A presentation on
Steam Generator
Coal to Electricity ….. Basics
Coal
Chemical
Energy
Super Heated
Steam
Pollutants
Thermal
Energy
Turbine
Torque
Heat LossIn
Condenser
Kinetic
Energy
Electrical
Energy
Alternating current
in Stator
Mech. Energy
LossASH
Heat
Loss
Elet. Energy
Loss
Major Energy
Sources of
India
Why Coal?
Coal
55%
Gas
10%
Diesel
1%
Hydel
26%
RES
5%
Nuclear
3%
Share of Coal in Power
Generation
Advantages of Coal Fuel
•Abundantly available in India
•Low cost
•Technology for Power
Generation well developed.
•Easy to handle, transport,
store and use
Shortcomings of Coal
•Low Calorific Value
•Large quantity to be Handled
•Produces pollutants, ash
•Disposal of ash is
Problematic
•Reserves depleting fast
•India’s Coal Reserves are estimated to be 206 billion tonnes. Present consumption is
about 450 million tonnes.
•Cost of coal for producing 1 unit of electricity (Cost of coal Rs 1000/MT)is Rs 0.75.
•Cost of Gas for producing 1 unit of electricity (Cost of Gas Rs 6/SMC)is Rs 1.20.
Knowing more about Coal
Coal production
•Surface Mining
•Underground Mining
Coal
Transportation
•Rail
•Truck
•Conveyor
•Ship
Coal Properties
•Calorific Value
•Grade of Coal (UHV)
•Proximate Analysis
•Ultimate Analysis
•Ash and Minerals
•Grindability
•Rank
•Physical
Characteristics
Coal Beneficiation
•Why?
•Processes
•Effectiveness
Coal production
•Surface Mining
•Underground Mining
Useful Heat Value (UHV)
UHV= 8900-138(A+M)
Boiler/ steam generator
 Steam generating device for a specific purpose.
 Capable to meet variation in load demand
 Capable of generating steam in a range of operating
pressure and temperature
 For utility purpose, it should generate steam
uninterruptedly at operating pressure and
temperature for running steam turbines.
Boiler/ steam generator
 Raw materials for design
of boilers
1. Coal from mines
2. Ambient air
3. Water from natural
resources (river, ponds)
o Generating heat energy
o Air for combustion
o Working fluid for steam
generation, possessing
heat energy
A 500MW steam generator consumes about 8000 tonnes of coal every day
It will be considered if it requires about 200 cubic meter of DM water in a day
It will produce about 9500 tonnes of Carbon di Oxide every day
Coal analysis
 Typical composition (Proximate analysis)
1. Fixed carbon
2. Fuel ash
3. Volatile material
4. Total Moisture
5. Sulfur
o High calorific value/ Lower calorific value
(Kcal/kg)
o Hardgrove Index (HGI)
Combustion of coal
 Carbon, hydrogen, sulfur are sources of heat
on combustion
 Surface moisture removed on heating during
pulverization.
 Inherent moisture and volatiles are released at
higher temperature, making coal porous and
leading to char/ coke formation. (Thermal
preparation stage)
Fuel Oil
 Three liquid fuels used in power plants
• 1. Heavy Fuel Oil (HFO)
• 2. LSHS (Low Sulfur Heavy stock)
• 3. High speed Diesel (HSD)
Oil firing is preceded by
 Lowering viscosity and increasing flowability on
heating for better combustion in given turn down ratio.
(125o
C)
 Droplet formation on atomization (by steam/
compressed air/ mechanical pressurization)
 Combustion initiation by High energy spark ignition
Combustion of reactants
 Reaction rate depends on concentration of one of
the reactants
 Concentration varies on partial pressure of the
reactants.
 Partial pressure is a function of gas temperature.
 Therefore, reaction rate depends on temperature
and substance that enter the reaction.
Combustion Reactions (Carbon)
 Main reactions
2C + O2 = 2CO + 3950 BTU/lb(Deficit air)
C + O2 = CO2 +14093 BTU/lb
Secondary reactions
2CO + O2 = 2CO2 + 4347BTU/lb
C + CO2 = 2CO -7.25MJ/kg
Combustion Reactions (Carbon)
 Carbon reaction
2C + O2 =2CO [Eco =60kJ/mol]
C + O2 =CO2 [Eco2 =140kJ/mol]
reaction at 1200o
C
4C + 3O2 =2CO + 2CO2 (Ratio 1:1)
Reaction at 1700o
C
3C + 2O2 = 2CO +CO2 (Ratio 2:1)
It is desirable to supply combustion air at lower temperature
regime in furnace
Combustion Reaction (H2, S)
 Hydrogen reaction
2H2 + O2 = 2H2O +61095 BTU/lb
 Sulfur reaction
S + O2 = SO2 + 3980 BTU/lb
(undesirable)
Coal for combustion
 Anthracite
 Semi-anthracite
 Bituminous
 Semi-Bituminous
 Lignite
 Peat
 High CV, low VM
 High CV, low VM
 Medium CV, medium VM
 Medium CV, medium VM
 Low CV, high VM, high TM
 Very low CV, high VM & TM
Heat Generation in furnace
 Heat input in the furnace
 Efficiency of thermal power plants is 37%-45%
for different types of cycle
 For typical conventional P.F. boilers, coal flow
rate is
290-350 T/hr For 500 MW units
120-145 T/hr For 200 MW units
Cycle
Elect
Furnace
MW
Q
η
=
Tangential Firing System
MAIN EQUIPMENTS OF FUEL & FIRING SYSTEM
• MILLS OR PULVERISERS
• FEDDERS
• BURNERS
TYPES OF FEEDERS
• VOLUMETRIC FEEDRES
• GRAVIMETRIC FEEDERS
PULVERIZERS
OBJECTIVES
• TO CRUSHED THE COAL
• REDCED TO A FINENESS SUCH THAT 70-80% PASSES THROUGH A
200MESH SIEVE
ADVANTAGES OF PULVERISED COAL FIRING
• EFFICIENT UTILISATION OF CHEAPER GRADE OF COALS
• FLEXIBILITY IN FIRING WITH ABILITY TO MEET FLUCTUATING LOADS
• BETTER COAL COMBUSTION INCREASING THE BOILER EFFICIENCY
• HIGH AVAILIBILITY
X R P
( B H E L )
E M IL L S
( B A B C O C K )
M P S
B O W L /
B A L L & R A C E
V E R T IC A L S P IN D L E
P R E S S U R IZ E D
T U B E
C L A S S IF IC A T IO N O F M IL L S
BOWL MILL
Model no. Base
capacity(T/Hr)
623XRP 18.4
703XRP 26.4
