Restore up to 7,100 feet of stream channel and connecting tributaries
Reduce sediment transport
Protect existing infrastructure
Coordinate with Little Pimmit Run Sewer Realignment Project
Maintain close coordination with stakeholders
Little Pimmit Run at Chesterbrook Stream Restoration Project and Little Pimmi...Fairfax County
Restore up to 7,500 feet of stream channel and tributaries
Reduce erosion and sediment transport
Install new sanitary sewers serving over 500 single family homes
Improve watershed conditions and reduce downstream impacts
Improve and protect public infrastructure
Prevent costly emergency repairs
Reduce risk to public health and the environment
Maintain close coordination with stakeholders and community
Build partnerships with local organizations
Franklin Park Chesterbrook Neighborhood Project HighlightsFairfax County
This project included 3,000 linear feet of stormwater improvements that promote infiltration, improve water quality, and safely convey stormwater through the neighborhood to a stream.
The project included rehabilitation of approximately 1,641 linear feet of 24-inch diameter pipe with cured-in-place pipe liner and replacement of 175 linear feet of sanitary sewer pipe. Crushed glass from the I-95 Landfill Complex was used as bedding material for the pipe replacement portion of work.
Dead Run at Georgetown Pike Stream Restoration Fairfax County
Stabilize streambed and banks, ~5,600 linear feet
Reduce sediment and nutrient inputs into stream system
Installation of grade control structures, improve/correct channel dimension and alignment
Improve floodplain connectivity and ecological processes
Increase frequency and residence time of water on floodplain
Reduce force and volume of water within the channel during storm and flood events
Naturally process nutrients and sediments on the floodplain and within the streambed
Improve habitat for biological community
Native landscaping
Floodplain wetlands
Streambed and flow diversity
In-stream structures
Protect Infrastructure – Sanitary Sewer Lines
Channel Relocation away from sanitary sewer lines when possible
Armoring channel banks and bottom where relocation is not an option
Little Pimmit Run at Woodland Terrace Community Meeting 09 30-2020Fairfax County
A community meeting was held on Sept 30, 2020 to inform residents and gather information from them about the stream restoration project at Little Pimmit Run Tributary at Woodland Terrace.
Cameron Run Tributary At La Vista Drive: Stream RestorationFairfax County
Anticipated Schedule for Construction (estimate 34 weeks)
Restoration schedules can overlap with multiple crews
Plantings occur in spring, fall, and/or winter (live stakes) seasons
Includes 1-year warranty on structures and vegetation
Vegetation warranty starts when planting ends (may be delayed for season)
Little Pimmit Run at Chesterbrook Stream Restoration Project and Little Pimmi...Fairfax County
Restore up to 7,500 feet of stream channel and tributaries
Reduce erosion and sediment transport
Install new sanitary sewers serving over 500 single family homes
Improve watershed conditions and reduce downstream impacts
Improve and protect public infrastructure
Prevent costly emergency repairs
Reduce risk to public health and the environment
Maintain close coordination with stakeholders and community
Build partnerships with local organizations
Franklin Park Chesterbrook Neighborhood Project HighlightsFairfax County
This project included 3,000 linear feet of stormwater improvements that promote infiltration, improve water quality, and safely convey stormwater through the neighborhood to a stream.
The project included rehabilitation of approximately 1,641 linear feet of 24-inch diameter pipe with cured-in-place pipe liner and replacement of 175 linear feet of sanitary sewer pipe. Crushed glass from the I-95 Landfill Complex was used as bedding material for the pipe replacement portion of work.
Dead Run at Georgetown Pike Stream Restoration Fairfax County
Stabilize streambed and banks, ~5,600 linear feet
Reduce sediment and nutrient inputs into stream system
Installation of grade control structures, improve/correct channel dimension and alignment
Improve floodplain connectivity and ecological processes
Increase frequency and residence time of water on floodplain
Reduce force and volume of water within the channel during storm and flood events
Naturally process nutrients and sediments on the floodplain and within the streambed
Improve habitat for biological community
Native landscaping
Floodplain wetlands
Streambed and flow diversity
In-stream structures
Protect Infrastructure – Sanitary Sewer Lines
Channel Relocation away from sanitary sewer lines when possible
Armoring channel banks and bottom where relocation is not an option
Little Pimmit Run at Woodland Terrace Community Meeting 09 30-2020Fairfax County
A community meeting was held on Sept 30, 2020 to inform residents and gather information from them about the stream restoration project at Little Pimmit Run Tributary at Woodland Terrace.
