SlideShare a Scribd company logo
1 of 27
SGTDPoolYardExtensionProject
February 01
By
Abdirahman Houssein Hoch
Supervised by:
 AMAL MOHAMED
Internship tutor:
 Eng. HOUSSEIN KAYAD
CONTENT
I. ProjectDescription
 Locationofthe Project
 TypesofContract
II. DescriptionOfEntirelyProject
 AccessRoad
 PoolYard
III. DesignOfAccessRoadPavement
INTRODUCTION
2
Conclusion
INTRODUCTION
3
Société de Gestion du Terminal à conteneurs de Doraleh (SGTD) and their mission
 Mission during my internship is divided two main points:
 Design of an access road pavement.
 Description Of Entirely Project.
The mission of our department is to develop and follow project which complies with the client’s
objectives.
I. ProjectDescription
 Locationofthe Project
Location of the project is a Doraleh container terminal
and the project site named as Pool Yard
4
 TypesofContract
 PROJECT DELIVERY METHOD
I. ProjectDescription
 Design- Build
5
 The Traditional(design-bid-build)
II. DescriptionOfEntirely Project
 AccessRoad
 Backfilling Method
Phase-1
Phase-2
Phase-3
Phase-4
6
Phase-5
Phase-6
Phase-7
Phase- 8
II. DescriptionOfEntirely Project
 AccessRoad
 Backfilling Method
7
II. DescriptionOfEntirely Project
 AccessRoad
 Dynamic Compaction Method
- Definition
- Why we use the dynamic compaction
• Weak bearing capacity.
• Liquefaction
- Execution work of dynamic compaction
8
-Setting out of DC Prints in grid spacing,
II. DescriptionOfEntirely Project
 AccessRoad
 Post treatment testing
 Plate load test Result
 Balancing pipe
- Definition
• The main reason that we used balancing pip was stability
tides and water levels
9
II. DescriptionOfEntirely Project
 PoolYard
 Backfilling Method
Step-1
Step-2
10
II. DescriptionOfEntirely Project
 PoolYard
 Backfilling Method
Step-3
Step-4
Step-5
Step- 6
11
II. DescriptionOfEntirely Project
 PoolYard
 Backfilling Method
Step- 7
Step- 8
12
II. DescriptionOfEntirely Project
 PoolYard
 Stone Column
- Definition
- Why we use the stone column
The main reason, we use stone column is to prevent
liquefaction phenomenon.
 Liquefaction mitigation
Stone columns are thought to reduce liquefaction hazard and
improve soil performance in four main ways.
• stone columns, also called aggregate column
• The stone column provides increased drainage of the soil
surrounding the columns which results in a reduction of pore
water pressure during a seismic event.
• Densification of the soil occurs around the stone column
during installation which increases the resistance to
liquefaction.
• The stone column serves as reinforcement to the treated soil
area since it is stiffer and stronger than the surrounding soil
• The stone column method increases the lateral stresses in the
soil surrounding the column.
 Methods of construction
• Vibro-Replacement ( wet, Top Feed method)
• Vibro-displacement ( Dry, Top and Bottom Feed method )
• In this project, they had chosen the wet method (top feed
method). 13
II. DescriptionOfEntirely Project
 PoolYard
• water is jetted under high pressure from the nose of the
vibroflot to assist with penetration of the probe.
- Definition
Wet Method
14
Dry Method
- Definition
• Dry method or vibro-displacement, the hole is created by
forcing the vibroflot into the ground.
 Dry -top feed method process
 Dry -bottom feed method process
 Project specification and design requirement
Structure Working
load (Kpa)
Working platform
level (m CD)
Top of
column
(m CD)
Treatment
depth
below
T.0.C)*
Empty
run( m)
container 50 +4.05 +3.0 14 ˜ 1
II. DescriptionOfEntirely Project
 PoolYard
Soil layer
Elevation (m) as
considered in
design
Design
qc
(Mpa)`
Modulus
of
elasticity
(Mpa)
Constrained
modulus (Mpa)
Finishing blancket +5.96 to 3.0 - - 70.0(assumed)
Fill 3.0 t0 -1.0 - - 30.0(assumed)
Silty sand -1.0 to -8.5 1.0 4.0 5.92
Clay -8.5 to -14.0 0.5 2.0 2.96
Sandy silt -14 to -17.0 3.5 14.0 20.72
Stiff sandy silt Below -17.0 6.0 24.0 35.52
The stone columns will have the following diameter and
characteristics
Stone column
Dia. Nominal(m)
Bulk density
(KN/𝒎𝟑
)
Submerged
density
(KN/𝒎𝟑
)
Angle of
friction(°)
Constrained
modulus
(MN/𝒎𝟐
)
0.8 to 0.9 21 12 47.5 120
Plaxis 2D calculation
Presentation of the software
PLAXIS 2D is a finite element package that has been developed
specifically for the analysis of deformation, stability and flow in
geotechnical engineering projects.
15
The creation of a new project
II. DescriptionOfEntirely Project
 PoolYard
16
Settlement for 2 year with stone column in plaxis-2D
The settlements of the Plaxis-2D calculations result
• Settlement for 2 year without stone column in plaxis-2D
When the platform was not conducted with the stone
