This document discusses methods for calculating quantum, or monetary amounts owed, in construction disputes. It examines valuation rules in standard construction contracts like the Public Works Contract, FIDIC Red Book, and RIAI contract. These contracts generally use rates in the contract documents as the basis for valuation and allow for recovery of costs, expenses, losses, and overheads. The document also discusses key concepts like similar work, reasonable rates, fair valuation based on costs plus profit, and direct vs indirect losses. Calculating quantum should follow contractual mechanisms and consider all relevant circumstances.
NEC4 overview: key changes and impacts - London, September 2017Browne Jacobson LLP
This seminar looked at the changes to the NEC structrure, changes in approach following the change to the structure, and the introduction of two new contracts to the suite.
NEC4: The good, the bad, and the ugly
Part 1: Contract strategy changes webinar
Tuesday 14 November 2017
APM Contracts and Procurement Specific Interest Group (SIG)
presented by Dr Jon Broome
hosted by John Lake
APM Contracts and Procurement SIG previous Chair and Chair respectively
Pankaj participated as faculty in Construction Risk Lifecycle Management Conference (17th & 18th April 2011 AT Abu Dhabi, UAE) organised by Marcus Evans. He gave his presentation on ‘Managing the Complexity of Change Order and Claims in Major Projects by establishing a Change Management Framework’.
Do you find yourself unable to agree contract terms because of their complexity?
Are you paralysed by indecision over which elements are important?
Do you find yourself avoiding the pain of paperwork by not signing or reviewing contracts?
Do you want a quick way of sorting out if your construction contract is good to go or may cause problems later in the project?
This checklist is designed for use during the tender stage to determine whether to continue.
The checklist was developed by Sarah Fox, author of the 500-Word Contract for construction projects. If you want to know how to use 4 key elements to evaluate contracts before they are signed then 500 Words Ltd runs a 90-minute introductory workshop to help you spot the disasters waiting to happen.
For information on how we can give you the confidence to use contracts for project success, email sarah@500words.co.uk or visit www.500words.co.uk
NEC4 overview: key changes and impacts - London, September 2017Browne Jacobson LLP
This seminar looked at the changes to the NEC structrure, changes in approach following the change to the structure, and the introduction of two new contracts to the suite.
NEC4: The good, the bad, and the ugly
Part 1: Contract strategy changes webinar
Tuesday 14 November 2017
APM Contracts and Procurement Specific Interest Group (SIG)
presented by Dr Jon Broome
hosted by John Lake
APM Contracts and Procurement SIG previous Chair and Chair respectively
Pankaj participated as faculty in Construction Risk Lifecycle Management Conference (17th & 18th April 2011 AT Abu Dhabi, UAE) organised by Marcus Evans. He gave his presentation on ‘Managing the Complexity of Change Order and Claims in Major Projects by establishing a Change Management Framework’.
Do you find yourself unable to agree contract terms because of their complexity?
Are you paralysed by indecision over which elements are important?
Do you find yourself avoiding the pain of paperwork by not signing or reviewing contracts?
Do you want a quick way of sorting out if your construction contract is good to go or may cause problems later in the project?
This checklist is designed for use during the tender stage to determine whether to continue.
The checklist was developed by Sarah Fox, author of the 500-Word Contract for construction projects. If you want to know how to use 4 key elements to evaluate contracts before they are signed then 500 Words Ltd runs a 90-minute introductory workshop to help you spot the disasters waiting to happen.
For information on how we can give you the confidence to use contracts for project success, email sarah@500words.co.uk or visit www.500words.co.uk
Contract management is the process of managing
contract creation
execution and
analysis to maximize operational and financial performance at an organization, all while reducing financial risk.
Clause 14.9 Payment of Retention Money-Understanding Clauses in FIDIC ‘Condit...Divyanshu Dayal
•Retention money is held as a percentage of interim payments.
•Retention money is returned in parts after issue of taking over certificate and after expiry of defects notification period.
•In lieu of retention as percentage of interim payments, the contractor can issue a retention guarantee as agreed by the parties.
APM webinar sponsored by the Thames Valley Branch on 29 September 2021.
Speaker:
Richard Patterson, NEC4 drafter and Procurement & NEC Specialist at Mott MacDonald
NEC has clear mechanism for risk allocation for specific events. Is it a compensation event, or not? And it has a clear, detailed and flexible process for managing and agreeing the assessment of those compensation events. Effective management of the process is key to dispute avoidance under NEC. This webinar was held on 29 September 2021.
Hear about the importance of the F word - forecast. Change control is critical to the finances of any supplier - so you need to know how to use the process.
https://youtu.be/QOrw_KqUZiE
Tips for effective administration of a construction contract and for reducing the risk of delay and change orders. Interplay between the contractors, the consultant and an owner.
