activity I is 3 weeks.
   – Activity G will not start until end of week 7.
   – Volume of work in activity L has been increased by 33%
     approximately.
   – Activity J has been omitted.
   – It is decided to shorten activity K by 2 weeks.

• Construct the updated schedule indicating the critical
  path and showing new activities times.
  Spring 2008,           Time and Cost Control             3
  King Saud University    Dr. Khalid Al-Gahtani
Spring   Time and Cost Control    4
2008,     Dr. Khalid Al-Gahtani
Work Breakdown Structure
• WBS divides the project into recognizable systems (work
  packages, WP’s or Bid Packages) that responsible
  assignable work units, and for which accountability can
  be expected/assigned.

                    P ro ject



                W o rk P ackages



                   A ct ivit ies                 S equenc ing


Spring                  Time and Cost Control                   5
2008,                    Dr. Khalid Al-Gahtani
Traditional A/E PDS

                       O w ner



      A /E                               GC



     Su b1                  Su b2                     Su b3   Su b4




Spring 2008,                     Time and Cost Control                6
King Saud University              Dr. Khalid Al-Gahtani
Professional Construction Management

                                    O w ne r



                 A /E                 CM



  W P1                  W P2         W P3               W P4   W P4




 Spring 2008,                  Time and Cost Control                  7
 King Saud University           Dr. Khalid Al-Gahtani
Developing WPs
•        Develop WBS
     – Identify WPs
•        Draw a WPs Network

                               W P3
              W P1

                               W P4             W P6
              W P2

                               W P5

Spring                 Time and Cost Control           8
2008,                   Dr. Khalid Al-Gahtani
Developing WPs
•       Each WP must have
      – One Performing Agency (PA) such as
        Subcontractor
      – One Responsible Agency (RA) such owner’s
        Project Engineers
•       Interconnection between Packages should
        be district and clear to facilitate
        coordination
                                W P1           W P2


                                               W P3
    Spring            Time and Cost Control           9
    2008,              Dr. Khalid Al-Gahtani
Developing WPs
•        Bid a WP at the most short time so as to
         stimulate competition (Keep away
         uncertainty)


         W P1        W P2                      W P3   W P4




Spring                Time and Cost Control              10
2008,                  Dr. Khalid Al-Gahtani
Cost Coding System
• Cost Central level = Lowest level at which
  functional responsibility for individual WBS
  element exit.
     – XXX XXX XXX XXX
• An example:
     – 0534.02220.21.A.00.cf34




Spring 2008,           Time and Cost Control    11
King Saud University    Dr. Khalid Al-Gahtani
MASTERFORMAT system
T A B L E 1 M a jo r D ivisio ns in the U nifo rm C o nstructio n Inde x

0   C o nd itio ns o f the co ntract                9 F inishes
1   G enera l requ ire m e nts                      10 S pec ia lt ies
2   S ite w o rk                                    11 E quip m e nt
3   C o ncrete                                      12 Furnishing s
4   M aso nry                                       13 S pec ia l co nstructio n
5   M etals                                         14 C o nve ying syste m
6   W o o d and p last ic s                         15 M echa nica l
7   T herm a l a nd m o isture prevent io n         16 E lectrica l
8   D oors and w indo w s



Spring                         Time and Cost Control                               12
2008,                           Dr. Khalid Al-Gahtani
Cost Coding System
• Advantages of coding systems are:
     – Provide a numbering system to replace verbal
       descriptions of items.
     – These codes reduce the length or complexity of the
       information to be recorded.
     – aids consistency in definitions and categories
       between projects and among the various parties
       involved in a project.
     – aid in the retrieval of historical records of cost,
       productivity and duration on particular activities.
     – electronic data storage and retrieval operations are
       much more efficient with standard coding systems.
Spring 2008,             Time and Cost Control                13
King Saud University      Dr. Khalid Al-Gahtani
Project Cost Control
• Budgeted Cost of Work Scheduled (BCWS) is the
  budgeted amount of cost of the work scheduled to be
  accomplished in a given time period (including support
  and allocated overhead).

• Budgeted Cost of Work Performed (BCWP) is the
  budgeted amount of cost for the work completed in a
  given time period, including support effort and allocated
  overhead. (This is sometimes referred to as “earned
  value of work accomplished”.)