763XRP 33.8
803XRP 36.5
883XRP 51.1
903XRP 54.1
1003XRP 68.1
1043XRP 72.0
BASE CAPACITY(T/HR)
AT
HGI -55
Total Moisture-10%
Fineness-70% THRU 200
MESH
BALL& RACE MILL(E MILL)
Model no. Base
capacity(T/Hr)
7E9 25
8.5E10 35
8.5E9 40
10E10 55
10.9E11 61
10.9E10 70
10.9E8 80
TUBE MILL
Model no. Base
capacity(T/Hr)
BBD4760 83
BBD4772 90
AIR AND DRAFT SYSTEM
OBJECTIVES
• THE AIR WE NEED FOR COMBUSTION IN THE FURNACE AND FLUE
GAS THAT WE MUST EVACUATE
• TRANSPORT AND DRY THE PULVERISED COAL
• SEALING OF BEARINGS FROM COAL/DUST
DRAFT SYSTEM
DRAFT MEANS THE DIFFRENCE BETWEEN THE ATMOSPHERIC PRESSRE
AND PRESSURE EXISTING IN THE FURNACE
•NATURAL DRAFT- OBTAINED BY TALL CHIMNEY
• INDUCED DRAFT- BY ID FANS
• FORCED DRAFT- BY FD FANS
• BALANCE DRAFT - BY ID AND FD FANS
•GENERALLY IN POWER PLANT BALANCE DRAFT SYSTEM IS USED.
FANS IN POWER PLANT
• FORCED DRAFT FAN
• INDUCED DRAFT FAN
• PRIMARY AIR FAN
• SEAL AIR FAN
• SCANNER AIR FAN
THE BASIC INFORMATION NEEDED TO SELECT A FAN ARE
• AIR OR GAS FLOW-KG/HR
• DENSITY(FUNCTION OF TEMPERATURE AND PRESSURE)
• SYSTEM RESISTANCE(LOSSES)
AIR PRE HEATERS
OBJECTIVES
• TO RAISE THE TEMPERATURES OF PRIMARY AND SECONDARY AIR
BY UTILISING HEAT FROM FLUE GAS AT LOW TEMPERATURE
ADVANTAGES OF AIR PREHEATERS
• INCREASE THE BOILER EFFICIENCY
• STABILITY OF COMBUSTION IMPROVED BY USE OF HOT AIR
• PERMITTING TO BURN POOR QUALITY COAL
Ljungstrom type Bisector
TWO PASS BOILER
ARRANGEMENT
Electro Static Precipitator
To remove fly ash from the flue gases
electrostatic precipitators are used.
They have collection efficiency over 99.5%
The efficiency depends on various
parameters such as velocity of flow,
quantity of gas, resistivity of ash, voltage
of fields, temperature etc
Principle of Operation
The fluegas laden with flyash is sent through ducts having negatively charged
plates which give the particles a negative charge. The particles are then routed
past positively charged plates, or grounded plates, which attract the now
negatively-charged ash particles. The particles stick to the positive plates until
they are collected by periodically rapping.
SELECTION OF BOILER
TYPE OF BOILER
Based on steam parameter- Subcritical/ Supercritacal
Based on steam/ water circuit-Once throuh/ drum type
Based on air/ flue gas path- Tower/Two path/ T-type
Type of fuel- Coal fired/ oil fired
Type of draft system-
Type of burner arrangement- Tangential/Front/ opposed
Selection of Firing system- Type of mills
Single reheat/ double reheat
Type of water wall tube- Plain, rifled
Type of tubing arrangement- Spiral/ straight
• Tube leakages from boiler pressure parts.
• Erosion of tubes due to high ash content and velocities
• Over heating of tubes
• Passing from valves causing difficulty in maintaining the parameters
• Failure or incorrectness of measured parameters
• Overloading of boiler due to very poor quality of coal
• Deposition of ash (clinkers) on furnace walls.
• Difficulties in removal of ash from the boiler
• Reduced effectiveness of heat transfer leading to loss of efficiency.
• Improper combustion of coal in the boiler.
Typical Boiler Problems
• Air ingress from the nose arch, penthouse and boiler second pass
and quantification thereof
• Difference between on line reading and the actual oxygen in the flue
gas duct
• Difference between actual and 'on line' temperature
• measurement of air heater air / gas outlet temperatures
• Fouling and Slagging
• High unburnt Carbon in flyash or bottomash
• High air heater leakage
• Boiler operation at high excess air
Typical Boiler Problems contd..
A Few words on Super Critical Boiler
Definition
“CRITICAL” is a thermodynamic expression
describing the state of a substance beyond
which there is no clear distinction between
the liquid and gaseous phase.
 The critical pressure & temperature for
water are
 Pressure = 225.56 Kg / cm2
 Temperature = 374.15 C
SUPERCRITICALTHERMAL CYCLE
ADVANTAGES (1)
 Improvements in plant efficiency by
more than 2 %
 Decrease in Coal Consumption
 Reduction in Green House gases.
 Overall reduction in Auxiliary Power
consumption.
 Reduction in requirement of Ash dyke
Land & Consumptive water.
SUPERCRITICAL – ADVANTAGES (2)
 Sliding pressure operation because of Once
through system .
 Even distribution of heat due to spiral wall
arrangement leading to less Boiler tube failure,
thereby improving system continuity and
availability of the station.
 Low thermal stress in Turbine .
 The startup time is less for boiler.
SUPERCRITICAL – DISADVANTAGES
Higher power consumption of BFP
Higher feed water quality required.
More complex supporting and framing in
Boiler due to Spiral Wall tubes.
Slight higher capital cost.
Description unit 660 500
S/H STEAM FLOW T/HR 2225 1625
SH STEAM PR KG/CM2
256 179
SH STEAM TEMP 0
C 540 540
RH STEAM FLOW T/HR 1742 1397.4
RH STEAM TEMP INLET 0
C 303.7 338.5
RH STEAM TEMP OUTLET 0
C 568 540
RH STEAM PRESS INLET KG/CM2
51.17 46.1
FEED WATER TEMP 0
C 291.4 255.2
COMPARISION OF 660 MW Vs 500 MW BOILER
COST COMPARISON FOR
660 MW vs. 500 MW
DESCRIPTION 660 MW 500 MW
1. 1Cost of Boiler alone 1970.73 Cr 1020.54 Cr
2 Cost of ESP 153.00 Cr Included above
3 Total cost of Boiler + ESP 2124.00 Cr 1020.54 Cr
4 Boiler cost Per MW 1.07 Cr 1.02 Cr
5 Cost of TG for entire stage 1204.72 Cr 634.31 Cr
6 Cost of TG Per MW 0.6Cr 0.63 Cr

