SlideShare a Scribd company logo
1 of 1
Download to read offline
Volume IV Issue No. 3


                                                                                                 The Global Leader in Managing Construction Risk
               Why does an extension of time not automatically entitle a contractor to prolongation costs?

  A contractor often believes that an                     from delay then the Sharia principles of            It has been mooted by the SCL that
  extension of time also entitles him to                  fairness and equity may lead a court to             contracts should contain a provision setting
  damages or compensation for being kept on               consider that a party should be liable for the      out an agreed amount per day that can be
  site longer than agreed. However it has                 consequences arising from their default, i.e.       applied to each day of prolongation. In
  been held in the UK courts 1 that the sole              the costs incurred as a consequence of the          other words the reverse of the Employer’s
  purpose of an extension of time is to relieve           action of the employer.                             liquidated damages provision. Anything
  the contractor of the obligation to pay                                                                     which may reduce the likelihood of dispute
  liquidated damages for the whole or part of             But what about the situation where there is         must be worthy of consideration.
  the overrun period.                                     more than one cause of delay at any one
                                                          time? Unhelpfully, there is a lack of any           In summary the reason an extension of time
  To establish an entitlement to prolongation             uniformly      accepted      view     among         does not automatically entitle a contractor
  costs, a contractor must demonstrate that a             practitioners regarding concurrent delay            to prolongation costs is that entitlement to
  delay to completion of the contract has                 and how it should be treated, both for              recovery of costs associated with delay does
  occurred and the cause of the delay is an               extensions of time and prolongation costs.          not flow from the same contractual
  action or inaction of the employer which                One point worthy of comment however is              entitlement as time. Cost recovery will
  amounts either to a breach of contract or is            the position taken under the SCL Protocol.          depend on there being either a specific
  an event for which the contract specifically            With regard to extensions of time, the              contractual provision allowing recovery of
  provides an entitlement to extra payment                Protocol states that provided one of the            prolongation costs or the contractor being
  for the contractor.                                     causes of delay in any given concurrency            able to prove that the delay was a breach of
                                                          situation affords grounds for extension of          the contract by the employer and that the
  If the contract specifically provides for the           time under the contract, the contractor             breach actually caused the costs claimed.
  contractor to recover his costs in the event            should be given a time extension                    Clearly in this instance, to paraphrase
  of certain specified events and the event               notwithstanding any contemporaneous                 Benjamin Franklin, time is not the same as
  that has caused delay is one of those                   default on his part. Interestingly, in the          money.
  specified then he can recover under the                 context of prolongation costs the Protocol
  contractual mechanism. If the contract                  states that recovery of prolongation costs in             -      Nicola Caley
  does not specifically provide for the                   the situation where there is both employer                       Managing Consultant of Hill Claims
                                                                                                                           Group
  contractor to recover his costs or it does but          and contractor delay will be only for the
  the event that has occurred is not one of               costs arising solely from the employer delay
  those specified in the contract then the                and will depend on the contractor being
  contractor’s remedy will lie in a claim for             able to separate the costs of the employer
  breach of contract. A claim for breach of               delay event from those of the contractor
  contract will require proof of causation i.e.           delay event.
  that the action or inaction of the employer
  actually caused the loss2.                              Thus it is arguable that the Protocol sets the
                                                          threshold for recovery of prolongation costs
  The UK cases quoted are persuasive only                 at a higher level than that required for an
  rather than binding but there is nothing in             extension of time as, in practical terms, it is
  the UAE Civil Code or Sharia law which                  suggested that there would be significant
  would preclude the payment of damages if                difficulties in separating out losses arising
  set out in the contract , as long as they were          from ‘contractor’ and ‘employer’ delays.
  reflective of the actual loss rather than               The potential to recover costs for non-                       Hill   International,   with   3,000
                                                                                                                        employees in 100 offices worldwide,
  punitive or compensation for a future                   critical delay also exists. However delay
                                                                                                                        provides     program    management,
  possible gain. It should be borne in mind               costs arising from non-critical elements of
                                                                                                                        project management, construction
  that if the amount was not representative               work, which do not lead to delays to
                                                                                                                        management and construction claims
  of actual loss it is open to the courts to              completion of the works overall, would                        and consulting services. Engineering
  amend the figure up or down so that the                 normally be regarded as loss of productivity                  News - Record magazine recently
  damages reflect the actual loss incurred.               or disruption costs. The same principles for                  ranked Hill as the 11th largest
  It is suggested that if the contract is silent          recovery of the costs would apply except it                   construction management firm in the
  on the question of recovery of costs arising            would not be possible to recover any                          United States.
                                                          contribution to overhead or overall project
  1
    H Fairweather & Co Ltd v London Borough of            costs, only costs specific to the element in                  For more information on Hill, please
  Wandsworth [1987] 39 BLR 106                            delay.                                                        visit our website at www.hillintl.com.
  2
    Costain Ltd v Charles Haswell & Partners Ltd [2009]
  EWHC 3140 (TCC), [2010] TCLR 1, 128 Con LR154
David Brodie-Stedman                                           David Merritt
                                                                                                               Disclaimer: This article does not constitute advice, legal or
Senior Vice President & Managing Director                      Senior Vice President & Managing Director       otherwise,     and     is    provided    only     as   general
Asia, Middle East and Africa                                   Middle East and Africa                          commentary. Appropriate professional advice should always
                                                                                                               be obtained before taking or refraining from taking any
Abu Dhabi Office                                               Sultan Business Centre                          action in relation to such information and/or the application
Butti Al Otaiba Bldg., Suite 1601 & 1602                       5th Floor, Suite 501                            of applicable law. This article and the materials contained in
Sh. Khalifa St., P.O. Box: 5201, Abu Dhabi – U.A.E             P.O. Box: 71467, Dubai - U.A.E.                 it are provided on the basis that all liability for any loss or
                                                                                                               damage, whether direct or indirect, arising out of or in
Tel : +971 – 2 – 627 2855                                      Tel. : +971 - 4 - 337 2145                      connection with any use or reliance upon this article is
Fax: +971 – 2 – 627 2042                                       Fax : +971 - 4 - 335 6077                       excluded to the fullest extent permitted by law.
E-mail: auh@hillintl.com                                       E-mail : dxb@hillintl.com

