Luxury Home_Cost Summary_05.05.15
Job DescriptionJob Name : ARCHITECT SAMPLE
Construction of 2 Storey Luxury ResidenceClient's Name: Architect / Designer Sample
m2Cost/TradeTrade DescriptionTrd Trade
TotalNo. %
NOTES1
95,750DEMOLITION & EXCAVATION 4.54 239.382
177,610CONCRETE 8.42 444.033
188,090BRICKWORK / BLOCKWORK 8.92 470.234
38,640STRUCTURAL STEEL 1.83 96.605
151,750METAL WORK 7.19 379.386
60,780ROOFING 2.88 151.957
144,520CARPENTRY 6.85 361.308
99,800JOINERY (PROVISIONAL SUM) 4.73 249.509
77,650WINDOWS & GLAZING 3.68 194.1310
33,590FIXTURES & FITTINGS (PROVISIONAL SUM) 1.59 83.9811
146,320WATERPROOFING & TILING 6.94 365.8012
72,855PLASTERING 3.45 182.1413
84,785RENDERING 4.02 211.9614
19,800FLOOR FINISHES (PROVISIONAL SUM) 0.94 49.5015
31,580PAINTING 1.50 78.9516
42,400HYDRAULIC SERVICES (PROVISIONAL
SUM)
2.01 106.0017
42,000ELECTRICAL SERVICES (PROVISIONAL
SUM)
1.99 105.0018
21,400MECHANICAL SERVICES (PROVISIONAL
SUM)
1.01 53.5019
70,000LIFT SERVICES 3.32 175.0020
74,245EXTERNAL WORKS 3.52 185.6121
239,800PRELIMINARIES 11.37 599.5022
95,669PROFIT/MARGIN 4.54 239.1723
Subtotal24 2,009,034
100,452CONTINGENCY RECOMMENDED 4.76 251.1325
2,109,486100.00 5,273.72GFA: 400 m2.
$ 2,109,486Final Total :
Page : 1NEWIN ESTIMATING SERVICE 5/May/15Date of Printing:
Global Estimating System (32 Bit) - H10 FIRST AVE BERALA NSW 2141
of 1
SAM
PLE
Luxury Home_Cost Break Up_05.05.15
Job Name : ARCHITECT SAMPLE Job Description
Client's Name: Architect / Designer Sample Construction of 2 Storey Luxury Residence
Item DescriptionItem AmountRateUnitQuantity
No.
NOTESTrade : 1
DRAWINGS
NoteThis estimate was prepared from the following
drawings and documentation:
1
Architectural Drawings 00 to 27 (Rev A) dated
11 March 2015 and prepared by Michael
Robilliard & Associates
2
Structural Drawings S.01 to 12 dated February
2015 and prepared by Birzulis Associates
3
INCLUSIONS
Rock excavation.4
Demolition & general site clearance.5
Bulk excavation and detailed excavation.6
Allowance for services connections and
associated works.
7
Allowance for smoke detectors.8
Allowance for wet area ventilation9
Allowace for air conditioning.10
Allowance for lift service.11
Allowance for landscaping over site.12
High quality finishes and fitments.13
Builder's preliminaries in the order of
approximately 13% and a builder's profit of 5%
of the construction cost which we believe are
generally fair and reasonable in current market
conditions.
14
A construction period of 48 weeks.15
16
EXCLUSIONS
Services diversions, easement, encasements or
the like.
17
Grey water management.18
Water Authority requirements.19
Smart system wiring.20
Contingency. We recommend a contingency of
5% be allowed over the entire project.
21
Escalation in costs and union enterprise
bargaining costs.
22
Any cost increases associated with the 10% GST.23
Page : 1NEWIN ESTIMATING SERVICE 5/May/15Date of Printing:
- H10 FIRST AVE BERALA NSW 2141 Global Estimating System (32 Bit)
of 14
SAM
PLE
Luxury Home_Cost Break Up_05.05.15
Job Name : ARCHITECT SAMPLE Job Description
Client's Name: Architect / Designer Sample Construction of 2 Storey Luxury Residence
Item DescriptionItem AmountRateUnitQuantity
No.
NOTESTrade : 1 (Continued)
Any cost increases associated with the Carbon
Tax.
24
Council contributions, design fees, authority fees,
bank fees and charges, marketing, leasing and
selling costs.
25
26
DISCLAIMER
This report is for use by the party to whom it is
addressed and for no other purposes. No
responsibility is taken for any third party who
may use or rely on the whole or any part of this
report.
27
All quantities are approximate only.28
Under no circumstances are the quantities or
rates to form part of the building contract.
29
Our costs include no provision for any change in
costs associated with amendments to current tax
laws and/or for the introduction of a goods and
services tax (GST).
30
NOTES Total :
DEMOLITION & EXCAVATIONTrade : 2
DEMOLITION & EXCAVATION
Demolition
1.00 ItemDemolish existing structures1 35,000.00 35,000.00
Excavation
468.00 m2Site clearance2 25.00 11,700.00
234.00 m3Bulk excavation into rock3 145.00 33,930.00
54.00 m3Detailed excavation into rock4 280.00 15,120.00
DEMOLITION & EXCAVATION Total : 95,750.00
CONCRETETrade : 3
CONCRETE
Foundation
52.00 m3Concrete strip footings :[142 m]1 550.00 28,600.00
3.00 m3Concrete pad footings :[27 No]2 550.00 1,650.00
1.00 ItemLift pit complete3 5,000.00 5,000.00
Page : 2NEWIN ESTIMATING SERVICE 5/May/15Date of Printing:
- H10 FIRST AVE BERALA NSW 2141 Global Estimating System (32 Bit)
of 14
SAM
PLE
Luxury Home_Cost Break Up_05.05.15
Job Name : ARCHITECT SAMPLE Job Description
Client's Name: Architect / Designer Sample Construction of 2 Storey Luxury Residence
Item DescriptionItem AmountRateUnitQuantity
No.
CONCRETETrade : 3 (Continued)
Lower Floor
38.00 m3Suspended concrete slab :[235 m2]4 220.00 8,360.00
235.00 m2Bondek to suspended slab5 90.00 21,150.00
70.00 mStop ends6 35.00 2,450.00
5.00 TonneReinforcement to suspended slab (120kg/m3)7 1,500.00 7,500.00
Upper Floor
63.00 m3Suspended concrete slab :[337 m2]8 220.00 13,860.00
337.00 m2Formwork to suspended slab9 80.00 26,960.00
98.00 mStop ends10 35.00 3,430.00
8.00 TonneReinforcement to suspended slab (120kg/m3)11 1,500.00 12,000.00
Stair / Ramp
1.00 ItemConcrete curved internal stair12 12,000.00 12,000.00
131.00 m2External ramp / footpath13 150.00 19,650.00
Sundries
1.00 ItemDrains/sumps/cure/joints/pump/test/etc14 15,000.00 15,000.00
CONCRETE Total : 177,610.00
BRICKWORK / BLOCKWORKTrade : 4
BRICKWORK / BLOCKWORK
Foundation
156.00 m2230mm brick foundation walling (Assume avg
1.2m high)
1 160.00 24,960.00
27.00 NoBrick piers2 120.00 3,240.00
11.00 m2140mm concrete corefilled block lift walling3 180.00 1,980.00
Lower Floor
31.00 m2140mm concrete corefilled block lift walling4 180.00 5,580.00
233.00 m2Double common brick external walling5 160.00 37,280.00
15.00 m2Double common brick internal walling6 160.00 2,400.00
213.00 m2Single common brick internal walling7 90.00 19,170.00
Upper Floor
27.00 m2140mm concrete corefilled block lift walling8 180.00 4,860.00
156.00 m2Double common brick external walling9 160.00 24,960.00
Page : 3NEWIN ESTIMATING SERVICE 5/May/15Date of Printing:
- H10 FIRST AVE BERALA NSW 2141 Global Estimating System (32 Bit)
of 14
SAM
PLE
Luxury Home_Cost Break Up_05.05.15
Job Name : ARCHITECT SAMPLE Job Description
Client's Name: Architect / Designer Sample Construction of 2 Storey Luxury Residence
Item DescriptionItem AmountRateUnitQuantity
No.
BRICKWORK / BLOCKWORKTrade : 4 (Continued)
6.00 m2Double common brick internal walling10 160.00 960.00
99.00 m2Single common brick internal walling11 90.00 8,910.00
External
118.00 m2140mm concrete corefilled block retaining walls
(Assume avg 2m high)
12 180.00 21,240.00
21.00 m2Double common brick front boundary fence13 160.00 3,360.00
Sundries
98.00 mTermite treatment14 30.00 2,940.00
75.00 ThouMud, dpc, lintels, etc15 350.00 26,250.00
BRICKWORK / BLOCKWORK Total : 188,090.00
STRUCTURAL STEELTrade : 5
STRUCTURAL STEEL
3.00 TonneStructural Steel1 11,500.00 34,500.00
1.00 ItemBolts, plates, braces etc.. @ 12%2 4,140.00 4,140.00
STRUCTURAL STEEL Total : 38,640.00
METAL WORKTrade : 6
METAL WORK
Wrought Iron Works
1.00 ItemWrought iron security double leaf door to house
entry
1 5,500.00 5,500.00
14.00 mWrought iron curved balustrade to internal stair2 1,350.00 18,900.00
29.00 mWrought iron balustrade3 1,150.00 33,350.00
1.00 ItemWrought iron car entry gate - automated4 20,000.00 20,000.00
1.00 ItemWrought iron pedestrian entry gate5 4,000.00 4,000.00
11.00 m2Wrought iron fence panels to front brick wall6 1,150.00 12,650.00
7.00 m2Wrought iron security bars to windows7 1,150.00 8,050.00
Strip Drains
