SlideShare a Scribd company logo
PROFESSIONAL PRACTICE 1
TUTORIAL NO.7
WONG JIA JING
YEAP PHAY SHIAN
YEE JYH LIN
QUESTION
Contractor’s claims for loss and expense have long been a contentious
issue in many building contracts. These claims are usually resolved during the
final accounting process but where negotiation fails, they usually become
disputes with the parties adopting legal route to resolve their differences.
Discuss the matters below based on the PAM Form of Contract 2006 (With Quantities):
a) The Contractor is granted an extension of time. Is there an automatic right to the recovery of loss
and expense?
b) Explain the grounds for claim of loss and expense and describe how the Contractor can register
their claims.
c) Claims are invariably initiated by the Contractor. Contractual claims, Extra contractual claims and
Exgratia claims are the 3 types of claims in a contract. Give SIX (6) main reasons for claims and SIX (6)
common types of claims. How does the Quantity Surveyor assess such claims?
QUESTION
● A contractor is NOT AUTOMATICALLY ENTITLED to the recovery of loss and
expense following the granting of an extension of time.
● The entitlements to extensions of time and loss and expense are separate.
7a) The Contractor is granted an extension of time. Is there an automatic right to
the recovery of loss and expense?
LOSS AND EXPENSE
The contractor may claim for loss and expense if it is according to clause 24.1.
Clause 24.1
Loss and/or expense caused by matters affecting the regular progress of the
Works
● 24.1 (a)
● 24.1 (b)
Contractor’s Entitlement to EOT and Loss and/or Expense
Entitlement to recover loss & expense is separate from entitlement to EOT.
● In the case where EOT is granted, there is no automatic right to the
recovery of loss of expense.
● If EOT is granted under relevant event in clause 23.8 but the relevant event
is not listed in clause 24.3, then the contractor is not entitled and has no
right to claim for loss and expense.
What is Loss and/or Expenses?
Loss : any MONIES that the contractor should have received, but which he did not
receive, because of one or more of those 14 event listed in PAM Contract 2006
under Clause 24.3 and no more, which entitle him to reimbursement of direct loss
and/or expense
Expense : any COST to the contractor which is MORE THAN it would otherwise have
been, because of one or more of those 14 event listed in PAM Contract 2006 under
Clause 24.3 and no more, which entitle him to reimbursement of direct loss and/or
expense
b) Explain the grounds for claim of loss and expense and describe how the
Contractor can register their claims.
What are the grounds for claim of loss & expense?
The contractor can claim for Loss and/or Expense suffered, if:
- work is disrupted or delayed due to certain specific causes or events, which are no fault of their own.
- regular progress of works has been materially affected by the relevant event.
- loss and/or expense must be caused by the relevant events under clause 24.3.
- a written formal application made; this is condition precedent to a claim.
- contractor has taken reasonable steps to mitigate the delay
- contractor has actually incurred loss and/or expense
The loss and/or expense cannot be reimbursed under other provisions under the contract e.g. clauses 1.4, 11.6,
11.7.
How the Contractor can register their claim?
Base on Clause 24.1(a) & (b) :
Step 1
Contractor to give written notice of intention to claim for loss and/or expense
- notice shall include (initial estimate of claim, duly supported by all necessary calculations)
- notice must be given within 28 days from the date of AI (or the start of the occurrence of relevant event, whichever
is earlier).
Lack of notice on Loss and/or Expense claim is often fatal.
Step 2
Contractor shall submit a formal application for claim.
- formal application shall include (complete particulars of his claim, together with all necessary evidence &
calculation to substantiate his claims)
- shall be submitted after the 28 days of completion of the relevant matters.
Failure to submit within 28 days or any extended date agreed; it is deemed the contractor has waived his right to claim.
Step 3
Architect shall then ascertain the amount of such Loss and/or Expense which had been incurred by the Contractor, as and
when necessary from time to time, provided that:
- Contractor’s application is made in writing / reasonably apparent to him that had been or likely to be affected
- Contractor submits together with his application relevant information substantiating his claim
- Contractor upon request submit to him any other additional details of loss and/or expense as are reasonably
necessary for ascertainment
How the Contractor can register their claim?
What is asserted without evidence can be dismissed without evidence
Evidence required to substantiate a claim :
1. Instructions from employer’s agents
2. Extracts from contract documents
3. Contract drawings
4. Register of revisions issued by date
5. Remeasured quantities with guidance as to source material used
6. Photographs
7. Daily site reports
8. Programme updates
● Contractual claims
● Extra contractual claims
● Exgratia claims
c) Claims are invariably initiated by the Contractor. Contractual claims, Extra
contractual claims and Exgratia claims are the 3 types of claims in a contract.
Give SIX (6) main reasons for claims and SIX (6) common types of claims. How
does the Quantity Surveyor assess such claims?
SIX (6) main reasons for claims
● Late instruction
● Late issue of materials
● Failure of employer to carry out works
● Divergence between contract documents
● Variation
● Postponement of works
SIX (6) common types of claims
● Standing time for plant and labour
● Uneconomic working for plant and labour
● Additional contract overhead cost
● Disruption of work due to variation
● Carrying out work later than anticipated
● Condition different from planned
How does the Quantity Surveyor assess such
claims?
● Based on contractor’s disrupted output
● Based on contract overheads
● Based on formula:-eg. Hudson’s formula
THANK YOU!

