The Pathway to Documenting
Successful Contract Claims
April 22, 2013
By: Mohamed Hassanin’ PMP
E-mail : www.mohamed@gmail.com
It is Important to Recognize
A. Requirements of a Successful
Claim
B. The Main Reasons for Disputes
Arising on a Construction
Projects
2
Claims
Claims arise on many construction
projects. A great deal of emotion is
wasted by parties to a construction
dispute because claims are often not
fully and fairly documented and
properly presented.
The purpose of this presentation is to
provide practical tips in organizing,
documenting, negotiating and
resolving construction claims.
3
A. Requirements of a Successful Claim
Many contractors harm their credibility in providing verbose, complicated,
emotionally charged and over reaching claims without addressing the primary
requirements for a successful claim.
What Are The Requirements of a Successful Claim???
1. Recognize when a potential claim arises and provide timely notice;
2. Determine the facts;
3. Establish entitlement/identify the applicable contract provision or
law/establish liability;
4. Establish causation;
5. Calculate damages in accordance with the contract; and
6. Negotiate or adjudicate the claim.
4
1. Recognize when a potential claim arises and provide timely
notice
It is quite common that at the commencement of construction,
both parties wish to remain in a non-adversarial relationship.
No one likes to give notice of a claim at the early stages of a
construction project
Early notice of claim has the advantage of avoiding surprise and
enables the parties at an early stage to consider solutions to avoid
and minimize the impact of any potential claim.
Timely notice of a claim is critical to the claim’s ultimate success.
5
A. Requirements of a Successful Claim (Count.)
When Notices Can Be Sent ???
• Changes, (Changing In Scope, Specifications, Quantities….)
• Unknown Site Conditions (discovers subsurface conditions )
• Delays (Delayed in the performance of the work)
• Force Majeure In the event that force majeure has prevented (or will
prevent) a party from performing an obligation.
• Terminate the Contract by Owner or Contractor
• Dispute Resolution If a dispute arises between the parties
• Damages
• Waiver of Claims If any party waives and releases the other party from all
claims
• Warranty The owner is obliged to provide a notice in writing of defects
6
A. Requirements of a Successful Claim (Count.)
2. DETERMINE THE FACTS
• Often contractors are unsuccessful in presenting a claim because the
historical account is unclear because of poor contract administration.
• It is extremely important that a proper program of record be implemented
in order to successfully capture all facts.
Suggestions for Proper Contract Documentation:
• Establish effective estimating cost accounting systems and procedures
• Record and track both budgeted and actual work quantities, costs, labor
hours and productivity
• Track the cost of all changes,
• Use photographs , daily diaries and other data collection techniques .
7
A. Requirements of a Successful Claim (Count.)
• Develop standard forms for costing information, allocating labor and
materials to extra work.
• Daily report which includes basic project information, weather information,
site conditions, activities, use of equipment, work performed, man-power
and material deliveries.
• Communication and Correspondence must be clear and concise. Limit each
letter to one topic.
• Maintain logs for change order and submittals.
If these records are properly maintained, they should be an excellent
collection of information to form the factual basis of a claim.
8
A. Requirements of a Successful Claim (Count.)
3. ESTABLISH ENTITLEMENT
• A claim will have no chance of success if it is not grounded in the contract
• There must be a breach of an obligation by a party to the contract or a
change in the scope of the work or a delay under the contract as a basis for
a claim.
• Contracts on large projects contain many volumes of specifications and
often consist of a confused assembly of general conditions, special
provisions, special conditions, specifications, etc
A detailed familiarity with the terms and conditions of the contract is essential
to the success of a claim. In order to be successful, the contractor must be
familiar with the Dispute Resolution Clauses.
9
A. Requirements of a Successful Claim (Count.)
10
In establishing entitlement, the following information should be collected:
• Identify the issue and establish a claim file
• Provide notice of claim with specific contractual references
• Define the scope of the problem, change, delay, impact, etc.;
• Maintain proper records of costs;
• Base Line Schedule and updated schedule;
• Prepare an estimate of the costs .
Document the change order or delay request describing the scope of the
work, the proposed cost and time, direct costs, indirect costs, overhead
costs and profit – use a standard cost estimating form to price out the
costs.
A. Requirements of a Successful Claim (Count.)
4. CAUSATION
•Without establishing causation, there is no basis of a claim.
•Writing a lot of letters and pointing an finger does not establish causation.
•Causation is established by the injured party demonstrating that its loss due to
an act or omission of the other party or by Force majeure event.
•The most important requirement is a proper analysis of the facts.
Whatever evidence is presented there must be a clear understanding of what it
is meant to establish and the evidence must be in a form which can be readily
understood by parties.
11
A. Requirements of a Successful Claim (Count.)
5. CALCULATE DAMAGES
Many contractors spend a great deal of effort in documenting the claim and
establishing causation but pay little attention to the calculation of damages.
Calculating damages can be one or more of following:
Extra Work: This claim should include the direct labor hours, equipment and
subcontractor costs incurred in performing extra work. It should also include
supervision, overhead and profit as agreed in the contract.
12
A. Requirements of a Successful Claim (Count.)
Delay Costs: These costs should include the additional labor hours, additional
