SlideShare a Scribd company logo
1 of 14
Download to read offline
Building Design and Construction Division
Stormwater Wastewater Facility
March 29, 2022
Construction Phase
Building Design and Construction Division
Agenda
2
Stormwater Wastewater Facility
• Welcome
• Team Introductions
• Project Overview & Updates
• Proposed Construction Phasing, Operations & Schedule
• Project Communication
• Questions & Answers
Building Design and Construction Division
Stormwater Wastewater Facility
Project Team
3
Project Team
• Stormwater and Wastewater Divisions
• Building Design and Construction Division – CAP/DPWES
• Michael Baker Int. – Architect of the Record
• Manhattan Construction Company – General Contractor
Building Design and Construction Division
Project Overview
4
Stormwater Wastewater Facility
SITE 13
WCD Property
SITE 11
Concrete Plant site
Benefits of Consolidated Facility
• Building and Site Efficiencies
• Operational Efficiencies
• Addresses Space Deficiencies
• Addresses Renovations and
Capital Renewal Requirements
for WCD
• Provides for a Centrally
Located Site that
Accommodates Program
• Consolidates Integrated
Services on One Centrally
Located Site
Site 11: 9.3 acres
Site 13: 14.4 acres
Total: 23.7 acres
Building Design and Construction Division
Site Plan
5
Stormwater Wastewater Facility
Clara
Barton
Dr
.
Fairfax County Pkwy
1
7
5
4
8
2
3 6
-
Building Design and Construction Division
Site Plan
6
Stormwater Wastewater Facility
Building Design and Construction Division
Stormwater Wastewater Facility
Project Enhancement
7
Features
• Targeting LEED Gold Certification
• Green Roof
• Solar Ready-Photovoltaics Panels
• Electrical Vehicles Ready
• Geothermal
• Rainwater Harvesting
• Stormwater Cisterns
• Natural Landscaping
• Bioretention Facilities
• Pervious Pavement Types
• Green Wall
• Video Wall
• Education
• Fencing
Photovoltaics Panels
Green Roof
Rainwater Harvesting
Stormwater Cistern
Pervious Pavement Types
Green Wall
Geothermal Fence
Building Design and Construction Division
Administrative Offices & Support Area - Building 1
8
Stormwater Wastewater Facility
Building 1 – South Façade Front Elevation
Building 1 – North Façade Main Entrance Building 1 – Main Entrance
Building Design and Construction Division
Proposed Construction Phasing
9
Stormwater Wastewater Facility
Construction
Entrance 1
(primary entrance
for Phase 1)
Construction
Entrance 2
Construction
Entrance 3
Building Design and Construction Division
Stormwater Wastewater Facility
Construction Activities
10
Notice-to-proceed issued: March 15, 2022
Work Underway or Completed:
• Contractor procurement & submittal coordination
• Site Surveying
• Phase 1 Area site mobilization & contractor staging
• Site clearing, tree tagging, protection & select removal
• Installation of E&S control & LOD confirmed
• Safety fencing secured
Look-Ahead:
• Phase 1:
• Deconstruction of concrete plant & site preparation
• Construction Buildings 2-8
• Phase 1 Area connection to Freds Oak Road
• Phase 2:
• Building 1 & site features
• Phase 3:
• Transition of existing WCD operations into Building 1
• Demolition of Existing WCD building & remaining
site/landscape work
Building Design and Construction Division
Stormwater Wastewater Facility
Construction Operations
11
✓ Hours of operation: M-F 7 AM to 4 PM,
Saturdays 9 AM start(occasional)
✓ County noise ordinance will be followed
✓ Phase 1 construction area secured with perimeter safety fencing
✓ Dust and stormwater control measures will be in place
✓ Phase 1 construction traffic: Clara Barton Drive (primary access)
Southern Freds Oak Road entrance also utilized
✓ Phase 2 & 3 construction traffic: Freds Oak entrances mainly utilized
✓ Existing WCD will remain operational throughout 3.5-4 yr. construction
Building Design and Construction Division
Stormwater Wastewater Facility
Proposed Construction Schedule
12
*Schedule projection based on standard construction scheduling parameters.
Actual schedule may be impacted by unforeseen weather and other natural occurrences.
Proposed Schedule*
• Start: March 2022
• Phase 1: Fall 2023
• Phase 2: Early 2025
• Phase 3: Fall 2025
• Completion: Fall 2025
Building Design and Construction Division
Project Communication
13
Stormwater Wastewater Consolidation
Main Points of Contact:
For Updates Visit the Project Website at:
https://www.fairfaxcounty.gov/publicworks/proposed-stormwater-and-wastewater-consolidation-facility
POC Email or Phone
Project Design Allison Terzigni, Senior Design Manager Allison.Terzigni@FairfaxCounty.gov
Project Construction/Safety Eric James, Senior Construction Manager John.James@FairfaxCounty.gov
Onsite Wastewater Operations Shwan Fatah, Director WCD Shwan.Fatah@FairfaxCounty.gov
Wastewater Emergency Trouble Response Center (703) 323-1211
Building Design and Construction Division
Questions & Answers
14
Stormwater Wastewater Facility

