SlideShare a Scribd company logo
SUSTAINABLE
MODIFICATIONS &
INNOVATIONS
AutoCAD Semester Project Presentation
UG-CE-2011-SECTION-B
PRESENTED TO:
LEC. ABDUL BASEER
CHIEF
ENGINEER
INTERIOR
DESIGNER
FIELD
ENGINEER
CHIEF
ARCHITECT
MANAGER
HR
LEED
ENGINEER
PROFESSIONALRANKS:
MPR, SS &
COMPILATION
INDOOR
ENVIRONMENTAL
QUALITY
MATERIAL &
RESOURCES
ENERGY &
ATMOSPHERE
WATER EFFICIENCY
ENERGY &
ATMOSPHERE
DIVISION OF WORK:
OVERVIEW:
PLAN:
SIDE ELEVATION:
BACK ELEVATION:
SUSTAINABLE SITES
SS PREREQUISITE 1 : Construction
Activity Pollution Prevention
INTENT
To reduce pollution from
construction activities by
controlling soil erosion,
waterway sedimentation and
airborne dust generation.
Figure 6 SILT FENCING
Figure 7 Stockpiling the Soil to prevent erosion in an event of
storm and covering it with Sheets to avoid loss due to natural
factors.
Figure 8 Features of Temporary Seeding
WHAT WE DID:-
Does over site meet the requirements written on the left
Prime farmland as defined by the U.S. Department
of Agriculture in the United States Code of Federal
Regulations, Title 7, Volume 6, Parts 400 to 699,
Section 657.5 (citation 7CFR657.5)
NO
Previously undeveloped land whose elevation is
lower than 5 feet above the elevation of the 100-
year flood as defined by the Federal Emergency
Management Agency (FEMA)
NO
Land specifically identified as habitat for any
species on federal or state threatened or
endangered lists
NO
Land within 100 feet of any wetlands as defined by
the U.S. Code of Federal Regulations 40 CFR, Parts
230-233 and Part 22, and isolated wetlands or areas
of special concern identified by state or local rule,
OR within setback distances from wetlands
prescribed in state or local regulations, as defined
by local or state rule or law, whichever is more
stringent
NO
Previously undeveloped land that is within 50 feet
of a water body, defined as seas, lakes, rivers,
streams and tributaries that support or could
support fish, recreation or industrial use, consistent
with the terminology of the Clean Water Act
NO
nLand that prior to acquisition for the project was
public parkland, unless land of equal or greater
value as parkland is accepted in trade by the public
landowner (park authority projects are exempt).
NO
SS Credit 1: Site Selection
1 Point (SATISFIED)
INTENT : To avoid the development of inappropriate sites and reduce the
environmental impact from the location of a building on a site.
SS Credit 4.1: Alternative Transportation—Public
Transportation Access
Intent
To reduce pollution and land development impacts from
automobile use.
WHAT WE DID: We made and designed a 15 sitter bus stop to
facilitate the students and the staff.
Figure 9 A BUS STOP ADJACENT TO THE MAIN ENTRANCE
OF THE BUILDING
SS Credit 4.2: Alternative Transportation—
Bicycle Storage and Changing Rooms
Intent
To reduce pollution and land development impacts from automobile use.
WHAT WE DID:
We designed, built and provided bicycles stands just near to the main
entrances thus facilitating the students. Changing rooms were located inside
LEED Project Building.
Figure 10 Bike stands at the main entrance of the LEED Project Boundary
Figure 11 SW-ISOMETRIC VIEW OF THE BIKE STAND
SS Credit 4.3: Alternative Transportation—
Low-Emitting and Fuel-Efficient Vehicles
Figure 16 ""LOW EMITTING FUEL EFFICIENT VEHICLES ONLY"" written on the parking
spaces adjacent to the entrance to the LEED Project Figure 5 TOYOTA PRIUS C
Figure 18 MERCEDES-BENZ
SMART ELECTRIC DRIVE
CONVERTIBLE/COUPE
Figure 14 Real Life illustration of our concept which
we showed you on the previous page on AutoCAD
Figure 17 SIGN BOARDS
INSTALLED ADJACENT TO
PREFERED PARKING
S Credit 4.4: Alternative Transportation—
Parking Capacity
Figure 21 Sign Board
SS Credit 6.1 & 6.2: Storm water
Design—Quantity & Quality Control
Figure 22 Vegetated Roof
Figure 23 Pervious Pavement
Figure 25 Rain water collection tank made
underground in the lowest part of the LEED
Project Boundary. This will collect Rain water
as all the slope of the area is towards it,
which will later be used in urinal flushing. as
shown in FIG. 24A
The Dark Brown hatching shows the
permeable pavement while the light
brown shows impervious pavement.
Water Efficiency
WE credit 1: (4 points)
Water Efficient Landscaping
•Requirement: 20% less water than baseline
•No potable water for irrigation
•Use treated waste water
•Or no potable water for irrigation
Method:
•Temporary installation for 1 year
•Careful analysis before selecting species
1.Soil analysis
2.PLANNING & DESIGN
3.EFFICIENT IRRIGATION
4.PROPER PLANT SELECTION
5.PRACTICAL GRASS AREA
6.MULCHING
7.PROPER MAINTENANCE
SPECIES
1) Dohm palm
2) Athel tree
3) Cunvolvulus hystrix
SYMBOLS IN AutoCAD
Dohm palm
Athel tree
WE Credit 2: (2 points)
Innovative Wastewater Technologies:
•To reduce wastewater generation
•Treat 50% of wastewater on-site to tertiary
standards
•Use it on site for irrigation or other non potable
water use.
Innovation:
•Biological nutrient removal on site
•Remove total nitrogen(TN) and total phosphorus
(TP) by biological and chemical method
Benefits:
• No odors, No noise,
• Low energy requirement,
• sludge settling,
• Minimized operator attention
• Treated water can be used for irrigation.
ENERGY
&
ATMOSPHERE
Prerequisite 1
Fundamental Commissioning of Building Energy
Systems
Benefits of commissioning:
Reduced energy use.
Lower operating costs.
Fewer contractor call backs.
Better building documentation.
Improved occupant productivity.
Verification that the systems perform in accordance with
the owner’s project requirements.
 PREREQUISITE 2
 Minimum Energy Performance
 PREREQUISITE 3
 Fundamental Refrigerant Management
 To reduce stratospheric ozone depletion.
 LIGHTING AND DAYLIGHTING
 Opimize Energy Performance
 Lighting Controls
 Occupancy sensor with a manual override switch
Daylight brightness sensor
 Shading Controls
 Lighting for Thermal Comfort
 Shading Controls
 Facades
 Lighting Controls for Thermal Comfort
The Lumen Method of Lighting Design
 1. Select Required Illumination
 2. Determine Received Flux
 3. Select a Light Fixture
 4. Determine Mounting Height
 5. Determine Room Index
 6. Determine Utilization Factor (UF)
 7. Determine Maintenance Factor (MF)
 Good = 0.70
Medium = 0.65
Poor = 0.55
 8. Determine Number of Fixtures
 9. Check Spacing of Fixtures
To reduce ozone depletion and support early compliance while
minimizing direct contributions to climate change.
The inverter controls the compressor speed so that the system
optimizes the load distribution to deliver the capacity needed to reach
and maintain the required temperature. This technology can lower the
energy consumption for any cooling or heating application, save money
and make a contribution to a cleaner environment.
 Reduced energy consumption and low running costs.
 Improves power factor leading to better power supply quality as well
as better system diagnostics.
 Accurate temperature control.
 Near zero inrush current and improves EER (Energy Efficiency Ratio).
 Better humidity control.
 Less noise than with conventional on-off systems
 Improves Profitability
 Emit 60% less CFC’s and HCFC’s and other ozone depleting
compounds than a normal AC compressor
 Improved EER from a normal compressor by 44%
HVAC inverters are used for following purposes
 Enhanced Refrigeration system
 Enhanced Ventilation system
 Enhanced Heating and Cooling system
 Precise Temperature Control
 Precise Humidity Control
 Reduce Energy Usage
 Reduce emission of ozone depleting gases
FANS
 Variable Air Volume (VAV) systems
 Constant Air Volume (CAV) systems
 Cooling tower fans
 Condenser fans
 Boiler fans
 Car Park ventilation fans
 Stairway ventilation
PUMPS
 Chilling
 Heating
 Booster pump
 Cold and hot water pumps
 Cooling tower pumps
 Swimming pool pumps
Compressors
 Chilling
 Clean air compressors
 Gas compressors
 Heat pumps
SmartDrive HVAC
Honeywell company USA
 Special energy saving mode to provide more savings than a standard
inverter in the market for fan and pump applications.
 A proportional-integral-derivative controller (PID controller) with
advanced features built-in: Sleep mode, pressure loss compensation
, pump soft fill etc.
 Pump and fan cascade controller with full auto-change
functionality.
 Electrolyte free capacitors increase the lifetime of the product.
 Temperature-controlled fans and high switching frequency to
reduce device noise
NXL HVAC
Honeywell company USA
 Built-in proportional-integral-derivative controller
PID-controller with sleep mode for standalone applications.
 Robust design in metal frame with cooling air
completely separated from electrical parts.
 Over temperature ride through to automatically adapt
to short time over temperatures.
 Power ride through to adapt to changes in input voltage.
SmartDrive COMPACT
Honeywell company USA
 Integrated Electromagnetic interference (or EMI, also called radio-
frequency interference) filters.
 Single rating suitable for both pump and
fan or machine applications.
 Maximum ambient temperature 50oC
 Minimum ambient temperature 10oC
 Configurable Inputs and Outputs.
 Built-in PI-controller for standalone
applications
MATERIAL
&
RESOURCES
• Intent
• To facilitate the reduction of waste generated
by building occupants that is hauled to and
disposed of in landfills.
• Requirements in LEED documents for the
above intent are:
• Provide an easily-accessible dedicated area or
areas for the collection and storage of
materials for recycling for the entire building.
• Procedure being followed by us is:
• Nearest locality 2 km away from construction
site.
• Roads are available so easily accessible.
• We will also have storage facilities 0.2 Km
from the construction site.
MR Prerequisite 1: Storage and
collection of recyclables:
• Intent
• To divert construction and demolition debris
from disposal in landfills and incineration
facilities. Redirect recyclable recovered
resources back to the manufacturing process
and reusable materials to appropriate sites.
• Procedure followed by us:
• For construction waste management we are
going to perform the procedure of composting
of organic materials which are not worth being
reused instead of land filling the organic
products, so that they do not leach into the
ground water. Other non-recyclable materials
will be sent to incinerators or landfills.
MR Credit 2: Construction Waste Management:
• Intent
• To reuse building materials and products to reduce
demand for virgin materials and reduce waste,
thereby lessening impacts associated with the
extraction and processing of virgin resources
• Procedure followed by us:
• Thus to avoid wastage of materials we will have
on the spot demands made and then delivery. But
still we have storage facilities made 0.2 km away
from the construction site for materials which
cannot be delivered on the spot.
• catering the wastage of such material we will
include in our agreement with the supplier to use
them in the manufacturing process again for us to
reuse the wasted material this will reduce the
wastage and cost both.
MR Credit 3: Materials Reuse:
• Intent
• To increase demand for building materials and
products that are extracted and manufactured
within the region, thereby supporting the use of
indigenous resources and reducing the
environmental impacts resulting from
transportation.
• Procedure opted by us:
• We are using local materials for our
construction . Sources shown on the following
slides.
MR Credit 5: Regional Materials
• Meister Construction Materials
• Present in Country/Region: Saudi
Arabia(Riyadh)
• Main Products :Construction Chemicals
,Structural Steel, Recycled Base Oil, Equipments
for special Needs, Juices
MR Credit 5: Regional Materials
Continues…..
• The innovation we are using in case of materials
is corncob ash as fine aggregate in light weight
concrete for use in non-structural walls. It’s
source is:
MR Credit 5: Regional Materials
Continues…..
Ash from rice husk from rice
fields , saw dust ash from
nearby places and ash from
nearby incerators
Waste Of Corn i.e corncob
from corn fields near the
university will be
transported to the
construction site on trucks.
Ash also transported from its
respected source
Corncob
Ash
Concrete
• THE LINES COLOURED PURPLE ARE SHOWING THE USE OF
CORNCOB ASH CONCRETE IN NON-STRUCTURAL WALLS
MR Credit 5: Regional Materials
Continues…..
• Intent
• To reduce the use and depletion of finite raw
materials and long-cycle renewable materials by
replacing them with rapidly renewable
materials.
• Procedure we opted is:
• As we are using corncob and ash aggregate in
our concrete, both the materials are renewable
and are considered as wastage, and also they
are rapidly available again as both have short
production cycles
MR Credit 6: Rapidly Renewable
Materials:
• Highly energy efficient , as it has
high thermal mass.
• Indoor air is kept clean.
• Walls will absorb sound.
• Corn cob is immune to termite
attacks.
• Corn cob does not burn.
Properties of corn cob ash.
INDOOR
ENVIRONMENTAL
QUALITY
Prerequisite 1: Minimum Indoor
Air Quality Performance
 Naturally ventilated spaces comply with ASHARE
(American Society of Heating Refrigerating, and Air
Conditioning Engineer )standard (62.1-2007)
 Natural ventilation is the process of supplying and
removing air through an indoor space without using
mechanical systems. It refers to the flow of external air
to an indoor space as a result of pressure or
temperature differences
Environmental Tobacco Smoke
(ETS) Control Prerequisite
 Prohibit smoking in building
 Locate a designated smoking room on each floor
 Prohibit smoking within 25 feet of entries
Outdoor Air Delivery
Monitoring
 Atlas 4-2 co2 monitor controller
Construction Indoor Air Quality
Management Plan—During
Construction
 Make up air
 Make up air cost calculator
Construction Indoor Air Quality
Management Plan—Before
Occupancy
 Building flush out
 MERV (minimum efficiency reporting value)
 MERV rating 1 to 16
 MERV 13
Construction Indoor Air Quality
Management Plan—Before
Occupancy
Low-Emitting Materials—
Paints and Coatings
 comply with Green Seal Standard GS-11
Low-Emitting Materials—
Flooring Systems
 Comply with FloorScore2 standard
KITCHEN FLOORING
 LONECO
 50% recycle content
 Reduced VOC
 Conceal scuffing
Low-Emitting Materials—
Flooring Systems
OUTDOOR FLOORING
 LONDECK SIERRA
 withstand high volumes of pedestrian traffic and weather-wear
INDOOR FLOORING
 LONWOOD DAKOTA
 40% recycle content
KITHCEN OLD KITCHEN NEW
ATLAS IN SMOKING
ROOM
COST: COST CALCULATIONS:
 Architectural Design cost = PKR 30-40/ft2
 Constructional cost = PKR 1900-2500/ft2

