SlideShare a Scribd company logo
O N M O D E R N C O N C E P T S A N D A D V A N C E D
T E C H N I Q U E S O F E A R T H I N G
1
Technical Presentation to
PROJECT PRICIPALS
B Y P A N K A J C H A K R A B O R T Y
OF
PBC INDUSTRIAL SERVICES
B L O C K – 1 9 , F L A Y – 1 1 7 ,
P A R N A S R E E G O V T . H O U S I N G ,
K O L K A T A – 7 0 0 0 6 0 , ( W E S T - B E N G A L )
7/2/2013PBC Training Document PBC/ER/005 Rev 0
Objectives
Return path during continuous operation should not
be thru earth path unless designed.
Instantaneous fault current should not flow thru the
neutral circuit creating live and dangerous neutral.
Dissipate the stray currents, lightning, surges
2
Dissipate the stray currents, lightning, surges
keeping system hazard free.
Maintain the whole facility at equipotential.
Provide reference to run the system at specified
voltage
7/2/2013PBC Training Document PBC/ER/005 Rev 0
TN System
Transformer neutral is earthed
Frames of electrical load are connected to neutral
Fault is cleared by SCPD
3
Fault is cleared by SCPD
TN-C, TN-S, TN-CS
SCPD/ loop impedance matching
Not recommended for premises having electronic and
communication system
Not used when cross-section of live cond. < 10 sqmm
PE may get damaged by loads generating 3rd harmonics.
7/2/2013PBC Training Document PBC/ER/005 Rev 0
TT system
Transformer neutral is earthed
Frame of electrical load is connected to earth
connection
Fault cleared by RCD.
4
7/2/2013PBC Training Document PBC/ER/005 Rev 0
IT System
Transformer neutral is not earthed.
Frame of electrical load is earthed.
First fault does not present risk, indication is
sufficient
Second fault cleared by SCPD
5
Second fault cleared by SCPD
Ensure continuity of service where human life is at
stake or with furnaces
7/2/2013PBC Training Document MEPL/ER/005 Rev 0
7/2/2013PBC Training Document PBC/ER/005 Rev 0 6
Problem for electronic and communication system
7/2/2013PBC Training Document PBC/ER/005 Rev 0 7
Comparing Earthing system
8
7/2/2013PBC Training Document PBC/ER/005 Rev 0
Parallel association of Earthing system
9
7/2/2013PBC Training Document PBC/ER/005 Rev 0
BREAK 1
10
T H I N K I N G T I M E
PBC Training Document PBC/ER/005 Rev 0 7/2/2013
Soil Resistivity of different Soil Types
11
7/2/2013PBC Training Document PBC/ER/005 Rev 0
Resistivity Plot
Use Wenner 4 point method.
Take at least 4 readings in one
direction from 7mt spacing to
spacing equal to diagonal of
the electrical installation.
Repeat these readings in all 8
directions separated by 450
angle.
12
7/2/2013PBC Training Document PBC/ER/005 Rev 0
angle.
Calculate the resistivity.
Make a polar plot.
Calculate the area under the
polar plot
Draw a circle of equal area
Radius of the circle is the
resistivity of the point.
Variation in Resistivity
13
PBC Training Document PBC/ER/005 Rev 0 7/2/2013
7/2/2013PBC Training Document PBC/ER/005 Rev 0 14
Resistivity Plot
15
7/2/2013PBC Training Document PBC/ER/005 Rev 0
Wenner’s method
16
PBC Training Document PBC/ER/005 Rev 0 7/2/2013
Schulemberger method
17
PBC Training Document PBC/ER/005 Rev 0 7/2/2013
Essential Practices
Use meter
having stray current filter.
where the injected current frequencies can be changed
Injected current can be made high or low depending on current
probe resistance.
Apply water and compact the current and potential
18
Apply water and compact the current and potential
probes to avoid undue high probe resistance.
Lose potential probe can give high value of R and high
resistivity.
Avoid measuring along buried or superficial metal
conductors
Take readings in multiple directions
7/2/2013
Abstract of IEEE 81 1993
19
PBC Training Document PBC/ER/005 Rev 0 7/2/2013
Polar curve method for Uniform Soil
Resistivity
• Resistivity taken in min 8
directions
• Angular distance between
readings 450
• Cautiously Interpolate the
readings to 7.50
• Join the Points to form a polar
curve
20
PBC Training Document PBC/ER/005 Rev 0
curve
• Calculate the area of the polar
curve
• Draw equivalent Circular area
• Radius of the circle is the average
soil resistivity
• This method is particularly
beneficial when the resistivity
varies significantly in different
directions
7/2/2013
Inverse Slope method for 2 layer soil Resistivity
1
1.2
1.4
1.6
1.8
Spacings/apparentresistivityρa
Approximate method
21
PBC Training Document PBC/ER/005 Rev 0
0
0.2
0.4
0.6
0.8
1
0 5 10 15 20 25 30 35
0.5/5=.1
1/.1=ρ2=10Ω
m
Spacings/apparentresistivity
Spacing s in m
0.2/5=.04
1/.04=ρ1=25Ω
m
H=13
7/2/2013
Sunde’s Method
22
PBC Training Document PBC/ER/005 Rev 0 7/2/2013
BREAK 2
23
T H I N K I N G T I M E
PBC Training Document PBC/ER/005 Rev 0 7/2/2013
Essentials of Earthing Design
Crossection
Area
Current
Density
Dangerous
Potentials
Resistance
The Crossection
of the conductor
to be sufficient
for carrying
Continuous
surface current
density
Step potential Horizontal Plane
Touch potential Vertical Plane
24
PBC Training Document PBC/ER/005 Rev 0
for carrying
GRID fault
current Instantaneous
Surface current
density
Mesh Potential Mutual
resistance
GPR
Transfer
Potential
PASS PASS PASSPASS OK
7/2/2013
(Clause 11.3 of IEEE
80:2000)
TERMS:
I – rms current in KA
TCAP – Thermal capacity per unit volume in J/(cm3. 0C)
Calculation of required minimum cross sectional area of
grid conductor:
25
TCAP – Thermal capacity per unit volume in J/(cm . C)
tc – Duration of fault current in sec
αr – Thermal coefficient of resistivity at reference temperature in 1/0C
ρr – Resistivity of the ground conductor at reference temperature in µ -cm
Ko – 1/ α0 in 0C
Tm – Maximum allowable temperature in 0C
Ta – Ambient temperature in 0C
Cross Sectional Area of selected grid conductor must be greater than minimum required
Cross Sectional Area as required by Asymmetric fault current.
7/2/2013PBC Training Document PBC/ER/005 Rev 0
Crossection area
Equation 37 of IEEE 80 2000
The current is Symmetrical fault
current
Enthalpy of vaporization decreases
with increase in temperature.
For a large grid the fault current gets
See also
26
PBC Training Document PBC/ER/005 Rev 0
For a large grid the fault current gets
multiple parallel paths hence Tm
doesn’t pose a problem.
If the Tm is allowed to rise beyond a
limit in smaller grids or pits the
water molecules beyond a
temperature will instantaneously
vaporizes and escape from the soil
surrounding the conductor.
Tm also applies to surface layer
coating or cover
Compound
At 1000C
Heat of
vaporizatio
n
(kJ mol-1)
Heat of
vaporizatio
n
(kJ kg−1)
Water 40.65 2257
7/2/2013
Calculate Grid Current
(Clause 5.2.8.1 of IEEE 665:1995)
TERMS:
27
TERMS:
I – rms current in KA
Sf – Split factor (Annex C of IEEE 80:2000)
Df – Decremtent factor (Clause 5.2.5.4 of IEEE 665:1995)
Cp – Corrective Projection factor
The Remaining design depends on the Current that takes the ground path to
return to the source. It is only a portion of 3I0.
7/2/2013PBC Training Document PBC/ER/005 Rev 0
Long term surface CurrentsLong term surface Currents Short Term surface currentsShort Term surface currents
Surface current density as per BS7340 clause 15
If surface current densities are not maintained, junction between electrode
and soil, will heat up reducing moisture, failing the electrode or grid.
28
PBC Training Document PBC/ER/005 Rev 0
Long term Surface
current density is
40A/m2
Independent of soil
resistivity
Given by the formula
1000*Sqrt (57.7/(ρ*t))
Dependent on soil
resistivity and time of
clearance of fault
EFFECT OF COROSSION
7/2/2013
Symbol unit Value
Relay setting at 6KA 0.32Sec IG A 6000 Input
Diameter of electrode d m 0.04 Input
Length of Electrode
Soil ls m 37 Input
Water lw m 1 Input
Resistivity
Soil ρs Ωm 360 Input
Water ρw Ωm 2 Input
Resistance
Soil Rs Ω 12.25394 Equation 55 IEEE 80 2000
Water Rw Ω 1.368891 Equation 55 IEEE 80 2000
Combined R Ω 1.231338
7/2/2013PBC Training Document PBC/ER/005 Rev 0
Combined Rc Ω 1.231338
Permissible Current Density
Soil σs A/m2 730.9304 Clause 15.2 BS7340
Water σw A/m2 9806.46 Clause 15.2 BS7341
Area
Soil As m2 4.6472 πdls
Water Aw m2 0.1256 πdlw
Current Division Resistance Capacity Design
Soil 3396.779785
Water 1231.691433
TOTAL 4627 A
29
Abstract of IEEE 80 2000
30
PBC Training Document PBC/ER/005 Rev 0 7/2/2013
Abstract of IEEE 80 2000
PBC Training Document PBC/ER/005 Rev 0 7/2/201331
Abstract of IEEE 80 2000
PBC Training Document PBC/ER/005 Rev 0 7/2/201332
Dangerous Potentials
33
PBC Training Document PBC/ER/005 Rev 0 7/2/2013
Voltage Variation with proximity
V
• The charges are distributed to
the surrounding soil.
• The Voltage is thus high near theV
V
• The Voltage is thus high near the
pit and low away from it
7/2/2013PBC Training Document PBC/ER/005 Rev 0 34
Step Potential
Calculation of permissible Step Potential:
(Clause 7.4 and 12.5 of IEEE 80:2000)
(Clause 8.3 of IEEE
35
TERMS:
ρ – Soil Resistivity in -m
ρs – Soil Resistivity of additional surface layer in -m
hs – Thickness of additional surface layer in m
ts – Shock current duration in sec
Cs – Surface layer de-rating factor
(Clause 8.3 of IEEE
80:2000)
(Clause 8.3 of IEEE
80:2000)
7/2/2013PBC Training Document PBC/ER/005 Rev 0
Calculation of actual Step Potential:
(Clause 16.5 of IEEE
80:2000)
TERMS:
ρ – Soil Resistivity in -m
36
ρ – Soil Resistivity in -m
Ks – Spacing factor for step voltage
Ki – Correction factor for grid geometry
IG – Grid current in KA
Ls – Effective length of (Lc + LR) for step voltage in m
where Lc = Total length of grid conductor