equipment time and supervision costs incurred beyond the planned completion
date for the contract. These costs should also include a component for site
indirect costs as well as home office overhead for the extended period.
Acceleration: This claim includes the premium overtime hours incurred by a
contractor in accelerating the work in order to meet a completion date.
Subcontractor Claims: This claim usually involves subcontractor claims of
delay, productivity or acceleration and should be documented in detail by each
subcontractor.
13
A. Requirements of a Successful Claim (Count.)
Overhead: This claim usually involves a claim for head office or site office
overheads for the incurred losses.
Profit: Profit may be claimed on the basis of the rate planned at the time of
bidding of the tender for the project.
Financing Costs: This is a claim for the costs of financing or other bank
interest charges.
14
A. Requirements of a Successful Claim (Count.)
6. NEGOTIATE THE CLAIM
•A properly documented and presented claim is much easier to negotiate the
claim.
•Negotiation is a much more profitable result for the resolution of a claim than
arbitration or litigation.
•Preparation for negotiations is key. In order to be successful,
15
A. Requirements of a Successful Claim (Count.)
CONCLUSION
•The proper organization and presentation of a claim takes time and a great
deal of care.
•More often than not, the claim reviewers must answer to corporate or
governmental managers whether or not a claim is valid and should be paid.
•Well prepared and documented claims are much more successful in getting
paid than ill prepared claims that lack foundation, analysis and justification.
If you follow the recommendations set out above, you will
have a much greater chance of success in having your claims
paid.
16
A. Requirements of a Successful Claim (Count.)
What are the most important causes that lead to claims?
Causes of claims
1. The increased complexity of projects
2. The effects of high inflation and decrease in profits
3. The high speed of construction and materials technology
4. Decreased capital availability
5. Withdrawal of governmental support to the contractors
6. Contractors have become more sophisticated
7. The economy's impact on the construction industry
8. Force Majeure
17
B. The Main Reasons for Disputes Arising on a
Construction Projects
Types of claims
A. Contractual claims.
B. Delay claims.
C. Acceleration claims
D. Change claims
E. Extra work claims
F. Different site conditions claims
G. Different measurement pricing claims
H. Damage claims
18
B. The Main Reasons for Disputes Arising on a
Construction Projects
Claims Factors Groups
1st Group: Poor planning
• Delay caused by owner
• Change orders
• Financial problem
• Delay in payment
• Planning errors
• Bad communication between parties
19
B. The Main Reasons for Disputes Arising on a
Construction Projects
2nd Group: Errors or Incomplete Documentation
• Design errors or omissions
• Poorly written contracts
• Variation in quantity and measurements
• Inconsistency of specifications and drawing
• Sub-contracting problem
• Constructive changes and Oral change orders
• Termination & Suspension of work
20
B. The Main Reasons for Disputes Arising on a
Construction Projects
3rd Group: Scheduling and Estimating Errors
• Changes in material and costs (Escalation)
• Delay caused by contractor
• Scheduling errors
• Subsurface problems
• Estimating errors
4th Group: Execution Deficiencies
• Execution errors
• Changes in material types
• Poor quality of the contractors work
• Accidents
21
B. The Main Reasons for Disputes Arising on a
Construction Projects
5th Group: Construction Environment
• Contractors not well organized
• Owners personality
• Government regulation
• Non-permitted contractors
• Low price of the contracts
22
B. The Main Reasons for Disputes Arising on a
Construction Projects
What are the Most Frequent Causes?
• Changes claims
• Delay claims
• Extra work claims
• Contractual claims
• Damage Claims
Changes claims: Depending on the contract and its terms, such changes
might have an effect in value addition to or deletions from the contract,
modifications of the work.
.
23
B. The Main Reasons for Disputes Arising on a
Construction Projects
Delay Claim: This category is subdivided into three main types as follows:
 Excusable delays: These are delays for which neither the owner nor the
contractor is responsible (Force Majeure).
 Compensable delays: for which the contractor is entitled to
compensation.
 Inexcusable delays: these delays represent problems in the contractor’s
organization such as lack of management or financial capability.
Extra Work Claims:
Extra work is any work that is ordered by the owner after construction has
started that was not included in the original contract.
24
B. The Main Reasons for Disputes Arising on a
Construction Projects
Contractual Claims:
•Contractual claims concerns matters with regard to the contract itself. This
includes any disagreement on the responsibility or liability of some parts that
are not included in the contract documents.
•The main reason of these types of claims is poorly written contracts.
Difference in Pricing Claims:
•These types of claims deal with the disagreement regarding measurements at
the final stage in the construction.
•Difference pricing by the contractor and the owner of some of the materials.
•The scope changes and the extra work usually create some differences in
pricing.
25
B. The Main Reasons for Disputes Arising on a
Construction Projects
Damage Claims:
•Property damages may occur due to the act of the owner or safety related
problems.
•This type of claims is very rare because usually contractors have the total
responsibility for the site.
Finally We Can Say
Careful preparation of the contract documents will help to avoid
disputes. The scope of the project should be clear, correct and
concise. Also, the contractor should ask the owner to write the
change orders instead of giving verbal change orders.
26
B. The Main Reasons for Disputes Arising on a
Construction Projects
27
Thank You for your attention