More Related Content

What's hot

FIDIC Lecture - Joint operation of multiple Fidic Forms - A Case Study
FIDIC Lecture - Joint operation of multiple Fidic Forms - A Case StudyFIDIC Lecture - Joint operation of multiple Fidic Forms - A Case Study
FIDIC Lecture - Joint operation of multiple Fidic Forms - A Case StudyKhalil Hasan
 
Construction claims, disputes and project closure
Construction claims, disputes and project closureConstruction claims, disputes and project closure
Construction claims, disputes and project closuresrinivas2036
 
Claim Preparation and Project Records - 2014 Olswang Construction Law Conference
Claim Preparation and Project Records - 2014 Olswang Construction Law ConferenceClaim Preparation and Project Records - 2014 Olswang Construction Law Conference
Claim Preparation and Project Records - 2014 Olswang Construction Law ConferenceFrancis Ho
 
Construction claims management + project documentation seminar
Construction claims management + project documentation seminarConstruction claims management + project documentation seminar
Construction claims management + project documentation seminarKegler Brown Hill + Ritter
 
Extension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationExtension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationAyush Joshi
 
Variations under the FIDIC form, subject to EU Procurement law
Variations under the FIDIC form, subject to EU Procurement lawVariations under the FIDIC form, subject to EU Procurement law
Variations under the FIDIC form, subject to EU Procurement law39 Essex Chambers
 
N.M.Raj's Master Bootcamp - Construction Claims
N.M.Raj's Master Bootcamp - Construction ClaimsN.M.Raj's Master Bootcamp - Construction Claims
N.M.Raj's Master Bootcamp - Construction Claimsrajj13
 
M5 - NEC3 Compensation Events:agreeing contractual change promptly, amicable ...
M5 - NEC3 Compensation Events:agreeing contractual change promptly, amicable ...M5 - NEC3 Compensation Events:agreeing contractual change promptly, amicable ...
M5 - NEC3 Compensation Events:agreeing contractual change promptly, amicable ...Project Controls Expo
 
"Types and Causes of Construction Claims"
"Types and Causes of Construction Claims""Types and Causes of Construction Claims"
"Types and Causes of Construction Claims"Abhishek Shah
 
Fidic yellow vs silver
Fidic yellow vs silverFidic yellow vs silver
Fidic yellow vs silverWeero Koster
 
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...Project Controls Expo
 
Claims & disputes management
Claims & disputes managementClaims & disputes management
Claims & disputes managementMohammed Tanbouz
 