More Related Content

What's hot

Report on Boilers at NTPC Ramagunadam
Report on  Boilers at NTPC RamagunadamReport on  Boilers at NTPC Ramagunadam
Report on Boilers at NTPC RamagunadamAbhinay Angari
 
A complete presentation on Boiler.
A complete presentation on Boiler.A complete presentation on Boiler.
A complete presentation on Boiler.Anuj Maurya
 
ASH HANDLING PLANT
ASH HANDLING PLANTASH HANDLING PLANT
ASH HANDLING PLANTAditya Anand
 
Thermal Power plant visit Report by Amit Hinge
Thermal Power plant visit Report by Amit HingeThermal Power plant visit Report by Amit Hinge
Thermal Power plant visit Report by Amit Hingeamit307
 
SUMMER INTERNSHIP(INDUSTRAIL REPORT) ON THERMAL POWER PLANT
SUMMER INTERNSHIP(INDUSTRAIL REPORT) ON THERMAL POWER PLANT SUMMER INTERNSHIP(INDUSTRAIL REPORT) ON THERMAL POWER PLANT
SUMMER INTERNSHIP(INDUSTRAIL REPORT) ON THERMAL POWER PLANT Amit Gupta
 
Ppt for power plant
Ppt for power plantPpt for power plant
Ppt for power plantra m
 
Project Report on Industrial Summer Training at NTPC Simhadri
 Project Report on Industrial Summer Training at NTPC Simhadri Project Report on Industrial Summer Training at NTPC Simhadri
Project Report on Industrial Summer Training at NTPC SimhadriAshish Uppu
 
210 mw turbine cycle heat rate
210 mw turbine cycle heat rate210 mw turbine cycle heat rate
210 mw turbine cycle heat rateManohar Tatwawadi
 
Combined Cycle Gas Turbine Power Plant Part 1
Combined Cycle Gas Turbine Power Plant Part 1Combined Cycle Gas Turbine Power Plant Part 1
Combined Cycle Gas Turbine Power Plant Part 1Anurak Atthasit
 
Thermal Power Plant training Report
Thermal Power Plant training ReportThermal Power Plant training Report
Thermal Power Plant training ReportShani Kumar Singh
 
Heat rate audit in thermal power plant
Heat rate audit in thermal power plantHeat rate audit in thermal power plant
Heat rate audit in thermal power plantSHIVAJI CHOUDHURY
 
Boilers and Its Auxiliaries & Plant Overview
Boilers and Its Auxiliaries & Plant OverviewBoilers and Its Auxiliaries & Plant Overview
Boilers and Its Auxiliaries & Plant Overviewseshu seelamsetti
 
TPS EFFICIENCY AND HEAT RATE
TPS EFFICIENCY AND HEAT RATE TPS EFFICIENCY AND HEAT RATE
TPS EFFICIENCY AND HEAT RATE Manohar Tatwawadi
 
Coal Handling Plant
Coal Handling PlantCoal Handling Plant
Coal Handling PlantVIVEK TOMAR
 

What's hot (20)

Report on Boilers at NTPC Ramagunadam
Report on  Boilers at NTPC RamagunadamReport on  Boilers at NTPC Ramagunadam
Report on Boilers at NTPC Ramagunadam
 
A complete presentation on Boiler.
A complete presentation on Boiler.A complete presentation on Boiler.
A complete presentation on Boiler.
 
ASH HANDLING PLANT
ASH HANDLING PLANTASH HANDLING PLANT
ASH HANDLING PLANT
 
Thermal Power plant visit Report by Amit Hinge
Thermal Power plant visit Report by Amit HingeThermal Power plant visit Report by Amit Hinge
Thermal Power plant visit Report by Amit Hinge
 
Ntpc dadri
Ntpc dadriNtpc dadri
Ntpc dadri
 
SUMMER INTERNSHIP(INDUSTRAIL REPORT) ON THERMAL POWER PLANT
SUMMER INTERNSHIP(INDUSTRAIL REPORT) ON THERMAL POWER PLANT SUMMER INTERNSHIP(INDUSTRAIL REPORT) ON THERMAL POWER PLANT
SUMMER INTERNSHIP(INDUSTRAIL REPORT) ON THERMAL POWER PLANT
 
Ppt for power plant
Ppt for power plantPpt for power plant
Ppt for power plant
 
Presentation on CFBC Boilers
Presentation on CFBC BoilersPresentation on CFBC Boilers
Presentation on CFBC Boilers
 
Project Report on Industrial Summer Training at NTPC Simhadri
 Project Report on Industrial Summer Training at NTPC Simhadri Project Report on Industrial Summer Training at NTPC Simhadri
Project Report on Industrial Summer Training at NTPC Simhadri
 
Cogeneration power plant
Cogeneration power plantCogeneration power plant
Cogeneration power plant
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
210 mw turbine cycle heat rate
210 mw turbine cycle heat rate210 mw turbine cycle heat rate
210 mw turbine cycle heat rate
 
Combined Cycle Gas Turbine Power Plant Part 1
Combined Cycle Gas Turbine Power Plant Part 1Combined Cycle Gas Turbine Power Plant Part 1
Combined Cycle Gas Turbine Power Plant Part 1
 
Steam boilers
Steam boilersSteam boilers
Steam boilers
 
A Seminar On Boiler
A Seminar On BoilerA Seminar On Boiler
A Seminar On Boiler
 
Thermal Power Plant training Report
Thermal Power Plant training ReportThermal Power Plant training Report
Thermal Power Plant training Report
 
Heat rate audit in thermal power plant
Heat rate audit in thermal power plantHeat rate audit in thermal power plant
Heat rate audit in thermal power plant
 
Boilers and Its Auxiliaries & Plant Overview
Boilers and Its Auxiliaries & Plant OverviewBoilers and Its Auxiliaries & Plant Overview
Boilers and Its Auxiliaries & Plant Overview
 
TPS EFFICIENCY AND HEAT RATE
TPS EFFICIENCY AND HEAT RATE TPS EFFICIENCY AND HEAT RATE
TPS EFFICIENCY AND HEAT RATE
 
Coal Handling Plant
Coal Handling PlantCoal Handling Plant
Coal Handling Plant
 

Viewers also liked

Fans in thermal power plants
Fans in thermal power plantsFans in thermal power plants
Fans in thermal power plantsSHIVAJI CHOUDHURY
 