LR = Total length of ground rods
Calculated Step Potential must be less than permissible Step Potential.
7/2/2013PBC Training Document PBC/ER/005 Rev 0
Touch Potential
Calculation of permissible Touch Potential:
(Clause 7.4 and 12.5 of IEEE 80:2000)
(Clause 8.3 of IEEE
37
TERMS:
ρ – Soil Resistivity in -m
ρs – Soil Resistivity of additional surface layer in -m
hs – Thickness of additional surface layer in m
ts – Shock current duration in sec
Cs – Surface layer de-rating factor
(Clause 8.3 of IEEE
80:2000)
(Clause 8.3 of IEEE
80:2000)
7/2/2013PBC Training Document PBC/ER/005 Rev 0
Calculation of actual Mesh Potential:
(Clause 16.5 of IEEE
80:2000)
TERMS:
ρ – Soil Resistivity in -m
Km – Spacing factor for mesh voltage
38
Km – Spacing factor for mesh voltage
Ki – Correction factor for grid geometry
IG – Grid current in KA
LM – Effective length of (Lc + LR) for mesh voltage in m
where Lc = Total length of grid conductor
LR = Total length of ground rods
Calculated Mesh Potential must be less than permissible Touch Potential.
7/2/2013PBC Training Document PBC/ER/005 Rev 0
Tolerable currents by Humans
Frequency based (lethal values)
DC 25Hz 50/60Hz 3-10 KHz
0.5A 0.15A 0.1A high current
39
7/2/2013PBC Training Document PBC/ER/005 Rev 0
Threshold current,
tingling feeling
Let – go current.
Can release
Cannot release
energized object
Ventricular fibrillation
1 mA 1-6 mA 9-25 mA 60 - higher
0.5A 0.15A 0.1A high current
Amplitude based
Tolerable currents by Humans (Con.)
Weight Based Time based
40
7/2/2013PBC Training Document PBC/ER/005 Rev 0
Step potential (Permissible Value)
It is the concentration of charge that creates Tension or Voltage
Voltage drives the Current
Permissible Estep = (1000+6Csρs)0.116/sqrt(t)
Actual E < Permissible E
VV
Actual Estep < Permissible Estep
7/2/2013PBC Training Document PBC/ER/005 Rev 0 41
Mesh Potential (Permissible Value)
E touch is the Voltage difference between where the person is
standing in the grid and GPR.
E mesh is the Max E touch in a grid
Permissible E touch is the voltage limit that can produce
dangerous currents
42
dangerous currents
E mesh < Permissible E touch
Permissible E touch =(1000+1.5Csρs)0.116/sqrt(t)
7/2/2013PBC Training Document PBC/ER/005 Rev 0
Potential Distribution
Permissible Step PotentialActual Step Potential
43
PBC Training Document PBC/ER/005 Rev 0
Permissible Step Potential
Dangerous Step Potential
Actual Step Potential
Corrected Step Potential
7/2/2013
Abstract of IEEE 80 2000
PBC Training Document PBC/ER/005 Rev 0 7/2/201344
Abstract of IEEE 80 2000
PBC Training Document PBC/ER/005 Rev 0 7/2/201345
Abstract of IEEE 80 2000
PBC Training Document PBC/ER/005 Rev 0 7/2/201346
Ring Earth
•The concentric conductors reduce the resistance
significantly
•The reactance is reduced by tying the rings to
each other at the corners
•A ramp arrangement is followed burying the out
conductors deeper than the inner conductors to
47
7/2/2013PBC Training Document PBC/ER/005 Rev 0
conductors deeper than the inner conductors to
obtain a gradual potential curve
Formulae to Calculate Resistance
for plate earthing
R = (ρ/4)* sqrt (π/2A)
for pipe earthing
R = (ρ/2πL)* [ln (8L/d)-1]
for strip earthing
R=(ρ/PπL)* [ln (2L2 /(wh))+ Q]
48
PBC Training Document PBC/ER/005 Rev 0
R=(ρ/PπL)* [ln (2L2 /(wh))+ Q]
for grid earthing
R=ρ[(1/LT)+ (1/sqrt (20A) (1+ (1/1+h) sqrt (20A)
Is Material of the grid important for achieving resistance?
No. If corrosion factor is taken care of
7/2/2013
Variation of resistance to earth with length at different Soil
resistivity
49
7/2/2013PBC Training Document PBC/ER/005 Rev 0
Abstract of IEEE 142
50
7/2/2013PBC Training Document PBC/ER/005 Rev 0
Effect of Resistance due to Artificial Treatment
50
60
70
80
Radius of
Artificial
treatment in
mm
Remaining percentage of
resistance to remote earth
51
PBC Training Document PBC/ER/005 Rev 0
0
10
20
30
40
1 10 100 1000 10000
Series1
30 75
60 62
90 54
150 48
300 32
1500 14
7/2/2013
Abstract of IEEE 80 2000
PBC Training Document PBC/ER/005 Rev 0 7/2/201352
Influence of
MV on LV
If Rp>1, the voltage Rp*Ihmt
should be less than
100V in under 500 ms
500V in under 100 ms
53
If this is not so Rp and Rn must be
separate
Exp. of PDS world wide
7/2/2013PBC Training Document PBC/ER/005 Rev 0
Internationally accepted MV/LV earthing systems
7/2/2013PBC Training Document PBC/ER/005 Rev 0 54
7/2/2013PBC Training Document PBC/ER/005 Rev 0 55
Measurement of Resistance of the grounding system
Fall of point method
61.8% distance rule
Tagg slope method
Tagg intersection curve
Covered in the paper
56
PBC Training Document PBC/ER/005 Rev 0
Covered in the paper
already with you
7/2/2013
Positioning of the potential probe
57
PBC Training Document PBC/ER/005 Rev 0 7/2/2013
Essential Practices
Must use insulation gear
Must keep a gap of at least 6 meters between potential and
current lead
Must insulate any joint appearing in the lead
Use meter
having stray current filter.
58
PBC Training Document PBC/ER/005 Rev 0
having stray current filter.
where the injected current frequencies can be changed
Injected current can be made high or low depending on current probe
resistance.
Apply water and compact the current and potential probes to
avoid undue high probe resistance.
Lose potential probe can give high value of R .
Avoid measuring along buried or superficial metal conductors
7/2/2013
Fall of point method
59
PBC Training Document PBC/ER/005 Rev 0
The average of the flat part of the graph gives the give the ground impedance
7/2/2013
61.8% Distance Rule
The reading levels of at P2 61.8% of the current
probe C2
At distances lower than 61.8%, the impedance
reading is lower and dips on approaching the
resistance zone of the grid
60
PBC Training Document PBC/ER/005 Rev 0
resistance zone of the grid
Similarly the impedance reading increases as the P2
enters the resistance zone of C2
7/2/2013
TAGG SLOPE Method
=(R3-R2)/(R2-R1)
0.4 < < 1.6
61
PBC Training Document PBC/ER/005 Rev 0 7/2/2013
BREAK 3
62
T H I N K I N G T I M E
PBC Training Document PBC/ER/005 Rev 0 7/2/2013
Earth fault Protection
Earth Fault protection in installations
Selection of device for automatic disconnection
Earth fault protection Devices
Duration 15 min
63
Duration 15 min
7/2/2013PBC Training Document PBC/ER/005 Rev 0
Earth Fault Protection in Installation
Trip 65V in 10 Sec, and 230 V instantaneously
Earth fault protection involves automatic disconnection
to prevent dangerous duration and magnitude of touch
voltage.
The earth fault loop impedance has to be low enough to
trip overcurrent protective devices.
64
trip overcurrent protective devices.
Where low earth fault loop impedance cannot be
achieved, disconnection may be facilitated by RCCB or
Voltage operated ELCB
RCD having minimum operating current greater than
30mA indirect shock risk protection
RCD having minimum operating current less than 30mA
direct shock risk protection
7/2/2013PBC Training Document PBC/ER/005 Rev 0
Voltage Operated ELCBVoltage Operated ELCB
RCD Current Operated
ELCB
RCD Current Operated
ELCB
Earth Fault Detection
65
Not suitable for protection of human
Trip coil set to operate at 50 V
7/2/2013PBC Training Document PBC/ER/005 Rev 0
RCD Connections
66
7/2/2013PBC Training Document PBC/ER/005 Rev 0
IS 3043
67
7/2/2013PBC Training Document PBC/ER/005 Rev 0
Earthing of Captive Power Plant
Low voltage generators
High voltage generators
Duration 30 min
68
7/2/2013PBC Training Document PBC/ER/005 Rev 0
• It should be connected to installation main earth
• The main earth terminal should be connected to earth electrode
• Installation should be protected by RCD
• RCD cannot protect generator side of the circuit.
• For mobile loads the RCD should be 30mA with tripping time of 40mS
7/2/2013PBC Training Document PBC/ER/005 Rev 0 69
Generators above 10kW Working in parallel
• To avoid flow of
circulating
currents, the
neutral point of
generator is
disconnected in
presence of supply
70
7/2/2013PBC Training Document PBC/ER/005 Rev 0
presence of supply
neutral
• Generators
working in
parallel, have only
1 common earth
point.
• 30mA RCD to be
provided for
protection of load
side of RCD
RCD
Low voltage standby generators with neutral earthing
transformers
71
7/2/2013PBC Training Document PBC/ER/005 Rev 0
Cable Core Sheath Bonding System
72
7/2/2013PBC Training Document PBC/ER/005 Rev 0
Statutory Provisions for Earthing
Should follow Indian Electricity Rule 1956
All MV and HV equipments to be earthed by 2
separate earths
Earth electrode should be devised such that testing is
possible.
73
possible.
The value of earth resistance should be based on
degree of shock protection.
No additional source to be added with out verifying
the capacity of earthing system
7/2/2013PBC Training Document PBC/ER/005 Rev 0
Bibliography
IEEE 80 2000 for substation
IEEE 665 1995 for Generating Station
IEEE 142 1991 for Industrial establishment
IEEE 81 1993 for Earthing Measurements
IEEE 1100 for powering and grounding electronic equipments.
IEEE 575 for sheath bonding and induced voltagesIEEE 575 for sheath bonding and induced voltages
BS 7430 1998 Code of practice for Earthing
IS 3043-1987 Code of practice for Earthing
IEC 62305 Part 1 to Part 4
NFPA 70 and NFPA 780
API RP 2003 for statics and lightning protection
And many more ref. texts
7/2/2013PBC Training Document PBC/ER/005 Rev 0 74
S A F E T Y T H R U D E S I G N
Saving life and Assets
75
T H A N K Y O U
7/2/2013PBC Training Document PBC/ER/005 Rev 0

