The Sutton Oaks Pond Improvements project is located within the Cub Run Watershed. This project included restoration and improvement of the maintenance access road, extension of the existing principal spillway pipe, extension of an existing storm sewer pipe, removal of sediment from the basin, stabilization of two incoming channels, minor grading of the dam embankment, installation of a forebay using imbricated stones, and stabilization of the emergency spillway.
Pohick Creek Tributary at Greentree Village Park Stream RestorationFairfax County
The Pohick Creek Tributary at Greentree Village Park Stream Restoration project included restoration of approximately 2,500 linear feet of stream using Natural Channel Design. The project enhanced and stabilized the degraded stream channel, bed and bank, provided water quality benefits and aesthetics, and prevented further erosion. The project includes in-stream structures, realignment of a portion of the channel, engineered regenerative mix to promote groundwater recharge, fiberglass pedestrian bridge, and the re-establishment of the riparian buffer with native species.
Dead Run Stream Restoration at McLean Central Park - Segments 2 and 3Fairfax County
The project restored approximately 3,000 linear feet of stream within the Dead Run Watershed which drains directly to the Potomac River in McLean, Virginia. Restoration of the stream was achieved using natural channel design principles. The project included boulder riffles, step pools, log vanes, root wad structures, buried rock sills, reinforced stream bed material, removal of invasive plants and the re-establishment of the riparian buffer with native species.
The project included rehabilitation of approximately 1,641 linear feet of 24-inch diameter pipe with cured-in-place pipe liner and replacement of 175 linear feet of sanitary sewer pipe. Crushed glass from the I-95 Landfill Complex was used as bedding material for the pipe replacement portion of work.
Dead Run at Georgetown Pike Stream Restoration Fairfax County
Stabilize streambed and banks, ~5,600 linear feet
Reduce sediment and nutrient inputs into stream system
Installation of grade control structures, improve/correct channel dimension and alignment
Improve floodplain connectivity and ecological processes
Increase frequency and residence time of water on floodplain
Reduce force and volume of water within the channel during storm and flood events
Naturally process nutrients and sediments on the floodplain and within the streambed
Improve habitat for biological community
Native landscaping
Floodplain wetlands
Streambed and flow diversity
In-stream structures
Protect Infrastructure – Sanitary Sewer Lines
Channel Relocation away from sanitary sewer lines when possible
Armoring channel banks and bottom where relocation is not an option
Little Pimmit Run at Woodland Terrace Community Meeting 09 30-2020Fairfax County
A community meeting was held on Sept 30, 2020 to inform residents and gather information from them about the stream restoration project at Little Pimmit Run Tributary at Woodland Terrace.
Pohick Creek Tributary at Greentree Village Park Stream RestorationFairfax County
The Pohick Creek Tributary at Greentree Village Park Stream Restoration project included restoration of approximately 2,500 linear feet of stream using Natural Channel Design. The project enhanced and stabilized the degraded stream channel, bed and bank, provided water quality benefits and aesthetics, and prevented further erosion. The project includes in-stream structures, realignment of a portion of the channel, engineered regenerative mix to promote groundwater recharge, fiberglass pedestrian bridge, and the re-establishment of the riparian buffer with native species.
Dead Run Stream Restoration at McLean Central Park - Segments 2 and 3Fairfax County
The project restored approximately 3,000 linear feet of stream within the Dead Run Watershed which drains directly to the Potomac River in McLean, Virginia. Restoration of the stream was achieved using natural channel design principles. The project included boulder riffles, step pools, log vanes, root wad structures, buried rock sills, reinforced stream bed material, removal of invasive plants and the re-establishment of the riparian buffer with native species.
The project included rehabilitation of approximately 1,641 linear feet of 24-inch diameter pipe with cured-in-place pipe liner and replacement of 175 linear feet of sanitary sewer pipe. Crushed glass from the I-95 Landfill Complex was used as bedding material for the pipe replacement portion of work.
Dead Run at Georgetown Pike Stream Restoration Fairfax County
Stabilize streambed and banks, ~5,600 linear feet
Reduce sediment and nutrient inputs into stream system
Installation of grade control structures, improve/correct channel dimension and alignment
Improve floodplain connectivity and ecological processes
Increase frequency and residence time of water on floodplain
Reduce force and volume of water within the channel during storm and flood events
Naturally process nutrients and sediments on the floodplain and within the streambed
Improve habitat for biological community
Native landscaping
Floodplain wetlands
Streambed and flow diversity
In-stream structures
Protect Infrastructure – Sanitary Sewer Lines
Channel Relocation away from sanitary sewer lines when possible
Armoring channel banks and bottom where relocation is not an option
Little Pimmit Run at Woodland Terrace Community Meeting 09 30-2020Fairfax County
A community meeting was held on Sept 30, 2020 to inform residents and gather information from them about the stream restoration project at Little Pimmit Run Tributary at Woodland Terrace.