5.00 mCustom strip drain to wet areas8 450.00 2,250.00
19.00 mCustom strip drain to verandahs9 450.00 8,550.00
Fireplace
2.00 NoGas fire place complete10 9,000.00 18,000.00
Page : 4NEWIN ESTIMATING SERVICE 5/May/15Date of Printing:
- H10 FIRST AVE BERALA NSW 2141 Global Estimating System (32 Bit)
of 14
SAM
PLE
Luxury Home_Cost Break Up_05.05.15
Job Name : ARCHITECT SAMPLE Job Description
Client's Name: Architect / Designer Sample Construction of 2 Storey Luxury Residence
Item DescriptionItem AmountRateUnitQuantity
No.
METAL WORKTrade : 6 (Continued)
Awning
28.00 m2Retractable awning above upper level verandah11 550.00 15,400.00
Miscellaneous
1.00 ItemAutomated garage door - Provisional Sum12 4,500.00 4,500.00
1.00 ItemLetter box13 450.00 450.00
1.00 ItemSignage14 150.00 150.00
METAL WORK Total : 151,750.00
ROOFINGTrade : 7
ROOFING
1.00 ItemAllowance for tarp protection during
construction
1 2,500.00 2,500.00
297.00 m2Terracotta roof cladding2 100.00 29,700.00
297.00 m2EO insulation3 30.00 8,910.00
81.00 mFascia4 65.00 5,265.00
40.00 mGutter5 55.00 2,200.00
57.00 m2Eaves lining6 65.00 3,705.00
60.00 mDownpipes7 50.00 3,000.00
2.00 ItemElectric skylights8 2,750.00 5,500.00
ROOFING Total : 60,780.00
CARPENTRYTrade : 8
CARPENTRY
Doors
Lower Floor
1.00 NoLift door1 2,500.00 2,500.00
10.00 NoInternal solidcore single leaf door2 1,500.00 15,000.00
11.00 NoDoor hardware3 250.00 2,750.00
Upper Floor
1.00 NoLift door4 2,500.00 2,500.00
3.00 NoInternal solidcore single leaf door5 1,500.00 4,500.00
1.00 NoInternal solidcore double leaf door6 1,500.00 1,500.00
Page : 5NEWIN ESTIMATING SERVICE 5/May/15Date of Printing:
- H10 FIRST AVE BERALA NSW 2141 Global Estimating System (32 Bit)
of 14
SAM
PLE
Luxury Home_Cost Break Up_05.05.15
Job Name : ARCHITECT SAMPLE Job Description
Client's Name: Architect / Designer Sample Construction of 2 Storey Luxury Residence
Item DescriptionItem AmountRateUnitQuantity
No.
CARPENTRYTrade : 8 (Continued)
1.00 No3 panel cavity sliding door to dining room -
Provisional Sum
7 10,000.00 10,000.00
1.00 NoOperable wall to living / kitchen - Provisional
Sum
8 10,000.00 10,000.00
7.00 NoDoor hardware9 250.00 1,750.00
Framing
27.00 m2Internal timber stud walling10 45.00 1,215.00
297.00 m2Timber roof framing11 165.00 49,005.00
1.00 ItemDucts/boxing out12 5,000.00 5,000.00
Glazing
160.00 HrsLabour to install glazing - 2 men x 10 days13 55.00 8,800.00
1.00 ItemSundries14 5,000.00 5,000.00
Architraves / Skirting
1.00 ItemProvisional sum allowance for architraves and
skirtings
15 15,000.00 15,000.00
1.00 ItemExternal window concrete architraves16 10,000.00 10,000.00
CARPENTRY Total : 144,520.00
JOINERY (PROVISIONAL SUM)Trade : 9
JOINERY (PROVISIONAL SUM)
1.00 ItemKitchen fitout incl. stone bench top, splashback
& island
1 40,000.00 40,000.00
1.00 ItemLaundry fitout incl. stone bench top2 15,000.00 15,000.00
1.00 ItemLinen fitout3 5,000.00 5,000.00
1.00 ItemBroom closet fitout4 10,000.00 10,000.00
2.00 ItemWalk in robe5 10,000.00 20,000.00
1.00 NoBuilt in robe6 1,500.00 1,500.00
1.00 NoStudy / library storage cupboard7 1,500.00 1,500.00
1.00 NoDouble basin vanity with stone benchtop8 3,000.00 3,000.00
2.00 NoSingle basin vanity with stone benchtop9 1,500.00 3,000.00
1.00 NoShower built in seat to ensuite10 800.00 800.00
JOINERY (PROVISIONAL SUM) Total : 99,800.00
WINDOWS & GLAZINGTrade : 10
Page : 6NEWIN ESTIMATING SERVICE 5/May/15Date of Printing:
- H10 FIRST AVE BERALA NSW 2141 Global Estimating System (32 Bit)
of 14
SAM
PLE
Luxury Home_Cost Break Up_05.05.15
Job Name : ARCHITECT SAMPLE Job Description
Client's Name: Architect / Designer Sample Construction of 2 Storey Luxury Residence
Item DescriptionItem AmountRateUnitQuantity
No.
WINDOWS & GLAZINGTrade : 10
WINDOWS & GLAZING
Lower Floor
19.00 m2Supply timber framed windows :[13 No]1 850.00 16,150.00
13.00 m2Supply timber framed doors :[3 No]2 950.00 12,350.00
Upper Floor
31.00 m2Supply timber framed windows :[23 No]3 850.00 26,350.00
24.00 m2Supply timber framed doors :[4 No]4 950.00 22,800.00
WINDOWS & GLAZING Total : 77,650.00
FIXTURES & FITTINGS (PROVISIONAL SUM)Trade : 11
FIXTURES & FITTINGS (PROVISIONAL
SUM)
Lower Floor
Family Bath
1.00 ItemFrameless shower screen1 1,500.00 1,500.00
1.00 ItemShower set2 550.00 550.00
1.00 ItemInwall toilet suite3 1,600.00 1,600.00
1.00 ItemBidet4 1,200.00 1,200.00
2.00 ItemBasin mixer5 150.00 300.00
1.00 ItemMirror6 1,000.00 1,000.00
1.00 ItemSoap holder7 100.00 100.00
1.00 ItemToilet roll holder8 80.00 80.00
1.00 ItemTowel Rack9 120.00 120.00
1.00 ItemCoat hook10 80.00 80.00
Ensuite
1.00 ItemFrameless shower screen11 1,500.00 1,500.00
1.00 ItemShower set12 550.00 550.00
1.00 ItemFree standing bath / spa13 3,000.00 3,000.00
1.00 ItemWall mounted spout & mixer14 650.00 650.00
1.00 ItemInwall toilet suite15 1,600.00 1,600.00
1.00 ItemBidet16 1,200.00 1,200.00
2.00 ItemBasin mixer17 150.00 300.00
Page : 7NEWIN ESTIMATING SERVICE 5/May/15Date of Printing:
- H10 FIRST AVE BERALA NSW 2141 Global Estimating System (32 Bit)
of 14
SAM
PLE
Luxury Home_Cost Break Up_05.05.15
Job Name : ARCHITECT SAMPLE Job Description
Client's Name: Architect / Designer Sample Construction of 2 Storey Luxury Residence
Item DescriptionItem AmountRateUnitQuantity
No.
FIXTURES & FITTINGS (PROVISIONAL SUM)Trade : 11 (Continued)
1.00 ItemMirror18 1,000.00 1,000.00
1.00 ItemSoap holder19 100.00 100.00
1.00 ItemToilet roll holder20 80.00 80.00
1.00 ItemTowel Rack21 120.00 120.00
1.00 ItemCoat hook22 80.00 80.00
Laundry
1.00 ItemLaundry tub23 550.00 550.00
1.00 ItemMixer24 250.00 250.00
Upper Floor
Kitchen
1.00 ItemUndermount sink25 750.00 750.00
1.00 ItemSpout mixer26 450.00 450.00
1.00 ItemInsinkerator27 950.00 950.00
1.00 ItemCooktop28 1,500.00 1,500.00
2.00 ItemOven29 1,800.00 3,600.00
1.00 ItemRangehood30 1,250.00 1,250.00
1.00 ItemMicrowave31 600.00 600.00
1.00 ItemDishwasher32 1,800.00 1,800.00
Guest WC
1.00 ItemFrameless shower screen33 1,500.00 1,500.00
1.00 ItemShower set34 550.00 550.00
1.00 ItemInwall toilet suite35 1,600.00 1,600.00
1.00 ItemBasin mixer36 150.00 150.00
1.00 ItemMirror37 1,000.00 1,000.00
1.00 ItemSoap holder38 100.00 100.00
1.00 ItemToilet roll holder39 80.00 80.00
1.00 ItemTowel Rack40 120.00 120.00
1.00 ItemCoat hook41 80.00 80.00
FIXTURES & FITTINGS (PROVISIONAL SUM) Total : 33,590.00
WATERPROOFING & TILINGTrade : 12
WATERPROOFING & TILING
Page : 8NEWIN ESTIMATING SERVICE 5/May/15Date of Printing:
- H10 FIRST AVE BERALA NSW 2141 Global Estimating System (32 Bit)
of 14
SAM
PLE
Luxury Home_Cost Break Up_05.05.15
Job Name : ARCHITECT SAMPLE Job Description
Client's Name: Architect / Designer Sample Construction of 2 Storey Luxury Residence
Item DescriptionItem AmountRateUnitQuantity
No.
WATERPROOFING & TILINGTrade : 12 (Continued)
Waterproofing
129.00 m2Bitumen paint to planter terrace retaining walls1 50.00 6,450.00
47.00 m2Waterproof wet area floors2 55.00 2,585.00
135.00 m2Waterproof wet area walls3 55.00 7,425.00
66.00 m2Waterproof to verandahs4 55.00 3,630.00
83.00 m2Waterproof to porch / path and driveway5 55.00 4,565.00
Tiling
305.00 m2Screeding to wet areas / kitchen / hallway / linen
/ dining / entry / rear hall / broom / linen / airlock
/ garage / verandah (max 40mm high)
6 35.00 10,675.00
47.00 m2Supply and fix stone / mosaic wet area floor tiles
incl. epoxy grout (PC Sum Supply $80/m2)
7 190.00 8,930.00
163.00 m2Supply and fix stone / mosaic wet area wall tiles
incl. epoxy grout (PC Sum Supply $80/m2)
8 190.00 30,970.00
7.00 m2Supply and fix stone floor tiles to broom incl.
epoxy grout (PC Sum Supply $80/m2)
9 190.00 1,330.00
3.00 m2Supply and fix stone floor tiles to air lock incl.
epoxy grout (PC Sum Supply $80/m2)
10 190.00 570.00
4.00 m2Supply and fix stone tiles to linen incl. epoxy
grout (PC Sum Supply $80/m2)