Overview to Contract Mangement includes the understanding of contract and contract management, it's issues, resources required, contingency plans and detailed analysis at planning stage.
An Introduction to Civil Engineering Cost ManagementMark Wearen
An Introduction to Civil Engineering Cost Management - aimed at Quantity Surveyors and Commercial Managers interested in learning about civil engineering cost management with a particular focus on risk management and mitigation
Contract management is the process of managing
contract creation
execution and
analysis to maximize operational and financial performance at an organization, all while reducing financial risk.
Clause 14.9 Payment of Retention Money-Understanding Clauses in FIDIC ‘Condit...Divyanshu Dayal
•Retention money is held as a percentage of interim payments.
•Retention money is returned in parts after issue of taking over certificate and after expiry of defects notification period.
•In lieu of retention as percentage of interim payments, the contractor can issue a retention guarantee as agreed by the parties.
APM webinar sponsored by the Thames Valley Branch on 29 September 2021.
Speaker:
Richard Patterson, NEC4 drafter and Procurement & NEC Specialist at Mott MacDonald
NEC has clear mechanism for risk allocation for specific events. Is it a compensation event, or not? And it has a clear, detailed and flexible process for managing and agreeing the assessment of those compensation events. Effective management of the process is key to dispute avoidance under NEC. This webinar was held on 29 September 2021.
Hear about the importance of the F word - forecast. Change control is critical to the finances of any supplier - so you need to know how to use the process.
https://youtu.be/QOrw_KqUZiE
Tips for effective administration of a construction contract and for reducing the risk of delay and change orders. Interplay between the contractors, the consultant and an owner.
Overview to Contract Mangement includes the understanding of contract and contract management, it's issues, resources required, contingency plans and detailed analysis at planning stage.
An Introduction to Civil Engineering Cost ManagementMark Wearen
An Introduction to Civil Engineering Cost Management - aimed at Quantity Surveyors and Commercial Managers interested in learning about civil engineering cost management with a particular focus on risk management and mitigation
The Edugate federation has been in operation in Ireland for two years. As your nearest neighbouring federation, we have looked on with envy as the gardens of the UK federation matured, but we have been busy growing on our side of the fence too and we will present some of the tools that can be borrowed from our shed and show our finest exhibits that are ready for cross-pollination.
InterTech is a leading Russian civil engineering companyMaxim Gavrik
InterTech is a leading Russian civil engineering company, which provides a full range of services for design, construction, installation, commissioning and start-up of the MEP systems in the buildings and structures under industrial, commercial and civil construction.
Civil engineering in Russia 2017 – InterTech presentationMaxim Gavrik
Civil engineering in Russia 2017 – InterTech presentation. Our company provides a full range of services for design, construction, installation, commissioning and start-up of the MEP systems in the buildings and structures under industrial, commercial and civil construction.
InterTech is a Saint Petersburg based civil engineering companyMaxim Gavrik
InterTech is a Saint Petersburg based civil engineering company, which provides a full range of services for design, construction, installation, commissioning and start-up of the MEP systems in the buildings and structures under industrial, commercial and civil construction.
Invest in Russian construction industry - our company looking for investorsMaxim Gavrik
Invest in Russian construction industry - construction company «Intertech» offer you different investment projects: construction of the hotel on the first line of the Black sea; construction of a residential complex; cottage village. Take a look at our presentation to learn more.
TEEM'16 - Track 2 Engineering and technological learning in educational and professional contexts
Authors: Francisco Cambronero; Jesús Mínguez; Roberto Serrano
https://youtu.be/CJOcYTzlOy0
InterTech is one of the top construction companies in Qatar civil engineeringMaxim Gavrik
InterTech is one of the top construction companies in Qatar civil engineering, which provides a full range of services for design, construction, installation, commissioning and start-up of the MEP systems in the buildings and structures under industrial, commercial and civil construction.
InterTech is a St Petersburg architecture and civil engineering companyMaxim Gavrik
InterTech is a St Petersburg architecture and civil engineering company, which provides a full range of services for design, construction, installation, commissioning and start-up of the MEP systems in the buildings and structures under industrial, commercial and civil construction.
Government Contracts 101 - Understanding the Basics of Contract Types Unanet
This is the slide deck from a recent Unanet webinar. We looked at the three main types of government contracts and the new hybrids that have cropped up in recent years. Whether you are new to Government Contracting, or are a long-term GovCon, there will be a little something for contractors of all shapes and sizes and all levels of experience.
Learn more at: https://www.unanet.com/news/demand-webinars
Planning and development club providing a construction law update, an overview of the housing white paper and advice on wayleaves, easements and substation transfers.