Seb Oram - The 2015 CDM Regulations - changes and impact on litigation
Seb Oram - The 2015 CDM Regulations - changes and impact on litigationSeb Oram - The 2015 CDM Regulations - changes and impact on litigation
Seb Oram - The 2015 CDM Regulations - changes and impact on litigationSeb Oram
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementASHISH KUMAR SINGH
 
Ohio Construction Seminar- "Dealing with One-Sided Public Contracts: Survivin...
Ohio Construction Seminar- "Dealing with One-Sided Public Contracts: Survivin...Ohio Construction Seminar- "Dealing with One-Sided Public Contracts: Survivin...
Ohio Construction Seminar- "Dealing with One-Sided Public Contracts: Survivin...Kegler Brown Hill + Ritter
 
CFW NEC Management of change under the NEC3
CFW NEC  Management of change under the NEC3 CFW NEC  Management of change under the NEC3
CFW NEC Management of change under the NEC3 Rae Davies
 
Advanced training for construction management: CONTRACTS MANAGEMENT part 2 (...
Advanced training for  construction management: CONTRACTS MANAGEMENT part 2 (...Advanced training for  construction management: CONTRACTS MANAGEMENT part 2 (...
Advanced training for construction management: CONTRACTS MANAGEMENT part 2 (...Antonio Coladarce
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2ahmong4
 
NEC4 overview: key changes and impacts - London, September 2017
NEC4 overview: key changes and impacts - London, September 2017NEC4 overview: key changes and impacts - London, September 2017
NEC4 overview: key changes and impacts - London, September 2017Browne Jacobson LLP
 

What's hot (20)

FIDIC Lecture - Joint operation of multiple Fidic Forms - A Case Study
FIDIC Lecture - Joint operation of multiple Fidic Forms - A Case StudyFIDIC Lecture - Joint operation of multiple Fidic Forms - A Case Study
FIDIC Lecture - Joint operation of multiple Fidic Forms - A Case Study
 
Construction claims, disputes and project closure
Construction claims, disputes and project closureConstruction claims, disputes and project closure
Construction claims, disputes and project closure
 
Claim Preparation and Project Records - 2014 Olswang Construction Law Conference
Claim Preparation and Project Records - 2014 Olswang Construction Law ConferenceClaim Preparation and Project Records - 2014 Olswang Construction Law Conference
Claim Preparation and Project Records - 2014 Olswang Construction Law Conference
 
Construction claims management + project documentation seminar
Construction claims management + project documentation seminarConstruction claims management + project documentation seminar
Construction claims management + project documentation seminar
 
Extension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationExtension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentation
 
Variations under the FIDIC form, subject to EU Procurement law
Variations under the FIDIC form, subject to EU Procurement lawVariations under the FIDIC form, subject to EU Procurement law
Variations under the FIDIC form, subject to EU Procurement law
 
N.M.Raj's Master Bootcamp - Construction Claims
N.M.Raj's Master Bootcamp - Construction ClaimsN.M.Raj's Master Bootcamp - Construction Claims
N.M.Raj's Master Bootcamp - Construction Claims
 
M5 - NEC3 Compensation Events:agreeing contractual change promptly, amicable ...
M5 - NEC3 Compensation Events:agreeing contractual change promptly, amicable ...M5 - NEC3 Compensation Events:agreeing contractual change promptly, amicable ...
M5 - NEC3 Compensation Events:agreeing contractual change promptly, amicable ...
 
"Types and Causes of Construction Claims"
"Types and Causes of Construction Claims""Types and Causes of Construction Claims"
"Types and Causes of Construction Claims"
 
Fidic yellow vs silver
Fidic yellow vs silverFidic yellow vs silver
Fidic yellow vs silver
 
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...
 
Claims & disputes management
Claims & disputes managementClaims & disputes management
Claims & disputes management
 
Seb Oram - The 2015 CDM Regulations - changes and impact on litigation
Seb Oram - The 2015 CDM Regulations - changes and impact on litigationSeb Oram - The 2015 CDM Regulations - changes and impact on litigation
Seb Oram - The 2015 CDM Regulations - changes and impact on litigation
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time Management
 
Ohio Construction Seminar- "Dealing with One-Sided Public Contracts: Survivin...
Ohio Construction Seminar- "Dealing with One-Sided Public Contracts: Survivin...Ohio Construction Seminar- "Dealing with One-Sided Public Contracts: Survivin...
Ohio Construction Seminar- "Dealing with One-Sided Public Contracts: Survivin...
 