Coal mill pulverizer in thermal power plants
Coal mill pulverizer in thermal power plantsCoal mill pulverizer in thermal power plants
Coal mill pulverizer in thermal power plantsSHIVAJI CHOUDHURY
 
Fan and blowers (mech 326)
Fan and blowers (mech 326)Fan and blowers (mech 326)
Fan and blowers (mech 326)Yuri Melliza
 
STUDY OF VARIOUS SYSTEMS IN 500MW THERMAL POWER PLANT
STUDY OF VARIOUS SYSTEMS IN 500MW THERMAL POWER PLANTSTUDY OF VARIOUS SYSTEMS IN 500MW THERMAL POWER PLANT
STUDY OF VARIOUS SYSTEMS IN 500MW THERMAL POWER PLANTRajashekar Gurrala
 
Amardeep jadeja copy.ppt [autosaved]
Amardeep jadeja   copy.ppt [autosaved]Amardeep jadeja   copy.ppt [autosaved]
Amardeep jadeja copy.ppt [autosaved]Amardeep Jadeja
 
Regenerative feed water heating cycle
Regenerative feed water heating cycleRegenerative feed water heating cycle
Regenerative feed water heating cycle431996
 
Closed feed water heaters :)
Closed feed water heaters :)Closed feed water heaters :)
Closed feed water heaters :)JhePoi Santos
 
Day 3: Fans and Pumps
Day 3: Fans and Pumps Day 3: Fans and Pumps
Day 3: Fans and Pumps RCREEE
 
Feedwater heaters in thermal power plants
Feedwater heaters in thermal power plantsFeedwater heaters in thermal power plants
Feedwater heaters in thermal power plantsSHIVAJI CHOUDHURY
 
Boiler mountings & accessories
Boiler mountings & accessoriesBoiler mountings & accessories
Boiler mountings & accessoriesMalav Patel
 
Boiler ssasit
Boiler  ssasitBoiler  ssasit
Boiler ssasitlotiyo
 
Vocational training at mejia thermal power plant
Vocational training at mejia thermal power plantVocational training at mejia thermal power plant
Vocational training at mejia thermal power plantNipak Banerjee
 
Boiler ssasit
Boiler  ssasitBoiler  ssasit
Boiler ssasitlotiyo
 

Viewers also liked (20)

Fans in thermal power plants
Fans in thermal power plantsFans in thermal power plants
Fans in thermal power plants
 
Fans and blowers
Fans and blowersFans and blowers
Fans and blowers
 
Coal mill pulverizer in thermal power plants
Coal mill pulverizer in thermal power plantsCoal mill pulverizer in thermal power plants
Coal mill pulverizer in thermal power plants
 
Industrial fan(ID FD Fans)
Industrial fan(ID FD Fans)Industrial fan(ID FD Fans)
Industrial fan(ID FD Fans)
 
Study of fans
Study of fansStudy of fans
Study of fans
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
Fan and blowers (mech 326)
Fan and blowers (mech 326)Fan and blowers (mech 326)
Fan and blowers (mech 326)
 
STUDY OF VARIOUS SYSTEMS IN 500MW THERMAL POWER PLANT
STUDY OF VARIOUS SYSTEMS IN 500MW THERMAL POWER PLANTSTUDY OF VARIOUS SYSTEMS IN 500MW THERMAL POWER PLANT
STUDY OF VARIOUS SYSTEMS IN 500MW THERMAL POWER PLANT
 
Amardeep jadeja copy.ppt [autosaved]
Amardeep jadeja   copy.ppt [autosaved]Amardeep jadeja   copy.ppt [autosaved]
Amardeep jadeja copy.ppt [autosaved]
 
Regenerative feed water heating cycle
Regenerative feed water heating cycleRegenerative feed water heating cycle
Regenerative feed water heating cycle
 
Closed feed water heaters :)
Closed feed water heaters :)Closed feed water heaters :)
Closed feed water heaters :)
 
Day 3: Fans and Pumps
Day 3: Fans and Pumps Day 3: Fans and Pumps
Day 3: Fans and Pumps
 
Feedwater heaters in thermal power plants
Feedwater heaters in thermal power plantsFeedwater heaters in thermal power plants
Feedwater heaters in thermal power plants
 
Boiler mountings & accessories
Boiler mountings & accessoriesBoiler mountings & accessories
Boiler mountings & accessories
 
Steam turbine
Steam turbineSteam turbine
Steam turbine
 
Boiler ssasit
Boiler  ssasitBoiler  ssasit
Boiler ssasit
 
Thermal power plant term project
Thermal power plant term projectThermal power plant term project
Thermal power plant term project
 
Vocational training at mejia thermal power plant
Vocational training at mejia thermal power plantVocational training at mejia thermal power plant
Vocational training at mejia thermal power plant
 
Boiler ssasit
Boiler  ssasitBoiler  ssasit
Boiler ssasit
 
371 379
371 379371 379
371 379
 

Similar to Thermal Power Plants

Boiler thermalpowerplants 12898051220529-phpapp02
Boiler thermalpowerplants 12898051220529-phpapp02Boiler thermalpowerplants 12898051220529-phpapp02
Boiler thermalpowerplants 12898051220529-phpapp02akjshare
 
Generation of electricity from coal vol 1
Generation of electricity from coal vol 1Generation of electricity from coal vol 1
Generation of electricity from coal vol 1Sunil9009
 
Generation of electricity from coal parul
Generation of electricity from coal  parulGeneration of electricity from coal  parul
Generation of electricity from coal parulSwapnil Sharma
 
Thermal Power plant familarisation & its Auxillaries
Thermal Power plant familarisation & its AuxillariesThermal Power plant familarisation & its Auxillaries
Thermal Power plant familarisation & its AuxillariesVaibhav Paydelwar
 
Energy conservation boiler
Energy conservation boilerEnergy conservation boiler
Energy conservation boilerMANJUNATH N
 
OVERVIEW OF SUPERCRITICAL THERMAL POWERPLANT , DPSTS
OVERVIEW OF SUPERCRITICAL THERMAL POWERPLANT , DPSTSOVERVIEW OF SUPERCRITICAL THERMAL POWERPLANT , DPSTS
OVERVIEW OF SUPERCRITICAL THERMAL POWERPLANT , DPSTSharshavardhan sivadi
 
Post-combustion CO2 capture and its effects on power plants
Post-combustion CO2 capture and its effects on power plantsPost-combustion CO2 capture and its effects on power plants
Post-combustion CO2 capture and its effects on power plantsHamid Abroshan
 