Leigh Meadow & Towlston Basin (0584DP/0103DP)Fairfax County
Leigh Meadow & Towlston Basin project was substantially completed on October 29, 2021. This project consists of 1,660 feet of stream restoration, a 22,300 cubic foot Regenerative Stormwater Conveyance (RSC) facility and a 28,500 cubic foot sand filter. The scope of work also included grading, excavation, pollution and sediment removal, and restoration planting.
South Lakes Drive Walkway was substantially completed on September 17, 2021. The project included construction of 3,370 linear feet of sidewalk, pedestrian ramps, pedestrian signals, handrail, bus shelter and loading pads, curbs and gutters, asphalt milling and paving, pavement markings and signage, fire hydrant relocation, and drainage adjustment.
The Telegraph Walkway Project was substantially completed on time and under budget on September 13, 2021. This project consisted of construction of 5’ concrete sidewalk, curb ramp, curb & gutter, drilled shaft for slope stability, RW-3, handrail, pavement mill and overlay, pavement marking, water line relocation and some other related items.
Little Pimmit Run at Chesterbrook Road Stream Restoration Project - April 2021Fairfax County
Restore up to 7,100 feet of stream channel and connecting tributaries
Reduce sediment transport
Protect existing infrastructure
Coordinate with Little Pimmit Run Sewer Realignment Project
Maintain close coordination with stakeholders
Accotink Creek at Wakefield Park Stream Restoration ProjectFairfax County
Accotink Creek at Wakefield Park Stream Restoration project was substantially completed on November 23, 2021. This project consists of restoring, enhancing, and stabilizing of approximately 4,900 linear feet of stream channel through the installation of four Newbury Riffles within the main channel of Accotink Creek and one Newbury Riffle within a side channel to provide aquatic benefits, grade control, improve water quality and prevent further erosion.
The Quander Road Walkway project was substantially completed on June 15, 2021. The project included construction of approximately 1,800 linear feet of five-foot wide concrete sidewalk along the west side of Quander Road with curb and gutter, refuge island with ramps, curb-cut ramps, driveway aprons, vast storm drainage improvements, utility relocations, asphalt pavement, pavement markings, and roadway widening to provide minimum lane widths of 11 feet between Emmett Drive and Stokes Lane.
The work on this project included investigation and repair to an 8-inch sewer line in Waterway Drive which had been previously lined with a plastic liner system. The project location was in Waterway Drive from Cavalier Court to the vicinity of Half Moon Circle. The project involved setting up a bypass system to remove sewage from the line so the pipe could be properly cleaned and inspected. Following this process, it was determined the plastic liner was causing capacity issues. It was determined that the liner could be repaired using internal methods and no excavation was needed. In addition, the five manholes associated with the segments of pipe in the project area were also rehabilitated. This project was substantially complete on June 25, 2021.
Crook Branch at Mantua Elementary School Stream Restoration Community Meeting...Fairfax County
A section of Crook Branch will be restored to accomplish the following goals:
Stabilize stream
Reduce excess sediment from being transported downstream
Reduce excess nutrients from entering the waterway
Improve aesthetics
Reduce hazards (steep, eroding banks)
Reconnect stream to floodplain
Improve Riparian Buffers
The purpose of this emergency project was to replace approximately 60-ft. segment of 8-inch wastewater sewer pipe that was broken and to retrieve a Closed-Circuit Television Inspection (CCTV) camera that was stuck in the pipe during routine maintenance work. The project was substantially complete on May 14, 2021.
Flag Run at Elgar Street Stream Restoration Project - May 24, 2017Fairfax County
The project will restore about 2,900 linear feet of the channel to stabilize the banks and prevent future erosion. A healthy ecosystem will be created by installing native trees and herbaceous plants.
Flatlick Branch Phase II Stream Restoration ProjectFairfax County
The Flatlick Branch Phase II Stream Restoration project included restoration of 4,600 linear feet of Flatlick Branch and its tributaries, provided a sustainable channel form, pattern and profile to meet today’s developed landscape, added in-stream habitat enhancement and flood plain restoration, rock structures to provide grade control throughout the channel and provide energy dissipation, and the planting of the stream areas with native vegetation.
