SlideShare a Scribd company logo
Simple control circuits in
domestic installations:-
For domestic appliances, Single-phase, 230V, 50Hz a.c.
supply is available. Lighting circuits and power circuits are
separately controlled. Lighting circuit consists of lamp, fan
and devices upto 5A. On the other hand, power circuit
mainly consists of loads which have more than 5A i.e. 15A
capacity. In this section, we will discuss the simple control
circuit for lighting purpose.
Control of one Lamp from
one point:-
Fig. indicates the control circuit of single lamp operated
from single point or switch.
In this case, the phase wire and neutral are made
available at the lamp terminals.
Phase wire is taken through single pole single throw
(SPST) switch and neutral is directly connected to the
lamp terminal.
Switch must be connected in the phase wire and never
in the neutral wire. Similarly the fuse is always connected
in the phase wire and not in the neutral wire. This
provides more safety to the operator. If the switch is
provided in the neutral, there is a potential between the
live wire and the earth, even with the switch in the off
position. This would cause the shock to the operator
repairing the lighting points with the switch in the off
position. If the switch is in the phase wire then open (off)
position of the switch makes the entire circuit dead and
the operator does not get the shock while repairing the
lighiting points with the switch in the off position.
Two way control of Lamps or
Staircase Wiring
The circuit used for staircase lighiting is shown in fig.
In this case, there are two two-way switches used. The
first two-way switch S1 is placed near the first step of the
staircase. The other two-way switch S2 is placed at the
upper storey where the stairs end. The light point is
provided at an adequate height between the first and last
stairs.
As shown in fig. when the two-way switch S1 is moved
from position 2 to 3,the lamp gets connected between
the phase and the neutral and thus glows. Path is P – (1-
3) – (1-2) – lamp.
Having reached the top of the staircase where S2 is
installed, the switch S2 is moved from 1 to 3. Thus,the
circuit through the lamp gets broken. The circuit is open
and hence the lamp becomes OFF> The circuit path P –
(1-3) – 1 only.
In this way, the lamp which is switched ON by the lower
Switch can be switched OFF by the upper switch and vice-
versa.
fig. shows that the line diagram of a double staircase.
In this case, the person starts climbing the staircase
from the bottom. He puts on the first two-way switch S1.
Thus, the circuit through L1 is completed and the lamp
L1 gets ON. Thus L1 glows from the first switch board.
When he reaches the second switch board he puts on
the second two-way switch S2 there. This makes the
circuit of L1 open and that of L2 is complete. So the lamp
L2 glows. When he reaches the third switch board and
puts on the switch S3 there,the second lamp L2 goes OFF
and the lamp L3 goes ON. The schematic diagram is
shown fig.
Godown (Corridor) Lighting
Circuits:-
This circuit is an extension of staircase lighting circuit. This
system of wiring is done in long corridor or godown or factory
where the lamp is required to be switched ON from one
location and OFF from the another location.
When a person enters into the godown from one direction,
he can put on the light by pressing the switch installed at the
entrance of the godown on the switch board SB1.
When he reaches the second switchboard (SB2) he can put
off the first switch and put on the second switch with the help
of two-way switch provided on the same switchboard (SB2).
Again when he reaches the third switchboard (SB3), he
can put off the previous light (L2) by a switch 2 and switch
on the next lamp by switch 1 installed on the same
switchboard (SB3).This process can be repeated so long as
it is required.
Fig. shows the schematic diagram of godown wiring.
From the schematic diagram, it can be seen that there are
2 two-way switches on the switchboarda SB2,SB3,SB4.
While moving in the godown, he can put lamp L1 by
operating the first two-way switch on the switch board SB1.
When he reaches the switchboards SB2, he can operate
the two-way switch 1 on SB2. Thus lamp L2 will be connected
between the phase and neutral and will become ON.L1 can be
brought to OFF by operating the two-way switch 2 on sB2.
Again when he reaches the switchboards SB3, he can
operate the switch 2 on SB3 to put L2 OFF and operate L3 by
operating the switch 1 on SB3 and so on.