More Related Content

What's hot

Earthing Concepts
Earthing ConceptsEarthing Concepts
Earthing Concepts
mvrkprasad
 
Neutral grounding
Neutral groundingNeutral grounding
Neutral grounding
Vinod Srivastava
 
Principles of Cable Sizing
Principles of Cable SizingPrinciples of Cable Sizing
Principles of Cable Sizing
Leonardo ENERGY
 
GIS (Gas-Insulated Substation) by Bharat & Shanni
GIS (Gas-Insulated Substation) by Bharat & ShanniGIS (Gas-Insulated Substation) by Bharat & Shanni
GIS (Gas-Insulated Substation) by Bharat & Shanni
BHARATKUMAR RATHOD
 
presentation on substation layout and BUS bar arrangement.
presentation on substation layout and BUS bar arrangement.presentation on substation layout and BUS bar arrangement.
presentation on substation layout and BUS bar arrangement.
Hemendra Kumar Rajput
 
Grounding,Earthing,Bonding
Grounding,Earthing,BondingGrounding,Earthing,Bonding
Grounding,Earthing,Bonding
Ko Winnwe
 
Eat105 chapter 2
Eat105 chapter 2Eat105 chapter 2
Using High Resistance Grounding to Mitigate Arc Flash Hazards
Using High Resistance Grounding to Mitigate Arc Flash HazardsUsing High Resistance Grounding to Mitigate Arc Flash Hazards
Using High Resistance Grounding to Mitigate Arc Flash Hazards
michaeljmack
 
Tutorial on Distance and Over Current Protection
Tutorial on Distance and Over  Current ProtectionTutorial on Distance and Over  Current Protection
Tutorial on Distance and Over Current Protection
SARAVANAN A
 
BREAKDOWN OF GAS|DIELECTRIC BREAKDOWN PROCESS IN HINDI|HIGH VOLTAGE ENGINEERING
BREAKDOWN OF GAS|DIELECTRIC BREAKDOWN PROCESS IN HINDI|HIGH VOLTAGE ENGINEERINGBREAKDOWN OF GAS|DIELECTRIC BREAKDOWN PROCESS IN HINDI|HIGH VOLTAGE ENGINEERING
BREAKDOWN OF GAS|DIELECTRIC BREAKDOWN PROCESS IN HINDI|HIGH VOLTAGE ENGINEERING
Prasant Kumar
 
Switchyard
SwitchyardSwitchyard
Switchyard
I.E.T. lucknow
 
INTERFACING.ppt
INTERFACING.pptINTERFACING.ppt
INTERFACING.ppt
DundiKumarBevara
 
surge diverters
surge diverterssurge diverters
surge diverters
nehakardam
 
CT design aspects - Nageswar-6
CT design aspects - Nageswar-6CT design aspects - Nageswar-6
CT design aspects - Nageswar-6
Nageswar Rao
 
Grounding in power system
Grounding in power systemGrounding in power system
Grounding in power system
vardhan k
 
Testing of circuit breakers
Testing of circuit breakersTesting of circuit breakers
Testing of circuit breakers
Kabilesh K
 
CONDUCTION & BREAKDOWN IN LIQUID DIELECTRICS|HIGH VOLTAGE ENGINEERING|ELECTRI...
CONDUCTION & BREAKDOWN IN LIQUID DIELECTRICS|HIGH VOLTAGE ENGINEERING|ELECTRI...CONDUCTION & BREAKDOWN IN LIQUID DIELECTRICS|HIGH VOLTAGE ENGINEERING|ELECTRI...
CONDUCTION & BREAKDOWN IN LIQUID DIELECTRICS|HIGH VOLTAGE ENGINEERING|ELECTRI...
Prasant Kumar
 