More Related Content

What's hot

Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)
mohamed Ismail
 
Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)Fakhar-un -Nisa
 
Fidic contracts management introduction
Fidic contracts management introductionFidic contracts management introduction
Fidic contracts management introduction
Essam Lotffy, PMP®, CCP®
 
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16Arvind Solanki
 
FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
FIDIC 2017 Yellow and Silver in EPC and PPP ContractsFIDIC 2017 Yellow and Silver in EPC and PPP Contracts
FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
Loay Ghazaleh MBA, BSc Civil Eng.
 
Contract payment and variation
Contract payment and variationContract payment and variation
Contract payment and variation
Vj NiroSh
 
Fidic Form of Contract.
Fidic Form of Contract.Fidic Form of Contract.
Fidic Form of Contract.
Shantanu Kumar Behera
 
Contracts & Claims Management Workshop (Session-1)
Contracts & Claims Management Workshop (Session-1)Contracts & Claims Management Workshop (Session-1)
Contracts & Claims Management Workshop (Session-1)Tahir B Mirza
 
Construction tender process
Construction tender processConstruction tender process
# FIDIC Payment Flow Charts # By SN Panigrahi
# FIDIC Payment Flow Charts # By SN Panigrahi# FIDIC Payment Flow Charts # By SN Panigrahi
# FIDIC Payment Flow Charts # By SN Panigrahi
SN Panigrahi, PMP
 
Tenders for construction
Tenders for constructionTenders for construction
Tenders for construction
gandrajuadityavarmagav
 
Construction claims, disputes and project closure
Construction claims, disputes and project closureConstruction claims, disputes and project closure
Construction claims, disputes and project closure
srinivas2036
 
EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
 EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
HossamNegidaPMPRMPPS
 
Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...
Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...
Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...
Divyanshu Dayal
 
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdfFIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
BayuDarma4
 
"Types and Causes of Construction Claims"
"Types and Causes of Construction Claims""Types and Causes of Construction Claims"
"Types and Causes of Construction Claims"
Abhishek Shah
 
Ss training fidic moustafa ismail 2017 _ lec. 1
Ss training fidic moustafa ismail  2017 _ lec. 1Ss training fidic moustafa ismail  2017 _ lec. 1
Ss training fidic moustafa ismail 2017 _ lec. 1
Moustafa Ismail Abu Dief
 
fidic-flow-chart.pptx
fidic-flow-chart.pptxfidic-flow-chart.pptx
fidic-flow-chart.pptx
ssuserb337ce1
 
FIDIC variation, claim & dispute - CYLFEx workshop
FIDIC variation, claim & dispute - CYLFEx workshopFIDIC variation, claim & dispute - CYLFEx workshop
FIDIC variation, claim & dispute - CYLFEx workshop
M Maged Hegazy, LLM, MBA, CCP, P3O
 

What's hot (20)

Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)
 
Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)
 
Fidic contracts management introduction
Fidic contracts management introductionFidic contracts management introduction
Fidic contracts management introduction
 
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
 
FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
FIDIC 2017 Yellow and Silver in EPC and PPP ContractsFIDIC 2017 Yellow and Silver in EPC and PPP Contracts
FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
 
Contract payment and variation
Contract payment and variationContract payment and variation
Contract payment and variation
 
Fidic Form of Contract.
Fidic Form of Contract.Fidic Form of Contract.
Fidic Form of Contract.
 
Contracts & Claims Management Workshop (Session-1)
Contracts & Claims Management Workshop (Session-1)Contracts & Claims Management Workshop (Session-1)
Contracts & Claims Management Workshop (Session-1)
 
Construction tender process
Construction tender processConstruction tender process
Construction tender process
 
# FIDIC Payment Flow Charts # By SN Panigrahi
# FIDIC Payment Flow Charts # By SN Panigrahi# FIDIC Payment Flow Charts # By SN Panigrahi
# FIDIC Payment Flow Charts # By SN Panigrahi
 
Tenders for construction
Tenders for constructionTenders for construction
Tenders for construction
 
Construction claims, disputes and project closure
Construction claims, disputes and project closureConstruction claims, disputes and project closure
Construction claims, disputes and project closure
 
EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
 EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
 
Fidic law1
Fidic law1Fidic law1
Fidic law1
 
Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...
Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...
Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...
 
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdfFIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
 
"Types and Causes of Construction Claims"
"Types and Causes of Construction Claims""Types and Causes of Construction Claims"
"Types and Causes of Construction Claims"
 
Ss training fidic moustafa ismail 2017 _ lec. 1
Ss training fidic moustafa ismail  2017 _ lec. 1Ss training fidic moustafa ismail  2017 _ lec. 1
Ss training fidic moustafa ismail 2017 _ lec. 1
 
fidic-flow-chart.pptx
fidic-flow-chart.pptxfidic-flow-chart.pptx
fidic-flow-chart.pptx
 
FIDIC variation, claim & dispute - CYLFEx workshop
FIDIC variation, claim & dispute - CYLFEx workshopFIDIC variation, claim & dispute - CYLFEx workshop
FIDIC variation, claim & dispute - CYLFEx workshop
 

Viewers also liked

Why does an eot not automatically entitle a contractor to prolongation costs ...
Why does an eot not automatically entitle a contractor to prolongation costs ...Why does an eot not automatically entitle a contractor to prolongation costs ...
Why does an eot not automatically entitle a contractor to prolongation costs ...
Iffat Al Gharbi
 
Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...
Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...
Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...
Asia Master Training آسيا ماسترز للتدريب والتطوير
 
Cases in Delays - Indian Contract Act, 1872
Cases in Delays - Indian Contract Act, 1872Cases in Delays - Indian Contract Act, 1872
Cases in Delays - Indian Contract Act, 1872Karthik Madhavan
 
VERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule AnalysesVERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule Analyses
The Vertex Companies, LLC
 
Extension of time in construction contracts
Extension of time in construction contractsExtension of time in construction contracts
Extension of time in construction contracts
Kheng Hoe Advocates
 
Extension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed IbarhimExtension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed Ibarhim
Ahmed Al-Senosy Ph.D(cand),MSc,PMP,RMP
 
Update Delay Analysis
Update Delay AnalysisUpdate Delay Analysis
Update Delay Analysis
Chris Carson
 
EOT Related Cost Compensation Determination
EOT Related Cost Compensation DeterminationEOT Related Cost Compensation Determination
EOT Related Cost Compensation Determination
Vimal Daluwatta
 
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of ContractSession W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Project Controls Expo
 