More Related Content

What's hot

Unit 01 electrical wiring diagrams
Unit 01 electrical wiring diagramsUnit 01 electrical wiring diagrams
Unit 01 electrical wiring diagrams
Parneet Chowdhary
 
UNIT - 03 LIGHTING INSTALLATION
UNIT - 03 LIGHTING INSTALLATIONUNIT - 03 LIGHTING INSTALLATION
UNIT - 03 LIGHTING INSTALLATION
PremanandDesai
 
HOME WIRING(domestic wiring)
HOME WIRING(domestic wiring)HOME WIRING(domestic wiring)
HOME WIRING(domestic wiring)
Arshad Hussain
 
Experiment no. 5
Experiment no. 5Experiment no. 5
Experiment no. 5
Suhas Chate
 
Relay
RelayRelay
Stair case wiring and tubelight wiring
Stair case wiring and tubelight wiring Stair case wiring and tubelight wiring
Stair case wiring and tubelight wiring
Harsh Parmar
 
Substations
SubstationsSubstations
Substations
itfakash
 
33/11 KV SUBSTATION
33/11 KV SUBSTATION33/11 KV SUBSTATION
33/11 KV SUBSTATION
k,l polytechnic roorkee
 
Cable Sizing Calculations
Cable Sizing CalculationsCable Sizing Calculations
Cable Sizing Calculations
Siddhartha mudgal
 
Single line diagram
Single line diagramSingle line diagram
Single line diagram
Md. Rimon Mia
 
Mechanical design of overhead lines
Mechanical design of overhead linesMechanical design of overhead lines
Mechanical design of overhead lines
Md. Rimon Mia
 
Basic Electrical
Basic Electrical Basic Electrical
Basic Electrical
ddsshukla
 
Earthing system
Earthing system   Earthing system
Earthing system
Dr Ashok Tiwari
 
Power factor correction
Power factor correctionPower factor correction
Power factor correction
utkarsh srivastav
 
Electrical wiring system - and estimation
Electrical wiring system -  and estimation Electrical wiring system -  and estimation
Electrical wiring system - and estimation
Mahfuz Sikder
 
Relays
  Relays  Relays
Electrical Wiring Practices and Diagrams
Electrical Wiring Practices and DiagramsElectrical Wiring Practices and Diagrams
Electrical Wiring Practices and Diagrams
Practicing In Some Infra Company
 
Distribution boards and Protection devices ppt
Distribution boards and Protection devices  pptDistribution boards and Protection devices  ppt
Distribution boards and Protection devices ppt
ZuhairQadri
 
Relays
RelaysRelays
Relays
PPT4U
 

What's hot (20)

Unit 01 electrical wiring diagrams
Unit 01 electrical wiring diagramsUnit 01 electrical wiring diagrams
Unit 01 electrical wiring diagrams
 
UNIT - 03 LIGHTING INSTALLATION
UNIT - 03 LIGHTING INSTALLATIONUNIT - 03 LIGHTING INSTALLATION
UNIT - 03 LIGHTING INSTALLATION
 
HOME WIRING(domestic wiring)
HOME WIRING(domestic wiring)HOME WIRING(domestic wiring)
HOME WIRING(domestic wiring)
 
Experiment no. 5
Experiment no. 5Experiment no. 5
Experiment no. 5
 
Relay
RelayRelay
Relay
 
Stair case wiring and tubelight wiring
Stair case wiring and tubelight wiring Stair case wiring and tubelight wiring
Stair case wiring and tubelight wiring
 
Substations
SubstationsSubstations
Substations
 
33/11 KV SUBSTATION
33/11 KV SUBSTATION33/11 KV SUBSTATION
33/11 KV SUBSTATION
 
Cable Sizing Calculations
Cable Sizing CalculationsCable Sizing Calculations
Cable Sizing Calculations
 
Single line diagram
Single line diagramSingle line diagram
Single line diagram
 
Mechanical design of overhead lines
Mechanical design of overhead linesMechanical design of overhead lines
Mechanical design of overhead lines
 