Training Slides of Public Meeting - Contract Close-Out - Ground Rules.
For further information regarding the course, please contact:
info@asia-masters.com
www.asia-masters.com
Baker Tilly Presents: New to Cost Reimbursement Contracts? Meet Your New Frie...BakerTillyConsulting
Presented at NCMA's World Congress 2016
Presenters: Baker Tilly's Brent Calhoon, CPA, Partner and Jennifer Flickinger, Partner
The world of cost reimbursement contracts has many exciting twists and turns. Contractors have to be ready to tackle the roller-coaster ride that comes with these complex contracts. This session provides an overview of some of the strict regulatory requirements that come into play as contract value and risk increase. The presenters will touch on the business system criteria, annual cost reporting requirements, the Cost Accounting Standards, and more. www.bakertilly.com/governmentcontractors
Please join Unanet's Kim Koster, and BDO's Senior Associate, Tetiana Gervis, CPA , for an informative session to help in understanding your upcoming Incurred Cost Submission (ICS). The webinar will provide Government Contractors with an introduction to Incurred Cost Submissions, overview of preparation techniques and best practices, and common mistakes which could lead to scrutiny from the DCAA. Additionally, we will provide an update on the most recent DCAA audit trends.
You will learn about:
• Current ICS audit landscape
• General overview of the requirements of an ICS
• ICS schedules explanations
• ICS timeline and submission
• Common mistakes when preparing the submission and how these mistakes could lead to inadequacies and/or inquiries from the DCAA
If you would like to join Unanet for an upcoming webinar, please visit us at; https://www.unanet.com/webinars
This ppt is a comprehensive presentation on various aspects for the entities working in the construction domain. Starting from Tendering to Budgeting and going on to indirect tax aspects like VAT and service Tax.
Similar to SCSI / RICS Presentation on Construction Quantum - Part 1 (20)
HEAP SORT ILLUSTRATED WITH HEAPIFY, BUILD HEAP FOR DYNAMIC ARRAYS.
Heap sort is a comparison-based sorting technique based on Binary Heap data structure. It is similar to the selection sort where we first find the minimum element and place the minimum element at the beginning. Repeat the same process for the remaining elements.
Hierarchical Digital Twin of a Naval Power SystemKerry Sado
A hierarchical digital twin of a Naval DC power system has been developed and experimentally verified. Similar to other state-of-the-art digital twins, this technology creates a digital replica of the physical system executed in real-time or faster, which can modify hardware controls. However, its advantage stems from distributing computational efforts by utilizing a hierarchical structure composed of lower-level digital twin blocks and a higher-level system digital twin. Each digital twin block is associated with a physical subsystem of the hardware and communicates with a singular system digital twin, which creates a system-level response. By extracting information from each level of the hierarchy, power system controls of the hardware were reconfigured autonomously. This hierarchical digital twin development offers several advantages over other digital twins, particularly in the field of naval power systems. The hierarchical structure allows for greater computational efficiency and scalability while the ability to autonomously reconfigure hardware controls offers increased flexibility and responsiveness. The hierarchical decomposition and models utilized were well aligned with the physical twin, as indicated by the maximum deviations between the developed digital twin hierarchy and the hardware.
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)MdTanvirMahtab2
This presentation is about the working procedure of Shahjalal Fertilizer Company Limited (SFCL). A Govt. owned Company of Bangladesh Chemical Industries Corporation under Ministry of Industries.
Using recycled concrete aggregates (RCA) for pavements is crucial to achieving sustainability. Implementing RCA for new pavement can minimize carbon footprint, conserve natural resources, reduce harmful emissions, and lower life cycle costs. Compared to natural aggregate (NA), RCA pavement has fewer comprehensive studies and sustainability assessments.
6th International Conference on Machine Learning & Applications (CMLA 2024)ClaraZara1
6th International Conference on Machine Learning & Applications (CMLA 2024) will provide an excellent international forum for sharing knowledge and results in theory, methodology and applications of on Machine Learning & Applications.
Welcome to WIPAC Monthly the magazine brought to you by the LinkedIn Group Water Industry Process Automation & Control.
In this month's edition, along with this month's industry news to celebrate the 13 years since the group was created we have articles including
A case study of the used of Advanced Process Control at the Wastewater Treatment works at Lleida in Spain
A look back on an article on smart wastewater networks in order to see how the industry has measured up in the interim around the adoption of Digital Transformation in the Water Industry.