Extension of time Analysis
Extension of time AnalysisExtension of time Analysis
Extension of time Analysis
Farhan Moosa
 
Construction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedConstruction Delay Analysis, Simplified
Construction Delay Analysis, Simplified
Michael Pink
 
Statistical Methods for Construction Delay Analysis
Statistical Methods for Construction Delay Analysis Statistical Methods for Construction Delay Analysis
Statistical Methods for Construction Delay Analysis
IOSR Journals
 
Methods of delay analysis
Methods of delay analysisMethods of delay analysis
Methods of delay analysis
katrin enders
 
K011138084
K011138084K011138084
K011138084
IOSR Journals
 
Construction claims management + project documentation seminar
Construction claims management + project documentation seminarConstruction claims management + project documentation seminar
Construction claims management + project documentation seminar
Kegler Brown Hill + Ritter
 
Managing the Risks of Delay in Construction Projects
Managing the Risks of Delay in Construction ProjectsManaging the Risks of Delay in Construction Projects
Managing the Risks of Delay in Construction Projects
Francis Ho
 

Viewers also liked (16)

Why does an eot not automatically entitle a contractor to prolongation costs ...
Why does an eot not automatically entitle a contractor to prolongation costs ...Why does an eot not automatically entitle a contractor to prolongation costs ...
Why does an eot not automatically entitle a contractor to prolongation costs ...
 
Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...
Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...
Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...
 
Cases in Delays - Indian Contract Act, 1872
Cases in Delays - Indian Contract Act, 1872Cases in Delays - Indian Contract Act, 1872
Cases in Delays - Indian Contract Act, 1872
 
VERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule AnalysesVERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule Analyses
 
Extension of time in construction contracts
Extension of time in construction contractsExtension of time in construction contracts
Extension of time in construction contracts
 
Extension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed IbarhimExtension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed Ibarhim
 
Update Delay Analysis
Update Delay AnalysisUpdate Delay Analysis
Update Delay Analysis
 
EOT Related Cost Compensation Determination
EOT Related Cost Compensation DeterminationEOT Related Cost Compensation Determination
EOT Related Cost Compensation Determination
 
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of ContractSession W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
 
Extension of time Analysis
Extension of time AnalysisExtension of time Analysis
Extension of time Analysis
 
Construction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedConstruction Delay Analysis, Simplified
Construction Delay Analysis, Simplified
 
Statistical Methods for Construction Delay Analysis
Statistical Methods for Construction Delay Analysis Statistical Methods for Construction Delay Analysis
Statistical Methods for Construction Delay Analysis
 
Methods of delay analysis
Methods of delay analysisMethods of delay analysis
Methods of delay analysis
 
K011138084
K011138084K011138084
K011138084
 
Construction claims management + project documentation seminar
Construction claims management + project documentation seminarConstruction claims management + project documentation seminar
Construction claims management + project documentation seminar
 
Managing the Risks of Delay in Construction Projects
Managing the Risks of Delay in Construction ProjectsManaging the Risks of Delay in Construction Projects
Managing the Risks of Delay in Construction Projects
 

Similar to The pathway to documenting successful contract claims..

Professional Practice 1 Tutorial 7
Professional Practice 1 Tutorial 7Professional Practice 1 Tutorial 7
Professional Practice 1 Tutorial 7
ashleyyeap
 
Payment in construction contracts: how to get paid
Payment in construction contracts: how to get paidPayment in construction contracts: how to get paid
Payment in construction contracts: how to get paid
Barry Hembling
 
Session-02 17-09-2011
Session-02 17-09-2011Session-02 17-09-2011
Session-02 17-09-2011Tahir B Mirza
 
Extra Work, Changes and Termination of the Contract
Extra Work, Changes and Termination of the ContractExtra Work, Changes and Termination of the Contract
Extra Work, Changes and Termination of the Contract
SHKLaw
 
TOPIC7.pdf
TOPIC7.pdfTOPIC7.pdf
TOPIC7.pdf
HASMANIRA
 
Seminar Presentation Slides (Chapter 2)
Seminar Presentation Slides (Chapter 2)Seminar Presentation Slides (Chapter 2)
Seminar Presentation Slides (Chapter 2)
Melvin Lim
 
Preserving Your Bottom Line
Preserving Your Bottom LinePreserving Your Bottom Line
Preserving Your Bottom Line
CallPM
 
Claims & disputes management
Claims & disputes managementClaims & disputes management
Claims & disputes managementMohammed Tanbouz
 
How to Write Better Proposals
How to Write Better Proposals How to Write Better Proposals
How to Write Better Proposals
Shene' Commodore, CPCM
 
AN EXAMPLE OF HOW PREPARING A CLAIM STEP BY STEP.pdf
AN EXAMPLE OF HOW PREPARING A CLAIM STEP BY STEP.pdfAN EXAMPLE OF HOW PREPARING A CLAIM STEP BY STEP.pdf
AN EXAMPLE OF HOW PREPARING A CLAIM STEP BY STEP.pdf
HamsathFarludeen
 
Contracts and-tenders
Contracts and-tendersContracts and-tenders
Contracts and-tenders
Archistudent Portal
 
Contract Specifications, Bidding and Contractor Selection for Capital Replace...
Contract Specifications, Bidding and Contractor Selection for Capital Replace...Contract Specifications, Bidding and Contractor Selection for Capital Replace...
Contract Specifications, Bidding and Contractor Selection for Capital Replace...
Kipcon Inc.
 