 Total Area = 690000 ft2
 Covered Building area = 88000 ft2
 Exterior pavement = 589314 ft2
 Landscaping = 12686 ft2

 Architectural Design Cost :
 (Covered Building area) x (unit price per square feet)
 (88000x40) ft2x PKR/ft2
 3520000 PKR
 For three storeys
 Architectural Design Cost = 3520000 x 3
 = 10560000 PKR

 Constructional Cost:
 (Covered Building area) x (unit price per square feet)
 (88000 x 2500) ft2 x PKR/ft2
220000000 PKR
For three storeys
Constructional Cost = 220000000
x 3
=
660000000 PKR
Exterior pavement:
Exterior pavement area= 589314
ft2
Cost of 1 MRV = 21000 PKR
Total MRV = 18
Cost of total MRV = 378000 PKR
Cost of 1 Atlas CO2 Room monitor
control = 60000 PKR
Total Atlas CO2 Room monitor
control = 4
Total Cost of Atlas CO2 Room
monitor control = 240000 PKR
 Landscaping Cost:
 The cost to Install Sod averages 35 PKR per square foot
 Landscaping area= 12686 ft2

 Landscaping Cost:
 (Landscaping area) x (unit price per square feet)

 (12686x35) ft2 x PKR/ft2
 444010 PKR
 Total Cost = 680000000 PKR
Sustainable Modifications and Innovations using LEED of a Women University in Al-Dilam, K.S.A

More Related Content

What's hot

Green building GRIHA criteria 32 &33
Green building GRIHA  criteria 32 &33Green building GRIHA  criteria 32 &33
Green building GRIHA criteria 32 &33Ashish Verma
 