Basic Electrical
Basic Electrical Basic Electrical
Basic Electrical
 
ELECTRICAL WIRING
ELECTRICAL WIRINGELECTRICAL WIRING
ELECTRICAL WIRING
 
Earthing system
Earthing system   Earthing system
Earthing system
 
Power factor correction
Power factor correctionPower factor correction
Power factor correction
 
Electrical wiring system - and estimation
Electrical wiring system -  and estimation Electrical wiring system -  and estimation
Electrical wiring system - and estimation
 
Relays
  Relays  Relays
Relays
 
Electrical Wiring Practices and Diagrams
Electrical Wiring Practices and DiagramsElectrical Wiring Practices and Diagrams
Electrical Wiring Practices and Diagrams
 
Distribution boards and Protection devices ppt
Distribution boards and Protection devices  pptDistribution boards and Protection devices  ppt
Distribution boards and Protection devices ppt
 
Relays
RelaysRelays
Relays
 

Similar to Simple control circuits in domestic installations,ppt,eee

control circuit
 control circuit control circuit
control circuit
harsh kothari
 
Staircase wiring & ground wiring
Staircase wiring & ground wiringStaircase wiring & ground wiring
Staircase wiring & ground wiring
Vaibhav Tandel
 
Q2W2-3-4-DAY-circuit-diagramG9-g-10-EIM.pptx
Q2W2-3-4-DAY-circuit-diagramG9-g-10-EIM.pptxQ2W2-3-4-DAY-circuit-diagramG9-g-10-EIM.pptx
Q2W2-3-4-DAY-circuit-diagramG9-g-10-EIM.pptx
krazyseimei
 
Hyraulics-1.pptx
Hyraulics-1.pptxHyraulics-1.pptx
Hyraulics-1.pptx
NIKHILAS12
 
SIMULATION OF A BI-DIRECTIONAL DC-DC CONVERTER FOR PV APPLICATIONS
SIMULATION OF A BI-DIRECTIONAL DC-DC CONVERTER FOR PV APPLICATIONSSIMULATION OF A BI-DIRECTIONAL DC-DC CONVERTER FOR PV APPLICATIONS
SIMULATION OF A BI-DIRECTIONAL DC-DC CONVERTER FOR PV APPLICATIONS
ecij
 
Ladder logic tutorial
Ladder logic tutorialLadder logic tutorial
Ladder logic tutorialdas1964
 
Temperature Switch.pptx
Temperature Switch.pptxTemperature Switch.pptx
Temperature Switch.pptx
ADITYATHAKUR373097
 
an introduction to electro pneumatic and
an introduction to electro pneumatic andan introduction to electro pneumatic and
an introduction to electro pneumatic and
simachewyangson111
 
Starting of fluorescent tube light by using inverter circuit instead of choke...
Starting of fluorescent tube light by using inverter circuit instead of choke...Starting of fluorescent tube light by using inverter circuit instead of choke...
Starting of fluorescent tube light by using inverter circuit instead of choke...
IJERA Editor
 
508 144-151
508 144-151508 144-151
508 144-151
idescitation
 
Go down wiring
Go down wiringGo down wiring
Go down wiring
mansi acharya
 
Solar Panel Using Active Stacked Npc Multi Level Converter
Solar Panel Using Active Stacked Npc Multi Level ConverterSolar Panel Using Active Stacked Npc Multi Level Converter
Solar Panel Using Active Stacked Npc Multi Level Converter
irjes
 
IRJET- A Dual Stage Flyback Converter using VC Method
IRJET- A Dual Stage Flyback Converter using VC MethodIRJET- A Dual Stage Flyback Converter using VC Method
IRJET- A Dual Stage Flyback Converter using VC Method
IRJET Journal
 
Week 4 2_basic_of_electro_hydraulics_design
Week 4 2_basic_of_electro_hydraulics_designWeek 4 2_basic_of_electro_hydraulics_design
Week 4 2_basic_of_electro_hydraulics_design
akmal ariffin
 
