SlideShare a Scribd company logo
Assessing Quantum in Construction Disputes
Contractual Mechanisms and the Courts – Part 1
Mark Wearen
MSCSI MRICS MCInstCES MSc
October 2015
April 2015
April 2015
Assessing Quantum in Construction Disputes
Contractual Mechanisms and the Courts
What is Quantum ?
Context of legal definitions – when do we concern ourselves with
such matters ?
Contract Forms for Traditional Contracting – PWC/FIDIC/RIAI
Key Issues
April 2015
Assessing Quantum in Construction Disputes
Contractual Mechanisms and the Courts
Definition of Quantum
‘a required or allowed amount, especially an amount of money legally
payable in damages’*
*Oxford Dictionary
April 2015
Assessing Quantum in Construction Disputes
Contractual Mechanisms and the Courts
Definition of Quantum – Construction Context
‘The amount of money sought in respect of any matter which it is alleged gives
rise to an entitlement to a payment (for whatever reason) which is additional to
the initial contract sum or to the contract sum derived from the rates and prices
in the contract’
i.e. not payment for work included in the contract in accordance with the
corresponding rates and prices included in the contract.
April 2015
Assessing Quantum in Construction Disputes
Contractual Mechanisms and the Courts
Calculating Quantum – Construction Context
• Construction and change go hand in hand – hence the need to include express
provisions dealing with change and it’s impacts
• Standard forms recognise this and include express provisions to permit change under
the contract and to manage that change within the contractual framework – these
provisions allocate risk and should simplify dispute resolution
• Calculating Quantum should not be a random process – can be governed by the
provisions of the Contract and/or applicable Law -not just the applicable Law
April 2015
Assessing Quantum in Construction Disputes
Contractual Mechanisms and the Courts
Calculating Quantum – Construction Context
• Express Provisions typically address how change (e.g. additional work or breaches of
contract) is to be valued – risk mitigation
• Bespoke forms generally mimic the standard forms with risk transfer tailored to suit the
bargaining position of the parties and their appetite for risk
• Limitations on valuing change can be expressly stated – risk mitigation
• How do we ascertain the required or allowed amount ?
April 2015
Assessing Quantum in Construction Disputes
Contractual Mechanisms and the Courts
Quantum – Items to Consider
Next Instalment….Part 2
• Damages
• Interest and Finance Charges
• Acceleration
• Quantum Meruit
• Causation
• Duty to Mitigate
• Irish Case Law
Today…Part 1
• Valuation Rules
• ‘Similar’ – Character and Conditions
• BOQ rates as a basis
• ‘Reasonable’
• Cost
• Fair Valuation
• Loss and/or Expense
• Overheads and Profit
• Substantiation
• Limitations Clauses
April 2015
Assessing Quantum in Construction Disputes
Contractual Mechanisms and the Courts
Public Works Contract* - Valuation Rules
* Public Works Contract for Building Works Designed by the Employer Document Reference PW-CF1 v.1.10 27 June 2014
April 2015
Assessing Quantum in Construction Disputes
Contractual Mechanisms and the Courts
Public Works Contract – Valuation Rules
10.6.1 Similar work under similar circumstances - use the rates in the pricing document
10.6.2 Not similar work and not under similar circumstances – use the rates in the pricing
document as the basis where reasonable
If the above rules do not apply…..then
10.6.3 Fair Valuation – to be based on rates for similar work in the locality, If available
Or the ER may ‘conclusively direct’ that
10.6.4 Valuation is based on Schedule 2D rates and provisions
Time and Materials/Dayworks
April 2015
Assessing Quantum in Construction Disputes
Contractual Mechanisms and the Courts
Public Works Contract – Other Valuation Provisions
10.3.4 Contractor to keep records of ‘costs’ associated with claims
10.7.1 (2) Delay Costs – defined as ‘expenses [excluding profit and loss of profit]’
10.7.4 Limits recovery for Delay, Disruption, Acceleration, Loss of Productivity, Knock
On Effects
Claimant must also inter alia….
10.3.1 (1) Set out ‘relevant facts’
10.3.1 (2) Provide a proposal ‘so far as is practicable’ and
10.3.3 (3) If ongoing, provide other information the ER ‘reasonably requires’
April 2015
Assessing Quantum in Construction Disputes
Contractual Mechanisms and the Courts
FIDIC Red Book 1999* Clause 12.3 – Valuation Rules
* FIDIC Conditions of Contract for Construction for Building and Engineering Works designed by the Contractor 1999
a) For each item of work, the appropriate rate or price specified in the contract shall
apply
b) If there is no such item in the contract, the rate or price specified in the contract
for ‘similar’ work executed under similar conditions shall apply failing which…
c) A new rate or price shall apply which shall be ‘derived from any relevant rates or
prices in the contract, with reasonable adjustments and…
d) If no rates or prices are relevant, new rates and prices shall be based on the
reasonable cost of executing the work, together with reasonable profit
Clause 13.6 - dayworks ‘for work of a minor or incidental basis’
April 2015
Assessing Quantum in Construction Disputes
Contractual Mechanisms and the Courts
FIDIC Red Book 1999 - Other Valuation Provisions
3.5 In the event that the parties fail to reach agreement on ‘any matter’, the
Engineer shall make a ‘fair determination in accordance with the Contract,
taking due regard of all relevant circumstances’
20.1 Contractor to maintain records ‘as may be necessary to substantiate any claim’
and must submit ‘a fully detailed claim which includes full supporting
particulars’
• Numerous provisions for recovery of ‘cost’ (e.g. 4.12)
• Numerous provisions for ‘cost plus reasonable profit’ (e.g. 4.7)
April 2015
Assessing Quantum in Construction Disputes
Contractual Mechanisms and the Courts
RIAI Contract* – Clause 13 Valuation Rules
Valuation rules to apply when valuing variations :
a) Bill rates if the additional work is similar in character and carried out under similar
conditions,
b) Bill rates shall form the basis of the valuation where work is not carried out under
similar conditions, ‘so far as may be reasonable’
c) Where no appropriate Bill Rates exist, a ‘Fair Valuation’ shall be made based upon
current rates for ‘similar work in the locality’.
d) daywork as tendered or SCS/CIF agreement
* RIAI Agreement and Schedule of Conditions of Building Contract 2002 (Rev 1 Print 4)
April 2015
Assessing Quantum in Construction Disputes