The Institute of Rural Research And Development (IRRAD)-Architecture case study
The Institute of Rural Research And Development (IRRAD)-Architecture case studyThe Institute of Rural Research And Development (IRRAD)-Architecture case study
The Institute of Rural Research And Development (IRRAD)-Architecture case study
Shailja km
 
buildings rated by GRIHA and LEED, sustainable buildings around the wold, gre...
buildings rated by GRIHA and LEED, sustainable buildings around the wold, gre...buildings rated by GRIHA and LEED, sustainable buildings around the wold, gre...
buildings rated by GRIHA and LEED, sustainable buildings around the wold, gre...
DhvaniR2
 
one angel square Manchester
 one angel square Manchester one angel square Manchester
one angel square Manchester
Yuktashah
 
Case Study: Sustainable Mixed-Use Development in Historic Urban Areas
Case Study: Sustainable Mixed-Use Development in Historic Urban AreasCase Study: Sustainable Mixed-Use Development in Historic Urban Areas
Case Study: Sustainable Mixed-Use Development in Historic Urban Areas
Sustainable Performance Institute
 
Green one- The first 5 Star Rated SVAGRIHA Project
Green one- The first 5 Star Rated SVAGRIHA ProjectGreen one- The first 5 Star Rated SVAGRIHA Project
Green one- The first 5 Star Rated SVAGRIHA Project
Nilanjan Bhowal
 
GREEN BUILDING SUZLON PUNE
GREEN BUILDING SUZLON PUNE GREEN BUILDING SUZLON PUNE
GREEN BUILDING SUZLON PUNE
Rameshwari Sutar
 
VGBC Online Series phần 8: Sức khoẻ và Tiện nghi trong Công trình xanh
VGBC Online Series phần 8: Sức khoẻ và Tiện nghi trong Công trình xanhVGBC Online Series phần 8: Sức khoẻ và Tiện nghi trong Công trình xanh
VGBC Online Series phần 8: Sức khoẻ và Tiện nghi trong Công trình xanh
Vietnam Green Building Council
 
Intent: The Real LEED Requirements
Intent: The Real LEED RequirementsIntent: The Real LEED Requirements
Intent: The Real LEED Requirements
Scott DeGaro
 
Green building, MSU students
Green building, MSU studentsGreen building, MSU students
Green building, MSU students
Nilesh Kachot
 
The british school design case study
The british school design case studyThe british school design case study
The british school design case study
Chandan kumar
 
ACEC Award Winning AFRC_Middletown CT Design Build
ACEC Award Winning AFRC_Middletown CT Design BuildACEC Award Winning AFRC_Middletown CT Design Build
ACEC Award Winning AFRC_Middletown CT Design BuildWilliam Naughton, P.G.
 
Itc hotel
Itc  hotelItc  hotel
Itc hotel
Shubhangi Goel
 
GRIHA RATING SYSTEM
GRIHA RATING SYSTEMGRIHA RATING SYSTEM
GRIHA RATING SYSTEM
Krina Vesuwala
 
Green Buildings - innovative green technologies and case studies
Green Buildings - innovative green technologies and case studiesGreen Buildings - innovative green technologies and case studies
Green Buildings - innovative green technologies and case studies
ctlachu
 
Case study
Case studyCase study
Case study
Vipula Mishra
 
Green Building Project
Green Building ProjectGreen Building Project
Green Building ProjectKaran Sitapara
 
Infosys Hyderabad
Infosys HyderabadInfosys Hyderabad
Infosys Hyderabad
GRIHA India
 

What's hot (20)

Green building GRIHA criteria 32 &33
Green building GRIHA  criteria 32 &33Green building GRIHA  criteria 32 &33
Green building GRIHA criteria 32 &33
 
The Institute of Rural Research And Development (IRRAD)-Architecture case study
The Institute of Rural Research And Development (IRRAD)-Architecture case studyThe Institute of Rural Research And Development (IRRAD)-Architecture case study
The Institute of Rural Research And Development (IRRAD)-Architecture case study
 
buildings rated by GRIHA and LEED, sustainable buildings around the wold, gre...
buildings rated by GRIHA and LEED, sustainable buildings around the wold, gre...buildings rated by GRIHA and LEED, sustainable buildings around the wold, gre...
buildings rated by GRIHA and LEED, sustainable buildings around the wold, gre...
 
one angel square Manchester
 one angel square Manchester one angel square Manchester
one angel square Manchester
 
leed-case-study_final-reduced
leed-case-study_final-reducedleed-case-study_final-reduced
leed-case-study_final-reduced
 
Case Study: Sustainable Mixed-Use Development in Historic Urban Areas
Case Study: Sustainable Mixed-Use Development in Historic Urban AreasCase Study: Sustainable Mixed-Use Development in Historic Urban Areas
Case Study: Sustainable Mixed-Use Development in Historic Urban Areas
 
Green one- The first 5 Star Rated SVAGRIHA Project
Green one- The first 5 Star Rated SVAGRIHA ProjectGreen one- The first 5 Star Rated SVAGRIHA Project
Green one- The first 5 Star Rated SVAGRIHA Project
 
GREEN BUILDING SUZLON PUNE
GREEN BUILDING SUZLON PUNE GREEN BUILDING SUZLON PUNE
GREEN BUILDING SUZLON PUNE
 
VGBC Online Series phần 8: Sức khoẻ và Tiện nghi trong Công trình xanh
VGBC Online Series phần 8: Sức khoẻ và Tiện nghi trong Công trình xanhVGBC Online Series phần 8: Sức khoẻ và Tiện nghi trong Công trình xanh
VGBC Online Series phần 8: Sức khoẻ và Tiện nghi trong Công trình xanh
 
Intent: The Real LEED Requirements
Intent: The Real LEED RequirementsIntent: The Real LEED Requirements
Intent: The Real LEED Requirements
 
Green building, MSU students
Green building, MSU studentsGreen building, MSU students
Green building, MSU students
 
The british school design case study
The british school design case studyThe british school design case study
The british school design case study
 
ACEC Award Winning AFRC_Middletown CT Design Build
ACEC Award Winning AFRC_Middletown CT Design BuildACEC Award Winning AFRC_Middletown CT Design Build
ACEC Award Winning AFRC_Middletown CT Design Build
 
Itc hotel
Itc  hotelItc  hotel
Itc hotel
 
GRIHA RATING SYSTEM
GRIHA RATING SYSTEMGRIHA RATING SYSTEM
GRIHA RATING SYSTEM
 
Green Buildings - innovative green technologies and case studies
Green Buildings - innovative green technologies and case studiesGreen Buildings - innovative green technologies and case studies
Green Buildings - innovative green technologies and case studies
 
Case study
Case studyCase study
Case study
 
Green buildings
Green buildings  Green buildings
Green buildings
 
Green Building Project
Green Building ProjectGreen Building Project
Green Building Project
 
Infosys Hyderabad
Infosys HyderabadInfosys Hyderabad
Infosys Hyderabad
 

Viewers also liked

Georgia Institute Of Technology Trb 2011 Presentation 3 D Pavement Imaging ...
Georgia Institute Of Technology Trb 2011 Presentation   3 D Pavement Imaging ...Georgia Institute Of Technology Trb 2011 Presentation   3 D Pavement Imaging ...
Georgia Institute Of Technology Trb 2011 Presentation 3 D Pavement Imaging ...Richard Fox-Ivey
 
Two-Lift Paving - Design Viewpoints
Two-Lift Paving - Design ViewpointsTwo-Lift Paving - Design Viewpoints
Two-Lift Paving - Design Viewpoints
Center for Transportation Research - UT Austin
 
Leed consultant review
Leed consultant reviewLeed consultant review
Leed consultant reviewJ C
 
Two Layer Porous Asphalt - Danish Experiences - BRRC Seminar 2005
Two Layer Porous Asphalt - Danish Experiences - BRRC Seminar 2005Two Layer Porous Asphalt - Danish Experiences - BRRC Seminar 2005
Two Layer Porous Asphalt - Danish Experiences - BRRC Seminar 2005
Ellebjerg
 