column, the total displacement is higher. In order to reduce
the displacement and the platform became suitable, we
were needed to use the stone column.
II. DescriptionOfEntirely Project
 PoolYard
17
 Pavement Structural Of Pool Yard
 Construction process of heavy duty pavement pavers
blocks
• In the construction process of heavy duty paver for pool yard
was completed before me.
• The construction of an electrical trench was summered the
construction process of heavy duty pavement
Subgrade
• Subgrade is also called formation level.
Sub-base
• Sub-base layer was constructed on top of the Subgrade
• Cement bound granular mixture (CBGM)
• Bedding sand
II. DescriptionOfEntirelyProject
 PoolYard
Installation of interlock concrete blocks pavers
• The blocks was laid
Joint Filling
 Different types of defect pavement
18
 Individual Pavers Separating
 Pavers crack
• This occurs when filler sand is not swept in between all
the joints of paver blocks.
• damaged by a
machine during
construction time
II. DescriptionOfEntirely Project
 PoolYard
19
 Repair Method
 Individual pavers separating
• Marking the rectification area
• They were opened up all rectification area
The issue was the technique to open up
• Isolate the rectification area with a squares frame by cutting
an extremity of the rectification area.
• Before and after the rectification area with close junction
• Removing by used two steel rebar pry.
 Pavers crack
• The best technique to overcome this issue was removed
and replace a pavers by using manual.
III. DesignOfAccessRoadPavement
 Whatispavement?
- Definition
 In terms of highway design, it means the total
thickness of road including surface, subgrade, base
and sub-base.
Functionality
 Its functionality is to transmit and distribute
traffic wheel loads to the natural ground.
 Different Types Of Road Pavement
 Flexible Pavements
 Rigid Pavements
 Heavy duty pavement
 Flexible Pavements
• Component layers : subgrade, drainage layer/sub-
base, base course, binder course and surfacing course.
• It should be analyzed by plate theory instead of layer theor
• Flexible pavements will transmit wheel load stresses
to the lower layers.
• Component layers : subgrade, drainage layer, sub-base
and slab concrete.
 Rigid Pavements
 Heavy duty pavement( Port Pavement )
20
21
 HeavyDutyPavementsDesignCalculations
 Traffic
𝐸𝑆𝐴𝐿 = 𝑁 × 𝑓𝑑 × 𝐹𝑖 × 𝐴𝐴𝐷𝑇 × 365 × 𝐺𝑟𝑛
 Equivalent Single Axle Load
III. DesignOfAccessRoadPavement
 𝐸𝑆𝐴𝐿 is an equivalent accumulated 18,000-lb axle
load for truck category i.
 𝑓𝑑 is the design lane factor
 𝐺𝑅𝑁 is a growth factor for a given growth rate (r) and
design period (n).
 AADT is a first year annual average daily traffic for
truck.
 𝐹𝑖 is a truck factor for vehicles in truck category i.
 𝑁 is a number of axle for truck.
𝐺𝑟𝑛 = [
(1 + 𝑟)𝑛
− 1
𝑟
]
= 12.55. 106 𝑆𝐴
𝐸𝑆𝐴𝐿6 𝑎𝑥𝑙𝑒 𝑡𝑟𝑢𝑐𝑘
For 6 axle truck
Type of Axle or Axle Group Load equivalent to one ESAL(Kips)
Single tire single axle 12
Dual tire axle 18
Tandem axle group 32
Tridem axle group 48
4 or more axle group 48
III. DesignOfAccessRoadPavement
22
III. DesignOfAccessRoadPavement
 HeavyDutyPavementsDesignCalculations
 Design for Pavement structural
 Flexible pavement using AASHTO 1993
By using Nomo chart
For given information
R = 70% 𝑆0 = 0.45
ΔPSI = 1.7 Mr for subgrade = 130MPa
𝑀𝑟 = 40,000𝑝𝑠𝑖
𝑀𝑟 = 20,900𝑝𝑠𝑖 Drainage quality = Fair
𝑚3−1= 𝑚3−2 = 1.0 (for sub-base) Traffic loading = 16.45 MSA
- For sub-base without Geocell
23
Because of cost and to make the construction of the pavement
more effective we only want to use 30 cm of sub-base without
geocell So, that 𝑆𝑁3.1 = 3.3
- For sub-base with Geocell
III. DesignOfAccessRoadPavement
 HeavyDutyPavementsDesignCalculations
By using Nomo chart
Because of cost and to make the construction of the pavement
more effective we only want to use 15 cm of sub-base with
geocell So, that 𝑆𝑁3−2 = 2.9
𝑆𝑁1 + 𝑆𝑁2 = 2.9 + 3.3 = 6.2 > 2.0
As the provided SN (6.2) is greater than required SN
(2.0), so the pavement layer thickness is safe for the
traffic load repetitions.
 Sub-base layer (including 75mm Geocell) = 150mm
 Sub-base layer without geocell = 300mm
conclusion
24
 Design thickness of CBGM
Static effective wheel load is 93.5 × 2.01 = 188𝑘𝑁
Single Equivalent Wheel Load (SEWL) = 282𝑘𝑁
25
III. DesignOfAccessRoadPavement
 HeavyDutyPavementsDesignCalculations
The Design chart shows that 250 mm thickness of C8/10
CBGM
Final Pavement
140 mm surfacing (pavers) 4,000 MPa
200 mm C8/10 CBGM base 40,000 MPa
Sub-base without
Geocell
Sub-base with
Geocell
C8/10 CBGM
surfacing (pavers)
30
cm
15
cm
20
cm
14
cm
26
Conclusion
27