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...Amil Baba Dawood bangali
Contact with Dawood Bhai Just call on +92322-6382012 and we'll help you. We'll solve all your problems within 12 to 24 hours and with 101% guarantee and with astrology systematic. If you want to take any personal or professional advice then also you can call us on +92322-6382012 , ONLINE LOVE PROBLEM & Other all types of Daily Life Problem's.Then CALL or WHATSAPP us on +92322-6382012 and Get all these problems solutions here by Amil Baba DAWOOD BANGALI
#vashikaranspecialist #astrologer #palmistry #amliyaat #taweez #manpasandshadi #horoscope #spiritual #lovelife #lovespell #marriagespell#aamilbabainpakistan #amilbabainkarachi #powerfullblackmagicspell #kalajadumantarspecialist #realamilbaba #AmilbabainPakistan #astrologerincanada #astrologerindubai #lovespellsmaster #kalajaduspecialist #lovespellsthatwork #aamilbabainlahore#blackmagicformarriage #aamilbaba #kalajadu #kalailam #taweez #wazifaexpert #jadumantar #vashikaranspecialist #astrologer #palmistry #amliyaat #taweez #manpasandshadi #horoscope #spiritual #lovelife #lovespell #marriagespell#aamilbabainpakistan #amilbabainkarachi #powerfullblackmagicspell #kalajadumantarspecialist #realamilbaba #AmilbabainPakistan #astrologerincanada #astrologerindubai #lovespellsmaster #kalajaduspecialist #lovespellsthatwork #aamilbabainlahore #blackmagicforlove #blackmagicformarriage #aamilbaba #kalajadu #kalailam #taweez #wazifaexpert #jadumantar #vashikaranspecialist #astrologer #palmistry #amliyaat #taweez #manpasandshadi #horoscope #spiritual #lovelife #lovespell #marriagespell#aamilbabainpakistan #amilbabainkarachi #powerfullblackmagicspell #kalajadumantarspecialist #realamilbaba #AmilbabainPakistan #astrologerincanada #astrologerindubai #lovespellsmaster #kalajaduspecialist #lovespellsthatwork #aamilbabainlahore #Amilbabainuk #amilbabainspain #amilbabaindubai #Amilbabainnorway #amilbabainkrachi #amilbabainlahore #amilbabaingujranwalan #amilbabainislamabad
About
Indigenized remote control interface card suitable for MAFI system CCR equipment. Compatible for IDM8000 CCR. Backplane mounted serial and TCP/Ethernet communication module for CCR remote access. IDM 8000 CCR remote control on serial and TCP protocol.
• Remote control: Parallel or serial interface.
• Compatible with MAFI CCR system.
• Compatible with IDM8000 CCR.
• Compatible with Backplane mount serial communication.
• Compatible with commercial and Defence aviation CCR system.
• Remote control system for accessing CCR and allied system over serial or TCP.
• Indigenized local Support/presence in India.
• Easy in configuration using DIP switches.
Technical Specifications
Indigenized remote control interface card suitable for MAFI system CCR equipment. Compatible for IDM8000 CCR. Backplane mounted serial and TCP/Ethernet communication module for CCR remote access. IDM 8000 CCR remote control on serial and TCP protocol.
Key Features
Indigenized remote control interface card suitable for MAFI system CCR equipment. Compatible for IDM8000 CCR. Backplane mounted serial and TCP/Ethernet communication module for CCR remote access. IDM 8000 CCR remote control on serial and TCP protocol.
• Remote control: Parallel or serial interface
• Compatible with MAFI CCR system
• Copatiable with IDM8000 CCR
• Compatible with Backplane mount serial communication.
• Compatible with commercial and Defence aviation CCR system.
• Remote control system for accessing CCR and allied system over serial or TCP.
• Indigenized local Support/presence in India.
Application
• Remote control: Parallel or serial interface.
• Compatible with MAFI CCR system.
• Compatible with IDM8000 CCR.
• Compatible with Backplane mount serial communication.
• Compatible with commercial and Defence aviation CCR system.
• Remote control system for accessing CCR and allied system over serial or TCP.
• Indigenized local Support/presence in India.
• Easy in configuration using DIP switches.
SCSI / RICS Presentation on Construction Quantum - Part 1
1. Assessing Quantum in Construction Disputes
Contractual Mechanisms and the Courts – Part 1
Mark Wearen
MSCSI MRICS MCInstCES MSc
October 2015
April 2015
2. April 2015
Assessing Quantum in Construction Disputes
Contractual Mechanisms and the Courts
What is Quantum ?
Context of legal definitions – when do we concern ourselves with
such matters ?