CFW NEC Management of change under the NEC3
CFW NEC  Management of change under the NEC3 CFW NEC  Management of change under the NEC3
CFW NEC Management of change under the NEC3
 
Advanced training for construction management: CONTRACTS MANAGEMENT part 2 (...
Advanced training for  construction management: CONTRACTS MANAGEMENT part 2 (...Advanced training for  construction management: CONTRACTS MANAGEMENT part 2 (...
Advanced training for construction management: CONTRACTS MANAGEMENT part 2 (...
 
Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...
Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...
Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2
 
NEC4 overview: key changes and impacts - London, September 2017
NEC4 overview: key changes and impacts - London, September 2017NEC4 overview: key changes and impacts - London, September 2017
NEC4 overview: key changes and impacts - London, September 2017
 

Similar to Why does an eot not automatically entitle a contractor to prolongation costs vol. iv issue no.3

The saga of concurrent delay vol. iv issue no. 4
The saga of concurrent delay   vol. iv issue no. 4The saga of concurrent delay   vol. iv issue no. 4
The saga of concurrent delay vol. iv issue no. 4Iffat Al Gharbi
 
Star rates vol. iv issue no. 2
Star rates   vol. iv issue no. 2Star rates   vol. iv issue no. 2
Star rates vol. iv issue no. 2Iffat Al Gharbi
 
PP2 - Seminar Presentation
PP2 - Seminar Presentation PP2 - Seminar Presentation
PP2 - Seminar Presentation Lin Hui
 
Commercial and Legal Aspects of Liquidated Damages and Penalties
Commercial and Legal Aspects of Liquidated Damages and PenaltiesCommercial and Legal Aspects of Liquidated Damages and Penalties
Commercial and Legal Aspects of Liquidated Damages and PenaltiesAMILA GAYAN
 
Time Bars and their enforceability in English law EPC contracts
Time Bars and their enforceability in English law EPC contractsTime Bars and their enforceability in English law EPC contracts
Time Bars and their enforceability in English law EPC contractsEversheds Sutherland
 
Assessing Loss And Expenses Claim By Prolongation Cost
Assessing Loss And Expenses Claim By Prolongation CostAssessing Loss And Expenses Claim By Prolongation Cost
Assessing Loss And Expenses Claim By Prolongation CostJessica Navarro
 
10 Essentials For An Effective Construction Contract
10 Essentials For An Effective Construction Contract10 Essentials For An Effective Construction Contract
10 Essentials For An Effective Construction ContractSarah Fox
 
Rollits Construction Focus June 2016
Rollits Construction Focus June 2016 Rollits Construction Focus June 2016
Rollits Construction Focus June 2016 Pat Coyle
 
Law relating-to-payment
Law relating-to-paymentLaw relating-to-payment
Law relating-to-paymentArthur Wilson
 
Reasonableness of Construction Completion Costs
Reasonableness of Construction Completion CostsReasonableness of Construction Completion Costs
Reasonableness of Construction Completion CostsThe Vertex Companies, LLC
 
Wind_Energy_Law_2014_Amanda James_Overcoming Wind Energy Project Financing Ob...
Wind_Energy_Law_2014_Amanda James_Overcoming Wind Energy Project Financing Ob...Wind_Energy_Law_2014_Amanda James_Overcoming Wind Energy Project Financing Ob...
Wind_Energy_Law_2014_Amanda James_Overcoming Wind Energy Project Financing Ob...Amanda James
 
Liquidated damages contracts
Liquidated damages   contractsLiquidated damages   contracts
Liquidated damages contractsBhushan Goyal
 
Construction Contract Issues for Owners of Residences
Construction Contract Issues for Owners of ResidencesConstruction Contract Issues for Owners of Residences
Construction Contract Issues for Owners of ResidencesConstruction Cicerone
 
What is Constructive about Acceleration
What is Constructive about AccelerationWhat is Constructive about Acceleration
What is Constructive about AccelerationHKA
 
Assignment 1 Complete
Assignment 1 CompleteAssignment 1 Complete
Assignment 1 CompleteJohn Ashton
 
Construction Law Presentation
Construction Law PresentationConstruction Law Presentation
Construction Law Presentationelliotfus
 
Systech insights edition-Mark Woodward Smith
Systech insights edition-Mark Woodward Smith Systech insights edition-Mark Woodward Smith
Systech insights edition-Mark Woodward Smith mark woodward-smith
 
Professional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOTProfessional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOTYee Len Wan
 