More Related Content

Similar to Présentation master thesesis in civil department pptx

INTERLOCKING CONCRETE BLOCKS PAVEMENTS
INTERLOCKING CONCRETE BLOCKS PAVEMENTSINTERLOCKING CONCRETE BLOCKS PAVEMENTS
INTERLOCKING CONCRETE BLOCKS PAVEMENTSDileep Gowda
 
101under water conustrution.pptx
101under water conustrution.pptx101under water conustrution.pptx
101under water conustrution.pptxMEHALAS3
 
Design and analysis of flexible pavemeT
Design and analysis of flexible pavemeTDesign and analysis of flexible pavemeT
Design and analysis of flexible pavemeTDevesh Chaurasia
 
Structural Design and Rehabilitation of Reinforced Concrete Structure
Structural Design and Rehabilitation of Reinforced Concrete StructureStructural Design and Rehabilitation of Reinforced Concrete Structure
Structural Design and Rehabilitation of Reinforced Concrete StructureIJERA Editor
 
Retrofitting of Bridge with Voided Slab to raise the Deck Level
Retrofitting of Bridge with Voided Slab to raise the Deck LevelRetrofitting of Bridge with Voided Slab to raise the Deck Level
Retrofitting of Bridge with Voided Slab to raise the Deck LevelIRJET Journal
 
Construction site
Construction siteConstruction site
Construction siteTimun Loh
 
King Abdullah Road 4 12 07 Presentation
King Abdullah Road 4 12 07 PresentationKing Abdullah Road 4 12 07 Presentation
King Abdullah Road 4 12 07 Presentationguest2d44ee
 