Cameron Run Tributary At La Vista Drive: Stream RestorationFairfax County
Anticipated Schedule for Construction (estimate 34 weeks)
Restoration schedules can overlap with multiple crews
Plantings occur in spring, fall, and/or winter (live stakes) seasons
Includes 1-year warranty on structures and vegetation
Vegetation warranty starts when planting ends (may be delayed for season)
Crook Branch at Mantua Elementary School Stream Restoration Community Meeting...Fairfax County
A section of Crook Branch will be restored to accomplish the following goals:
Stabilize stream
Reduce excess sediment from being transported downstream
Reduce excess nutrients from entering the waterway
Improve aesthetics
Reduce hazards (steep, eroding banks)
Reconnect stream to floodplain
Improve Riparian Buffers
Lakevale Estates Collection Improvements Community MeetingFairfax County
Short-term: Install Backflow Devices
Devices installed
Regular system maintenance is ongoing
Mid-term: Temporary modifications to the Lakevale Pump Station
Updated pump operating strategy
Replaced pump impeller to reduce pump station capacity
Flag Run at Elgar Street Stream Restoration Project - May 24, 2017Fairfax County
The project will restore about 2,900 linear feet of the channel to stabilize the banks and prevent future erosion. A healthy ecosystem will be created by installing native trees and herbaceous plants.
Dead Run Stream Restoration at McLean Central Park - Segments 2 and 3Fairfax County
The project restored approximately 3,000 linear feet of stream within the Dead Run Watershed which drains directly to the Potomac River in McLean, Virginia. Restoration of the stream was achieved using natural channel design principles. The project included boulder riffles, step pools, log vanes, root wad structures, buried rock sills, reinforced stream bed material, removal of invasive plants and the re-establishment of the riparian buffer with native species.
Tucker Avenue Neighborhood Stormwater Improvement Preliminary Design ReviewFairfax County
Identify and evaluate house flooding and public safety concerns
Improve drainage conditions to convey 100-year storm if feasible
Reduce and treat stormwater runoff at the source
Improve water quality and stream protection
Use innovative & functional designs
Make improvements compatible with characteristics of neighborhood
Partner with community to develop sound, cost effective solutions that can be collaboratively implemented and maintained
Build on lessons learned to help improve site development process for infill development
Pohick Creek Tributary at Greentree Village Park Stream RestorationFairfax County
The Pohick Creek Tributary at Greentree Village Park Stream Restoration project included restoration of approximately 2,500 linear feet of stream using Natural Channel Design. The project enhanced and stabilized the degraded stream channel, bed and bank, provided water quality benefits and aesthetics, and prevented further erosion. The project includes in-stream structures, realignment of a portion of the channel, engineered regenerative mix to promote groundwater recharge, fiberglass pedestrian bridge, and the re-establishment of the riparian buffer with native species.
The Sutton Oaks Pond Improvements project is located within the Cub Run Watershed. This project included restoration and improvement of the maintenance access road, extension of the existing principal spillway pipe, extension of an existing storm sewer pipe, removal of sediment from the basin, stabilization of two incoming channels, minor grading of the dam embankment, installation of a forebay using imbricated stones, and stabilization of the emergency spillway.
Restore ~4,000 feet by returning the form and function of the channel to dynamic equilibrium and improve the ecological processes of the riparian corridor.
Difficult Run at Brittenford Drive Information Meeting May 17, 2017Fairfax County
This project will mitigate flooding, reduce erosion, and protect public and private property. Approximately 3,000 feet of the main channel and 1,500 feet of tributaries will be restored.
Pike Branch at Ridgeview Park Stream Restoration Oct 2018Fairfax County
This project will restore 2,800 feet of stream in Ridgeview Park and surrounding properties. The streambed and banks will be stabilized to reduce sediment and nutrient inputs into stream system. Improved habitat will provide better ecology.