More Related Content

What's hot

Dead Run Stream Restoration Segment 2 – 3
Dead Run Stream Restoration Segment 2 – 3Dead Run Stream Restoration Segment 2 – 3
Dead Run Stream Restoration Segment 2 – 3Fairfax County
 
Bridge construction methodology
Bridge construction methodologyBridge construction methodology
Bridge construction methodologyELSAYED DIAB
 
Dulles Corridor Metrorail Project: Board Transportation Committee Update- Jul...
Dulles Corridor Metrorail Project: Board Transportation Committee Update- Jul...Dulles Corridor Metrorail Project: Board Transportation Committee Update- Jul...
Dulles Corridor Metrorail Project: Board Transportation Committee Update- Jul...Fairfax County
 
Alamo Heights CCM 01.14.19 Item #7 PPT Const Update 5500 Broadway
Alamo Heights CCM 01.14.19 Item #7  PPT Const Update 5500 BroadwayAlamo Heights CCM 01.14.19 Item #7  PPT Const Update 5500 Broadway
Alamo Heights CCM 01.14.19 Item #7 PPT Const Update 5500 Broadwayahcitycouncil
 
Lee Chapel Rd. Walkway Burke Lake Rd. to Britford Dr. July 2020
Lee Chapel Rd. Walkway Burke Lake Rd. to Britford Dr. July 2020Lee Chapel Rd. Walkway Burke Lake Rd. to Britford Dr. July 2020
Lee Chapel Rd. Walkway Burke Lake Rd. to Britford Dr. July 2020Fairfax County
 
Substantial completion flatlick branch iii stream restoration
Substantial completion   flatlick branch iii stream restorationSubstantial completion   flatlick branch iii stream restoration
Substantial completion flatlick branch iii stream restorationFairfax County
 
Flood Mitigation Project on Overly Drive
Flood Mitigation Project on Overly DriveFlood Mitigation Project on Overly Drive
Flood Mitigation Project on Overly DriveFairfax County
 
Turkey Run at Truro Subdivision Stream Restoration
Turkey Run at Truro Subdivision Stream RestorationTurkey Run at Truro Subdivision Stream Restoration
Turkey Run at Truro Subdivision Stream RestorationFairfax County
 
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptxFairfax County
 
Chaplin - Avenue Construction Liaison Committee Meeting - March 28, 2017
Chaplin - Avenue Construction Liaison Committee Meeting - March 28, 2017Chaplin - Avenue Construction Liaison Committee Meeting - March 28, 2017
Chaplin - Avenue Construction Liaison Committee Meeting - March 28, 2017Crosstown TO
 
Tysons Fire Station #29 and Bus Transit Facility - 111621 community meeting
Tysons Fire Station #29 and Bus Transit Facility - 111621 community meetingTysons Fire Station #29 and Bus Transit Facility - 111621 community meeting
Tysons Fire Station #29 and Bus Transit Facility - 111621 community meetingFairfax County
 
Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation - BTC U...
Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation - BTC U...Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation - BTC U...
Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation - BTC U...Fairfax County
 
Central West Fall Open House - Oct 28 2019
Central West Fall Open House - Oct 28 2019Central West Fall Open House - Oct 28 2019
Central West Fall Open House - Oct 28 2019Crosstown TO
 
Jefferson Fire Station #18
Jefferson Fire Station #18Jefferson Fire Station #18
Jefferson Fire Station #18Fairfax County
 
Burke View Court Emergency Sewer Repair
Burke View Court Emergency Sewer RepairBurke View Court Emergency Sewer Repair
Burke View Court Emergency Sewer RepairSharon Rae North
 
Burke View Court Emergency Sewer Repair
Burke View Court Emergency Sewer RepairBurke View Court Emergency Sewer Repair
Burke View Court Emergency Sewer RepairFairfax County
 
Eastern market metro park meeting 06 24-2020
Eastern market metro park meeting 06 24-2020Eastern market metro park meeting 06 24-2020
Eastern market metro park meeting 06 24-2020RamaChilamkurthy
 

What's hot (20)

Dead Run Stream Restoration Segment 2 – 3
Dead Run Stream Restoration Segment 2 – 3Dead Run Stream Restoration Segment 2 – 3
Dead Run Stream Restoration Segment 2 – 3
 
Bridge construction methodology
Bridge construction methodologyBridge construction methodology
Bridge construction methodology
 
School Facilities Referendum Recommendations
School Facilities Referendum RecommendationsSchool Facilities Referendum Recommendations
School Facilities Referendum Recommendations
 
Dulles Corridor Metrorail Project: Board Transportation Committee Update- Jul...
Dulles Corridor Metrorail Project: Board Transportation Committee Update- Jul...Dulles Corridor Metrorail Project: Board Transportation Committee Update- Jul...
Dulles Corridor Metrorail Project: Board Transportation Committee Update- Jul...
 
Alamo Heights CCM 01.14.19 Item #7 PPT Const Update 5500 Broadway
Alamo Heights CCM 01.14.19 Item #7  PPT Const Update 5500 BroadwayAlamo Heights CCM 01.14.19 Item #7  PPT Const Update 5500 Broadway
Alamo Heights CCM 01.14.19 Item #7 PPT Const Update 5500 Broadway
 
Crisis Care Facility
Crisis Care FacilityCrisis Care Facility
Crisis Care Facility
 
Lee Chapel Rd. Walkway Burke Lake Rd. to Britford Dr. July 2020
Lee Chapel Rd. Walkway Burke Lake Rd. to Britford Dr. July 2020Lee Chapel Rd. Walkway Burke Lake Rd. to Britford Dr. July 2020
Lee Chapel Rd. Walkway Burke Lake Rd. to Britford Dr. July 2020
 
Substantial completion flatlick branch iii stream restoration
Substantial completion   flatlick branch iii stream restorationSubstantial completion   flatlick branch iii stream restoration
Substantial completion flatlick branch iii stream restoration
 
Flood Mitigation Project on Overly Drive
Flood Mitigation Project on Overly DriveFlood Mitigation Project on Overly Drive
Flood Mitigation Project on Overly Drive
 
Turkey Run at Truro Subdivision Stream Restoration
Turkey Run at Truro Subdivision Stream RestorationTurkey Run at Truro Subdivision Stream Restoration
Turkey Run at Truro Subdivision Stream Restoration
 
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 
Chaplin - Avenue Construction Liaison Committee Meeting - March 28, 2017
Chaplin - Avenue Construction Liaison Committee Meeting - March 28, 2017Chaplin - Avenue Construction Liaison Committee Meeting - March 28, 2017
Chaplin - Avenue Construction Liaison Committee Meeting - March 28, 2017
 
Tysons Fire Station #29 and Bus Transit Facility - 111621 community meeting
Tysons Fire Station #29 and Bus Transit Facility - 111621 community meetingTysons Fire Station #29 and Bus Transit Facility - 111621 community meeting
Tysons Fire Station #29 and Bus Transit Facility - 111621 community meeting
 
Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation - BTC U...
Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation - BTC U...Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation - BTC U...
Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation - BTC U...
 