Noise reduction in pavement made of rubberized bituminious top layer ppt
Noise reduction in pavement made of rubberized bituminious top layer pptNoise reduction in pavement made of rubberized bituminious top layer ppt
Noise reduction in pavement made of rubberized bituminious top layer ppt
Abdul Aziz
 
Seminario Internacional Construcción y Rehabilitación con Pavimentos de Hormi...
Seminario Internacional Construcción y Rehabilitación con Pavimentos de Hormi...Seminario Internacional Construcción y Rehabilitación con Pavimentos de Hormi...
Seminario Internacional Construcción y Rehabilitación con Pavimentos de Hormi...
Instituto del cemento y Hormigón de Chile
 
Chapter 2 introduction-to_leed_rating_systems
Chapter 2 introduction-to_leed_rating_systemsChapter 2 introduction-to_leed_rating_systems
Chapter 2 introduction-to_leed_rating_systems
Venkatesh S
 
How to reduce early-age shrinkage in concrete pavement by using new technolog...
How to reduce early-age shrinkage in concrete pavement by using new technolog...How to reduce early-age shrinkage in concrete pavement by using new technolog...
How to reduce early-age shrinkage in concrete pavement by using new technolog...
Azdeen Najah
 
Randy Iwasaki: Quiet pavements
Randy Iwasaki: Quiet pavementsRandy Iwasaki: Quiet pavements
Randy Iwasaki: Quiet pavements
California Asphalt Pavement Association
 
Porous asphalt pavement for stormwater management
Porous asphalt pavement for stormwater managementPorous asphalt pavement for stormwater management
Porous asphalt pavement for stormwater management
Bhavin Sharma
 
Porous asphalt pavement
Porous asphalt pavementPorous asphalt pavement
Porous asphalt pavement
Ashif AR
 
Five Ss[1]
Five Ss[1]Five Ss[1]
Five Ss[1]
ahmad bassiouny
 
Leed v4-view-from-mep-seats-140429
Leed v4-view-from-mep-seats-140429Leed v4-view-from-mep-seats-140429
Leed v4-view-from-mep-seats-140429
Scott Bowman
 
An Introduction to the LEED Rating Systems
An Introduction to the LEED Rating SystemsAn Introduction to the LEED Rating Systems
An Introduction to the LEED Rating Systems
Allison Beer
 
LEED green buildings
LEED green buildingsLEED green buildings
LEED green buildings
Piyapong (Py) Muenprasertdee
 

Viewers also liked (15)

Georgia Institute Of Technology Trb 2011 Presentation 3 D Pavement Imaging ...
Georgia Institute Of Technology Trb 2011 Presentation   3 D Pavement Imaging ...Georgia Institute Of Technology Trb 2011 Presentation   3 D Pavement Imaging ...
Georgia Institute Of Technology Trb 2011 Presentation 3 D Pavement Imaging ...
 
Two-Lift Paving - Design Viewpoints
Two-Lift Paving - Design ViewpointsTwo-Lift Paving - Design Viewpoints
Two-Lift Paving - Design Viewpoints
 
Leed consultant review
Leed consultant reviewLeed consultant review
Leed consultant review
 
Two Layer Porous Asphalt - Danish Experiences - BRRC Seminar 2005
Two Layer Porous Asphalt - Danish Experiences - BRRC Seminar 2005Two Layer Porous Asphalt - Danish Experiences - BRRC Seminar 2005
Two Layer Porous Asphalt - Danish Experiences - BRRC Seminar 2005
 
Noise reduction in pavement made of rubberized bituminious top layer ppt
Noise reduction in pavement made of rubberized bituminious top layer pptNoise reduction in pavement made of rubberized bituminious top layer ppt
Noise reduction in pavement made of rubberized bituminious top layer ppt
 
Seminario Internacional Construcción y Rehabilitación con Pavimentos de Hormi...
Seminario Internacional Construcción y Rehabilitación con Pavimentos de Hormi...Seminario Internacional Construcción y Rehabilitación con Pavimentos de Hormi...
Seminario Internacional Construcción y Rehabilitación con Pavimentos de Hormi...
 
Chapter 2 introduction-to_leed_rating_systems
Chapter 2 introduction-to_leed_rating_systemsChapter 2 introduction-to_leed_rating_systems
Chapter 2 introduction-to_leed_rating_systems
 
How to reduce early-age shrinkage in concrete pavement by using new technolog...
How to reduce early-age shrinkage in concrete pavement by using new technolog...How to reduce early-age shrinkage in concrete pavement by using new technolog...
How to reduce early-age shrinkage in concrete pavement by using new technolog...
 
Randy Iwasaki: Quiet pavements
Randy Iwasaki: Quiet pavementsRandy Iwasaki: Quiet pavements
Randy Iwasaki: Quiet pavements
 
Porous asphalt pavement for stormwater management
Porous asphalt pavement for stormwater managementPorous asphalt pavement for stormwater management
Porous asphalt pavement for stormwater management
 
Porous asphalt pavement
Porous asphalt pavementPorous asphalt pavement
Porous asphalt pavement
 
Five Ss[1]
Five Ss[1]Five Ss[1]
Five Ss[1]
 
Leed v4-view-from-mep-seats-140429
Leed v4-view-from-mep-seats-140429Leed v4-view-from-mep-seats-140429
Leed v4-view-from-mep-seats-140429
 
An Introduction to the LEED Rating Systems
An Introduction to the LEED Rating SystemsAn Introduction to the LEED Rating Systems
An Introduction to the LEED Rating Systems
 
LEED green buildings
LEED green buildingsLEED green buildings
LEED green buildings
 

Similar to Sustainable Modifications and Innovations using LEED of a Women University in Al-Dilam, K.S.A

Sustainability In Steel Construction
Sustainability In Steel ConstructionSustainability In Steel Construction
Sustainability In Steel ConstructionMahmoud Sayed Ahmed
 
IRJET-Model House of Green Building
IRJET-Model House of Green BuildingIRJET-Model House of Green Building
IRJET-Model House of Green Building
IRJET Journal
 
LEED-EB Presentation
LEED-EB PresentationLEED-EB Presentation
LEED-EB Presentation
Kevin Sneed
 
L-paper_pulp_mill_case study-ppt (1).ppt
L-paper_pulp_mill_case study-ppt (1).pptL-paper_pulp_mill_case study-ppt (1).ppt
L-paper_pulp_mill_case study-ppt (1).ppt
nehasolanki83
 
05 Water and Energy
05 Water and Energy05 Water and Energy
05 Water and EnergyJill Watkins
 
Ramanujan IT City, Chennai - 100 % recycled water used for cooling tower
Ramanujan IT City, Chennai - 100 % recycled water used for cooling towerRamanujan IT City, Chennai - 100 % recycled water used for cooling tower
Ramanujan IT City, Chennai - 100 % recycled water used for cooling tower
Danfoss India
 
Leed Modeling
Leed ModelingLeed Modeling
Leed Modeling
Kim Mitchell
 
Sustainable Modifications and Innovations using LEED of a Women University in...
Sustainable Modifications and Innovations using LEED of a Women University in...Sustainable Modifications and Innovations using LEED of a Women University in...
Sustainable Modifications and Innovations using LEED of a Women University in...
Asadullah Malik
 
IRJET - Automatic Solar Panel Cleaning Mechanism
IRJET -  	  Automatic Solar Panel Cleaning MechanismIRJET -  	  Automatic Solar Panel Cleaning Mechanism
IRJET - Automatic Solar Panel Cleaning Mechanism
IRJET Journal
 
High Performance Green Design for High-Precision Manufacturing
High Performance Green Design for High-Precision ManufacturingHigh Performance Green Design for High-Precision Manufacturing
High Performance Green Design for High-Precision Manufacturing
cjmichal
 
Water efficient hybrid cooler -Best project of Electrical Engineering https:/...
Water efficient hybrid cooler -Best project of Electrical Engineering https:/...Water efficient hybrid cooler -Best project of Electrical Engineering https:/...
Water efficient hybrid cooler -Best project of Electrical Engineering https:/...
Prasant Kumar
 
Hearst Tower LEED Overview
Hearst Tower LEED OverviewHearst Tower LEED Overview
Hearst Tower LEED Overview
carlosvalverderojo
 
Green building presentation
Green building presentationGreen building presentation
Green building presentation
Amr Shalash
 