Protecting Your Contract Receivables – PA Mechanics Lien Law and Payment Bond...
Protecting Your Contract Receivables – PA Mechanics Lien Law and Payment Bond...Protecting Your Contract Receivables – PA Mechanics Lien Law and Payment Bond...
Protecting Your Contract Receivables – PA Mechanics Lien Law and Payment Bond...
McKonly & Asbury, LLP
 
Disputes ans Arbitration..
Disputes ans Arbitration..Disputes ans Arbitration..
Disputes ans Arbitration..Rajesh Prasad
 
Disputes and Claims in Engineering Contracts - 18.07.07.ppt
Disputes and Claims in Engineering Contracts - 18.07.07.pptDisputes and Claims in Engineering Contracts - 18.07.07.ppt
Disputes and Claims in Engineering Contracts - 18.07.07.ppt
NesrElhandasa1
 
Kreischer Miller Architecture & Engineering Industry Seminar
Kreischer Miller Architecture & Engineering Industry SeminarKreischer Miller Architecture & Engineering Industry Seminar
Kreischer Miller Architecture & Engineering Industry Seminar
Kreischer Miller
 
10 Essentials For An Effective Construction Contract
10 Essentials For An Effective Construction Contract10 Essentials For An Effective Construction Contract
10 Essentials For An Effective Construction Contract
Sarah Fox
 
PP Seminar Tutorial 7
PP Seminar Tutorial 7PP Seminar Tutorial 7
PP Seminar Tutorial 7
Farah Sham
 
Chapter 25: Creation and Negotiation
Chapter 25: Creation and NegotiationChapter 25: Creation and Negotiation
Chapter 25: Creation and Negotiation
Tara Kissel, M.Ed
 
How to Get Out of Your Timeshare
How to Get Out of Your TimeshareHow to Get Out of Your Timeshare
How to Get Out of Your Timeshare
PotomacLegalGroup
 

Similar to The pathway to documenting successful contract claims.. (20)

Professional Practice 1 Tutorial 7
Professional Practice 1 Tutorial 7Professional Practice 1 Tutorial 7
Professional Practice 1 Tutorial 7
 
Payment in construction contracts: how to get paid
Payment in construction contracts: how to get paidPayment in construction contracts: how to get paid
Payment in construction contracts: how to get paid
 
Session-02 17-09-2011
Session-02 17-09-2011Session-02 17-09-2011
Session-02 17-09-2011
 
Extra Work, Changes and Termination of the Contract
Extra Work, Changes and Termination of the ContractExtra Work, Changes and Termination of the Contract
Extra Work, Changes and Termination of the Contract
 
TOPIC7.pdf
TOPIC7.pdfTOPIC7.pdf
TOPIC7.pdf
 
Seminar Presentation Slides (Chapter 2)
Seminar Presentation Slides (Chapter 2)Seminar Presentation Slides (Chapter 2)
Seminar Presentation Slides (Chapter 2)
 
Preserving Your Bottom Line
Preserving Your Bottom LinePreserving Your Bottom Line
Preserving Your Bottom Line
 
Claims & disputes management
Claims & disputes managementClaims & disputes management
Claims & disputes management
 
How to Write Better Proposals
How to Write Better Proposals How to Write Better Proposals
How to Write Better Proposals
 
AN EXAMPLE OF HOW PREPARING A CLAIM STEP BY STEP.pdf
AN EXAMPLE OF HOW PREPARING A CLAIM STEP BY STEP.pdfAN EXAMPLE OF HOW PREPARING A CLAIM STEP BY STEP.pdf
AN EXAMPLE OF HOW PREPARING A CLAIM STEP BY STEP.pdf
 
Contracts and-tenders
Contracts and-tendersContracts and-tenders
Contracts and-tenders
 
Contract Specifications, Bidding and Contractor Selection for Capital Replace...
Contract Specifications, Bidding and Contractor Selection for Capital Replace...Contract Specifications, Bidding and Contractor Selection for Capital Replace...
Contract Specifications, Bidding and Contractor Selection for Capital Replace...
 
Protecting Your Contract Receivables – PA Mechanics Lien Law and Payment Bond...
Protecting Your Contract Receivables – PA Mechanics Lien Law and Payment Bond...Protecting Your Contract Receivables – PA Mechanics Lien Law and Payment Bond...
Protecting Your Contract Receivables – PA Mechanics Lien Law and Payment Bond...
 
Disputes ans Arbitration..
Disputes ans Arbitration..Disputes ans Arbitration..
Disputes ans Arbitration..
 
Disputes and Claims in Engineering Contracts - 18.07.07.ppt
Disputes and Claims in Engineering Contracts - 18.07.07.pptDisputes and Claims in Engineering Contracts - 18.07.07.ppt
Disputes and Claims in Engineering Contracts - 18.07.07.ppt
 
Kreischer Miller Architecture & Engineering Industry Seminar
Kreischer Miller Architecture & Engineering Industry SeminarKreischer Miller Architecture & Engineering Industry Seminar
Kreischer Miller Architecture & Engineering Industry Seminar
 
10 Essentials For An Effective Construction Contract
10 Essentials For An Effective Construction Contract10 Essentials For An Effective Construction Contract
10 Essentials For An Effective Construction Contract
 
PP Seminar Tutorial 7
PP Seminar Tutorial 7PP Seminar Tutorial 7
PP Seminar Tutorial 7
 
Chapter 25: Creation and Negotiation
Chapter 25: Creation and NegotiationChapter 25: Creation and Negotiation
Chapter 25: Creation and Negotiation
 
How to Get Out of Your Timeshare
How to Get Out of Your TimeshareHow to Get Out of Your Timeshare
How to Get Out of Your Timeshare
 

Recently uploaded

Search Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdfSearch Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Arihant Webtech Pvt. Ltd
 