Heat optimisation pradeep kumar
Heat optimisation  pradeep kumarHeat optimisation  pradeep kumar
Heat optimisation pradeep kumarpradeepdeepi
 
Cfbc & pfbc technology ps jalkote-ea-0366
Cfbc & pfbc technology ps jalkote-ea-0366Cfbc & pfbc technology ps jalkote-ea-0366
Cfbc & pfbc technology ps jalkote-ea-0366vivektmax
 
660 mw supercritical boiler
660 mw supercritical boiler660 mw supercritical boiler
660 mw supercritical boilerAshvani Shukla
 
Developments in Ammonia Production Technology
Developments in Ammonia Production TechnologyDevelopments in Ammonia Production Technology
Developments in Ammonia Production TechnologyJahanzeb Khan
 
Urja thermal solutions
Urja thermal solutionsUrja thermal solutions
Urja thermal solutionsHemant Sharma
 
Ntpc (national thermal power corporation) sipat boiler haxxo24 i~i
Ntpc (national thermal power corporation) sipat boiler haxxo24 i~iNtpc (national thermal power corporation) sipat boiler haxxo24 i~i
Ntpc (national thermal power corporation) sipat boiler haxxo24 i~ihaxxo24
 
Clean Coal Technologies
Clean Coal TechnologiesClean Coal Technologies
Clean Coal TechnologiesArnab Mitra
 
Gasifier Design.pptx
Gasifier Design.pptxGasifier Design.pptx
Gasifier Design.pptxUkashaUsman3
 
Energy audit boiler and steam lines
Energy audit  boiler and steam linesEnergy audit  boiler and steam lines
Energy audit boiler and steam linesRohil Kumar
 
Exhaust heat utility system copy
Exhaust heat utility system   copyExhaust heat utility system   copy
Exhaust heat utility system copyKapil Venkat
 
COAL BASED THERMAL POWER PLANTS (UNIT-1).pptx
COAL BASED THERMAL POWER PLANTS (UNIT-1).pptxCOAL BASED THERMAL POWER PLANTS (UNIT-1).pptx
COAL BASED THERMAL POWER PLANTS (UNIT-1).pptxCHANDRA KUMAR S
 

Similar to Thermal Power Plants (20)

Boiler thermalpowerplants 12898051220529-phpapp02
Boiler thermalpowerplants 12898051220529-phpapp02Boiler thermalpowerplants 12898051220529-phpapp02
Boiler thermalpowerplants 12898051220529-phpapp02
 
Generation of electricity from coal vol 1
Generation of electricity from coal vol 1Generation of electricity from coal vol 1
Generation of electricity from coal vol 1
 
Generation of electricity from coal parul
Generation of electricity from coal  parulGeneration of electricity from coal  parul
Generation of electricity from coal parul
 
Thermal Power plant familarisation & its Auxillaries
Thermal Power plant familarisation & its AuxillariesThermal Power plant familarisation & its Auxillaries
Thermal Power plant familarisation & its Auxillaries
 
Energy conservation boiler
Energy conservation boilerEnergy conservation boiler
Energy conservation boiler
 
OVERVIEW OF SUPERCRITICAL THERMAL POWERPLANT , DPSTS
OVERVIEW OF SUPERCRITICAL THERMAL POWERPLANT , DPSTSOVERVIEW OF SUPERCRITICAL THERMAL POWERPLANT , DPSTS
OVERVIEW OF SUPERCRITICAL THERMAL POWERPLANT , DPSTS
 
Post-combustion CO2 capture and its effects on power plants
Post-combustion CO2 capture and its effects on power plantsPost-combustion CO2 capture and its effects on power plants
Post-combustion CO2 capture and its effects on power plants
 
Heat optimisation pradeep kumar
Heat optimisation  pradeep kumarHeat optimisation  pradeep kumar
Heat optimisation pradeep kumar
 
Cfbc & pfbc technology ps jalkote-ea-0366
Cfbc & pfbc technology ps jalkote-ea-0366Cfbc & pfbc technology ps jalkote-ea-0366
Cfbc & pfbc technology ps jalkote-ea-0366
 
660 mw supercritical boiler
660 mw supercritical boiler660 mw supercritical boiler
660 mw supercritical boiler
 
Developments in Ammonia Production Technology
Developments in Ammonia Production TechnologyDevelopments in Ammonia Production Technology
Developments in Ammonia Production Technology
 
Urja thermal solutions
Urja thermal solutionsUrja thermal solutions
Urja thermal solutions
 
Adavance Power Plants
Adavance Power PlantsAdavance Power Plants
Adavance Power Plants
 
Ntpc (national thermal power corporation) sipat boiler haxxo24 i~i
Ntpc (national thermal power corporation) sipat boiler haxxo24 i~iNtpc (national thermal power corporation) sipat boiler haxxo24 i~i
Ntpc (national thermal power corporation) sipat boiler haxxo24 i~i
 
Conserve energy
Conserve energyConserve energy
Conserve energy
 
Clean Coal Technologies
Clean Coal TechnologiesClean Coal Technologies
Clean Coal Technologies
 
Gasifier Design.pptx
Gasifier Design.pptxGasifier Design.pptx
Gasifier Design.pptx
 
Energy audit boiler and steam lines
Energy audit  boiler and steam linesEnergy audit  boiler and steam lines
Energy audit boiler and steam lines
 
Exhaust heat utility system copy
Exhaust heat utility system   copyExhaust heat utility system   copy
Exhaust heat utility system copy
 
COAL BASED THERMAL POWER PLANTS (UNIT-1).pptx
COAL BASED THERMAL POWER PLANTS (UNIT-1).pptxCOAL BASED THERMAL POWER PLANTS (UNIT-1).pptx
COAL BASED THERMAL POWER PLANTS (UNIT-1).pptx
 

Recently uploaded

JavaScript Usage Statistics 2024 - The Ultimate Guide
JavaScript Usage Statistics 2024 - The Ultimate GuideJavaScript Usage Statistics 2024 - The Ultimate Guide
JavaScript Usage Statistics 2024 - The Ultimate GuidePixlogix Infotech
 
JohnPollard-hybrid-app-RailsConf2024.pptx
JohnPollard-hybrid-app-RailsConf2024.pptxJohnPollard-hybrid-app-RailsConf2024.pptx
JohnPollard-hybrid-app-RailsConf2024.pptxJohnPollard37
 
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost SavingRepurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost SavingEdi Saputra
 