A Closed-Circuit Television (CCTV) Camera became stuck in the sanitary sewer line located in the Old Keene Mill Shopping Center. Wastewater Design and Construction Division mobilized to the site with the on-call contractor to begin the 15-foot excavation to replace 50 feet of broken gravity sewer. Because the work was within a shopping center parking lot, the project team worked the night shift to limit disturbance to the community. After four days of work, the camera was retrieved, and the pit was backfilled. This project was substantially complete on August 27, 2021.
Pike Branch at Ridgeview Park Stream Restoration Oct 2018Fairfax County
This project will restore 2,800 feet of stream in Ridgeview Park and surrounding properties. The streambed and banks will be stabilized to reduce sediment and nutrient inputs into stream system. Improved habitat will provide better ecology.
The project consists primarily of the interior renovation and reconfiguration of an
existing one story institutional residential care facility with minor site improvements.
The building is approximately 9,500 square feet (SF) previously housing a Boys
Probation House. The renovation will provide for a Crisis Care Program providing
adult crisis stabilization treatment services through the Fairfax County Community
Services Board (CSB). The key elements of the overall project scope include:
Interior renovation with selective demolition and floor plan changes
Interior finish upgrades
New toilet rooms and existing bathroom ADA update
Building system upgrades for MEP, fire protection and security
Roofing and dormer improvements
Parking lot re-striping, new fencing and concrete pads
The Green Hill Estates Sewer Emergency project addressed a broken 8-inch sewer pipe and the erosion of the adjacent stream. The emergency was discovered during routine sewer cleaning and inspection. A break, along with several other defects, were noted in the sewer. In addition, the creek had eroded and had partially exposed the pipe. The stream was diverted and restored, and the broken pipe segment was replaced with a section of PVC pipe. The project was substantially completed August 10, 2021.
The Meadow Run (0273DP) dry pond is located within the Bull Neck Run Watershed. The project replaced a deteriorating control structure and primary spillway, increased the storage volume and incorporated water quality improvements through the use of extended detention, wetland plantings and increased travel time. The project also upgraded the maintenance access.
The Sully Basins Stormwater Pond Retrofits project was substantially completed on April 19, 2022. The project is located within the Cub Run watershed. The project consisted of repair and enhancement of multiple stormwater basins, 0326DP, 0964DP and 1484DP. The project also included construction of new stone cascades, stone weir basin structures and the construction of wetlands with high and low marsh areas. The project will facilitate improved sediment removal and improve downstream water quality using forebays and micro pools. Aquatic and natural habitat were also added within the three basins.
Leigh Meadow & Towlston Basin (0584DP/0103DP)Fairfax County
Leigh Meadow & Towlston Basin project was substantially completed on October 29, 2021. This project consists of 1,660 feet of stream restoration, a 22,300 cubic foot Regenerative Stormwater Conveyance (RSC) facility and a 28,500 cubic foot sand filter. The scope of work also included grading, excavation, pollution and sediment removal, and restoration planting.
South Lakes Drive Walkway was substantially completed on September 17, 2021. The project included construction of 3,370 linear feet of sidewalk, pedestrian ramps, pedestrian signals, handrail, bus shelter and loading pads, curbs and gutters, asphalt milling and paving, pavement markings and signage, fire hydrant relocation, and drainage adjustment.
The Telegraph Walkway Project was substantially completed on time and under budget on September 13, 2021. This project consisted of construction of 5’ concrete sidewalk, curb ramp, curb & gutter, drilled shaft for slope stability, RW-3, handrail, pavement mill and overlay, pavement marking, water line relocation and some other related items.
Little Pimmit Run at Chesterbrook Road Stream Restoration Project - April 2021Fairfax County
Restore up to 7,100 feet of stream channel and connecting tributaries
Reduce sediment transport
Protect existing infrastructure
Coordinate with Little Pimmit Run Sewer Realignment Project
Maintain close coordination with stakeholders
Accotink Creek at Wakefield Park Stream Restoration ProjectFairfax County
Accotink Creek at Wakefield Park Stream Restoration project was substantially completed on November 23, 2021. This project consists of restoring, enhancing, and stabilizing of approximately 4,900 linear feet of stream channel through the installation of four Newbury Riffles within the main channel of Accotink Creek and one Newbury Riffle within a side channel to provide aquatic benefits, grade control, improve water quality and prevent further erosion.
The Quander Road Walkway project was substantially completed on June 15, 2021. The project included construction of approximately 1,800 linear feet of five-foot wide concrete sidewalk along the west side of Quander Road with curb and gutter, refuge island with ramps, curb-cut ramps, driveway aprons, vast storm drainage improvements, utility relocations, asphalt pavement, pavement markings, and roadway widening to provide minimum lane widths of 11 feet between Emmett Drive and Stokes Lane.
