Pre-estimating
         Requirements

         ● Mat Naim Abdullah
         ● matnaim@utm.my
         ● C04-308




www.utm.my             innovative ● entrepreneurial ● global   1
Pre-construction - Information
                         CONSTRUCTION STAGES
Inception
    Designing & Tender Document Preparation

            Tendering & Procurement

                 Construction

                         Operation & Maintenance


            www.utm.my           innovative ● entrepreneurial ● global   2
THE BUILDING COMMUNICATION

1.   Drawings
2.   Specification
3.   Bills of Quantities (BQ)
4.   Tender Documents
5.   Contracts Documents
6.   Work Programmes
7.   Operation & Maintenance Manual

          www.utm.my   innovative ● entrepreneurial ● global   3
2. The Drawings


  Imagine!!!!!!
    How to
   design and
     draw?




www.utm.my        innovative ● entrepreneurial ● global   4
2. The Drawings (Cont’d)

Types of Drawings

1.   Conceptual Drawings
2.   Tender Drawings
3.   Contract Drawings
4.   Construction Drawings
5.   Shop Drawings
6.   As-built Drawings


           www.utm.my   innovative ● entrepreneurial ● global   5
2. The Drawings (Cont’d)

Conceptual Drawings – What can you see?




     www.utm.my      innovative ● entrepreneurial ● global   6
2. The Drawings (Cont’d)
Conceptual Drawings – What can you see?




        www.utm.my      innovative ● entrepreneurial ● global   7
2. The Drawings (Cont’d)




AERIAL PERSPECTIVE

             www.utm.my   innovative ● entrepreneurial ● global   8
2. The Drawings (Cont’d)




CONSTRUCTION DRAWINGS    CIQ COMPLEX - FRONT ELEVATION

            www.utm.my       innovative ● entrepreneurial ● global   9
2. The Drawings (Cont’d)




CONSTRUCTION DRAWINGS    CIQ COMPLEX - LEFT ELEVATION

            www.utm.my       innovative ● entrepreneurial ● global   10
2. The Drawings (Cont’d)




       MOTORCYLES


                                                          BUS & COACHES
                           LV
HGV




CONSTRUCTION DRAWINGS           CIQ COMPLEX - PARTIAL SECTION

              www.utm.my            innovative ● entrepreneurial ● global   11
2. The Drawings (Cont’d)



             To Malaysia




                          To Singapore




CONSTRUCTION DRAWINGS - CIQ Layout Plan (Level 1)

             www.utm.my              innovative ● entrepreneurial ● global   12
2. The Drawings (Cont’d)
Offices & Passengers’ Hall (Level 2)


             To           To
             Malaysia     Singapore




 CONSTRUCTION DRAWINGS

             www.utm.my         innovative ● entrepreneurial ● global   13
2. The Drawings (Cont’d)
Shop Drawings – What can you see?




    www.utm.my       innovative ● entrepreneurial ● global   14
2. The Drawings (Cont’d)
    As Built Drawings – What can you see?




Any difference from the construction drawings?

         www.utm.my       innovative ● entrepreneurial ● global   15
2. The Drawings (Cont’d)




www.utm.my   innovative ● entrepreneurial ● global   16
2. The Drawings (Cont’d)




www.utm.my   innovative ● entrepreneurial ● global   17
Bills of Quantities (BQ)

The forms where the contractor fills in his price
based on:

1. The description of works
2. Quantities                                                     Example
                                                                   of BQ
3. Unit – m, m2, m3, kg, Lump sum, Item, No.