Power Quality
Power QualityPower Quality
Power Quality
kunwartouseef
 
Chap 8_Mechanical Design of Overhead Tx Line_Part 2.pptx
Chap 8_Mechanical Design of Overhead Tx Line_Part 2.pptxChap 8_Mechanical Design of Overhead Tx Line_Part 2.pptx
Chap 8_Mechanical Design of Overhead Tx Line_Part 2.pptx
DaniyalAhmadKhan3
 
Distribution System Planning and Design
Distribution System Planning and DesignDistribution System Planning and Design
Distribution System Planning and Design
Adithya Ballaji
 

What's hot (20)

Earthing Concepts
Earthing ConceptsEarthing Concepts
Earthing Concepts
 
Neutral grounding
Neutral groundingNeutral grounding
Neutral grounding
 
Principles of Cable Sizing
Principles of Cable SizingPrinciples of Cable Sizing
Principles of Cable Sizing
 
GIS (Gas-Insulated Substation) by Bharat & Shanni
GIS (Gas-Insulated Substation) by Bharat & ShanniGIS (Gas-Insulated Substation) by Bharat & Shanni
GIS (Gas-Insulated Substation) by Bharat & Shanni
 
presentation on substation layout and BUS bar arrangement.
presentation on substation layout and BUS bar arrangement.presentation on substation layout and BUS bar arrangement.
presentation on substation layout and BUS bar arrangement.
 
Grounding,Earthing,Bonding
Grounding,Earthing,BondingGrounding,Earthing,Bonding
Grounding,Earthing,Bonding
 
Eat105 chapter 2
Eat105 chapter 2Eat105 chapter 2
Eat105 chapter 2
 
Using High Resistance Grounding to Mitigate Arc Flash Hazards
Using High Resistance Grounding to Mitigate Arc Flash HazardsUsing High Resistance Grounding to Mitigate Arc Flash Hazards
Using High Resistance Grounding to Mitigate Arc Flash Hazards
 
Tutorial on Distance and Over Current Protection
Tutorial on Distance and Over  Current ProtectionTutorial on Distance and Over  Current Protection
Tutorial on Distance and Over Current Protection
 
BREAKDOWN OF GAS|DIELECTRIC BREAKDOWN PROCESS IN HINDI|HIGH VOLTAGE ENGINEERING
BREAKDOWN OF GAS|DIELECTRIC BREAKDOWN PROCESS IN HINDI|HIGH VOLTAGE ENGINEERINGBREAKDOWN OF GAS|DIELECTRIC BREAKDOWN PROCESS IN HINDI|HIGH VOLTAGE ENGINEERING
BREAKDOWN OF GAS|DIELECTRIC BREAKDOWN PROCESS IN HINDI|HIGH VOLTAGE ENGINEERING
 
Switchyard
SwitchyardSwitchyard
Switchyard
 
INTERFACING.ppt
INTERFACING.pptINTERFACING.ppt
INTERFACING.ppt
 
surge diverters
surge diverterssurge diverters
surge diverters
 
CT design aspects - Nageswar-6
CT design aspects - Nageswar-6CT design aspects - Nageswar-6
CT design aspects - Nageswar-6
 
Grounding in power system
Grounding in power systemGrounding in power system
Grounding in power system
 
Testing of circuit breakers
Testing of circuit breakersTesting of circuit breakers
Testing of circuit breakers
 
CONDUCTION & BREAKDOWN IN LIQUID DIELECTRICS|HIGH VOLTAGE ENGINEERING|ELECTRI...
CONDUCTION & BREAKDOWN IN LIQUID DIELECTRICS|HIGH VOLTAGE ENGINEERING|ELECTRI...CONDUCTION & BREAKDOWN IN LIQUID DIELECTRICS|HIGH VOLTAGE ENGINEERING|ELECTRI...
CONDUCTION & BREAKDOWN IN LIQUID DIELECTRICS|HIGH VOLTAGE ENGINEERING|ELECTRI...
 
Power Quality
Power QualityPower Quality
Power Quality
 
Chap 8_Mechanical Design of Overhead Tx Line_Part 2.pptx
Chap 8_Mechanical Design of Overhead Tx Line_Part 2.pptxChap 8_Mechanical Design of Overhead Tx Line_Part 2.pptx
Chap 8_Mechanical Design of Overhead Tx Line_Part 2.pptx
 
Distribution System Planning and Design
Distribution System Planning and DesignDistribution System Planning and Design
Distribution System Planning and Design
 

Viewers also liked

Det4 tc2
Det4 tc2Det4 tc2
Det4 tc2
Niroj Bhujel
 
ATS, Grounding Issues & Installation Considerations
ATS, Grounding Issues & Installation ConsiderationsATS, Grounding Issues & Installation Considerations
ATS, Grounding Issues & Installation Considerations
michaeljmack
 
Electrical grounding and earthing
Electrical grounding and earthingElectrical grounding and earthing
Electrical grounding and earthing
Nitesh Dash
 
2015 Upload Campaigns Calendar - SlideShare
2015 Upload Campaigns Calendar - SlideShare2015 Upload Campaigns Calendar - SlideShare
2015 Upload Campaigns Calendar - SlideShare
SlideShare
 
What to Upload to SlideShare
What to Upload to SlideShareWhat to Upload to SlideShare
What to Upload to SlideShare
SlideShare
 
Getting Started With SlideShare
Getting Started With SlideShareGetting Started With SlideShare
Getting Started With SlideShare
SlideShare
 

Viewers also liked (6)

Det4 tc2
Det4 tc2Det4 tc2
Det4 tc2
 
ATS, Grounding Issues & Installation Considerations
ATS, Grounding Issues & Installation ConsiderationsATS, Grounding Issues & Installation Considerations
ATS, Grounding Issues & Installation Considerations
 
Electrical grounding and earthing
Electrical grounding and earthingElectrical grounding and earthing
Electrical grounding and earthing
 
2015 Upload Campaigns Calendar - SlideShare
2015 Upload Campaigns Calendar - SlideShare2015 Upload Campaigns Calendar - SlideShare
2015 Upload Campaigns Calendar - SlideShare
 
What to Upload to SlideShare
What to Upload to SlideShareWhat to Upload to SlideShare
What to Upload to SlideShare
 
Getting Started With SlideShare
Getting Started With SlideShareGetting Started With SlideShare
Getting Started With SlideShare
 

Similar to Technical presentation on modern earthing

Modeling and Analysis of a 3-Phase 132kv GasInsulated Substation
Modeling and Analysis of a 3-Phase 132kv GasInsulated SubstationModeling and Analysis of a 3-Phase 132kv GasInsulated Substation
Modeling and Analysis of a 3-Phase 132kv GasInsulated Substation
IRJET Journal
 
Grounding pad mounted transformers
Grounding   pad mounted transformersGrounding   pad mounted transformers
Grounding pad mounted transformers
Jimmy Chaparro
 
Grounding pad mounted transformers
Grounding   pad mounted transformersGrounding   pad mounted transformers
Grounding pad mounted transformers
Jimmy Chaparro
 
G-57.pdf
G-57.pdfG-57.pdf
G-57.pdf
donalplus
 
grad project IEEE paper
grad project IEEE papergrad project IEEE paper
grad project IEEE paper
Akash Patel, EIT
 
unit-iii- Sphere Gap.ppt
unit-iii- Sphere Gap.pptunit-iii- Sphere Gap.ppt
unit-iii- Sphere Gap.ppt
VijayHiremath26
 
cable sizing.ppt
cable sizing.pptcable sizing.ppt
cable sizing.ppt
ChadWood16
 
A Novel Design of a Microstrip Microwave Power Amplifier for DCS Application ...
A Novel Design of a Microstrip Microwave Power Amplifier for DCS Application ...A Novel Design of a Microstrip Microwave Power Amplifier for DCS Application ...
A Novel Design of a Microstrip Microwave Power Amplifier for DCS Application ...
IJECEIAES
 
Grounding System Analysis
Grounding System AnalysisGrounding System Analysis
Grounding System Analysis
ijtsrd
 