Contractual Mechanisms and the Courts
RIAI Contract – Other Valuation Provisions
Clause 2 Loss and Expense
‘beyond that provided for or reasonably contemplated by
this contract’ – limitation
(Balfour Beatty v Scottish Power 1994)
April 2015
Assessing Quantum in Construction Disputes
Contractual Mechanisms and the Courts
Valuing Change – Consistency in the Approach across Forms
a) Valuation Rules generally apply for valuing variations/compensation events
b) Contract Rates and Prices to be utilised – similar works under similar conditions
c) Contract Rates form the basis – where reasonable
d) Fair Valuation variants – reasonable cost and/or market rates
e) Actual Resources utilising defined rates and mark-ups
Contracts also allow for recovery of:
• Cost
• Expense
• Loss and Expense
April 2015
Assessing Quantum in Construction Disputes
Contractual Mechanisms and the Courts
Why use the Rules ?
• Parties must first look to the Contract to value additional work - If the work meets
the definition of a variation or compensation event, the Valuation Rules apply (MT
Hojgaard v E.ON 2013)
• The rates and prices in the contract are the starting point for valuing additional
work – ‘sacrosanct’ (Henry Boot v Alstom 2000; Maeda Corp v Hong Kong 2012)
• To move away from the contract rates, establish that work is not similar or is not
executed under similar conditions, or is outside the scope of the contract (Costain v
Zanen 1996) - thus the application of contract rates would be unreasonable as a
basis or in their entirety
• Risk Transfer – within the scope of the contract
April 2015
Assessing Quantum in Construction Disputes
Contractual Mechanisms and the Courts
Bill Rates as a Basis (Henry Boot v Alstom 2000 & Maeda Corp v Hong Kong 2011)
• Rates are sacrosanct
• Only insofar as they apply to similar works executed under similar circumstances
• Rates can be opened up and relevant elements changed to produce a new rate based on
the contract rates – a ‘star rate’
• Fair Valuation for relevant elements of a contract rate
• Not an opportunity to right any wrongs/correct any errors
April 2015
Assessing Quantum in Construction Disputes
Contractual Mechanisms and the Courts
Similar Character and Similar Conditions
• The Contract is ‘the means of which the intention of the parties was expressed’. The
‘factual matrix’ within which consideration as to whether or not work was similar or
undertaken under similar conditions must be based on the contract (Wates v Bredero
Fleet 1993)
• Thus the Contractor cannot rely upon information known to him when pricing the project
but which is not incorporated into the contract (e.g. the information pack under the Public
Works Contract and Clause 1.9.1 – the entire agreement clause)
• An ‘ambiguity or peculiarity’ in the wording of the contract may render extrinsic
information admissible but only where known to both parties
April 2015
Assessing Quantum in Construction Disputes
Contractual Mechanisms and the Courts
Reasonable and Reasonableness – What is ‘Reasonable’ ?
Chitty 31st Edn. 37-101 :
‘a question requiring consideration of all the factors in a particular case’ but ‘no rigid rules
apply’ …… ‘cost plus a percentage for profit’ often equates to ’reasonable remuneration’
Keating 9th Edn. 4-001 :
Is the reasonable remuneration to be calculated ‘within a contractual framework’ ?
Keating 9th Edn. 20-183 :
‘In considering what is reasonable, the Court would have regard to all the circumstances
including the terms of the Contract’ – in the context of issuing instructions – why not when
calculating quantum ?
April 2015
Assessing Quantum in Construction Disputes
Contractual Mechanisms and the Courts
Reasonable and Reasonableness – What is ‘Reasonable’ ?
• Contract conditions should be construed so as to give them the meaning that ‘a
reasonable person, having all the background knowledge which would have been
available to the parties would have understood them to be using the language in the
contract to mean’ (Chartbrook v Persimmon 2009)
• What factors determine reasonableness ?
• Consideration of relevant information
• Within a contractual framework
• Opinion is that of a ‘reasonable person’ suitably informed – legal standard
• Offer Value for Money and address Obligation to Mitigate
• If you want to be ‘unreasonable’, utilise express terms
April 2015
Assessing Quantum in Construction Disputes
Contractual Mechanisms and the Courts
Cost
‘an amount that has to be paid or spent to buy or obtain something’*
• Cost under the contract is not an estimate; a quotation; an allowance; an on account
sum…..or an amount based on contract rates unless expressly described as such in the
contract (selling price)
• FIDIC 1.1.4.3 defines cost as ‘expenditure reasonably incurred’ and goes on to state that it
includes ‘overheads and similar charges, but does not include profit’ (off site costs included)
*Oxford Dictionary
April 2015
Assessing Quantum in Construction Disputes
Contractual Mechanisms and the Courts
Fair Valuation
• Where bill rates don’t apply, or it would be unreasonable to use them as a
basis for a valuation, a Fair Valuation shall be made…..result is new rates and
prices
What is a Fair Valuation ?
• A fair valuation will ‘ordinarily be based on the reasonable costs of carrying out
the work, if reasonably and properly incurred’…thus there is no entitlement to
payment for expenditure which ‘would not have been incurred by a reasonably
competent Contractor in the same or similar circumstances’ (Weldon Plant v
Commissioner for New Towns 2000)
April 2015
Assessing Quantum in Construction Disputes
Contractual Mechanisms and the Courts
Fair Valuation
• For a valuation to be ‘fair’, it must contain all the elements ‘ordinarily found in
contract rate or price’ – labour/plant/materials/overheads/profit (Weldon Plant v
Commissioner for New Towns 2000)
• Profit is an integral element of the rates and prices included in the contract and a fair
rate would include profit (Semco Salvage v Lancer 1997)
• Clause 12.3 of FIDIC – a ‘new rate or price’….based on the ‘reasonable Cost of
executing the work, together with reasonable profit, taking account of any other
relevant matter’.
April 2015
Assessing Quantum in Construction Disputes
Contractual Mechanisms and the Courts
Fair Valuation
• Elements usually found in a contract rate
• Can be cost based however….Cost must be reasonable costs – reasonably and properly incurred
• PWC – ‘rates for similar work in the locality, if available’
• RIAI – based on current Market Rates but
• FIDIC – Based on reasonable cost and reasonable profit
