SlideShare a Scribd company logo
MEASUREMENT OF QUANTITIES




                     ● Mat Naim bin Abdullah @ Mohd Asmoni
                     ● Diploma QS (UTM), BSc. QS (Glasgow
                         Caledonian University), M.Eng. Construction
                         (UTM), PhD Facilities Management (UTM)
                     ●   matnaim@utm.my
                     ●   amn871969@yahoo.com
                     ●   C04-308
                     ●   019-7573760




        www.utm.my              innovative ● entrepreneurial ● global   1
MEASUREMENT OF QUANTITIES


Assumption No. 1:       Total land area = 10m x 10m




                                  Project Title: Construction and completion of
                                  guard house
                                  Owner: Panicsonic Sdn Bhd
                                  Architect: A to Z Sdn Bhd
                                  Drawing Title: Ground beam and foundation plan
                                  -------------------------------------------------------------------------
                                  Drawn by: Sheila
                                  Checked by: Aaron




           www.utm.my            innovative ● entrepreneurial ● global                                        2
MEASUREMENT OF QUANTITIES




        www.utm.my          innovative ● entrepreneurial ● global   3
MEASUREMENT OF QUANTITIES

                      Construction Method

 1.    Preliminaries (Initial site works) - % of total cost
 2.    Site clearance and earthwork
 3.    Foundation construction (E.g. Piling and footing)
 4.    Work below lowest floor finish
 5.    Frame
 6.    Staircase
 7.    Upper Floor
 8.    Roof
 9.    Wall and partition
 10.   Door and window
 11.   Finishes
 12.   Sundries (Built-in furniture)
 13.   Building services (M&E, ICT etc)
 14.   External works (Water reticulation, landscape etc)



              www.utm.my                  innovative ● entrepreneurial ● global   4
MEASUREMENT OF QUANTITIES


Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

1) Site clearance

1.1) Clear the site including grubbing of Area of the site:
     trees, shrubs and demolish any       10 x 10 = 100m2
     existing structure and cart away
     and dump to the specified
     location.

      10.00
      10.00
     ----------
     100.00          100 m2
     ----------




                    www.utm.my                  innovative ● entrepreneurial ● global   5
MEASUREMENT OF QUANTITIES




        www.utm.my          innovative ● entrepreneurial ● global   6
MEASUREMENT OF QUANTITIES


Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

2) Foundation

2.1) Piling including all related works   Area of the building:
                                          Length = 3048 + 3048 = 6096
        6.10                              Width = 3048 + 3048 = 6096
        6.10
     ----------
      37.21         37 m2
     ----------




                    www.utm.my                 innovative ● entrepreneurial ● global   7
MEASUREMENT OF QUANTITIES


Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

2) Foundation

2.2) Excavation for pile cap            Size of pile cap = 1219 x 1219
                                        Depth of excavation:
     9/1.22                                1524 + 50 (lean concrete) = 1574
        1.22
        1.57
     ----------
      21.03        21 m3
     ----------



                                              Excavation and Lean concrete as base
                                                               for pile cap




                    www.utm.my               innovative ● entrepreneurial ● global   8
MEASUREMENT OF QUANTITIES




        www.utm.my          innovative ● entrepreneurial ● global   9
MEASUREMENT OF QUANTITIES


Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

2) Foundation
2.3) Reinforced concrete Grade 30 for   Size of pile cap:
     pile cap                           Length = 1219
                                        Width = 1219
    9/1.22                              Thickness = 305
       1.22
       0.31
    ----------
       4.15       4 m3
    ----------



                                                     Concrete for pile cap




                   www.utm.my                 innovative ● entrepreneurial ● global   10
MEASUREMENT OF QUANTITIES


Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

2) Foundation
2.4) 50mm thick lean concrete Grade     Size of pile cap:
     15 for pile cap                    Length = 1219
                                        Width = 1219
   9 / 1.22
       1.22
    ----------
     13.40        13 m2
    ----------




                                               Excavation and Lean concrete as base
                                                                for pile cap




                   www.utm.my                 innovative ● entrepreneurial ● global   11
MEASUREMENT OF QUANTITIES




        www.utm.my          innovative ● entrepreneurial ● global   12
MEASUREMENT OF QUANTITIES

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

2) Foundation

2.5) Formwork for pile cap              Size of pile cap:
                                        Length = 1219
 9 / 4 /1.22                            Width = 1219
        0.31                            Thickness = 305
     ----------
       13.62             14 m2          9/2/1.22
     ----------                              0.31 6.81

                                        9/2/1.50
                                             0.31 8.37
                                                 15.18 15m2



              Formwork for pile cap


                          www.utm.my          innovative ● entrepreneurial ● global   13
MEASUREMENT OF QUANTITIES


Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

2) Foundation
2.6) Reinforcement bar Y12 for pile cap   Length:
                                            a                    c
 9/2/ 12/ 1.53
       ----------                                      b

       330.48m x 0.89 kg/m = 294.13kg     = a + b + c – cover
       ----------                         = 305 + 1219 + 305 – 6(50)
                            = 294 kg      = 1829 – 300
                                          = 1529

                                          No. of bars:
                                          = (b/100) + 1
                                          = ((1219 – 2(50)cover )/100 )+1
                                          = 12 nos.



                   www.utm.my                   innovative ● entrepreneurial ● global   14
MEASUREMENT OF QUANTITIES




                     @100 c/c




        www.utm.my              innovative ● entrepreneurial ● global   15
MEASUREMENT OF QUANTITIES


Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

3) WBLFF                                Taker off :              Checked by:
3.1) Column stump                       Size of column stump:
3.1.1) Reinforced concrete Grade 30     Length = 229
       for column stump                 Width = 229
                                        Height = 1524 – 305 thickness of pile
    9/0.23                                         cap – (351/2) Half of beam’s
       0.23                                        thickness
       1.04                                      = 1043.50
    ----------
       0.50       1 m3
    ----------




                   www.utm.my                 innovative ● entrepreneurial ● global   16
MEASUREMENT OF QUANTITIES


Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

3) WBLFF
3.1) Column stump                       Size of column stump:
3.1.2) Formwork for column stump        Length = 229
                                        Width = 229
  9/4/0.23                              Height = 1524 – 305 thickness of pile
        1.04                                       cap – (351/2) Half of beam’s
     ----------                                    thickness
       8.61       9 m2                           = 1043.50
     ----------




                   www.utm.my                innovative ● entrepreneurial ● global   17
MEASUREMENT OF QUANTITIES




               Height of column stump

                        @100 c/c




        www.utm.my                      innovative ● entrepreneurial ● global   18
MEASUREMENT OF QUANTITIES


Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

3) WBLFF
3.1) Column stump                       Length = a + half beam’s thickness –
3.1.3) Reinforcement bar Y12 for        cover + 2 laps
       column stump                          lap



  9/4/2.97
     ----------                                    a

     106.92m x 0.89kg/m = 95.16kg
     ----------                                        lap
                           95kg
                                        = 1524 + (351/2) – 50 + (660x2)
                                        = 2969.50




                   www.utm.my                innovative ● entrepreneurial ● global   19
MEASUREMENT OF QUANTITIES
                     General Notes




        www.utm.my                   innovative ● entrepreneurial ● global   20
MEASUREMENT OF QUANTITIES


Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

3) WBLFF
3.1) Column stump                       Length of link: (length of CS– 2cover) x
3.1.4) R6 link in for column stump      4 +hook            Hook


  9/6/0.62
     ----------
      33.48m x 0.22kg/m = 7.36kg        =(229-100)+(229-100)+(229-100)+(229-
     ----------                         100)+100=616
                           7kg
                                        No. of link:
                                        Height of column stump = 1043.50
                                        =(1043.50/229)+1
                                        = 6 nos.