Long Branch at Arlington Boulevard and Robin Ridge Court - Concept Design and...Fairfax County
Restore streambed and banks, ~4,500 linear feet
Reduce sediment and nutrient inputs into stream system
Installation of grade control structures, improve/correct channel dimension and alignment
Improve floodplain connectivity and ecological processes
Reduce force and volume of water within the channel during storm and flood events
Naturally process nutrients and sediments on the floodplain and within the streambed
Improve habitat for biological community
Native landscaping
Floodplain wetlands
Streambed and flow diversity
In-stream structures
Protect Infrastructure – Sanitary Sewer Lines
Channel Relocation away from sanitary sewer lines when possible
Armoring channel banks and bottom where relocation is not an option
Little Pimmit Run at Woodland Terrace Community Meeting Sept. 30 2020Fairfax County
1. Restore up to 1,000 feet of stream channel
– Reduce sediment restricting flow in the drainage system
2. Improve drainage at the North Albemarle St. and Chesterbrook Rd. intersection
– Maximize efficiency of drainage system
3. Maintain close coordination with stakeholders
Paul Spring Branch at Sherwood Hall Stream Restoration ProjectFairfax County
The plan is to return the form and function of the channel to dynamic equilibrium and improve the ecological processes of the riparian corridor within the constraints of the developed landscape.
Crook Branch at Mantua Elementary School Stream Restoration Community Meeting...Fairfax County
A section of Crook Branch will be restored to accomplish the following goals:
Stabilize stream
Reduce excess sediment from being transported downstream
Reduce excess nutrients from entering the waterway
Improve aesthetics
Reduce hazards (steep, eroding banks)
Reconnect stream to floodplain
Improve Riparian Buffers
Lakevale Estates Collection Improvements Community MeetingFairfax County
Short-term: Install Backflow Devices
Devices installed
Regular system maintenance is ongoing
Mid-term: Temporary modifications to the Lakevale Pump Station
Updated pump operating strategy
Replaced pump impeller to reduce pump station capacity
Flag Run at Elgar Street Stream Restoration Project - May 24, 2017Fairfax County
The project will restore about 2,900 linear feet of the channel to stabilize the banks and prevent future erosion. A healthy ecosystem will be created by installing native trees and herbaceous plants.
Dead Run Stream Restoration at McLean Central Park - Segments 2 and 3Fairfax County
The project restored approximately 3,000 linear feet of stream within the Dead Run Watershed which drains directly to the Potomac River in McLean, Virginia. Restoration of the stream was achieved using natural channel design principles. The project included boulder riffles, step pools, log vanes, root wad structures, buried rock sills, reinforced stream bed material, removal of invasive plants and the re-establishment of the riparian buffer with native species.
Tucker Avenue Neighborhood Stormwater Improvement Preliminary Design ReviewFairfax County
Identify and evaluate house flooding and public safety concerns
Improve drainage conditions to convey 100-year storm if feasible
Reduce and treat stormwater runoff at the source
Improve water quality and stream protection
Use innovative & functional designs
Make improvements compatible with characteristics of neighborhood
Partner with community to develop sound, cost effective solutions that can be collaboratively implemented and maintained
Build on lessons learned to help improve site development process for infill development
Pohick Creek Tributary at Greentree Village Park Stream RestorationFairfax County
The Pohick Creek Tributary at Greentree Village Park Stream Restoration project included restoration of approximately 2,500 linear feet of stream using Natural Channel Design. The project enhanced and stabilized the degraded stream channel, bed and bank, provided water quality benefits and aesthetics, and prevented further erosion. The project includes in-stream structures, realignment of a portion of the channel, engineered regenerative mix to promote groundwater recharge, fiberglass pedestrian bridge, and the re-establishment of the riparian buffer with native species.
The Sutton Oaks Pond Improvements project is located within the Cub Run Watershed. This project included restoration and improvement of the maintenance access road, extension of the existing principal spillway pipe, extension of an existing storm sewer pipe, removal of sediment from the basin, stabilization of two incoming channels, minor grading of the dam embankment, installation of a forebay using imbricated stones, and stabilization of the emergency spillway.
Restore ~4,000 feet by returning the form and function of the channel to dynamic equilibrium and improve the ecological processes of the riparian corridor.
Difficult Run at Brittenford Drive Information Meeting May 17, 2017Fairfax County
This project will mitigate flooding, reduce erosion, and protect public and private property. Approximately 3,000 feet of the main channel and 1,500 feet of tributaries will be restored.
Pike Branch at Ridgeview Park Stream Restoration Oct 2018Fairfax County
This project will restore 2,800 feet of stream in Ridgeview Park and surrounding properties. The streambed and banks will be stabilized to reduce sediment and nutrient inputs into stream system. Improved habitat will provide better ecology.