Conen 442 module3 S2021 Pavement Design and Construction
Conen  442 module3  S2021 Pavement Design and Construction Conen  442 module3  S2021 Pavement Design and Construction
Conen 442 module3 S2021 Pavement Design and Construction Wael ElDessouki
 
Bridge & Road Construction .pptx
Bridge & Road Construction .pptxBridge & Road Construction .pptx
Bridge & Road Construction .pptxMosaddekHaqueReyad
 
Rigid pavement
Rigid pavementRigid pavement
Rigid pavementpjainrahul
 
tunnelling scope, construction techniques and necessity
tunnelling scope, construction techniques and necessitytunnelling scope, construction techniques and necessity
tunnelling scope, construction techniques and necessityShashank Gaurav
 
Ground improvement using rapid impact compaction
Ground improvement using rapid impact compactionGround improvement using rapid impact compaction
Ground improvement using rapid impact compactionBegum Emte Ajom
 
underwater-construction-55849d4caf8cd.pptx
underwater-construction-55849d4caf8cd.pptxunderwater-construction-55849d4caf8cd.pptx
underwater-construction-55849d4caf8cd.pptxJayachandran68
 
GROUP_6_YOUNGMAN_L_ANNEX_15-16
GROUP_6_YOUNGMAN_L_ANNEX_15-16GROUP_6_YOUNGMAN_L_ANNEX_15-16
GROUP_6_YOUNGMAN_L_ANNEX_15-16Leo Youngman
 
Jaipur metro rail corporation summer training report
Jaipur metro rail corporation summer training reportJaipur metro rail corporation summer training report
Jaipur metro rail corporation summer training reportRajendra Jhurawat
 
BFC 31802 Chapter 4a - Copy.ppt
BFC 31802 Chapter 4a - Copy.pptBFC 31802 Chapter 4a - Copy.ppt
BFC 31802 Chapter 4a - Copy.pptArdeeArdee
 
Developers Transflex Installation
Developers Transflex InstallationDevelopers Transflex Installation
Developers Transflex Installationguest470ea8
 

Similar to Présentation master thesesis in civil department pptx (20)

Shib
ShibShib
Shib
 
INTERLOCKING CONCRETE BLOCKS PAVEMENTS
INTERLOCKING CONCRETE BLOCKS PAVEMENTSINTERLOCKING CONCRETE BLOCKS PAVEMENTS
INTERLOCKING CONCRETE BLOCKS PAVEMENTS
 
101under water conustrution.pptx
101under water conustrution.pptx101under water conustrution.pptx
101under water conustrution.pptx
 
Design and analysis of flexible pavemeT
Design and analysis of flexible pavemeTDesign and analysis of flexible pavemeT
Design and analysis of flexible pavemeT
 
Structural Design and Rehabilitation of Reinforced Concrete Structure
Structural Design and Rehabilitation of Reinforced Concrete StructureStructural Design and Rehabilitation of Reinforced Concrete Structure
Structural Design and Rehabilitation of Reinforced Concrete Structure
 
DESIGN OF FLEXIBLE PEVEMENT
DESIGN OF FLEXIBLE PEVEMENTDESIGN OF FLEXIBLE PEVEMENT
DESIGN OF FLEXIBLE PEVEMENT
 
Retrofitting of Bridge with Voided Slab to raise the Deck Level
Retrofitting of Bridge with Voided Slab to raise the Deck LevelRetrofitting of Bridge with Voided Slab to raise the Deck Level
Retrofitting of Bridge with Voided Slab to raise the Deck Level
 
Metroppt
MetropptMetroppt
Metroppt
 
Construction site
Construction siteConstruction site
Construction site
 
King Abdullah Road 4 12 07 Presentation
King Abdullah Road 4 12 07 PresentationKing Abdullah Road 4 12 07 Presentation
King Abdullah Road 4 12 07 Presentation
 
Conen 442 module3 S2021 Pavement Design and Construction
Conen  442 module3  S2021 Pavement Design and Construction Conen  442 module3  S2021 Pavement Design and Construction
Conen 442 module3 S2021 Pavement Design and Construction
 