• Actual Cost of Work Performed (ACWP) is the amount
  reported as actually expended in completing the
  particular work accomplished within a given time period.
Spring 2008,            Time and Cost Control                 14
King Saud University     Dr. Khalid Al-Gahtani
Type of performance
                                                     BC W P


                                                     BC W S



                                                     ACW P




                       Fast & L o w

Spring 2008,                Time and Cost Control             15
King Saud University         Dr. Khalid Al-Gahtani   BCWS
Type of performance
                                                   ACW P


                                                   BC W P



                                                   BC W S




                       Fast & H ig h
Spring 2008,              Time and Cost Control             16
King Saud University       Dr. Khalid Al-Gahtani
Type of operformance
            Fast & L w


                                          BCWS


                                          BCW P



                                          AC W P




            S low & Low
Spring           Time and Cost Control             17
2008,             Dr. Khalid Al-Gahtani
TypeFast & performance
              of H ig h
                                          BCWS


                                          AC W P



                                          BCWP




              S low & H igh
Spring           Time and Cost Control             18
2008,             Dr. Khalid Al-Gahtani
Cost Index
C o st V ariance = B C W P A C W P
                         + ve      U nder B udget
C o st V ariance         0         W ithin B udget
                         - ve      O ver B udget
C o st P erfo rm ance Index = B C W P /A C W P
                          > 1        U nder B udget
CPI                       = 1        W ithin B udget
                          < 1        O ver B udget
% co st o verrun/u nderrun

                ACW P    BCWP
            =                         ,
                       BCWP
Spring 2008,                  Time and Cost Control    19
King Saud University           Dr. Khalid Al-Gahtani
Schedule Index
S chedu le/P erfo rma nc e V aria nce =B C W P -B C W S .
                          +ve          A head S chedule
S ch./per. V ariance      0            O n S chedule
                          -ve          B ehind S chedule
S chedu le P erfo rma nce Inde x = B C W P / B C W S .
                         >1          A head S chedule
SPI                      =1          O n S chedule
                         <1          B ehind S chedule


Spring 2008,              Time and Cost Control             20
King Saud University       Dr. Khalid Al-Gahtani
B udgeted C o st A t C o m pletio n (B A C )

 Estimatedo fCost/Timenit price
      = T o tal Q uantities U At Completion

 P udgeted C e A t t o o pletio n (T A C C
 Blanned T imo st A CC mm pletio n (B A ) )

            = T o tal o f Q uantities ÷ P lanned P ro ductivity
                            uantities U nit price
 E lanned T imo st A CC mm pletio n (E A C )
 P stim ated C e A t t o o pletio n (T A C )

          = T oC Wo f oD ate
            A tal PT Q uantities ÷ P lanned P ro ductivity
                                          BAC
          =                   BAC =
             B C W PT oD ate            C P I T oD ate
 E stim ated C o st A t C o m pletio n (E A C )
M ore accurate estim ate can be reach ed by using these form ulas:
  T o D ate VA C W P T im e
               ariance                            BAC
                        T oD ate
E stim ated=C o st A t Co m p let B A C = C )
                                    io n (E A
              BB C W PoD ate
                 C W PT                        C P I T oD ate
                          T oD ate
           =                         1     T im e T oD D ate
                                 (B A C - B C W PT o ate )
         = V arianceate im
  T o D ate A CB C W S T oD atee
                W P T oD T
                                         C P I T hisPeriod

ESpring ated T im eC W CooD ate letandn (EControl )
 stim            B A t PT m p io Cost T A C
                              Time                                 21
 2008,      =                          1       T im e
                                  Dr. Khalid Al-Gahtani T oD ate
Spring   Time and Cost Control    22
2008,     Dr. Khalid Al-Gahtani
Project Example




Spring 2008,               Time and Cost Control    23
King Saud University        Dr. Khalid Al-Gahtani
Project Example




Spring       Time and Cost Control    24
2008,         Dr. Khalid Al-Gahtani
Project Example
         E N G IN E E R IN G SU B T ASKS ST AT U S AT E N D O F M O N T H 3
                                 (tho usands o f do llars)

                T ask                      Status          BCW S    BCW P     ACW P
System design                          C o mp leted        $131.0   $131.0    $144.0
Subco ntract specs                       Started           132.0     82.0      84.0
M aterial tests                        C o mp leted         22.0     22.0      22.5
Specs review                             Started            22.0     15.0      15.5
D rafting                                Started            97.0     59.0      59.0
Fabricatio n/assembly suppo rt         C o mp leted         29.0     29.0      36.0
Fabricatio n/assembly pro cess           Started           100.0     63.0      67.0
T est suppo rt                           Started            21.0     21.0      21.0
E ngineering release and review        N ot Started
                T otal                                     $554.0   $422.0    $449.0

Spring 2008,                      Time and Cost Control                            25
King Saud University               Dr. Khalid Al-Gahtani
Project Example
Figure 5 -9 S tatus sum m ary o f engineering subtasks in pro gress and estim ate to co m plete.