Preparation of BQ is by Quantity Surveyor based
on the Standard Method of Measurement (SMM)

                 www.utm.my          innovative ● entrepreneurial ● global   18
Specification

Specification – Describe:
1. Materials
2. Standard of materials
3. Construction processes &
4. workmanship.
                                               Making Cake




          www.utm.my          innovative ● entrepreneurial ● global   19
Tender Documents
Tender Documents
1.   Instruction to tenderers
2.   Form of tender
3.   Conditions of contracts
4.   Bills of Quantities
5.   Tender Particulars
6.   Tender Drawings
7.   Specification
8.   Proposed work programme

               www.utm.my       innovative ● entrepreneurial ● global   20
Instruction to Tenderers & Form of Tender
Instruction to Tenderers contains:
1. The content of the tender documents
2. Selection of the tenderers
                                                      Form of Tender is a
3. Visiting the site
                                                      declaration by the
4. Procedure for addendum                             tenderer to abide to
5. Procedure for tender preparation &                 the instruction of
    submission                                        tenderers
6. Content of Bills of Quantities
7. Opening & closing of tender
8. Any significant matters related to the
    project


                  www.utm.my                innovative ● entrepreneurial ● global   21
Conditions of Contract
The Details of Agreement between the Employer and the Contractor.
Usually consists of:
1. Contractor’s liabilities
2. Provision of preliminary works
3. Variations
4. Payments
5. Commencement & completion
6. Defects liability
7. Delay & extension of time
8. Termination
9. Mediation & Arbitration

                www.utm.my           innovative ● entrepreneurial ● global   22
Contract Documents
Contract Documents
1.   Letter of Award
2.   Instruction to tenderers
3.   Form of tender
4.   Conditions of contracts
5.   Agreed Bills of Quantities
6.   Tender Particulars
7.   Contract Drawings
8.   Specification
9.   Agreed work programme


                  www.utm.my      innovative ● entrepreneurial ● global   23
Work Programme
Indicate the time to complete each of
      the construction activities or
  package of the project in the form of
   bar chart or Critical Path Method,
  hence the total completion period for
           the whole project.

         www.utm.my   innovative ● entrepreneurial ● global   24
Master Implementation Programme
                                  2002               2003              2004               2005                   2006                2007
 ACTIVITY
                              Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
                                          Oct ‘02                                                                                  CIQ Facilities
CIQ Complex                 Aug ‘02                                                  CIQ Building
                                                                                                VPA                     Jul ‘06     Operational
                                                                                                                                       (Dec ’06)
                                                          Aug ‘03
JB Sentral Terminal                   Mar ‘03                                                    Section 1               Section 2     Jun ‘07

Interchange No. 1 & Other    Sep ‘02
                                                    Apr ‘03
                                                                                                                        May
Infrastructure Works                                                                                                    ‘06
                                                                                                              Feb ‘06
Short Term Access                                                   Nov ‘04                                                   Dec‘06

JBS Short Term Access                                                           Jul ‘05           Oct ‘05
                                                                                                                                       Jul ‘07

                                                Jan ‘03
Road Bridge (Suspended)         Oct ‘02                                                                 Dec ‘05

                                                                      Mar ‘04
Rail Bridge (Suspended)                 Jun ‘03                                                                          Aug ‘06

                                                                                                            Jan ‘06
Causeway Removal/ (Suspended)
                                                                           May ‘05                                                   Apr ‘07
Navigation Channel




LEGEND:
              Physical Works   Stage Completion                                   Milestones
              Commencement     Works
                         www.utm.my                                      innovative ● entrepreneurial ● global                                 25
Work Programme




 www.utm.my   innovative ● entrepreneurial ● global   26
The pre-estimating requirements


 1. Drawings
 2. Specification
 3. Rate – Built-up rate, sub-
    contractor’s price or schedule
    of rate
 4. Work programme


       www.utm.my     innovative ● entrepreneurial ● global   27
Built-up Rate


1. Material’s cost
2. Manpower’s cost
3. Machinery’s cost
4. Wastage
5. Margin



      www.utm.my      innovative ● entrepreneurial ● global   28

More Related Content

Viewers also liked

50451783 taking-off-quantity
50451783 taking-off-quantity50451783 taking-off-quantity
50451783 taking-off-quantityhlksd
 
Reinforcement detailing
Reinforcement  detailingReinforcement  detailing
Reinforcement detailingAli Ishaqi
 