                   www.utm.my                innovative ● entrepreneurial ● global   21
MEASUREMENT OF QUANTITIES


Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

3) WBLFF
3.2) Ground beam                        Size of ground beam:
3.2.1) Excavation for ground beam       Length=3048+3048=6096
                                        Width = 229
  2/3/6.10                              Thickness = 351
       0.23
       0.35
     ----------
       2.95m3
     ----------
                           3m3


                                               Excavation for ground beam



                   www.utm.my                innovative ● entrepreneurial ● global   22
MEASUREMENT OF QUANTITIES


Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

3) WBLFF
3.2) Ground beam                          Size of ground beam:
3.2.2) Reinforced concrete Grade 30 for   Length=3048+3048=6096
        ground beam                       Width = 229
                                          Thickness = 351
  2/3/6.10
       0.23
       0.35
     ----------
       2.95m3
     ----------
                            3m3


                                                  RC for ground beam


                   www.utm.my                 innovative ● entrepreneurial ● global   23
MEASUREMENT OF QUANTITIES


Assumption No. 1:       Total land area = 10m x 10m




                                  Project Title: Construction and completion of
                                  guard house
                                  Owner: Panicsonic Sdn Bhd
                                  Architect: A to Z Sdn Bhd
                                  Drawing Title: Ground beam and foundation plan
                                  -------------------------------------------------------------------------
                                  Drawn by: Sheila
                                  Checked by: Aaron




           www.utm.my            innovative ● entrepreneurial ● global                                        24
MEASUREMENT OF QUANTITIES




               Height of column stump

                        @100 c/c




        www.utm.my                      innovative ● entrepreneurial ● global   25
MEASUREMENT OF QUANTITIES


Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

3) WBLFF
3.2) Ground beam                        Size of ground beam:
3.2.3) Formwork for ground beam         Length=3048+3048=6096
                                        Width = 229
                                        Thickness = 351
2/3/2/6.10
       0.35
     ----------
      25.62       26m2
     ----------



                                                 Installation of reinforcement bar and
                                                           formwork for ground beam




                   www.utm.my                innovative ● entrepreneurial ● global       26
MEASUREMENT OF QUANTITIES


Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

3) WBLFF
3.2) Ground beam                        Length = (length–2cover)+(2bend-
3.2.4) Reinforcement bar Y10 for        2cover)
       ground beam                      =(6096-(2x50))+(2x351)-(4x50)
                                        = 6498
2/3/4/6.50
     ----------
    156.00m x 0.62kg/m = 96.72kg
     ----------
                          97kg




                   www.utm.my                innovative ● entrepreneurial ● global   27
MEASUREMENT OF QUANTITIES


Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

3) WBLFF
3.2) Ground beam                        Length of stirrup:
3.2.5) R6 stirrup for ground beam                            Hook


2/3/28/0.86
      ----------                        =(229-100)+(351-100)+(229-100)+(351-
     144.48m x 0.22kg/m = 31.79kg       100)+100
      ----------                        =860
                          32kg
                                        No. of stirrup:
                                        Length of grd beam= 6096
                                        =(6096/229)+1
                                        = 28 nos.




                   www.utm.my                innovative ● entrepreneurial ● global   28
MEASUREMENT OF QUANTITIES
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

3) WBLFF

3.3) Ground slab                                     Area of slab = length x width
3.3.1) Excavation for ground slab                    Depth of excavation = 500mm

       6.10
       6.10                                                             BRC A8
                                                                                     150mm thick
                                                                                     concrete slab
       0.50
      ----------
      18.61m3               19 m3
      ----------                                                                             50mm thick
                                                                                                sand

                                                                                            300mm thick
                                                                                              hardcore



                                                                             DPM




      Installation of formwork,Damp Proof Membrane
         (DPM) and BRC wire mesh for ground slab



                               www.utm.my                     innovative ● entrepreneurial ● global       29
MEASUREMENT OF QUANTITIES


Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

3) WBLFF
3.3) Ground slab                        Area of slab = length x width
3.3.2) Reinforced concrete G30 in       Depth of excavation = 500mm
       ground slab
                                                                      150mm thick
                                                        BRC A8
                                                                      concrete slab
       6.10
       6.10
       0.15                                                                   50mm thick

      ----------                                                                 sand


       5.58m3                                                                300mm thick
                                                                               hardcore

      ----------   6 m3
                                                            DPM




                   www.utm.my                innovative ● entrepreneurial ● global         30
MEASUREMENT OF QUANTITIES


Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

3) WBLFF
3.3) Ground slab                        Area of slab = length x width
3.3.3) Formwork for ground slab         Depth of excavation = 500mm

     4/6.10                                            BRC A8
                                                                     150mm thick
                                                                     concrete slab
       0.15
      ----------
       3.66m2                                                                50mm thick

      ----------                                                                sand


                           4 m2                                             300mm thick
                                                                              hardcore



                                                           DPM




                   www.utm.my                innovative ● entrepreneurial ● global        31
MEASUREMENT OF QUANTITIES


Project: Construction and completion of
Guard House for Panicsonic Sdn Bhd
3) WBLFF
3.3) Ground slab                          Area of slab = length x width
3.3.4) BRC A8 for ground slab             Depth of excavation = 500mm
                                                                       150mm thick
                                                         BRC A8
       6.10                                                            concrete slab


       6.10
      ----------
                                                                               50mm thick
      37.21m2                                                                     sand

      ----------                                                              300mm thick
                                                                                hardcore
                           37 m2
                                                             DPM




                   www.utm.my                  innovative ● entrepreneurial ● global        32
MEASUREMENT OF QUANTITIES


Project: Construction and completion of
Guard House for Panicsonic Sdn Bhd
3) WBLFF
3.3) Ground slab                          Area of slab = length x width
3.3.5) DPM for ground slab                Depth of excavation = 500mm
                                                                        150mm thick
                                                          BRC A8
       6.10                                                             concrete slab


       6.10
      ----------
                                                                                50mm thick
      37.21m2                                                                      sand

      ----------                                                               300mm thick
                                                                                 hardcore
                             37 m2
                                                              DPM




                   www.utm.my                  innovative ● entrepreneurial ● global         33
MEASUREMENT OF QUANTITIES

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

3) WBLFF
3.3) Ground slab                         Area of slab = length x width
3.3.6) 50mm sand blinding for ground     Depth of excavation = 500mm
       slab
                                                                         150mm thick
                                                          BRC A8
       6.10                                                              concrete slab


       6.10
      ----------
                                                                                 50mm thick
      37.21m2                                                                       sand

      ----------                                                                300mm thick
                                                                                  hardcore
                           37 m2
                                                              DPM




                   www.utm.my                 innovative ● entrepreneurial ● global           34
MEASUREMENT OF QUANTITIES


Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

3) WBLFF
3.3) Ground slab                        Area of slab = length x width
3.3.7) Hardcore for ground slab         Depth of excavation = 500mm

       6.10                                             BRC A8
                                                                      150mm thick
                                                                      concrete slab
       6.10
       0.30
      ----------                                                              50mm thick

      11.16m3                                                                    sand


      ----------                                                             300mm thick
                                                                               hardcore

                           11 m3
                                                            DPM




                   www.utm.my                innovative ● entrepreneurial ● global         35
MEASUREMENT OF QUANTITIES

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

4) FRAME                                Taker off :                       Checked by:
4.1) Column                             Size of column:
4.1.1) Reinforced concrete Grade 30     Length = 229
       for column                       Width = 229
                                        Height = Height of the wall
    9/0.23                                       = 3000mm
       0.23
       3.00
    ----------
       1.43       1 m3
    ----------



                                                Installation of reinforcement bar and
                                                             formwork for column



                   www.utm.my                 innovative ● entrepreneurial ● global     36
MEASUREMENT OF QUANTITIES


Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

4) FRAME
4.1) Column                             Size of column:
4.1.2) Formwork for column              Length = 229
                                        Width = 229
  9/4/0.23                              Height = 3000
        3.00
     ----------
      24.84       25 m2
     ----------




                   www.utm.my                innovative ● entrepreneurial ● global   37
MEASUREMENT OF QUANTITIES

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

4) FRAME
4.1) Column                             Length = height of column + half of roof
4.1.3) Reinforcement bar Y12 for        beam + 1 lap + bend
       column
                                                 bend


  9/4/4.50
     ----------                                  Height of wall
    162.00m x 0.89kg/m = 144.18kg
     ----------
                          144kg
                                                  lap




                                        = 3000+ (0.5x351) + 660 + 660
                                        = 4495.5


                   www.utm.my                innovative ● entrepreneurial ● global   38
MEASUREMENT OF QUANTITIES


Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

4) FRAME
4.1) Column                             Length of link: (length of CS– 2cover) x
4.1.4) R6 link in for column            4 +hook
                                                          Hook

  9/14/0.82
     ----------
    103.32m x 0.22kg/m = 22.73kg        =(229-50)+(229-50)+(229-50)+(229-
     ----------                         50)+100=816
                          23kg
                                        No. of link:
                                        Height of column = 3000
                                        =(3000/229)+1
                                        = 14 nos.



                    www.utm.my               innovative ● entrepreneurial ● global   39
MEASUREMENT OF QUANTITIES


Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

4) FRAME
4.2) Roof beam                            Size of roof beam:
4.2.1) Reinforced concrete Grade 30 for   Length=3048+3048=6096
        roof beam                         Width = 229
                                          Thickness = 351
  2/3/6.10
       0.23
       0.35
     ----------
       2.95m3
     ----------
                            3m3




                   www.utm.my                 innovative ● entrepreneurial ● global   40
MEASUREMENT OF QUANTITIES


Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

4) FRAME
4.2) Roof beam                          Size of roof beam:
4.2.2) Formwork for roof beam           Length=3048+3048=6096
                                        Width = 229                        Side

                                        Thickness = 351
  2/3/6.10                                                             Soffit
       0.93
     ----------
      34.04       34m2
     ----------




                                        = 351 + 229 + 351
                                        = 931
                   www.utm.my                 innovative ● entrepreneurial ● global   41
MEASUREMENT OF QUANTITIES


Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

4) FRAME
4.2) Roof beam                          Length = (length–2cover)+(2bend-
4.2.3) Reinforcement bar Y10 for roof   2cover)
       beam                             =(6096-(2x50))+(2x351)-(4x50)
                                        = 6498
2/3/4/6.50
     ----------
    156.00m x 0.62kg/m = 96.72kg
     ----------
                          97kg




                   www.utm.my                innovative ● entrepreneurial ● global   42
MEASUREMENT OF QUANTITIES


Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

4) FRAME
3.2) Roof beam                          Length of stirrup:
3.2.5) R6 stirrup for roof beam                              Hook


2/3/28/1.06
      ----------                        =(229-50)+(351-50)+(229-50)+(351-
     178.08m x 0.22kg/m = 39.18kg       50)+100
      ----------                        =1060
                          39kg
                                        No. of stirrup:
                                        Length of beam= 6096
                                        =(6096/229)+1
                                        = 28 nos.




                   www.utm.my                innovative ● entrepreneurial ● global   43

More Related Content

What's hot

industrialised building systems_achah
industrialised building systems_achahindustrialised building systems_achah
industrialised building systems_achah
Aisyah Asyikin
 
SMM2 Explained
SMM2 ExplainedSMM2 Explained
SMM2 Explained
Tantish QS, UTM
 
Estimating calculation
Estimating calculationEstimating calculation
Estimating calculation
ZIyeeTan
 
Excavation 2014a-Lecture2
Excavation 2014a-Lecture2Excavation 2014a-Lecture2
Excavation 2014a-Lecture2
Anne Allan
 
Bcon
BconBcon
Cube test REPORT - DCC2042
Cube test REPORT - DCC2042Cube test REPORT - DCC2042
Cube test REPORT - DCC2042
Pavitrah Segaran
 
Prefabricated timber framing systems
Prefabricated timber framing  systemsPrefabricated timber framing  systems
Prefabricated timber framing systems
Farah Sham
 
Proktor compaction
Proktor compactionProktor compaction
Proktor compaction
Natalie Ulza
 
Group Assignment:IBS System
Group Assignment:IBS SystemGroup Assignment:IBS System
Group Assignment:IBS System
마 이환
 
Project 1: Industrialised Building System [ IBS ]
Project 1: Industrialised Building System [ IBS ]Project 1: Industrialised Building System [ IBS ]
Project 1: Industrialised Building System [ IBS ]
JerotichMaswan
 
Sieve analysis of fine aggregates student experiment
Sieve analysis of fine aggregates student experimentSieve analysis of fine aggregates student experiment
Sieve analysis of fine aggregates student experiment
kolveasna
 
Pile foundation design
Pile foundation designPile foundation design
Pile foundation design
UTHM
 
Ibs score
Ibs scoreIbs score
Ibs score
Afiq Knick
 
Silt test
Silt testSilt test
Silt test
YASMINE HASLAN
 
STRUCTURAL CALCULATION - CURTAIN WALL (SAMPLE DESIGN)
STRUCTURAL CALCULATION - CURTAIN WALL (SAMPLE DESIGN)STRUCTURAL CALCULATION - CURTAIN WALL (SAMPLE DESIGN)
STRUCTURAL CALCULATION - CURTAIN WALL (SAMPLE DESIGN)
Eduardo H. Pare
 
Shore pile
Shore pileShore pile
Shore pile
Rifat Bin Ahmed
 
Introduction building construction
Introduction building constructionIntroduction building construction
Introduction building construction
salsa moyara
 
Solid Ground Floors
 Solid Ground Floors  Solid Ground Floors
Solid Ground Floors
Luke D'Arcy
 
CT Assignment Written Report
CT Assignment Written ReportCT Assignment Written Report
CT Assignment Written Report
Yap Xin
 
M3 EG BQ metal frame door
M3 EG BQ metal frame doorM3 EG BQ metal frame door
M3 EG BQ metal frame door
Est
 

What's hot (20)

industrialised building systems_achah
industrialised building systems_achahindustrialised building systems_achah
industrialised building systems_achah
 
SMM2 Explained
SMM2 ExplainedSMM2 Explained
SMM2 Explained
 
Estimating calculation
Estimating calculationEstimating calculation
Estimating calculation
 
Excavation 2014a-Lecture2
Excavation 2014a-Lecture2Excavation 2014a-Lecture2
Excavation 2014a-Lecture2
 
Bcon
BconBcon
Bcon
 
Cube test REPORT - DCC2042
Cube test REPORT - DCC2042Cube test REPORT - DCC2042
Cube test REPORT - DCC2042
 
Prefabricated timber framing systems
Prefabricated timber framing  systemsPrefabricated timber framing  systems
Prefabricated timber framing systems
 
Proktor compaction
Proktor compactionProktor compaction
Proktor compaction
 
Group Assignment:IBS System
Group Assignment:IBS SystemGroup Assignment:IBS System
Group Assignment:IBS System
 
Project 1: Industrialised Building System [ IBS ]
Project 1: Industrialised Building System [ IBS ]Project 1: Industrialised Building System [ IBS ]
Project 1: Industrialised Building System [ IBS ]
 
Sieve analysis of fine aggregates student experiment
Sieve analysis of fine aggregates student experimentSieve analysis of fine aggregates student experiment
Sieve analysis of fine aggregates student experiment
 
Pile foundation design
Pile foundation designPile foundation design
Pile foundation design
 