               T ask                  BCWS      BCWP       ACW P                     S tatus
S ubco ntract specs                    $132       $82        $84      B e hind sc hedu le and o ver co st
S pecs review                           22         15        15.5 B e hind sc hedu le and o ver co st
D ra fting                              97         59         59      B e hind sc hedu le but w ithin co st
Fa bricat io n/asse m b ly pro cess    100         63         67      B e hind sc hedu le and o ver co st
T est suppo rt                          21         21         21      O n sc hedu le a nd w it hin co st
                                                         449
                            E stim ated to co m p lete:         765 = $812 K
                                                         442
S u m m ary: E ng ine ering w o rk is be hind sc hedu le a nd a co st o verrun is o ccurring




  Spring 2008,                            Time and Cost Control                                        26
  King Saud University                     Dr. Khalid Al-Gahtani

More Related Content

Viewers also liked

Viewers also liked (14)

Organization
OrganizationOrganization
Organization
 
01 project management framework
01 project management framework01 project management framework
01 project management framework
 
02 project scope management
02 project scope management02 project scope management
02 project scope management
 
PMO Presentation
PMO PresentationPMO Presentation
PMO Presentation
 
Project Management Definitions
Project Management DefinitionsProject Management Definitions
Project Management Definitions
 
08 pmp communication management
08 pmp communication management08 pmp communication management
08 pmp communication management
 
03 project time managment
03 project time managment03 project time managment
03 project time managment
 
Microsoft Office Excel 2007 for Project Managers
Microsoft Office Excel 2007 for Project ManagersMicrosoft Office Excel 2007 for Project Managers
Microsoft Office Excel 2007 for Project Managers
 
PMP exam changing in 2016
PMP exam changing in 2016PMP exam changing in 2016
PMP exam changing in 2016
 
Human Logic _Feb 2016
Human Logic _Feb 2016Human Logic _Feb 2016
Human Logic _Feb 2016
 
Project risk management handbook final 29.06.12
Project risk management handbook   final 29.06.12Project risk management handbook   final 29.06.12
Project risk management handbook final 29.06.12
 
Project management professional (PMP)
Project management professional (PMP)Project management professional (PMP)
Project management professional (PMP)
 
Human Resources KPIs
Human Resources KPIsHuman Resources KPIs
Human Resources KPIs
 
Pmp risk management
Pmp risk managementPmp risk management
Pmp risk management
 

Similar to Time cost-control

Assessing EPC Contract Risk by using integrated systems
Assessing EPC Contract Risk by using integrated systemsAssessing EPC Contract Risk by using integrated systems
Assessing EPC Contract Risk by using integrated systemsPedram Danesh-Mand
 
C:\documents and settings\ckampschulte\desktop\in sync risk range analysis
C:\documents and settings\ckampschulte\desktop\in sync risk range analysisC:\documents and settings\ckampschulte\desktop\in sync risk range analysis
C:\documents and settings\ckampschulte\desktop\in sync risk range analysisInSync Conference
 
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...Performance Evaluation of Construction Projects by EVM Method, Using Primaver...
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...Mohammad Lemar ZALMAİ
 
AVEVA ProCon FPSO Europe Congress 2016
AVEVA ProCon FPSO Europe Congress 2016AVEVA ProCon FPSO Europe Congress 2016
AVEVA ProCon FPSO Europe Congress 2016AVEVA ProCon
 
Dublin Port Company - Energy Case Study
Dublin Port Company - Energy Case StudyDublin Port Company - Energy Case Study
Dublin Port Company - Energy Case StudyCodema
 
Petrotech Presenttaion- Punj Lloyd
Petrotech Presenttaion- Punj LloydPetrotech Presenttaion- Punj Lloyd
Petrotech Presenttaion- Punj LloydNitin Sethi
 