11 190.00 760.00
50.00 m2Supply and fix stone floor tiles to hall incl. epoxy
grout (PC Sum Supply $80/m2)
12 190.00 9,500.00
38.00 m2Supply and fix ceramic floor tiles to garage incl.
epoxy grout (PC Sum Supply $80/m2)
13 190.00 7,220.00
83.00 m2Supply and fix ceramic floor tiles to porch / path
& driveway incl. epoxy grout (PC Sum Supply
$80/m2)
14 190.00 15,770.00
66.00 m2Supply and fix stone floor tiles to verandahs incl.
epoxy grout (PC Sum Supply $80/m2)
15 190.00 12,540.00
28.00 m2Supply and fix marble tiles to kitchen incl. epoxy
grout (PC Sum Supply $150/m2)
16 260.00 7,280.00
62.00 m2Supply and fix marble tiles to dining / entry / rear
hall incl. epoxy grout (PC Sum Supply $150/m2)
17 260.00 16,120.00
Supply and fix ceramic floor tiles to porch / path
& driveway incl. epoxy grout (PC Sum Supply
$80/m2)
18
WATERPROOFING & TILING Total : 146,320.00
PLASTERINGTrade : 13
PLASTERING
Ceilings
326.00 m2Plasterboard suspended ceiling1 35.00 11,410.00
Page : 9NEWIN ESTIMATING SERVICE 5/May/15Date of Printing:
- H10 FIRST AVE BERALA NSW 2141 Global Estimating System (32 Bit)
of 14
SAM
PLE
Luxury Home_Cost Break Up_05.05.15
Job Name : ARCHITECT SAMPLE Job Description
Client's Name: Architect / Designer Sample Construction of 2 Storey Luxury Residence
Item DescriptionItem AmountRateUnitQuantity
No.
PLASTERINGTrade : 13 (Continued)
1.00 ItemExtra over ceiling coffers2 5,000.00 5,000.00
47.00 m2Moisture resistant plasterboard ceiling3 45.00 2,115.00
365.00 mCornice4 75.00 27,375.00
2.00 NoCeiling access panels5 350.00 700.00
Walls
54.00 m2Internal plasterboard lining6 35.00 1,890.00
163.00 m2Villaboard lining7 45.00 7,335.00
27.00 m2Insulation8 30.00 810.00
811.00 m2Setting to internal walls9 20.00 16,220.00
PLASTERING Total : 72,855.00
RENDERINGTrade : 14
WALL FINISHES
811.00 m2Render to internal walls1 35.00 28,385.00
705.00 m2Allowance for acrylic render to external
brickwork
2 80.00 56,400.00
RENDERING Total : 84,785.00
FLOOR FINISHES (PROVISIONAL SUM)Trade : 15
FLOOR FINISHES (PROVISIONAL SUM)
78.00 m2Carpet to bedrooms and walk in robes1 120.00 9,360.00
58.00 m2Timber floorboards living & study / library2 180.00 10,440.00
FLOOR FINISHES (PROVISIONAL SUM) Total : 19,800.00
PAINTINGTrade : 16
PAINTING
648.00 m2Paint to new internal walls1 15.00 9,720.00
691.00 m2Paint to set ceiling2 20.00 13,820.00
19.00 NoPaint to doors3 160.00 3,040.00
1.00 ItemPaint miscellaneous4 5,000.00 5,000.00
1.00 ItemPaint external walls - allowed for in acrylic
render
5 EXCL
Page : 10NEWIN ESTIMATING SERVICE 5/May/15Date of Printing:
- H10 FIRST AVE BERALA NSW 2141 Global Estimating System (32 Bit)
of 14
SAM
PLE
Luxury Home_Cost Break Up_05.05.15
Job Name : ARCHITECT SAMPLE Job Description
Client's Name: Architect / Designer Sample Construction of 2 Storey Luxury Residence
Item DescriptionItem AmountRateUnitQuantity
No.
PAINTING Total : 31,580.00
HYDRAULIC SERVICES (PROVISIONAL SUM)Trade : 17
HYDRAULIC SERVICES (PROVISIONAL
SUM)
1.00 ItemSewer connection1 3,000.00 3,000.00
1.00 ItemStormwater connection2 3,000.00 3,000.00
1.00 ItemWater supply in3 850.00 850.00
1.00 ItemGas supply in4 2,250.00 2,250.00
1.00 ItemBoundary trap5 750.00 750.00
50.00 mSewer line rough-in6 65.00 3,250.00
80.00 mStormwater line rough-in7 65.00 5,200.00
1.00 NoSewer Pit8 500.00 500.00
10.00 NoStormwater Pit9 500.00 5,000.00
2.00 NoGas bayonets10 250.00 500.00
5.00 NoExternal hose cocks11 150.00 750.00
1.00 NoUnder slab sewer lines12 500.00 500.00
1.00 NoHeat insulation to pipework (lagging)13 350.00 350.00
1.00 NoConduits to floor14 450.00 450.00
1.00 NoFloor wastes15 700.00 700.00
1.00 NoStacks16 600.00 600.00
1.00 ItemHW Unit17 2,250.00 2,250.00
1.00 NoInitial fix18 5,000.00 5,000.00
1.00 NoFinial fix19 7,500.00 7,500.00
HYDRAULIC SERVICES (PROVISIONAL SUM) Total : 42,400.00
ELECTRICAL SERVICES (PROVISIONAL SUM)Trade : 18
ELECTRICAL SERVICES (PROVISIONAL
SUM)
Power
1.00 ItemElectrical Supply1 5,000.00 5,000.00
1.00 ItemMainboard2 2,500.00 2,500.00
5.00 NoCircuits3 450.00 2,250.00
49.00 NoDouble GPO4 110.00 5,390.00
3.00 NoWeatherproof double GPO5 150.00 450.00
Page : 11NEWIN ESTIMATING SERVICE 5/May/15Date of Printing:
- H10 FIRST AVE BERALA NSW 2141 Global Estimating System (32 Bit)
of 14
SAM
PLE
Luxury Home_Cost Break Up_05.05.15
Job Name : ARCHITECT SAMPLE Job Description
Client's Name: Architect / Designer Sample Construction of 2 Storey Luxury Residence
Item DescriptionItem AmountRateUnitQuantity
No.
ELECTRICAL SERVICES (PROVISIONAL SUM)Trade : 18 (Continued)
Lighting
1.00 ItemLighting supply allowance6 15,000.00 15,000.00
90.00 NoInstall lights only7 80.00 7,200.00
Communication
1.00 NoHardwired smoke alarm8 200.00 200.00
8.00 NoData outlet9 165.00 1,320.00
6.00 NoTV outlet10 165.00 990.00
1.00 ItemTV antenna11 500.00 500.00
Miscellaneous
1.00 ItemAllowance install appliances12 1,200.00 1,200.00
ELECTRICAL SERVICES (PROVISIONAL SUM) Total : 42,000.00
MECHANICAL SERVICES (PROVISIONAL SUM)Trade : 19
MECHANICAL SERVICES
(PROVISIONAL SUM)
4.00 NoWet area ventilation1 350.00 1,400.00
1.00 ItemDucted air conditioning system2 20,000.00 20,000.00
MECHANICAL SERVICES (PROVISIONAL SUM) Total : 21,400.00
LIFT SERVICESTrade : 20
1.00 NoPassenger lift servicing 2 levels1 70,000.00 70,000.00
LIFT SERVICES Total : 70,000.00
EXTERNAL WORKSTrade : 21
EXTERNAL WORKS
Council Works
18.00 mNew / repair kerb and gutter1 50.00 900.00
26.00 m2Council footpath2 60.00 1,560.00
29.00 m2Verge landscaping3 25.00 725.00
1.00 NoCrossover4 3,500.00 3,500.00
Landscaping
657.00 m2Landscaping to over site5 50.00 32,850.00
Page : 12NEWIN ESTIMATING SERVICE 5/May/15Date of Printing:
- H10 FIRST AVE BERALA NSW 2141 Global Estimating System (32 Bit)
of 14
SAM
PLE
Luxury Home_Cost Break Up_05.05.15
Job Name : ARCHITECT SAMPLE Job Description
Client's Name: Architect / Designer Sample Construction of 2 Storey Luxury Residence
Item DescriptionItem AmountRateUnitQuantity
No.
EXTERNAL WORKSTrade : 21 (Continued)
657.00 m2Drainage and fill to site6 30.00 19,710.00
1.00 ItemAutomatic irrigation system7 15,000.00 15,000.00
EXTERNAL WORKS Total : 74,245.00
PRELIMINARIESTrade : 22
PRELIMINARIES
1.00 ItemSite establishment1 1,000.00 1,000.00
1.00 ItemAuthority fees2 2,000.00 2,000.00
1.00 ItemInsurances3 10,000.00 10,000.00
48.00 wksSite management4 1,700.00 81,600.00
48.00 wksSite labour5 1,000.00 48,000.00
48.00 wksSite admin/safety6 50.00 2,400.00
1.00 ItemScaffolding / hoarding / fencing7 20,000.00 20,000.00
48.00 wksConsumeables8 50.00 2,400.00
48.00 wksPlant and tools9 100.00 4,800.00
48.00 wksTemp services10 50.00 2,400.00
48.00 wksMaterials handling11 1,000.00 48,000.00
48.00 wksTraffic management12 100.00 4,800.00
1.00 ItemAnti errosion measures13 1,000.00 1,000.00
48.00 wksProgressive clean14 150.00 7,200.00
1.00 ItemSurveyor15 2,000.00 2,000.00
1.00 ItemFinal clean up16 1,200.00 1,200.00
1.00 ItemSite demobilisation17 1,000.00 1,000.00
PRELIMINARIES Total : 239,800.00
PROFIT/MARGINTrade : 23
0.05 %Allowance for Builders Margin at 5%1 1,913,365.00 95,668.25
1.00 Item2
PROFIT/MARGIN Total : 95,668.25
SubtotalTrade : 24
Page : 13NEWIN ESTIMATING SERVICE 5/May/15Date of Printing:
- H10 FIRST AVE BERALA NSW 2141 Global Estimating System (32 Bit)
of 14
SAM
PLE
Luxury Home_Cost Break Up_05.05.15
Job Name : ARCHITECT SAMPLE Job Description
Client's Name: Architect / Designer Sample Construction of 2 Storey Luxury Residence
Item DescriptionItem AmountRateUnitQuantity
No.
SubtotalTrade : 24
Subtotal Total :
CONTINGENCY RECOMMENDEDTrade : 25
1.00 ItemAllowance of 5% for Contingency1 100,451.70 100,451.70
CONTINGENCY RECOMMENDED Total : 100,451.70
Page : 14NEWIN ESTIMATING SERVICE 5/May/15Date of Printing:
- H10 FIRST AVE BERALA NSW 2141 Global Estimating System (32 Bit)
of 14
SAM
PLE