Improvement of Transient Stability in Doubly Fed Induction Wind Generator usi...
Improvement of Transient Stability in Doubly Fed Induction Wind Generator usi...Improvement of Transient Stability in Doubly Fed Induction Wind Generator usi...
Improvement of Transient Stability in Doubly Fed Induction Wind Generator usi...
IRJET Journal
 
Life Cycle of Big Data Analysis by using MapReduce Algorithm
Life Cycle of Big Data Analysis by using MapReduce AlgorithmLife Cycle of Big Data Analysis by using MapReduce Algorithm
Life Cycle of Big Data Analysis by using MapReduce Algorithm
IRJET Journal
 
UNDERGROUND CABLE FAULT DISTANCE LOCATOR
UNDERGROUND CABLE FAULT DISTANCE LOCATORUNDERGROUND CABLE FAULT DISTANCE LOCATOR
UNDERGROUND CABLE FAULT DISTANCE LOCATOR
ijiert bestjournal
 
Tertiary interbus transformer and alternative protection
Tertiary interbus transformer and alternative protectionTertiary interbus transformer and alternative protection
Tertiary interbus transformer and alternative protection
Souvik Dutta
 
Earthing Types and role in power substation.ppt
Earthing Types and role in power substation.pptEarthing Types and role in power substation.ppt
Earthing Types and role in power substation.ppt
wazakify
 
Design of bridgeless high-power-factor buck-converter operating in discontinu...
Design of bridgeless high-power-factor buck-converter operating in discontinu...Design of bridgeless high-power-factor buck-converter operating in discontinu...
Design of bridgeless high-power-factor buck-converter operating in discontinu...
IRJET Journal
 
final year project report
final year project reportfinal year project report
final year project report
Anuj Kumar
 
WIRELESS POWER TRANSMISSION Project
WIRELESS POWER TRANSMISSION ProjectWIRELESS POWER TRANSMISSION Project
WIRELESS POWER TRANSMISSION Project
sagnikchoudhury
 
Underground Cable Fault Detection Using Arduino
Underground Cable Fault Detection Using ArduinoUnderground Cable Fault Detection Using Arduino
Underground Cable Fault Detection Using Arduino
IRJET Journal
 
Boukhriss Compeng Italy 2022.pdf
Boukhriss Compeng Italy 2022.pdfBoukhriss Compeng Italy 2022.pdf
Boukhriss Compeng Italy 2022.pdf
ALIBOUKHRISS
 
Wireless Power Transfer Project
Wireless Power Transfer  ProjectWireless Power Transfer  Project
Wireless Power Transfer Project
sagnikchoudhury
 

Similar to Technical presentation on modern earthing (20)

Modeling and Analysis of a 3-Phase 132kv GasInsulated Substation
Modeling and Analysis of a 3-Phase 132kv GasInsulated SubstationModeling and Analysis of a 3-Phase 132kv GasInsulated Substation
Modeling and Analysis of a 3-Phase 132kv GasInsulated Substation
 
Grounding pad mounted transformers
Grounding   pad mounted transformersGrounding   pad mounted transformers
Grounding pad mounted transformers
 
Grounding pad mounted transformers
Grounding   pad mounted transformersGrounding   pad mounted transformers
Grounding pad mounted transformers
 
G-57.pdf
G-57.pdfG-57.pdf
G-57.pdf
 
grad project IEEE paper
grad project IEEE papergrad project IEEE paper
grad project IEEE paper
 
unit-iii- Sphere Gap.ppt
unit-iii- Sphere Gap.pptunit-iii- Sphere Gap.ppt
unit-iii- Sphere Gap.ppt
 
cable sizing.ppt
cable sizing.pptcable sizing.ppt
cable sizing.ppt
 
A Novel Design of a Microstrip Microwave Power Amplifier for DCS Application ...
A Novel Design of a Microstrip Microwave Power Amplifier for DCS Application ...A Novel Design of a Microstrip Microwave Power Amplifier for DCS Application ...
A Novel Design of a Microstrip Microwave Power Amplifier for DCS Application ...
 
Grounding System Analysis
Grounding System AnalysisGrounding System Analysis
Grounding System Analysis
 
Improvement of Transient Stability in Doubly Fed Induction Wind Generator usi...
Improvement of Transient Stability in Doubly Fed Induction Wind Generator usi...Improvement of Transient Stability in Doubly Fed Induction Wind Generator usi...
Improvement of Transient Stability in Doubly Fed Induction Wind Generator usi...
 
Life Cycle of Big Data Analysis by using MapReduce Algorithm
Life Cycle of Big Data Analysis by using MapReduce AlgorithmLife Cycle of Big Data Analysis by using MapReduce Algorithm
Life Cycle of Big Data Analysis by using MapReduce Algorithm
 
UNDERGROUND CABLE FAULT DISTANCE LOCATOR
UNDERGROUND CABLE FAULT DISTANCE LOCATORUNDERGROUND CABLE FAULT DISTANCE LOCATOR
UNDERGROUND CABLE FAULT DISTANCE LOCATOR
 
Tertiary interbus transformer and alternative protection
Tertiary interbus transformer and alternative protectionTertiary interbus transformer and alternative protection
Tertiary interbus transformer and alternative protection
 
Earthing Types and role in power substation.ppt
Earthing Types and role in power substation.pptEarthing Types and role in power substation.ppt
Earthing Types and role in power substation.ppt
 
Design of bridgeless high-power-factor buck-converter operating in discontinu...
Design of bridgeless high-power-factor buck-converter operating in discontinu...Design of bridgeless high-power-factor buck-converter operating in discontinu...
Design of bridgeless high-power-factor buck-converter operating in discontinu...
 
final year project report
final year project reportfinal year project report
final year project report
 
WIRELESS POWER TRANSMISSION Project
WIRELESS POWER TRANSMISSION ProjectWIRELESS POWER TRANSMISSION Project
WIRELESS POWER TRANSMISSION Project
 
Underground Cable Fault Detection Using Arduino
Underground Cable Fault Detection Using ArduinoUnderground Cable Fault Detection Using Arduino
Underground Cable Fault Detection Using Arduino
 
Boukhriss Compeng Italy 2022.pdf
Boukhriss Compeng Italy 2022.pdfBoukhriss Compeng Italy 2022.pdf
Boukhriss Compeng Italy 2022.pdf
 
Wireless Power Transfer Project
Wireless Power Transfer  ProjectWireless Power Transfer  Project
Wireless Power Transfer Project
 

Recently uploaded

一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
ecqow
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
KrishnaveniKrishnara1
 
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by AnantLLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
Anant Corporation
 
CompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURS
CompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURSCompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURS
CompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURS
RamonNovais6
 
An Introduction to the Compiler Designss
An Introduction to the Compiler DesignssAn Introduction to the Compiler Designss
An Introduction to the Compiler Designss
ElakkiaU
 
AI assisted telemedicine KIOSK for Rural India.pptx
AI assisted telemedicine KIOSK for Rural India.pptxAI assisted telemedicine KIOSK for Rural India.pptx
AI assisted telemedicine KIOSK for Rural India.pptx
architagupta876
 
Manufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptxManufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptx
Madan Karki
 
Certificates - Mahmoud Mohamed Moursi Ahmed
Certificates - Mahmoud Mohamed Moursi AhmedCertificates - Mahmoud Mohamed Moursi Ahmed
Certificates - Mahmoud Mohamed Moursi Ahmed
Mahmoud Morsy
 
Engineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdfEngineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdf
abbyasa1014
 
Rainfall intensity duration frequency curve statistical analysis and modeling...
Rainfall intensity duration frequency curve statistical analysis and modeling...Rainfall intensity duration frequency curve statistical analysis and modeling...
Rainfall intensity duration frequency curve statistical analysis and modeling...
bijceesjournal
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
Madan Karki
 
Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...
bijceesjournal
 
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
IJECEIAES
 
BRAIN TUMOR DETECTION for seminar ppt.pdf
BRAIN TUMOR DETECTION for seminar ppt.pdfBRAIN TUMOR DETECTION for seminar ppt.pdf
BRAIN TUMOR DETECTION for seminar ppt.pdf
LAXMAREDDY22
 
People as resource Grade IX.pdf minimala
People as resource Grade IX.pdf minimalaPeople as resource Grade IX.pdf minimala
People as resource Grade IX.pdf minimala
riddhimaagrawal986
 