Similar to Why does an eot not automatically entitle a contractor to prolongation costs vol. iv issue no.3 (20)

The saga of concurrent delay vol. iv issue no. 4
The saga of concurrent delay   vol. iv issue no. 4The saga of concurrent delay   vol. iv issue no. 4
The saga of concurrent delay vol. iv issue no. 4
 
Prolongation and HOOH Costs
Prolongation and HOOH CostsProlongation and HOOH Costs
Prolongation and HOOH Costs
 
Star rates vol. iv issue no. 2
Star rates   vol. iv issue no. 2Star rates   vol. iv issue no. 2
Star rates vol. iv issue no. 2
 
PP2 - Seminar Presentation
PP2 - Seminar Presentation PP2 - Seminar Presentation
PP2 - Seminar Presentation
 
Commercial and Legal Aspects of Liquidated Damages and Penalties
Commercial and Legal Aspects of Liquidated Damages and PenaltiesCommercial and Legal Aspects of Liquidated Damages and Penalties
Commercial and Legal Aspects of Liquidated Damages and Penalties
 
Time Bars and their enforceability in English law EPC contracts
Time Bars and their enforceability in English law EPC contractsTime Bars and their enforceability in English law EPC contracts
Time Bars and their enforceability in English law EPC contracts
 
Assessing Loss And Expenses Claim By Prolongation Cost
Assessing Loss And Expenses Claim By Prolongation CostAssessing Loss And Expenses Claim By Prolongation Cost
Assessing Loss And Expenses Claim By Prolongation Cost
 
10 Essentials For An Effective Construction Contract
10 Essentials For An Effective Construction Contract10 Essentials For An Effective Construction Contract
10 Essentials For An Effective Construction Contract
 
Rollits Construction Focus June 2016
Rollits Construction Focus June 2016 Rollits Construction Focus June 2016
Rollits Construction Focus June 2016
 
Against all odds
Against all odds Against all odds
Against all odds
 
Law relating-to-payment
Law relating-to-paymentLaw relating-to-payment
Law relating-to-payment
 
Reasonableness of Construction Completion Costs
Reasonableness of Construction Completion CostsReasonableness of Construction Completion Costs
Reasonableness of Construction Completion Costs
 
Wind_Energy_Law_2014_Amanda James_Overcoming Wind Energy Project Financing Ob...
Wind_Energy_Law_2014_Amanda James_Overcoming Wind Energy Project Financing Ob...Wind_Energy_Law_2014_Amanda James_Overcoming Wind Energy Project Financing Ob...
Wind_Energy_Law_2014_Amanda James_Overcoming Wind Energy Project Financing Ob...
 
Liquidated damages contracts
Liquidated damages   contractsLiquidated damages   contracts
Liquidated damages contracts
 
Construction Contract Issues for Owners of Residences
Construction Contract Issues for Owners of ResidencesConstruction Contract Issues for Owners of Residences
Construction Contract Issues for Owners of Residences
 
What is Constructive about Acceleration
What is Constructive about AccelerationWhat is Constructive about Acceleration
What is Constructive about Acceleration
 
Assignment 1 Complete
Assignment 1 CompleteAssignment 1 Complete
Assignment 1 Complete
 
Construction Law Presentation
Construction Law PresentationConstruction Law Presentation
Construction Law Presentation
 
Systech insights edition-Mark Woodward Smith
Systech insights edition-Mark Woodward Smith Systech insights edition-Mark Woodward Smith
Systech insights edition-Mark Woodward Smith
 
Professional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOTProfessional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOT
 

Why does an eot not automatically entitle a contractor to prolongation costs vol. iv issue no.3