• ‘ ”Fair Valuation” will normally mean cost plus a reasonable percentage for profit…with a
deduction for any proven inefficiency….but if there is proof of general market rate for
comparable work it may be taken into consideration or applied completely’* ….’reasonably and
properly incurred cost’
*Max . W. Abrahamson; Engineering Law and the ICE Contracts, 4th Edn.
April 2015
Assessing Quantum in Construction Disputes
Contractual Mechanisms and the Courts
Fair Valuation
• Fair to who ?
• Cost based – therefore includes risk NOT included for in Contract Rates
however must be read in conjunction with the balance of the contract
– are the limitations clauses relevant in this context ?
• Cost Plus indicative of maximum entitlement…but Market Rate could
produce a higher return (Laserbore v Morrison 1993)
April 2015
Assessing Quantum in Construction Disputes
Contractual Mechanisms and the Courts
Loss and/or Expense
• Loss and/or damage; Loss and/or Expense – equates to damages in a legal context (Wraight v OH&T
Holdings 1968)
• Direct loss and /or expense – ‘not merely consequential’ but resulted ‘directly and naturally’ from the
breach (Crudace v Cawoods 1978)
• In the context of damages, for costs to be recoverable, they must be ‘necessarily and reasonably
incurred’ (Floods of Queensferry v Shand 1999)
• The term ‘direct’ relates to ‘remoteness’ and not the type of damage
(direct v indirect cost)
• Limitations clause can provide same effect – FIDIC 17.6 ‘indirect consequential loss or damage’ is not
recoverable
• Loss of Profit is recoverable (Hotel Services v Hilton 2000; Deepak v ICI 1999)
April 2015
Assessing Quantum in Construction Disputes
Contractual Mechanisms and the Courts
Direct Loss and/or Expense (Robertson v Amey 2005)
• Cost and Expense are synonymous
• Loss and Losses are synonymous
• Direct = Remoteness not causation
• ‘Direct’ and ‘Directly Incurred’ = Arising Naturally (must flow naturally from the event)
• Direct Loss and/or Expense – Indirect Loss and/or Expense is not recoverable (2nd limb
of Hadley v Baxendale)
• Failure to make a profit due to an entitlement event = a loss
April 2015
Assessing Quantum in Construction Disputes
Contractual Mechanisms and the Courts
Overheads and Profit (Lilly v Mackay 2012)
• Judge considered previous case law and ruled :
‘A contractor can recover head office overheads and profit lost as a result of delay on a
construction project caused by factors which entitle it to loss and expense’
‘It is necessary for the contractor to prove on a balance of probabilities that if the delay had
not occurred, it would have secured work on projects which would have produced a return
(over and above costs) representing a profit and/or contribution to head office overheads’
‘The use of a formula, such as Emden or Hudson, is a legitimate and indeed helpful way of
ascertaining, on a balance of probabilities, what that return can be calculated to be’
April 2015
Assessing Quantum in Construction Disputes
Contractual Mechanisms and the Courts
Substantiation
• Obligation to prove to the Court that the amount being claimed is appropriate
• Plaintiff obliged to provide ‘such particularity’ as required to inform the Respondent of
the case being made (Wharf Properties v Cumine 1991)
• ‘Strict Proof’ not required in construction litigation – Court recognises that there is an
‘acceptable margin of error’ and that the use of resources to enhance detail to a
negligible degree is unnecessary as it is ‘misleading as to an exactitude’ which is not
attainable in construction litigation (Ascon v McAlpine 1999)
• In the ‘absence of detailed evidence’, the Court will seek to assess the appropriate
quantum ‘on the balance of probabilities’….’albeit based on the minimum
probability so attributable’ (CBUK v SRS 2012; also Robertson v Amey 2005)
April 2015
Assessing Quantum in Construction Disputes
Contractual Mechanisms and the Courts
Substantiation
• Where loss is proved to have occurred, and the Claimant has used his best
endeavours to assist the Court, quantum assessment will not be denied ‘for want of
fine detail’*
• However the Court may dismiss the Claim where the Claimant has not helped
himself or the Court – the Court will not make the Claimant’s case and if the case is
not pleaded on the available information, the case may be dismissed
• Causation is a pre-requisite to entitlement – link the impact to the cause (Holland v
Kvaerner 1996)
*Ennis & Breyer; SCL Paper D162 Para 4.19
April 2015
Assessing Quantum in Construction Disputes
Contractual Mechanisms and the Courts
Substantiation
• Under Clause 4.23 of the JCT, the Contractor is obliged to submit such information ‘as
should reasonably enable the Architect/Contract Administrator to form an opinion’ and
‘details of such loss and/or expense as are reasonably necessary for such ascertainment’
• ‘the Architect and the Quantity Surveyor are not strangers to the project in considering what
needs to be provided to them’ (Lilly v Mackay 2012)
• Even if Contract Terms are perceived as being more onerous, it is likely the Courts will follow
CBUK v SRS 2012 & Lilly Mackay 2012
• Front Line Factual Information produces the most compelling case
April 2015
Assessing Quantum in Construction Disputes
Contractual Mechanisms and the Courts
LIMITATIONS CLAUSES – Impact on Quantum
• PWC Compensation Events Definition – Disruption Excluded
• FIDIC Clause 17.6 excludes entitlement to consequential or indirect loss or
damage (Hedley v Baxendale 1854 – first limb)
• RIAI Clause 2 – Loss and Expense…within reasonable contemplation
(Balfour Beatty v Scottish Power 1994)
April 2015
Assessing Quantum in Construction Disputes
Contractual Mechanisms and the Courts
Context of legal interpretations – when should we concern
ourselves with such matters ?
• Preparation of Tender/Contract Documents
Drafting Contract Conditions & BOQ Prep
• Contract Administration
• Risk Assessment/Claims Risk Assessment
• Disputes
….all the time !
GCCC Review – BOQ Status ; Single Person DAB €10m+
April 2015
Assessing Quantum in Construction Disputes
Contractual Mechanisms and the Courts
Whilst general principles/legal doctrine
exists which may provide guidance,
every case must be considered on it’s
own merits and particular circumstances
If in doubt and stakes are high…consult
your Lawyer…..
and your QS
Assessing Quantum in Construction Disputes
Contractual Mechanisms and the Courts
Thank You
For Case Law….go to http://www.bailii.org/
http://www.irlii.org
Mark Wearen
MSCSI MRICS MCInstCES MSc
October 2015
April 2015