More Related Content

What's hot

A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006
Melvin Lim
 
Tender evaluation procedure
Tender evaluation procedureTender evaluation procedure
Tender evaluation procedure
ayushida
 
Provisional sum prime cost sum
Provisional sum  prime cost sumProvisional sum  prime cost sum
Provisional sum prime cost sum
Est
 
Civil tenders and contracts spce
Civil tenders and contracts spceCivil tenders and contracts spce
Civil tenders and contracts spce
irkportal
 
Pp2 coursework 2 201808
Pp2 coursework 2   201808Pp2 coursework 2   201808
Pp2 coursework 2 201808
Arissa Loh
 
Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1
Lee Pei Gie
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2
ahmong4
 
Professional practice 1 (QS)
Professional practice 1 (QS)Professional practice 1 (QS)
Professional practice 1 (QS)
Hasif Alias
 
Tender
TenderTender
PP2 - Assignment
PP2 - Assignment PP2 - Assignment
PP2 - Assignment
lucaschinsheng
 
Arbitration Of Construction Disputes
Arbitration Of Construction DisputesArbitration Of Construction Disputes
Arbitration Of Construction Disputes
louchang
 
Extension of time in construction contracts
Extension of time in construction contractsExtension of time in construction contracts
Extension of time in construction contracts
Kheng Hoe Advocates
 
Earnest Money
Earnest MoneyEarnest Money
Earnest Money
Dr K M SONI
 
Construction Contract in Malaysia
Construction Contract in MalaysiaConstruction Contract in Malaysia
Construction Contract in Malaysia
Dayat Mohamad
 
Professional practice 1 report
Professional practice 1 reportProfessional practice 1 report
Professional practice 1 report
Ngo Jia Haur
 
Pp1 group assignment
Pp1 group assignmentPp1 group assignment
Pp1 group assignment
Pui Chun Shian
 
Site possession
Site possessionSite possession
Site possession
Amir Ibrahim
 

What's hot (20)

A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006
 
Defects liability
Defects liabilityDefects liability
Defects liability
 
Procurement system
Procurement systemProcurement system
Procurement system
 
Tender evaluation procedure
Tender evaluation procedureTender evaluation procedure
Tender evaluation procedure
 
Provisional sum prime cost sum
Provisional sum  prime cost sumProvisional sum  prime cost sum
Provisional sum prime cost sum
 
Civil tenders and contracts spce
Civil tenders and contracts spceCivil tenders and contracts spce
Civil tenders and contracts spce
 
Pp2 coursework 2 201808
Pp2 coursework 2   201808Pp2 coursework 2   201808
Pp2 coursework 2 201808
 
Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2
 
Professional practice 1 (QS)
Professional practice 1 (QS)Professional practice 1 (QS)
Professional practice 1 (QS)
 
Tender
TenderTender
Tender
 
PP2 - Assignment
PP2 - Assignment PP2 - Assignment
PP2 - Assignment
 
Pp2 chapter 1 cheeyong & yih shyang
Pp2 chapter 1 cheeyong & yih shyangPp2 chapter 1 cheeyong & yih shyang
Pp2 chapter 1 cheeyong & yih shyang
 
Arbitration Of Construction Disputes
Arbitration Of Construction DisputesArbitration Of Construction Disputes
Arbitration Of Construction Disputes
 
Extension of time in construction contracts
Extension of time in construction contractsExtension of time in construction contracts
Extension of time in construction contracts
 