Data Control Language.pptx Data Control Language.pptx
Data Control Language.pptx Data Control Language.pptxData Control Language.pptx Data Control Language.pptx
Data Control Language.pptx Data Control Language.pptx
ramrag33
 
Curve Fitting in Numerical Methods Regression
Curve Fitting in Numerical Methods RegressionCurve Fitting in Numerical Methods Regression
Curve Fitting in Numerical Methods Regression
Nada Hikmah
 
Welding Metallurgy Ferrous Materials.pdf
Welding Metallurgy Ferrous Materials.pdfWelding Metallurgy Ferrous Materials.pdf
Welding Metallurgy Ferrous Materials.pdf
AjmalKhan50578
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
kandramariana6
 
integral complex analysis chapter 06 .pdf
integral complex analysis chapter 06 .pdfintegral complex analysis chapter 06 .pdf
integral complex analysis chapter 06 .pdf
gaafergoudaay7aga
 

Recently uploaded (20)

一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
 
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by AnantLLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
 
CompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURS
CompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURSCompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURS
CompEx~Manual~1210 (2).pdf COMPEX GAS AND VAPOURS
 
An Introduction to the Compiler Designss
An Introduction to the Compiler DesignssAn Introduction to the Compiler Designss
An Introduction to the Compiler Designss
 
AI assisted telemedicine KIOSK for Rural India.pptx
AI assisted telemedicine KIOSK for Rural India.pptxAI assisted telemedicine KIOSK for Rural India.pptx
AI assisted telemedicine KIOSK for Rural India.pptx
 
Manufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptxManufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptx
 
Certificates - Mahmoud Mohamed Moursi Ahmed
Certificates - Mahmoud Mohamed Moursi AhmedCertificates - Mahmoud Mohamed Moursi Ahmed
Certificates - Mahmoud Mohamed Moursi Ahmed
 
Engineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdfEngineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdf
 
Rainfall intensity duration frequency curve statistical analysis and modeling...
Rainfall intensity duration frequency curve statistical analysis and modeling...Rainfall intensity duration frequency curve statistical analysis and modeling...
Rainfall intensity duration frequency curve statistical analysis and modeling...
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
 
Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...
 
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
 
BRAIN TUMOR DETECTION for seminar ppt.pdf
BRAIN TUMOR DETECTION for seminar ppt.pdfBRAIN TUMOR DETECTION for seminar ppt.pdf
BRAIN TUMOR DETECTION for seminar ppt.pdf
 
People as resource Grade IX.pdf minimala
People as resource Grade IX.pdf minimalaPeople as resource Grade IX.pdf minimala
People as resource Grade IX.pdf minimala
 
Data Control Language.pptx Data Control Language.pptx
Data Control Language.pptx Data Control Language.pptxData Control Language.pptx Data Control Language.pptx
Data Control Language.pptx Data Control Language.pptx
 
Curve Fitting in Numerical Methods Regression
Curve Fitting in Numerical Methods RegressionCurve Fitting in Numerical Methods Regression
Curve Fitting in Numerical Methods Regression
 
Welding Metallurgy Ferrous Materials.pdf
Welding Metallurgy Ferrous Materials.pdfWelding Metallurgy Ferrous Materials.pdf
Welding Metallurgy Ferrous Materials.pdf
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
 
integral complex analysis chapter 06 .pdf
integral complex analysis chapter 06 .pdfintegral complex analysis chapter 06 .pdf
integral complex analysis chapter 06 .pdf
 