Ibs score
Ibs scoreIbs score
Ibs score
 
Silt test
Silt testSilt test
Silt test
 
STRUCTURAL CALCULATION - CURTAIN WALL (SAMPLE DESIGN)
STRUCTURAL CALCULATION - CURTAIN WALL (SAMPLE DESIGN)STRUCTURAL CALCULATION - CURTAIN WALL (SAMPLE DESIGN)
STRUCTURAL CALCULATION - CURTAIN WALL (SAMPLE DESIGN)
 
Shore pile
Shore pileShore pile
Shore pile
 
Introduction building construction
Introduction building constructionIntroduction building construction
Introduction building construction
 
Solid Ground Floors
 Solid Ground Floors  Solid Ground Floors
Solid Ground Floors
 
CT Assignment Written Report
CT Assignment Written ReportCT Assignment Written Report
CT Assignment Written Report
 
M3 EG BQ metal frame door
M3 EG BQ metal frame doorM3 EG BQ metal frame door
M3 EG BQ metal frame door
 

Viewers also liked

Preestimating requirements r1
Preestimating requirements r1Preestimating requirements r1
Preestimating requirements r1
alanchong88
 
Construction industry and estimating
Construction industry and estimatingConstruction industry and estimating
Construction industry and estimating
alanchong88
 
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PPT
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PPTCTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PPT
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PPT
Shankar Ramasamy
 
Associates and joint arrangements
Associates and joint arrangementsAssociates and joint arrangements
Associates and joint arrangements
wamorena lempadi
 
Stages in Construction
Stages in Construction Stages in Construction
Stages in Construction
Mereia Kali
 
Building construction-report (1)
Building construction-report (1)Building construction-report (1)
Building construction-report (1)
Soh Shing
 
50 Creativity Creation Techniques And Strategies
50 Creativity Creation Techniques And Strategies50 Creativity Creation Techniques And Strategies
50 Creativity Creation Techniques And Strategies
John Fallon
 
Building Construction
Building ConstructionBuilding Construction
Building Construction
Wilden How
 

Viewers also liked (8)

Preestimating requirements r1
Preestimating requirements r1Preestimating requirements r1
Preestimating requirements r1
 
Construction industry and estimating
Construction industry and estimatingConstruction industry and estimating
Construction industry and estimating
 
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PPT
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PPTCTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PPT
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PPT
 
Associates and joint arrangements
Associates and joint arrangementsAssociates and joint arrangements
Associates and joint arrangements
 
Stages in Construction
Stages in Construction Stages in Construction
Stages in Construction
 
Building construction-report (1)
Building construction-report (1)Building construction-report (1)
Building construction-report (1)
 
50 Creativity Creation Techniques And Strategies
50 Creativity Creation Techniques And Strategies50 Creativity Creation Techniques And Strategies
50 Creativity Creation Techniques And Strategies
 
Building Construction
Building ConstructionBuilding Construction
Building Construction
 

Similar to Sgp4813 measurement of quantities

DELHI METRO UNDERGROUND TUNNELING : SHAHBAZ KHAN DMRC
DELHI METRO UNDERGROUND TUNNELING : SHAHBAZ KHAN DMRCDELHI METRO UNDERGROUND TUNNELING : SHAHBAZ KHAN DMRC
DELHI METRO UNDERGROUND TUNNELING : SHAHBAZ KHAN DMRC
Al Hakam Khan
 
Industrial training report
Industrial training reportIndustrial training report
Industrial training report
kiransuresh7
 
Industrial training report
Industrial training reportIndustrial training report
Industrial training report
kiransuresh7
 
Dda training presentation
Dda training presentationDda training presentation
Dda training presentation
AKASHGARG131
 
11. KGA, MALL - Execution Plan - R- 06.03.2023.pptx
11. KGA, MALL - Execution Plan - R- 06.03.2023.pptx11. KGA, MALL - Execution Plan - R- 06.03.2023.pptx
11. KGA, MALL - Execution Plan - R- 06.03.2023.pptx
ssuser2ec079
 
Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)
AJAY SHAHU
 
DSLIP 2015 Technical Report
DSLIP 2015 Technical ReportDSLIP 2015 Technical Report
DSLIP 2015 Technical Report
Joanna Ding
 
Dslip report
Dslip reportDslip report
Dslip report
Joanna Ding
 
Introduction & under ground water tank problem
Introduction & under ground water tank problemIntroduction & under ground water tank problem
Introduction & under ground water tank problem
dhineshkumar002
 
Environment friendly building_material_technologies_for_low_cost_housing (1)
Environment friendly building_material_technologies_for_low_cost_housing (1)Environment friendly building_material_technologies_for_low_cost_housing (1)
Environment friendly building_material_technologies_for_low_cost_housing (1)
Hammam El Meseiry
 
hochPPT thesis statement master civil engineering.pptx
hochPPT thesis statement master civil engineering.pptxhochPPT thesis statement master civil engineering.pptx
hochPPT thesis statement master civil engineering.pptx
Zakaria156221
 
Présentation master thesesis in civil department pptx
Présentation master thesesis in civil department pptxPrésentation master thesesis in civil department pptx
Présentation master thesesis in civil department pptx
Zakaria156221
 
Burj al arab
Burj al arabBurj al arab
Burj al arab
Rajat Nainwal
 
@ETCONp Construction Exam 8 .DOCX
@ETCONp Construction Exam 8  .DOCX@ETCONp Construction Exam 8  .DOCX
@ETCONp Construction Exam 8 .DOCX
MekonnenAyal
 
IRJET - Experimental Investigation on Plasticizing Agent in Concrete
IRJET - Experimental Investigation on Plasticizing Agent in ConcreteIRJET - Experimental Investigation on Plasticizing Agent in Concrete
IRJET - Experimental Investigation on Plasticizing Agent in Concrete
IRJET Journal
 
IRJET- Design and Analysis of Residential Building
IRJET-  	  Design and Analysis of Residential BuildingIRJET-  	  Design and Analysis of Residential Building
IRJET- Design and Analysis of Residential Building
IRJET Journal
 
Architect Sample
Architect SampleArchitect Sample
Architect Sample
Hai Nguyen
 
Icng eco housing (1)
Icng eco housing (1)Icng eco housing (1)
Icng eco housing (1)
Sarah Waddle
 
Manufacturing of fly-ash brick
Manufacturing of fly-ash brickManufacturing of fly-ash brick
Manufacturing of fly-ash brick
Basitali Nevarekar
 
Site report 1
Site report 1Site report 1
Site report 1
Jenny Huoy Miin
 

Similar to Sgp4813 measurement of quantities (20)

DELHI METRO UNDERGROUND TUNNELING : SHAHBAZ KHAN DMRC
DELHI METRO UNDERGROUND TUNNELING : SHAHBAZ KHAN DMRCDELHI METRO UNDERGROUND TUNNELING : SHAHBAZ KHAN DMRC
DELHI METRO UNDERGROUND TUNNELING : SHAHBAZ KHAN DMRC
 
Industrial training report
Industrial training reportIndustrial training report
Industrial training report
 
Industrial training report
Industrial training reportIndustrial training report
Industrial training report
 
Dda training presentation
Dda training presentationDda training presentation
Dda training presentation
 
11. KGA, MALL - Execution Plan - R- 06.03.2023.pptx
11. KGA, MALL - Execution Plan - R- 06.03.2023.pptx11. KGA, MALL - Execution Plan - R- 06.03.2023.pptx
11. KGA, MALL - Execution Plan - R- 06.03.2023.pptx
 
Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)
 
DSLIP 2015 Technical Report
DSLIP 2015 Technical ReportDSLIP 2015 Technical Report
DSLIP 2015 Technical Report
 
Dslip report
Dslip reportDslip report
Dslip report
 
Introduction & under ground water tank problem
Introduction & under ground water tank problemIntroduction & under ground water tank problem
Introduction & under ground water tank problem
 