Webinar: CCS major project development lessons from the ZeroGen experience
Webinar: CCS major project development lessons from the ZeroGen experienceWebinar: CCS major project development lessons from the ZeroGen experience
Webinar: CCS major project development lessons from the ZeroGen experienceGlobal CCS Institute
 
IPTC-18322-MS_SHE&S Improvement of a Major Subcontractor on the RG Barzan Ons...
IPTC-18322-MS_SHE&S Improvement of a Major Subcontractor on the RG Barzan Ons...IPTC-18322-MS_SHE&S Improvement of a Major Subcontractor on the RG Barzan Ons...
IPTC-18322-MS_SHE&S Improvement of a Major Subcontractor on the RG Barzan Ons...Bob DeHart
 
Passivhaus Dissertation
Passivhaus DissertationPassivhaus Dissertation
Passivhaus DissertationDavid Baines
 
project-160729043426.pptx
project-160729043426.pptxproject-160729043426.pptx
project-160729043426.pptxAjitJaiswal27
 
New base 795 special 25 february 2016
New base 795 special 25 february 2016New base 795 special 25 february 2016
New base 795 special 25 february 2016Khaled Al Awadi
 
(07) 5806 project control
(07) 5806 project control(07) 5806 project control
(07) 5806 project controldiwupower
 
Dinesh Sharma and Jayeeta Dutta: Simplified Agile EVM - The Art Of Managing T...
Dinesh Sharma and Jayeeta Dutta: Simplified Agile EVM - The Art Of Managing T...Dinesh Sharma and Jayeeta Dutta: Simplified Agile EVM - The Art Of Managing T...
Dinesh Sharma and Jayeeta Dutta: Simplified Agile EVM - The Art Of Managing T...Lviv Startup Club
 
PM Session 7
PM Session 7PM Session 7
PM Session 7dmdk12
 

Similar to Time cost-control (20)

Assessing EPC Contract Risk by using integrated systems
Assessing EPC Contract Risk by using integrated systemsAssessing EPC Contract Risk by using integrated systems
Assessing EPC Contract Risk by using integrated systems
 
Net present value (NPV)
Net present value (NPV) Net present value (NPV)
Net present value (NPV)
 
C:\documents and settings\ckampschulte\desktop\in sync risk range analysis
C:\documents and settings\ckampschulte\desktop\in sync risk range analysisC:\documents and settings\ckampschulte\desktop\in sync risk range analysis
C:\documents and settings\ckampschulte\desktop\in sync risk range analysis
 
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...Performance Evaluation of Construction Projects by EVM Method, Using Primaver...
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...
 
AVEVA ProCon FPSO Europe Congress 2016
AVEVA ProCon FPSO Europe Congress 2016AVEVA ProCon FPSO Europe Congress 2016
AVEVA ProCon FPSO Europe Congress 2016
 
Bar chart
Bar chartBar chart
Bar chart
 
Dublin Port Company - Energy Case Study
Dublin Port Company - Energy Case StudyDublin Port Company - Energy Case Study
Dublin Port Company - Energy Case Study
 
Time cost-trade-off
Time cost-trade-offTime cost-trade-off
Time cost-trade-off
 
Symons
SymonsSymons
Symons
 
Petrotech Presenttaion- Punj Lloyd
Petrotech Presenttaion- Punj LloydPetrotech Presenttaion- Punj Lloyd
Petrotech Presenttaion- Punj Lloyd
 
Webinar: CCS major project development lessons from the ZeroGen experience
Webinar: CCS major project development lessons from the ZeroGen experienceWebinar: CCS major project development lessons from the ZeroGen experience
Webinar: CCS major project development lessons from the ZeroGen experience
 
IPTC-18322-MS_SHE&S Improvement of a Major Subcontractor on the RG Barzan Ons...
IPTC-18322-MS_SHE&S Improvement of a Major Subcontractor on the RG Barzan Ons...IPTC-18322-MS_SHE&S Improvement of a Major Subcontractor on the RG Barzan Ons...
IPTC-18322-MS_SHE&S Improvement of a Major Subcontractor on the RG Barzan Ons...
 