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
taqyed
 
The effects of customers service quality and online reviews on customer loyal...
The effects of customers service quality and online reviews on customer loyal...The effects of customers service quality and online reviews on customer loyal...
The effects of customers service quality and online reviews on customer loyal...
balatucanapplelovely
 
Project File Report BBA 6th semester.pdf
Project File Report BBA 6th semester.pdfProject File Report BBA 6th semester.pdf
Project File Report BBA 6th semester.pdf
RajPriye
 
Improving profitability for small business
Improving profitability for small businessImproving profitability for small business
Improving profitability for small business
Ben Wann
 
Affordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n PrintAffordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n Print
Navpack & Print
 
ENTREPRENEURSHIP TRAINING.ppt for graduating class (1).ppt
ENTREPRENEURSHIP TRAINING.ppt for graduating class (1).pptENTREPRENEURSHIP TRAINING.ppt for graduating class (1).ppt
ENTREPRENEURSHIP TRAINING.ppt for graduating class (1).ppt
zechu97
 
Skye Residences | Extended Stay Residences Near Toronto Airport
Skye Residences | Extended Stay Residences Near Toronto AirportSkye Residences | Extended Stay Residences Near Toronto Airport
Skye Residences | Extended Stay Residences Near Toronto Airport
marketingjdass
 
Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111
zoyaansari11365
 
anas about venice for grade 6f about venice
anas about venice for grade 6f about veniceanas about venice for grade 6f about venice
anas about venice for grade 6f about venice
anasabutalha2013
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptx
Cynthia Clay
 
April 2024 Nostalgia Products Newsletter
April 2024 Nostalgia Products NewsletterApril 2024 Nostalgia Products Newsletter
April 2024 Nostalgia Products Newsletter
NathanBaughman3
 
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBdCree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
creerey
 
falcon-invoice-discounting-a-premier-platform-for-investors-in-india
falcon-invoice-discounting-a-premier-platform-for-investors-in-indiafalcon-invoice-discounting-a-premier-platform-for-investors-in-india
falcon-invoice-discounting-a-premier-platform-for-investors-in-india
Falcon Invoice Discounting
 
Brand Analysis for an artist named Struan
Brand Analysis for an artist named StruanBrand Analysis for an artist named Struan
Brand Analysis for an artist named Struan
sarahvanessa51503
 
Attending a job Interview for B1 and B2 Englsih learners
Attending a job Interview for B1 and B2 Englsih learnersAttending a job Interview for B1 and B2 Englsih learners
Attending a job Interview for B1 and B2 Englsih learners
Erika906060
 
5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer
ofm712785
 
Digital Transformation and IT Strategy Toolkit and Templates
Digital Transformation and IT Strategy Toolkit and TemplatesDigital Transformation and IT Strategy Toolkit and Templates
Digital Transformation and IT Strategy Toolkit and Templates
Aurelien Domont, MBA
 
The Parable of the Pipeline a book every new businessman or business student ...
The Parable of the Pipeline a book every new businessman or business student ...The Parable of the Pipeline a book every new businessman or business student ...
The Parable of the Pipeline a book every new businessman or business student ...
awaisafdar
 
Premium MEAN Stack Development Solutions for Modern Businesses
Premium MEAN Stack Development Solutions for Modern BusinessesPremium MEAN Stack Development Solutions for Modern Businesses
Premium MEAN Stack Development Solutions for Modern Businesses
SynapseIndia
 

Recently uploaded (20)

Search Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdfSearch Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdf
 
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
一比一原版加拿大渥太华大学毕业证(uottawa毕业证书)如何办理
 
The effects of customers service quality and online reviews on customer loyal...
The effects of customers service quality and online reviews on customer loyal...The effects of customers service quality and online reviews on customer loyal...
The effects of customers service quality and online reviews on customer loyal...
 
Project File Report BBA 6th semester.pdf
Project File Report BBA 6th semester.pdfProject File Report BBA 6th semester.pdf
Project File Report BBA 6th semester.pdf
 
Improving profitability for small business
Improving profitability for small businessImproving profitability for small business
Improving profitability for small business
 
Affordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n PrintAffordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n Print
 
ENTREPRENEURSHIP TRAINING.ppt for graduating class (1).ppt
ENTREPRENEURSHIP TRAINING.ppt for graduating class (1).pptENTREPRENEURSHIP TRAINING.ppt for graduating class (1).ppt
ENTREPRENEURSHIP TRAINING.ppt for graduating class (1).ppt
 
Skye Residences | Extended Stay Residences Near Toronto Airport
Skye Residences | Extended Stay Residences Near Toronto AirportSkye Residences | Extended Stay Residences Near Toronto Airport
Skye Residences | Extended Stay Residences Near Toronto Airport
 
Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111
 
anas about venice for grade 6f about venice
anas about venice for grade 6f about veniceanas about venice for grade 6f about venice
anas about venice for grade 6f about venice
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptx
 
April 2024 Nostalgia Products Newsletter
April 2024 Nostalgia Products NewsletterApril 2024 Nostalgia Products Newsletter
April 2024 Nostalgia Products Newsletter
 
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBdCree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
 
falcon-invoice-discounting-a-premier-platform-for-investors-in-india
falcon-invoice-discounting-a-premier-platform-for-investors-in-indiafalcon-invoice-discounting-a-premier-platform-for-investors-in-india
falcon-invoice-discounting-a-premier-platform-for-investors-in-india
 
Brand Analysis for an artist named Struan
Brand Analysis for an artist named StruanBrand Analysis for an artist named Struan
Brand Analysis for an artist named Struan
 
Attending a job Interview for B1 and B2 Englsih learners
Attending a job Interview for B1 and B2 Englsih learnersAttending a job Interview for B1 and B2 Englsih learners
Attending a job Interview for B1 and B2 Englsih learners
 
5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer
 
Digital Transformation and IT Strategy Toolkit and Templates
Digital Transformation and IT Strategy Toolkit and TemplatesDigital Transformation and IT Strategy Toolkit and Templates
Digital Transformation and IT Strategy Toolkit and Templates
 
The Parable of the Pipeline a book every new businessman or business student ...
The Parable of the Pipeline a book every new businessman or business student ...The Parable of the Pipeline a book every new businessman or business student ...
The Parable of the Pipeline a book every new businessman or business student ...
 