More Related Content

Similar to Architect Sample

Home Owner Sample
Home Owner SampleHome Owner Sample
Home Owner SampleHai Nguyen
 
Home Owner Sample
Home Owner SampleHome Owner Sample
Home Owner SampleHai Nguyen
 
Labour Productivity for construction projects
Labour Productivity for construction projectsLabour Productivity for construction projects
Labour Productivity for construction projectsKapugantikapuganti Gupta
 
DESIGN OF G+20 MULTISTOREY BUILDING
DESIGN OF G+20 MULTISTOREY BUILDINGDESIGN OF G+20 MULTISTOREY BUILDING
DESIGN OF G+20 MULTISTOREY BUILDINGAnjneya Srivastava
 
Construction report (boq, wbs, reports, evm)
Construction report (boq, wbs, reports, evm)Construction report (boq, wbs, reports, evm)
Construction report (boq, wbs, reports, evm)Hamza Waheed
 
EarthQuake Reistant Building
EarthQuake Reistant BuildingEarthQuake Reistant Building
EarthQuake Reistant BuildingHemant Srivastava
 
Industrial training report
Industrial training reportIndustrial training report
Industrial training reportkiransuresh7
 
Industrial training report
Industrial training reportIndustrial training report
Industrial training reportkiransuresh7
 
SMM7 Bill of Quantities
SMM7 Bill of QuantitiesSMM7 Bill of Quantities
SMM7 Bill of QuantitiesNatalie Reid
 
Selleck, Matthew NEDF Built Environment Project
Selleck, Matthew NEDF Built Environment Project Selleck, Matthew NEDF Built Environment Project
Selleck, Matthew NEDF Built Environment Project MatthewSelleck1
 
Schedule of Works Cost Summary Report
Schedule of Works Cost Summary ReportSchedule of Works Cost Summary Report
Schedule of Works Cost Summary ReportNatalie Reid
 
Rajgir Sports Complex_Project Kick Off Presentation.pptx
Rajgir Sports Complex_Project Kick Off Presentation.pptxRajgir Sports Complex_Project Kick Off Presentation.pptx
Rajgir Sports Complex_Project Kick Off Presentation.pptxsyedaliabl2023
 
Computer Aided Analysis and Design of Multi-Storeyed Building using Staad Pro
Computer Aided Analysis and Design of Multi-Storeyed Building using Staad ProComputer Aided Analysis and Design of Multi-Storeyed Building using Staad Pro
Computer Aided Analysis and Design of Multi-Storeyed Building using Staad ProIRJET Journal
 
Project Management Services
Project Management ServicesProject Management Services
Project Management ServicesBruce Tharp
 
Prima Vera Final Project PPT.pptx
Prima Vera Final Project PPT.pptxPrima Vera Final Project PPT.pptx
Prima Vera Final Project PPT.pptxZiyad Zaidi
 

