This project will restore 2,800 feet of stream in Ridgeview Park and surrounding properties. The streambed and banks will be stabilized to reduce sediment and nutrient inputs into stream system. Improved habitat will provide better ecology.
Pike Branch Tributary at Ridgeview Park - October 2015Fairfax County
This document discusses a stream restoration project along Pike Branch Tributary at Ridgeview Park in Fairfax County, VA. It aims to restore 3,300 feet of stream and stabilize streambeds and banks to reduce sediment and nutrient inputs. The project goals are to improve watershed conditions, reduce flooding and erosion, and protect infrastructure. The document outlines the existing poor conditions of the stream banks, describes typical restoration structures to be used such as plunge pools and cross vanes, and provides examples of previous successful stream restoration projects. It concludes by discussing next steps which include completing assessments, designing concepts, and holding community meetings.
Flag Run at Elgar Street Stream Restoration Project - May 24, 2017Fairfax County
The project will restore about 2,900 linear feet of the channel to stabilize the banks and prevent future erosion. A healthy ecosystem will be created by installing native trees and herbaceous plants.
Crook Branch at Mantua Elementary School Stream Restoration Community Meeting...Fairfax County
A section of Crook Branch will be restored to accomplish the following goals:
Stabilize stream
Reduce excess sediment from being transported downstream
Reduce excess nutrients from entering the waterway
Improve aesthetics
Reduce hazards (steep, eroding banks)
Reconnect stream to floodplain
Improve Riparian Buffers
Dead Run at Georgetown Pike Stream Restoration Fairfax County
Stabilize streambed and banks, ~5,600 linear feet
Reduce sediment and nutrient inputs into stream system
Installation of grade control structures, improve/correct channel dimension and alignment
Improve floodplain connectivity and ecological processes
Increase frequency and residence time of water on floodplain
Reduce force and volume of water within the channel during storm and flood events
Naturally process nutrients and sediments on the floodplain and within the streambed
Improve habitat for biological community
Native landscaping
Floodplain wetlands
Streambed and flow diversity
In-stream structures
Protect Infrastructure – Sanitary Sewer Lines
Channel Relocation away from sanitary sewer lines when possible
Armoring channel banks and bottom where relocation is not an option
Little Pimmit Run at Woodland Terrace Community Meeting 09 30-2020Fairfax County
A community meeting was held on Sept 30, 2020 to inform residents and gather information from them about the stream restoration project at Little Pimmit Run Tributary at Woodland Terrace.
Pike Branch Tributary at Ridgeview Park - October 2015Fairfax County
This document discusses a stream restoration project along Pike Branch Tributary at Ridgeview Park in Fairfax County, VA. It aims to restore 3,300 feet of stream and stabilize streambeds and banks to reduce sediment and nutrient inputs. The project goals are to improve watershed conditions, reduce flooding and erosion, and protect infrastructure. The document outlines the existing poor conditions of the stream banks, describes typical restoration structures to be used such as plunge pools and cross vanes, and provides examples of previous successful stream restoration projects. It concludes by discussing next steps which include completing assessments, designing concepts, and holding community meetings.
Flag Run at Elgar Street Stream Restoration Project - May 24, 2017Fairfax County
The project will restore about 2,900 linear feet of the channel to stabilize the banks and prevent future erosion. A healthy ecosystem will be created by installing native trees and herbaceous plants.
Crook Branch at Mantua Elementary School Stream Restoration Community Meeting...Fairfax County
A section of Crook Branch will be restored to accomplish the following goals:
Stabilize stream
Reduce excess sediment from being transported downstream
Reduce excess nutrients from entering the waterway
Improve aesthetics
Reduce hazards (steep, eroding banks)
Reconnect stream to floodplain
Improve Riparian Buffers
Dead Run at Georgetown Pike Stream Restoration Fairfax County
Stabilize streambed and banks, ~5,600 linear feet
Reduce sediment and nutrient inputs into stream system
Installation of grade control structures, improve/correct channel dimension and alignment
Improve floodplain connectivity and ecological processes
Increase frequency and residence time of water on floodplain
Reduce force and volume of water within the channel during storm and flood events
Naturally process nutrients and sediments on the floodplain and within the streambed
Improve habitat for biological community
Native landscaping
Floodplain wetlands
Streambed and flow diversity
In-stream structures
Protect Infrastructure – Sanitary Sewer Lines
Channel Relocation away from sanitary sewer lines when possible
Armoring channel banks and bottom where relocation is not an option
Little Pimmit Run at Woodland Terrace Community Meeting 09 30-2020Fairfax County
A community meeting was held on Sept 30, 2020 to inform residents and gather information from them about the stream restoration project at Little Pimmit Run Tributary at Woodland Terrace.
Fairfax County Leigh Meadow Kickoff Presentation January 2016Fairfax County
The Leigh Meadow basin retrofit and stream restoration project will improve watershed conditions, mitigate flooding where possible, reduce erosion and protect infrastructure.