  • 1. Volume IV Issue No. 3 The Global Leader in Managing Construction Risk Why does an extension of time not automatically entitle a contractor to prolongation costs? A contractor often believes that an from delay then the Sharia principles of It has been mooted by the SCL that extension of time also entitles him to fairness and equity may lead a court to contracts should contain a provision setting damages or compensation for being kept on consider that a party should be liable for the out an agreed amount per day that can be site longer than agreed. However it has consequences arising from their default, i.e. applied to each day of prolongation. In been held in the UK courts 1 that the sole the costs incurred as a consequence of the other words the reverse of the Employer’s purpose of an extension of time is to relieve action of the employer. liquidated damages provision. Anything the contractor of the obligation to pay which may reduce the likelihood of dispute liquidated damages for the whole or part of But what about the situation where there is must be worthy of consideration. the overrun period. more than one cause of delay at any one time? Unhelpfully, there is a lack of any In summary the reason an extension of time To establish an entitlement to prolongation uniformly accepted view among does not automatically entitle a contractor costs, a contractor must demonstrate that a practitioners regarding concurrent delay to prolongation costs is that entitlement to delay to completion of the contract has and how it should be treated, both for recovery of costs associated with delay does occurred and the cause of the delay is an extensions of time and prolongation costs. not flow from the same contractual action or inaction of the employer which One point worthy of comment however is entitlement as time. Cost recovery will amounts either to a breach of contract or is the position taken under the SCL Protocol. depend on there being either a specific an event for which the contract specifically With regard to extensions of time, the contractual provision allowing recovery of provides an entitlement to extra payment Protocol states that provided one of the prolongation costs or the contractor being for the contractor. causes of delay in any given concurrency able to prove that the delay was a breach of situation affords grounds for extension of the contract by the employer and that the If the contract specifically provides for the time under the contract, the contractor breach actually caused the costs claimed. contractor to recover his costs in the event should be given a time extension Clearly in this instance, to paraphrase of certain specified events and the event notwithstanding any contemporaneous Benjamin Franklin, time is not the same as that has caused delay is one of those default on his part. Interestingly, in the money. specified then he can recover under the context of prolongation costs the Protocol contractual mechanism. If the contract states that recovery of prolongation costs in - Nicola Caley does not specifically provide for the the situation where there is both employer Managing Consultant of Hill Claims Group contractor to recover his costs or it does but and contractor delay will be only for the the event that has occurred is not one of costs arising solely from the employer delay those specified in the contract then the and will depend on the contractor being contractor’s remedy will lie in a claim for able to separate the costs of the employer breach of contract. A claim for breach of delay event from those of the contractor contract will require proof of causation i.e. delay event. that the action or inaction of the employer actually caused the loss2. Thus it is arguable that the Protocol sets the threshold for recovery of prolongation costs The UK cases quoted are persuasive only at a higher level than that required for an rather than binding but there is nothing in extension of time as, in practical terms, it is the UAE Civil Code or Sharia law which suggested that there would be significant would preclude the payment of damages if difficulties in separating out losses arising set out in the contract , as long as they were from ‘contractor’ and ‘employer’ delays. reflective of the actual loss rather than The potential to recover costs for non- Hill International, with 3,000 employees in 100 offices worldwide, punitive or compensation for a future critical delay also exists. However delay provides program management, possible gain. It should be borne in mind costs arising from non-critical elements of project management, construction that if the amount was not representative work, which do not lead to delays to management and construction claims of actual loss it is open to the courts to completion of the works overall, would and consulting services. Engineering amend the figure up or down so that the normally be regarded as loss of productivity News - Record magazine recently damages reflect the actual loss incurred. or disruption costs. The same principles for ranked Hill as the 11th largest It is suggested that if the contract is silent recovery of the costs would apply except it construction management firm in the on the question of recovery of costs arising would not be possible to recover any United States. contribution to overhead or overall project 1 H Fairweather & Co Ltd v London Borough of costs, only costs specific to the element in For more information on Hill, please Wandsworth [1987] 39 BLR 106 delay. visit our website at www.hillintl.com. 2 Costain Ltd v Charles Haswell & Partners Ltd [2009] EWHC 3140 (TCC), [2010] TCLR 1, 128 Con LR154 David Brodie-Stedman David Merritt Disclaimer: This article does not constitute advice, legal or Senior Vice President & Managing Director Senior Vice President & Managing Director otherwise, and is provided only as general Asia, Middle East and Africa Middle East and Africa commentary. Appropriate professional advice should always be obtained before taking or refraining from taking any Abu Dhabi Office Sultan Business Centre action in relation to such information and/or the application Butti Al Otaiba Bldg., Suite 1601 & 1602 5th Floor, Suite 501 of applicable law. This article and the materials contained in Sh. Khalifa St., P.O. Box: 5201, Abu Dhabi – U.A.E P.O. Box: 71467, Dubai - U.A.E. it are provided on the basis that all liability for any loss or damage, whether direct or indirect, arising out of or in Tel : +971 – 2 – 627 2855 Tel. : +971 - 4 - 337 2145 connection with any use or reliance upon this article is Fax: +971 – 2 – 627 2042 Fax : +971 - 4 - 335 6077 excluded to the fullest extent permitted by law. E-mail: auh@hillintl.com E-mail : dxb@hillintl.com