Similar to Architect Sample (20)

Home Owner Sample
Home Owner SampleHome Owner Sample
Home Owner Sample
 
Home Owner Sample
Home Owner SampleHome Owner Sample
Home Owner Sample
 
Labour Productivity for construction projects
Labour Productivity for construction projectsLabour Productivity for construction projects
Labour Productivity for construction projects
 
ECA form
ECA formECA form
ECA form
 
Project assign 2
Project assign 2Project assign 2
Project assign 2
 
DESIGN OF G+20 MULTISTOREY BUILDING
DESIGN OF G+20 MULTISTOREY BUILDINGDESIGN OF G+20 MULTISTOREY BUILDING
DESIGN OF G+20 MULTISTOREY BUILDING
 
3. Hansons lodge.pdf
3. Hansons lodge.pdf3. Hansons lodge.pdf
3. Hansons lodge.pdf
 
Construction report (boq, wbs, reports, evm)
Construction report (boq, wbs, reports, evm)Construction report (boq, wbs, reports, evm)
Construction report (boq, wbs, reports, evm)
 
EarthQuake Reistant Building
EarthQuake Reistant BuildingEarthQuake Reistant Building
EarthQuake Reistant Building
 
Industrial training report
Industrial training reportIndustrial training report
Industrial training report
 
Industrial training report
Industrial training reportIndustrial training report
Industrial training report
 
SMM7 Bill of Quantities
SMM7 Bill of QuantitiesSMM7 Bill of Quantities
SMM7 Bill of Quantities
 
Selleck, Matthew NEDF Built Environment Project
Selleck, Matthew NEDF Built Environment Project Selleck, Matthew NEDF Built Environment Project
Selleck, Matthew NEDF Built Environment Project
 
Schedule of Works Cost Summary Report
Schedule of Works Cost Summary ReportSchedule of Works Cost Summary Report
Schedule of Works Cost Summary Report
 
Training PPT
Training PPTTraining PPT
Training PPT
 
Rajgir Sports Complex_Project Kick Off Presentation.pptx
Rajgir Sports Complex_Project Kick Off Presentation.pptxRajgir Sports Complex_Project Kick Off Presentation.pptx
Rajgir Sports Complex_Project Kick Off Presentation.pptx
 
GBI: Role of BS
GBI: Role of BSGBI: Role of BS
GBI: Role of BS
 
Computer Aided Analysis and Design of Multi-Storeyed Building using Staad Pro
Computer Aided Analysis and Design of Multi-Storeyed Building using Staad ProComputer Aided Analysis and Design of Multi-Storeyed Building using Staad Pro
Computer Aided Analysis and Design of Multi-Storeyed Building using Staad Pro
 
Project Management Services
Project Management ServicesProject Management Services
Project Management Services
 
Prima Vera Final Project PPT.pptx
Prima Vera Final Project PPT.pptxPrima Vera Final Project PPT.pptx
Prima Vera Final Project PPT.pptx
 