Turkeycock Creek at Brookside Office Park Stream StabilizationFairfax County
The document summarizes plans by Fairfax County, VA to stabilize 350 linear feet of Turkeycock Creek near Brookside Office Park. The project will include installing a retaining wall along the creek bank next to the parking lot, in-stream stabilization features like step pools and rock sills, and native plantings. Easements will be secured in summer 2021, construction bidding will occur in fall 2021, and completion is scheduled for fall 2022. The project aims to mitigate further erosion and ensure bank stability along the creek.
Little Pimmit Run at Chesterbrook Road Stream Restoration Project - April 2021Fairfax County
Restore up to 7,100 feet of stream channel and connecting tributaries
Reduce sediment transport
Protect existing infrastructure
Coordinate with Little Pimmit Run Sewer Realignment Project
Maintain close coordination with stakeholders
Peyton Run at Longwood Knolls Community Meeting Oct 1, 2018Fairfax County
This project will restore up to 2,500 feet of stream on Longwood Knolls HOA and Cherry Run section 3 subdivision properties. Sediment and nutrient inputs will be reduced and habitat will be improved.
Dead Run Stream Restoration at McLean Central Park - Segments 2 and 3Fairfax County
The project restored approximately 3,000 linear feet of stream within the Dead Run Watershed which drains directly to the Potomac River in McLean, Virginia. Restoration of the stream was achieved using natural channel design principles. The project included boulder riffles, step pools, log vanes, root wad structures, buried rock sills, reinforced stream bed material, removal of invasive plants and the re-establishment of the riparian buffer with native species.
Crook at Mantua Elementary School Stream RestorationFairfax County
3,700 linear feet of stream will be restored using Natural Channel Design methodologies
Pollutant reduction
2,986 lbs/total phosphorus
6,483 lbs/total nitrogren
514.6 tons of total suspended sediment
Protection of private property and public infrastructure
Increased ecological diversity with native vegetation
DEQ has awarded a SLAF grant to this project for these environmental benefits
Leigh Meadow & Towlston Basin (0584DP/0103DP)Fairfax County
Leigh Meadow & Towlston Basin project was substantially completed on October 29, 2021. This project consists of 1,660 feet of stream restoration, a 22,300 cubic foot Regenerative Stormwater Conveyance (RSC) facility and a 28,500 cubic foot sand filter. The scope of work also included grading, excavation, pollution and sediment removal, and restoration planting.
The document summarizes a community meeting to discuss the conceptual design for the Huntington Levee project. The meeting covered the project background and flooding issues facing the community. It then reviewed the conceptual design features being considered, including the use of collection drains versus a cutoff wall, different locations for a pump station, options for stormwater diversion, and use of an earthen levee alone or in combination with an I-wall. The design aims to meet FEMA accreditation standards to reduce flooding and received feedback from the community.
Lakevale Sewer Improvements Community MeetingFairfax County
The document summarizes sewer improvement plans for Lakevale, VA following a sewer backup event. Short term plans include installing backflow devices on homes impacted by the backup and maintenance before storms. Mid term plans involve temporary pump station modifications. Long term plans include hydraulic modeling of system alternatives, preliminary engineering and design reports, and construction which may include upsizing pipes and storage. Community input will be gathered during planning, design, and construction through public meetings and an online project website.
The Sutton Oaks Pond Improvements project is located within the Cub Run Watershed. This project included restoration and improvement of the maintenance access road, extension of the existing principal spillway pipe, extension of an existing storm sewer pipe, removal of sediment from the basin, stabilization of two incoming channels, minor grading of the dam embankment, installation of a forebay using imbricated stones, and stabilization of the emergency spillway.
Paul Spring Branch at Sherwood Hall Stream Restoration ProjectFairfax County
The plan is to return the form and function of the channel to dynamic equilibrium and improve the ecological processes of the riparian corridor within the constraints of the developed landscape.
Piney Run at Lake Werowance Stream Restoration Project Oct 2019Fairfax County
Restore approximately 3,500 feet of stream on Lake Werowance Inc. and privately owned properties.
Stabilize streambed and banks
Reduce sediment and nutrient inputs into stream system
Improve habitat
Maintain close coordination with stakeholders
Enhance water quality and biological diversity through the enhancements of existing wetland features within the former lakebed
Powerpoint tripps run at barrett road presentation websiteFairfax County
This document summarizes a study of flood mitigation scenarios for Tripps Run at Barrett Road in Fairfax County, VA. Four scenarios were analyzed: 1) raising a bridge, 2) stream enhancements without property acquisition, 3) acquiring 9 properties for floodplain restoration, and 4) acquiring 16 properties for restoration. Scenario 3 provided the best balance of benefits, reducing flood levels by up to 4.6 feet, removing 13 structures from the floodplain, and costing an estimated $12.7 million. The consultants recommended pursuing additional information to support a decision on implementing Scenario 3.
Pohick Creek Tributary at Greentree Village Park Stream RestorationFairfax County
The Pohick Creek Tributary at Greentree Village Park Stream Restoration project included restoration of approximately 2,500 linear feet of stream using Natural Channel Design. The project enhanced and stabilized the degraded stream channel, bed and bank, provided water quality benefits and aesthetics, and prevented further erosion. The project includes in-stream structures, realignment of a portion of the channel, engineered regenerative mix to promote groundwater recharge, fiberglass pedestrian bridge, and the re-establishment of the riparian buffer with native species.