Earnest Money
Earnest MoneyEarnest Money
Earnest Money
 
Construction Contract in Malaysia
Construction Contract in MalaysiaConstruction Contract in Malaysia
Construction Contract in Malaysia
 
Professional practice 1 report
Professional practice 1 reportProfessional practice 1 report
Professional practice 1 report
 
Pp1 group assignment
Pp1 group assignmentPp1 group assignment
Pp1 group assignment
 
Site possession
Site possessionSite possession
Site possession
 

Similar to Professional Practice 1 Tutorial 7

Professional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOTProfessional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOT
Yee Len Wan
 
PP Seminar Tutorial 7
PP Seminar Tutorial 7PP Seminar Tutorial 7
PP Seminar Tutorial 7
Farah Sham
 
The pathway to documenting successful contract claims..
The pathway to documenting successful contract claims..The pathway to documenting successful contract claims..
The pathway to documenting successful contract claims..
Mohamed Hassanein, BSc , PMP, MBA
 
Pp2 p5
Pp2   p5Pp2   p5
Pp2 p5
Shze Hwa Lee
 
PP2 - Seminar Presentation
PP2 - Seminar Presentation PP2 - Seminar Presentation
PP2 - Seminar Presentation
Lin Hui
 
time bar clauses
time bar clausestime bar clauses
time bar clausesAMILA GAYAN
 
Colin Harris and Mark Kenney
Colin Harris and Mark KenneyColin Harris and Mark Kenney
Colin Harris and Mark Kenney
Resolution Institute
 
Construction Claims
Construction ClaimsConstruction Claims
Construction Claims
Rajesh Sharma
 
Claims and insolvencies (1)
Claims and insolvencies (1)Claims and insolvencies (1)
Claims and insolvencies (1)
mohammedAlmusawi11
 
Lecture 8-determination-of-own-employment-by
Lecture 8-determination-of-own-employment-byLecture 8-determination-of-own-employment-by
Lecture 8-determination-of-own-employment-by
seenyeeyong
 
2 claims under new fidic
2 claims under new fidic2 claims under new fidic
2 claims under new fidic
AhmetArslan47
 
Seminar - CIPAA 2012
Seminar - CIPAA 2012Seminar - CIPAA 2012
Seminar - CIPAA 2012
Kai Yun Pang
 
Construction law update august 2015 quarter 2 a
Construction law update august 2015 quarter 2 aConstruction law update august 2015 quarter 2 a
Construction law update august 2015 quarter 2 a
Colin Tomlinson
 
Commercial and Construction Law Update Q2 2015
Commercial and Construction Law Update Q2 2015Commercial and Construction Law Update Q2 2015
Commercial and Construction Law Update Q2 2015
Colin Tomlinson
 
Commericial Management and Construction law update 2015 Q2
Commericial Management and Construction law update 2015 Q2Commericial Management and Construction law update 2015 Q2
Commericial Management and Construction law update 2015 Q2
Colin Tomlinson
 
CIPAA presentation
CIPAA presentationCIPAA presentation
CIPAA presentation
Doreen Yeo
 
Cl compilation
Cl compilationCl compilation
Cl compilation
Jessyca Than
 
Techno Engineering & Associates
Techno Engineering & AssociatesTechno Engineering & Associates
Techno Engineering & Associates
Cerasela Angelescu
 
Preserving Your Bottom Line
Preserving Your Bottom LinePreserving Your Bottom Line
Preserving Your Bottom Line
CallPM
 
eCourt malpractice traps and relation back
eCourt malpractice traps and relation backeCourt malpractice traps and relation back
eCourt malpractice traps and relation back
Oregon Law Practice Management
 

Similar to Professional Practice 1 Tutorial 7 (20)

Professional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOTProfessional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOT
 
PP Seminar Tutorial 7
PP Seminar Tutorial 7PP Seminar Tutorial 7
PP Seminar Tutorial 7
 
The pathway to documenting successful contract claims..
The pathway to documenting successful contract claims..The pathway to documenting successful contract claims..
The pathway to documenting successful contract claims..
 