Passivhaus Dissertation
Passivhaus DissertationPassivhaus Dissertation
Passivhaus Dissertation
 
project-160729043426.pptx
project-160729043426.pptxproject-160729043426.pptx
project-160729043426.pptx
 
PMP Preparation - 07 Cost Management
PMP Preparation - 07 Cost ManagementPMP Preparation - 07 Cost Management
PMP Preparation - 07 Cost Management
 
Financial Innovation on renewables
Financial Innovation on renewablesFinancial Innovation on renewables
Financial Innovation on renewables
 
New base 795 special 25 february 2016
New base 795 special 25 february 2016New base 795 special 25 february 2016
New base 795 special 25 february 2016
 
(07) 5806 project control
(07) 5806 project control(07) 5806 project control
(07) 5806 project control
 
Dinesh Sharma and Jayeeta Dutta: Simplified Agile EVM - The Art Of Managing T...
Dinesh Sharma and Jayeeta Dutta: Simplified Agile EVM - The Art Of Managing T...Dinesh Sharma and Jayeeta Dutta: Simplified Agile EVM - The Art Of Managing T...
Dinesh Sharma and Jayeeta Dutta: Simplified Agile EVM - The Art Of Managing T...
 
PM Session 7
PM Session 7PM Session 7
PM Session 7
 

More from Tu Nguyen, PMP®,PMI-RMP®

More from Tu Nguyen, PMP®,PMI-RMP® (20)

4.contracting
4.contracting4.contracting
4.contracting
 
3.estimating
3.estimating3.estimating
3.estimating
 
2.tendering
2.tendering2.tendering
2.tendering
 
1.introduction
1.introduction1.introduction
1.introduction
 
Session 8 gdas pmp study group presentation
Session 8   gdas pmp study group presentationSession 8   gdas pmp study group presentation
Session 8 gdas pmp study group presentation
 
Session 7 gdas pmp study group presentation
Session 7   gdas pmp study group presentationSession 7   gdas pmp study group presentation
Session 7 gdas pmp study group presentation
 
Session 6 gdas pmp study group presentation
Session 6   gdas pmp study group presentationSession 6   gdas pmp study group presentation
Session 6 gdas pmp study group presentation
 
Session 5 gdas pmp study group presentation
Session 5   gdas pmp study group presentationSession 5   gdas pmp study group presentation
Session 5 gdas pmp study group presentation
 
Session 4 gdas pmp study group presentation
Session 4   gdas pmp study group presentationSession 4   gdas pmp study group presentation
Session 4 gdas pmp study group presentation
 
Session 10 gdas pmp study group presentation
Session 10   gdas pmp study group presentationSession 10   gdas pmp study group presentation
Session 10 gdas pmp study group presentation
 
Session 3 gdas pmp study group presentation
Session 3   gdas pmp study group presentationSession 3   gdas pmp study group presentation
Session 3 gdas pmp study group presentation
 
Session 2 gdas pmp study group presentation
Session 2   gdas pmp study group presentationSession 2   gdas pmp study group presentation
Session 2 gdas pmp study group presentation
 
Node
NodeNode
Node
 
Contract
ContractContract
Contract
 
Cash flow
Cash flowCash flow
Cash flow
 
Arrow computation
Arrow computationArrow computation
Arrow computation
 
Arrow
ArrowArrow
Arrow
 
Administration
AdministrationAdministration
Administration
 
Ch 6 construction progress control
Ch 6 construction progress controlCh 6 construction progress control
Ch 6 construction progress control
 
Ch 4 cash flow and investment appraisal
Ch 4 cash flow and investment appraisalCh 4 cash flow and investment appraisal
Ch 4 cash flow and investment appraisal
 