Stages in Construction
Stages in Construction Stages in Construction
Stages in Construction Mereia Kali
 
Building construction-report (1)
Building construction-report (1)Building construction-report (1)
Building construction-report (1)Soh Shing
 
A view to civil engineering in india by 2020
A view to civil engineering in india by 2020A view to civil engineering in india by 2020
A view to civil engineering in india by 2020ash09uce
 
50 Creativity Creation Techniques And Strategies
50 Creativity Creation Techniques And Strategies50 Creativity Creation Techniques And Strategies
50 Creativity Creation Techniques And StrategiesJohn Fallon
 
Building Construction
Building ConstructionBuilding Construction
Building ConstructionWilden How
 

Viewers also liked (8)

50451783 taking-off-quantity
50451783 taking-off-quantity50451783 taking-off-quantity
50451783 taking-off-quantity
 
Scope of Civil Engineering
Scope of Civil EngineeringScope of Civil Engineering
Scope of Civil Engineering
 
Reinforcement detailing
Reinforcement  detailingReinforcement  detailing
Reinforcement detailing
 
Stages in Construction
Stages in Construction Stages in Construction
Stages in Construction
 
Building construction-report (1)
Building construction-report (1)Building construction-report (1)
Building construction-report (1)
 
A view to civil engineering in india by 2020
A view to civil engineering in india by 2020A view to civil engineering in india by 2020
A view to civil engineering in india by 2020
 
50 Creativity Creation Techniques And Strategies
50 Creativity Creation Techniques And Strategies50 Creativity Creation Techniques And Strategies
50 Creativity Creation Techniques And Strategies
 
Building Construction
Building ConstructionBuilding Construction
Building Construction
 

Similar to Preestimating requirements r1

Similar to Preestimating requirements r1 (20)

Summer training @ L&T
Summer training @ L&TSummer training @ L&T
Summer training @ L&T
 
00 index
00   index00   index
00 index
 
Motorcycle Pallet Rack Project Report
Motorcycle Pallet Rack Project ReportMotorcycle Pallet Rack Project Report
Motorcycle Pallet Rack Project Report
 
Progress Slides - Jan 17.pptx
Progress Slides - Jan 17.pptxProgress Slides - Jan 17.pptx
Progress Slides - Jan 17.pptx
 
presentation quantity survey and estimate
presentation quantity survey and estimatepresentation quantity survey and estimate
presentation quantity survey and estimate
 
IRJET - Delay Analysis of a Construction Project- A Case Study
IRJET - Delay Analysis of a Construction Project- A Case StudyIRJET - Delay Analysis of a Construction Project- A Case Study
IRJET - Delay Analysis of a Construction Project- A Case Study
 
Resume[q]
Resume[q]Resume[q]
Resume[q]
 
Asraful Latest_CV
Asraful Latest_CVAsraful Latest_CV
Asraful Latest_CV
 
Nabendu_Ghosh
Nabendu_GhoshNabendu_Ghosh
Nabendu_Ghosh
 
Project Management Report for Tank Farm
Project Management Report for Tank FarmProject Management Report for Tank Farm
Project Management Report for Tank Farm
 
CV Shahzad Ahmed
CV Shahzad AhmedCV Shahzad Ahmed
CV Shahzad Ahmed
 
CV_Pratip_Dutta_Design Engg Mechanical_(31.07.2016)
CV_Pratip_Dutta_Design Engg Mechanical_(31.07.2016)CV_Pratip_Dutta_Design Engg Mechanical_(31.07.2016)
CV_Pratip_Dutta_Design Engg Mechanical_(31.07.2016)
 
QUANTITY SURVEYOR (MUHAMMAD AZEEM) UPDATED 1-22-2017
QUANTITY SURVEYOR  (MUHAMMAD AZEEM) UPDATED 1-22-2017QUANTITY SURVEYOR  (MUHAMMAD AZEEM) UPDATED 1-22-2017
QUANTITY SURVEYOR (MUHAMMAD AZEEM) UPDATED 1-22-2017
 