Central West Fall Open House - Oct 28 2019
Central West Fall Open House - Oct 28 2019Central West Fall Open House - Oct 28 2019
Central West Fall Open House - Oct 28 2019
 
0609_PenRen
0609_PenRen0609_PenRen
0609_PenRen
 
Jefferson Fire Station #18
Jefferson Fire Station #18Jefferson Fire Station #18
Jefferson Fire Station #18
 
Burke View Court Emergency Sewer Repair
Burke View Court Emergency Sewer RepairBurke View Court Emergency Sewer Repair
Burke View Court Emergency Sewer Repair
 
Burke View Court Emergency Sewer Repair
Burke View Court Emergency Sewer RepairBurke View Court Emergency Sewer Repair
Burke View Court Emergency Sewer Repair
 
Eastern market metro park meeting 06 24-2020
Eastern market metro park meeting 06 24-2020Eastern market metro park meeting 06 24-2020
Eastern market metro park meeting 06 24-2020
 

Similar to Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022

Bull Neck Stream Restoration Pardon Our Dust Meeting May 2, 2018
Bull Neck Stream Restoration Pardon Our Dust Meeting May 2, 2018Bull Neck Stream Restoration Pardon Our Dust Meeting May 2, 2018
Bull Neck Stream Restoration Pardon Our Dust Meeting May 2, 2018Fairfax County
 
Construction of Primary School slides-1.pptx
Construction of Primary School slides-1.pptxConstruction of Primary School slides-1.pptx
Construction of Primary School slides-1.pptxSardarMuhammadHashir
 
Jefferson Manor Phase IIIA (Albemarle Drive and Portions of Edgehill Drive)
Jefferson Manor Phase IIIA (Albemarle Drive and Portions of Edgehill Drive)Jefferson Manor Phase IIIA (Albemarle Drive and Portions of Edgehill Drive)
Jefferson Manor Phase IIIA (Albemarle Drive and Portions of Edgehill Drive)Fairfax County
 
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationScotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationFairfax County
 
9. introduction to site preparation
9. introduction to site preparation9. introduction to site preparation
9. introduction to site preparationNoshad Ahmed Wahocho
 
JAT4 Kick off Introduction - UAE Navy
JAT4 Kick off Introduction - UAE NavyJAT4 Kick off Introduction - UAE Navy
JAT4 Kick off Introduction - UAE NavyMike Bisland
 
Stormwater Wastewater Consolidation
Stormwater Wastewater ConsolidationStormwater Wastewater Consolidation
Stormwater Wastewater ConsolidationFairfax County
 
Land Subdivisions University Course
Land Subdivisions University CourseLand Subdivisions University Course
Land Subdivisions University CourseNettlemanU
 
Kalorama Park & Playground ANC Presentation (December 3, 2014)
Kalorama Park & Playground ANC Presentation (December 3, 2014)Kalorama Park & Playground ANC Presentation (December 3, 2014)
Kalorama Park & Playground ANC Presentation (December 3, 2014)DC Department of General Services
 
LMPP Final Presentation_FINAL1
LMPP Final Presentation_FINAL1LMPP Final Presentation_FINAL1
LMPP Final Presentation_FINAL1Theodore McNeal
 
Pardon Our Dust meeting, March 9, 2016
Pardon Our Dust meeting, March 9, 2016Pardon Our Dust meeting, March 9, 2016
Pardon Our Dust meeting, March 9, 2016VDOT Northern Virginia
 
Huntington Levee Community Meeting: Feb. 23, 2016
Huntington Levee Community Meeting: Feb. 23, 2016Huntington Levee Community Meeting: Feb. 23, 2016
Huntington Levee Community Meeting: Feb. 23, 2016Fairfax County
 
Faisalaiah project (english) 3 REV.03
Faisalaiah project (english) 3 REV.03Faisalaiah project (english) 3 REV.03
Faisalaiah project (english) 3 REV.03Wael Nafad
 