The project included rehabilitation of approximately 1,641 linear feet of 24-inch diameter pipe with cured-in-place pipe liner and replacement of 175 linear feet of sanitary sewer pipe. Crushed glass from the I-95 Landfill Complex was used as bedding material for the pipe replacement portion of work.
Long Branch at Arlington Boulevard and Robin Ridge Court - Concept Design and...Fairfax County
Restore streambed and banks, ~4,500 linear feet
Reduce sediment and nutrient inputs into stream system
Installation of grade control structures, improve/correct channel dimension and alignment
Improve floodplain connectivity and ecological processes
Reduce force and volume of water within the channel during storm and flood events
Naturally process nutrients and sediments on the floodplain and within the streambed
Improve habitat for biological community
Native landscaping
Floodplain wetlands
Streambed and flow diversity
In-stream structures
Protect Infrastructure – Sanitary Sewer Lines
Channel Relocation away from sanitary sewer lines when possible
Armoring channel banks and bottom where relocation is not an option
Restore ~1,400 feet by returning the form and function of the channel to dynamic equilibrium and improve the ecological processes of the riparian corridor.
Stabilize the eroding stream banks
Water quality improvement
Sustainability
Infrastructure protection
Habitat improvement
Fairfax County Leigh Meadow Kickoff Presentation January 2016Fairfax County
The Leigh Meadow basin retrofit and stream restoration project will improve watershed conditions, mitigate flooding where possible, reduce erosion and protect infrastructure.
Turkeycock Creek at Brookside Office Park Stream StabilizationFairfax County
The document summarizes plans by Fairfax County, VA to stabilize 350 linear feet of Turkeycock Creek near Brookside Office Park. The project will include installing a retaining wall along the creek bank next to the parking lot, in-stream stabilization features like step pools and rock sills, and native plantings. Easements will be secured in summer 2021, construction bidding will occur in fall 2021, and completion is scheduled for fall 2022. The project aims to mitigate further erosion and ensure bank stability along the creek.
Little Pimmit Run at Chesterbrook Road Stream Restoration Project - April 2021Fairfax County
Restore up to 7,100 feet of stream channel and connecting tributaries
Reduce sediment transport
Protect existing infrastructure
Coordinate with Little Pimmit Run Sewer Realignment Project
Maintain close coordination with stakeholders
Peyton Run at Longwood Knolls Community Meeting Oct 1, 2018Fairfax County
This project will restore up to 2,500 feet of stream on Longwood Knolls HOA and Cherry Run section 3 subdivision properties. Sediment and nutrient inputs will be reduced and habitat will be improved.
Dead Run Stream Restoration at McLean Central Park - Segments 2 and 3Fairfax County
The project restored approximately 3,000 linear feet of stream within the Dead Run Watershed which drains directly to the Potomac River in McLean, Virginia. Restoration of the stream was achieved using natural channel design principles. The project included boulder riffles, step pools, log vanes, root wad structures, buried rock sills, reinforced stream bed material, removal of invasive plants and the re-establishment of the riparian buffer with native species.
Crook at Mantua Elementary School Stream RestorationFairfax County
3,700 linear feet of stream will be restored using Natural Channel Design methodologies
Pollutant reduction
2,986 lbs/total phosphorus
6,483 lbs/total nitrogren
514.6 tons of total suspended sediment
Protection of private property and public infrastructure
Increased ecological diversity with native vegetation
DEQ has awarded a SLAF grant to this project for these environmental benefits
Leigh Meadow & Towlston Basin (0584DP/0103DP)Fairfax County
Leigh Meadow & Towlston Basin project was substantially completed on October 29, 2021. This project consists of 1,660 feet of stream restoration, a 22,300 cubic foot Regenerative Stormwater Conveyance (RSC) facility and a 28,500 cubic foot sand filter. The scope of work also included grading, excavation, pollution and sediment removal, and restoration planting.
The document summarizes a community meeting to discuss the conceptual design for the Huntington Levee project. The meeting covered the project background and flooding issues facing the community. It then reviewed the conceptual design features being considered, including the use of collection drains versus a cutoff wall, different locations for a pump station, options for stormwater diversion, and use of an earthen levee alone or in combination with an I-wall. The design aims to meet FEMA accreditation standards to reduce flooding and received feedback from the community.
Lakevale Sewer Improvements Community MeetingFairfax County
The document summarizes sewer improvement plans for Lakevale, VA following a sewer backup event. Short term plans include installing backflow devices on homes impacted by the backup and maintenance before storms. Mid term plans involve temporary pump station modifications. Long term plans include hydraulic modeling of system alternatives, preliminary engineering and design reports, and construction which may include upsizing pipes and storage. Community input will be gathered during planning, design, and construction through public meetings and an online project website.
The Sutton Oaks Pond Improvements project is located within the Cub Run Watershed. This project included restoration and improvement of the maintenance access road, extension of the existing principal spillway pipe, extension of an existing storm sewer pipe, removal of sediment from the basin, stabilization of two incoming channels, minor grading of the dam embankment, installation of a forebay using imbricated stones, and stabilization of the emergency spillway.