The work on this project included investigation and repair to an 8-inch sewer line in Waterway Drive which had been previously lined with a plastic liner system. The project location was in Waterway Drive from Cavalier Court to the vicinity of Half Moon Circle. The project involved setting up a bypass system to remove sewage from the line so the pipe could be properly cleaned and inspected. Following this process, it was determined the plastic liner was causing capacity issues. It was determined that the liner could be repaired using internal methods and no excavation was needed. In addition, the five manholes associated with the segments of pipe in the project area were also rehabilitated. This project was substantially complete on June 25, 2021.
Crook Branch at Mantua Elementary School Stream Restoration Community Meeting...Fairfax County
A section of Crook Branch will be restored to accomplish the following goals:
Stabilize stream
Reduce excess sediment from being transported downstream
Reduce excess nutrients from entering the waterway
Improve aesthetics
Reduce hazards (steep, eroding banks)
Reconnect stream to floodplain
Improve Riparian Buffers
The purpose of this emergency project was to replace approximately 60-ft. segment of 8-inch wastewater sewer pipe that was broken and to retrieve a Closed-Circuit Television Inspection (CCTV) camera that was stuck in the pipe during routine maintenance work. The project was substantially complete on May 14, 2021.
Flag Run at Elgar Street Stream Restoration Project - May 24, 2017Fairfax County
The project will restore about 2,900 linear feet of the channel to stabilize the banks and prevent future erosion. A healthy ecosystem will be created by installing native trees and herbaceous plants.
Flatlick Branch Phase II Stream Restoration ProjectFairfax County
The Flatlick Branch Phase II Stream Restoration project included restoration of 4,600 linear feet of Flatlick Branch and its tributaries, provided a sustainable channel form, pattern and profile to meet today’s developed landscape, added in-stream habitat enhancement and flood plain restoration, rock structures to provide grade control throughout the channel and provide energy dissipation, and the planting of the stream areas with native vegetation.
A Closed-Circuit Television (CCTV) Camera became stuck in the sanitary sewer line located in the Old Keene Mill Shopping Center. Wastewater Design and Construction Division mobilized to the site with the on-call contractor to begin the 15-foot excavation to replace 50 feet of broken gravity sewer. Because the work was within a shopping center parking lot, the project team worked the night shift to limit disturbance to the community. After four days of work, the camera was retrieved, and the pit was backfilled. This project was substantially complete on August 27, 2021.
Pike Branch at Ridgeview Park Stream Restoration Oct 2018Fairfax County
This project will restore 2,800 feet of stream in Ridgeview Park and surrounding properties. The streambed and banks will be stabilized to reduce sediment and nutrient inputs into stream system. Improved habitat will provide better ecology.
The project consists primarily of the interior renovation and reconfiguration of an
existing one story institutional residential care facility with minor site improvements.
The building is approximately 9,500 square feet (SF) previously housing a Boys
Probation House. The renovation will provide for a Crisis Care Program providing
adult crisis stabilization treatment services through the Fairfax County Community
Services Board (CSB). The key elements of the overall project scope include:
Interior renovation with selective demolition and floor plan changes
Interior finish upgrades
New toilet rooms and existing bathroom ADA update
Building system upgrades for MEP, fire protection and security
Roofing and dormer improvements
Parking lot re-striping, new fencing and concrete pads
The Green Hill Estates Sewer Emergency project addressed a broken 8-inch sewer pipe and the erosion of the adjacent stream. The emergency was discovered during routine sewer cleaning and inspection. A break, along with several other defects, were noted in the sewer. In addition, the creek had eroded and had partially exposed the pipe. The stream was diverted and restored, and the broken pipe segment was replaced with a section of PVC pipe. The project was substantially completed August 10, 2021.
The Meadow Run (0273DP) dry pond is located within the Bull Neck Run Watershed. The project replaced a deteriorating control structure and primary spillway, increased the storage volume and incorporated water quality improvements through the use of extended detention, wetland plantings and increased travel time. The project also upgraded the maintenance access.
The Sully Basins Stormwater Pond Retrofits project was substantially completed on April 19, 2022. The project is located within the Cub Run watershed. The project consisted of repair and enhancement of multiple stormwater basins, 0326DP, 0964DP and 1484DP. The project also included construction of new stone cascades, stone weir basin structures and the construction of wetlands with high and low marsh areas. The project will facilitate improved sediment removal and improve downstream water quality using forebays and micro pools. Aquatic and natural habitat were also added within the three basins.