Time cost-control

  • 1. Updating Construction Schedules • Procedure: – Change the duration of all completed activities to zeros. – Identify all activities on which work is currently proceeding as live activities. – Put early start time of live activities equals the update time and their durations equal the remaining duration given by the update report. – Change durations of future activities as given in the update report. – Carry out network analysis in the normal way and prepare a new activity schedule. Spring 2008, Time and Cost Control 1 King Saud University Dr. Khalid Al-Gahtani
  • 2. Example Spring Time and Cost Control 2 2008, Dr. Khalid Al-Gahtani
  • 3. Example • The position of the activities at the end of the fifth week is as follows: – Activities B, C, D and E have been completed. – Activity F is ready to start at beginning of week 6. – Remaining duration of activity H is 4 weeks. – Remaining duration of activity I is 3 weeks. – Activity G will not start until end of week 7. – Volume of work in activity L has been increased by 33% approximately. – Activity J has been omitted. – It is decided to shorten activity K by 2 weeks. • Construct the updated schedule indicating the critical path and showing new activities times. Spring 2008, Time and Cost Control 3 King Saud University Dr. Khalid Al-Gahtani
  • 4. Spring Time and Cost Control 4 2008, Dr. Khalid Al-Gahtani
  • 5. Work Breakdown Structure • WBS divides the project into recognizable systems (work packages, WP’s or Bid Packages) that responsible assignable work units, and for which accountability can be expected/assigned. P ro ject W o rk P ackages A ct ivit ies S equenc ing Spring Time and Cost Control 5 2008, Dr. Khalid Al-Gahtani
  • 6. Traditional A/E PDS O w ner A /E GC Su b1 Su b2 Su b3 Su b4 Spring 2008, Time and Cost Control 6 King Saud University Dr. Khalid Al-Gahtani
  • 7. Professional Construction Management O w ne r A /E CM W P1 W P2 W P3 W P4 W P4 Spring 2008, Time and Cost Control 7 King Saud University Dr. Khalid Al-Gahtani
  • 8. Developing WPs • Develop WBS – Identify WPs • Draw a WPs Network W P3 W P1 W P4 W P6 W P2 W P5 Spring Time and Cost Control 8 2008, Dr. Khalid Al-Gahtani
  • 9. Developing WPs • Each WP must have – One Performing Agency (PA) such as Subcontractor – One Responsible Agency (RA) such owner’s Project Engineers • Interconnection between Packages should be district and clear to facilitate coordination W P1 W P2 W P3 Spring Time and Cost Control 9 2008, Dr. Khalid Al-Gahtani
  • 10. Developing WPs • Bid a WP at the most short time so as to stimulate competition (Keep away uncertainty) W P1 W P2 W P3 W P4 Spring Time and Cost Control 10 2008, Dr. Khalid Al-Gahtani
  • 11. Cost Coding System • Cost Central level = Lowest level at which functional responsibility for individual WBS element exit. – XXX XXX XXX XXX • An example: – 0534.02220.21.A.00.cf34 Spring 2008, Time and Cost Control 11 King Saud University Dr. Khalid Al-Gahtani
  • 12. MASTERFORMAT system T A B L E 1 M a jo r D ivisio ns in the U nifo rm C o nstructio n Inde x 0 C o nd itio ns o f the co ntract 9 F inishes 1 G enera l requ ire m e nts 10 S pec ia lt ies 2 S ite w o rk 11 E quip m e nt 3 C o ncrete 12 Furnishing s 4 M aso nry 13 S pec ia l co nstructio n 5 M etals 14 C o nve ying syste m 6 W o o d and p last ic s 15 M echa nica l 7 T herm a l a nd m o isture prevent io n 16 E lectrica l 8 D oors and w indo w s Spring Time and Cost Control 12 2008, Dr. Khalid Al-Gahtani
  • 13. Cost Coding System • Advantages of coding systems are: – Provide a numbering system to replace verbal descriptions of items. – These codes reduce the length or complexity of the information to be recorded. – aids consistency in definitions and categories between projects and among the various parties involved in a project. – aid in the retrieval of historical records of cost, productivity and duration on particular activities. – electronic data storage and retrieval operations are much more efficient with standard coding systems. Spring 2008, Time and Cost Control 13 King Saud University Dr. Khalid Al-Gahtani