Environment friendly building_material_technologies_for_low_cost_housing (1)
Environment friendly building_material_technologies_for_low_cost_housing (1)Environment friendly building_material_technologies_for_low_cost_housing (1)
Environment friendly building_material_technologies_for_low_cost_housing (1)
 
hochPPT thesis statement master civil engineering.pptx
hochPPT thesis statement master civil engineering.pptxhochPPT thesis statement master civil engineering.pptx
hochPPT thesis statement master civil engineering.pptx
 
Présentation master thesesis in civil department pptx
Présentation master thesesis in civil department pptxPrésentation master thesesis in civil department pptx
Présentation master thesesis in civil department pptx
 
Burj al arab
Burj al arabBurj al arab
Burj al arab
 
@ETCONp Construction Exam 8 .DOCX
@ETCONp Construction Exam 8  .DOCX@ETCONp Construction Exam 8  .DOCX
@ETCONp Construction Exam 8 .DOCX
 
IRJET - Experimental Investigation on Plasticizing Agent in Concrete
IRJET - Experimental Investigation on Plasticizing Agent in ConcreteIRJET - Experimental Investigation on Plasticizing Agent in Concrete
IRJET - Experimental Investigation on Plasticizing Agent in Concrete
 
IRJET- Design and Analysis of Residential Building
IRJET-  	  Design and Analysis of Residential BuildingIRJET-  	  Design and Analysis of Residential Building
IRJET- Design and Analysis of Residential Building
 
Architect Sample
Architect SampleArchitect Sample
Architect Sample
 
Icng eco housing (1)
Icng eco housing (1)Icng eco housing (1)
Icng eco housing (1)
 
Manufacturing of fly-ash brick
Manufacturing of fly-ash brickManufacturing of fly-ash brick
Manufacturing of fly-ash brick
 
Site report 1
Site report 1Site report 1
Site report 1
 

Recently uploaded

How MJ Global Leads the Packaging Industry.pdf
How MJ Global Leads the Packaging Industry.pdfHow MJ Global Leads the Packaging Industry.pdf
How MJ Global Leads the Packaging Industry.pdf
MJ Global
 
2024-6-01-IMPACTSilver-Corp-Presentation.pdf
2024-6-01-IMPACTSilver-Corp-Presentation.pdf2024-6-01-IMPACTSilver-Corp-Presentation.pdf
2024-6-01-IMPACTSilver-Corp-Presentation.pdf
hartfordclub1
 
Zodiac Signs and Food Preferences_ What Your Sign Says About Your Taste
Zodiac Signs and Food Preferences_ What Your Sign Says About Your TasteZodiac Signs and Food Preferences_ What Your Sign Says About Your Taste
Zodiac Signs and Food Preferences_ What Your Sign Says About Your Taste
my Pandit
 
Creative Web Design Company in Singapore
Creative Web Design Company in SingaporeCreative Web Design Company in Singapore
Creative Web Design Company in Singapore
techboxsqauremedia
 
The APCO Geopolitical Radar - Q3 2024 The Global Operating Environment for Bu...
The APCO Geopolitical Radar - Q3 2024 The Global Operating Environment for Bu...The APCO Geopolitical Radar - Q3 2024 The Global Operating Environment for Bu...
The APCO Geopolitical Radar - Q3 2024 The Global Operating Environment for Bu...
APCO
 
Authentically Social by Corey Perlman - EO Puerto Rico
Authentically Social by Corey Perlman - EO Puerto RicoAuthentically Social by Corey Perlman - EO Puerto Rico
Authentically Social by Corey Perlman - EO Puerto Rico
Corey Perlman, Social Media Speaker and Consultant
 
Part 2 Deep Dive: Navigating the 2024 Slowdown
Part 2 Deep Dive: Navigating the 2024 SlowdownPart 2 Deep Dive: Navigating the 2024 Slowdown
Part 2 Deep Dive: Navigating the 2024 Slowdown
jeffkluth1
 
Chapter 7 Final business management sciences .ppt
Chapter 7 Final business management sciences .pptChapter 7 Final business management sciences .ppt
Chapter 7 Final business management sciences .ppt
ssuser567e2d
 
一比一原版新西兰奥塔哥大学毕业证(otago毕业证)如何办理
一比一原版新西兰奥塔哥大学毕业证(otago毕业证)如何办理一比一原版新西兰奥塔哥大学毕业证(otago毕业证)如何办理
一比一原版新西兰奥塔哥大学毕业证(otago毕业证)如何办理
taqyea
 
3 Simple Steps To Buy Verified Payoneer Account In 2024
3 Simple Steps To Buy Verified Payoneer Account In 20243 Simple Steps To Buy Verified Payoneer Account In 2024
3 Simple Steps To Buy Verified Payoneer Account In 2024
SEOSMMEARTH
 
Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Satta Matka
Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Satta MatkaDpboss Matka Guessing Satta Matta Matka Kalyan Chart Satta Matka
Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Satta Matka
➒➌➎➏➑➐➋➑➐➐Dpboss Matka Guessing Satta Matka Kalyan Chart Indian Matka
 
Company Valuation webinar series - Tuesday, 4 June 2024
Company Valuation webinar series - Tuesday, 4 June 2024Company Valuation webinar series - Tuesday, 4 June 2024
Company Valuation webinar series - Tuesday, 4 June 2024
FelixPerez547899
 
BeMetals Investor Presentation_June 1, 2024.pdf
BeMetals Investor Presentation_June 1, 2024.pdfBeMetals Investor Presentation_June 1, 2024.pdf
BeMetals Investor Presentation_June 1, 2024.pdf
DerekIwanaka1
 
Best practices for project execution and delivery
Best practices for project execution and deliveryBest practices for project execution and delivery
Best practices for project execution and delivery
CLIVE MINCHIN
 
Brian Fitzsimmons on the Business Strategy and Content Flywheel of Barstool S...
Brian Fitzsimmons on the Business Strategy and Content Flywheel of Barstool S...Brian Fitzsimmons on the Business Strategy and Content Flywheel of Barstool S...
Brian Fitzsimmons on the Business Strategy and Content Flywheel of Barstool S...
Neil Horowitz
 
Creative Web Design Company in Singapore
Creative Web Design Company in SingaporeCreative Web Design Company in Singapore
Creative Web Design Company in Singapore
techboxsqauremedia
 
Event Report - SAP Sapphire 2024 Orlando - lots of innovation and old challenges
Event Report - SAP Sapphire 2024 Orlando - lots of innovation and old challengesEvent Report - SAP Sapphire 2024 Orlando - lots of innovation and old challenges
Event Report - SAP Sapphire 2024 Orlando - lots of innovation and old challenges
Holger Mueller
 
Innovation Management Frameworks: Your Guide to Creativity & Innovation
Innovation Management Frameworks: Your Guide to Creativity & InnovationInnovation Management Frameworks: Your Guide to Creativity & Innovation
Innovation Management Frameworks: Your Guide to Creativity & Innovation
Operational Excellence Consulting
 
Structural Design Process: Step-by-Step Guide for Buildings
Structural Design Process: Step-by-Step Guide for BuildingsStructural Design Process: Step-by-Step Guide for Buildings
Structural Design Process: Step-by-Step Guide for Buildings
Chandresh Chudasama
 
Digital Transformation Frameworks: Driving Digital Excellence
Digital Transformation Frameworks: Driving Digital ExcellenceDigital Transformation Frameworks: Driving Digital Excellence
Digital Transformation Frameworks: Driving Digital Excellence
Operational Excellence Consulting
 

Recently uploaded (20)

How MJ Global Leads the Packaging Industry.pdf
How MJ Global Leads the Packaging Industry.pdfHow MJ Global Leads the Packaging Industry.pdf
How MJ Global Leads the Packaging Industry.pdf
 
2024-6-01-IMPACTSilver-Corp-Presentation.pdf
2024-6-01-IMPACTSilver-Corp-Presentation.pdf2024-6-01-IMPACTSilver-Corp-Presentation.pdf
2024-6-01-IMPACTSilver-Corp-Presentation.pdf
 
Zodiac Signs and Food Preferences_ What Your Sign Says About Your Taste
Zodiac Signs and Food Preferences_ What Your Sign Says About Your TasteZodiac Signs and Food Preferences_ What Your Sign Says About Your Taste
Zodiac Signs and Food Preferences_ What Your Sign Says About Your Taste
 
Creative Web Design Company in Singapore
Creative Web Design Company in SingaporeCreative Web Design Company in Singapore
Creative Web Design Company in Singapore
 
The APCO Geopolitical Radar - Q3 2024 The Global Operating Environment for Bu...
The APCO Geopolitical Radar - Q3 2024 The Global Operating Environment for Bu...The APCO Geopolitical Radar - Q3 2024 The Global Operating Environment for Bu...
The APCO Geopolitical Radar - Q3 2024 The Global Operating Environment for Bu...
 