Scotts Run Tributary at Windy Hill Road Stream StabilizationFairfax County
This stream stabilization is located within the Scotts Run Watershed in McLean, Va. The project restored 600 feet of intermittent stream using natural channel design, installed a new drop inlet, 32 linear feet of 36-inch diameter reinforced concrete pipe, an end wall at Box Elder Court, and installation of instream structures such as rock weir, imbricated toe protection, step pools, reinforced bed material.
Project Description:
The Newington Commons Pond Improvement Project has been Substantially Completed. The purpose of this project was the restoration of approximately 351 linear feet of stream and improvement of the receiving stormwater pond.
Project Overview:
Dredging of the pond to increase storage volume
Replacement of the concrete riser structure
Restoration of stream channels utilizing natural channel design
Bull Neck Run at Spring Hill Recreation Center Stream RestorationFairfax County
The project site is situated east of Springhill Road, north of Lewinsville Road, and south of Old Dominion Drive. This project included restoring approximately 2,000 linear feet of the Bull Neck stream channel and tributaries which drain directly to the Potomac River in Mclean, Virginia. Restoration of the stream was achieved using natural channel design principles. The project included rock sill, boulder toe protection, buried rock toe, riffle with log sill, step pools, boulder clusters, modified cross vanes with woody debris, removal of invasive plants and the re-establishment of the riparian buffer with native species.
Long Branch Tributary at Long Branch Falls ParkFairfax County
The Long Branch Tributary at Long Branch Falls Park project restored approximately 670 linear feet of stream within the Accotink Creek watershed. The stream channel was enhanced and stabilized using natural channel design elements. Existing erosion damage was repaired and future water quality has been improved. The project included channel realignment, in-stream rock structures, log structures, constructed wetlands, wood habitat clusters, deer exclusion fence, removal of invasive plants and the re-establishment of the riparian buffer with native species.
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationFairfax County
Scotts Run @ Old Meadow Road Stream Restoration was substantially completed on March 30, 2022. The Scotts Run project consisted of restoring, enhancement, and stabilizing of approximately 2,930 linear feet of eroding stream using Natural Channel Design criteria. This project included two phases: Phase I was funded by proffers from a private development and Phase II was County funded. Also included was the removal of invasive non-native plants and the installation of new plantings to stabilize the stream and floodplain.
Flatlick Branch III Stream Restoration June 6, 2020Fairfax County
The Flatlick Branch Phase III Stream Stabilization Project was substantially completed on April 10, 2020. The project aims to stabilize approximately 4000 linear feet of degraded stream channel from Walney Road to the culvert at Route 28 in Fairfax County and improve the water quality of the channel and downstream receiving waters.
The Oakton Community Park Phase 2A project consisted of a new reinforced concrete roundabout, concrete and asphalt sidewalks, curb ramps, concrete medians, and curb and gutter. The scope of work also included storm drainage, site improvements, asphalt restoration, pavement markings and other associated work.
Merrifield Nursery Emergency Gravity Sewer ReplacementFairfax County
During a routine Closed-Circuit Television (CCTV) Camera inspection by Wastewater Collection Division (WCD), it was found that 45 linear feet of 8-inch asbestos reinforced concrete pipe (RCP) between MH-292 to MH-291 was within imminent danger of failing. The bottom of the RCP was missing within the 45 linear feet of repair and the pipe was on the verge of surcharging. After an immediate pre-construction meeting with Merrifield Nursery, it was agreed to work from 6pm-10am everyday of the week to avoid disruption and potentially placing patrons at risk during the biggest time of the year for Merrifield Garden Center. The contractor mobilized to the site and began the 20-foot excavation to replace 45 linear feet of broken gravity sewer. The project started on March 14th, 2022 and was substantially complete on March 23, 2022.
Clarks Crossing Road Improvements 05-13-22Fairfax County
The Clarks Crossing Road Pedestrian Access Improvement project improved the pedestrian and bicycle access along Clarks Crossing Road and was substantially completed on March 23, 2022.
This project completed the missing link between the existing sidewalk at Brookside Lane and the previously constructed sidewalk along Clarks Crossing Road. The scope of this project included construction of asphalt sidewalk, curb ramps, curb and gutter, drainage improvements along Brookside Lane and asphalt mill/overlay on Clarks Crossing and Brookside Lane.