Paul Spring Branch at Sherwood Hall Stream Restoration ProjectFairfax County
The plan is to return the form and function of the channel to dynamic equilibrium and improve the ecological processes of the riparian corridor within the constraints of the developed landscape.
Piney Run at Lake Werowance Stream Restoration Project Oct 2019Fairfax County
Restore approximately 3,500 feet of stream on Lake Werowance Inc. and privately owned properties.
Stabilize streambed and banks
Reduce sediment and nutrient inputs into stream system
Improve habitat
Maintain close coordination with stakeholders
Enhance water quality and biological diversity through the enhancements of existing wetland features within the former lakebed
Powerpoint tripps run at barrett road presentation websiteFairfax County
This document summarizes a study of flood mitigation scenarios for Tripps Run at Barrett Road in Fairfax County, VA. Four scenarios were analyzed: 1) raising a bridge, 2) stream enhancements without property acquisition, 3) acquiring 9 properties for floodplain restoration, and 4) acquiring 16 properties for restoration. Scenario 3 provided the best balance of benefits, reducing flood levels by up to 4.6 feet, removing 13 structures from the floodplain, and costing an estimated $12.7 million. The consultants recommended pursuing additional information to support a decision on implementing Scenario 3.
Pohick Creek Tributary at Greentree Village Park Stream RestorationFairfax County
The Pohick Creek Tributary at Greentree Village Park Stream Restoration project included restoration of approximately 2,500 linear feet of stream using Natural Channel Design. The project enhanced and stabilized the degraded stream channel, bed and bank, provided water quality benefits and aesthetics, and prevented further erosion. The project includes in-stream structures, realignment of a portion of the channel, engineered regenerative mix to promote groundwater recharge, fiberglass pedestrian bridge, and the re-establishment of the riparian buffer with native species.
The project included rehabilitation of approximately 1,641 linear feet of 24-inch diameter pipe with cured-in-place pipe liner and replacement of 175 linear feet of sanitary sewer pipe. Crushed glass from the I-95 Landfill Complex was used as bedding material for the pipe replacement portion of work.
Long Branch at Arlington Boulevard and Robin Ridge Court - Concept Design and...Fairfax County
Restore streambed and banks, ~4,500 linear feet
Reduce sediment and nutrient inputs into stream system
Installation of grade control structures, improve/correct channel dimension and alignment
Improve floodplain connectivity and ecological processes
Reduce force and volume of water within the channel during storm and flood events
Naturally process nutrients and sediments on the floodplain and within the streambed
Improve habitat for biological community
Native landscaping
Floodplain wetlands
Streambed and flow diversity
In-stream structures
Protect Infrastructure – Sanitary Sewer Lines
Channel Relocation away from sanitary sewer lines when possible
Armoring channel banks and bottom where relocation is not an option
Restore ~1,400 feet by returning the form and function of the channel to dynamic equilibrium and improve the ecological processes of the riparian corridor.
Stabilize the eroding stream banks
Water quality improvement
Sustainability
Infrastructure protection
Habitat improvement
Hunting Creek at Fairchild MVCCA-Meeting March 7, 2018Fairfax County
This document summarizes a stream restoration project in Fairfax County, VA. The project aims to restore 1,200 feet of streams and improve water quality by reducing sediment and nutrient inputs. It will stabilize streambeds and banks, provide floodplain connectivity, and improve habitat. The presentation provides information on watershed management goals, existing stream conditions, restoration designs including typical structures, construction examples, and landscaping plans. It outlines next steps such as design reviews and permitting before anticipated construction from fall/winter 2018 to fall/winter 2019.
Rocky Run Tributary at Dulles Access Road Stream Restoration ProjectFairfax County
Restore up to 1,200 feet of stream within the wooded dry pond footprint.
Stabilize streambed and banks
Reduce sediment and nutrient inputs into stream
Improve habitat
Reduce long-term maintenance of pond
Consider water quality enhancements and a litter collection system in the open pond area
Maintain close coordination with stakeholders
Paul Spring Segment 1 at Hollin Hills Stream Restoration ProjectFairfax County
This document summarizes a stream restoration project along Paul Spring Segment 1 in Fairfax County, VA. The project aims to restore 1,600 feet of stream through stabilizing banks, reducing sediment and improving habitat. It will address issues like erosion, flooding, and loss of recreational areas. The design process involves community input, assessing existing conditions, developing conceptual plans, and securing easements. Construction will use structures like cross vanes and root wads to control flows and velocities. The project goals are to improve watershed conditions while coordinating with stakeholders.
Huntington Levee Community Meeting: Nov. 1, 2017Fairfax County
This document summarizes a community meeting about the Huntington Levee project. It provides background on past flooding issues, an overview of the levee system design which includes an I-wall, open channel, and pump station to protect homes from a 100-year storm event. It also discusses construction details and schedules, community amenities like trails, environmental considerations, and outlines ongoing community outreach and contact information.
Long Branch Central Watershed Management Area Project Overview July 2020Fairfax County
Fairfax County overview of the Long Branch Central Watershed Project restoration of eight miles of stream to achieve waste load reduction requirements and provide long term stability with less maintenance.