  • 14. Project Cost Control • Budgeted Cost of Work Scheduled (BCWS) is the budgeted amount of cost of the work scheduled to be accomplished in a given time period (including support and allocated overhead). • Budgeted Cost of Work Performed (BCWP) is the budgeted amount of cost for the work completed in a given time period, including support effort and allocated overhead. (This is sometimes referred to as “earned value of work accomplished”.) • Actual Cost of Work Performed (ACWP) is the amount reported as actually expended in completing the particular work accomplished within a given time period. Spring 2008, Time and Cost Control 14 King Saud University Dr. Khalid Al-Gahtani
  • 15. Type of performance BC W P BC W S ACW P Fast & L o w Spring 2008, Time and Cost Control 15 King Saud University Dr. Khalid Al-Gahtani BCWS
  • 16. Type of performance ACW P BC W P BC W S Fast & H ig h Spring 2008, Time and Cost Control 16 King Saud University Dr. Khalid Al-Gahtani
  • 17. Type of operformance Fast & L w BCWS BCW P AC W P S low & Low Spring Time and Cost Control 17 2008, Dr. Khalid Al-Gahtani
  • 18. TypeFast & performance of H ig h BCWS AC W P BCWP S low & H igh Spring Time and Cost Control 18 2008, Dr. Khalid Al-Gahtani
  • 19. Cost Index C o st V ariance = B C W P A C W P + ve U nder B udget C o st V ariance 0 W ithin B udget - ve O ver B udget C o st P erfo rm ance Index = B C W P /A C W P > 1 U nder B udget CPI = 1 W ithin B udget < 1 O ver B udget % co st o verrun/u nderrun ACW P BCWP = , BCWP Spring 2008, Time and Cost Control 19 King Saud University Dr. Khalid Al-Gahtani
  • 20. Schedule Index S chedu le/P erfo rma nc e V aria nce =B C W P -B C W S . +ve A head S chedule S ch./per. V ariance 0 O n S chedule -ve B ehind S chedule S chedu le P erfo rma nce Inde x = B C W P / B C W S . >1 A head S chedule SPI =1 O n S chedule <1 B ehind S chedule Spring 2008, Time and Cost Control 20 King Saud University Dr. Khalid Al-Gahtani
  • 21. B udgeted C o st A t C o m pletio n (B A C ) Estimatedo fCost/Timenit price = T o tal Q uantities U At Completion P udgeted C e A t t o o pletio n (T A C C Blanned T imo st A CC mm pletio n (B A ) ) = T o tal o f Q uantities ÷ P lanned P ro ductivity uantities U nit price E lanned T imo st A CC mm pletio n (E A C ) P stim ated C e A t t o o pletio n (T A C ) = T oC Wo f oD ate A tal PT Q uantities ÷ P lanned P ro ductivity BAC = BAC = B C W PT oD ate C P I T oD ate E stim ated C o st A t C o m pletio n (E A C ) M ore accurate estim ate can be reach ed by using these form ulas: T o D ate VA C W P T im e ariance BAC T oD ate E stim ated=C o st A t Co m p let B A C = C ) io n (E A BB C W PoD ate C W PT C P I T oD ate T oD ate = 1 T im e T oD D ate (B A C - B C W PT o ate ) = V arianceate im T o D ate A CB C W S T oD atee W P T oD T C P I T hisPeriod ESpring ated T im eC W CooD ate letandn (EControl ) stim B A t PT m p io Cost T A C Time 21 2008, = 1 T im e Dr. Khalid Al-Gahtani T oD ate
  • 22. Spring Time and Cost Control 22 2008, Dr. Khalid Al-Gahtani
  • 23. Project Example Spring 2008, Time and Cost Control 23 King Saud University Dr. Khalid Al-Gahtani
  • 24. Project Example Spring Time and Cost Control 24 2008, Dr. Khalid Al-Gahtani
  • 25. Project Example E N G IN E E R IN G SU B T ASKS ST AT U S AT E N D O F M O N T H 3 (tho usands o f do llars) T ask Status BCW S BCW P ACW P System design C o mp leted $131.0 $131.0 $144.0 Subco ntract specs Started 132.0 82.0 84.0 M aterial tests C o mp leted 22.0 22.0 22.5 Specs review Started 22.0 15.0 15.5 D rafting Started 97.0 59.0 59.0 Fabricatio n/assembly suppo rt C o mp leted 29.0 29.0 36.0 Fabricatio n/assembly pro cess Started 100.0 63.0 67.0 T est suppo rt Started 21.0 21.0 21.0 E ngineering release and review N ot Started T otal $554.0 $422.0 $449.0 Spring 2008, Time and Cost Control 25 King Saud University Dr. Khalid Al-Gahtani
  • 26. Project Example Figure 5 -9 S tatus sum m ary o f engineering subtasks in pro gress and estim ate to co m plete. T ask BCWS BCWP ACW P S tatus S ubco ntract specs $132 $82 $84 B e hind sc hedu le and o ver co st S pecs review 22 15 15.5 B e hind sc hedu le and o ver co st D ra fting 97 59 59 B e hind sc hedu le but w ithin co st Fa bricat io n/asse m b ly pro cess 100 63 67 B e hind sc hedu le and o ver co st T est suppo rt 21 21 21 O n sc hedu le a nd w it hin co st 449 E stim ated to co m p lete: 765 = $812 K 442 S u m m ary: E ng ine ering w o rk is be hind sc hedu le a nd a co st o verrun is o ccurring Spring 2008, Time and Cost Control 26 King Saud University Dr. Khalid Al-Gahtani