Contract Forms for Traditional Contracting – PWC/FIDIC/RIAI
Key Issues
3. April 2015
Assessing Quantum in Construction Disputes
Contractual Mechanisms and the Courts
Definition of Quantum
‘a required or allowed amount, especially an amount of money legally
payable in damages’*
*Oxford Dictionary
4. April 2015
Assessing Quantum in Construction Disputes
Contractual Mechanisms and the Courts
Definition of Quantum – Construction Context
‘The amount of money sought in respect of any matter which it is alleged gives
rise to an entitlement to a payment (for whatever reason) which is additional to
the initial contract sum or to the contract sum derived from the rates and prices
in the contract’
i.e. not payment for work included in the contract in accordance with the
corresponding rates and prices included in the contract.
5. April 2015
Assessing Quantum in Construction Disputes
Contractual Mechanisms and the Courts
Calculating Quantum – Construction Context
• Construction and change go hand in hand – hence the need to include express
provisions dealing with change and it’s impacts
• Standard forms recognise this and include express provisions to permit change under
the contract and to manage that change within the contractual framework – these
provisions allocate risk and should simplify dispute resolution
• Calculating Quantum should not be a random process – can be governed by the
provisions of the Contract and/or applicable Law -not just the applicable Law
6. April 2015
Assessing Quantum in Construction Disputes
Contractual Mechanisms and the Courts
Calculating Quantum – Construction Context
• Express Provisions typically address how change (e.g. additional work or breaches of
contract) is to be valued – risk mitigation
• Bespoke forms generally mimic the standard forms with risk transfer tailored to suit the
bargaining position of the parties and their appetite for risk
• Limitations on valuing change can be expressly stated – risk mitigation
• How do we ascertain the required or allowed amount ?
7. April 2015
Assessing Quantum in Construction Disputes
Contractual Mechanisms and the Courts
Quantum – Items to Consider
Next Instalment….Part 2
• Damages
• Interest and Finance Charges
• Acceleration
• Quantum Meruit
• Causation
• Duty to Mitigate
• Irish Case Law
Today…Part 1
• Valuation Rules
• ‘Similar’ – Character and Conditions
• BOQ rates as a basis
• ‘Reasonable’
• Cost
• Fair Valuation
• Loss and/or Expense
• Overheads and Profit
• Substantiation
• Limitations Clauses
8. April 2015
Assessing Quantum in Construction Disputes
Contractual Mechanisms and the Courts
Public Works Contract* - Valuation Rules
* Public Works Contract for Building Works Designed by the Employer Document Reference PW-CF1 v.1.10 27 June 2014
9. April 2015
Assessing Quantum in Construction Disputes
Contractual Mechanisms and the Courts
Public Works Contract – Valuation Rules
10.6.1 Similar work under similar circumstances - use the rates in the pricing document
10.6.2 Not similar work and not under similar circumstances – use the rates in the pricing
document as the basis where reasonable
If the above rules do not apply…..then
10.6.3 Fair Valuation – to be based on rates for similar work in the locality, If available
Or the ER may ‘conclusively direct’ that
10.6.4 Valuation is based on Schedule 2D rates and provisions
Time and Materials/Dayworks
10. April 2015
Assessing Quantum in Construction Disputes
Contractual Mechanisms and the Courts
Public Works Contract – Other Valuation Provisions
10.3.4 Contractor to keep records of ‘costs’ associated with claims
10.7.1 (2) Delay Costs – defined as ‘expenses [excluding profit and loss of profit]’
10.7.4 Limits recovery for Delay, Disruption, Acceleration, Loss of Productivity, Knock
On Effects
Claimant must also inter alia….
10.3.1 (1) Set out ‘relevant facts’
10.3.1 (2) Provide a proposal ‘so far as is practicable’ and
10.3.3 (3) If ongoing, provide other information the ER ‘reasonably requires’
11. April 2015
Assessing Quantum in Construction Disputes
Contractual Mechanisms and the Courts
FIDIC Red Book 1999* Clause 12.3 – Valuation Rules
* FIDIC Conditions of Contract for Construction for Building and Engineering Works designed by the Contractor 1999
a) For each item of work, the appropriate rate or price specified in the contract shall
apply
b) If there is no such item in the contract, the rate or price specified in the contract
for ‘similar’ work executed under similar conditions shall apply failing which…
c) A new rate or price shall apply which shall be ‘derived from any relevant rates or
prices in the contract, with reasonable adjustments and…
d) If no rates or prices are relevant, new rates and prices shall be based on the
reasonable cost of executing the work, together with reasonable profit
Clause 13.6 - dayworks ‘for work of a minor or incidental basis’
12. April 2015
Assessing Quantum in Construction Disputes
Contractual Mechanisms and the Courts
FIDIC Red Book 1999 - Other Valuation Provisions
3.5 In the event that the parties fail to reach agreement on ‘any matter’, the
Engineer shall make a ‘fair determination in accordance with the Contract,
taking due regard of all relevant circumstances’
20.1 Contractor to maintain records ‘as may be necessary to substantiate any claim’
and must submit ‘a fully detailed claim which includes full supporting
particulars’
• Numerous provisions for recovery of ‘cost’ (e.g. 4.12)
• Numerous provisions for ‘cost plus reasonable profit’ (e.g. 4.7)
13. April 2015
Assessing Quantum in Construction Disputes
Contractual Mechanisms and the Courts
RIAI Contract* – Clause 13 Valuation Rules
Valuation rules to apply when valuing variations :
a) Bill rates if the additional work is similar in character and carried out under similar
conditions,
b) Bill rates shall form the basis of the valuation where work is not carried out under
similar conditions, ‘so far as may be reasonable’
c) Where no appropriate Bill Rates exist, a ‘Fair Valuation’ shall be made based upon
current rates for ‘similar work in the locality’.