Banks Property Stream Restoration (DC9218)Fairfax County
The Banks Property Stream Restoration project restored 1,150 linear feet of degraded stream tributary. The project established a stable channel geometry, reconnected the stream to its floodplain, stabilized the stream bed and banks with structures like rock sills and cross-vanes, daylighted piped sections, and replanted the site with native vegetation. The restoration is estimated to reduce nitrogen, phosphorus, and sediment loads to the stream. The project involved several Fairfax County departments and private organizations and was substantially completed in November 2014.
Long Branch Central Watershed Management Area 03-03-2021Fairfax County
Project Goals:
Achieve Long Branch Central TMDL waste load reduction requirements.
Provide long-term stability and have low maintenance.
Improve water quality within the Long Branch Central watershed.
Improve habitat and environmental health (ecological lift).
This document provides information about a stream restoration project on Pike Branch at Wilton Road in Fairfax County, Virginia. It outlines the project area limits, typical restoration practices that will be used such as native vegetation planting, reinforced streambeds, and instream rock structures. It also shows examples of construction efforts like access roads and channel grading. The presentation discusses the project overview, current steps being taken to get approvals, and outlines a timeline for advertising, beginning, and completing construction over the next 2-3 years.
Long Branch Central Watershed Management Area Project Overview October 26, 2020Fairfax County
Information about development in Fairfax County, major stormwater management project drivers, a functions-based approach to stream restoration and more information about the project is included in the presentation.
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptxFairfax County
4,800 linear feet of stream will be restored using Natural Channel Design methodologies
Pollutant reduction
1,439 lbs/total phosphorus
3,400 lbs/total nitrogen
462.1 tons of total suspended sediment
Protection of private property and public infrastructure
Increased ecological diversity with native vegetation
DEQ has awarded a SLAF grant to this project for these environmental benefits
Dead Run Segment One Stream Restoration ProjectFairfax County
The document summarizes a public meeting held by Fairfax County to discuss plans for restoring a segment of Dead Run stream. The project aims to create a stable stream channel that reduces erosion and improves water quality. It will involve regrading the channel, installing structures to reduce erosion, replacing trees lost to the project, and adding two pedestrian bridges and a fording area. Attendees viewed design plans, asked questions, and were invited to provide comments and tour the project site.
Huntington Levee Community Meeting: Oct. 26. 2016Fairfax County
The document outlines plans for the Huntington Levee Project which aims to protect homes from flooding through the construction of an earthen levee and pump station, and discusses the project background, design features, construction process, community amenities, flood modeling results, permitting, schedule, environmental considerations, and community outreach efforts. Construction is scheduled to begin in early 2017 and be completed by spring 2019. The project team is committed to ongoing communication and addressing community concerns throughout construction.
Franklin Park Chesterbrook Neighborhood Project HighlightsFairfax County
This project included 3,000 linear feet of stormwater improvements that promote infiltration, improve water quality, and safely convey stormwater through the neighborhood to a stream.
Quander Road Outfall and Stream RestorationFairfax County
The Quander Road Stream Restoration project restored approximately 775 linear feet of a highly eroded storm drainage channel and 225 linear feet of an associated tributary using natural channel design techniques. This included installing structures like boulder pools, step pools, and rock sills to prevent future erosion and planting native vegetation to improve water quality. The project reduced nitrogen by over 3,000 pounds per year, phosphorus by over 1,300 pounds per year, and suspended solids by over 230 tons per year. Before the project, the stream banks were very steep and highly eroded, and the restoration efforts reconnected the channel to the floodplain and re-established natural flow dynamics.
The Bradley Acres Pond Retrofit project in Fairfax County, VA converted an existing dry pond into a constructed wetland pond. The project removed the existing trickle ditch, excavated three shallow marshes, constructed a step pool conveyance channel and plunge pool, and installed two stone weir structures. Native plants were seeded and trees/plugs were replanted. The project provides improved downstream water quality by removing nutrients and suspended solids from stormwater runoff.
Similar to Pike Branch at Ridgeview Park Stream Restoration Oct 2018 (20)
Merrifield Nursery Emergency Gravity Sewer ReplacementFairfax County
During a routine Closed-Circuit Television (CCTV) Camera inspection by Wastewater Collection Division (WCD), it was found that 45 linear feet of 8-inch asbestos reinforced concrete pipe (RCP) between MH-292 to MH-291 was within imminent danger of failing. The bottom of the RCP was missing within the 45 linear feet of repair and the pipe was on the verge of surcharging. After an immediate pre-construction meeting with Merrifield Nursery, it was agreed to work from 6pm-10am everyday of the week to avoid disruption and potentially placing patrons at risk during the biggest time of the year for Merrifield Garden Center. The contractor mobilized to the site and began the 20-foot excavation to replace 45 linear feet of broken gravity sewer. The project started on March 14th, 2022 and was substantially complete on March 23, 2022.
The Sully Basins Stormwater Pond Retrofits project was substantially completed on April 19, 2022. The project is located within the Cub Run watershed. The project consisted of repair and enhancement of multiple stormwater basins, 0326DP, 0964DP and 1484DP. The project also included construction of new stone cascades, stone weir basin structures and the construction of wetlands with high and low marsh areas. The project will facilitate improved sediment removal and improve downstream water quality using forebays and micro pools. Aquatic and natural habitat were also added within the three basins.