Ecm442 lecture 1 latest
Ecm442 lecture 1 latestEcm442 lecture 1 latest
Ecm442 lecture 1 latest
 
CONSTRUCTION PRESENTATION
CONSTRUCTION PRESENTATIONCONSTRUCTION PRESENTATION
CONSTRUCTION PRESENTATION
 
Thandapani Portfolio
Thandapani PortfolioThandapani Portfolio
Thandapani Portfolio
 
ITD Presentation
ITD PresentationITD Presentation
ITD Presentation
 
Resum
ResumResum
Resum
 
ICI ITD QS PROJECT 1 (1).pptx
ICI ITD QS PROJECT 1 (1).pptxICI ITD QS PROJECT 1 (1).pptx
ICI ITD QS PROJECT 1 (1).pptx
 
140189-1000-41EC-0001_00
140189-1000-41EC-0001_00140189-1000-41EC-0001_00
140189-1000-41EC-0001_00
 

Preestimating requirements r1

  • 1. Pre-estimating Requirements ● Mat Naim Abdullah ● matnaim@utm.my ● C04-308 www.utm.my innovative ● entrepreneurial ● global 1
  • 2. Pre-construction - Information CONSTRUCTION STAGES Inception Designing & Tender Document Preparation Tendering & Procurement Construction Operation & Maintenance www.utm.my innovative ● entrepreneurial ● global 2
  • 3. THE BUILDING COMMUNICATION 1. Drawings 2. Specification 3. Bills of Quantities (BQ) 4. Tender Documents 5. Contracts Documents 6. Work Programmes 7. Operation & Maintenance Manual www.utm.my innovative ● entrepreneurial ● global 3
  • 4. 2. The Drawings Imagine!!!!!! How to design and draw? www.utm.my innovative ● entrepreneurial ● global 4
  • 5. 2. The Drawings (Cont’d) Types of Drawings 1. Conceptual Drawings 2. Tender Drawings 3. Contract Drawings 4. Construction Drawings 5. Shop Drawings 6. As-built Drawings www.utm.my innovative ● entrepreneurial ● global 5
  • 6. 2. The Drawings (Cont’d) Conceptual Drawings – What can you see? www.utm.my innovative ● entrepreneurial ● global 6
  • 7. 2. The Drawings (Cont’d) Conceptual Drawings – What can you see? www.utm.my innovative ● entrepreneurial ● global 7
  • 8. 2. The Drawings (Cont’d) AERIAL PERSPECTIVE www.utm.my innovative ● entrepreneurial ● global 8
  • 9. 2. The Drawings (Cont’d) CONSTRUCTION DRAWINGS CIQ COMPLEX - FRONT ELEVATION www.utm.my innovative ● entrepreneurial ● global 9
  • 10. 2. The Drawings (Cont’d) CONSTRUCTION DRAWINGS CIQ COMPLEX - LEFT ELEVATION www.utm.my innovative ● entrepreneurial ● global 10
  • 11. 2. The Drawings (Cont’d) MOTORCYLES BUS & COACHES LV HGV CONSTRUCTION DRAWINGS CIQ COMPLEX - PARTIAL SECTION www.utm.my innovative ● entrepreneurial ● global 11
  • 12. 2. The Drawings (Cont’d) To Malaysia To Singapore CONSTRUCTION DRAWINGS - CIQ Layout Plan (Level 1) www.utm.my innovative ● entrepreneurial ● global 12
  • 13. 2. The Drawings (Cont’d) Offices & Passengers’ Hall (Level 2) To To Malaysia Singapore CONSTRUCTION DRAWINGS www.utm.my innovative ● entrepreneurial ● global 13
  • 14. 2. The Drawings (Cont’d) Shop Drawings – What can you see? www.utm.my innovative ● entrepreneurial ● global 14
  • 15. 2. The Drawings (Cont’d) As Built Drawings – What can you see? Any difference from the construction drawings? www.utm.my innovative ● entrepreneurial ● global 15
  • 16. 2. The Drawings (Cont’d) www.utm.my innovative ● entrepreneurial ● global 16
  • 17. 2. The Drawings (Cont’d) www.utm.my innovative ● entrepreneurial ● global 17