Bridge & Road Construction .pptx
Bridge & Road Construction .pptxBridge & Road Construction .pptx
Bridge & Road Construction .pptx
 
Rigid pavement
Rigid pavementRigid pavement
Rigid pavement
 
tunnelling scope, construction techniques and necessity
tunnelling scope, construction techniques and necessitytunnelling scope, construction techniques and necessity
tunnelling scope, construction techniques and necessity
 
Ground improvement using rapid impact compaction
Ground improvement using rapid impact compactionGround improvement using rapid impact compaction
Ground improvement using rapid impact compaction
 
underwater-construction-55849d4caf8cd.pptx
underwater-construction-55849d4caf8cd.pptxunderwater-construction-55849d4caf8cd.pptx
underwater-construction-55849d4caf8cd.pptx
 
GROUP_6_YOUNGMAN_L_ANNEX_15-16
GROUP_6_YOUNGMAN_L_ANNEX_15-16GROUP_6_YOUNGMAN_L_ANNEX_15-16
GROUP_6_YOUNGMAN_L_ANNEX_15-16
 
Jaipur metro rail corporation summer training report
Jaipur metro rail corporation summer training reportJaipur metro rail corporation summer training report
Jaipur metro rail corporation summer training report
 
BFC 31802 Chapter 4a - Copy.ppt
BFC 31802 Chapter 4a - Copy.pptBFC 31802 Chapter 4a - Copy.ppt
BFC 31802 Chapter 4a - Copy.ppt
 
Developers Transflex Installation
Developers Transflex InstallationDevelopers Transflex Installation
Developers Transflex Installation
 

Recently uploaded

CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .Satyam Kumar
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxvipinkmenon1
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 

Recently uploaded (20)

CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptx
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 