Rising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdf
Rising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdfRising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdf
Rising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdfOrbitshub
 
Corporate and higher education May webinar.pptx
Corporate and higher education May webinar.pptxCorporate and higher education May webinar.pptx
Corporate and higher education May webinar.pptxRustici Software
 
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FMESafe Software
 
DBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor PresentationDBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor PresentationDropbox
 
WSO2's API Vision: Unifying Control, Empowering Developers
WSO2's API Vision: Unifying Control, Empowering DevelopersWSO2's API Vision: Unifying Control, Empowering Developers
WSO2's API Vision: Unifying Control, Empowering DevelopersWSO2
 
Platformless Horizons for Digital Adaptability
Platformless Horizons for Digital AdaptabilityPlatformless Horizons for Digital Adaptability
Platformless Horizons for Digital AdaptabilityWSO2
 
Navigating Identity and Access Management in the Modern Enterprise
Navigating Identity and Access Management in the Modern EnterpriseNavigating Identity and Access Management in the Modern Enterprise
Navigating Identity and Access Management in the Modern EnterpriseWSO2
 
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FMESafe Software
 
Architecting Cloud Native Applications
Architecting Cloud Native ApplicationsArchitecting Cloud Native Applications
Architecting Cloud Native ApplicationsWSO2
 
Six Myths about Ontologies: The Basics of Formal Ontology
Six Myths about Ontologies: The Basics of Formal OntologySix Myths about Ontologies: The Basics of Formal Ontology
Six Myths about Ontologies: The Basics of Formal Ontologyjohnbeverley2021
 
Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024Victor Rentea
 
WSO2 Micro Integrator for Enterprise Integration in a Decentralized, Microser...
WSO2 Micro Integrator for Enterprise Integration in a Decentralized, Microser...WSO2 Micro Integrator for Enterprise Integration in a Decentralized, Microser...
WSO2 Micro Integrator for Enterprise Integration in a Decentralized, Microser...WSO2
 
Stronger Together: Developing an Organizational Strategy for Accessible Desig...
Stronger Together: Developing an Organizational Strategy for Accessible Desig...Stronger Together: Developing an Organizational Strategy for Accessible Desig...
Stronger Together: Developing an Organizational Strategy for Accessible Desig...caitlingebhard1
 
Introduction to use of FHIR Documents in ABDM
Introduction to use of FHIR Documents in ABDMIntroduction to use of FHIR Documents in ABDM
Introduction to use of FHIR Documents in ABDMKumar Satyam
 
API Governance and Monetization - The evolution of API governance
API Governance and Monetization -  The evolution of API governanceAPI Governance and Monetization -  The evolution of API governance
API Governance and Monetization - The evolution of API governanceWSO2
 
How to Check CNIC Information Online with Pakdata cf
How to Check CNIC Information Online with Pakdata cfHow to Check CNIC Information Online with Pakdata cf
How to Check CNIC Information Online with Pakdata cfdanishmna97
 
MINDCTI Revenue Release Quarter One 2024
MINDCTI Revenue Release Quarter One 2024MINDCTI Revenue Release Quarter One 2024
MINDCTI Revenue Release Quarter One 2024MIND CTI
 

Recently uploaded (20)

JavaScript Usage Statistics 2024 - The Ultimate Guide
JavaScript Usage Statistics 2024 - The Ultimate GuideJavaScript Usage Statistics 2024 - The Ultimate Guide
JavaScript Usage Statistics 2024 - The Ultimate Guide
 
JohnPollard-hybrid-app-RailsConf2024.pptx
JohnPollard-hybrid-app-RailsConf2024.pptxJohnPollard-hybrid-app-RailsConf2024.pptx
JohnPollard-hybrid-app-RailsConf2024.pptx
 
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost SavingRepurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
 
Rising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdf
Rising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdfRising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdf
Rising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdf
 
Corporate and higher education May webinar.pptx
Corporate and higher education May webinar.pptxCorporate and higher education May webinar.pptx
Corporate and higher education May webinar.pptx
 
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
 
DBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor PresentationDBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor Presentation
 
WSO2's API Vision: Unifying Control, Empowering Developers
WSO2's API Vision: Unifying Control, Empowering DevelopersWSO2's API Vision: Unifying Control, Empowering Developers
WSO2's API Vision: Unifying Control, Empowering Developers
 
Platformless Horizons for Digital Adaptability
Platformless Horizons for Digital AdaptabilityPlatformless Horizons for Digital Adaptability
Platformless Horizons for Digital Adaptability
 
Navigating Identity and Access Management in the Modern Enterprise
Navigating Identity and Access Management in the Modern EnterpriseNavigating Identity and Access Management in the Modern Enterprise
Navigating Identity and Access Management in the Modern Enterprise
 
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
 
Architecting Cloud Native Applications
Architecting Cloud Native ApplicationsArchitecting Cloud Native Applications
Architecting Cloud Native Applications
 
Six Myths about Ontologies: The Basics of Formal Ontology
Six Myths about Ontologies: The Basics of Formal OntologySix Myths about Ontologies: The Basics of Formal Ontology
Six Myths about Ontologies: The Basics of Formal Ontology
 
Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024
 
WSO2 Micro Integrator for Enterprise Integration in a Decentralized, Microser...
WSO2 Micro Integrator for Enterprise Integration in a Decentralized, Microser...WSO2 Micro Integrator for Enterprise Integration in a Decentralized, Microser...
WSO2 Micro Integrator for Enterprise Integration in a Decentralized, Microser...
 
Stronger Together: Developing an Organizational Strategy for Accessible Desig...
Stronger Together: Developing an Organizational Strategy for Accessible Desig...Stronger Together: Developing an Organizational Strategy for Accessible Desig...
Stronger Together: Developing an Organizational Strategy for Accessible Desig...
 
