2. CONTENT
I. ProjectDescription
Locationofthe Project
TypesofContract
II. DescriptionOfEntirelyProject
AccessRoad
PoolYard
III. DesignOfAccessRoadPavement
INTRODUCTION
2
Conclusion
3. INTRODUCTION
3
Société de Gestion du Terminal à conteneurs de Doraleh (SGTD) and their mission
Mission during my internship is divided two main points:
Design of an access road pavement.
Description Of Entirely Project.
The mission of our department is to develop and follow project which complies with the client’s
objectives.
8. II. DescriptionOfEntirely Project
AccessRoad
Dynamic Compaction Method
- Definition
- Why we use the dynamic compaction
• Weak bearing capacity.
• Liquefaction
- Execution work of dynamic compaction
8
-Setting out of DC Prints in grid spacing,
9. II. DescriptionOfEntirely Project
AccessRoad
Post treatment testing
Plate load test Result
Balancing pipe
- Definition
• The main reason that we used balancing pip was stability
tides and water levels
9
13. II. DescriptionOfEntirely Project
PoolYard
Stone Column
- Definition
- Why we use the stone column
The main reason, we use stone column is to prevent
liquefaction phenomenon.
Liquefaction mitigation
Stone columns are thought to reduce liquefaction hazard and
improve soil performance in four main ways.
• stone columns, also called aggregate column
• The stone column provides increased drainage of the soil
surrounding the columns which results in a reduction of pore
water pressure during a seismic event.
• Densification of the soil occurs around the stone column
during installation which increases the resistance to
liquefaction.
• The stone column serves as reinforcement to the treated soil
area since it is stiffer and stronger than the surrounding soil
• The stone column method increases the lateral stresses in the
soil surrounding the column.
Methods of construction
• Vibro-Replacement ( wet, Top Feed method)
• Vibro-displacement ( Dry, Top and Bottom Feed method )
• In this project, they had chosen the wet method (top feed
method). 13
14. II. DescriptionOfEntirely Project
PoolYard
• water is jetted under high pressure from the nose of the
vibroflot to assist with penetration of the probe.
- Definition
Wet Method
14
Dry Method
- Definition
• Dry method or vibro-displacement, the hole is created by
forcing the vibroflot into the ground.
Dry -top feed method process
Dry -bottom feed method process
Project specification and design requirement
Structure Working
load (Kpa)
Working platform
level (m CD)
Top of
column
(m CD)
Treatment
depth
below
T.0.C)*
Empty
run( m)
container 50 +4.05 +3.0 14 ˜ 1
15. II. DescriptionOfEntirely Project
PoolYard
Soil layer
Elevation (m) as
considered in
design
Design
qc
(Mpa)`
Modulus
of
elasticity
(Mpa)
Constrained
modulus (Mpa)
Finishing blancket +5.96 to 3.0 - - 70.0(assumed)
Fill 3.0 t0 -1.0 - - 30.0(assumed)
Silty sand -1.0 to -8.5 1.0 4.0 5.92
Clay -8.5 to -14.0 0.5 2.0 2.96
Sandy silt -14 to -17.0 3.5 14.0 20.72
Stiff sandy silt Below -17.0 6.0 24.0 35.52
The stone columns will have the following diameter and
characteristics
Stone column
Dia. Nominal(m)
Bulk density
(KN/𝒎𝟑
)
Submerged
density
(KN/𝒎𝟑
)
Angle of
friction(°)
Constrained
modulus
(MN/𝒎𝟐
)
0.8 to 0.9 21 12 47.5 120
Plaxis 2D calculation
Presentation of the software
PLAXIS 2D is a finite element package that has been developed
specifically for the analysis of deformation, stability and flow in
geotechnical engineering projects.
15
The creation of a new project
16. II. DescriptionOfEntirely Project
PoolYard
16
Settlement for 2 year with stone column in plaxis-2D
The settlements of the Plaxis-2D calculations result
• Settlement for 2 year without stone column in plaxis-2D
When the platform was not conducted with the stone
column, the total displacement is higher. In order to reduce
the displacement and the platform became suitable, we
were needed to use the stone column.
17. II. DescriptionOfEntirely Project
PoolYard
17
Pavement Structural Of Pool Yard
Construction process of heavy duty pavement pavers
blocks
• In the construction process of heavy duty paver for pool yard
was completed before me.
• The construction of an electrical trench was summered the
construction process of heavy duty pavement
Subgrade
• Subgrade is also called formation level.
Sub-base
• Sub-base layer was constructed on top of the Subgrade
• Cement bound granular mixture (CBGM)
• Bedding sand
18. II. DescriptionOfEntirelyProject
PoolYard
Installation of interlock concrete blocks pavers
• The blocks was laid
Joint Filling
Different types of defect pavement
18
Individual Pavers Separating
Pavers crack
• This occurs when filler sand is not swept in between all
the joints of paver blocks.