Présentation master thesesis in civil department pptx

  • 1. SGTDPoolYardExtensionProject February 01 By Abdirahman Houssein Hoch Supervised by:  AMAL MOHAMED Internship tutor:  Eng. HOUSSEIN KAYAD
  • 2. CONTENT I. ProjectDescription  Locationofthe Project  TypesofContract II. DescriptionOfEntirelyProject  AccessRoad  PoolYard III. DesignOfAccessRoadPavement INTRODUCTION 2 Conclusion
  • 3. INTRODUCTION 3 Société de Gestion du Terminal à conteneurs de Doraleh (SGTD) and their mission  Mission during my internship is divided two main points:  Design of an access road pavement.  Description Of Entirely Project. The mission of our department is to develop and follow project which complies with the client’s objectives.
  • 4. I. ProjectDescription  Locationofthe Project Location of the project is a Doraleh container terminal and the project site named as Pool Yard 4
  • 5.  TypesofContract  PROJECT DELIVERY METHOD I. ProjectDescription  Design- Build 5  The Traditional(design-bid-build)
  • 6. II. DescriptionOfEntirely Project  AccessRoad  Backfilling Method Phase-1 Phase-2 Phase-3 Phase-4 6
  • 7. Phase-5 Phase-6 Phase-7 Phase- 8 II. DescriptionOfEntirely Project  AccessRoad  Backfilling Method 7
  • 8. II. DescriptionOfEntirely Project  AccessRoad  Dynamic Compaction Method - Definition - Why we use the dynamic compaction • Weak bearing capacity. • Liquefaction - Execution work of dynamic compaction 8 -Setting out of DC Prints in grid spacing,
  • 9. II. DescriptionOfEntirely Project  AccessRoad  Post treatment testing  Plate load test Result  Balancing pipe - Definition • The main reason that we used balancing pip was stability tides and water levels 9
  • 10. II. DescriptionOfEntirely Project  PoolYard  Backfilling Method Step-1 Step-2 10
  • 11. II. DescriptionOfEntirely Project  PoolYard  Backfilling Method Step-3 Step-4 Step-5 Step- 6 11
  • 12. II. DescriptionOfEntirely Project  PoolYard  Backfilling Method Step- 7 Step- 8 12
  • 13. II. DescriptionOfEntirely Project  PoolYard  Stone Column - Definition - Why we use the stone column The main reason, we use stone column is to prevent liquefaction phenomenon.  Liquefaction mitigation Stone columns are thought to reduce liquefaction hazard and improve soil performance in four main ways. • stone columns, also called aggregate column • The stone column provides increased drainage of the soil surrounding the columns which results in a reduction of pore water pressure during a seismic event. • Densification of the soil occurs around the stone column during installation which increases the resistance to liquefaction. • The stone column serves as reinforcement to the treated soil area since it is stiffer and stronger than the surrounding soil • The stone column method increases the lateral stresses in the soil surrounding the column.  Methods of construction • Vibro-Replacement ( wet, Top Feed method) • Vibro-displacement ( Dry, Top and Bottom Feed method ) • In this project, they had chosen the wet method (top feed method). 13
  • 14. II. DescriptionOfEntirely Project  PoolYard • water is jetted under high pressure from the nose of the vibroflot to assist with penetration of the probe. - Definition Wet Method 14 Dry Method - Definition • Dry method or vibro-displacement, the hole is created by forcing the vibroflot into the ground.  Dry -top feed method process  Dry -bottom feed method process  Project specification and design requirement Structure Working load (Kpa) Working platform level (m CD) Top of column (m CD) Treatment depth below T.0.C)* Empty run( m) container 50 +4.05 +3.0 14 ˜ 1
  • 15. II. DescriptionOfEntirely Project  PoolYard Soil layer Elevation (m) as considered in design Design qc (Mpa)` Modulus of elasticity (Mpa) Constrained modulus (Mpa) Finishing blancket +5.96 to 3.0 - - 70.0(assumed) Fill 3.0 t0 -1.0 - - 30.0(assumed) Silty sand -1.0 to -8.5 1.0 4.0 5.92 Clay -8.5 to -14.0 0.5 2.0 2.96 Sandy silt -14 to -17.0 3.5 14.0 20.72 Stiff sandy silt Below -17.0 6.0 24.0 35.52 The stone columns will have the following diameter and characteristics Stone column Dia. Nominal(m) Bulk density (KN/𝒎𝟑 ) Submerged density (KN/𝒎𝟑 ) Angle of friction(°) Constrained modulus (MN/𝒎𝟐 ) 0.8 to 0.9 21 12 47.5 120 Plaxis 2D calculation Presentation of the software PLAXIS 2D is a finite element package that has been developed specifically for the analysis of deformation, stability and flow in geotechnical engineering projects. 15 The creation of a new project