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxFairfax County
Future wastewater flows in northern Fairfax County exceed existing system capacity
Treatment capacity is available in Noman M. Cole Jr. Pollution Control Plant in Lorton, VA
New pipes and pumps are needed to move future flows to treatment plant
NEXT STEPS
Field investigations / surveys
Finalize alignments and pump station layout
Use of open cut excavation
Use of trenchless methods
Easement acquisition needed
Develop traffic control plans
Description:
The project consists of a new, 23,000 square feet, two-story, four-bay fire station facility and associated improvements to the 3.3-acre site including storm water detention, landscaping and parking. The scope also included the demolition of the existing fire station, and a temporary fire station to house the Fire and Rescue Department during construction of the new facility. The key elements of the overall project include:
Riverwood Community Meeting - 04-14-2022- Presentation.pptxFairfax County
The new 4-inch ductile iron force main will serve the surrounding community for the foreseeable future. Replacement of the force main will:
Reduce the level and frequency of maintenance required to keep the force main operating.
Prevent costly emergency repairs.
Provide residents with safe, reliable utility infrastructure.
Enhance the quality of life for residents.
Reduce risks to public health and the environment.
Burke Centre VRE Connector Phase IV project was substantially completed on March 7, 2022. This project enhanced the access to mass transit by creating a more direct connection from the VRE Station to the residential areas west of Premier Court. This project also connects the Oak Bluff community to the Virginia Rail Express (VRE) Burke Station and provides a multi-use shared pedestrian and bicycle trail for outdoor recreation.
Long Branch Public Meeting - FINAL - 04-11-2022Fairfax County
Overarching Project Goals:
-Achieve Long Branch Central TMDL waste load reduction requirements.
-Provide long-term stability and have low maintenance.
-Improve water quality within the Long Branch Central Watershed.
-Improve habitat and environmental health (ecological lift).
Objectives: Share our project understanding with the council and seek input on the unique opportunities and housing goals for this site that could help guide
our master planning process.
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptxFairfax County
4,800 linear feet of stream will be restored using Natural Channel Design methodologies
Pollutant reduction
1,439 lbs/total phosphorus
3,400 lbs/total nitrogen
462.1 tons of total suspended sediment
Protection of private property and public infrastructure
Increased ecological diversity with native vegetation
DEQ has awarded a SLAF grant to this project for these environmental benefits
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT Fairfax County
The Lake Barton Dredging, Restoration, and Riser Modification project was substantially completed on December 29, 2021. The project is located within the Pohick Creek watershed. The project consisted of dredging and removal of approximately 19,100 cubic yards of sediment to restore the sediment trapping capacity and improve water quality. The project also included construction of new sediment forebays, in-lake haul roads, and riser modifications (new mid-level sluice gate and cold-water intake) to facilitate future maintenance, stabilize the shoreline, and improve downstream water quality. Fish habitat was also added within the lake.
Reston Arts Community Center Feasibility - Wrap UpFairfax County
This is the last of 5 engagement meetings. We are excited to report back what we heard from you – your preferences, priorities, questions, hopes, concerns. The information we received will be used to inform the space allocations and cost estimating for discussion of the proffer by Fairfax County.
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Fairfax County
Benefits of Consolidated Facility
Building and Site Efficiencies
Operational Efficiencies
Addresses Space Deficiencies
Addresses Renovations and Capital Renewal Requirements
for WCD
Provides for a Centrally Located Site that Accommodates Program
Consolidates Integrated Services on One Centrally Located Site
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Fairfax County
This is the 4th of 5 engagement meetings. We are excited to hear from you – your preferences, priorities, questions, hopes, concerns. The information we receive today will be used to inform the space allocations and cost estimating for discussion of the proffer by Fairfax County.
Oak Marr Pump Station Rehabilitation – Construction ProjectFairfax County
Neighborhood was built in the 1980s, and the sewer infrastructure has been in operation since.
Aged pump station equipment – pumps, valves, fans, concrete, etc.
This aging equipment has the potential of causing:
Sanitary Sewer Overflows (SSO)
Sewer back-ups into homes
Environmental damages
Maintenance problems
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Fairfax County
Identify and evaluate house flooding and public safety concerns
Improve drainage conditions to convey 100-year storm if feasible
Reduce and treat stormwater runoff at the source
Improve water quality and stream protection
Use resilient & functional designs
Make improvements compatible with characteristics of neighborhood
Partner with community to develop sound, cost effective solutions that can be collaboratively implemented and maintained
Build on lessons learned to help improve site development process for infill development
Reston Arts Center Feasibility - Focus Group Visual ArtsFairfax County
These community outreach meetings are being conducted to understand community needs for a proposed arts venue in the Reston Town Center.