Long Branch at Arlington Boulevard and Robin Ridge Court - Concept Design and...Fairfax County
Restore streambed and banks, ~4,500 linear feet
Reduce sediment and nutrient inputs into stream system
Installation of grade control structures, improve/correct channel dimension and alignment
Improve floodplain connectivity and ecological processes
Reduce force and volume of water within the channel during storm and flood events
Naturally process nutrients and sediments on the floodplain and within the streambed
Improve habitat for biological community
Native landscaping
Floodplain wetlands
Streambed and flow diversity
In-stream structures
Protect Infrastructure – Sanitary Sewer Lines
Channel Relocation away from sanitary sewer lines when possible
Armoring channel banks and bottom where relocation is not an option
Little Pimmit Run at Woodland Terrace Community Meeting Sept. 30 2020Fairfax County
1. Restore up to 1,000 feet of stream channel
– Reduce sediment restricting flow in the drainage system
2. Improve drainage at the North Albemarle St. and Chesterbrook Rd. intersection
– Maximize efficiency of drainage system
3. Maintain close coordination with stakeholders
Paul Spring Branch at Sherwood Hall Stream Restoration ProjectFairfax County
The plan is to return the form and function of the channel to dynamic equilibrium and improve the ecological processes of the riparian corridor within the constraints of the developed landscape.
Little Pimmit Run at Chesterbrook Road Stream Restoration and Sanitary Reali...Fairfax County
Chesterbrook Road Emergency Project – Summer 2019
Final Scoping Technical Memorandum – January 2020
Professional Services Contract Execution – April 2021
Community Meeting on stream restoration Pre-design/Channel alignments – April 2021
Final Preliminary Engineering Report – October 2021
Community Meeting on Sanitary Realignment Preliminary Engineering Report – October 2021
Value Engineering Study completed – November 2021
One joint study for both projects
Community Meeting with Board of Supervisor – December 2021
Community meeting – January 2022
Design Contract Development – (We are at this step)
Land Acquisition – (We are at this step)
Complete Design
Construction
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Fairfax County
Identify and evaluate house flooding and public safety concerns
Improve drainage conditions to convey 100-year storm if feasible
Reduce and treat stormwater runoff at the source
Improve water quality and stream protection
Use resilient & functional designs
Make improvements compatible with characteristics of neighborhood
Partner with community to develop sound, cost effective solutions that can be collaboratively implemented and maintained
Build on lessons learned to help improve site development process for infill development
MTH 251 Lab 7 FALL 2016NAME 1. Inverse trigonometric .docxgilpinleeanna
MTH 251 Lab 7 FALL 2016
NAME :
1. Inverse trigonometric derivatives review. Find the derivative of the following functions:
(a) d
dx
(ln(tan−1(x2 + 3))). For what values of x is this derivative valid?
(b) d
dx
(π sec−1(x2 − 1)). For what values of x is this derivative valid?
(c) d
dx
(
11 sin−1(−3x)
)
. For what values of x is this derivative valid?
2. Consider the linear function y = 1 − 2x. Find the inverse function, then compute the
derivatives of both functions. What do you notice?
3. The relationship in the previous problem works for any differentiable function with an
inverse. If f is differentiable at a point x0, then the derivative of f
−1 at an appropriate
point should be 1/f ′(x0), if f
′(x0) 6= 0.
(a) Sketch the graph of y =
√
x− 1, then find and carefully sketch its inverse on the
same graph.
(b) Find the tangent line to the graph of y =
√
x− 1 at the point where x = 5.
Sketch the tangent line on your curve.
(c) What is the corresponding tangent line on the graph of the inverse function?
What is its slope? You should be able to get this just by thinking about the
geometry.
(d) Compute the derivative of the inverse function directly. What input value must
you plug-in to get 1/y′(5)? (This is the slope you should have found in the previous
part.)
4. The previous problem illustrates the following result: If f is differentiable and has an
inverse on some interval I, and x0 is a point in I such that f
′(x0) 6= 0, then f−1 is
differentiable at y0 = f(x0), and
(f−1)′(y0) =
1
f ′(x0)
.
Use this to determine (f−1)′(3) for the function f(x) = x3 + x + 1, without finding the
inverse first.
PROJECT COMPLETION REPORT
MISSISSIPPI RIVER SEDIMENT DELIVERY SYSTEM
BAYOU DUPONT STATE PROJECT NO. BA-39
JEFFERSON AND ST. BERNARD PARISHES,
LOUISIANA
Prepared for
STATE OF LOUISIANA
DEPARTMENT OF NATURAL RESOURCES
OFFICE OF COASTAL PROTECTION AND RESTORATION
Prepared by
ABMB Engineers, Inc.