• damaged by a
machine during
construction time
19. II. DescriptionOfEntirely Project
PoolYard
19
Repair Method
Individual pavers separating
• Marking the rectification area
• They were opened up all rectification area
The issue was the technique to open up
• Isolate the rectification area with a squares frame by cutting
an extremity of the rectification area.
• Before and after the rectification area with close junction
• Removing by used two steel rebar pry.
Pavers crack
• The best technique to overcome this issue was removed
and replace a pavers by using manual.
20. III. DesignOfAccessRoadPavement
Whatispavement?
- Definition
In terms of highway design, it means the total
thickness of road including surface, subgrade, base
and sub-base.
Functionality
Its functionality is to transmit and distribute
traffic wheel loads to the natural ground.
Different Types Of Road Pavement
Flexible Pavements
Rigid Pavements
Heavy duty pavement
Flexible Pavements
• Component layers : subgrade, drainage layer/sub-
base, base course, binder course and surfacing course.
• It should be analyzed by plate theory instead of layer theor
• Flexible pavements will transmit wheel load stresses
to the lower layers.
• Component layers : subgrade, drainage layer, sub-base
and slab concrete.
Rigid Pavements
Heavy duty pavement( Port Pavement )
20
21. 21
HeavyDutyPavementsDesignCalculations
Traffic
𝐸𝑆𝐴𝐿 = 𝑁 × 𝑓𝑑 × 𝐹𝑖 × 𝐴𝐴𝐷𝑇 × 365 × 𝐺𝑟𝑛
Equivalent Single Axle Load
III. DesignOfAccessRoadPavement
𝐸𝑆𝐴𝐿 is an equivalent accumulated 18,000-lb axle
load for truck category i.
𝑓𝑑 is the design lane factor
𝐺𝑅𝑁 is a growth factor for a given growth rate (r) and
design period (n).
AADT is a first year annual average daily traffic for
truck.
𝐹𝑖 is a truck factor for vehicles in truck category i.
𝑁 is a number of axle for truck.
𝐺𝑟𝑛 = [
(1 + 𝑟)𝑛
− 1
𝑟
]
= 12.55. 106 𝑆𝐴
𝐸𝑆𝐴𝐿6 𝑎𝑥𝑙𝑒 𝑡𝑟𝑢𝑐𝑘
For 6 axle truck
Type of Axle or Axle Group Load equivalent to one ESAL(Kips)
Single tire single axle 12
Dual tire axle 18
Tandem axle group 32
Tridem axle group 48
4 or more axle group 48
23. III. DesignOfAccessRoadPavement
HeavyDutyPavementsDesignCalculations
Design for Pavement structural
Flexible pavement using AASHTO 1993
By using Nomo chart
For given information
R = 70% 𝑆0 = 0.45
ΔPSI = 1.7 Mr for subgrade = 130MPa
𝑀𝑟 = 40,000𝑝𝑠𝑖
𝑀𝑟 = 20,900𝑝𝑠𝑖 Drainage quality = Fair
𝑚3−1= 𝑚3−2 = 1.0 (for sub-base) Traffic loading = 16.45 MSA
- For sub-base without Geocell
23
Because of cost and to make the construction of the pavement
more effective we only want to use 30 cm of sub-base without
geocell So, that 𝑆𝑁3.1 = 3.3
- For sub-base with Geocell
24. III. DesignOfAccessRoadPavement
HeavyDutyPavementsDesignCalculations
By using Nomo chart
Because of cost and to make the construction of the pavement
more effective we only want to use 15 cm of sub-base with
geocell So, that 𝑆𝑁3−2 = 2.9
𝑆𝑁1 + 𝑆𝑁2 = 2.9 + 3.3 = 6.2 > 2.0
As the provided SN (6.2) is greater than required SN
(2.0), so the pavement layer thickness is safe for the
traffic load repetitions.
Sub-base layer (including 75mm Geocell) = 150mm
Sub-base layer without geocell = 300mm
conclusion
24
Design thickness of CBGM
Static effective wheel load is 93.5 × 2.01 = 188𝑘𝑁
Single Equivalent Wheel Load (SEWL) = 282𝑘𝑁
25. 25
III. DesignOfAccessRoadPavement
HeavyDutyPavementsDesignCalculations
The Design chart shows that 250 mm thickness of C8/10
CBGM
Final Pavement
140 mm surfacing (pavers) 4,000 MPa
200 mm C8/10 CBGM base 40,000 MPa
Sub-base without
Geocell
Sub-base with
Geocell
C8/10 CBGM
surfacing (pavers)
30
cm
15
cm
20
cm
14
cm