The proposed arts center would be a result of a proffer from Boston Properties in the next phase of Reston Town Center development (Block J).
The proffer would provide for an approximately 60,000 gross square foot facility to house a stage suitable for large-scale music and dance performances, as well as other arts-related amenities.
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022Fairfax County
These community outreach meetings are being conducted to understand community needs for a proposed arts venue in the Reston Town Center.
The proposed arts center would be a result of a proffer from Boston Properties in the next phase of Reston Town Center development (Block J).
The proffer would provide for an approximately 60,000 gross square foot facility to house a stage suitable for large-scale music and dance performances, as well as other arts-related amenities.
The project consists of a new 17,400 square feet, two-story, four-bay fire station facility and associated improvements to the one-acre site including stormwater detention, landscaping, and parking. The scope also included the demolition of the existing two and a half bay facility, and construction of a temporary fire station to house the Fire and Rescue Department during construction of the new facility. The key elements include:
Apparatus Bays, Control Room and Offices
Battalion Chief Suite
Kitchen, Dayroom, and Dining Room
Bunk Rooms
Showers and Locker Rooms
Exercise Room
Ready Gear Room
Natural farming @ Dr. Siddhartha S. Jena.pptxsidjena70
A brief about organic farming/ Natural farming/ Zero budget natural farming/ Subash Palekar Natural farming which keeps us and environment safe and healthy. Next gen Agricultural practices of chemical free farming.
UNDERSTANDING WHAT GREEN WASHING IS!.pdfJulietMogola
Many companies today use green washing to lure the public into thinking they are conserving the environment but in real sense they are doing more harm. There have been such several cases from very big companies here in Kenya and also globally. This ranges from various sectors from manufacturing and goes to consumer products. Educating people on greenwashing will enable people to make better choices based on their analysis and not on what they see on marketing sites.
Characterization and the Kinetics of drying at the drying oven and with micro...Open Access Research Paper
The objective of this work is to contribute to valorization de Nephelium lappaceum by the characterization of kinetics of drying of seeds of Nephelium lappaceum. The seeds were dehydrated until a constant mass respectively in a drying oven and a microwawe oven. The temperatures and the powers of drying are respectively: 50, 60 and 70°C and 140, 280 and 420 W. The results show that the curves of drying of seeds of Nephelium lappaceum do not present a phase of constant kinetics. The coefficients of diffusion vary between 2.09.10-8 to 2.98. 10-8m-2/s in the interval of 50°C at 70°C and between 4.83×10-07 at 9.04×10-07 m-8/s for the powers going of 140 W with 420 W the relation between Arrhenius and a value of energy of activation of 16.49 kJ. mol-1 expressed the effect of the temperature on effective diffusivity.
Willie Nelson Net Worth: A Journey Through Music, Movies, and Business Venturesgreendigital
Willie Nelson is a name that resonates within the world of music and entertainment. Known for his unique voice, and masterful guitar skills. and an extraordinary career spanning several decades. Nelson has become a legend in the country music scene. But, his influence extends far beyond the realm of music. with ventures in acting, writing, activism, and business. This comprehensive article delves into Willie Nelson net worth. exploring the various facets of his career that have contributed to his large fortune.
Follow us on: Pinterest
Introduction
Willie Nelson net worth is a testament to his enduring influence and success in many fields. Born on April 29, 1933, in Abbott, Texas. Nelson's journey from a humble beginning to becoming one of the most iconic figures in American music is nothing short of inspirational. His net worth, which estimated to be around $25 million as of 2024. reflects a career that is as diverse as it is prolific.
Early Life and Musical Beginnings
Humble Origins
Willie Hugh Nelson was born during the Great Depression. a time of significant economic hardship in the United States. Raised by his grandparents. Nelson found solace and inspiration in music from an early age. His grandmother taught him to play the guitar. setting the stage for what would become an illustrious career.
First Steps in Music
Nelson's initial foray into the music industry was fraught with challenges. He moved to Nashville, Tennessee, to pursue his dreams, but success did not come . Working as a songwriter, Nelson penned hits for other artists. which helped him gain a foothold in the competitive music scene. His songwriting skills contributed to his early earnings. laying the foundation for his net worth.
Rise to Stardom
Breakthrough Albums
The 1970s marked a turning point in Willie Nelson's career. His albums "Shotgun Willie" (1973), "Red Headed Stranger" (1975). and "Stardust" (1978) received critical acclaim and commercial success. These albums not only solidified his position in the country music genre. but also introduced his music to a broader audience. The success of these albums played a crucial role in boosting Willie Nelson net worth.