Clarks Crossing Road Improvements 05-13-22Fairfax County
This document summarizes a pedestrian access improvement project along Clarks Crossing Road in Fairfax County, Virginia. The project improved pedestrian and bicycle access by constructing a missing link of sidewalk between Brookside Lane and an existing sidewalk further along Clarks Crossing Road. Work included installing sidewalk, curb ramps, drainage improvements, and milling and overlaying asphalt. The project was substantially completed in March 2022 and provides approximately 200 feet of new pedestrian access along Clarks Crossing Road.
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxFairfax County
Future wastewater flows in northern Fairfax County exceed existing system capacity
Treatment capacity is available in Noman M. Cole Jr. Pollution Control Plant in Lorton, VA
New pipes and pumps are needed to move future flows to treatment plant
NEXT STEPS
Field investigations / surveys
Finalize alignments and pump station layout
Use of open cut excavation
Use of trenchless methods
Easement acquisition needed
Develop traffic control plans
Description:
The project consists of a new, 23,000 square feet, two-story, four-bay fire station facility and associated improvements to the 3.3-acre site including storm water detention, landscaping and parking. The scope also included the demolition of the existing fire station, and a temporary fire station to house the Fire and Rescue Department during construction of the new facility. The key elements of the overall project include:
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationFairfax County
Scotts Run @ Old Meadow Road Stream Restoration was substantially completed on March 30, 2022. The Scotts Run project consisted of restoring, enhancement, and stabilizing of approximately 2,930 linear feet of eroding stream using Natural Channel Design criteria. This project included two phases: Phase I was funded by proffers from a private development and Phase II was County funded. Also included was the removal of invasive non-native plants and the installation of new plantings to stabilize the stream and floodplain.
Sully Community Center Construction ProgressFairfax County
This document provides construction progress photos of the Sully Community Center in Fairfax County, Virginia. The photos show the ongoing construction of the building's exterior, interior spaces like the lobby, corridors, multi-purpose rooms, game room, gym, exercise room, and healthcare suite. The document was published by the Fairfax County Department of Public Works and Environmental Services to share updates on the construction of the new community center, which is scheduled to open in summer 2022.
Riverwood Community Meeting - 04-14-2022- Presentation.pptxFairfax County
The new 4-inch ductile iron force main will serve the surrounding community for the foreseeable future. Replacement of the force main will:
Reduce the level and frequency of maintenance required to keep the force main operating.
Prevent costly emergency repairs.
Provide residents with safe, reliable utility infrastructure.
Enhance the quality of life for residents.
Reduce risks to public health and the environment.
Burke Centre VRE Connector Phase IV project was substantially completed on March 7, 2022. This project enhanced the access to mass transit by creating a more direct connection from the VRE Station to the residential areas west of Premier Court. This project also connects the Oak Bluff community to the Virginia Rail Express (VRE) Burke Station and provides a multi-use shared pedestrian and bicycle trail for outdoor recreation.
Long Branch Public Meeting - FINAL - 04-11-2022Fairfax County
Overarching Project Goals:
-Achieve Long Branch Central TMDL waste load reduction requirements.
-Provide long-term stability and have low maintenance.
-Improve water quality within the Long Branch Central Watershed.
-Improve habitat and environmental health (ecological lift).
Objectives: Share our project understanding with the council and seek input on the unique opportunities and housing goals for this site that could help guide
our master planning process.
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT Fairfax County
The Lake Barton Dredging, Restoration, and Riser Modification project was substantially completed on December 29, 2021. The project is located within the Pohick Creek watershed. The project consisted of dredging and removal of approximately 19,100 cubic yards of sediment to restore the sediment trapping capacity and improve water quality. The project also included construction of new sediment forebays, in-lake haul roads, and riser modifications (new mid-level sluice gate and cold-water intake) to facilitate future maintenance, stabilize the shoreline, and improve downstream water quality. Fish habitat was also added within the lake.
Reston Arts Community Center Feasibility - Wrap UpFairfax County
This document summarizes a meeting about a proposed arts center in Reston, Virginia that would result from a proffer from Boston Properties for development of an area known as Block J. The meeting covered the background and objectives of community outreach efforts to understand needs for the arts venue. Feedback was shared from previous focus group meetings on performing arts, visual arts, and other topics. Key spaces discussed included a 500-seat theater, art studios, galleries, and support spaces. Next steps include further programming, cost estimating, and community input before potential design and construction.
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Fairfax County
Benefits of Consolidated Facility
Building and Site Efficiencies
Operational Efficiencies
Addresses Space Deficiencies
Addresses Renovations and Capital Renewal Requirements
for WCD
Provides for a Centrally Located Site that Accommodates Program
Consolidates Integrated Services on One Centrally Located Site
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Fairfax County
This is the 4th of 5 engagement meetings. We are excited to hear from you – your preferences, priorities, questions, hopes, concerns. The information we receive today will be used to inform the space allocations and cost estimating for discussion of the proffer by Fairfax County.