Pike Branch at Wilton Road Presentation
Pike Branch at Wilton Road PresentationPike Branch at Wilton Road Presentation
Pike Branch at Wilton Road PresentationFairfax County
 
Chandler Geoff 2016 cv
Chandler Geoff 2016 cvChandler Geoff 2016 cv
Chandler Geoff 2016 cvGeoff Chandler
 
Public Facilities Manual Flexibility Project : Update to the Development Proc...
Public Facilities Manual Flexibility Project : Update to the Development Proc...Public Facilities Manual Flexibility Project : Update to the Development Proc...
Public Facilities Manual Flexibility Project : Update to the Development Proc...Fairfax County
 
Sunset Hills Road Drainage Improvement Project
Sunset Hills Road Drainage Improvement ProjectSunset Hills Road Drainage Improvement Project
Sunset Hills Road Drainage Improvement ProjectFairfax County
 
Cameron Run Tributary At La Vista Drive: Stream Restoration
Cameron Run Tributary At La Vista Drive: Stream RestorationCameron Run Tributary At La Vista Drive: Stream Restoration
Cameron Run Tributary At La Vista Drive: Stream RestorationFairfax County
 

Similar to Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022 (20)

Bull Neck Stream Restoration Pardon Our Dust Meeting May 2, 2018
Bull Neck Stream Restoration Pardon Our Dust Meeting May 2, 2018Bull Neck Stream Restoration Pardon Our Dust Meeting May 2, 2018
Bull Neck Stream Restoration Pardon Our Dust Meeting May 2, 2018
 
Construction of Primary School slides-1.pptx
Construction of Primary School slides-1.pptxConstruction of Primary School slides-1.pptx
Construction of Primary School slides-1.pptx
 
Jefferson Manor Phase IIIA (Albemarle Drive and Portions of Edgehill Drive)
Jefferson Manor Phase IIIA (Albemarle Drive and Portions of Edgehill Drive)Jefferson Manor Phase IIIA (Albemarle Drive and Portions of Edgehill Drive)
Jefferson Manor Phase IIIA (Albemarle Drive and Portions of Edgehill Drive)
 
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationScotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
 
9. introduction to site preparation
9. introduction to site preparation9. introduction to site preparation
9. introduction to site preparation
 
JAT4 Kick off Introduction - UAE Navy
JAT4 Kick off Introduction - UAE NavyJAT4 Kick off Introduction - UAE Navy
JAT4 Kick off Introduction - UAE Navy
 
Stormwater Wastewater Consolidation
Stormwater Wastewater ConsolidationStormwater Wastewater Consolidation
Stormwater Wastewater Consolidation
 
Land Subdivisions University Course
Land Subdivisions University CourseLand Subdivisions University Course
Land Subdivisions University Course
 
Kalorama Park & Playground ANC Presentation (December 3, 2014)
Kalorama Park & Playground ANC Presentation (December 3, 2014)Kalorama Park & Playground ANC Presentation (December 3, 2014)
Kalorama Park & Playground ANC Presentation (December 3, 2014)
 
LMPP Final Presentation_FINAL1
LMPP Final Presentation_FINAL1LMPP Final Presentation_FINAL1
LMPP Final Presentation_FINAL1
 
 
Pardon Our Dust meeting, March 9, 2016
Pardon Our Dust meeting, March 9, 2016Pardon Our Dust meeting, March 9, 2016
Pardon Our Dust meeting, March 9, 2016
 
Huntington Levee Community Meeting: Feb. 23, 2016
Huntington Levee Community Meeting: Feb. 23, 2016Huntington Levee Community Meeting: Feb. 23, 2016
Huntington Levee Community Meeting: Feb. 23, 2016
 
Faisalaiah project (english) 3 REV.03
Faisalaiah project (english) 3 REV.03Faisalaiah project (english) 3 REV.03
Faisalaiah project (english) 3 REV.03
 
Pike Branch at Wilton Road Presentation
Pike Branch at Wilton Road PresentationPike Branch at Wilton Road Presentation
Pike Branch at Wilton Road Presentation
 
Chandler Geoff 2016 cv
Chandler Geoff 2016 cvChandler Geoff 2016 cv
Chandler Geoff 2016 cv
 
Public Facilities Manual Flexibility Project : Update to the Development Proc...
Public Facilities Manual Flexibility Project : Update to the Development Proc...Public Facilities Manual Flexibility Project : Update to the Development Proc...
Public Facilities Manual Flexibility Project : Update to the Development Proc...
 