d) daywork as tendered or SCS/CIF agreement
* RIAI Agreement and Schedule of Conditions of Building Contract 2002 (Rev 1 Print 4)
14. April 2015
Assessing Quantum in Construction Disputes
Contractual Mechanisms and the Courts
RIAI Contract – Other Valuation Provisions
Clause 2 Loss and Expense
‘beyond that provided for or reasonably contemplated by
this contract’ – limitation
(Balfour Beatty v Scottish Power 1994)
15. April 2015
Assessing Quantum in Construction Disputes
Contractual Mechanisms and the Courts
Valuing Change – Consistency in the Approach across Forms
a) Valuation Rules generally apply for valuing variations/compensation events
b) Contract Rates and Prices to be utilised – similar works under similar conditions
c) Contract Rates form the basis – where reasonable
d) Fair Valuation variants – reasonable cost and/or market rates
e) Actual Resources utilising defined rates and mark-ups
Contracts also allow for recovery of:
• Cost
• Expense
• Loss and Expense
16. April 2015
Assessing Quantum in Construction Disputes
Contractual Mechanisms and the Courts
Why use the Rules ?
• Parties must first look to the Contract to value additional work - If the work meets
the definition of a variation or compensation event, the Valuation Rules apply (MT
Hojgaard v E.ON 2013)
• The rates and prices in the contract are the starting point for valuing additional
work – ‘sacrosanct’ (Henry Boot v Alstom 2000; Maeda Corp v Hong Kong 2012)
• To move away from the contract rates, establish that work is not similar or is not
executed under similar conditions, or is outside the scope of the contract (Costain v
Zanen 1996) - thus the application of contract rates would be unreasonable as a
basis or in their entirety
• Risk Transfer – within the scope of the contract
17. April 2015
Assessing Quantum in Construction Disputes
Contractual Mechanisms and the Courts
Bill Rates as a Basis (Henry Boot v Alstom 2000 & Maeda Corp v Hong Kong 2011)
• Rates are sacrosanct
• Only insofar as they apply to similar works executed under similar circumstances
• Rates can be opened up and relevant elements changed to produce a new rate based on
the contract rates – a ‘star rate’
• Fair Valuation for relevant elements of a contract rate
• Not an opportunity to right any wrongs/correct any errors
18. April 2015
Assessing Quantum in Construction Disputes
Contractual Mechanisms and the Courts
Similar Character and Similar Conditions
• The Contract is ‘the means of which the intention of the parties was expressed’. The
‘factual matrix’ within which consideration as to whether or not work was similar or
undertaken under similar conditions must be based on the contract (Wates v Bredero
Fleet 1993)
• Thus the Contractor cannot rely upon information known to him when pricing the project
but which is not incorporated into the contract (e.g. the information pack under the Public
Works Contract and Clause 1.9.1 – the entire agreement clause)
• An ‘ambiguity or peculiarity’ in the wording of the contract may render extrinsic
information admissible but only where known to both parties
19. April 2015
Assessing Quantum in Construction Disputes
Contractual Mechanisms and the Courts
Reasonable and Reasonableness – What is ‘Reasonable’ ?
Chitty 31st Edn. 37-101 :
‘a question requiring consideration of all the factors in a particular case’ but ‘no rigid rules
apply’ …… ‘cost plus a percentage for profit’ often equates to ’reasonable remuneration’
Keating 9th Edn. 4-001 :
Is the reasonable remuneration to be calculated ‘within a contractual framework’ ?
Keating 9th Edn. 20-183 :
‘In considering what is reasonable, the Court would have regard to all the circumstances
including the terms of the Contract’ – in the context of issuing instructions – why not when
calculating quantum ?