Architect Sample

  • 1. Luxury Home_Cost Summary_05.05.15 Job DescriptionJob Name : ARCHITECT SAMPLE Construction of 2 Storey Luxury ResidenceClient's Name: Architect / Designer Sample m2Cost/TradeTrade DescriptionTrd Trade TotalNo. % NOTES1 95,750DEMOLITION & EXCAVATION 4.54 239.382 177,610CONCRETE 8.42 444.033 188,090BRICKWORK / BLOCKWORK 8.92 470.234 38,640STRUCTURAL STEEL 1.83 96.605 151,750METAL WORK 7.19 379.386 60,780ROOFING 2.88 151.957 144,520CARPENTRY 6.85 361.308 99,800JOINERY (PROVISIONAL SUM) 4.73 249.509 77,650WINDOWS & GLAZING 3.68 194.1310 33,590FIXTURES & FITTINGS (PROVISIONAL SUM) 1.59 83.9811 146,320WATERPROOFING & TILING 6.94 365.8012 72,855PLASTERING 3.45 182.1413 84,785RENDERING 4.02 211.9614 19,800FLOOR FINISHES (PROVISIONAL SUM) 0.94 49.5015 31,580PAINTING 1.50 78.9516 42,400HYDRAULIC SERVICES (PROVISIONAL SUM) 2.01 106.0017 42,000ELECTRICAL SERVICES (PROVISIONAL SUM) 1.99 105.0018 21,400MECHANICAL SERVICES (PROVISIONAL SUM) 1.01 53.5019 70,000LIFT SERVICES 3.32 175.0020 74,245EXTERNAL WORKS 3.52 185.6121 239,800PRELIMINARIES 11.37 599.5022 95,669PROFIT/MARGIN 4.54 239.1723 Subtotal24 2,009,034 100,452CONTINGENCY RECOMMENDED 4.76 251.1325 2,109,486100.00 5,273.72GFA: 400 m2. $ 2,109,486Final Total : Page : 1NEWIN ESTIMATING SERVICE 5/May/15Date of Printing: Global Estimating System (32 Bit) - H10 FIRST AVE BERALA NSW 2141 of 1 SAM PLE
  • 2. Luxury Home_Cost Break Up_05.05.15 Job Name : ARCHITECT SAMPLE Job Description Client's Name: Architect / Designer Sample Construction of 2 Storey Luxury Residence Item DescriptionItem AmountRateUnitQuantity No. NOTESTrade : 1 DRAWINGS NoteThis estimate was prepared from the following drawings and documentation: 1 Architectural Drawings 00 to 27 (Rev A) dated 11 March 2015 and prepared by Michael Robilliard & Associates 2 Structural Drawings S.01 to 12 dated February 2015 and prepared by Birzulis Associates 3 INCLUSIONS Rock excavation.4 Demolition & general site clearance.5 Bulk excavation and detailed excavation.6 Allowance for services connections and associated works. 7 Allowance for smoke detectors.8 Allowance for wet area ventilation9 Allowace for air conditioning.10 Allowance for lift service.11 Allowance for landscaping over site.12 High quality finishes and fitments.13 Builder's preliminaries in the order of approximately 13% and a builder's profit of 5% of the construction cost which we believe are generally fair and reasonable in current market conditions. 14 A construction period of 48 weeks.15 16 EXCLUSIONS Services diversions, easement, encasements or the like. 17 Grey water management.18 Water Authority requirements.19 Smart system wiring.20 Contingency. We recommend a contingency of 5% be allowed over the entire project. 21 Escalation in costs and union enterprise bargaining costs. 22 Any cost increases associated with the 10% GST.23 Page : 1NEWIN ESTIMATING SERVICE 5/May/15Date of Printing: - H10 FIRST AVE BERALA NSW 2141 Global Estimating System (32 Bit) of 14 SAM PLE
  • 3. Luxury Home_Cost Break Up_05.05.15 Job Name : ARCHITECT SAMPLE Job Description Client's Name: Architect / Designer Sample Construction of 2 Storey Luxury Residence Item DescriptionItem AmountRateUnitQuantity No. NOTESTrade : 1 (Continued) Any cost increases associated with the Carbon Tax. 24 Council contributions, design fees, authority fees, bank fees and charges, marketing, leasing and selling costs. 25 26 DISCLAIMER This report is for use by the party to whom it is addressed and for no other purposes. No responsibility is taken for any third party who may use or rely on the whole or any part of this report. 27 All quantities are approximate only.28 Under no circumstances are the quantities or rates to form part of the building contract. 29 Our costs include no provision for any change in costs associated with amendments to current tax laws and/or for the introduction of a goods and services tax (GST). 30 NOTES Total : DEMOLITION & EXCAVATIONTrade : 2 DEMOLITION & EXCAVATION Demolition 1.00 ItemDemolish existing structures1 35,000.00 35,000.00 Excavation 468.00 m2Site clearance2 25.00 11,700.00 234.00 m3Bulk excavation into rock3 145.00 33,930.00 54.00 m3Detailed excavation into rock4 280.00 15,120.00 DEMOLITION & EXCAVATION Total : 95,750.00 CONCRETETrade : 3 CONCRETE Foundation 52.00 m3Concrete strip footings :[142 m]1 550.00 28,600.00 3.00 m3Concrete pad footings :[27 No]2 550.00 1,650.00 1.00 ItemLift pit complete3 5,000.00 5,000.00 Page : 2NEWIN ESTIMATING SERVICE 5/May/15Date of Printing: - H10 FIRST AVE BERALA NSW 2141 Global Estimating System (32 Bit) of 14 SAM PLE
  • 4. Luxury Home_Cost Break Up_05.05.15 Job Name : ARCHITECT SAMPLE Job Description Client's Name: Architect / Designer Sample Construction of 2 Storey Luxury Residence Item DescriptionItem AmountRateUnitQuantity No. CONCRETETrade : 3 (Continued) Lower Floor 38.00 m3Suspended concrete slab :[235 m2]4 220.00 8,360.00 235.00 m2Bondek to suspended slab5 90.00 21,150.00 70.00 mStop ends6 35.00 2,450.00 5.00 TonneReinforcement to suspended slab (120kg/m3)7 1,500.00 7,500.00 Upper Floor 63.00 m3Suspended concrete slab :[337 m2]8 220.00 13,860.00 337.00 m2Formwork to suspended slab9 80.00 26,960.00 98.00 mStop ends10 35.00 3,430.00 8.00 TonneReinforcement to suspended slab (120kg/m3)11 1,500.00 12,000.00 Stair / Ramp 1.00 ItemConcrete curved internal stair12 12,000.00 12,000.00 131.00 m2External ramp / footpath13 150.00 19,650.00 Sundries 1.00 ItemDrains/sumps/cure/joints/pump/test/etc14 15,000.00 15,000.00 CONCRETE Total : 177,610.00 BRICKWORK / BLOCKWORKTrade : 4 BRICKWORK / BLOCKWORK Foundation 156.00 m2230mm brick foundation walling (Assume avg 1.2m high) 1 160.00 24,960.00 27.00 NoBrick piers2 120.00 3,240.00 11.00 m2140mm concrete corefilled block lift walling3 180.00 1,980.00 Lower Floor 31.00 m2140mm concrete corefilled block lift walling4 180.00 5,580.00 233.00 m2Double common brick external walling5 160.00 37,280.00 15.00 m2Double common brick internal walling6 160.00 2,400.00 213.00 m2Single common brick internal walling7 90.00 19,170.00 Upper Floor 27.00 m2140mm concrete corefilled block lift walling8 180.00 4,860.00 156.00 m2Double common brick external walling9 160.00 24,960.00 Page : 3NEWIN ESTIMATING SERVICE 5/May/15Date of Printing: - H10 FIRST AVE BERALA NSW 2141 Global Estimating System (32 Bit) of 14 SAM PLE
  • 5. Luxury Home_Cost Break Up_05.05.15 Job Name : ARCHITECT SAMPLE Job Description Client's Name: Architect / Designer Sample Construction of 2 Storey Luxury Residence Item DescriptionItem AmountRateUnitQuantity No. BRICKWORK / BLOCKWORKTrade : 4 (Continued) 6.00 m2Double common brick internal walling10 160.00 960.00 99.00 m2Single common brick internal walling11 90.00 8,910.00 External 118.00 m2140mm concrete corefilled block retaining walls (Assume avg 2m high) 12 180.00 21,240.00 21.00 m2Double common brick front boundary fence13 160.00 3,360.00 Sundries 98.00 mTermite treatment14 30.00 2,940.00 75.00 ThouMud, dpc, lintels, etc15 350.00 26,250.00 BRICKWORK / BLOCKWORK Total : 188,090.00 STRUCTURAL STEELTrade : 5 STRUCTURAL STEEL 3.00 TonneStructural Steel1 11,500.00 34,500.00 1.00 ItemBolts, plates, braces etc.. @ 12%2 4,140.00 4,140.00 STRUCTURAL STEEL Total : 38,640.00 METAL WORKTrade : 6 METAL WORK Wrought Iron Works 1.00 ItemWrought iron security double leaf door to house entry 1 5,500.00 5,500.00 14.00 mWrought iron curved balustrade to internal stair2 1,350.00 18,900.00 29.00 mWrought iron balustrade3 1,150.00 33,350.00 1.00 ItemWrought iron car entry gate - automated4 20,000.00 20,000.00 1.00 ItemWrought iron pedestrian entry gate5 4,000.00 4,000.00 11.00 m2Wrought iron fence panels to front brick wall6 1,150.00 12,650.00 7.00 m2Wrought iron security bars to windows7 1,150.00 8,050.00 Strip Drains 5.00 mCustom strip drain to wet areas8 450.00 2,250.00 19.00 mCustom strip drain to verandahs9 450.00 8,550.00 Fireplace 2.00 NoGas fire place complete10 9,000.00 18,000.00 Page : 4NEWIN ESTIMATING SERVICE 5/May/15Date of Printing: - H10 FIRST AVE BERALA NSW 2141 Global Estimating System (32 Bit) of 14 SAM PLE