  • 18. Bills of Quantities (BQ) The forms where the contractor fills in his price based on: 1. The description of works 2. Quantities Example of BQ 3. Unit – m, m2, m3, kg, Lump sum, Item, No. Preparation of BQ is by Quantity Surveyor based on the Standard Method of Measurement (SMM) www.utm.my innovative ● entrepreneurial ● global 18
  • 19. Specification Specification – Describe: 1. Materials 2. Standard of materials 3. Construction processes & 4. workmanship. Making Cake www.utm.my innovative ● entrepreneurial ● global 19
  • 20. Tender Documents Tender Documents 1. Instruction to tenderers 2. Form of tender 3. Conditions of contracts 4. Bills of Quantities 5. Tender Particulars 6. Tender Drawings 7. Specification 8. Proposed work programme www.utm.my innovative ● entrepreneurial ● global 20
  • 21. Instruction to Tenderers & Form of Tender Instruction to Tenderers contains: 1. The content of the tender documents 2. Selection of the tenderers Form of Tender is a 3. Visiting the site declaration by the 4. Procedure for addendum tenderer to abide to 5. Procedure for tender preparation & the instruction of submission tenderers 6. Content of Bills of Quantities 7. Opening & closing of tender 8. Any significant matters related to the project www.utm.my innovative ● entrepreneurial ● global 21
  • 22. Conditions of Contract The Details of Agreement between the Employer and the Contractor. Usually consists of: 1. Contractor’s liabilities 2. Provision of preliminary works 3. Variations 4. Payments 5. Commencement & completion 6. Defects liability 7. Delay & extension of time 8. Termination 9. Mediation & Arbitration www.utm.my innovative ● entrepreneurial ● global 22
  • 23. Contract Documents Contract Documents 1. Letter of Award 2. Instruction to tenderers 3. Form of tender 4. Conditions of contracts 5. Agreed Bills of Quantities 6. Tender Particulars 7. Contract Drawings 8. Specification 9. Agreed work programme www.utm.my innovative ● entrepreneurial ● global 23
  • 24. Work Programme Indicate the time to complete each of the construction activities or package of the project in the form of bar chart or Critical Path Method, hence the total completion period for the whole project. www.utm.my innovative ● entrepreneurial ● global 24
  • 25. Master Implementation Programme 2002 2003 2004 2005 2006 2007 ACTIVITY Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Oct ‘02 CIQ Facilities CIQ Complex Aug ‘02 CIQ Building VPA Jul ‘06 Operational (Dec ’06) Aug ‘03 JB Sentral Terminal Mar ‘03 Section 1 Section 2 Jun ‘07 Interchange No. 1 & Other Sep ‘02 Apr ‘03 May Infrastructure Works ‘06 Feb ‘06 Short Term Access Nov ‘04 Dec‘06 JBS Short Term Access Jul ‘05 Oct ‘05 Jul ‘07 Jan ‘03 Road Bridge (Suspended) Oct ‘02 Dec ‘05 Mar ‘04 Rail Bridge (Suspended) Jun ‘03 Aug ‘06 Jan ‘06 Causeway Removal/ (Suspended) May ‘05 Apr ‘07 Navigation Channel LEGEND: Physical Works Stage Completion Milestones Commencement Works www.utm.my innovative ● entrepreneurial ● global 25
  • 26. Work Programme www.utm.my innovative ● entrepreneurial ● global 26
  • 27. The pre-estimating requirements 1. Drawings 2. Specification 3. Rate – Built-up rate, sub- contractor’s price or schedule of rate 4. Work programme www.utm.my innovative ● entrepreneurial ● global 27
  • 28. Built-up Rate 1. Material’s cost 2. Manpower’s cost 3. Machinery’s cost 4. Wastage 5. Margin www.utm.my innovative ● entrepreneurial ● global 28