20. April 2015
Assessing Quantum in Construction Disputes
Contractual Mechanisms and the Courts
Reasonable and Reasonableness – What is ‘Reasonable’ ?
• Contract conditions should be construed so as to give them the meaning that ‘a
reasonable person, having all the background knowledge which would have been
available to the parties would have understood them to be using the language in the
contract to mean’ (Chartbrook v Persimmon 2009)
• What factors determine reasonableness ?
• Consideration of relevant information
• Within a contractual framework
• Opinion is that of a ‘reasonable person’ suitably informed – legal standard
• Offer Value for Money and address Obligation to Mitigate
• If you want to be ‘unreasonable’, utilise express terms
21. April 2015
Assessing Quantum in Construction Disputes
Contractual Mechanisms and the Courts
Cost
‘an amount that has to be paid or spent to buy or obtain something’*
• Cost under the contract is not an estimate; a quotation; an allowance; an on account
sum…..or an amount based on contract rates unless expressly described as such in the
contract (selling price)
• FIDIC 1.1.4.3 defines cost as ‘expenditure reasonably incurred’ and goes on to state that it
includes ‘overheads and similar charges, but does not include profit’ (off site costs included)
*Oxford Dictionary
22. April 2015
Assessing Quantum in Construction Disputes
Contractual Mechanisms and the Courts
Fair Valuation
• Where bill rates don’t apply, or it would be unreasonable to use them as a
basis for a valuation, a Fair Valuation shall be made…..result is new rates and
prices
What is a Fair Valuation ?
• A fair valuation will ‘ordinarily be based on the reasonable costs of carrying out
the work, if reasonably and properly incurred’…thus there is no entitlement to
payment for expenditure which ‘would not have been incurred by a reasonably
competent Contractor in the same or similar circumstances’ (Weldon Plant v
Commissioner for New Towns 2000)
23. April 2015
Assessing Quantum in Construction Disputes
Contractual Mechanisms and the Courts
Fair Valuation
• For a valuation to be ‘fair’, it must contain all the elements ‘ordinarily found in
contract rate or price’ – labour/plant/materials/overheads/profit (Weldon Plant v
Commissioner for New Towns 2000)
• Profit is an integral element of the rates and prices included in the contract and a fair
rate would include profit (Semco Salvage v Lancer 1997)
• Clause 12.3 of FIDIC – a ‘new rate or price’….based on the ‘reasonable Cost of
executing the work, together with reasonable profit, taking account of any other
relevant matter’.
24. April 2015
Assessing Quantum in Construction Disputes
Contractual Mechanisms and the Courts
Fair Valuation
• Elements usually found in a contract rate
• Can be cost based however….Cost must be reasonable costs – reasonably and properly incurred
• PWC – ‘rates for similar work in the locality, if available’
• RIAI – based on current Market Rates but
• FIDIC – Based on reasonable cost and reasonable profit
• ‘ ”Fair Valuation” will normally mean cost plus a reasonable percentage for profit…with a
deduction for any proven inefficiency….but if there is proof of general market rate for
comparable work it may be taken into consideration or applied completely’* ….’reasonably and
properly incurred cost’
*Max . W. Abrahamson; Engineering Law and the ICE Contracts, 4th Edn.
25. April 2015
Assessing Quantum in Construction Disputes
Contractual Mechanisms and the Courts
Fair Valuation
• Fair to who ?
• Cost based – therefore includes risk NOT included for in Contract Rates
however must be read in conjunction with the balance of the contract
– are the limitations clauses relevant in this context ?