Authentically Social by Corey Perlman - EO Puerto Rico
Authentically Social by Corey Perlman - EO Puerto RicoAuthentically Social by Corey Perlman - EO Puerto Rico
Authentically Social by Corey Perlman - EO Puerto Rico
 
Part 2 Deep Dive: Navigating the 2024 Slowdown
Part 2 Deep Dive: Navigating the 2024 SlowdownPart 2 Deep Dive: Navigating the 2024 Slowdown
Part 2 Deep Dive: Navigating the 2024 Slowdown
 
Chapter 7 Final business management sciences .ppt
Chapter 7 Final business management sciences .pptChapter 7 Final business management sciences .ppt
Chapter 7 Final business management sciences .ppt
 
一比一原版新西兰奥塔哥大学毕业证(otago毕业证)如何办理
一比一原版新西兰奥塔哥大学毕业证(otago毕业证)如何办理一比一原版新西兰奥塔哥大学毕业证(otago毕业证)如何办理
一比一原版新西兰奥塔哥大学毕业证(otago毕业证)如何办理
 
3 Simple Steps To Buy Verified Payoneer Account In 2024
3 Simple Steps To Buy Verified Payoneer Account In 20243 Simple Steps To Buy Verified Payoneer Account In 2024
3 Simple Steps To Buy Verified Payoneer Account In 2024
 
Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Satta Matka
Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Satta MatkaDpboss Matka Guessing Satta Matta Matka Kalyan Chart Satta Matka
Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Satta Matka
 
Company Valuation webinar series - Tuesday, 4 June 2024
Company Valuation webinar series - Tuesday, 4 June 2024Company Valuation webinar series - Tuesday, 4 June 2024
Company Valuation webinar series - Tuesday, 4 June 2024
 
BeMetals Investor Presentation_June 1, 2024.pdf
BeMetals Investor Presentation_June 1, 2024.pdfBeMetals Investor Presentation_June 1, 2024.pdf
BeMetals Investor Presentation_June 1, 2024.pdf
 
Best practices for project execution and delivery
Best practices for project execution and deliveryBest practices for project execution and delivery
Best practices for project execution and delivery
 
Brian Fitzsimmons on the Business Strategy and Content Flywheel of Barstool S...
Brian Fitzsimmons on the Business Strategy and Content Flywheel of Barstool S...Brian Fitzsimmons on the Business Strategy and Content Flywheel of Barstool S...
Brian Fitzsimmons on the Business Strategy and Content Flywheel of Barstool S...
 
Creative Web Design Company in Singapore
Creative Web Design Company in SingaporeCreative Web Design Company in Singapore
Creative Web Design Company in Singapore
 
Event Report - SAP Sapphire 2024 Orlando - lots of innovation and old challenges
Event Report - SAP Sapphire 2024 Orlando - lots of innovation and old challengesEvent Report - SAP Sapphire 2024 Orlando - lots of innovation and old challenges
Event Report - SAP Sapphire 2024 Orlando - lots of innovation and old challenges
 
Innovation Management Frameworks: Your Guide to Creativity & Innovation
Innovation Management Frameworks: Your Guide to Creativity & InnovationInnovation Management Frameworks: Your Guide to Creativity & Innovation
Innovation Management Frameworks: Your Guide to Creativity & Innovation
 
Structural Design Process: Step-by-Step Guide for Buildings
Structural Design Process: Step-by-Step Guide for BuildingsStructural Design Process: Step-by-Step Guide for Buildings
Structural Design Process: Step-by-Step Guide for Buildings
 
Digital Transformation Frameworks: Driving Digital Excellence
Digital Transformation Frameworks: Driving Digital ExcellenceDigital Transformation Frameworks: Driving Digital Excellence
Digital Transformation Frameworks: Driving Digital Excellence
 