Technical presentation on modern earthing

  • 1. O N M O D E R N C O N C E P T S A N D A D V A N C E D T E C H N I Q U E S O F E A R T H I N G 1 Technical Presentation to PROJECT PRICIPALS B Y P A N K A J C H A K R A B O R T Y OF PBC INDUSTRIAL SERVICES B L O C K – 1 9 , F L A Y – 1 1 7 , P A R N A S R E E G O V T . H O U S I N G , K O L K A T A – 7 0 0 0 6 0 , ( W E S T - B E N G A L ) 7/2/2013PBC Training Document PBC/ER/005 Rev 0
  • 2. Objectives Return path during continuous operation should not be thru earth path unless designed. Instantaneous fault current should not flow thru the neutral circuit creating live and dangerous neutral. Dissipate the stray currents, lightning, surges 2 Dissipate the stray currents, lightning, surges keeping system hazard free. Maintain the whole facility at equipotential. Provide reference to run the system at specified voltage 7/2/2013PBC Training Document PBC/ER/005 Rev 0
  • 3. TN System Transformer neutral is earthed Frames of electrical load are connected to neutral Fault is cleared by SCPD 3 Fault is cleared by SCPD TN-C, TN-S, TN-CS SCPD/ loop impedance matching Not recommended for premises having electronic and communication system Not used when cross-section of live cond. < 10 sqmm PE may get damaged by loads generating 3rd harmonics. 7/2/2013PBC Training Document PBC/ER/005 Rev 0
  • 4. TT system Transformer neutral is earthed Frame of electrical load is connected to earth connection Fault cleared by RCD. 4 7/2/2013PBC Training Document PBC/ER/005 Rev 0
  • 5. IT System Transformer neutral is not earthed. Frame of electrical load is earthed. First fault does not present risk, indication is sufficient Second fault cleared by SCPD 5 Second fault cleared by SCPD Ensure continuity of service where human life is at stake or with furnaces 7/2/2013PBC Training Document MEPL/ER/005 Rev 0
  • 6. 7/2/2013PBC Training Document PBC/ER/005 Rev 0 6
  • 7. Problem for electronic and communication system 7/2/2013PBC Training Document PBC/ER/005 Rev 0 7
  • 8. Comparing Earthing system 8 7/2/2013PBC Training Document PBC/ER/005 Rev 0
  • 9. Parallel association of Earthing system 9 7/2/2013PBC Training Document PBC/ER/005 Rev 0
  • 10. BREAK 1 10 T H I N K I N G T I M E PBC Training Document PBC/ER/005 Rev 0 7/2/2013
  • 11. Soil Resistivity of different Soil Types 11 7/2/2013PBC Training Document PBC/ER/005 Rev 0
  • 12. Resistivity Plot Use Wenner 4 point method. Take at least 4 readings in one direction from 7mt spacing to spacing equal to diagonal of the electrical installation. Repeat these readings in all 8 directions separated by 450 angle. 12 7/2/2013PBC Training Document PBC/ER/005 Rev 0 angle. Calculate the resistivity. Make a polar plot. Calculate the area under the polar plot Draw a circle of equal area Radius of the circle is the resistivity of the point.
  • 13. Variation in Resistivity 13 PBC Training Document PBC/ER/005 Rev 0 7/2/2013
  • 14. 7/2/2013PBC Training Document PBC/ER/005 Rev 0 14
  • 15. Resistivity Plot 15 7/2/2013PBC Training Document PBC/ER/005 Rev 0
  • 16. Wenner’s method 16 PBC Training Document PBC/ER/005 Rev 0 7/2/2013
  • 17. Schulemberger method 17 PBC Training Document PBC/ER/005 Rev 0 7/2/2013
  • 18. Essential Practices Use meter having stray current filter. where the injected current frequencies can be changed Injected current can be made high or low depending on current probe resistance. Apply water and compact the current and potential 18 Apply water and compact the current and potential probes to avoid undue high probe resistance. Lose potential probe can give high value of R and high resistivity. Avoid measuring along buried or superficial metal conductors Take readings in multiple directions 7/2/2013
  • 19. Abstract of IEEE 81 1993 19 PBC Training Document PBC/ER/005 Rev 0 7/2/2013
  • 20. Polar curve method for Uniform Soil Resistivity • Resistivity taken in min 8 directions • Angular distance between readings 450 • Cautiously Interpolate the readings to 7.50 • Join the Points to form a polar curve 20 PBC Training Document PBC/ER/005 Rev 0 curve • Calculate the area of the polar curve • Draw equivalent Circular area • Radius of the circle is the average soil resistivity • This method is particularly beneficial when the resistivity varies significantly in different directions 7/2/2013
  • 21. Inverse Slope method for 2 layer soil Resistivity 1 1.2 1.4 1.6 1.8 Spacings/apparentresistivityρa Approximate method 21 PBC Training Document PBC/ER/005 Rev 0 0 0.2 0.4 0.6 0.8 1 0 5 10 15 20 25 30 35 0.5/5=.1 1/.1=ρ2=10Ω m Spacings/apparentresistivity Spacing s in m 0.2/5=.04 1/.04=ρ1=25Ω m H=13 7/2/2013
  • 22. Sunde’s Method 22 PBC Training Document PBC/ER/005 Rev 0 7/2/2013
  • 23. BREAK 2 23 T H I N K I N G T I M E PBC Training Document PBC/ER/005 Rev 0 7/2/2013
  • 24. Essentials of Earthing Design Crossection Area Current Density Dangerous Potentials Resistance The Crossection of the conductor to be sufficient for carrying Continuous surface current density Step potential Horizontal Plane Touch potential Vertical Plane 24 PBC Training Document PBC/ER/005 Rev 0 for carrying GRID fault current Instantaneous Surface current density Mesh Potential Mutual resistance GPR Transfer Potential PASS PASS PASSPASS OK 7/2/2013
  • 25. (Clause 11.3 of IEEE 80:2000) TERMS: I – rms current in KA TCAP – Thermal capacity per unit volume in J/(cm3. 0C) Calculation of required minimum cross sectional area of grid conductor: 25 TCAP – Thermal capacity per unit volume in J/(cm . C) tc – Duration of fault current in sec αr – Thermal coefficient of resistivity at reference temperature in 1/0C ρr – Resistivity of the ground conductor at reference temperature in µ -cm Ko – 1/ α0 in 0C Tm – Maximum allowable temperature in 0C Ta – Ambient temperature in 0C Cross Sectional Area of selected grid conductor must be greater than minimum required Cross Sectional Area as required by Asymmetric fault current. 7/2/2013PBC Training Document PBC/ER/005 Rev 0
  • 26. Crossection area Equation 37 of IEEE 80 2000 The current is Symmetrical fault current Enthalpy of vaporization decreases with increase in temperature. For a large grid the fault current gets See also 26 PBC Training Document PBC/ER/005 Rev 0 For a large grid the fault current gets multiple parallel paths hence Tm doesn’t pose a problem. If the Tm is allowed to rise beyond a limit in smaller grids or pits the water molecules beyond a temperature will instantaneously vaporizes and escape from the soil surrounding the conductor. Tm also applies to surface layer coating or cover Compound At 1000C Heat of vaporizatio n (kJ mol-1) Heat of vaporizatio n (kJ kg−1) Water 40.65 2257 7/2/2013
  • 27. Calculate Grid Current (Clause 5.2.8.1 of IEEE 665:1995) TERMS: 27 TERMS: I – rms current in KA Sf – Split factor (Annex C of IEEE 80:2000) Df – Decremtent factor (Clause 5.2.5.4 of IEEE 665:1995) Cp – Corrective Projection factor The Remaining design depends on the Current that takes the ground path to return to the source. It is only a portion of 3I0. 7/2/2013PBC Training Document PBC/ER/005 Rev 0
  • 28. Long term surface CurrentsLong term surface Currents Short Term surface currentsShort Term surface currents Surface current density as per BS7340 clause 15 If surface current densities are not maintained, junction between electrode and soil, will heat up reducing moisture, failing the electrode or grid. 28 PBC Training Document PBC/ER/005 Rev 0 Long term Surface current density is 40A/m2 Independent of soil resistivity Given by the formula 1000*Sqrt (57.7/(ρ*t)) Dependent on soil resistivity and time of clearance of fault EFFECT OF COROSSION 7/2/2013
  • 29. Symbol unit Value Relay setting at 6KA 0.32Sec IG A 6000 Input Diameter of electrode d m 0.04 Input Length of Electrode Soil ls m 37 Input Water lw m 1 Input Resistivity Soil ρs Ωm 360 Input Water ρw Ωm 2 Input Resistance Soil Rs Ω 12.25394 Equation 55 IEEE 80 2000 Water Rw Ω 1.368891 Equation 55 IEEE 80 2000 Combined R Ω 1.231338 7/2/2013PBC Training Document PBC/ER/005 Rev 0 Combined Rc Ω 1.231338 Permissible Current Density Soil σs A/m2 730.9304 Clause 15.2 BS7340 Water σw A/m2 9806.46 Clause 15.2 BS7341 Area Soil As m2 4.6472 πdls Water Aw m2 0.1256 πdlw Current Division Resistance Capacity Design Soil 3396.779785 Water 1231.691433 TOTAL 4627 A 29
  • 30. Abstract of IEEE 80 2000 30 PBC Training Document PBC/ER/005 Rev 0 7/2/2013
  • 31. Abstract of IEEE 80 2000 PBC Training Document PBC/ER/005 Rev 0 7/2/201331
  • 32. Abstract of IEEE 80 2000 PBC Training Document PBC/ER/005 Rev 0 7/2/201332
  • 33. Dangerous Potentials 33 PBC Training Document PBC/ER/005 Rev 0 7/2/2013
  • 34. Voltage Variation with proximity V • The charges are distributed to the surrounding soil. • The Voltage is thus high near theV V • The Voltage is thus high near the pit and low away from it 7/2/2013PBC Training Document PBC/ER/005 Rev 0 34
  • 35. Step Potential Calculation of permissible Step Potential: (Clause 7.4 and 12.5 of IEEE 80:2000) (Clause 8.3 of IEEE 35 TERMS: ρ – Soil Resistivity in -m ρs – Soil Resistivity of additional surface layer in -m hs – Thickness of additional surface layer in m ts – Shock current duration in sec Cs – Surface layer de-rating factor (Clause 8.3 of IEEE 80:2000) (Clause 8.3 of IEEE 80:2000) 7/2/2013PBC Training Document PBC/ER/005 Rev 0
  • 36. Calculation of actual Step Potential: (Clause 16.5 of IEEE 80:2000) TERMS: ρ – Soil Resistivity in -m 36 ρ – Soil Resistivity in -m Ks – Spacing factor for step voltage Ki – Correction factor for grid geometry IG – Grid current in KA Ls – Effective length of (Lc + LR) for step voltage in m where Lc = Total length of grid conductor LR = Total length of ground rods Calculated Step Potential must be less than permissible Step Potential. 7/2/2013PBC Training Document PBC/ER/005 Rev 0