Pp2 p5
Pp2   p5Pp2   p5
Pp2 p5
 
PP2 - Seminar Presentation
PP2 - Seminar Presentation PP2 - Seminar Presentation
PP2 - Seminar Presentation
 
time bar clauses
time bar clausestime bar clauses
time bar clauses
 
Colin Harris and Mark Kenney
Colin Harris and Mark KenneyColin Harris and Mark Kenney
Colin Harris and Mark Kenney
 
Construction Claims
Construction ClaimsConstruction Claims
Construction Claims
 
Claims and insolvencies (1)
Claims and insolvencies (1)Claims and insolvencies (1)
Claims and insolvencies (1)
 
Lecture 8-determination-of-own-employment-by
Lecture 8-determination-of-own-employment-byLecture 8-determination-of-own-employment-by
Lecture 8-determination-of-own-employment-by
 
2 claims under new fidic
2 claims under new fidic2 claims under new fidic
2 claims under new fidic
 
Seminar - CIPAA 2012
Seminar - CIPAA 2012Seminar - CIPAA 2012
Seminar - CIPAA 2012
 
Construction law update august 2015 quarter 2 a
Construction law update august 2015 quarter 2 aConstruction law update august 2015 quarter 2 a
Construction law update august 2015 quarter 2 a
 
Commercial and Construction Law Update Q2 2015
Commercial and Construction Law Update Q2 2015Commercial and Construction Law Update Q2 2015
Commercial and Construction Law Update Q2 2015
 
Commericial Management and Construction law update 2015 Q2
Commericial Management and Construction law update 2015 Q2Commericial Management and Construction law update 2015 Q2
Commericial Management and Construction law update 2015 Q2
 
CIPAA presentation
CIPAA presentationCIPAA presentation
CIPAA presentation
 
Cl compilation
Cl compilationCl compilation
Cl compilation
 
Techno Engineering & Associates
Techno Engineering & AssociatesTechno Engineering & Associates
Techno Engineering & Associates
 
Preserving Your Bottom Line
Preserving Your Bottom LinePreserving Your Bottom Line
Preserving Your Bottom Line
 
eCourt malpractice traps and relation back
eCourt malpractice traps and relation backeCourt malpractice traps and relation back
eCourt malpractice traps and relation back
 

More from ashleyyeap

CSI JOURNAL cover page
CSI JOURNAL cover pageCSI JOURNAL cover page
CSI JOURNAL cover page
ashleyyeap
 
CSI JOURNAL
CSI JOURNALCSI JOURNAL
CSI JOURNAL
ashleyyeap
 
Fm group assignment
Fm group assignment Fm group assignment
Fm group assignment
ashleyyeap
 
Pp2 assignment-final
Pp2 assignment-finalPp2 assignment-final
Pp2 assignment-final
ashleyyeap
 
PP2 final account assignment calculations
PP2 final account assignment calculationsPP2 final account assignment calculations
PP2 final account assignment calculations
ashleyyeap
 
Fm august 2018 group assignment brief
Fm august 2018 group assignment briefFm august 2018 group assignment brief
Fm august 2018 group assignment brief
ashleyyeap
 
Building Economics Assignment Report
Building Economics Assignment ReportBuilding Economics Assignment Report
Building Economics Assignment Report
ashleyyeap
 
Building Economics Preliminary Cost Appraisal
Building Economics Preliminary Cost Appraisal Building Economics Preliminary Cost Appraisal
Building Economics Preliminary Cost Appraisal
ashleyyeap
 
PP2 Seminar Presentation
PP2 Seminar PresentationPP2 Seminar Presentation
PP2 Seminar Presentation
ashleyyeap
 
Pp2 final account assignment excel
Pp2 final account assignment excelPp2 final account assignment excel
Pp2 final account assignment excel
ashleyyeap
 
Pp2 assignment-final
Pp2 assignment-finalPp2 assignment-final
Pp2 assignment-final
ashleyyeap
 
Pp2 coursework 2 201808
Pp2 coursework 2   201808Pp2 coursework 2   201808
Pp2 coursework 2 201808
ashleyyeap
 
Measurement Assignment
Measurement AssignmentMeasurement Assignment
Measurement Assignment
ashleyyeap
 
Professional Practice 1 Tutorial 3
Professional Practice 1 Tutorial 3Professional Practice 1 Tutorial 3
Professional Practice 1 Tutorial 3
ashleyyeap
 
Professional Practice I Assignment Slides
Professional Practice I Assignment SlidesProfessional Practice I Assignment Slides
Professional Practice I Assignment Slides
ashleyyeap
 
Professional Practice I Assignment
Professional Practice I AssignmentProfessional Practice I Assignment
Professional Practice I Assignment
ashleyyeap
 
Estimating Assignment
Estimating Assignment Estimating Assignment
Estimating Assignment
ashleyyeap
 