500 Main Street
Baton Rouge, Louisiana 70801
May 24, 2011
MISSISSIPPI RIVER SEDIMENT DELIVERY SYSTEM
BAYOU DUPONT STATE PROJECT NO. BA-39
JEFFERSON AND ST. BERNARD PARISHES, LOUISIANA
PROJECT COMPLETION REPORT
1
PROJECT NAME Bayou Dupont Marsh Creation Project
CWPPRA/STATE PROJECT NO. BA-39
Report Date: May 24, 2011
BY: ABMB Engineers, Inc.
500 Main Street
Baton Rouge, Louisiana 70801
1. DNR Project Managers/Engineer/Federal Sponsor/Construction Contractor/Inspection
Services:
DNR/OCPR Project Manager Brad Miller Telephone 225-342-4122
DNR/OCPR Construction Project
Manager
Peter Hopkins Telephone 504-280-4070
DNR/OCPR Monitoring Manager Bill Boshart Telephone 504-280-4063
Federal Agency Project Manager
(CWPPRA)
Paul Kaspar
(EPA)
Telephone 214 ...
Merrifield Nursery Emergency Gravity Sewer ReplacementFairfax County
During a routine Closed-Circuit Television (CCTV) Camera inspection by Wastewater Collection Division (WCD), it was found that 45 linear feet of 8-inch asbestos reinforced concrete pipe (RCP) between MH-292 to MH-291 was within imminent danger of failing. The bottom of the RCP was missing within the 45 linear feet of repair and the pipe was on the verge of surcharging. After an immediate pre-construction meeting with Merrifield Nursery, it was agreed to work from 6pm-10am everyday of the week to avoid disruption and potentially placing patrons at risk during the biggest time of the year for Merrifield Garden Center. The contractor mobilized to the site and began the 20-foot excavation to replace 45 linear feet of broken gravity sewer. The project started on March 14th, 2022 and was substantially complete on March 23, 2022.
The Sully Basins Stormwater Pond Retrofits project was substantially completed on April 19, 2022. The project is located within the Cub Run watershed. The project consisted of repair and enhancement of multiple stormwater basins, 0326DP, 0964DP and 1484DP. The project also included construction of new stone cascades, stone weir basin structures and the construction of wetlands with high and low marsh areas. The project will facilitate improved sediment removal and improve downstream water quality using forebays and micro pools. Aquatic and natural habitat were also added within the three basins.
Clarks Crossing Road Improvements 05-13-22Fairfax County
The Clarks Crossing Road Pedestrian Access Improvement project improved the pedestrian and bicycle access along Clarks Crossing Road and was substantially completed on March 23, 2022.
This project completed the missing link between the existing sidewalk at Brookside Lane and the previously constructed sidewalk along Clarks Crossing Road. The scope of this project included construction of asphalt sidewalk, curb ramps, curb and gutter, drainage improvements along Brookside Lane and asphalt mill/overlay on Clarks Crossing and Brookside Lane.
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxFairfax County
Future wastewater flows in northern Fairfax County exceed existing system capacity
Treatment capacity is available in Noman M. Cole Jr. Pollution Control Plant in Lorton, VA
New pipes and pumps are needed to move future flows to treatment plant
NEXT STEPS
Field investigations / surveys
Finalize alignments and pump station layout
Use of open cut excavation
Use of trenchless methods
Easement acquisition needed
Develop traffic control plans
Description:
The project consists of a new, 23,000 square feet, two-story, four-bay fire station facility and associated improvements to the 3.3-acre site including storm water detention, landscaping and parking. The scope also included the demolition of the existing fire station, and a temporary fire station to house the Fire and Rescue Department during construction of the new facility. The key elements of the overall project include:
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationFairfax County
Scotts Run @ Old Meadow Road Stream Restoration was substantially completed on March 30, 2022. The Scotts Run project consisted of restoring, enhancement, and stabilizing of approximately 2,930 linear feet of eroding stream using Natural Channel Design criteria. This project included two phases: Phase I was funded by proffers from a private development and Phase II was County funded. Also included was the removal of invasive non-native plants and the installation of new plantings to stabilize the stream and floodplain.
Riverwood Community Meeting - 04-14-2022- Presentation.pptxFairfax County
The new 4-inch ductile iron force main will serve the surrounding community for the foreseeable future. Replacement of the force main will:
Reduce the level and frequency of maintenance required to keep the force main operating.
Prevent costly emergency repairs.
Provide residents with safe, reliable utility infrastructure.
Enhance the quality of life for residents.
Reduce risks to public health and the environment.