Introduction to use of FHIR Documents in ABDM
Introduction to use of FHIR Documents in ABDMIntroduction to use of FHIR Documents in ABDM
Introduction to use of FHIR Documents in ABDM
 
API Governance and Monetization - The evolution of API governance
API Governance and Monetization -  The evolution of API governanceAPI Governance and Monetization -  The evolution of API governance
API Governance and Monetization - The evolution of API governance
 
How to Check CNIC Information Online with Pakdata cf
How to Check CNIC Information Online with Pakdata cfHow to Check CNIC Information Online with Pakdata cf
How to Check CNIC Information Online with Pakdata cf
 
MINDCTI Revenue Release Quarter One 2024
MINDCTI Revenue Release Quarter One 2024MINDCTI Revenue Release Quarter One 2024
MINDCTI Revenue Release Quarter One 2024
 

Thermal Power Plants

  • 2. Coal to Electricity ….. Basics Coal Chemical Energy Super Heated Steam Pollutants Thermal Energy Turbine Torque Heat LossIn Condenser Kinetic Energy Electrical Energy Alternating current in Stator Mech. Energy LossASH Heat Loss Elet. Energy Loss
  • 4. Why Coal? Coal 55% Gas 10% Diesel 1% Hydel 26% RES 5% Nuclear 3% Share of Coal in Power Generation Advantages of Coal Fuel •Abundantly available in India •Low cost •Technology for Power Generation well developed. •Easy to handle, transport, store and use Shortcomings of Coal •Low Calorific Value •Large quantity to be Handled •Produces pollutants, ash •Disposal of ash is Problematic •Reserves depleting fast •India’s Coal Reserves are estimated to be 206 billion tonnes. Present consumption is about 450 million tonnes. •Cost of coal for producing 1 unit of electricity (Cost of coal Rs 1000/MT)is Rs 0.75. •Cost of Gas for producing 1 unit of electricity (Cost of Gas Rs 6/SMC)is Rs 1.20.
  • 5. Knowing more about Coal Coal production •Surface Mining •Underground Mining Coal Transportation •Rail •Truck •Conveyor •Ship Coal Properties •Calorific Value •Grade of Coal (UHV) •Proximate Analysis •Ultimate Analysis •Ash and Minerals •Grindability •Rank •Physical Characteristics Coal Beneficiation •Why? •Processes •Effectiveness Coal production •Surface Mining •Underground Mining Useful Heat Value (UHV) UHV= 8900-138(A+M)
  • 6. Boiler/ steam generator  Steam generating device for a specific purpose.  Capable to meet variation in load demand  Capable of generating steam in a range of operating pressure and temperature  For utility purpose, it should generate steam uninterruptedly at operating pressure and temperature for running steam turbines.
  • 7. Boiler/ steam generator  Raw materials for design of boilers 1. Coal from mines 2. Ambient air 3. Water from natural resources (river, ponds) o Generating heat energy o Air for combustion o Working fluid for steam generation, possessing heat energy A 500MW steam generator consumes about 8000 tonnes of coal every day It will be considered if it requires about 200 cubic meter of DM water in a day It will produce about 9500 tonnes of Carbon di Oxide every day
  • 8. Coal analysis  Typical composition (Proximate analysis) 1. Fixed carbon 2. Fuel ash 3. Volatile material 4. Total Moisture 5. Sulfur o High calorific value/ Lower calorific value (Kcal/kg) o Hardgrove Index (HGI)
  • 9. Combustion of coal  Carbon, hydrogen, sulfur are sources of heat on combustion  Surface moisture removed on heating during pulverization.  Inherent moisture and volatiles are released at higher temperature, making coal porous and leading to char/ coke formation. (Thermal preparation stage)
  • 10. Fuel Oil  Three liquid fuels used in power plants • 1. Heavy Fuel Oil (HFO) • 2. LSHS (Low Sulfur Heavy stock) • 3. High speed Diesel (HSD) Oil firing is preceded by  Lowering viscosity and increasing flowability on heating for better combustion in given turn down ratio. (125o C)  Droplet formation on atomization (by steam/ compressed air/ mechanical pressurization)  Combustion initiation by High energy spark ignition
  • 11. Combustion of reactants  Reaction rate depends on concentration of one of the reactants  Concentration varies on partial pressure of the reactants.  Partial pressure is a function of gas temperature.  Therefore, reaction rate depends on temperature and substance that enter the reaction.
  • 12. Combustion Reactions (Carbon)  Main reactions 2C + O2 = 2CO + 3950 BTU/lb(Deficit air) C + O2 = CO2 +14093 BTU/lb Secondary reactions 2CO + O2 = 2CO2 + 4347BTU/lb C + CO2 = 2CO -7.25MJ/kg
  • 13. Combustion Reactions (Carbon)  Carbon reaction 2C + O2 =2CO [Eco =60kJ/mol] C + O2 =CO2 [Eco2 =140kJ/mol] reaction at 1200o C 4C + 3O2 =2CO + 2CO2 (Ratio 1:1) Reaction at 1700o C 3C + 2O2 = 2CO +CO2 (Ratio 2:1) It is desirable to supply combustion air at lower temperature regime in furnace
  • 14. Combustion Reaction (H2, S)  Hydrogen reaction 2H2 + O2 = 2H2O +61095 BTU/lb  Sulfur reaction S + O2 = SO2 + 3980 BTU/lb (undesirable)
  • 15. Coal for combustion  Anthracite  Semi-anthracite  Bituminous  Semi-Bituminous  Lignite  Peat  High CV, low VM  High CV, low VM  Medium CV, medium VM  Medium CV, medium VM  Low CV, high VM, high TM  Very low CV, high VM & TM
  • 16. Heat Generation in furnace  Heat input in the furnace  Efficiency of thermal power plants is 37%-45% for different types of cycle  For typical conventional P.F. boilers, coal flow rate is 290-350 T/hr For 500 MW units 120-145 T/hr For 200 MW units Cycle Elect Furnace MW Q η =
  • 17.
  • 18.
  • 20.
  • 21.
  • 22.
  • 23. MAIN EQUIPMENTS OF FUEL & FIRING SYSTEM • MILLS OR PULVERISERS • FEDDERS • BURNERS TYPES OF FEEDERS • VOLUMETRIC FEEDRES • GRAVIMETRIC FEEDERS
  • 24. PULVERIZERS OBJECTIVES • TO CRUSHED THE COAL • REDCED TO A FINENESS SUCH THAT 70-80% PASSES THROUGH A 200MESH SIEVE ADVANTAGES OF PULVERISED COAL FIRING • EFFICIENT UTILISATION OF CHEAPER GRADE OF COALS • FLEXIBILITY IN FIRING WITH ABILITY TO MEET FLUCTUATING LOADS • BETTER COAL COMBUSTION INCREASING THE BOILER EFFICIENCY • HIGH AVAILIBILITY