Software Assignment
Software AssignmentSoftware Assignment
Software Assignment
ashleyyeap
 
Management Science Assignment
Management Science Assignment Management Science Assignment
Management Science Assignment
ashleyyeap
 
People Dynamics Individual Assignment - Case Study
People Dynamics Individual Assignment - Case StudyPeople Dynamics Individual Assignment - Case Study
People Dynamics Individual Assignment - Case Study
ashleyyeap
 

More from ashleyyeap (20)

CSI JOURNAL cover page
CSI JOURNAL cover pageCSI JOURNAL cover page
CSI JOURNAL cover page
 
CSI JOURNAL
CSI JOURNALCSI JOURNAL
CSI JOURNAL
 
Fm group assignment
Fm group assignment Fm group assignment
Fm group assignment
 
Pp2 assignment-final
Pp2 assignment-finalPp2 assignment-final
Pp2 assignment-final
 
PP2 final account assignment calculations
PP2 final account assignment calculationsPP2 final account assignment calculations
PP2 final account assignment calculations
 
Fm august 2018 group assignment brief
Fm august 2018 group assignment briefFm august 2018 group assignment brief
Fm august 2018 group assignment brief
 
Building Economics Assignment Report
Building Economics Assignment ReportBuilding Economics Assignment Report
Building Economics Assignment Report
 
Building Economics Preliminary Cost Appraisal
Building Economics Preliminary Cost Appraisal Building Economics Preliminary Cost Appraisal
Building Economics Preliminary Cost Appraisal
 
PP2 Seminar Presentation
PP2 Seminar PresentationPP2 Seminar Presentation
PP2 Seminar Presentation
 
Pp2 final account assignment excel
Pp2 final account assignment excelPp2 final account assignment excel
Pp2 final account assignment excel
 
Pp2 assignment-final
Pp2 assignment-finalPp2 assignment-final
Pp2 assignment-final
 
Pp2 coursework 2 201808
Pp2 coursework 2   201808Pp2 coursework 2   201808
Pp2 coursework 2 201808
 
Measurement Assignment
Measurement AssignmentMeasurement Assignment
Measurement Assignment
 
Professional Practice 1 Tutorial 3
Professional Practice 1 Tutorial 3Professional Practice 1 Tutorial 3
Professional Practice 1 Tutorial 3
 
Professional Practice I Assignment Slides
Professional Practice I Assignment SlidesProfessional Practice I Assignment Slides
Professional Practice I Assignment Slides
 
Professional Practice I Assignment
Professional Practice I AssignmentProfessional Practice I Assignment
Professional Practice I Assignment
 
Estimating Assignment
Estimating Assignment Estimating Assignment
Estimating Assignment
 
Software Assignment
Software AssignmentSoftware Assignment
Software Assignment
 
Management Science Assignment
Management Science Assignment Management Science Assignment
Management Science Assignment
 
People Dynamics Individual Assignment - Case Study
People Dynamics Individual Assignment - Case StudyPeople Dynamics Individual Assignment - Case Study
People Dynamics Individual Assignment - Case Study
 

Recently uploaded

TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
EugeneSaldivar
 
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
MysoreMuleSoftMeetup
 
2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...
Sandy Millin
 
The Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official PublicationThe Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official Publication
Delapenabediema
 
Synthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptxSynthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptx
Pavel ( NSTU)
 
How to Break the cycle of negative Thoughts
How to Break the cycle of negative ThoughtsHow to Break the cycle of negative Thoughts
How to Break the cycle of negative Thoughts
Col Mukteshwar Prasad
 
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCECLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
BhavyaRajput3
 
The French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free downloadThe French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free download
Vivekanand Anglo Vedic Academy
 
ESC Beyond Borders _From EU to You_ InfoPack general.pdf
ESC Beyond Borders _From EU to You_ InfoPack general.pdfESC Beyond Borders _From EU to You_ InfoPack general.pdf
ESC Beyond Borders _From EU to You_ InfoPack general.pdf
Fundacja Rozwoju Społeczeństwa Przedsiębiorczego
 
Model Attribute Check Company Auto Property
Model Attribute  Check Company Auto PropertyModel Attribute  Check Company Auto Property
Model Attribute Check Company Auto Property
Celine George
 
Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345
beazzy04
 
Operation Blue Star - Saka Neela Tara
Operation Blue Star   -  Saka Neela TaraOperation Blue Star   -  Saka Neela Tara
Operation Blue Star - Saka Neela Tara
Balvir Singh
 