Sez presentation-6
Sez presentation-6Sez presentation-6
Sez presentation-6domsr
 
Austin Energy RP/SOC/NOC Finish-Out - LEED Report
Austin Energy RP/SOC/NOC Finish-Out - LEED ReportAustin Energy RP/SOC/NOC Finish-Out - LEED Report
Austin Energy RP/SOC/NOC Finish-Out - LEED Report
Austin Office of the City Architect
 
LEED India + Case Study : CII Sohrabji Godrej, ITC Green Center
LEED India + Case Study : CII Sohrabji Godrej, ITC Green CenterLEED India + Case Study : CII Sohrabji Godrej, ITC Green Center
LEED India + Case Study : CII Sohrabji Godrej, ITC Green Center
baburajiv2007
 
Green building
Green buildingGreen building
Green building
Manthan Shah
 
Green
GreenGreen
Pramod Bisht
Pramod BishtPramod Bisht
Pramod Bisht
deepap25
 
How to build a very green DC
How to build a very green DCHow to build a very green DC
How to build a very green DC
Heembouw
 

Similar to Sustainable Modifications and Innovations using LEED of a Women University in Al-Dilam, K.S.A (20)

Sustainability In Steel Construction
Sustainability In Steel ConstructionSustainability In Steel Construction
Sustainability In Steel Construction
 
IRJET-Model House of Green Building
IRJET-Model House of Green BuildingIRJET-Model House of Green Building
IRJET-Model House of Green Building
 
LEED-EB Presentation
LEED-EB PresentationLEED-EB Presentation
LEED-EB Presentation
 
L-paper_pulp_mill_case study-ppt (1).ppt
L-paper_pulp_mill_case study-ppt (1).pptL-paper_pulp_mill_case study-ppt (1).ppt
L-paper_pulp_mill_case study-ppt (1).ppt
 
05 Water and Energy
05 Water and Energy05 Water and Energy
05 Water and Energy
 
Ramanujan IT City, Chennai - 100 % recycled water used for cooling tower
Ramanujan IT City, Chennai - 100 % recycled water used for cooling towerRamanujan IT City, Chennai - 100 % recycled water used for cooling tower
Ramanujan IT City, Chennai - 100 % recycled water used for cooling tower
 
Leed Modeling
Leed ModelingLeed Modeling
Leed Modeling
 
Sustainable Modifications and Innovations using LEED of a Women University in...
Sustainable Modifications and Innovations using LEED of a Women University in...Sustainable Modifications and Innovations using LEED of a Women University in...
Sustainable Modifications and Innovations using LEED of a Women University in...
 
IRJET - Automatic Solar Panel Cleaning Mechanism
IRJET -  	  Automatic Solar Panel Cleaning MechanismIRJET -  	  Automatic Solar Panel Cleaning Mechanism
IRJET - Automatic Solar Panel Cleaning Mechanism
 
High Performance Green Design for High-Precision Manufacturing
High Performance Green Design for High-Precision ManufacturingHigh Performance Green Design for High-Precision Manufacturing
High Performance Green Design for High-Precision Manufacturing
 
Water efficient hybrid cooler -Best project of Electrical Engineering https:/...
Water efficient hybrid cooler -Best project of Electrical Engineering https:/...Water efficient hybrid cooler -Best project of Electrical Engineering https:/...
Water efficient hybrid cooler -Best project of Electrical Engineering https:/...
 
Hearst Tower LEED Overview
Hearst Tower LEED OverviewHearst Tower LEED Overview
Hearst Tower LEED Overview
 
Green building presentation
Green building presentationGreen building presentation
Green building presentation
 
Sez presentation-6
Sez presentation-6Sez presentation-6
Sez presentation-6
 
Austin Energy RP/SOC/NOC Finish-Out - LEED Report
Austin Energy RP/SOC/NOC Finish-Out - LEED ReportAustin Energy RP/SOC/NOC Finish-Out - LEED Report
Austin Energy RP/SOC/NOC Finish-Out - LEED Report
 
LEED India + Case Study : CII Sohrabji Godrej, ITC Green Center
LEED India + Case Study : CII Sohrabji Godrej, ITC Green CenterLEED India + Case Study : CII Sohrabji Godrej, ITC Green Center
LEED India + Case Study : CII Sohrabji Godrej, ITC Green Center
 
Green building
Green buildingGreen building
Green building
 
Green
GreenGreen
Green
 
Pramod Bisht
Pramod BishtPramod Bisht
Pramod Bisht
 
How to build a very green DC
How to build a very green DCHow to build a very green DC
How to build a very green DC
 

More from Asadullah Malik

A review of advanced linear repetitive scheduling methods and techniques
A review of advanced linear repetitive scheduling methods and techniquesA review of advanced linear repetitive scheduling methods and techniques
A review of advanced linear repetitive scheduling methods and techniques
Asadullah Malik
 
Urban Transportation Planning for the Region of Waterloo
Urban Transportation Planning for the Region of WaterlooUrban Transportation Planning for the Region of Waterloo
Urban Transportation Planning for the Region of Waterloo
Asadullah Malik
 
Building Energy Simulation project by using eQuest
Building Energy Simulation project by using eQuestBuilding Energy Simulation project by using eQuest
Building Energy Simulation project by using eQuest
Asadullah Malik
 
House Energy Audit Report
House Energy Audit ReportHouse Energy Audit Report
House Energy Audit Report
Asadullah Malik
 
UN Habitat Report
UN Habitat ReportUN Habitat Report
UN Habitat Report
Asadullah Malik
 
Ways of Determining the Moisture of Soil
Ways of Determining the Moisture of SoilWays of Determining the Moisture of Soil
Ways of Determining the Moisture of Soil
Asadullah Malik
 
Shuttle Route Optimization for the Sector # H-12, Islamabad using GIS software
Shuttle Route Optimization for the Sector # H-12, Islamabad using GIS softwareShuttle Route Optimization for the Sector # H-12, Islamabad using GIS software
Shuttle Route Optimization for the Sector # H-12, Islamabad using GIS software
Asadullah Malik
 
Neighbourhood Design Report
Neighbourhood Design ReportNeighbourhood Design Report
Neighbourhood Design Report
Asadullah Malik
 
The Struve Geodetic arc & its future possibilities of being the one (Semester...
The Struve Geodetic arc & its future possibilities of being the one (Semester...The Struve Geodetic arc & its future possibilities of being the one (Semester...
The Struve Geodetic arc & its future possibilities of being the one (Semester...
Asadullah Malik
 
The Struve Geodetic arc & its future possibilities of being the one
The Struve Geodetic arc & its future possibilities of being the oneThe Struve Geodetic arc & its future possibilities of being the one
The Struve Geodetic arc & its future possibilities of being the one
Asadullah Malik
 
Shuttle Route Optimization for the Sector # H-12, Islamabad using GIS software
Shuttle Route Optimization for the Sector # H-12, Islamabad using GIS softwareShuttle Route Optimization for the Sector # H-12, Islamabad using GIS software
Shuttle Route Optimization for the Sector # H-12, Islamabad using GIS software
Asadullah Malik
 
Shuttle Route Optimization for the Sector # H-12, Islamabad using GIS software
Shuttle Route Optimization for the Sector # H-12, Islamabad using GIS softwareShuttle Route Optimization for the Sector # H-12, Islamabad using GIS software
Shuttle Route Optimization for the Sector # H-12, Islamabad using GIS software
Asadullah Malik
 
Detailed Case Study of Pind Dadan Khan, Punjab, Pakistan with special emphasi...
Detailed Case Study of Pind Dadan Khan, Punjab, Pakistan with special emphasi...Detailed Case Study of Pind Dadan Khan, Punjab, Pakistan with special emphasi...
Detailed Case Study of Pind Dadan Khan, Punjab, Pakistan with special emphasi...
Asadullah Malik
 
Final Year Project Presentation (June 2015) : INVESTIGATION OF SHEAR BEHAVIOU...
Final Year Project Presentation (June 2015) : INVESTIGATION OF SHEAR BEHAVIOU...Final Year Project Presentation (June 2015) : INVESTIGATION OF SHEAR BEHAVIOU...
Final Year Project Presentation (June 2015) : INVESTIGATION OF SHEAR BEHAVIOU...
Asadullah Malik
 

More from Asadullah Malik (14)