Iconic Songs
Willie Nelson net worth is also attributed to his extensive catalog of hit songs. Tracks like "Blue Eyes Crying in the Rain," "On the Road Again," and "Always on My Mind" have become timeless classics. These songs have not only earned Nelson large royalties but have also ensured his continued relevance in the music industry.
Acting and Film Career
Hollywood Ventures
In addition to his music career, Willie Nelson has also made a mark in Hollywood. His distinctive personality and on-screen presence have landed him roles in several films and television shows. Notable appearances include roles in "The Electric Horseman" (1979), "Honeysuckle Rose" (1980), and "Barbarosa" (1982). These acting gigs have added a significant amount to Willie Nelson net worth.
Television Appearances
Nelson's char
"Understanding the Carbon Cycle: Processes, Human Impacts, and Strategies for...MMariSelvam4
The carbon cycle is a critical component of Earth's environmental system, governing the movement and transformation of carbon through various reservoirs, including the atmosphere, oceans, soil, and living organisms. This complex cycle involves several key processes such as photosynthesis, respiration, decomposition, and carbon sequestration, each contributing to the regulation of carbon levels on the planet.
Human activities, particularly fossil fuel combustion and deforestation, have significantly altered the natural carbon cycle, leading to increased atmospheric carbon dioxide concentrations and driving climate change. Understanding the intricacies of the carbon cycle is essential for assessing the impacts of these changes and developing effective mitigation strategies.
By studying the carbon cycle, scientists can identify carbon sources and sinks, measure carbon fluxes, and predict future trends. This knowledge is crucial for crafting policies aimed at reducing carbon emissions, enhancing carbon storage, and promoting sustainable practices. The carbon cycle's interplay with climate systems, ecosystems, and human activities underscores its importance in maintaining a stable and healthy planet.
In-depth exploration of the carbon cycle reveals the delicate balance required to sustain life and the urgent need to address anthropogenic influences. Through research, education, and policy, we can work towards restoring equilibrium in the carbon cycle and ensuring a sustainable future for generations to come.
1. A Fairfax County, VA, publication
Department of Public Works and Environmental Services
Working for You!
Contract No. CN19125216
Project No. SD-000033-064
Sully District
Tax Map No. 044-4-((04))-A
May 9, 2019
Sutton Oaks Pond (0133DP)
Improvements
2. Sutton Oaks Pond (0133DP) Improvements
Capital Facilities/Utilities Design and Construction Division, Stormwater Construction Branch
3. Project Details
Sutton Oaks Pond (0133DP) Improvements
Capital Facilities/Utilities Design and Construction Division, Stormwater Construction Branch
Description:
The Sutton Oaks Pond (0133DP) Improvements project has been substantially completed. The site is located within the Cub Run
Watershed. This project included restoration and improvement of the maintenance access road, extension of the existing spillway
pipe, extension of an existing storm sewer pipe, removal of sediment from the basin, stabilization of two incoming channels,
minor grading of the dam embankment, installation of a forebay using imbricated stones, and stabilization of the emergency
spillway.
Project Benefits:
• Restored basin to original design parameters
• Provides dam safety improvements
• Provides safe access to basin for maintenance staff
• Prevents the erosion of two incoming channels
• Forebay will collect debris and sediment to ease future maintenance
Project Team:
• Project Manager - Ganesh Thapa, Maintenance and Stormwater Management Division
• Construction Manager - Scott Bishop, Utilities Design and Construction Division (UDCD)
• Construction Inspector - Bharat Khanal, UDCD
• Project Inspector - Tony Wall, Land Development Services
4. Sutton Oaks Pond (0133DP) Improvements
Capital Facilities/Utilities Design and Construction Division, Stormwater Construction Branch
Poplar Tree Road, Tax Map No. 44-4
PROJECT
SITE
0133DP
5. Before After
Maintenance Access
Capital Facilities/Utilities Design and Construction Division, Stormwater Construction Branch
Sutton Oaks Pond (0133DP) Improvements
7. Before After
Pond Floor
Capital Facilities/Utilities Design and Construction Division, Stormwater Construction Branch
Sutton Oaks Pond (0133DP) Improvements
8. Additional Information
For additional Information, please call
www.fairfaxcounty.gov/publicworks
Capital Facilities/Utilities Design and Construction Division, Stormwater Construction Branch
Matthew Kaiser, Public Information Officer
703-324-8455, TTY 711
Matthew.Kaiser@fairfaxcounty.gov
Sutton Oaks Pond (0133DP) Improvements