Sgp4813 measurement of quantities

  • 1. MEASUREMENT OF QUANTITIES ● Mat Naim bin Abdullah @ Mohd Asmoni ● Diploma QS (UTM), BSc. QS (Glasgow Caledonian University), M.Eng. Construction (UTM), PhD Facilities Management (UTM) ● matnaim@utm.my ● amn871969@yahoo.com ● C04-308 ● 019-7573760 www.utm.my innovative ● entrepreneurial ● global 1
  • 2. MEASUREMENT OF QUANTITIES Assumption No. 1: Total land area = 10m x 10m Project Title: Construction and completion of guard house Owner: Panicsonic Sdn Bhd Architect: A to Z Sdn Bhd Drawing Title: Ground beam and foundation plan ------------------------------------------------------------------------- Drawn by: Sheila Checked by: Aaron www.utm.my innovative ● entrepreneurial ● global 2
  • 3. MEASUREMENT OF QUANTITIES www.utm.my innovative ● entrepreneurial ● global 3
  • 4. MEASUREMENT OF QUANTITIES Construction Method 1. Preliminaries (Initial site works) - % of total cost 2. Site clearance and earthwork 3. Foundation construction (E.g. Piling and footing) 4. Work below lowest floor finish 5. Frame 6. Staircase 7. Upper Floor 8. Roof 9. Wall and partition 10. Door and window 11. Finishes 12. Sundries (Built-in furniture) 13. Building services (M&E, ICT etc) 14. External works (Water reticulation, landscape etc) www.utm.my innovative ● entrepreneurial ● global 4
  • 5. MEASUREMENT OF QUANTITIES Project: Construction and completion of Guard House for Panicsonic Sdn Bhd 1) Site clearance 1.1) Clear the site including grubbing of Area of the site: trees, shrubs and demolish any 10 x 10 = 100m2 existing structure and cart away and dump to the specified location. 10.00 10.00 ---------- 100.00 100 m2 ---------- www.utm.my innovative ● entrepreneurial ● global 5
  • 6. MEASUREMENT OF QUANTITIES www.utm.my innovative ● entrepreneurial ● global 6
  • 7. MEASUREMENT OF QUANTITIES Project: Construction and completion of Guard House for Panicsonic Sdn Bhd 2) Foundation 2.1) Piling including all related works Area of the building: Length = 3048 + 3048 = 6096 6.10 Width = 3048 + 3048 = 6096 6.10 ---------- 37.21 37 m2 ---------- www.utm.my innovative ● entrepreneurial ● global 7
  • 8. MEASUREMENT OF QUANTITIES Project: Construction and completion of Guard House for Panicsonic Sdn Bhd 2) Foundation 2.2) Excavation for pile cap Size of pile cap = 1219 x 1219 Depth of excavation: 9/1.22 1524 + 50 (lean concrete) = 1574 1.22 1.57 ---------- 21.03 21 m3 ---------- Excavation and Lean concrete as base for pile cap www.utm.my innovative ● entrepreneurial ● global 8
  • 9. MEASUREMENT OF QUANTITIES www.utm.my innovative ● entrepreneurial ● global 9
  • 10. MEASUREMENT OF QUANTITIES Project: Construction and completion of Guard House for Panicsonic Sdn Bhd 2) Foundation 2.3) Reinforced concrete Grade 30 for Size of pile cap: pile cap Length = 1219 Width = 1219 9/1.22 Thickness = 305 1.22 0.31 ---------- 4.15 4 m3 ---------- Concrete for pile cap www.utm.my innovative ● entrepreneurial ● global 10
  • 11. MEASUREMENT OF QUANTITIES Project: Construction and completion of Guard House for Panicsonic Sdn Bhd 2) Foundation 2.4) 50mm thick lean concrete Grade Size of pile cap: 15 for pile cap Length = 1219 Width = 1219 9 / 1.22 1.22 ---------- 13.40 13 m2 ---------- Excavation and Lean concrete as base for pile cap www.utm.my innovative ● entrepreneurial ● global 11
  • 12. MEASUREMENT OF QUANTITIES www.utm.my innovative ● entrepreneurial ● global 12
  • 13. MEASUREMENT OF QUANTITIES Project: Construction and completion of Guard House for Panicsonic Sdn Bhd 2) Foundation 2.5) Formwork for pile cap Size of pile cap: Length = 1219 9 / 4 /1.22 Width = 1219 0.31 Thickness = 305 ---------- 13.62 14 m2 9/2/1.22 ---------- 0.31 6.81 9/2/1.50 0.31 8.37 15.18 15m2 Formwork for pile cap www.utm.my innovative ● entrepreneurial ● global 13
  • 14. MEASUREMENT OF QUANTITIES Project: Construction and completion of Guard House for Panicsonic Sdn Bhd 2) Foundation 2.6) Reinforcement bar Y12 for pile cap Length: a c 9/2/ 12/ 1.53 ---------- b 330.48m x 0.89 kg/m = 294.13kg = a + b + c – cover ---------- = 305 + 1219 + 305 – 6(50) = 294 kg = 1829 – 300 = 1529 No. of bars: = (b/100) + 1 = ((1219 – 2(50)cover )/100 )+1 = 12 nos. www.utm.my innovative ● entrepreneurial ● global 14
  • 15. MEASUREMENT OF QUANTITIES @100 c/c www.utm.my innovative ● entrepreneurial ● global 15
  • 16. MEASUREMENT OF QUANTITIES Project: Construction and completion of Guard House for Panicsonic Sdn Bhd 3) WBLFF Taker off : Checked by: 3.1) Column stump Size of column stump: 3.1.1) Reinforced concrete Grade 30 Length = 229 for column stump Width = 229 Height = 1524 – 305 thickness of pile 9/0.23 cap – (351/2) Half of beam’s 0.23 thickness 1.04 = 1043.50 ---------- 0.50 1 m3 ---------- www.utm.my innovative ● entrepreneurial ● global 16
  • 17. MEASUREMENT OF QUANTITIES Project: Construction and completion of Guard House for Panicsonic Sdn Bhd 3) WBLFF 3.1) Column stump Size of column stump: 3.1.2) Formwork for column stump Length = 229 Width = 229 9/4/0.23 Height = 1524 – 305 thickness of pile 1.04 cap – (351/2) Half of beam’s ---------- thickness 8.61 9 m2 = 1043.50 ---------- www.utm.my innovative ● entrepreneurial ● global 17
  • 18. MEASUREMENT OF QUANTITIES Height of column stump @100 c/c www.utm.my innovative ● entrepreneurial ● global 18
  • 19. MEASUREMENT OF QUANTITIES Project: Construction and completion of Guard House for Panicsonic Sdn Bhd 3) WBLFF 3.1) Column stump Length = a + half beam’s thickness – 3.1.3) Reinforcement bar Y12 for cover + 2 laps column stump lap 9/4/2.97 ---------- a 106.92m x 0.89kg/m = 95.16kg ---------- lap 95kg = 1524 + (351/2) – 50 + (660x2) = 2969.50 www.utm.my innovative ● entrepreneurial ● global 19
  • 20. MEASUREMENT OF QUANTITIES General Notes www.utm.my innovative ● entrepreneurial ● global 20
  • 21. MEASUREMENT OF QUANTITIES Project: Construction and completion of Guard House for Panicsonic Sdn Bhd 3) WBLFF 3.1) Column stump Length of link: (length of CS– 2cover) x 3.1.4) R6 link in for column stump 4 +hook Hook 9/6/0.62 ---------- 33.48m x 0.22kg/m = 7.36kg =(229-100)+(229-100)+(229-100)+(229- ---------- 100)+100=616 7kg No. of link: Height of column stump = 1043.50 =(1043.50/229)+1 = 6 nos. www.utm.my innovative ● entrepreneurial ● global 21
  • 22. MEASUREMENT OF QUANTITIES Project: Construction and completion of Guard House for Panicsonic Sdn Bhd 3) WBLFF 3.2) Ground beam Size of ground beam: 3.2.1) Excavation for ground beam Length=3048+3048=6096 Width = 229 2/3/6.10 Thickness = 351 0.23 0.35 ---------- 2.95m3 ---------- 3m3 Excavation for ground beam www.utm.my innovative ● entrepreneurial ● global 22
  • 23. MEASUREMENT OF QUANTITIES Project: Construction and completion of Guard House for Panicsonic Sdn Bhd 3) WBLFF 3.2) Ground beam Size of ground beam: 3.2.2) Reinforced concrete Grade 30 for Length=3048+3048=6096 ground beam Width = 229 Thickness = 351 2/3/6.10 0.23 0.35 ---------- 2.95m3 ---------- 3m3 RC for ground beam www.utm.my innovative ● entrepreneurial ● global 23
  • 24. MEASUREMENT OF QUANTITIES Assumption No. 1: Total land area = 10m x 10m Project Title: Construction and completion of guard house Owner: Panicsonic Sdn Bhd Architect: A to Z Sdn Bhd Drawing Title: Ground beam and foundation plan ------------------------------------------------------------------------- Drawn by: Sheila Checked by: Aaron www.utm.my innovative ● entrepreneurial ● global 24