More Related Content

What's hot

Effective Contract Management
Effective Contract ManagementEffective Contract Management
Effective Contract Management
Dr Gordon Murray
 
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...Praveen Premkumar
 
CFW NEC Management of change under the NEC3
CFW NEC  Management of change under the NEC3 CFW NEC  Management of change under the NEC3
CFW NEC Management of change under the NEC3
Rae Davies
 
Contract Management
Contract Management Contract Management
Contract Management
Gazi Sanaul Hasan
 
# FIDIC Payment Flow Charts # By SN Panigrahi
# FIDIC Payment Flow Charts # By SN Panigrahi# FIDIC Payment Flow Charts # By SN Panigrahi
# FIDIC Payment Flow Charts # By SN Panigrahi
SN Panigrahi, PMP
 
Presentation - Construction Contract Dispute Resolution
Presentation - Construction Contract Dispute ResolutionPresentation - Construction Contract Dispute Resolution
Presentation - Construction Contract Dispute ResolutionJustin DeMerchant
 
Clause 14.9 Payment of Retention Money-Understanding Clauses in FIDIC ‘Condit...
Clause 14.9 Payment of Retention Money-Understanding Clauses in FIDIC ‘Condit...Clause 14.9 Payment of Retention Money-Understanding Clauses in FIDIC ‘Condit...
Clause 14.9 Payment of Retention Money-Understanding Clauses in FIDIC ‘Condit...
Divyanshu Dayal
 
NEC Engineering and Construction Contract (ECC) - compensation events webinar
NEC Engineering and Construction Contract (ECC) -  compensation events webinarNEC Engineering and Construction Contract (ECC) -  compensation events webinar
NEC Engineering and Construction Contract (ECC) - compensation events webinar
Association for Project Management
 
Cost value reconciliation (cvr)
Cost value reconciliation (cvr)Cost value reconciliation (cvr)
Cost value reconciliation (cvr)
EVERSENDAI ENGINEERING (L.L.C.)
 
Fidic flow charts final
Fidic flow charts finalFidic flow charts final
Fidic flow charts finalFitBlar Mit
 
Effective contract administration may 2014
Effective contract administration may 2014Effective contract administration may 2014
Effective contract administration may 2014
SHKLaw
 
Building contracts and the JCT
Building contracts and the JCTBuilding contracts and the JCT
Building contracts and the JCTJulian Swindell
 
Contracts & Claims Management Workshop (Session-1)
Contracts & Claims Management Workshop (Session-1)Contracts & Claims Management Workshop (Session-1)
Contracts & Claims Management Workshop (Session-1)Tahir B Mirza
 
Bid and Tender Process Training Presentation
Bid and Tender Process Training PresentationBid and Tender Process Training Presentation
Bid and Tender Process Training Presentation
Michael Lee
 