Oak Marr Pump Station Rehabilitation – Construction ProjectFairfax County
Neighborhood was built in the 1980s, and the sewer infrastructure has been in operation since.
Aged pump station equipment – pumps, valves, fans, concrete, etc.
This aging equipment has the potential of causing:
Sanitary Sewer Overflows (SSO)
Sewer back-ups into homes
Environmental damages
Maintenance problems
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Fairfax County
Identify and evaluate house flooding and public safety concerns
Improve drainage conditions to convey 100-year storm if feasible
Reduce and treat stormwater runoff at the source
Improve water quality and stream protection
Use resilient & functional designs
Make improvements compatible with characteristics of neighborhood
Partner with community to develop sound, cost effective solutions that can be collaboratively implemented and maintained
Build on lessons learned to help improve site development process for infill development
Reston Arts Center Feasibility - Focus Group Visual ArtsFairfax County
This document summarizes a focus group meeting to discuss needs and ideas for a proposed new arts center in Reston, Virginia. The meeting covered background on the proposed project, which would result from a development proffer. Attendees provided input through polls and discussion on desired visual arts programming, spaces, and amenities. Key priorities identified included studio space, galleries, classrooms, digital media facilities, and ensuring the center is diverse, equitable and accessible. The project team will take this community feedback into account as they continue planning.
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022Fairfax County
These community outreach meetings are being conducted to understand community needs for a proposed arts venue in the Reston Town Center.
The proposed arts center would be a result of a proffer from Boston Properties in the next phase of Reston Town Center development (Block J).
The proffer would provide for an approximately 60,000 gross square foot facility to house a stage suitable for large-scale music and dance performances, as well as other arts-related amenities.
Jennifer Schaus and Associates hosts a complimentary webinar series on The FAR in 2024. Join the webinars on Wednesdays and Fridays at noon, eastern.
Recordings are on YouTube and the company website.
https://www.youtube.com/@jenniferschaus/videos
Jennifer Schaus and Associates hosts a complimentary webinar series on The FAR in 2024. Join the webinars on Wednesdays and Fridays at noon, eastern.
Recordings are on YouTube and the company website.
https://www.youtube.com/@jenniferschaus/videos
Donate to charity during this holiday seasonSERUDS INDIA
For people who have money and are philanthropic, there are infinite opportunities to gift a needy person or child a Merry Christmas. Even if you are living on a shoestring budget, you will be surprised at how much you can do.
Donate Us
https://serudsindia.org/how-to-donate-to-charity-during-this-holiday-season/
#charityforchildren, #donateforchildren, #donateclothesforchildren, #donatebooksforchildren, #donatetoysforchildren, #sponsorforchildren, #sponsorclothesforchildren, #sponsorbooksforchildren, #sponsortoysforchildren, #seruds, #kurnool
Jennifer Schaus and Associates hosts a complimentary webinar series on The FAR in 2024. Join the webinars on Wednesdays and Fridays at noon, eastern.
Recordings are on YouTube and the company website.
https://www.youtube.com/@jenniferschaus/videos
Combined Illegal, Unregulated and Unreported (IUU) Vessel List.Christina Parmionova
The best available, up-to-date information on all fishing and related vessels that appear on the illegal, unregulated, and unreported (IUU) fishing vessel lists published by Regional Fisheries Management Organisations (RFMOs) and related organisations. The aim of the site is to improve the effectiveness of the original IUU lists as a tool for a wide variety of stakeholders to better understand and combat illegal fishing and broader fisheries crime.
To date, the following regional organisations maintain or share lists of vessels that have been found to carry out or support IUU fishing within their own or adjacent convention areas and/or species of competence:
Commission for the Conservation of Antarctic Marine Living Resources (CCAMLR)
Commission for the Conservation of Southern Bluefin Tuna (CCSBT)
General Fisheries Commission for the Mediterranean (GFCM)
Inter-American Tropical Tuna Commission (IATTC)
International Commission for the Conservation of Atlantic Tunas (ICCAT)
Indian Ocean Tuna Commission (IOTC)
Northwest Atlantic Fisheries Organisation (NAFO)
North East Atlantic Fisheries Commission (NEAFC)
North Pacific Fisheries Commission (NPFC)
South East Atlantic Fisheries Organisation (SEAFO)
South Pacific Regional Fisheries Management Organisation (SPRFMO)
Southern Indian Ocean Fisheries Agreement (SIOFA)
Western and Central Pacific Fisheries Commission (WCPFC)
The Combined IUU Fishing Vessel List merges all these sources into one list that provides a single reference point to identify whether a vessel is currently IUU listed. Vessels that have been IUU listed in the past and subsequently delisted (for example because of a change in ownership, or because the vessel is no longer in service) are also retained on the site, so that the site contains a full historic record of IUU listed fishing vessels.
Unlike the IUU lists published on individual RFMO websites, which may update vessel details infrequently or not at all, the Combined IUU Fishing Vessel List is kept up to date with the best available information regarding changes to vessel identity, flag state, ownership, location, and operations.