1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx
JosvitaDsouza2
 
The Art Pastor's Guide to Sabbath | Steve Thomason
The Art Pastor's Guide to Sabbath | Steve ThomasonThe Art Pastor's Guide to Sabbath | Steve Thomason
The Art Pastor's Guide to Sabbath | Steve Thomason
Steve Thomason
 
Cambridge International AS A Level Biology Coursebook - EBook (MaryFosbery J...
Cambridge International AS  A Level Biology Coursebook - EBook (MaryFosbery J...Cambridge International AS  A Level Biology Coursebook - EBook (MaryFosbery J...
Cambridge International AS A Level Biology Coursebook - EBook (MaryFosbery J...
AzmatAli747758
 
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptxStudents, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
EduSkills OECD
 
Supporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptxSupporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptx
Jisc
 
How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17
Celine George
 
How to Split Bills in the Odoo 17 POS Module
How to Split Bills in the Odoo 17 POS ModuleHow to Split Bills in the Odoo 17 POS Module
How to Split Bills in the Odoo 17 POS Module
Celine George
 
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup   New Member Orientation and Q&A (May 2024).pdfWelcome to TechSoup   New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
TechSoup
 

Recently uploaded (20)

TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
 
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
 
2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...
 
The Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official PublicationThe Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official Publication
 
Synthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptxSynthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptx
 
How to Break the cycle of negative Thoughts
How to Break the cycle of negative ThoughtsHow to Break the cycle of negative Thoughts
How to Break the cycle of negative Thoughts
 
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCECLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
 
The French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free downloadThe French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free download
 
ESC Beyond Borders _From EU to You_ InfoPack general.pdf
ESC Beyond Borders _From EU to You_ InfoPack general.pdfESC Beyond Borders _From EU to You_ InfoPack general.pdf
ESC Beyond Borders _From EU to You_ InfoPack general.pdf
 
Model Attribute Check Company Auto Property
Model Attribute  Check Company Auto PropertyModel Attribute  Check Company Auto Property
Model Attribute Check Company Auto Property
 
Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345
 
Operation Blue Star - Saka Neela Tara
Operation Blue Star   -  Saka Neela TaraOperation Blue Star   -  Saka Neela Tara
Operation Blue Star - Saka Neela Tara
 
1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx
 
The Art Pastor's Guide to Sabbath | Steve Thomason
The Art Pastor's Guide to Sabbath | Steve ThomasonThe Art Pastor's Guide to Sabbath | Steve Thomason
The Art Pastor's Guide to Sabbath | Steve Thomason
 
Cambridge International AS A Level Biology Coursebook - EBook (MaryFosbery J...
Cambridge International AS  A Level Biology Coursebook - EBook (MaryFosbery J...Cambridge International AS  A Level Biology Coursebook - EBook (MaryFosbery J...
Cambridge International AS A Level Biology Coursebook - EBook (MaryFosbery J...
 
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptxStudents, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
 
Supporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptxSupporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptx
 
How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17
 
How to Split Bills in the Odoo 17 POS Module
How to Split Bills in the Odoo 17 POS ModuleHow to Split Bills in the Odoo 17 POS Module
How to Split Bills in the Odoo 17 POS Module
 
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup   New Member Orientation and Q&A (May 2024).pdfWelcome to TechSoup   New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
 