  • 37. Touch Potential Calculation of permissible Touch Potential: (Clause 7.4 and 12.5 of IEEE 80:2000) (Clause 8.3 of IEEE 37 TERMS: ρ – Soil Resistivity in -m ρs – Soil Resistivity of additional surface layer in -m hs – Thickness of additional surface layer in m ts – Shock current duration in sec Cs – Surface layer de-rating factor (Clause 8.3 of IEEE 80:2000) (Clause 8.3 of IEEE 80:2000) 7/2/2013PBC Training Document PBC/ER/005 Rev 0
  • 38. Calculation of actual Mesh Potential: (Clause 16.5 of IEEE 80:2000) TERMS: ρ – Soil Resistivity in -m Km – Spacing factor for mesh voltage 38 Km – Spacing factor for mesh voltage Ki – Correction factor for grid geometry IG – Grid current in KA LM – Effective length of (Lc + LR) for mesh voltage in m where Lc = Total length of grid conductor LR = Total length of ground rods Calculated Mesh Potential must be less than permissible Touch Potential. 7/2/2013PBC Training Document PBC/ER/005 Rev 0
  • 39. Tolerable currents by Humans Frequency based (lethal values) DC 25Hz 50/60Hz 3-10 KHz 0.5A 0.15A 0.1A high current 39 7/2/2013PBC Training Document PBC/ER/005 Rev 0 Threshold current, tingling feeling Let – go current. Can release Cannot release energized object Ventricular fibrillation 1 mA 1-6 mA 9-25 mA 60 - higher 0.5A 0.15A 0.1A high current Amplitude based
  • 40. Tolerable currents by Humans (Con.) Weight Based Time based 40 7/2/2013PBC Training Document PBC/ER/005 Rev 0
  • 41. Step potential (Permissible Value) It is the concentration of charge that creates Tension or Voltage Voltage drives the Current Permissible Estep = (1000+6Csρs)0.116/sqrt(t) Actual E < Permissible E VV Actual Estep < Permissible Estep 7/2/2013PBC Training Document PBC/ER/005 Rev 0 41
  • 42. Mesh Potential (Permissible Value) E touch is the Voltage difference between where the person is standing in the grid and GPR. E mesh is the Max E touch in a grid Permissible E touch is the voltage limit that can produce dangerous currents 42 dangerous currents E mesh < Permissible E touch Permissible E touch =(1000+1.5Csρs)0.116/sqrt(t) 7/2/2013PBC Training Document PBC/ER/005 Rev 0
  • 43. Potential Distribution Permissible Step PotentialActual Step Potential 43 PBC Training Document PBC/ER/005 Rev 0 Permissible Step Potential Dangerous Step Potential Actual Step Potential Corrected Step Potential 7/2/2013
  • 44. Abstract of IEEE 80 2000 PBC Training Document PBC/ER/005 Rev 0 7/2/201344
  • 45. Abstract of IEEE 80 2000 PBC Training Document PBC/ER/005 Rev 0 7/2/201345
  • 46. Abstract of IEEE 80 2000 PBC Training Document PBC/ER/005 Rev 0 7/2/201346
  • 47. Ring Earth •The concentric conductors reduce the resistance significantly •The reactance is reduced by tying the rings to each other at the corners •A ramp arrangement is followed burying the out conductors deeper than the inner conductors to 47 7/2/2013PBC Training Document PBC/ER/005 Rev 0 conductors deeper than the inner conductors to obtain a gradual potential curve
  • 48. Formulae to Calculate Resistance for plate earthing R = (ρ/4)* sqrt (π/2A) for pipe earthing R = (ρ/2πL)* [ln (8L/d)-1] for strip earthing R=(ρ/PπL)* [ln (2L2 /(wh))+ Q] 48 PBC Training Document PBC/ER/005 Rev 0 R=(ρ/PπL)* [ln (2L2 /(wh))+ Q] for grid earthing R=ρ[(1/LT)+ (1/sqrt (20A) (1+ (1/1+h) sqrt (20A) Is Material of the grid important for achieving resistance? No. If corrosion factor is taken care of 7/2/2013
  • 49. Variation of resistance to earth with length at different Soil resistivity 49 7/2/2013PBC Training Document PBC/ER/005 Rev 0
  • 50. Abstract of IEEE 142 50 7/2/2013PBC Training Document PBC/ER/005 Rev 0
  • 51. Effect of Resistance due to Artificial Treatment 50 60 70 80 Radius of Artificial treatment in mm Remaining percentage of resistance to remote earth 51 PBC Training Document PBC/ER/005 Rev 0 0 10 20 30 40 1 10 100 1000 10000 Series1 30 75 60 62 90 54 150 48 300 32 1500 14 7/2/2013
  • 52. Abstract of IEEE 80 2000 PBC Training Document PBC/ER/005 Rev 0 7/2/201352
  • 53. Influence of MV on LV If Rp>1, the voltage Rp*Ihmt should be less than 100V in under 500 ms 500V in under 100 ms 53 If this is not so Rp and Rn must be separate Exp. of PDS world wide 7/2/2013PBC Training Document PBC/ER/005 Rev 0
  • 54. Internationally accepted MV/LV earthing systems 7/2/2013PBC Training Document PBC/ER/005 Rev 0 54
  • 55. 7/2/2013PBC Training Document PBC/ER/005 Rev 0 55
  • 56. Measurement of Resistance of the grounding system Fall of point method 61.8% distance rule Tagg slope method Tagg intersection curve Covered in the paper 56 PBC Training Document PBC/ER/005 Rev 0 Covered in the paper already with you 7/2/2013
  • 57. Positioning of the potential probe 57 PBC Training Document PBC/ER/005 Rev 0 7/2/2013
  • 58. Essential Practices Must use insulation gear Must keep a gap of at least 6 meters between potential and current lead Must insulate any joint appearing in the lead Use meter having stray current filter. 58 PBC Training Document PBC/ER/005 Rev 0 having stray current filter. where the injected current frequencies can be changed Injected current can be made high or low depending on current probe resistance. Apply water and compact the current and potential probes to avoid undue high probe resistance. Lose potential probe can give high value of R . Avoid measuring along buried or superficial metal conductors 7/2/2013
  • 59. Fall of point method 59 PBC Training Document PBC/ER/005 Rev 0 The average of the flat part of the graph gives the give the ground impedance 7/2/2013
  • 60. 61.8% Distance Rule The reading levels of at P2 61.8% of the current probe C2 At distances lower than 61.8%, the impedance reading is lower and dips on approaching the resistance zone of the grid 60 PBC Training Document PBC/ER/005 Rev 0 resistance zone of the grid Similarly the impedance reading increases as the P2 enters the resistance zone of C2 7/2/2013
  • 61. TAGG SLOPE Method =(R3-R2)/(R2-R1) 0.4 < < 1.6 61 PBC Training Document PBC/ER/005 Rev 0 7/2/2013
  • 62. BREAK 3 62 T H I N K I N G T I M E PBC Training Document PBC/ER/005 Rev 0 7/2/2013
  • 63. Earth fault Protection Earth Fault protection in installations Selection of device for automatic disconnection Earth fault protection Devices Duration 15 min 63 Duration 15 min 7/2/2013PBC Training Document PBC/ER/005 Rev 0
  • 64. Earth Fault Protection in Installation Trip 65V in 10 Sec, and 230 V instantaneously Earth fault protection involves automatic disconnection to prevent dangerous duration and magnitude of touch voltage. The earth fault loop impedance has to be low enough to trip overcurrent protective devices. 64 trip overcurrent protective devices. Where low earth fault loop impedance cannot be achieved, disconnection may be facilitated by RCCB or Voltage operated ELCB RCD having minimum operating current greater than 30mA indirect shock risk protection RCD having minimum operating current less than 30mA direct shock risk protection 7/2/2013PBC Training Document PBC/ER/005 Rev 0
  • 65. Voltage Operated ELCBVoltage Operated ELCB RCD Current Operated ELCB RCD Current Operated ELCB Earth Fault Detection 65 Not suitable for protection of human Trip coil set to operate at 50 V 7/2/2013PBC Training Document PBC/ER/005 Rev 0
  • 66. RCD Connections 66 7/2/2013PBC Training Document PBC/ER/005 Rev 0
  • 67. IS 3043 67 7/2/2013PBC Training Document PBC/ER/005 Rev 0
  • 68. Earthing of Captive Power Plant Low voltage generators High voltage generators Duration 30 min 68 7/2/2013PBC Training Document PBC/ER/005 Rev 0
  • 69. • It should be connected to installation main earth • The main earth terminal should be connected to earth electrode • Installation should be protected by RCD • RCD cannot protect generator side of the circuit. • For mobile loads the RCD should be 30mA with tripping time of 40mS 7/2/2013PBC Training Document PBC/ER/005 Rev 0 69
  • 70. Generators above 10kW Working in parallel • To avoid flow of circulating currents, the neutral point of generator is disconnected in presence of supply 70 7/2/2013PBC Training Document PBC/ER/005 Rev 0 presence of supply neutral • Generators working in parallel, have only 1 common earth point. • 30mA RCD to be provided for protection of load side of RCD RCD
  • 71. Low voltage standby generators with neutral earthing transformers 71 7/2/2013PBC Training Document PBC/ER/005 Rev 0
  • 72. Cable Core Sheath Bonding System 72 7/2/2013PBC Training Document PBC/ER/005 Rev 0
  • 73. Statutory Provisions for Earthing Should follow Indian Electricity Rule 1956 All MV and HV equipments to be earthed by 2 separate earths Earth electrode should be devised such that testing is possible. 73 possible. The value of earth resistance should be based on degree of shock protection. No additional source to be added with out verifying the capacity of earthing system 7/2/2013PBC Training Document PBC/ER/005 Rev 0
  • 74. Bibliography IEEE 80 2000 for substation IEEE 665 1995 for Generating Station IEEE 142 1991 for Industrial establishment IEEE 81 1993 for Earthing Measurements IEEE 1100 for powering and grounding electronic equipments. IEEE 575 for sheath bonding and induced voltagesIEEE 575 for sheath bonding and induced voltages BS 7430 1998 Code of practice for Earthing IS 3043-1987 Code of practice for Earthing IEC 62305 Part 1 to Part 4 NFPA 70 and NFPA 780 API RP 2003 for statics and lightning protection And many more ref. texts 7/2/2013PBC Training Document PBC/ER/005 Rev 0 74
  • 75. S A F E T Y T H R U D E S I G N Saving life and Assets 75 T H A N K Y O U 7/2/2013PBC Training Document PBC/ER/005 Rev 0