Automatic Temperature Controlled Switch
Automatic Temperature Controlled SwitchAutomatic Temperature Controlled Switch
Automatic Temperature Controlled Switch
COMSATS Abbottabad
 
Adjustable dc power supply ppt
Adjustable dc power supply pptAdjustable dc power supply ppt
Adjustable dc power supply ppt
dibyendudas1996
 
Energy lesson 10
Energy lesson 10Energy lesson 10
Energy lesson 10
dhmcmillan
 
Mantenimiento de Instrumentación y Control
Mantenimiento de Instrumentación y ControlMantenimiento de Instrumentación y Control
Mantenimiento de Instrumentación y Control
petacalcomarvel
 
circuit explanation of Three phase fault analysis with auto reset for tempora...
circuit explanation of Three phase fault analysis with auto reset for tempora...circuit explanation of Three phase fault analysis with auto reset for tempora...
circuit explanation of Three phase fault analysis with auto reset for tempora...
Vikram Rawani
 

Similar to Simple control circuits in domestic installations,ppt,eee (20)

control circuit
 control circuit control circuit
control circuit
 
Staircase wiring & ground wiring
Staircase wiring & ground wiringStaircase wiring & ground wiring
Staircase wiring & ground wiring
 
Q2W2-3-4-DAY-circuit-diagramG9-g-10-EIM.pptx
Q2W2-3-4-DAY-circuit-diagramG9-g-10-EIM.pptxQ2W2-3-4-DAY-circuit-diagramG9-g-10-EIM.pptx
Q2W2-3-4-DAY-circuit-diagramG9-g-10-EIM.pptx
 
Hyraulics-1.pptx
Hyraulics-1.pptxHyraulics-1.pptx
Hyraulics-1.pptx
 
SIMULATION OF A BI-DIRECTIONAL DC-DC CONVERTER FOR PV APPLICATIONS
SIMULATION OF A BI-DIRECTIONAL DC-DC CONVERTER FOR PV APPLICATIONSSIMULATION OF A BI-DIRECTIONAL DC-DC CONVERTER FOR PV APPLICATIONS
SIMULATION OF A BI-DIRECTIONAL DC-DC CONVERTER FOR PV APPLICATIONS
 
Ladder logic tutorial
Ladder logic tutorialLadder logic tutorial
Ladder logic tutorial
 
Temperature Switch.pptx
Temperature Switch.pptxTemperature Switch.pptx
Temperature Switch.pptx
 
an introduction to electro pneumatic and
an introduction to electro pneumatic andan introduction to electro pneumatic and
an introduction to electro pneumatic and
 
Starting of fluorescent tube light by using inverter circuit instead of choke...
Starting of fluorescent tube light by using inverter circuit instead of choke...Starting of fluorescent tube light by using inverter circuit instead of choke...
Starting of fluorescent tube light by using inverter circuit instead of choke...
 
508 144-151
508 144-151508 144-151
508 144-151
 
Go down wiring
Go down wiringGo down wiring
Go down wiring
 
Solar Panel Using Active Stacked Npc Multi Level Converter
Solar Panel Using Active Stacked Npc Multi Level ConverterSolar Panel Using Active Stacked Npc Multi Level Converter
Solar Panel Using Active Stacked Npc Multi Level Converter
 
3 way switch
3 way switch3 way switch
3 way switch
 
IRJET- A Dual Stage Flyback Converter using VC Method
IRJET- A Dual Stage Flyback Converter using VC MethodIRJET- A Dual Stage Flyback Converter using VC Method
IRJET- A Dual Stage Flyback Converter using VC Method
 
Week 4 2_basic_of_electro_hydraulics_design
Week 4 2_basic_of_electro_hydraulics_designWeek 4 2_basic_of_electro_hydraulics_design
Week 4 2_basic_of_electro_hydraulics_design
 
Automatic Temperature Controlled Switch
Automatic Temperature Controlled SwitchAutomatic Temperature Controlled Switch
Automatic Temperature Controlled Switch
 
Adjustable dc power supply ppt
Adjustable dc power supply pptAdjustable dc power supply ppt
Adjustable dc power supply ppt
 
Energy lesson 10
Energy lesson 10Energy lesson 10
Energy lesson 10
 
Mantenimiento de Instrumentación y Control
Mantenimiento de Instrumentación y ControlMantenimiento de Instrumentación y Control
Mantenimiento de Instrumentación y Control
 
circuit explanation of Three phase fault analysis with auto reset for tempora...
circuit explanation of Three phase fault analysis with auto reset for tempora...circuit explanation of Three phase fault analysis with auto reset for tempora...
circuit explanation of Three phase fault analysis with auto reset for tempora...
 