Professional Practice 1 Tutorial 7

  • 1. PROFESSIONAL PRACTICE 1 TUTORIAL NO.7 WONG JIA JING YEAP PHAY SHIAN YEE JYH LIN
  • 2. QUESTION Contractor’s claims for loss and expense have long been a contentious issue in many building contracts. These claims are usually resolved during the final accounting process but where negotiation fails, they usually become disputes with the parties adopting legal route to resolve their differences.
  • 3. Discuss the matters below based on the PAM Form of Contract 2006 (With Quantities): a) The Contractor is granted an extension of time. Is there an automatic right to the recovery of loss and expense? b) Explain the grounds for claim of loss and expense and describe how the Contractor can register their claims. c) Claims are invariably initiated by the Contractor. Contractual claims, Extra contractual claims and Exgratia claims are the 3 types of claims in a contract. Give SIX (6) main reasons for claims and SIX (6) common types of claims. How does the Quantity Surveyor assess such claims? QUESTION
  • 4. ● A contractor is NOT AUTOMATICALLY ENTITLED to the recovery of loss and expense following the granting of an extension of time. ● The entitlements to extensions of time and loss and expense are separate. 7a) The Contractor is granted an extension of time. Is there an automatic right to the recovery of loss and expense?
  • 5. LOSS AND EXPENSE The contractor may claim for loss and expense if it is according to clause 24.1. Clause 24.1 Loss and/or expense caused by matters affecting the regular progress of the Works ● 24.1 (a) ● 24.1 (b)
  • 6. Contractor’s Entitlement to EOT and Loss and/or Expense Entitlement to recover loss & expense is separate from entitlement to EOT. ● In the case where EOT is granted, there is no automatic right to the recovery of loss of expense. ● If EOT is granted under relevant event in clause 23.8 but the relevant event is not listed in clause 24.3, then the contractor is not entitled and has no right to claim for loss and expense.
  • 7. What is Loss and/or Expenses? Loss : any MONIES that the contractor should have received, but which he did not receive, because of one or more of those 14 event listed in PAM Contract 2006 under Clause 24.3 and no more, which entitle him to reimbursement of direct loss and/or expense Expense : any COST to the contractor which is MORE THAN it would otherwise have been, because of one or more of those 14 event listed in PAM Contract 2006 under Clause 24.3 and no more, which entitle him to reimbursement of direct loss and/or expense b) Explain the grounds for claim of loss and expense and describe how the Contractor can register their claims.
  • 8. What are the grounds for claim of loss & expense? The contractor can claim for Loss and/or Expense suffered, if: - work is disrupted or delayed due to certain specific causes or events, which are no fault of their own. - regular progress of works has been materially affected by the relevant event. - loss and/or expense must be caused by the relevant events under clause 24.3. - a written formal application made; this is condition precedent to a claim. - contractor has taken reasonable steps to mitigate the delay - contractor has actually incurred loss and/or expense The loss and/or expense cannot be reimbursed under other provisions under the contract e.g. clauses 1.4, 11.6, 11.7.
  • 9. How the Contractor can register their claim? Base on Clause 24.1(a) & (b) : Step 1 Contractor to give written notice of intention to claim for loss and/or expense - notice shall include (initial estimate of claim, duly supported by all necessary calculations) - notice must be given within 28 days from the date of AI (or the start of the occurrence of relevant event, whichever is earlier). Lack of notice on Loss and/or Expense claim is often fatal. Step 2 Contractor shall submit a formal application for claim. - formal application shall include (complete particulars of his claim, together with all necessary evidence & calculation to substantiate his claims) - shall be submitted after the 28 days of completion of the relevant matters. Failure to submit within 28 days or any extended date agreed; it is deemed the contractor has waived his right to claim. Step 3 Architect shall then ascertain the amount of such Loss and/or Expense which had been incurred by the Contractor, as and when necessary from time to time, provided that: - Contractor’s application is made in writing / reasonably apparent to him that had been or likely to be affected - Contractor submits together with his application relevant information substantiating his claim - Contractor upon request submit to him any other additional details of loss and/or expense as are reasonably necessary for ascertainment
  • 10. How the Contractor can register their claim? What is asserted without evidence can be dismissed without evidence Evidence required to substantiate a claim : 1. Instructions from employer’s agents 2. Extracts from contract documents 3. Contract drawings 4. Register of revisions issued by date 5. Remeasured quantities with guidance as to source material used 6. Photographs 7. Daily site reports 8. Programme updates
  • 11. ● Contractual claims ● Extra contractual claims ● Exgratia claims c) Claims are invariably initiated by the Contractor. Contractual claims, Extra contractual claims and Exgratia claims are the 3 types of claims in a contract. Give SIX (6) main reasons for claims and SIX (6) common types of claims. How does the Quantity Surveyor assess such claims?
  • 12. SIX (6) main reasons for claims ● Late instruction ● Late issue of materials ● Failure of employer to carry out works ● Divergence between contract documents ● Variation ● Postponement of works
  • 13. SIX (6) common types of claims ● Standing time for plant and labour ● Uneconomic working for plant and labour ● Additional contract overhead cost ● Disruption of work due to variation ● Carrying out work later than anticipated ● Condition different from planned
  • 14. How does the Quantity Surveyor assess such claims? ● Based on contractor’s disrupted output ● Based on contract overheads ● Based on formula:-eg. Hudson’s formula