Kalorama Community Meeting Presentation (October 9, 2014)
Kalorama Community Meeting Presentation (October 9, 2014)Kalorama Community Meeting Presentation (October 9, 2014)
Kalorama Community Meeting Presentation (October 9, 2014)
 
Sunset Hills Road Drainage Improvement Project
Sunset Hills Road Drainage Improvement ProjectSunset Hills Road Drainage Improvement Project
Sunset Hills Road Drainage Improvement Project
 
Cameron Run Tributary At La Vista Drive: Stream Restoration
Cameron Run Tributary At La Vista Drive: Stream RestorationCameron Run Tributary At La Vista Drive: Stream Restoration
Cameron Run Tributary At La Vista Drive: Stream Restoration
 

More from Fairfax County

Merrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementMerrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementFairfax County
 
SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS Fairfax County
 
Clarks Crossing Road Improvements 05-13-22
 Clarks Crossing Road Improvements 05-13-22 Clarks Crossing Road Improvements 05-13-22
Clarks Crossing Road Improvements 05-13-22Fairfax County
 
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxTysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxFairfax County
 
Lorton Volunteer Fire Station #19
Lorton Volunteer Fire Station  #19 Lorton Volunteer Fire Station  #19
Lorton Volunteer Fire Station #19 Fairfax County
 
Sully Community Center Construction Progress
Sully Community Center Construction ProgressSully Community Center Construction Progress
Sully Community Center Construction ProgressFairfax County
 
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxRiverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxFairfax County
 
Burke VRE Connector Phase IV
Burke VRE Connector Phase IVBurke VRE Connector Phase IV
Burke VRE Connector Phase IVFairfax County
 
Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Fairfax County
 
Workhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxWorkhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxFairfax County
 
Workhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilWorkhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilFairfax County
 
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT Fairfax County
 
Reston Arts Community Center Feasibility - Wrap Up
 Reston Arts Community Center Feasibility - Wrap Up Reston Arts Community Center Feasibility - Wrap Up
Reston Arts Community Center Feasibility - Wrap UpFairfax County
 
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Fairfax County
 
Oak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectOak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectFairfax County
 
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Fairfax County
 
Reston Arts Center Feasibility - Focus Group Visual Arts
Reston Arts Center Feasibility -  Focus Group Visual ArtsReston Arts Center Feasibility -  Focus Group Visual Arts
Reston Arts Center Feasibility - Focus Group Visual ArtsFairfax County
 
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022Fairfax County
 
Reston Fire Station #25
Reston Fire Station #25Reston Fire Station #25
Reston Fire Station #25Fairfax County
 
Reston Arts Center Community Meeting 02-28-22
Reston Arts Center Community Meeting 02-28-22Reston Arts Center Community Meeting 02-28-22
Reston Arts Center Community Meeting 02-28-22Fairfax County
 

More from Fairfax County (20)

Merrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementMerrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer Replacement
 
SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS
 
Clarks Crossing Road Improvements 05-13-22
 Clarks Crossing Road Improvements 05-13-22 Clarks Crossing Road Improvements 05-13-22
Clarks Crossing Road Improvements 05-13-22
 
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxTysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
 
Lorton Volunteer Fire Station #19
Lorton Volunteer Fire Station  #19 Lorton Volunteer Fire Station  #19
Lorton Volunteer Fire Station #19
 
Sully Community Center Construction Progress
Sully Community Center Construction ProgressSully Community Center Construction Progress
Sully Community Center Construction Progress
 
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxRiverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
 
Burke VRE Connector Phase IV
Burke VRE Connector Phase IVBurke VRE Connector Phase IV
Burke VRE Connector Phase IV
 
Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022
 
Workhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxWorkhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick Offpptx
 
Workhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilWorkhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing Council
 
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
 
Reston Arts Community Center Feasibility - Wrap Up
 Reston Arts Community Center Feasibility - Wrap Up Reston Arts Community Center Feasibility - Wrap Up
Reston Arts Community Center Feasibility - Wrap Up
 
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
 
Oak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectOak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction Project
 
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
 
Reston Arts Center Feasibility - Focus Group Visual Arts
Reston Arts Center Feasibility -  Focus Group Visual ArtsReston Arts Center Feasibility -  Focus Group Visual Arts
Reston Arts Center Feasibility - Focus Group Visual Arts
 
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022
 
Reston Fire Station #25
Reston Fire Station #25Reston Fire Station #25
Reston Fire Station #25
 
Reston Arts Center Community Meeting 02-28-22
Reston Arts Center Community Meeting 02-28-22Reston Arts Center Community Meeting 02-28-22
Reston Arts Center Community Meeting 02-28-22
 

Recently uploaded

Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Call Girls Mumbai
 
Digital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptxDigital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptxpritamlangde
 
UNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptxUNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptxkalpana413121
 
fitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .pptfitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .pptAfnanAhmad53
 
Ground Improvement Technique: Earth Reinforcement
Ground Improvement Technique: Earth ReinforcementGround Improvement Technique: Earth Reinforcement
Ground Improvement Technique: Earth ReinforcementDr. Deepak Mudgal
 
457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx
457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx
457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptxrouholahahmadi9876
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationBhangaleSonal
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdfKamal Acharya
 
PE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiesPE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiessarkmank1
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptxJIT KUMAR GUPTA
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.Kamal Acharya
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxSCMS School of Architecture
 
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxOrlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxMuhammadAsimMuhammad6
 
Linux Systems Programming: Inter Process Communication (IPC) using Pipes
Linux Systems Programming: Inter Process Communication (IPC) using PipesLinux Systems Programming: Inter Process Communication (IPC) using Pipes
Linux Systems Programming: Inter Process Communication (IPC) using PipesRashidFaridChishti
 
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...Amil baba
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdfAldoGarca30
 
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...jabtakhaidam7
 
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...drmkjayanthikannan
 

Recently uploaded (20)

Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
 
Digital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptxDigital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptx
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
 
UNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptxUNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptx
 
fitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .pptfitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .ppt
 
Ground Improvement Technique: Earth Reinforcement
Ground Improvement Technique: Earth ReinforcementGround Improvement Technique: Earth Reinforcement
Ground Improvement Technique: Earth Reinforcement
 
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
 
457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx
457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx
457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equation
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdf
 
PE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiesPE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and properties
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
 
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxOrlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
 
Linux Systems Programming: Inter Process Communication (IPC) using Pipes
Linux Systems Programming: Inter Process Communication (IPC) using PipesLinux Systems Programming: Inter Process Communication (IPC) using Pipes
Linux Systems Programming: Inter Process Communication (IPC) using Pipes
 
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
 
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...
 