• Cost Plus indicative of maximum entitlement…but Market Rate could
produce a higher return (Laserbore v Morrison 1993)
26. April 2015
Assessing Quantum in Construction Disputes
Contractual Mechanisms and the Courts
Loss and/or Expense
• Loss and/or damage; Loss and/or Expense – equates to damages in a legal context (Wraight v OH&T
Holdings 1968)
• Direct loss and /or expense – ‘not merely consequential’ but resulted ‘directly and naturally’ from the
breach (Crudace v Cawoods 1978)
• In the context of damages, for costs to be recoverable, they must be ‘necessarily and reasonably
incurred’ (Floods of Queensferry v Shand 1999)
• The term ‘direct’ relates to ‘remoteness’ and not the type of damage
(direct v indirect cost)
• Limitations clause can provide same effect – FIDIC 17.6 ‘indirect consequential loss or damage’ is not
recoverable
• Loss of Profit is recoverable (Hotel Services v Hilton 2000; Deepak v ICI 1999)
27. April 2015
Assessing Quantum in Construction Disputes
Contractual Mechanisms and the Courts
Direct Loss and/or Expense (Robertson v Amey 2005)
• Cost and Expense are synonymous
• Loss and Losses are synonymous
• Direct = Remoteness not causation
• ‘Direct’ and ‘Directly Incurred’ = Arising Naturally (must flow naturally from the event)
• Direct Loss and/or Expense – Indirect Loss and/or Expense is not recoverable (2nd limb
of Hadley v Baxendale)
• Failure to make a profit due to an entitlement event = a loss
28. April 2015
Assessing Quantum in Construction Disputes
Contractual Mechanisms and the Courts
Overheads and Profit (Lilly v Mackay 2012)
• Judge considered previous case law and ruled :
‘A contractor can recover head office overheads and profit lost as a result of delay on a
construction project caused by factors which entitle it to loss and expense’
‘It is necessary for the contractor to prove on a balance of probabilities that if the delay had
not occurred, it would have secured work on projects which would have produced a return
(over and above costs) representing a profit and/or contribution to head office overheads’
‘The use of a formula, such as Emden or Hudson, is a legitimate and indeed helpful way of
ascertaining, on a balance of probabilities, what that return can be calculated to be’
29. April 2015
Assessing Quantum in Construction Disputes
Contractual Mechanisms and the Courts
Substantiation
• Obligation to prove to the Court that the amount being claimed is appropriate
• Plaintiff obliged to provide ‘such particularity’ as required to inform the Respondent of
the case being made (Wharf Properties v Cumine 1991)
• ‘Strict Proof’ not required in construction litigation – Court recognises that there is an
‘acceptable margin of error’ and that the use of resources to enhance detail to a
negligible degree is unnecessary as it is ‘misleading as to an exactitude’ which is not
attainable in construction litigation (Ascon v McAlpine 1999)
• In the ‘absence of detailed evidence’, the Court will seek to assess the appropriate
quantum ‘on the balance of probabilities’….’albeit based on the minimum
probability so attributable’ (CBUK v SRS 2012; also Robertson v Amey 2005)
30. April 2015
Assessing Quantum in Construction Disputes
Contractual Mechanisms and the Courts
Substantiation
• Where loss is proved to have occurred, and the Claimant has used his best
endeavours to assist the Court, quantum assessment will not be denied ‘for want of
fine detail’*
• However the Court may dismiss the Claim where the Claimant has not helped
himself or the Court – the Court will not make the Claimant’s case and if the case is
not pleaded on the available information, the case may be dismissed
• Causation is a pre-requisite to entitlement – link the impact to the cause (Holland v
Kvaerner 1996)
*Ennis & Breyer; SCL Paper D162 Para 4.19
31. April 2015
Assessing Quantum in Construction Disputes
Contractual Mechanisms and the Courts
Substantiation
• Under Clause 4.23 of the JCT, the Contractor is obliged to submit such information ‘as
should reasonably enable the Architect/Contract Administrator to form an opinion’ and
‘details of such loss and/or expense as are reasonably necessary for such ascertainment’
• ‘the Architect and the Quantity Surveyor are not strangers to the project in considering what
needs to be provided to them’ (Lilly v Mackay 2012)
• Even if Contract Terms are perceived as being more onerous, it is likely the Courts will follow
CBUK v SRS 2012 & Lilly Mackay 2012
• Front Line Factual Information produces the most compelling case
32. April 2015
Assessing Quantum in Construction Disputes
Contractual Mechanisms and the Courts
LIMITATIONS CLAUSES – Impact on Quantum
• PWC Compensation Events Definition – Disruption Excluded
• FIDIC Clause 17.6 excludes entitlement to consequential or indirect loss or
damage (Hedley v Baxendale 1854 – first limb)
• RIAI Clause 2 – Loss and Expense…within reasonable contemplation
(Balfour Beatty v Scottish Power 1994)
33. April 2015
Assessing Quantum in Construction Disputes
Contractual Mechanisms and the Courts
Context of legal interpretations – when should we concern
ourselves with such matters ?
• Preparation of Tender/Contract Documents
Drafting Contract Conditions & BOQ Prep
• Contract Administration
• Risk Assessment/Claims Risk Assessment
• Disputes
….all the time !
GCCC Review – BOQ Status ; Single Person DAB €10m+
34. April 2015
Assessing Quantum in Construction Disputes
Contractual Mechanisms and the Courts
Whilst general principles/legal doctrine
exists which may provide guidance,
every case must be considered on it’s
own merits and particular circumstances
If in doubt and stakes are high…consult
your Lawyer…..
and your QS
35. Assessing Quantum in Construction Disputes
Contractual Mechanisms and the Courts
Thank You
For Case Law….go to http://www.bailii.org/
http://www.irlii.org
Mark Wearen
MSCSI MRICS MCInstCES MSc
October 2015
April 2015