Premium MEAN Stack Development Solutions for Modern Businesses
Premium MEAN Stack Development Solutions for Modern BusinessesPremium MEAN Stack Development Solutions for Modern Businesses
Premium MEAN Stack Development Solutions for Modern Businesses
 

The pathway to documenting successful contract claims..

  • 1. w w w . a c e s c o - l y . c o m The Pathway to Documenting Successful Contract Claims April 22, 2013 By: Mohamed Hassanin’ PMP E-mail : www.mohamed@gmail.com
  • 2. It is Important to Recognize A. Requirements of a Successful Claim B. The Main Reasons for Disputes Arising on a Construction Projects 2
  • 3. Claims Claims arise on many construction projects. A great deal of emotion is wasted by parties to a construction dispute because claims are often not fully and fairly documented and properly presented. The purpose of this presentation is to provide practical tips in organizing, documenting, negotiating and resolving construction claims. 3
  • 4. A. Requirements of a Successful Claim Many contractors harm their credibility in providing verbose, complicated, emotionally charged and over reaching claims without addressing the primary requirements for a successful claim. What Are The Requirements of a Successful Claim??? 1. Recognize when a potential claim arises and provide timely notice; 2. Determine the facts; 3. Establish entitlement/identify the applicable contract provision or law/establish liability; 4. Establish causation; 5. Calculate damages in accordance with the contract; and 6. Negotiate or adjudicate the claim. 4
  • 5. 1. Recognize when a potential claim arises and provide timely notice It is quite common that at the commencement of construction, both parties wish to remain in a non-adversarial relationship. No one likes to give notice of a claim at the early stages of a construction project Early notice of claim has the advantage of avoiding surprise and enables the parties at an early stage to consider solutions to avoid and minimize the impact of any potential claim. Timely notice of a claim is critical to the claim’s ultimate success. 5 A. Requirements of a Successful Claim (Count.)
  • 6. When Notices Can Be Sent ??? • Changes, (Changing In Scope, Specifications, Quantities….) • Unknown Site Conditions (discovers subsurface conditions ) • Delays (Delayed in the performance of the work) • Force Majeure In the event that force majeure has prevented (or will prevent) a party from performing an obligation. • Terminate the Contract by Owner or Contractor • Dispute Resolution If a dispute arises between the parties • Damages • Waiver of Claims If any party waives and releases the other party from all claims • Warranty The owner is obliged to provide a notice in writing of defects 6 A. Requirements of a Successful Claim (Count.)
  • 7. 2. DETERMINE THE FACTS • Often contractors are unsuccessful in presenting a claim because the historical account is unclear because of poor contract administration. • It is extremely important that a proper program of record be implemented in order to successfully capture all facts. Suggestions for Proper Contract Documentation: • Establish effective estimating cost accounting systems and procedures • Record and track both budgeted and actual work quantities, costs, labor hours and productivity • Track the cost of all changes, • Use photographs , daily diaries and other data collection techniques . 7 A. Requirements of a Successful Claim (Count.)
  • 8. • Develop standard forms for costing information, allocating labor and materials to extra work. • Daily report which includes basic project information, weather information, site conditions, activities, use of equipment, work performed, man-power and material deliveries. • Communication and Correspondence must be clear and concise. Limit each letter to one topic. • Maintain logs for change order and submittals. If these records are properly maintained, they should be an excellent collection of information to form the factual basis of a claim. 8 A. Requirements of a Successful Claim (Count.)
  • 9. 3. ESTABLISH ENTITLEMENT • A claim will have no chance of success if it is not grounded in the contract • There must be a breach of an obligation by a party to the contract or a change in the scope of the work or a delay under the contract as a basis for a claim. • Contracts on large projects contain many volumes of specifications and often consist of a confused assembly of general conditions, special provisions, special conditions, specifications, etc A detailed familiarity with the terms and conditions of the contract is essential to the success of a claim. In order to be successful, the contractor must be familiar with the Dispute Resolution Clauses. 9 A. Requirements of a Successful Claim (Count.)
  • 10. 10 In establishing entitlement, the following information should be collected: • Identify the issue and establish a claim file • Provide notice of claim with specific contractual references • Define the scope of the problem, change, delay, impact, etc.; • Maintain proper records of costs; • Base Line Schedule and updated schedule; • Prepare an estimate of the costs . Document the change order or delay request describing the scope of the work, the proposed cost and time, direct costs, indirect costs, overhead costs and profit – use a standard cost estimating form to price out the costs. A. Requirements of a Successful Claim (Count.)
  • 11. 4. CAUSATION •Without establishing causation, there is no basis of a claim. •Writing a lot of letters and pointing an finger does not establish causation. •Causation is established by the injured party demonstrating that its loss due to an act or omission of the other party or by Force majeure event. •The most important requirement is a proper analysis of the facts. Whatever evidence is presented there must be a clear understanding of what it is meant to establish and the evidence must be in a form which can be readily understood by parties. 11 A. Requirements of a Successful Claim (Count.)
  • 12. 5. CALCULATE DAMAGES Many contractors spend a great deal of effort in documenting the claim and establishing causation but pay little attention to the calculation of damages. Calculating damages can be one or more of following: Extra Work: This claim should include the direct labor hours, equipment and subcontractor costs incurred in performing extra work. It should also include supervision, overhead and profit as agreed in the contract. 12 A. Requirements of a Successful Claim (Count.)