M5 - NEC3 Compensation Events:agreeing contractual change promptly, amicable ...
M5 - NEC3 Compensation Events:agreeing contractual change promptly, amicable ...M5 - NEC3 Compensation Events:agreeing contractual change promptly, amicable ...
M5 - NEC3 Compensation Events:agreeing contractual change promptly, amicable ...
Project Controls Expo
 
Fidic Form of Contract.
Fidic Form of Contract.Fidic Form of Contract.
Fidic Form of Contract.
Shantanu Kumar Behera
 
Contract management sys
Contract management sysContract management sys
Contract management sys
susantakumarnayak
 
FIDIC variation, claim & dispute - CYLFEx workshop
FIDIC variation, claim & dispute - CYLFEx workshopFIDIC variation, claim & dispute - CYLFEx workshop
FIDIC variation, claim & dispute - CYLFEx workshop
M Maged Hegazy, LLM, MBA, CCP, P3O
 
Construction Claims
Construction ClaimsConstruction Claims
Construction Claims
Rajesh Sharma
 
Overview to contract management
Overview to contract managementOverview to contract management
Overview to contract management
Priyesh Nair
 

What's hot (20)

Effective Contract Management
Effective Contract ManagementEffective Contract Management
Effective Contract Management
 
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
 
CFW NEC Management of change under the NEC3
CFW NEC  Management of change under the NEC3 CFW NEC  Management of change under the NEC3
CFW NEC Management of change under the NEC3
 
Contract Management
Contract Management Contract Management
Contract Management
 
# FIDIC Payment Flow Charts # By SN Panigrahi
# FIDIC Payment Flow Charts # By SN Panigrahi# FIDIC Payment Flow Charts # By SN Panigrahi
# FIDIC Payment Flow Charts # By SN Panigrahi
 
Presentation - Construction Contract Dispute Resolution
Presentation - Construction Contract Dispute ResolutionPresentation - Construction Contract Dispute Resolution
Presentation - Construction Contract Dispute Resolution
 
Clause 14.9 Payment of Retention Money-Understanding Clauses in FIDIC ‘Condit...
Clause 14.9 Payment of Retention Money-Understanding Clauses in FIDIC ‘Condit...Clause 14.9 Payment of Retention Money-Understanding Clauses in FIDIC ‘Condit...
Clause 14.9 Payment of Retention Money-Understanding Clauses in FIDIC ‘Condit...
 
NEC Engineering and Construction Contract (ECC) - compensation events webinar
NEC Engineering and Construction Contract (ECC) -  compensation events webinarNEC Engineering and Construction Contract (ECC) -  compensation events webinar
NEC Engineering and Construction Contract (ECC) - compensation events webinar
 
Cost value reconciliation (cvr)
Cost value reconciliation (cvr)Cost value reconciliation (cvr)
Cost value reconciliation (cvr)
 
Fidic flow charts final
Fidic flow charts finalFidic flow charts final
Fidic flow charts final
 
Effective contract administration may 2014
Effective contract administration may 2014Effective contract administration may 2014
Effective contract administration may 2014
 
Building contracts and the JCT
Building contracts and the JCTBuilding contracts and the JCT
Building contracts and the JCT
 
Contracts & Claims Management Workshop (Session-1)
Contracts & Claims Management Workshop (Session-1)Contracts & Claims Management Workshop (Session-1)
Contracts & Claims Management Workshop (Session-1)
 
Bid and Tender Process Training Presentation
Bid and Tender Process Training PresentationBid and Tender Process Training Presentation
Bid and Tender Process Training Presentation
 
M5 - NEC3 Compensation Events:agreeing contractual change promptly, amicable ...
M5 - NEC3 Compensation Events:agreeing contractual change promptly, amicable ...M5 - NEC3 Compensation Events:agreeing contractual change promptly, amicable ...
M5 - NEC3 Compensation Events:agreeing contractual change promptly, amicable ...
 
Fidic Form of Contract.
Fidic Form of Contract.Fidic Form of Contract.
Fidic Form of Contract.
 
Contract management sys
Contract management sysContract management sys
Contract management sys
 
FIDIC variation, claim & dispute - CYLFEx workshop
FIDIC variation, claim & dispute - CYLFEx workshopFIDIC variation, claim & dispute - CYLFEx workshop
FIDIC variation, claim & dispute - CYLFEx workshop
 
Construction Claims
Construction ClaimsConstruction Claims
Construction Claims
 
Overview to contract management
Overview to contract managementOverview to contract management
Overview to contract management
 

Viewers also liked

Mlw Presentation Dof Risk Civilex 09
Mlw Presentation   Dof Risk   Civilex 09Mlw Presentation   Dof Risk   Civilex 09
Mlw Presentation Dof Risk Civilex 09
Mark Wearen
 
An Introduction to Civil Engineering Cost Management
An Introduction to Civil Engineering Cost ManagementAn Introduction to Civil Engineering Cost Management
An Introduction to Civil Engineering Cost Management
Mark Wearen
 
Edugate/IE Federation - Glenn Wearen, Edugate Federation Operator, HEAnet
Edugate/IE Federation -  Glenn Wearen, Edugate Federation Operator, HEAnetEdugate/IE Federation -  Glenn Wearen, Edugate Federation Operator, HEAnet
Edugate/IE Federation - Glenn Wearen, Edugate Federation Operator, HEAnet
Eduserv
 
MLW - Vfm Cmg Conference 25 02 10 Linkedin
MLW -   Vfm    Cmg Conference   25 02 10   LinkedinMLW -   Vfm    Cmg Conference   25 02 10   Linkedin
MLW - Vfm Cmg Conference 25 02 10 Linkedin
Mark Wearen
 