Burke Centre VRE Connector Phase IV project was substantially completed on March 7, 2022. This project enhanced the access to mass transit by creating a more direct connection from the VRE Station to the residential areas west of Premier Court. This project also connects the Oak Bluff community to the Virginia Rail Express (VRE) Burke Station and provides a multi-use shared pedestrian and bicycle trail for outdoor recreation.
Long Branch Public Meeting - FINAL - 04-11-2022Fairfax County
Overarching Project Goals:
-Achieve Long Branch Central TMDL waste load reduction requirements.
-Provide long-term stability and have low maintenance.
-Improve water quality within the Long Branch Central Watershed.
-Improve habitat and environmental health (ecological lift).
Objectives: Share our project understanding with the council and seek input on the unique opportunities and housing goals for this site that could help guide
our master planning process.
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptxFairfax County
4,800 linear feet of stream will be restored using Natural Channel Design methodologies
Pollutant reduction
1,439 lbs/total phosphorus
3,400 lbs/total nitrogen
462.1 tons of total suspended sediment
Protection of private property and public infrastructure
Increased ecological diversity with native vegetation
DEQ has awarded a SLAF grant to this project for these environmental benefits
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT Fairfax County
The Lake Barton Dredging, Restoration, and Riser Modification project was substantially completed on December 29, 2021. The project is located within the Pohick Creek watershed. The project consisted of dredging and removal of approximately 19,100 cubic yards of sediment to restore the sediment trapping capacity and improve water quality. The project also included construction of new sediment forebays, in-lake haul roads, and riser modifications (new mid-level sluice gate and cold-water intake) to facilitate future maintenance, stabilize the shoreline, and improve downstream water quality. Fish habitat was also added within the lake.
Reston Arts Community Center Feasibility - Wrap UpFairfax County
This is the last of 5 engagement meetings. We are excited to report back what we heard from you – your preferences, priorities, questions, hopes, concerns. The information we received will be used to inform the space allocations and cost estimating for discussion of the proffer by Fairfax County.
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Fairfax County
Benefits of Consolidated Facility
Building and Site Efficiencies
Operational Efficiencies
Addresses Space Deficiencies
Addresses Renovations and Capital Renewal Requirements
for WCD
Provides for a Centrally Located Site that Accommodates Program
Consolidates Integrated Services on One Centrally Located Site
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Fairfax County
This is the 4th of 5 engagement meetings. We are excited to hear from you – your preferences, priorities, questions, hopes, concerns. The information we receive today will be used to inform the space allocations and cost estimating for discussion of the proffer by Fairfax County.
Oak Marr Pump Station Rehabilitation – Construction ProjectFairfax County
Neighborhood was built in the 1980s, and the sewer infrastructure has been in operation since.
Aged pump station equipment – pumps, valves, fans, concrete, etc.
This aging equipment has the potential of causing:
Sanitary Sewer Overflows (SSO)
Sewer back-ups into homes
Environmental damages
Maintenance problems
Reston Arts Center Feasibility - Focus Group Visual ArtsFairfax County
These community outreach meetings are being conducted to understand community needs for a proposed arts venue in the Reston Town Center.
The proposed arts center would be a result of a proffer from Boston Properties in the next phase of Reston Town Center development (Block J).
The proffer would provide for an approximately 60,000 gross square foot facility to house a stage suitable for large-scale music and dance performances, as well as other arts-related amenities.
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022Fairfax County
These community outreach meetings are being conducted to understand community needs for a proposed arts venue in the Reston Town Center.
The proposed arts center would be a result of a proffer from Boston Properties in the next phase of Reston Town Center development (Block J).
The proffer would provide for an approximately 60,000 gross square foot facility to house a stage suitable for large-scale music and dance performances, as well as other arts-related amenities.
Using recycled concrete aggregates (RCA) for pavements is crucial to achieving sustainability. Implementing RCA for new pavement can minimize carbon footprint, conserve natural resources, reduce harmful emissions, and lower life cycle costs. Compared to natural aggregate (NA), RCA pavement has fewer comprehensive studies and sustainability assessments.
Saudi Arabia stands as a titan in the global energy landscape, renowned for its abundant oil and gas resources. It's the largest exporter of petroleum and holds some of the world's most significant reserves. Let's delve into the top 10 oil and gas projects shaping Saudi Arabia's energy future in 2024.
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)MdTanvirMahtab2
This presentation is about the working procedure of Shahjalal Fertilizer Company Limited (SFCL). A Govt. owned Company of Bangladesh Chemical Industries Corporation under Ministry of Industries.