More from Digvijaysinh Gohil

Hydraulic cranes
Hydraulic cranesHydraulic cranes
Hydraulic cranes
Digvijaysinh Gohil
 
Hydraulic braking systems
Hydraulic braking systemsHydraulic braking systems
Hydraulic braking systems
Digvijaysinh Gohil
 
Human resources management
Human resources managementHuman resources management
Human resources management
Digvijaysinh Gohil
 
Traits of a good listner (Communication Skills)
Traits of a good listner (Communication Skills)Traits of a good listner (Communication Skills)
Traits of a good listner (Communication Skills)
Digvijaysinh Gohil
 
Techniques of reading (Communication Skills)
Techniques of reading (Communication Skills)Techniques of reading (Communication Skills)
Techniques of reading (Communication Skills)
Digvijaysinh Gohil
 
Proxemics (Communication Skills)
Proxemics (Communication Skills)Proxemics (Communication Skills)
Proxemics (Communication Skills)
Digvijaysinh Gohil
 
Proxemics (2) (Communication Skills)
Proxemics (2) (Communication Skills)Proxemics (2) (Communication Skills)
Proxemics (2) (Communication Skills)
Digvijaysinh Gohil
 
Paralinguistic (Communication Skills)
Paralinguistic (Communication Skills)Paralinguistic (Communication Skills)
Paralinguistic (Communication Skills)
Digvijaysinh Gohil
 
Paralinguistic (2) (Communication Skills)
Paralinguistic (2) (Communication Skills)Paralinguistic (2) (Communication Skills)
Paralinguistic (2) (Communication Skills)
Digvijaysinh Gohil
 
Paralinguistic (1) (Communication Skills)
Paralinguistic (1) (Communication Skills)Paralinguistic (1) (Communication Skills)
Paralinguistic (1) (Communication Skills)
Digvijaysinh Gohil
 
Organizing a contents & preparing an outline
Organizing a contents & preparing an outlineOrganizing a contents & preparing an outline
Organizing a contents & preparing an outline
Digvijaysinh Gohil
 
Organizing a contents & preparing an outline (2)
Organizing a contents & preparing an outline (2)Organizing a contents & preparing an outline (2)
Organizing a contents & preparing an outline (2)
Digvijaysinh Gohil
 
Kinesics (Communication Skills)
Kinesics (Communication Skills)Kinesics (Communication Skills)
Kinesics (Communication Skills)
Digvijaysinh Gohil
 
Kinesics (3) (Communication Skills)
Kinesics (3) (Communication Skills)Kinesics (3) (Communication Skills)
Kinesics (3) (Communication Skills)
Digvijaysinh Gohil
 
Kinesics (2) (Communication Skills)
Kinesics (2) (Communication Skills)Kinesics (2) (Communication Skills)
Kinesics (2) (Communication Skills)
Digvijaysinh Gohil
 
Introduction to communication (Communication Skills)
Introduction to communication (Communication Skills)Introduction to communication (Communication Skills)
Introduction to communication (Communication Skills)
Digvijaysinh Gohil
 
Email etiquette (Communication Skills)
Email etiquette (Communication Skills)Email etiquette (Communication Skills)
Email etiquette (Communication Skills)
Digvijaysinh Gohil
 
Welded joints (machine design & industrial drafting )
Welded joints (machine design & industrial drafting )Welded joints (machine design & industrial drafting )
Welded joints (machine design & industrial drafting )
Digvijaysinh Gohil
 