InterTech is a leading Russian civil engineering company
InterTech is a leading Russian civil engineering companyInterTech is a leading Russian civil engineering company
InterTech is a leading Russian civil engineering company
Maxim Gavrik
 
Civil engineering
Civil engineeringCivil engineering
Civil engineering
Lokesh Gupta
 
E. soil classification
E. soil classificationE. soil classification
E. soil classification
Fazal-E- Jalal
 
Civil engineering in Russia 2017 – InterTech presentation
Civil engineering in Russia 2017 – InterTech presentationCivil engineering in Russia 2017 – InterTech presentation
Civil engineering in Russia 2017 – InterTech presentation
Maxim Gavrik
 
Lists of Civil Engineering Review Centers in the Philippines
Lists of Civil Engineering Review Centers in the PhilippinesLists of Civil Engineering Review Centers in the Philippines
Lists of Civil Engineering Review Centers in the Philippines
Dindo Mojica
 
InterTech is a Saint Petersburg based civil engineering company
InterTech is a Saint Petersburg based civil engineering companyInterTech is a Saint Petersburg based civil engineering company
InterTech is a Saint Petersburg based civil engineering company
Maxim Gavrik
 
What is Civil Engineering?
What is Civil Engineering? What is Civil Engineering?
What is Civil Engineering?
Andy Hahn
 
Invest in Russian construction industry - our company looking for investors
Invest in Russian construction industry - our company looking for investorsInvest in Russian construction industry - our company looking for investors
Invest in Russian construction industry - our company looking for investors
Maxim Gavrik
 
Academic performance correlation with the qualification of Final Projects in ...
Academic performance correlation with the qualification of Final Projects in ...Academic performance correlation with the qualification of Final Projects in ...
Academic performance correlation with the qualification of Final Projects in ...
Technological Ecosystems for Enhancing Multiculturality
 
Why you should study civil engineering
Why you should study civil engineeringWhy you should study civil engineering
Why you should study civil engineering
Eva Lantsoght
 
Introduction to Civil Engineering (Harsh Gupta)
Introduction to Civil Engineering (Harsh Gupta)Introduction to Civil Engineering (Harsh Gupta)
Introduction to Civil Engineering (Harsh Gupta)
Harsh Gupta
 
InterTech is one of the top construction companies in Qatar civil engineering
InterTech is one of the top construction companies in Qatar civil engineeringInterTech is one of the top construction companies in Qatar civil engineering
InterTech is one of the top construction companies in Qatar civil engineering
Maxim Gavrik
 
InterTech is a St Petersburg architecture and civil engineering company
InterTech is a St Petersburg architecture and civil engineering companyInterTech is a St Petersburg architecture and civil engineering company
InterTech is a St Petersburg architecture and civil engineering company
Maxim Gavrik
 
Python in Civil/Environmental Engineering
Python in Civil/Environmental EngineeringPython in Civil/Environmental Engineering
Python in Civil/Environmental Engineering
pmhobson
 
Simulating Civil Engineering Projects In Virtual Worlds
Simulating Civil Engineering Projects In Virtual WorldsSimulating Civil Engineering Projects In Virtual Worlds
Simulating Civil Engineering Projects In Virtual Worlds
Pam Broviak
 
Applications of waste tire products in civil engineering
Applications of waste tire products in civil engineeringApplications of waste tire products in civil engineering
Applications of waste tire products in civil engineering
MARCOS ANTONIO ROSSI
 

Viewers also liked (20)

Mlw Presentation Dof Risk Civilex 09
Mlw Presentation   Dof Risk   Civilex 09Mlw Presentation   Dof Risk   Civilex 09
Mlw Presentation Dof Risk Civilex 09
 
An Introduction to Civil Engineering Cost Management
An Introduction to Civil Engineering Cost ManagementAn Introduction to Civil Engineering Cost Management
An Introduction to Civil Engineering Cost Management
 
Edugate/IE Federation - Glenn Wearen, Edugate Federation Operator, HEAnet
Edugate/IE Federation -  Glenn Wearen, Edugate Federation Operator, HEAnetEdugate/IE Federation -  Glenn Wearen, Edugate Federation Operator, HEAnet
Edugate/IE Federation - Glenn Wearen, Edugate Federation Operator, HEAnet
 
MLW - Vfm Cmg Conference 25 02 10 Linkedin
MLW -   Vfm    Cmg Conference   25 02 10   LinkedinMLW -   Vfm    Cmg Conference   25 02 10   Linkedin
MLW - Vfm Cmg Conference 25 02 10 Linkedin
 
InterTech is a leading Russian civil engineering company
InterTech is a leading Russian civil engineering companyInterTech is a leading Russian civil engineering company
InterTech is a leading Russian civil engineering company
 
Civil engineering
Civil engineeringCivil engineering
Civil engineering
 
E. soil classification
E. soil classificationE. soil classification
E. soil classification
 
Civil engineering in Russia 2017 – InterTech presentation
Civil engineering in Russia 2017 – InterTech presentationCivil engineering in Russia 2017 – InterTech presentation
Civil engineering in Russia 2017 – InterTech presentation
 
Lists of Civil Engineering Review Centers in the Philippines
Lists of Civil Engineering Review Centers in the PhilippinesLists of Civil Engineering Review Centers in the Philippines
Lists of Civil Engineering Review Centers in the Philippines
 
InterTech is a Saint Petersburg based civil engineering company
InterTech is a Saint Petersburg based civil engineering companyInterTech is a Saint Petersburg based civil engineering company
InterTech is a Saint Petersburg based civil engineering company
 
What is Civil Engineering?
What is Civil Engineering? What is Civil Engineering?
What is Civil Engineering?
 