  • 6. Luxury Home_Cost Break Up_05.05.15 Job Name : ARCHITECT SAMPLE Job Description Client's Name: Architect / Designer Sample Construction of 2 Storey Luxury Residence Item DescriptionItem AmountRateUnitQuantity No. METAL WORKTrade : 6 (Continued) Awning 28.00 m2Retractable awning above upper level verandah11 550.00 15,400.00 Miscellaneous 1.00 ItemAutomated garage door - Provisional Sum12 4,500.00 4,500.00 1.00 ItemLetter box13 450.00 450.00 1.00 ItemSignage14 150.00 150.00 METAL WORK Total : 151,750.00 ROOFINGTrade : 7 ROOFING 1.00 ItemAllowance for tarp protection during construction 1 2,500.00 2,500.00 297.00 m2Terracotta roof cladding2 100.00 29,700.00 297.00 m2EO insulation3 30.00 8,910.00 81.00 mFascia4 65.00 5,265.00 40.00 mGutter5 55.00 2,200.00 57.00 m2Eaves lining6 65.00 3,705.00 60.00 mDownpipes7 50.00 3,000.00 2.00 ItemElectric skylights8 2,750.00 5,500.00 ROOFING Total : 60,780.00 CARPENTRYTrade : 8 CARPENTRY Doors Lower Floor 1.00 NoLift door1 2,500.00 2,500.00 10.00 NoInternal solidcore single leaf door2 1,500.00 15,000.00 11.00 NoDoor hardware3 250.00 2,750.00 Upper Floor 1.00 NoLift door4 2,500.00 2,500.00 3.00 NoInternal solidcore single leaf door5 1,500.00 4,500.00 1.00 NoInternal solidcore double leaf door6 1,500.00 1,500.00 Page : 5NEWIN ESTIMATING SERVICE 5/May/15Date of Printing: - H10 FIRST AVE BERALA NSW 2141 Global Estimating System (32 Bit) of 14 SAM PLE
  • 7. Luxury Home_Cost Break Up_05.05.15 Job Name : ARCHITECT SAMPLE Job Description Client's Name: Architect / Designer Sample Construction of 2 Storey Luxury Residence Item DescriptionItem AmountRateUnitQuantity No. CARPENTRYTrade : 8 (Continued) 1.00 No3 panel cavity sliding door to dining room - Provisional Sum 7 10,000.00 10,000.00 1.00 NoOperable wall to living / kitchen - Provisional Sum 8 10,000.00 10,000.00 7.00 NoDoor hardware9 250.00 1,750.00 Framing 27.00 m2Internal timber stud walling10 45.00 1,215.00 297.00 m2Timber roof framing11 165.00 49,005.00 1.00 ItemDucts/boxing out12 5,000.00 5,000.00 Glazing 160.00 HrsLabour to install glazing - 2 men x 10 days13 55.00 8,800.00 1.00 ItemSundries14 5,000.00 5,000.00 Architraves / Skirting 1.00 ItemProvisional sum allowance for architraves and skirtings 15 15,000.00 15,000.00 1.00 ItemExternal window concrete architraves16 10,000.00 10,000.00 CARPENTRY Total : 144,520.00 JOINERY (PROVISIONAL SUM)Trade : 9 JOINERY (PROVISIONAL SUM) 1.00 ItemKitchen fitout incl. stone bench top, splashback & island 1 40,000.00 40,000.00 1.00 ItemLaundry fitout incl. stone bench top2 15,000.00 15,000.00 1.00 ItemLinen fitout3 5,000.00 5,000.00 1.00 ItemBroom closet fitout4 10,000.00 10,000.00 2.00 ItemWalk in robe5 10,000.00 20,000.00 1.00 NoBuilt in robe6 1,500.00 1,500.00 1.00 NoStudy / library storage cupboard7 1,500.00 1,500.00 1.00 NoDouble basin vanity with stone benchtop8 3,000.00 3,000.00 2.00 NoSingle basin vanity with stone benchtop9 1,500.00 3,000.00 1.00 NoShower built in seat to ensuite10 800.00 800.00 JOINERY (PROVISIONAL SUM) Total : 99,800.00 WINDOWS & GLAZINGTrade : 10 Page : 6NEWIN ESTIMATING SERVICE 5/May/15Date of Printing: - H10 FIRST AVE BERALA NSW 2141 Global Estimating System (32 Bit) of 14 SAM PLE
  • 8. Luxury Home_Cost Break Up_05.05.15 Job Name : ARCHITECT SAMPLE Job Description Client's Name: Architect / Designer Sample Construction of 2 Storey Luxury Residence Item DescriptionItem AmountRateUnitQuantity No. WINDOWS & GLAZINGTrade : 10 WINDOWS & GLAZING Lower Floor 19.00 m2Supply timber framed windows :[13 No]1 850.00 16,150.00 13.00 m2Supply timber framed doors :[3 No]2 950.00 12,350.00 Upper Floor 31.00 m2Supply timber framed windows :[23 No]3 850.00 26,350.00 24.00 m2Supply timber framed doors :[4 No]4 950.00 22,800.00 WINDOWS & GLAZING Total : 77,650.00 FIXTURES & FITTINGS (PROVISIONAL SUM)Trade : 11 FIXTURES & FITTINGS (PROVISIONAL SUM) Lower Floor Family Bath 1.00 ItemFrameless shower screen1 1,500.00 1,500.00 1.00 ItemShower set2 550.00 550.00 1.00 ItemInwall toilet suite3 1,600.00 1,600.00 1.00 ItemBidet4 1,200.00 1,200.00 2.00 ItemBasin mixer5 150.00 300.00 1.00 ItemMirror6 1,000.00 1,000.00 1.00 ItemSoap holder7 100.00 100.00 1.00 ItemToilet roll holder8 80.00 80.00 1.00 ItemTowel Rack9 120.00 120.00 1.00 ItemCoat hook10 80.00 80.00 Ensuite 1.00 ItemFrameless shower screen11 1,500.00 1,500.00 1.00 ItemShower set12 550.00 550.00 1.00 ItemFree standing bath / spa13 3,000.00 3,000.00 1.00 ItemWall mounted spout & mixer14 650.00 650.00 1.00 ItemInwall toilet suite15 1,600.00 1,600.00 1.00 ItemBidet16 1,200.00 1,200.00 2.00 ItemBasin mixer17 150.00 300.00 Page : 7NEWIN ESTIMATING SERVICE 5/May/15Date of Printing: - H10 FIRST AVE BERALA NSW 2141 Global Estimating System (32 Bit) of 14 SAM PLE
  • 9. Luxury Home_Cost Break Up_05.05.15 Job Name : ARCHITECT SAMPLE Job Description Client's Name: Architect / Designer Sample Construction of 2 Storey Luxury Residence Item DescriptionItem AmountRateUnitQuantity No. FIXTURES & FITTINGS (PROVISIONAL SUM)Trade : 11 (Continued) 1.00 ItemMirror18 1,000.00 1,000.00 1.00 ItemSoap holder19 100.00 100.00 1.00 ItemToilet roll holder20 80.00 80.00 1.00 ItemTowel Rack21 120.00 120.00 1.00 ItemCoat hook22 80.00 80.00 Laundry 1.00 ItemLaundry tub23 550.00 550.00 1.00 ItemMixer24 250.00 250.00 Upper Floor Kitchen 1.00 ItemUndermount sink25 750.00 750.00 1.00 ItemSpout mixer26 450.00 450.00 1.00 ItemInsinkerator27 950.00 950.00 1.00 ItemCooktop28 1,500.00 1,500.00 2.00 ItemOven29 1,800.00 3,600.00 1.00 ItemRangehood30 1,250.00 1,250.00 1.00 ItemMicrowave31 600.00 600.00 1.00 ItemDishwasher32 1,800.00 1,800.00 Guest WC 1.00 ItemFrameless shower screen33 1,500.00 1,500.00 1.00 ItemShower set34 550.00 550.00 1.00 ItemInwall toilet suite35 1,600.00 1,600.00 1.00 ItemBasin mixer36 150.00 150.00 1.00 ItemMirror37 1,000.00 1,000.00 1.00 ItemSoap holder38 100.00 100.00 1.00 ItemToilet roll holder39 80.00 80.00 1.00 ItemTowel Rack40 120.00 120.00 1.00 ItemCoat hook41 80.00 80.00 FIXTURES & FITTINGS (PROVISIONAL SUM) Total : 33,590.00 WATERPROOFING & TILINGTrade : 12 WATERPROOFING & TILING Page : 8NEWIN ESTIMATING SERVICE 5/May/15Date of Printing: - H10 FIRST AVE BERALA NSW 2141 Global Estimating System (32 Bit) of 14 SAM PLE
  • 10. Luxury Home_Cost Break Up_05.05.15 Job Name : ARCHITECT SAMPLE Job Description Client's Name: Architect / Designer Sample Construction of 2 Storey Luxury Residence Item DescriptionItem AmountRateUnitQuantity No. WATERPROOFING & TILINGTrade : 12 (Continued) Waterproofing 129.00 m2Bitumen paint to planter terrace retaining walls1 50.00 6,450.00 47.00 m2Waterproof wet area floors2 55.00 2,585.00 135.00 m2Waterproof wet area walls3 55.00 7,425.00 66.00 m2Waterproof to verandahs4 55.00 3,630.00 83.00 m2Waterproof to porch / path and driveway5 55.00 4,565.00 Tiling 305.00 m2Screeding to wet areas / kitchen / hallway / linen / dining / entry / rear hall / broom / linen / airlock / garage / verandah (max 40mm high) 6 35.00 10,675.00 47.00 m2Supply and fix stone / mosaic wet area floor tiles incl. epoxy grout (PC Sum Supply $80/m2) 7 190.00 8,930.00 163.00 m2Supply and fix stone / mosaic wet area wall tiles incl. epoxy grout (PC Sum Supply $80/m2) 8 190.00 30,970.00 7.00 m2Supply and fix stone floor tiles to broom incl. epoxy grout (PC Sum Supply $80/m2) 9 190.00 1,330.00 3.00 m2Supply and fix stone floor tiles to air lock incl. epoxy grout (PC Sum Supply $80/m2) 10 190.00 570.00 4.00 m2Supply and fix stone tiles to linen incl. epoxy grout (PC Sum Supply $80/m2) 11 190.00 760.00 50.00 m2Supply and fix stone floor tiles to hall incl. epoxy grout (PC Sum Supply $80/m2) 12 190.00 9,500.00 38.00 m2Supply and fix ceramic floor tiles to garage incl. epoxy grout (PC Sum Supply $80/m2) 13 190.00 7,220.00 83.00 m2Supply and fix ceramic floor tiles to porch / path & driveway incl. epoxy grout (PC Sum Supply $80/m2) 14 190.00 15,770.00 66.00 m2Supply and fix stone floor tiles to verandahs incl. epoxy grout (PC Sum Supply $80/m2) 15 190.00 12,540.00 28.00 m2Supply and fix marble tiles to kitchen incl. epoxy grout (PC Sum Supply $150/m2) 16 260.00 7,280.00 62.00 m2Supply and fix marble tiles to dining / entry / rear hall incl. epoxy grout (PC Sum Supply $150/m2) 17 260.00 16,120.00 Supply and fix ceramic floor tiles to porch / path & driveway incl. epoxy grout (PC Sum Supply $80/m2) 18 WATERPROOFING & TILING Total : 146,320.00 PLASTERINGTrade : 13 PLASTERING Ceilings 326.00 m2Plasterboard suspended ceiling1 35.00 11,410.00 Page : 9NEWIN ESTIMATING SERVICE 5/May/15Date of Printing: - H10 FIRST AVE BERALA NSW 2141 Global Estimating System (32 Bit) of 14 SAM PLE