  • 25. X R P ( B H E L ) E M IL L S ( B A B C O C K ) M P S B O W L / B A L L & R A C E V E R T IC A L S P IN D L E P R E S S U R IZ E D T U B E C L A S S IF IC A T IO N O F M IL L S
  • 26. BOWL MILL Model no. Base capacity(T/Hr) 623XRP 18.4 703XRP 26.4 763XRP 33.8 803XRP 36.5 883XRP 51.1 903XRP 54.1 1003XRP 68.1 1043XRP 72.0 BASE CAPACITY(T/HR) AT HGI -55 Total Moisture-10% Fineness-70% THRU 200 MESH
  • 27. BALL& RACE MILL(E MILL) Model no. Base capacity(T/Hr) 7E9 25 8.5E10 35 8.5E9 40 10E10 55 10.9E11 61 10.9E10 70 10.9E8 80
  • 28. TUBE MILL Model no. Base capacity(T/Hr) BBD4760 83 BBD4772 90
  • 29. AIR AND DRAFT SYSTEM OBJECTIVES • THE AIR WE NEED FOR COMBUSTION IN THE FURNACE AND FLUE GAS THAT WE MUST EVACUATE • TRANSPORT AND DRY THE PULVERISED COAL • SEALING OF BEARINGS FROM COAL/DUST DRAFT SYSTEM DRAFT MEANS THE DIFFRENCE BETWEEN THE ATMOSPHERIC PRESSRE AND PRESSURE EXISTING IN THE FURNACE •NATURAL DRAFT- OBTAINED BY TALL CHIMNEY • INDUCED DRAFT- BY ID FANS • FORCED DRAFT- BY FD FANS • BALANCE DRAFT - BY ID AND FD FANS •GENERALLY IN POWER PLANT BALANCE DRAFT SYSTEM IS USED.
  • 30. FANS IN POWER PLANT • FORCED DRAFT FAN • INDUCED DRAFT FAN • PRIMARY AIR FAN • SEAL AIR FAN • SCANNER AIR FAN THE BASIC INFORMATION NEEDED TO SELECT A FAN ARE • AIR OR GAS FLOW-KG/HR • DENSITY(FUNCTION OF TEMPERATURE AND PRESSURE) • SYSTEM RESISTANCE(LOSSES)
  • 31. AIR PRE HEATERS OBJECTIVES • TO RAISE THE TEMPERATURES OF PRIMARY AND SECONDARY AIR BY UTILISING HEAT FROM FLUE GAS AT LOW TEMPERATURE ADVANTAGES OF AIR PREHEATERS • INCREASE THE BOILER EFFICIENCY • STABILITY OF COMBUSTION IMPROVED BY USE OF HOT AIR • PERMITTING TO BURN POOR QUALITY COAL
  • 32.
  • 35. Electro Static Precipitator To remove fly ash from the flue gases electrostatic precipitators are used. They have collection efficiency over 99.5% The efficiency depends on various parameters such as velocity of flow, quantity of gas, resistivity of ash, voltage of fields, temperature etc
  • 36. Principle of Operation The fluegas laden with flyash is sent through ducts having negatively charged plates which give the particles a negative charge. The particles are then routed past positively charged plates, or grounded plates, which attract the now negatively-charged ash particles. The particles stick to the positive plates until they are collected by periodically rapping.
  • 37.
  • 38.
  • 39. SELECTION OF BOILER TYPE OF BOILER Based on steam parameter- Subcritical/ Supercritacal Based on steam/ water circuit-Once throuh/ drum type Based on air/ flue gas path- Tower/Two path/ T-type Type of fuel- Coal fired/ oil fired Type of draft system- Type of burner arrangement- Tangential/Front/ opposed Selection of Firing system- Type of mills Single reheat/ double reheat Type of water wall tube- Plain, rifled Type of tubing arrangement- Spiral/ straight
  • 40. • Tube leakages from boiler pressure parts. • Erosion of tubes due to high ash content and velocities • Over heating of tubes • Passing from valves causing difficulty in maintaining the parameters • Failure or incorrectness of measured parameters • Overloading of boiler due to very poor quality of coal • Deposition of ash (clinkers) on furnace walls. • Difficulties in removal of ash from the boiler • Reduced effectiveness of heat transfer leading to loss of efficiency. • Improper combustion of coal in the boiler. Typical Boiler Problems
  • 41. • Air ingress from the nose arch, penthouse and boiler second pass and quantification thereof • Difference between on line reading and the actual oxygen in the flue gas duct • Difference between actual and 'on line' temperature • measurement of air heater air / gas outlet temperatures • Fouling and Slagging • High unburnt Carbon in flyash or bottomash • High air heater leakage • Boiler operation at high excess air Typical Boiler Problems contd..
  • 42. A Few words on Super Critical Boiler Definition “CRITICAL” is a thermodynamic expression describing the state of a substance beyond which there is no clear distinction between the liquid and gaseous phase.  The critical pressure & temperature for water are  Pressure = 225.56 Kg / cm2  Temperature = 374.15 C
  • 43. SUPERCRITICALTHERMAL CYCLE ADVANTAGES (1)  Improvements in plant efficiency by more than 2 %  Decrease in Coal Consumption  Reduction in Green House gases.  Overall reduction in Auxiliary Power consumption.  Reduction in requirement of Ash dyke Land & Consumptive water.
  • 44. SUPERCRITICAL – ADVANTAGES (2)  Sliding pressure operation because of Once through system .  Even distribution of heat due to spiral wall arrangement leading to less Boiler tube failure, thereby improving system continuity and availability of the station.  Low thermal stress in Turbine .  The startup time is less for boiler.
  • 45. SUPERCRITICAL – DISADVANTAGES Higher power consumption of BFP Higher feed water quality required. More complex supporting and framing in Boiler due to Spiral Wall tubes. Slight higher capital cost.
  • 46. Description unit 660 500 S/H STEAM FLOW T/HR 2225 1625 SH STEAM PR KG/CM2 256 179 SH STEAM TEMP 0 C 540 540 RH STEAM FLOW T/HR 1742 1397.4 RH STEAM TEMP INLET 0 C 303.7 338.5 RH STEAM TEMP OUTLET 0 C 568 540 RH STEAM PRESS INLET KG/CM2 51.17 46.1 FEED WATER TEMP 0 C 291.4 255.2 COMPARISION OF 660 MW Vs 500 MW BOILER
  • 47. COST COMPARISON FOR 660 MW vs. 500 MW DESCRIPTION 660 MW 500 MW 1. 1Cost of Boiler alone 1970.73 Cr 1020.54 Cr 2 Cost of ESP 153.00 Cr Included above 3 Total cost of Boiler + ESP 2124.00 Cr 1020.54 Cr 4 Boiler cost Per MW 1.07 Cr 1.02 Cr 5 Cost of TG for entire stage 1204.72 Cr 634.31 Cr 6 Cost of TG Per MW 0.6Cr 0.63 Cr