UN WOD 2024 will take us on a journey of discovery through the ocean's vastness, tapping into the wisdom and expertise of global policy-makers, scientists, managers, thought leaders, and artists to awaken new depths of understanding, compassion, collaboration and commitment for the ocean and all it sustains. The program will expand our perspectives and appreciation for our blue planet, build new foundations for our relationship to the ocean, and ignite a wave of action toward necessary change.
Contributi dei parlamentari del PD - Contributi L. 3/2019Partito democratico
DI SEGUITO SONO PUBBLICATI, AI SENSI DELL'ART. 11 DELLA LEGGE N. 3/2019, GLI IMPORTI RICEVUTI DALL'ENTRATA IN VIGORE DELLA SUDDETTA NORMA (31/01/2019) E FINO AL MESE SOLARE ANTECEDENTE QUELLO DELLA PUBBLICAZIONE SUL PRESENTE SITO
Food safety, prepare for the unexpected - So what can be done in order to be ready to address food safety, food Consumers, food producers and manufacturers, food transporters, food businesses, food retailers can ...
RFP for Reno's Community Assistance CenterThis Is Reno
Property appraisals completed in May for downtown Reno’s Community Assistance and Triage Centers (CAC) reveal that repairing the buildings to bring them back into service would cost an estimated $10.1 million—nearly four times the amount previously reported by city staff.
About Potato, The scientific name of the plant is Solanum tuberosum (L).Christina Parmionova
The potato is a starchy root vegetable native to the Americas that is consumed as a staple food in many parts of the world. Potatoes are tubers of the plant Solanum tuberosum, a perennial in the nightshade family Solanaceae. Wild potato species can be found from the southern United States to southern Chile
Synopsis (short abstract) In December 2023, the UN General Assembly proclaimed 30 May as the International Day of Potato.
This report explores the significance of border towns and spaces for strengthening responses to young people on the move. In particular it explores the linkages of young people to local service centres with the aim of further developing service, protection, and support strategies for migrant children in border areas across the region. The report is based on a small-scale fieldwork study in the border towns of Chipata and Katete in Zambia conducted in July 2023. Border towns and spaces provide a rich source of information about issues related to the informal or irregular movement of young people across borders, including smuggling and trafficking. They can help build a picture of the nature and scope of the type of movement young migrants undertake and also the forms of protection available to them. Border towns and spaces also provide a lens through which we can better understand the vulnerabilities of young people on the move and, critically, the strategies they use to navigate challenges and access support.
The findings in this report highlight some of the key factors shaping the experiences and vulnerabilities of young people on the move – particularly their proximity to border spaces and how this affects the risks that they face. The report describes strategies that young people on the move employ to remain below the radar of visibility to state and non-state actors due to fear of arrest, detention, and deportation while also trying to keep themselves safe and access support in border towns. These strategies of (in)visibility provide a way to protect themselves yet at the same time also heighten some of the risks young people face as their vulnerabilities are not always recognised by those who could offer support.
In this report we show that the realities and challenges of life and migration in this region and in Zambia need to be better understood for support to be strengthened and tuned to meet the specific needs of young people on the move. This includes understanding the role of state and non-state stakeholders, the impact of laws and policies and, critically, the experiences of the young people themselves. We provide recommendations for immediate action, recommendations for programming to support young people on the move in the two towns that would reduce risk for young people in this area, and recommendations for longer term policy advocacy.
Pike Branch at Ridgeview Park Stream Restoration Oct 2018
1. A Fairfax County, VA, publication
Department of Public Works and Environmental Services
Working for You!
Pike Branch Tributary
at Ridgeview Park
Stream Restoration Project
October 2018
2. 2
Agenda
Brief Review of previous community meetings
Vicinity Map
Project Area Limits
Environmental Benefits
Project Goals
Existing Conditions
Design
Next steps
Contact information
4. 4
Pike Branch Tributary at Ridgeview Park - Project Area Limits
Fort Hill Dr.
Ridge View Dr.
Duvawn St.
Red Wood Ln.
Approximate limits of disturbance
6. 6
Project Goals
Restore up to 2,800 feet of stream in Ridgeview Park and
surrounding properties
Stabilize streambed and banks
Reduces sediment and nutrient inputs into stream system
Improve habitat for better ecology
Maintain close coordination with stakeholders
25. 25
Schedule
• Community meeting on concept design – October 2015
• Community meeting on refined concept design – May 2016
• Permitting complete – November 2017
• Design Completion – May 2018
• Construction – November 2018
(Duration 14 months)
26. 26
Contact Information
Contact Information
Design
Fred Wilkins – Project Manager
703-324-5189
Fred.Wilkins@fairfaxcounty.gov
Stormwater Planning Division
703-324-5500, TTY 711
12000 Government Center Parkway
Suite 449
Fairfax, Virginia 22035
www.fairfaxcounty.gov/publicworks/stormwater
To request this information in an alternate
format call 703-324-5500, TTY 711
Contact Information
Construction
David Becker – Project Engineer
703-324-5111
David.Becker2@fairfaxcounty.gov
Utilities Design and Construction Division
12000 Government Center Parkway
Suite 463
Fairfax, Virginia 22035
https://www.fairfaxcounty.gov/publicworks/capital-
projects