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
 

Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022

  • 1. Building Design and Construction Division Stormwater Wastewater Facility March 29, 2022 Construction Phase
  • 2. Building Design and Construction Division Agenda 2 Stormwater Wastewater Facility • Welcome • Team Introductions • Project Overview & Updates • Proposed Construction Phasing, Operations & Schedule • Project Communication • Questions & Answers
  • 3. Building Design and Construction Division Stormwater Wastewater Facility Project Team 3 Project Team • Stormwater and Wastewater Divisions • Building Design and Construction Division – CAP/DPWES • Michael Baker Int. – Architect of the Record • Manhattan Construction Company – General Contractor
  • 4. Building Design and Construction Division Project Overview 4 Stormwater Wastewater Facility SITE 13 WCD Property SITE 11 Concrete Plant site Benefits of Consolidated Facility • Building and Site Efficiencies • Operational Efficiencies • Addresses Space Deficiencies • Addresses Renovations and Capital Renewal Requirements for WCD • Provides for a Centrally Located Site that Accommodates Program • Consolidates Integrated Services on One Centrally Located Site Site 11: 9.3 acres Site 13: 14.4 acres Total: 23.7 acres
  • 5. Building Design and Construction Division Site Plan 5 Stormwater Wastewater Facility Clara Barton Dr . Fairfax County Pkwy 1 7 5 4 8 2 3 6 -
  • 6. Building Design and Construction Division Site Plan 6 Stormwater Wastewater Facility
  • 7. Building Design and Construction Division Stormwater Wastewater Facility Project Enhancement 7 Features • Targeting LEED Gold Certification • Green Roof • Solar Ready-Photovoltaics Panels • Electrical Vehicles Ready • Geothermal • Rainwater Harvesting • Stormwater Cisterns • Natural Landscaping • Bioretention Facilities • Pervious Pavement Types • Green Wall • Video Wall • Education • Fencing Photovoltaics Panels Green Roof Rainwater Harvesting Stormwater Cistern Pervious Pavement Types Green Wall Geothermal Fence
  • 8. Building Design and Construction Division Administrative Offices & Support Area - Building 1 8 Stormwater Wastewater Facility Building 1 – South Façade Front Elevation Building 1 – North Façade Main Entrance Building 1 – Main Entrance
  • 9. Building Design and Construction Division Proposed Construction Phasing 9 Stormwater Wastewater Facility Construction Entrance 1 (primary entrance for Phase 1) Construction Entrance 2 Construction Entrance 3
  • 10. Building Design and Construction Division Stormwater Wastewater Facility Construction Activities 10 Notice-to-proceed issued: March 15, 2022 Work Underway or Completed: • Contractor procurement & submittal coordination • Site Surveying • Phase 1 Area site mobilization & contractor staging • Site clearing, tree tagging, protection & select removal • Installation of E&S control & LOD confirmed • Safety fencing secured Look-Ahead: • Phase 1: • Deconstruction of concrete plant & site preparation • Construction Buildings 2-8 • Phase 1 Area connection to Freds Oak Road • Phase 2: • Building 1 & site features • Phase 3: • Transition of existing WCD operations into Building 1 • Demolition of Existing WCD building & remaining site/landscape work
  • 11. Building Design and Construction Division Stormwater Wastewater Facility Construction Operations 11 ✓ Hours of operation: M-F 7 AM to 4 PM, Saturdays 9 AM start(occasional) ✓ County noise ordinance will be followed ✓ Phase 1 construction area secured with perimeter safety fencing ✓ Dust and stormwater control measures will be in place ✓ Phase 1 construction traffic: Clara Barton Drive (primary access) Southern Freds Oak Road entrance also utilized ✓ Phase 2 & 3 construction traffic: Freds Oak entrances mainly utilized ✓ Existing WCD will remain operational throughout 3.5-4 yr. construction
  • 12. Building Design and Construction Division Stormwater Wastewater Facility Proposed Construction Schedule 12 *Schedule projection based on standard construction scheduling parameters. Actual schedule may be impacted by unforeseen weather and other natural occurrences. Proposed Schedule* • Start: March 2022 • Phase 1: Fall 2023 • Phase 2: Early 2025 • Phase 3: Fall 2025 • Completion: Fall 2025
  • 13. Building Design and Construction Division Project Communication 13 Stormwater Wastewater Consolidation Main Points of Contact: For Updates Visit the Project Website at: https://www.fairfaxcounty.gov/publicworks/proposed-stormwater-and-wastewater-consolidation-facility POC Email or Phone Project Design Allison Terzigni, Senior Design Manager Allison.Terzigni@FairfaxCounty.gov Project Construction/Safety Eric James, Senior Construction Manager John.James@FairfaxCounty.gov Onsite Wastewater Operations Shwan Fatah, Director WCD Shwan.Fatah@FairfaxCounty.gov Wastewater Emergency Trouble Response Center (703) 323-1211
  • 14. Building Design and Construction Division Questions & Answers 14 Stormwater Wastewater Facility