A review of advanced linear repetitive scheduling methods and techniques
A review of advanced linear repetitive scheduling methods and techniquesA review of advanced linear repetitive scheduling methods and techniques
A review of advanced linear repetitive scheduling methods and techniques
 
Urban Transportation Planning for the Region of Waterloo
Urban Transportation Planning for the Region of WaterlooUrban Transportation Planning for the Region of Waterloo
Urban Transportation Planning for the Region of Waterloo
 
Building Energy Simulation project by using eQuest
Building Energy Simulation project by using eQuestBuilding Energy Simulation project by using eQuest
Building Energy Simulation project by using eQuest
 
House Energy Audit Report
House Energy Audit ReportHouse Energy Audit Report
House Energy Audit Report
 
UN Habitat Report
UN Habitat ReportUN Habitat Report
UN Habitat Report
 
Ways of Determining the Moisture of Soil
Ways of Determining the Moisture of SoilWays of Determining the Moisture of Soil
Ways of Determining the Moisture of Soil
 
Shuttle Route Optimization for the Sector # H-12, Islamabad using GIS software
Shuttle Route Optimization for the Sector # H-12, Islamabad using GIS softwareShuttle Route Optimization for the Sector # H-12, Islamabad using GIS software
Shuttle Route Optimization for the Sector # H-12, Islamabad using GIS software
 
Neighbourhood Design Report
Neighbourhood Design ReportNeighbourhood Design Report
Neighbourhood Design Report
 
The Struve Geodetic arc & its future possibilities of being the one (Semester...
The Struve Geodetic arc & its future possibilities of being the one (Semester...The Struve Geodetic arc & its future possibilities of being the one (Semester...
The Struve Geodetic arc & its future possibilities of being the one (Semester...
 
The Struve Geodetic arc & its future possibilities of being the one
The Struve Geodetic arc & its future possibilities of being the oneThe Struve Geodetic arc & its future possibilities of being the one
The Struve Geodetic arc & its future possibilities of being the one
 
Shuttle Route Optimization for the Sector # H-12, Islamabad using GIS software
Shuttle Route Optimization for the Sector # H-12, Islamabad using GIS softwareShuttle Route Optimization for the Sector # H-12, Islamabad using GIS software
Shuttle Route Optimization for the Sector # H-12, Islamabad using GIS software
 
Shuttle Route Optimization for the Sector # H-12, Islamabad using GIS software
Shuttle Route Optimization for the Sector # H-12, Islamabad using GIS softwareShuttle Route Optimization for the Sector # H-12, Islamabad using GIS software
Shuttle Route Optimization for the Sector # H-12, Islamabad using GIS software
 
Detailed Case Study of Pind Dadan Khan, Punjab, Pakistan with special emphasi...
Detailed Case Study of Pind Dadan Khan, Punjab, Pakistan with special emphasi...Detailed Case Study of Pind Dadan Khan, Punjab, Pakistan with special emphasi...
Detailed Case Study of Pind Dadan Khan, Punjab, Pakistan with special emphasi...
 
Final Year Project Presentation (June 2015) : INVESTIGATION OF SHEAR BEHAVIOU...
Final Year Project Presentation (June 2015) : INVESTIGATION OF SHEAR BEHAVIOU...Final Year Project Presentation (June 2015) : INVESTIGATION OF SHEAR BEHAVIOU...
Final Year Project Presentation (June 2015) : INVESTIGATION OF SHEAR BEHAVIOU...
 

Recently uploaded

Lapbook sobre os Regimes Totalitários.pdf
Lapbook sobre os Regimes Totalitários.pdfLapbook sobre os Regimes Totalitários.pdf
Lapbook sobre os Regimes Totalitários.pdf
Jean Carlos Nunes Paixão
 
Introduction to AI for Nonprofits with Tapp Network
Introduction to AI for Nonprofits with Tapp NetworkIntroduction to AI for Nonprofits with Tapp Network
Introduction to AI for Nonprofits with Tapp Network
TechSoup
 
How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...
Jisc
 
Honest Reviews of Tim Han LMA Course Program.pptx
Honest Reviews of Tim Han LMA Course Program.pptxHonest Reviews of Tim Han LMA Course Program.pptx
Honest Reviews of Tim Han LMA Course Program.pptx
timhan337
 
Biological Screening of Herbal Drugs in detailed.
Biological Screening of Herbal Drugs in detailed.Biological Screening of Herbal Drugs in detailed.
Biological Screening of Herbal Drugs in detailed.
Ashokrao Mane college of Pharmacy Peth-Vadgaon
 
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
siemaillard
 
Supporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptxSupporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptx
Jisc
 
The approach at University of Liverpool.pptx
The approach at University of Liverpool.pptxThe approach at University of Liverpool.pptx
The approach at University of Liverpool.pptx
Jisc
 
The Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official PublicationThe Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official Publication
Delapenabediema
 
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCECLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
BhavyaRajput3
 
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXXPhrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
MIRIAMSALINAS13
 
The basics of sentences session 5pptx.pptx
The basics of sentences session 5pptx.pptxThe basics of sentences session 5pptx.pptx
The basics of sentences session 5pptx.pptx
heathfieldcps1
 
Guidance_and_Counselling.pdf B.Ed. 4th Semester
Guidance_and_Counselling.pdf B.Ed. 4th SemesterGuidance_and_Counselling.pdf B.Ed. 4th Semester
Guidance_and_Counselling.pdf B.Ed. 4th Semester
Atul Kumar Singh
 
Language Across the Curriculm LAC B.Ed.
Language Across the  Curriculm LAC B.Ed.Language Across the  Curriculm LAC B.Ed.
Language Across the Curriculm LAC B.Ed.
Atul Kumar Singh
 
CACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdfCACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdf
camakaiclarkmusic
 
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
MysoreMuleSoftMeetup
 
Instructions for Submissions thorugh G- Classroom.pptx
Instructions for Submissions thorugh G- Classroom.pptxInstructions for Submissions thorugh G- Classroom.pptx
Instructions for Submissions thorugh G- Classroom.pptx
Jheel Barad
 
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup   New Member Orientation and Q&A (May 2024).pdfWelcome to TechSoup   New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
TechSoup
 
Adversarial Attention Modeling for Multi-dimensional Emotion Regression.pdf
Adversarial Attention Modeling for Multi-dimensional Emotion Regression.pdfAdversarial Attention Modeling for Multi-dimensional Emotion Regression.pdf
Adversarial Attention Modeling for Multi-dimensional Emotion Regression.pdf
Po-Chuan Chen
 
Palestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptxPalestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptx
RaedMohamed3
 

Recently uploaded (20)

Lapbook sobre os Regimes Totalitários.pdf
Lapbook sobre os Regimes Totalitários.pdfLapbook sobre os Regimes Totalitários.pdf
Lapbook sobre os Regimes Totalitários.pdf
 
Introduction to AI for Nonprofits with Tapp Network
Introduction to AI for Nonprofits with Tapp NetworkIntroduction to AI for Nonprofits with Tapp Network
Introduction to AI for Nonprofits with Tapp Network
 
How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...
 
Honest Reviews of Tim Han LMA Course Program.pptx
Honest Reviews of Tim Han LMA Course Program.pptxHonest Reviews of Tim Han LMA Course Program.pptx
Honest Reviews of Tim Han LMA Course Program.pptx
 
Biological Screening of Herbal Drugs in detailed.
Biological Screening of Herbal Drugs in detailed.Biological Screening of Herbal Drugs in detailed.
Biological Screening of Herbal Drugs in detailed.
 
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
 
Supporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptxSupporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptx
 
The approach at University of Liverpool.pptx
The approach at University of Liverpool.pptxThe approach at University of Liverpool.pptx
The approach at University of Liverpool.pptx
 
The Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official PublicationThe Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official Publication
 
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCECLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
 
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXXPhrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
 
The basics of sentences session 5pptx.pptx
The basics of sentences session 5pptx.pptxThe basics of sentences session 5pptx.pptx
The basics of sentences session 5pptx.pptx
 
Guidance_and_Counselling.pdf B.Ed. 4th Semester
Guidance_and_Counselling.pdf B.Ed. 4th SemesterGuidance_and_Counselling.pdf B.Ed. 4th Semester
Guidance_and_Counselling.pdf B.Ed. 4th Semester
 
Language Across the Curriculm LAC B.Ed.
Language Across the  Curriculm LAC B.Ed.Language Across the  Curriculm LAC B.Ed.
Language Across the Curriculm LAC B.Ed.
 
CACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdfCACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdf
 
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
 
Instructions for Submissions thorugh G- Classroom.pptx
Instructions for Submissions thorugh G- Classroom.pptxInstructions for Submissions thorugh G- Classroom.pptx
Instructions for Submissions thorugh G- Classroom.pptx
 
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup   New Member Orientation and Q&A (May 2024).pdfWelcome to TechSoup   New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
 
Adversarial Attention Modeling for Multi-dimensional Emotion Regression.pdf
Adversarial Attention Modeling for Multi-dimensional Emotion Regression.pdfAdversarial Attention Modeling for Multi-dimensional Emotion Regression.pdf
Adversarial Attention Modeling for Multi-dimensional Emotion Regression.pdf
 
Palestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptxPalestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptx
 

Sustainable Modifications and Innovations using LEED of a Women University in Al-Dilam, K.S.A

  • 1. SUSTAINABLE MODIFICATIONS & INNOVATIONS AutoCAD Semester Project Presentation UG-CE-2011-SECTION-B PRESENTED TO: LEC. ABDUL BASEER
  • 3. MPR, SS & COMPILATION INDOOR ENVIRONMENTAL QUALITY MATERIAL & RESOURCES ENERGY & ATMOSPHERE WATER EFFICIENCY ENERGY & ATMOSPHERE DIVISION OF WORK:
  • 7.
  • 9. SS PREREQUISITE 1 : Construction Activity Pollution Prevention INTENT To reduce pollution from construction activities by controlling soil erosion, waterway sedimentation and airborne dust generation. Figure 6 SILT FENCING Figure 7 Stockpiling the Soil to prevent erosion in an event of storm and covering it with Sheets to avoid loss due to natural factors. Figure 8 Features of Temporary Seeding WHAT WE DID:-
  • 10. Does over site meet the requirements written on the left Prime farmland as defined by the U.S. Department of Agriculture in the United States Code of Federal Regulations, Title 7, Volume 6, Parts 400 to 699, Section 657.5 (citation 7CFR657.5) NO Previously undeveloped land whose elevation is lower than 5 feet above the elevation of the 100- year flood as defined by the Federal Emergency Management Agency (FEMA) NO Land specifically identified as habitat for any species on federal or state threatened or endangered lists NO Land within 100 feet of any wetlands as defined by the U.S. Code of Federal Regulations 40 CFR, Parts 230-233 and Part 22, and isolated wetlands or areas of special concern identified by state or local rule, OR within setback distances from wetlands prescribed in state or local regulations, as defined by local or state rule or law, whichever is more stringent NO Previously undeveloped land that is within 50 feet of a water body, defined as seas, lakes, rivers, streams and tributaries that support or could support fish, recreation or industrial use, consistent with the terminology of the Clean Water Act NO nLand that prior to acquisition for the project was public parkland, unless land of equal or greater value as parkland is accepted in trade by the public landowner (park authority projects are exempt). NO SS Credit 1: Site Selection 1 Point (SATISFIED) INTENT : To avoid the development of inappropriate sites and reduce the environmental impact from the location of a building on a site.
  • 11. SS Credit 4.1: Alternative Transportation—Public Transportation Access Intent To reduce pollution and land development impacts from automobile use. WHAT WE DID: We made and designed a 15 sitter bus stop to facilitate the students and the staff. Figure 9 A BUS STOP ADJACENT TO THE MAIN ENTRANCE OF THE BUILDING
  • 12. SS Credit 4.2: Alternative Transportation— Bicycle Storage and Changing Rooms Intent To reduce pollution and land development impacts from automobile use. WHAT WE DID: We designed, built and provided bicycles stands just near to the main entrances thus facilitating the students. Changing rooms were located inside LEED Project Building. Figure 10 Bike stands at the main entrance of the LEED Project Boundary Figure 11 SW-ISOMETRIC VIEW OF THE BIKE STAND
  • 13. SS Credit 4.3: Alternative Transportation— Low-Emitting and Fuel-Efficient Vehicles Figure 16 ""LOW EMITTING FUEL EFFICIENT VEHICLES ONLY"" written on the parking spaces adjacent to the entrance to the LEED Project Figure 5 TOYOTA PRIUS C Figure 18 MERCEDES-BENZ SMART ELECTRIC DRIVE CONVERTIBLE/COUPE Figure 14 Real Life illustration of our concept which we showed you on the previous page on AutoCAD Figure 17 SIGN BOARDS INSTALLED ADJACENT TO PREFERED PARKING
  • 14.
  • 15. S Credit 4.4: Alternative Transportation— Parking Capacity Figure 21 Sign Board
  • 16. SS Credit 6.1 & 6.2: Storm water Design—Quantity & Quality Control Figure 22 Vegetated Roof Figure 23 Pervious Pavement
  • 17. Figure 25 Rain water collection tank made underground in the lowest part of the LEED Project Boundary. This will collect Rain water as all the slope of the area is towards it, which will later be used in urinal flushing. as shown in FIG. 24A The Dark Brown hatching shows the permeable pavement while the light brown shows impervious pavement.
  • 19. WE credit 1: (4 points) Water Efficient Landscaping •Requirement: 20% less water than baseline •No potable water for irrigation •Use treated waste water •Or no potable water for irrigation
  • 20. Method: •Temporary installation for 1 year •Careful analysis before selecting species 1.Soil analysis 2.PLANNING & DESIGN 3.EFFICIENT IRRIGATION 4.PROPER PLANT SELECTION 5.PRACTICAL GRASS AREA 6.MULCHING 7.PROPER MAINTENANCE
  • 21. SPECIES 1) Dohm palm 2) Athel tree 3) Cunvolvulus hystrix
  • 22. SYMBOLS IN AutoCAD Dohm palm Athel tree
  • 23. WE Credit 2: (2 points) Innovative Wastewater Technologies: •To reduce wastewater generation •Treat 50% of wastewater on-site to tertiary standards •Use it on site for irrigation or other non potable water use.
  • 24. Innovation: •Biological nutrient removal on site •Remove total nitrogen(TN) and total phosphorus (TP) by biological and chemical method
  • 25.
  • 26. Benefits: • No odors, No noise, • Low energy requirement, • sludge settling, • Minimized operator attention • Treated water can be used for irrigation.
  • 28.
  • 29. Prerequisite 1 Fundamental Commissioning of Building Energy Systems Benefits of commissioning: Reduced energy use. Lower operating costs. Fewer contractor call backs. Better building documentation. Improved occupant productivity. Verification that the systems perform in accordance with the owner’s project requirements.
  • 30.  PREREQUISITE 2  Minimum Energy Performance  PREREQUISITE 3  Fundamental Refrigerant Management  To reduce stratospheric ozone depletion.
  • 31.  LIGHTING AND DAYLIGHTING  Opimize Energy Performance  Lighting Controls  Occupancy sensor with a manual override switch Daylight brightness sensor
  • 32.  Shading Controls  Lighting for Thermal Comfort  Shading Controls  Facades
  • 33.
  • 34.  Lighting Controls for Thermal Comfort
  • 35. The Lumen Method of Lighting Design  1. Select Required Illumination  2. Determine Received Flux  3. Select a Light Fixture  4. Determine Mounting Height  5. Determine Room Index  6. Determine Utilization Factor (UF)  7. Determine Maintenance Factor (MF)  Good = 0.70 Medium = 0.65 Poor = 0.55  8. Determine Number of Fixtures  9. Check Spacing of Fixtures
  • 36. To reduce ozone depletion and support early compliance while minimizing direct contributions to climate change.
  • 37. The inverter controls the compressor speed so that the system optimizes the load distribution to deliver the capacity needed to reach and maintain the required temperature. This technology can lower the energy consumption for any cooling or heating application, save money and make a contribution to a cleaner environment.
  • 38.  Reduced energy consumption and low running costs.  Improves power factor leading to better power supply quality as well as better system diagnostics.  Accurate temperature control.  Near zero inrush current and improves EER (Energy Efficiency Ratio).  Better humidity control.  Less noise than with conventional on-off systems  Improves Profitability  Emit 60% less CFC’s and HCFC’s and other ozone depleting compounds than a normal AC compressor  Improved EER from a normal compressor by 44%