Invest in Russian construction industry - our company looking for investors
Invest in Russian construction industry - our company looking for investorsInvest in Russian construction industry - our company looking for investors
Invest in Russian construction industry - our company looking for investors
 
Academic performance correlation with the qualification of Final Projects in ...
Academic performance correlation with the qualification of Final Projects in ...Academic performance correlation with the qualification of Final Projects in ...
Academic performance correlation with the qualification of Final Projects in ...
 
Why you should study civil engineering
Why you should study civil engineeringWhy you should study civil engineering
Why you should study civil engineering
 
Introduction to Civil Engineering (Harsh Gupta)
Introduction to Civil Engineering (Harsh Gupta)Introduction to Civil Engineering (Harsh Gupta)
Introduction to Civil Engineering (Harsh Gupta)
 
InterTech is one of the top construction companies in Qatar civil engineering
InterTech is one of the top construction companies in Qatar civil engineeringInterTech is one of the top construction companies in Qatar civil engineering
InterTech is one of the top construction companies in Qatar civil engineering
 
InterTech is a St Petersburg architecture and civil engineering company
InterTech is a St Petersburg architecture and civil engineering companyInterTech is a St Petersburg architecture and civil engineering company
InterTech is a St Petersburg architecture and civil engineering company
 
Python in Civil/Environmental Engineering
Python in Civil/Environmental EngineeringPython in Civil/Environmental Engineering
Python in Civil/Environmental Engineering
 
Simulating Civil Engineering Projects In Virtual Worlds
Simulating Civil Engineering Projects In Virtual WorldsSimulating Civil Engineering Projects In Virtual Worlds
Simulating Civil Engineering Projects In Virtual Worlds
 
Applications of waste tire products in civil engineering
Applications of waste tire products in civil engineeringApplications of waste tire products in civil engineering
Applications of waste tire products in civil engineering
 

Similar to SCSI / RICS Presentation on Construction Quantum - Part 1

Irish Public Works Contract - Clause 10.6 - Practical Application
Irish Public Works Contract - Clause 10.6 - Practical ApplicationIrish Public Works Contract - Clause 10.6 - Practical Application
Irish Public Works Contract - Clause 10.6 - Practical Application
Mark Wearen
 
Government Contracts 101 - Understanding the Basics of Contract Types
Government Contracts 101 - Understanding the Basics of Contract Types Government Contracts 101 - Understanding the Basics of Contract Types
Government Contracts 101 - Understanding the Basics of Contract Types
Unanet
 
Revenue Recognition for Contractors - NECA NOW Conference
Revenue Recognition for Contractors - NECA NOW Conference Revenue Recognition for Contractors - NECA NOW Conference
Revenue Recognition for Contractors - NECA NOW Conference
CBIZ, Inc.
 
Audit of contracts version 2
Audit of contracts version 2Audit of contracts version 2
Audit of contracts version 2
EMAC Consulting Group
 
3. dcaa small_business_outreach
3. dcaa small_business_outreach3. dcaa small_business_outreach
3. dcaa small_business_outreachColorado PTAC
 
Planning and development club - May 2017, Nottingham
Planning and development club - May 2017, NottinghamPlanning and development club - May 2017, Nottingham
Planning and development club - May 2017, Nottingham
Browne Jacobson LLP
 
Cfr ias 11 construction contract presentation by MOHSIN MUMTAZ
Cfr  ias 11 construction contract presentation by MOHSIN MUMTAZCfr  ias 11 construction contract presentation by MOHSIN MUMTAZ
Cfr ias 11 construction contract presentation by MOHSIN MUMTAZ
mianmohsinmumtazshb
 
Issues in s. 43CA of Income Tax Act
Issues in s. 43CA of Income Tax ActIssues in s. 43CA of Income Tax Act
Issues in s. 43CA of Income Tax Act
Dharmesh Shah
 
Bills of quantities
Bills of quantitiesBills of quantities
Bills of quantities
Ar.Vijay Kumar
 
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Rae Davies
 
Chapter two.pptx
Chapter two.pptxChapter two.pptx
Chapter two.pptx
TeshomeMogez
 
Seminar Presentation Slides (Chapter 2)
Seminar Presentation Slides (Chapter 2)Seminar Presentation Slides (Chapter 2)
Seminar Presentation Slides (Chapter 2)
Melvin Lim
 
Public Meeting - Contract Close-Out - Ground Rules
Public Meeting - Contract Close-Out - Ground RulesPublic Meeting - Contract Close-Out - Ground Rules
Public Meeting - Contract Close-Out - Ground Rules
Asia Master Training آسيا ماسترز للتدريب والتطوير
 
Baker Tilly Presents: New to Cost Reimbursement Contracts? Meet Your New Frie...
Baker Tilly Presents: New to Cost Reimbursement Contracts? Meet Your New Frie...Baker Tilly Presents: New to Cost Reimbursement Contracts? Meet Your New Frie...
Baker Tilly Presents: New to Cost Reimbursement Contracts? Meet Your New Frie...
BakerTillyConsulting
 
The Scoop on the Incurred Cost Submission
The Scoop on the Incurred Cost SubmissionThe Scoop on the Incurred Cost Submission
The Scoop on the Incurred Cost Submission
Unanet
 