  • 25. MEASUREMENT OF QUANTITIES Height of column stump @100 c/c www.utm.my innovative ● entrepreneurial ● global 25
  • 26. MEASUREMENT OF QUANTITIES Project: Construction and completion of Guard House for Panicsonic Sdn Bhd 3) WBLFF 3.2) Ground beam Size of ground beam: 3.2.3) Formwork for ground beam Length=3048+3048=6096 Width = 229 Thickness = 351 2/3/2/6.10 0.35 ---------- 25.62 26m2 ---------- Installation of reinforcement bar and formwork for ground beam www.utm.my innovative ● entrepreneurial ● global 26
  • 27. MEASUREMENT OF QUANTITIES Project: Construction and completion of Guard House for Panicsonic Sdn Bhd 3) WBLFF 3.2) Ground beam Length = (length–2cover)+(2bend- 3.2.4) Reinforcement bar Y10 for 2cover) ground beam =(6096-(2x50))+(2x351)-(4x50) = 6498 2/3/4/6.50 ---------- 156.00m x 0.62kg/m = 96.72kg ---------- 97kg www.utm.my innovative ● entrepreneurial ● global 27
  • 28. MEASUREMENT OF QUANTITIES Project: Construction and completion of Guard House for Panicsonic Sdn Bhd 3) WBLFF 3.2) Ground beam Length of stirrup: 3.2.5) R6 stirrup for ground beam Hook 2/3/28/0.86 ---------- =(229-100)+(351-100)+(229-100)+(351- 144.48m x 0.22kg/m = 31.79kg 100)+100 ---------- =860 32kg No. of stirrup: Length of grd beam= 6096 =(6096/229)+1 = 28 nos. www.utm.my innovative ● entrepreneurial ● global 28
  • 29. MEASUREMENT OF QUANTITIES Project: Construction and completion of Guard House for Panicsonic Sdn Bhd 3) WBLFF 3.3) Ground slab Area of slab = length x width 3.3.1) Excavation for ground slab Depth of excavation = 500mm 6.10 6.10 BRC A8 150mm thick concrete slab 0.50 ---------- 18.61m3 19 m3 ---------- 50mm thick sand 300mm thick hardcore DPM Installation of formwork,Damp Proof Membrane (DPM) and BRC wire mesh for ground slab www.utm.my innovative ● entrepreneurial ● global 29
  • 30. MEASUREMENT OF QUANTITIES Project: Construction and completion of Guard House for Panicsonic Sdn Bhd 3) WBLFF 3.3) Ground slab Area of slab = length x width 3.3.2) Reinforced concrete G30 in Depth of excavation = 500mm ground slab 150mm thick BRC A8 concrete slab 6.10 6.10 0.15 50mm thick ---------- sand 5.58m3 300mm thick hardcore ---------- 6 m3 DPM www.utm.my innovative ● entrepreneurial ● global 30
  • 31. MEASUREMENT OF QUANTITIES Project: Construction and completion of Guard House for Panicsonic Sdn Bhd 3) WBLFF 3.3) Ground slab Area of slab = length x width 3.3.3) Formwork for ground slab Depth of excavation = 500mm 4/6.10 BRC A8 150mm thick concrete slab 0.15 ---------- 3.66m2 50mm thick ---------- sand 4 m2 300mm thick hardcore DPM www.utm.my innovative ● entrepreneurial ● global 31
  • 32. MEASUREMENT OF QUANTITIES Project: Construction and completion of Guard House for Panicsonic Sdn Bhd 3) WBLFF 3.3) Ground slab Area of slab = length x width 3.3.4) BRC A8 for ground slab Depth of excavation = 500mm 150mm thick BRC A8 6.10 concrete slab 6.10 ---------- 50mm thick 37.21m2 sand ---------- 300mm thick hardcore 37 m2 DPM www.utm.my innovative ● entrepreneurial ● global 32
  • 33. MEASUREMENT OF QUANTITIES Project: Construction and completion of Guard House for Panicsonic Sdn Bhd 3) WBLFF 3.3) Ground slab Area of slab = length x width 3.3.5) DPM for ground slab Depth of excavation = 500mm 150mm thick BRC A8 6.10 concrete slab 6.10 ---------- 50mm thick 37.21m2 sand ---------- 300mm thick hardcore 37 m2 DPM www.utm.my innovative ● entrepreneurial ● global 33
  • 34. MEASUREMENT OF QUANTITIES Project: Construction and completion of Guard House for Panicsonic Sdn Bhd 3) WBLFF 3.3) Ground slab Area of slab = length x width 3.3.6) 50mm sand blinding for ground Depth of excavation = 500mm slab 150mm thick BRC A8 6.10 concrete slab 6.10 ---------- 50mm thick 37.21m2 sand ---------- 300mm thick hardcore 37 m2 DPM www.utm.my innovative ● entrepreneurial ● global 34
  • 35. MEASUREMENT OF QUANTITIES Project: Construction and completion of Guard House for Panicsonic Sdn Bhd 3) WBLFF 3.3) Ground slab Area of slab = length x width 3.3.7) Hardcore for ground slab Depth of excavation = 500mm 6.10 BRC A8 150mm thick concrete slab 6.10 0.30 ---------- 50mm thick 11.16m3 sand ---------- 300mm thick hardcore 11 m3 DPM www.utm.my innovative ● entrepreneurial ● global 35
  • 36. MEASUREMENT OF QUANTITIES Project: Construction and completion of Guard House for Panicsonic Sdn Bhd 4) FRAME Taker off : Checked by: 4.1) Column Size of column: 4.1.1) Reinforced concrete Grade 30 Length = 229 for column Width = 229 Height = Height of the wall 9/0.23 = 3000mm 0.23 3.00 ---------- 1.43 1 m3 ---------- Installation of reinforcement bar and formwork for column www.utm.my innovative ● entrepreneurial ● global 36
  • 37. MEASUREMENT OF QUANTITIES Project: Construction and completion of Guard House for Panicsonic Sdn Bhd 4) FRAME 4.1) Column Size of column: 4.1.2) Formwork for column Length = 229 Width = 229 9/4/0.23 Height = 3000 3.00 ---------- 24.84 25 m2 ---------- www.utm.my innovative ● entrepreneurial ● global 37
  • 38. MEASUREMENT OF QUANTITIES Project: Construction and completion of Guard House for Panicsonic Sdn Bhd 4) FRAME 4.1) Column Length = height of column + half of roof 4.1.3) Reinforcement bar Y12 for beam + 1 lap + bend column bend 9/4/4.50 ---------- Height of wall 162.00m x 0.89kg/m = 144.18kg ---------- 144kg lap = 3000+ (0.5x351) + 660 + 660 = 4495.5 www.utm.my innovative ● entrepreneurial ● global 38
  • 39. MEASUREMENT OF QUANTITIES Project: Construction and completion of Guard House for Panicsonic Sdn Bhd 4) FRAME 4.1) Column Length of link: (length of CS– 2cover) x 4.1.4) R6 link in for column 4 +hook Hook 9/14/0.82 ---------- 103.32m x 0.22kg/m = 22.73kg =(229-50)+(229-50)+(229-50)+(229- ---------- 50)+100=816 23kg No. of link: Height of column = 3000 =(3000/229)+1 = 14 nos. www.utm.my innovative ● entrepreneurial ● global 39
  • 40. MEASUREMENT OF QUANTITIES Project: Construction and completion of Guard House for Panicsonic Sdn Bhd 4) FRAME 4.2) Roof beam Size of roof beam: 4.2.1) Reinforced concrete Grade 30 for Length=3048+3048=6096 roof beam Width = 229 Thickness = 351 2/3/6.10 0.23 0.35 ---------- 2.95m3 ---------- 3m3 www.utm.my innovative ● entrepreneurial ● global 40
  • 41. MEASUREMENT OF QUANTITIES Project: Construction and completion of Guard House for Panicsonic Sdn Bhd 4) FRAME 4.2) Roof beam Size of roof beam: 4.2.2) Formwork for roof beam Length=3048+3048=6096 Width = 229 Side Thickness = 351 2/3/6.10 Soffit 0.93 ---------- 34.04 34m2 ---------- = 351 + 229 + 351 = 931 www.utm.my innovative ● entrepreneurial ● global 41
  • 42. MEASUREMENT OF QUANTITIES Project: Construction and completion of Guard House for Panicsonic Sdn Bhd 4) FRAME 4.2) Roof beam Length = (length–2cover)+(2bend- 4.2.3) Reinforcement bar Y10 for roof 2cover) beam =(6096-(2x50))+(2x351)-(4x50) = 6498 2/3/4/6.50 ---------- 156.00m x 0.62kg/m = 96.72kg ---------- 97kg www.utm.my innovative ● entrepreneurial ● global 42
  • 43. MEASUREMENT OF QUANTITIES Project: Construction and completion of Guard House for Panicsonic Sdn Bhd 4) FRAME 3.2) Roof beam Length of stirrup: 3.2.5) R6 stirrup for roof beam Hook 2/3/28/1.06 ---------- =(229-50)+(351-50)+(229-50)+(351- 178.08m x 0.22kg/m = 39.18kg 50)+100 ---------- =1060 39kg No. of stirrup: Length of beam= 6096 =(6096/229)+1 = 28 nos. www.utm.my innovative ● entrepreneurial ● global 43