  • 39. HVAC inverters are used for following purposes  Enhanced Refrigeration system  Enhanced Ventilation system  Enhanced Heating and Cooling system  Precise Temperature Control  Precise Humidity Control  Reduce Energy Usage  Reduce emission of ozone depleting gases
  • 40. FANS  Variable Air Volume (VAV) systems  Constant Air Volume (CAV) systems  Cooling tower fans  Condenser fans  Boiler fans  Car Park ventilation fans  Stairway ventilation
  • 41. PUMPS  Chilling  Heating  Booster pump  Cold and hot water pumps  Cooling tower pumps  Swimming pool pumps
  • 42. Compressors  Chilling  Clean air compressors  Gas compressors  Heat pumps
  • 43. SmartDrive HVAC Honeywell company USA  Special energy saving mode to provide more savings than a standard inverter in the market for fan and pump applications.  A proportional-integral-derivative controller (PID controller) with advanced features built-in: Sleep mode, pressure loss compensation , pump soft fill etc.  Pump and fan cascade controller with full auto-change functionality.  Electrolyte free capacitors increase the lifetime of the product.  Temperature-controlled fans and high switching frequency to reduce device noise
  • 44. NXL HVAC Honeywell company USA  Built-in proportional-integral-derivative controller PID-controller with sleep mode for standalone applications.  Robust design in metal frame with cooling air completely separated from electrical parts.  Over temperature ride through to automatically adapt to short time over temperatures.  Power ride through to adapt to changes in input voltage.
  • 45. SmartDrive COMPACT Honeywell company USA  Integrated Electromagnetic interference (or EMI, also called radio- frequency interference) filters.  Single rating suitable for both pump and fan or machine applications.  Maximum ambient temperature 50oC  Minimum ambient temperature 10oC  Configurable Inputs and Outputs.  Built-in PI-controller for standalone applications
  • 47. • Intent • To facilitate the reduction of waste generated by building occupants that is hauled to and disposed of in landfills. • Requirements in LEED documents for the above intent are: • Provide an easily-accessible dedicated area or areas for the collection and storage of materials for recycling for the entire building. • Procedure being followed by us is: • Nearest locality 2 km away from construction site. • Roads are available so easily accessible. • We will also have storage facilities 0.2 Km from the construction site. MR Prerequisite 1: Storage and collection of recyclables:
  • 48. • Intent • To divert construction and demolition debris from disposal in landfills and incineration facilities. Redirect recyclable recovered resources back to the manufacturing process and reusable materials to appropriate sites. • Procedure followed by us: • For construction waste management we are going to perform the procedure of composting of organic materials which are not worth being reused instead of land filling the organic products, so that they do not leach into the ground water. Other non-recyclable materials will be sent to incinerators or landfills. MR Credit 2: Construction Waste Management:
  • 49. • Intent • To reuse building materials and products to reduce demand for virgin materials and reduce waste, thereby lessening impacts associated with the extraction and processing of virgin resources • Procedure followed by us: • Thus to avoid wastage of materials we will have on the spot demands made and then delivery. But still we have storage facilities made 0.2 km away from the construction site for materials which cannot be delivered on the spot. • catering the wastage of such material we will include in our agreement with the supplier to use them in the manufacturing process again for us to reuse the wasted material this will reduce the wastage and cost both. MR Credit 3: Materials Reuse:
  • 50. • Intent • To increase demand for building materials and products that are extracted and manufactured within the region, thereby supporting the use of indigenous resources and reducing the environmental impacts resulting from transportation. • Procedure opted by us: • We are using local materials for our construction . Sources shown on the following slides. MR Credit 5: Regional Materials
  • 51. • Meister Construction Materials • Present in Country/Region: Saudi Arabia(Riyadh) • Main Products :Construction Chemicals ,Structural Steel, Recycled Base Oil, Equipments for special Needs, Juices MR Credit 5: Regional Materials Continues…..
  • 52. • The innovation we are using in case of materials is corncob ash as fine aggregate in light weight concrete for use in non-structural walls. It’s source is: MR Credit 5: Regional Materials Continues….. Ash from rice husk from rice fields , saw dust ash from nearby places and ash from nearby incerators Waste Of Corn i.e corncob from corn fields near the university will be transported to the construction site on trucks. Ash also transported from its respected source Corncob Ash Concrete
  • 53. • THE LINES COLOURED PURPLE ARE SHOWING THE USE OF CORNCOB ASH CONCRETE IN NON-STRUCTURAL WALLS MR Credit 5: Regional Materials Continues…..
  • 54. • Intent • To reduce the use and depletion of finite raw materials and long-cycle renewable materials by replacing them with rapidly renewable materials. • Procedure we opted is: • As we are using corncob and ash aggregate in our concrete, both the materials are renewable and are considered as wastage, and also they are rapidly available again as both have short production cycles MR Credit 6: Rapidly Renewable Materials:
  • 55. • Highly energy efficient , as it has high thermal mass. • Indoor air is kept clean. • Walls will absorb sound. • Corn cob is immune to termite attacks. • Corn cob does not burn. Properties of corn cob ash.
  • 57. Prerequisite 1: Minimum Indoor Air Quality Performance  Naturally ventilated spaces comply with ASHARE (American Society of Heating Refrigerating, and Air Conditioning Engineer )standard (62.1-2007)  Natural ventilation is the process of supplying and removing air through an indoor space without using mechanical systems. It refers to the flow of external air to an indoor space as a result of pressure or temperature differences
  • 58. Environmental Tobacco Smoke (ETS) Control Prerequisite  Prohibit smoking in building  Locate a designated smoking room on each floor  Prohibit smoking within 25 feet of entries
  • 59. Outdoor Air Delivery Monitoring  Atlas 4-2 co2 monitor controller
  • 60. Construction Indoor Air Quality Management Plan—During Construction  Make up air  Make up air cost calculator
  • 61. Construction Indoor Air Quality Management Plan—Before Occupancy  Building flush out  MERV (minimum efficiency reporting value)  MERV rating 1 to 16  MERV 13
  • 62. Construction Indoor Air Quality Management Plan—Before Occupancy
  • 63. Low-Emitting Materials— Paints and Coatings  comply with Green Seal Standard GS-11
  • 64. Low-Emitting Materials— Flooring Systems  Comply with FloorScore2 standard KITCHEN FLOORING  LONECO  50% recycle content  Reduced VOC  Conceal scuffing
  • 65. Low-Emitting Materials— Flooring Systems OUTDOOR FLOORING  LONDECK SIERRA  withstand high volumes of pedestrian traffic and weather-wear INDOOR FLOORING  LONWOOD DAKOTA  40% recycle content
  • 66. KITHCEN OLD KITCHEN NEW ATLAS IN SMOKING ROOM
  • 67. COST: COST CALCULATIONS:  Architectural Design cost = PKR 30-40/ft2  Constructional cost = PKR 1900-2500/ft2   Total Area = 690000 ft2  Covered Building area = 88000 ft2  Exterior pavement = 589314 ft2  Landscaping = 12686 ft2   Architectural Design Cost :  (Covered Building area) x (unit price per square feet)  (88000x40) ft2x PKR/ft2  3520000 PKR  For three storeys  Architectural Design Cost = 3520000 x 3  = 10560000 PKR   Constructional Cost:  (Covered Building area) x (unit price per square feet)  (88000 x 2500) ft2 x PKR/ft2 220000000 PKR For three storeys Constructional Cost = 220000000 x 3 = 660000000 PKR Exterior pavement: Exterior pavement area= 589314 ft2 Cost of 1 MRV = 21000 PKR Total MRV = 18 Cost of total MRV = 378000 PKR Cost of 1 Atlas CO2 Room monitor control = 60000 PKR Total Atlas CO2 Room monitor control = 4 Total Cost of Atlas CO2 Room monitor control = 240000 PKR
  • 68.  Landscaping Cost:  The cost to Install Sod averages 35 PKR per square foot  Landscaping area= 12686 ft2   Landscaping Cost:  (Landscaping area) x (unit price per square feet)   (12686x35) ft2 x PKR/ft2  444010 PKR  Total Cost = 680000000 PKR