  • 11. Luxury Home_Cost Break Up_05.05.15 Job Name : ARCHITECT SAMPLE Job Description Client's Name: Architect / Designer Sample Construction of 2 Storey Luxury Residence Item DescriptionItem AmountRateUnitQuantity No. PLASTERINGTrade : 13 (Continued) 1.00 ItemExtra over ceiling coffers2 5,000.00 5,000.00 47.00 m2Moisture resistant plasterboard ceiling3 45.00 2,115.00 365.00 mCornice4 75.00 27,375.00 2.00 NoCeiling access panels5 350.00 700.00 Walls 54.00 m2Internal plasterboard lining6 35.00 1,890.00 163.00 m2Villaboard lining7 45.00 7,335.00 27.00 m2Insulation8 30.00 810.00 811.00 m2Setting to internal walls9 20.00 16,220.00 PLASTERING Total : 72,855.00 RENDERINGTrade : 14 WALL FINISHES 811.00 m2Render to internal walls1 35.00 28,385.00 705.00 m2Allowance for acrylic render to external brickwork 2 80.00 56,400.00 RENDERING Total : 84,785.00 FLOOR FINISHES (PROVISIONAL SUM)Trade : 15 FLOOR FINISHES (PROVISIONAL SUM) 78.00 m2Carpet to bedrooms and walk in robes1 120.00 9,360.00 58.00 m2Timber floorboards living & study / library2 180.00 10,440.00 FLOOR FINISHES (PROVISIONAL SUM) Total : 19,800.00 PAINTINGTrade : 16 PAINTING 648.00 m2Paint to new internal walls1 15.00 9,720.00 691.00 m2Paint to set ceiling2 20.00 13,820.00 19.00 NoPaint to doors3 160.00 3,040.00 1.00 ItemPaint miscellaneous4 5,000.00 5,000.00 1.00 ItemPaint external walls - allowed for in acrylic render 5 EXCL Page : 10NEWIN ESTIMATING SERVICE 5/May/15Date of Printing: - H10 FIRST AVE BERALA NSW 2141 Global Estimating System (32 Bit) of 14 SAM PLE
  • 12. Luxury Home_Cost Break Up_05.05.15 Job Name : ARCHITECT SAMPLE Job Description Client's Name: Architect / Designer Sample Construction of 2 Storey Luxury Residence Item DescriptionItem AmountRateUnitQuantity No. PAINTING Total : 31,580.00 HYDRAULIC SERVICES (PROVISIONAL SUM)Trade : 17 HYDRAULIC SERVICES (PROVISIONAL SUM) 1.00 ItemSewer connection1 3,000.00 3,000.00 1.00 ItemStormwater connection2 3,000.00 3,000.00 1.00 ItemWater supply in3 850.00 850.00 1.00 ItemGas supply in4 2,250.00 2,250.00 1.00 ItemBoundary trap5 750.00 750.00 50.00 mSewer line rough-in6 65.00 3,250.00 80.00 mStormwater line rough-in7 65.00 5,200.00 1.00 NoSewer Pit8 500.00 500.00 10.00 NoStormwater Pit9 500.00 5,000.00 2.00 NoGas bayonets10 250.00 500.00 5.00 NoExternal hose cocks11 150.00 750.00 1.00 NoUnder slab sewer lines12 500.00 500.00 1.00 NoHeat insulation to pipework (lagging)13 350.00 350.00 1.00 NoConduits to floor14 450.00 450.00 1.00 NoFloor wastes15 700.00 700.00 1.00 NoStacks16 600.00 600.00 1.00 ItemHW Unit17 2,250.00 2,250.00 1.00 NoInitial fix18 5,000.00 5,000.00 1.00 NoFinial fix19 7,500.00 7,500.00 HYDRAULIC SERVICES (PROVISIONAL SUM) Total : 42,400.00 ELECTRICAL SERVICES (PROVISIONAL SUM)Trade : 18 ELECTRICAL SERVICES (PROVISIONAL SUM) Power 1.00 ItemElectrical Supply1 5,000.00 5,000.00 1.00 ItemMainboard2 2,500.00 2,500.00 5.00 NoCircuits3 450.00 2,250.00 49.00 NoDouble GPO4 110.00 5,390.00 3.00 NoWeatherproof double GPO5 150.00 450.00 Page : 11NEWIN ESTIMATING SERVICE 5/May/15Date of Printing: - H10 FIRST AVE BERALA NSW 2141 Global Estimating System (32 Bit) of 14 SAM PLE
  • 13. Luxury Home_Cost Break Up_05.05.15 Job Name : ARCHITECT SAMPLE Job Description Client's Name: Architect / Designer Sample Construction of 2 Storey Luxury Residence Item DescriptionItem AmountRateUnitQuantity No. ELECTRICAL SERVICES (PROVISIONAL SUM)Trade : 18 (Continued) Lighting 1.00 ItemLighting supply allowance6 15,000.00 15,000.00 90.00 NoInstall lights only7 80.00 7,200.00 Communication 1.00 NoHardwired smoke alarm8 200.00 200.00 8.00 NoData outlet9 165.00 1,320.00 6.00 NoTV outlet10 165.00 990.00 1.00 ItemTV antenna11 500.00 500.00 Miscellaneous 1.00 ItemAllowance install appliances12 1,200.00 1,200.00 ELECTRICAL SERVICES (PROVISIONAL SUM) Total : 42,000.00 MECHANICAL SERVICES (PROVISIONAL SUM)Trade : 19 MECHANICAL SERVICES (PROVISIONAL SUM) 4.00 NoWet area ventilation1 350.00 1,400.00 1.00 ItemDucted air conditioning system2 20,000.00 20,000.00 MECHANICAL SERVICES (PROVISIONAL SUM) Total : 21,400.00 LIFT SERVICESTrade : 20 1.00 NoPassenger lift servicing 2 levels1 70,000.00 70,000.00 LIFT SERVICES Total : 70,000.00 EXTERNAL WORKSTrade : 21 EXTERNAL WORKS Council Works 18.00 mNew / repair kerb and gutter1 50.00 900.00 26.00 m2Council footpath2 60.00 1,560.00 29.00 m2Verge landscaping3 25.00 725.00 1.00 NoCrossover4 3,500.00 3,500.00 Landscaping 657.00 m2Landscaping to over site5 50.00 32,850.00 Page : 12NEWIN ESTIMATING SERVICE 5/May/15Date of Printing: - H10 FIRST AVE BERALA NSW 2141 Global Estimating System (32 Bit) of 14 SAM PLE
  • 14. Luxury Home_Cost Break Up_05.05.15 Job Name : ARCHITECT SAMPLE Job Description Client's Name: Architect / Designer Sample Construction of 2 Storey Luxury Residence Item DescriptionItem AmountRateUnitQuantity No. EXTERNAL WORKSTrade : 21 (Continued) 657.00 m2Drainage and fill to site6 30.00 19,710.00 1.00 ItemAutomatic irrigation system7 15,000.00 15,000.00 EXTERNAL WORKS Total : 74,245.00 PRELIMINARIESTrade : 22 PRELIMINARIES 1.00 ItemSite establishment1 1,000.00 1,000.00 1.00 ItemAuthority fees2 2,000.00 2,000.00 1.00 ItemInsurances3 10,000.00 10,000.00 48.00 wksSite management4 1,700.00 81,600.00 48.00 wksSite labour5 1,000.00 48,000.00 48.00 wksSite admin/safety6 50.00 2,400.00 1.00 ItemScaffolding / hoarding / fencing7 20,000.00 20,000.00 48.00 wksConsumeables8 50.00 2,400.00 48.00 wksPlant and tools9 100.00 4,800.00 48.00 wksTemp services10 50.00 2,400.00 48.00 wksMaterials handling11 1,000.00 48,000.00 48.00 wksTraffic management12 100.00 4,800.00 1.00 ItemAnti errosion measures13 1,000.00 1,000.00 48.00 wksProgressive clean14 150.00 7,200.00 1.00 ItemSurveyor15 2,000.00 2,000.00 1.00 ItemFinal clean up16 1,200.00 1,200.00 1.00 ItemSite demobilisation17 1,000.00 1,000.00 PRELIMINARIES Total : 239,800.00 PROFIT/MARGINTrade : 23 0.05 %Allowance for Builders Margin at 5%1 1,913,365.00 95,668.25 1.00 Item2 PROFIT/MARGIN Total : 95,668.25 SubtotalTrade : 24 Page : 13NEWIN ESTIMATING SERVICE 5/May/15Date of Printing: - H10 FIRST AVE BERALA NSW 2141 Global Estimating System (32 Bit) of 14 SAM PLE
  • 15. Luxury Home_Cost Break Up_05.05.15 Job Name : ARCHITECT SAMPLE Job Description Client's Name: Architect / Designer Sample Construction of 2 Storey Luxury Residence Item DescriptionItem AmountRateUnitQuantity No. SubtotalTrade : 24 Subtotal Total : CONTINGENCY RECOMMENDEDTrade : 25 1.00 ItemAllowance of 5% for Contingency1 100,451.70 100,451.70 CONTINGENCY RECOMMENDED Total : 100,451.70 Page : 14NEWIN ESTIMATING SERVICE 5/May/15Date of Printing: - H10 FIRST AVE BERALA NSW 2141 Global Estimating System (32 Bit) of 14 SAM PLE