  • 13. Delay Costs: These costs should include the additional labor hours, additional equipment time and supervision costs incurred beyond the planned completion date for the contract. These costs should also include a component for site indirect costs as well as home office overhead for the extended period. Acceleration: This claim includes the premium overtime hours incurred by a contractor in accelerating the work in order to meet a completion date. Subcontractor Claims: This claim usually involves subcontractor claims of delay, productivity or acceleration and should be documented in detail by each subcontractor. 13 A. Requirements of a Successful Claim (Count.)
  • 14. Overhead: This claim usually involves a claim for head office or site office overheads for the incurred losses. Profit: Profit may be claimed on the basis of the rate planned at the time of bidding of the tender for the project. Financing Costs: This is a claim for the costs of financing or other bank interest charges. 14 A. Requirements of a Successful Claim (Count.)
  • 15. 6. NEGOTIATE THE CLAIM •A properly documented and presented claim is much easier to negotiate the claim. •Negotiation is a much more profitable result for the resolution of a claim than arbitration or litigation. •Preparation for negotiations is key. In order to be successful, 15 A. Requirements of a Successful Claim (Count.)
  • 16. CONCLUSION •The proper organization and presentation of a claim takes time and a great deal of care. •More often than not, the claim reviewers must answer to corporate or governmental managers whether or not a claim is valid and should be paid. •Well prepared and documented claims are much more successful in getting paid than ill prepared claims that lack foundation, analysis and justification. If you follow the recommendations set out above, you will have a much greater chance of success in having your claims paid. 16 A. Requirements of a Successful Claim (Count.)
  • 17. What are the most important causes that lead to claims? Causes of claims 1. The increased complexity of projects 2. The effects of high inflation and decrease in profits 3. The high speed of construction and materials technology 4. Decreased capital availability 5. Withdrawal of governmental support to the contractors 6. Contractors have become more sophisticated 7. The economy's impact on the construction industry 8. Force Majeure 17 B. The Main Reasons for Disputes Arising on a Construction Projects
  • 18. Types of claims A. Contractual claims. B. Delay claims. C. Acceleration claims D. Change claims E. Extra work claims F. Different site conditions claims G. Different measurement pricing claims H. Damage claims 18 B. The Main Reasons for Disputes Arising on a Construction Projects
  • 19. Claims Factors Groups 1st Group: Poor planning • Delay caused by owner • Change orders • Financial problem • Delay in payment • Planning errors • Bad communication between parties 19 B. The Main Reasons for Disputes Arising on a Construction Projects
  • 20. 2nd Group: Errors or Incomplete Documentation • Design errors or omissions • Poorly written contracts • Variation in quantity and measurements • Inconsistency of specifications and drawing • Sub-contracting problem • Constructive changes and Oral change orders • Termination & Suspension of work 20 B. The Main Reasons for Disputes Arising on a Construction Projects
  • 21. 3rd Group: Scheduling and Estimating Errors • Changes in material and costs (Escalation) • Delay caused by contractor • Scheduling errors • Subsurface problems • Estimating errors 4th Group: Execution Deficiencies • Execution errors • Changes in material types • Poor quality of the contractors work • Accidents 21 B. The Main Reasons for Disputes Arising on a Construction Projects
  • 22. 5th Group: Construction Environment • Contractors not well organized • Owners personality • Government regulation • Non-permitted contractors • Low price of the contracts 22 B. The Main Reasons for Disputes Arising on a Construction Projects
  • 23. What are the Most Frequent Causes? • Changes claims • Delay claims • Extra work claims • Contractual claims • Damage Claims Changes claims: Depending on the contract and its terms, such changes might have an effect in value addition to or deletions from the contract, modifications of the work. . 23 B. The Main Reasons for Disputes Arising on a Construction Projects
  • 24. Delay Claim: This category is subdivided into three main types as follows:  Excusable delays: These are delays for which neither the owner nor the contractor is responsible (Force Majeure).  Compensable delays: for which the contractor is entitled to compensation.  Inexcusable delays: these delays represent problems in the contractor’s organization such as lack of management or financial capability. Extra Work Claims: Extra work is any work that is ordered by the owner after construction has started that was not included in the original contract. 24 B. The Main Reasons for Disputes Arising on a Construction Projects
  • 25. Contractual Claims: •Contractual claims concerns matters with regard to the contract itself. This includes any disagreement on the responsibility or liability of some parts that are not included in the contract documents. •The main reason of these types of claims is poorly written contracts. Difference in Pricing Claims: •These types of claims deal with the disagreement regarding measurements at the final stage in the construction. •Difference pricing by the contractor and the owner of some of the materials. •The scope changes and the extra work usually create some differences in pricing. 25 B. The Main Reasons for Disputes Arising on a Construction Projects
  • 26. Damage Claims: •Property damages may occur due to the act of the owner or safety related problems. •This type of claims is very rare because usually contractors have the total responsibility for the site. Finally We Can Say Careful preparation of the contract documents will help to avoid disputes. The scope of the project should be clear, correct and concise. Also, the contractor should ask the owner to write the change orders instead of giving verbal change orders. 26 B. The Main Reasons for Disputes Arising on a Construction Projects
  • 27. 27 Thank You for your attention