Types of stresses and theories of failure (machine design & industrial drafti...
Types of stresses and theories of failure (machine design & industrial drafti...Types of stresses and theories of failure (machine design & industrial drafti...
Types of stresses and theories of failure (machine design & industrial drafti...
Digvijaysinh Gohil
 
Treaded joint (machine design & industrial drafting )
Treaded joint (machine design & industrial drafting )Treaded joint (machine design & industrial drafting )
Treaded joint (machine design & industrial drafting )
Digvijaysinh Gohil
 

More from Digvijaysinh Gohil (20)

Hydraulic cranes
Hydraulic cranesHydraulic cranes
Hydraulic cranes
 
Hydraulic braking systems
Hydraulic braking systemsHydraulic braking systems
Hydraulic braking systems
 
Human resources management
Human resources managementHuman resources management
Human resources management
 
Traits of a good listner (Communication Skills)
Traits of a good listner (Communication Skills)Traits of a good listner (Communication Skills)
Traits of a good listner (Communication Skills)
 
Techniques of reading (Communication Skills)
Techniques of reading (Communication Skills)Techniques of reading (Communication Skills)
Techniques of reading (Communication Skills)
 
Proxemics (Communication Skills)
Proxemics (Communication Skills)Proxemics (Communication Skills)
Proxemics (Communication Skills)
 
Proxemics (2) (Communication Skills)
Proxemics (2) (Communication Skills)Proxemics (2) (Communication Skills)
Proxemics (2) (Communication Skills)
 
Paralinguistic (Communication Skills)
Paralinguistic (Communication Skills)Paralinguistic (Communication Skills)
Paralinguistic (Communication Skills)
 
Paralinguistic (2) (Communication Skills)
Paralinguistic (2) (Communication Skills)Paralinguistic (2) (Communication Skills)
Paralinguistic (2) (Communication Skills)
 
Paralinguistic (1) (Communication Skills)
Paralinguistic (1) (Communication Skills)Paralinguistic (1) (Communication Skills)
Paralinguistic (1) (Communication Skills)
 
Organizing a contents & preparing an outline
Organizing a contents & preparing an outlineOrganizing a contents & preparing an outline
Organizing a contents & preparing an outline
 
Organizing a contents & preparing an outline (2)
Organizing a contents & preparing an outline (2)Organizing a contents & preparing an outline (2)
Organizing a contents & preparing an outline (2)
 
Kinesics (Communication Skills)
Kinesics (Communication Skills)Kinesics (Communication Skills)
Kinesics (Communication Skills)
 
Kinesics (3) (Communication Skills)
Kinesics (3) (Communication Skills)Kinesics (3) (Communication Skills)
Kinesics (3) (Communication Skills)
 
Kinesics (2) (Communication Skills)
Kinesics (2) (Communication Skills)Kinesics (2) (Communication Skills)
Kinesics (2) (Communication Skills)
 
Introduction to communication (Communication Skills)
Introduction to communication (Communication Skills)Introduction to communication (Communication Skills)
Introduction to communication (Communication Skills)
 
Email etiquette (Communication Skills)
Email etiquette (Communication Skills)Email etiquette (Communication Skills)
Email etiquette (Communication Skills)
 
Welded joints (machine design & industrial drafting )
Welded joints (machine design & industrial drafting )Welded joints (machine design & industrial drafting )
Welded joints (machine design & industrial drafting )
 
Types of stresses and theories of failure (machine design & industrial drafti...
Types of stresses and theories of failure (machine design & industrial drafti...Types of stresses and theories of failure (machine design & industrial drafti...
Types of stresses and theories of failure (machine design & industrial drafti...
 