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...ssuser7dcef0
Power plants release a large amount of water vapor into the
atmosphere through the stack. The flue gas can be a potential
source for obtaining much needed cooling water for a power
plant. If a power plant could recover and reuse a portion of this
moisture, it could reduce its total cooling water intake
requirement. One of the most practical way to recover water
from flue gas is to use a condensing heat exchanger. The power
plant could also recover latent heat due to condensation as well
as sensible heat due to lowering the flue gas exit temperature.
Additionally, harmful acids released from the stack can be
reduced in a condensing heat exchanger by acid condensation. reduced in a condensing heat exchanger by acid condensation.
Condensation of vapors in flue gas is a complicated
phenomenon since heat and mass transfer of water vapor and
various acids simultaneously occur in the presence of noncondensable
gases such as nitrogen and oxygen. Design of a
condenser depends on the knowledge and understanding of the
heat and mass transfer processes. A computer program for
numerical simulations of water (H2O) and sulfuric acid (H2SO4)
condensation in a flue gas condensing heat exchanger was
developed using MATLAB. Governing equations based on
mass and energy balances for the system were derived to
predict variables such as flue gas exit temperature, cooling
water outlet temperature, mole fraction and condensation rates
of water and sulfuric acid vapors. The equations were solved
using an iterative solution technique with calculations of heat
and mass transfer coefficients and physical properties.
Final project report on grocery store management system..pdfKamal Acharya
In today’s fast-changing business environment, it’s extremely important to be able to respond to client needs in the most effective and timely manner. If your customers wish to see your business online and have instant access to your products or services.
Online Grocery Store is an e-commerce website, which retails various grocery products. This project allows viewing various products available enables registered users to purchase desired products instantly using Paytm, UPI payment processor (Instant Pay) and also can place order by using Cash on Delivery (Pay Later) option. This project provides an easy access to Administrators and Managers to view orders placed using Pay Later and Instant Pay options.
In order to develop an e-commerce website, a number of Technologies must be studied and understood. These include multi-tiered architecture, server and client-side scripting techniques, implementation technologies, programming language (such as PHP, HTML, CSS, JavaScript) and MySQL relational databases. This is a project with the objective to develop a basic website where a consumer is provided with a shopping cart website and also to know about the technologies used to develop such a website.
This document will discuss each of the underlying technologies to create and implement an e- commerce website.
Overview of the fundamental roles in Hydropower generation and the components involved in wider Electrical Engineering.
This paper presents the design and construction of hydroelectric dams from the hydrologist’s survey of the valley before construction, all aspects and involved disciplines, fluid dynamics, structural engineering, generation and mains frequency regulation to the very transmission of power through the network in the United Kingdom.
Author: Robbie Edward Sayers
Collaborators and co editors: Charlie Sims and Connor Healey.
(C) 2024 Robbie E. Sayers
Hierarchical Digital Twin of a Naval Power SystemKerry Sado
A hierarchical digital twin of a Naval DC power system has been developed and experimentally verified. Similar to other state-of-the-art digital twins, this technology creates a digital replica of the physical system executed in real-time or faster, which can modify hardware controls. However, its advantage stems from distributing computational efforts by utilizing a hierarchical structure composed of lower-level digital twin blocks and a higher-level system digital twin. Each digital twin block is associated with a physical subsystem of the hardware and communicates with a singular system digital twin, which creates a system-level response. By extracting information from each level of the hierarchy, power system controls of the hardware were reconfigured autonomously. This hierarchical digital twin development offers several advantages over other digital twins, particularly in the field of naval power systems. The hierarchical structure allows for greater computational efficiency and scalability while the ability to autonomously reconfigure hardware controls offers increased flexibility and responsiveness. The hierarchical decomposition and models utilized were well aligned with the physical twin, as indicated by the maximum deviations between the developed digital twin hierarchy and the hardware.
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Little Pimmit Run at Chesterbrook Road Stream Restoration Project - April 2021
1. A Fairfax County, VA, publication
Department of Public Works and Environmental Services
Working for You!
Little Pimmit Run at
Chesterbrook Road
Stream Restoration Project
April 2021
April 22, 2021
6. 6
Project Goals
1. Restore up to 7,100 feet of stream channel and connecting
tributaries
– Reduce sediment transport
2. Protect existing infrastructure
– Coordinate with Little Pimmit Run Sewer Realignment Project
3. Maintain close coordination with stakeholders
Stormwater Planning Division
7. Stormwater Planning Division
Social Goals
1. Maintain open dialog and share information.
2. Coordinate with all the stakeholders and the community.
3. Build partnerships with local organizations such as
homeowners associations.