  • 16. II. DescriptionOfEntirely Project  PoolYard 16 Settlement for 2 year with stone column in plaxis-2D The settlements of the Plaxis-2D calculations result • Settlement for 2 year without stone column in plaxis-2D When the platform was not conducted with the stone column, the total displacement is higher. In order to reduce the displacement and the platform became suitable, we were needed to use the stone column.
  • 17. II. DescriptionOfEntirely Project  PoolYard 17  Pavement Structural Of Pool Yard  Construction process of heavy duty pavement pavers blocks • In the construction process of heavy duty paver for pool yard was completed before me. • The construction of an electrical trench was summered the construction process of heavy duty pavement Subgrade • Subgrade is also called formation level. Sub-base • Sub-base layer was constructed on top of the Subgrade • Cement bound granular mixture (CBGM) • Bedding sand
  • 18. II. DescriptionOfEntirelyProject  PoolYard Installation of interlock concrete blocks pavers • The blocks was laid Joint Filling  Different types of defect pavement 18  Individual Pavers Separating  Pavers crack • This occurs when filler sand is not swept in between all the joints of paver blocks. • damaged by a machine during construction time
  • 19. II. DescriptionOfEntirely Project  PoolYard 19  Repair Method  Individual pavers separating • Marking the rectification area • They were opened up all rectification area The issue was the technique to open up • Isolate the rectification area with a squares frame by cutting an extremity of the rectification area. • Before and after the rectification area with close junction • Removing by used two steel rebar pry.  Pavers crack • The best technique to overcome this issue was removed and replace a pavers by using manual.
  • 20. III. DesignOfAccessRoadPavement  Whatispavement? - Definition  In terms of highway design, it means the total thickness of road including surface, subgrade, base and sub-base. Functionality  Its functionality is to transmit and distribute traffic wheel loads to the natural ground.  Different Types Of Road Pavement  Flexible Pavements  Rigid Pavements  Heavy duty pavement  Flexible Pavements • Component layers : subgrade, drainage layer/sub- base, base course, binder course and surfacing course. • It should be analyzed by plate theory instead of layer theor • Flexible pavements will transmit wheel load stresses to the lower layers. • Component layers : subgrade, drainage layer, sub-base and slab concrete.  Rigid Pavements  Heavy duty pavement( Port Pavement ) 20
  • 21. 21  HeavyDutyPavementsDesignCalculations  Traffic 𝐸𝑆𝐴𝐿 = 𝑁 × 𝑓𝑑 × 𝐹𝑖 × 𝐴𝐴𝐷𝑇 × 365 × 𝐺𝑟𝑛  Equivalent Single Axle Load III. DesignOfAccessRoadPavement  𝐸𝑆𝐴𝐿 is an equivalent accumulated 18,000-lb axle load for truck category i.  𝑓𝑑 is the design lane factor  𝐺𝑅𝑁 is a growth factor for a given growth rate (r) and design period (n).  AADT is a first year annual average daily traffic for truck.  𝐹𝑖 is a truck factor for vehicles in truck category i.  𝑁 is a number of axle for truck. 𝐺𝑟𝑛 = [ (1 + 𝑟)𝑛 − 1 𝑟 ] = 12.55. 106 𝑆𝐴 𝐸𝑆𝐴𝐿6 𝑎𝑥𝑙𝑒 𝑡𝑟𝑢𝑐𝑘 For 6 axle truck Type of Axle or Axle Group Load equivalent to one ESAL(Kips) Single tire single axle 12 Dual tire axle 18 Tandem axle group 32 Tridem axle group 48 4 or more axle group 48
  • 23. III. DesignOfAccessRoadPavement  HeavyDutyPavementsDesignCalculations  Design for Pavement structural  Flexible pavement using AASHTO 1993 By using Nomo chart For given information R = 70% 𝑆0 = 0.45 ΔPSI = 1.7 Mr for subgrade = 130MPa 𝑀𝑟 = 40,000𝑝𝑠𝑖 𝑀𝑟 = 20,900𝑝𝑠𝑖 Drainage quality = Fair 𝑚3−1= 𝑚3−2 = 1.0 (for sub-base) Traffic loading = 16.45 MSA - For sub-base without Geocell 23 Because of cost and to make the construction of the pavement more effective we only want to use 30 cm of sub-base without geocell So, that 𝑆𝑁3.1 = 3.3 - For sub-base with Geocell
  • 24. III. DesignOfAccessRoadPavement  HeavyDutyPavementsDesignCalculations By using Nomo chart Because of cost and to make the construction of the pavement more effective we only want to use 15 cm of sub-base with geocell So, that 𝑆𝑁3−2 = 2.9 𝑆𝑁1 + 𝑆𝑁2 = 2.9 + 3.3 = 6.2 > 2.0 As the provided SN (6.2) is greater than required SN (2.0), so the pavement layer thickness is safe for the traffic load repetitions.  Sub-base layer (including 75mm Geocell) = 150mm  Sub-base layer without geocell = 300mm conclusion 24  Design thickness of CBGM Static effective wheel load is 93.5 × 2.01 = 188𝑘𝑁 Single Equivalent Wheel Load (SEWL) = 282𝑘𝑁
  • 25. 25 III. DesignOfAccessRoadPavement  HeavyDutyPavementsDesignCalculations The Design chart shows that 250 mm thickness of C8/10 CBGM Final Pavement 140 mm surfacing (pavers) 4,000 MPa 200 mm C8/10 CBGM base 40,000 MPa Sub-base without Geocell Sub-base with Geocell C8/10 CBGM surfacing (pavers) 30 cm 15 cm 20 cm 14 cm
  • 27. 27