Treaded joint (machine design & industrial drafting )
Treaded joint (machine design & industrial drafting )Treaded joint (machine design & industrial drafting )
Treaded joint (machine design & industrial drafting )
 

Recently uploaded

CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
karthi keyan
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
BrazilAccount1
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
Pipe Restoration Solutions
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
AhmedHussein950959
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
Kerry Sado
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
zwunae
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
Jayaprasanna4
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
ankuprajapati0525
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 

Recently uploaded (20)

CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 

Simple control circuits in domestic installations,ppt,eee

  • 1. Simple control circuits in domestic installations:- For domestic appliances, Single-phase, 230V, 50Hz a.c. supply is available. Lighting circuits and power circuits are separately controlled. Lighting circuit consists of lamp, fan and devices upto 5A. On the other hand, power circuit mainly consists of loads which have more than 5A i.e. 15A capacity. In this section, we will discuss the simple control circuit for lighting purpose.
  • 2. Control of one Lamp from one point:- Fig. indicates the control circuit of single lamp operated from single point or switch.
  • 3. In this case, the phase wire and neutral are made available at the lamp terminals. Phase wire is taken through single pole single throw (SPST) switch and neutral is directly connected to the lamp terminal. Switch must be connected in the phase wire and never in the neutral wire. Similarly the fuse is always connected in the phase wire and not in the neutral wire. This provides more safety to the operator. If the switch is provided in the neutral, there is a potential between the live wire and the earth, even with the switch in the off position. This would cause the shock to the operator repairing the lighting points with the switch in the off position. If the switch is in the phase wire then open (off) position of the switch makes the entire circuit dead and the operator does not get the shock while repairing the lighiting points with the switch in the off position.
  • 4. Two way control of Lamps or Staircase Wiring The circuit used for staircase lighiting is shown in fig.
  • 5. In this case, there are two two-way switches used. The first two-way switch S1 is placed near the first step of the staircase. The other two-way switch S2 is placed at the upper storey where the stairs end. The light point is provided at an adequate height between the first and last stairs. As shown in fig. when the two-way switch S1 is moved from position 2 to 3,the lamp gets connected between the phase and the neutral and thus glows. Path is P – (1- 3) – (1-2) – lamp. Having reached the top of the staircase where S2 is installed, the switch S2 is moved from 1 to 3. Thus,the circuit through the lamp gets broken. The circuit is open and hence the lamp becomes OFF> The circuit path P – (1-3) – 1 only.
  • 6. In this way, the lamp which is switched ON by the lower Switch can be switched OFF by the upper switch and vice- versa. fig. shows that the line diagram of a double staircase.
  • 7. In this case, the person starts climbing the staircase from the bottom. He puts on the first two-way switch S1. Thus, the circuit through L1 is completed and the lamp L1 gets ON. Thus L1 glows from the first switch board. When he reaches the second switch board he puts on the second two-way switch S2 there. This makes the circuit of L1 open and that of L2 is complete. So the lamp L2 glows. When he reaches the third switch board and puts on the switch S3 there,the second lamp L2 goes OFF and the lamp L3 goes ON. The schematic diagram is shown fig.
  • 8.
  • 9. Godown (Corridor) Lighting Circuits:- This circuit is an extension of staircase lighting circuit. This system of wiring is done in long corridor or godown or factory where the lamp is required to be switched ON from one location and OFF from the another location. When a person enters into the godown from one direction, he can put on the light by pressing the switch installed at the entrance of the godown on the switch board SB1. When he reaches the second switchboard (SB2) he can put off the first switch and put on the second switch with the help of two-way switch provided on the same switchboard (SB2).
  • 10. Again when he reaches the third switchboard (SB3), he can put off the previous light (L2) by a switch 2 and switch on the next lamp by switch 1 installed on the same switchboard (SB3).This process can be repeated so long as it is required. Fig. shows the schematic diagram of godown wiring.
  • 11.
  • 12. From the schematic diagram, it can be seen that there are 2 two-way switches on the switchboarda SB2,SB3,SB4. While moving in the godown, he can put lamp L1 by operating the first two-way switch on the switch board SB1. When he reaches the switchboards SB2, he can operate the two-way switch 1 on SB2. Thus lamp L2 will be connected between the phase and neutral and will become ON.L1 can be brought to OFF by operating the two-way switch 2 on sB2. Again when he reaches the switchboards SB3, he can operate the switch 2 on SB3 to put L2 OFF and operate L3 by operating the switch 1 on SB3 and so on.