4. Design Team:
– Fairfax County Public Works
– Fairfax County Park Authority
– Wetland Studies and Solutions, Inc.
7
8. Stormwater Planning Division
Stormwater Program Drivers
• Municipal Separate Storm Sewer Permit (MS-4)
• Chesapeake Bay Total Maximum Daily Loads (TMDL)
– Regulates amount of pollutants in waterways
• Local TMDLs
• Dam Safety Regulations
• Maintenance of Existing Facilities
• Public Safety /Emergency Response
8
28. Proposed Design Alignments
28
Stormwater Planning Division
Alignment #1 – Establishes a balance between using the existing channel while
increasing curves in the proposed channel.
Alignment #2 – Adds the most curves to the proposed channel.
Alignment #3 – Utilizes the existing channel to the greatest degree (limited sections in
phase 2)
*All alignments largely utilize the existing over widened channel scar to minimize
disturbance.
Brown Dashed Line = Existing Channel
Solid black line = Alignment #1
Solid blue line = Alignment #2
Solid orange line = Alignment #3
29. 29
Proposed Channel Alignments – Phase 1
Flow
Stormwater Planning Division
Brown Dashed Line = Existing Channel
Solid black line = Alignment #1
Solid blue line = Alignment #2
X – Impacted tree
30. 30
Proposed Channel Alignments – Phase 1
Flow
Brown Dashed Line = Existing Channel
Solid black line = Alignment #1
Solid blue line = Alignment #2
X – Impacted tree
31. 31
Proposed Channel Alignments – Phase 1
Stormwater Planning Division
Flow
Brown Dashed Line = Existing Channel
Solid black line = Alignment #1
Solid blue line = Alignment #2
X – Impacted tree
32. 32
Proposed Channel Alignments – Phase 2
Brown Dashed Line = Existing Channel
Three solid black lines = Alignment #1
Shaded blue area = Alignment #2
Flow
X – Impacted tree
33. 33
Proposed Channel Alignments – Phase 2
Flow
Brown Dashed Line = Existing Channel
Solid black line = Alignment #1
Solid blue line = Alignment #2
Solid orange line = Alignment #3
X – Impacted tree
34. 34
Proposed Channel Alignments – Phase 2
Flow
Brown Dashed Line = Existing Channel
Solid black line = Alignment #1
Solid blue line = Alignment #2
Solid orange line = Alignment #3
35. 35
Proposed Channel Alignments – Phase 2
Flow
Brown Dashed Line = Existing Channel
Solid black line = Alignment #1
Solid blue line = Alignment #2
Solid orange line = Alignment #3
X – Impacted tree
36. 36
Proposed Channel Alignments – Phase 2
Flow
Brown Dashed Line = Existing Channel
Solid black line = Alignment #1
Solid blue line = Alignment #2
X – Impacted tree
37. 37
Schedule
• Concept design submission – September
2021
• Concept design community meeting –
November 2021
• Land Acquisition –
Easements required prior to final
design
• Construction – To be determined
Pending date of completed design
Stormwater Planning Division
• Community meeting on Pre-design/Channel alignments –
April 22, 2021
38. 38
Contact Information
Contact Information
Design
Fred Wilkins – Project Manager
703-509-0511
Fred.Wilkins@fairfaxcounty.gov
Stormwater Planning Division
703-324-5500, TTY 711
12000 Government Center Parkway
Suite 449
Fairfax, Virginia 22035
www.fairfaxcounty.gov/publicworks/stormwater
To request this information in an alternate
format call 703-324-5500, TTY 711
Stormwater Planning Division
39. Online Resources
39
Stormwater Planning Division Website
https://www.fairfaxcounty.gov/publicworks/stormwater/
Northern Virginia Soil and Water Conservation District
http://www.fairfaxcounty.gov/nvswcd/newsletter/planning.htm
Middle Potomac Watersheds Management Plan (Includes Pimmit Run)
https://www.fairfaxcounty.gov/publicworks/stormwater/middle-potomac-watersheds
Stormwater Planning Division
Little Pimmit Run at Chesterbrook Road
Stream Restoration and Stormwater
Improvement Project
Little Pimmit Run at Chesterbrook Road
Stream Restoration (SD-000031-246) |
Public Works and Environmental Services
(fairfaxcounty.gov)