Professional Practice 2: Group Assignment
Professional Practice 2: Group AssignmentProfessional Practice 2: Group Assignment
Professional Practice 2: Group Assignment
마 이환
 
Core_Services_White Papers Oracle Service PUR.pdf
Core_Services_White Papers Oracle Service PUR.pdfCore_Services_White Papers Oracle Service PUR.pdf
Core_Services_White Papers Oracle Service PUR.pdf
TarigTaha3
 
Commercial aspects of civil construction
Commercial aspects of civil constructionCommercial aspects of civil construction
Commercial aspects of civil construction
sandesh mundra
 

Similar to SCSI / RICS Presentation on Construction Quantum - Part 1 (20)

Irish Public Works Contract - Clause 10.6 - Practical Application
Irish Public Works Contract - Clause 10.6 - Practical ApplicationIrish Public Works Contract - Clause 10.6 - Practical Application
Irish Public Works Contract - Clause 10.6 - Practical Application
 
Government Contracts 101 - Understanding the Basics of Contract Types
Government Contracts 101 - Understanding the Basics of Contract Types Government Contracts 101 - Understanding the Basics of Contract Types
Government Contracts 101 - Understanding the Basics of Contract Types
 
Revenue Recognition for Contractors - NECA NOW Conference
Revenue Recognition for Contractors - NECA NOW Conference Revenue Recognition for Contractors - NECA NOW Conference
Revenue Recognition for Contractors - NECA NOW Conference
 
Audit of contracts version 2
Audit of contracts version 2Audit of contracts version 2
Audit of contracts version 2
 
3. dcaa small_business_outreach
3. dcaa small_business_outreach3. dcaa small_business_outreach
3. dcaa small_business_outreach
 
Planning and development club - May 2017, Nottingham
Planning and development club - May 2017, NottinghamPlanning and development club - May 2017, Nottingham
Planning and development club - May 2017, Nottingham
 
Ias11
Ias11Ias11
Ias11
 
Cfr ias 11 construction contract presentation by MOHSIN MUMTAZ
Cfr  ias 11 construction contract presentation by MOHSIN MUMTAZCfr  ias 11 construction contract presentation by MOHSIN MUMTAZ
Cfr ias 11 construction contract presentation by MOHSIN MUMTAZ
 
Ias 11
Ias 11Ias 11
Ias 11
 
Issues in s. 43CA of Income Tax Act
Issues in s. 43CA of Income Tax ActIssues in s. 43CA of Income Tax Act
Issues in s. 43CA of Income Tax Act
 
Bills of quantities
Bills of quantitiesBills of quantities
Bills of quantities
 
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
 
Chapter two.pptx
Chapter two.pptxChapter two.pptx
Chapter two.pptx
 
Seminar Presentation Slides (Chapter 2)
Seminar Presentation Slides (Chapter 2)Seminar Presentation Slides (Chapter 2)
Seminar Presentation Slides (Chapter 2)
 
Public Meeting - Contract Close-Out - Ground Rules
Public Meeting - Contract Close-Out - Ground RulesPublic Meeting - Contract Close-Out - Ground Rules
Public Meeting - Contract Close-Out - Ground Rules
 
Baker Tilly Presents: New to Cost Reimbursement Contracts? Meet Your New Frie...
Baker Tilly Presents: New to Cost Reimbursement Contracts? Meet Your New Frie...Baker Tilly Presents: New to Cost Reimbursement Contracts? Meet Your New Frie...
Baker Tilly Presents: New to Cost Reimbursement Contracts? Meet Your New Frie...
 
The Scoop on the Incurred Cost Submission
The Scoop on the Incurred Cost SubmissionThe Scoop on the Incurred Cost Submission
The Scoop on the Incurred Cost Submission
 
Professional Practice 2: Group Assignment
Professional Practice 2: Group AssignmentProfessional Practice 2: Group Assignment
Professional Practice 2: Group Assignment
 
Core_Services_White Papers Oracle Service PUR.pdf
Core_Services_White Papers Oracle Service PUR.pdfCore_Services_White Papers Oracle Service PUR.pdf
Core_Services_White Papers Oracle Service PUR.pdf
 
Commercial aspects of civil construction
Commercial aspects of civil constructionCommercial aspects of civil construction
Commercial aspects of civil construction
 

Recently uploaded

Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Soumen Santra
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
Vijay Dialani, PhD
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
Kerry Sado
 
Unbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptxUnbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptx
ChristineTorrepenida1
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
WENKENLI1
 
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdfTutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
aqil azizi
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
BrazilAccount1
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
BrazilAccount1
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
Aditya Rajan Patra
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
ClaraZara1
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
SyedAbiiAzazi1
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 

Recently uploaded (20)

Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
 
Unbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptxUnbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptx
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
 
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdfTutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 

SCSI / RICS Presentation on Construction Quantum - Part 1

  • 1. Assessing Quantum in Construction Disputes Contractual Mechanisms and the Courts – Part 1 Mark Wearen MSCSI MRICS MCInstCES MSc October 2015 April 2015
  • 2. April 2015 Assessing Quantum in Construction Disputes Contractual Mechanisms and the Courts What is Quantum ? Context of legal definitions – when do we concern ourselves with such matters ? Contract Forms for Traditional Contracting – PWC/FIDIC/RIAI Key Issues
  • 3. April 2015 Assessing Quantum in Construction Disputes Contractual Mechanisms and the Courts Definition of Quantum ‘a required or allowed amount, especially an amount of money legally payable in damages’* *Oxford Dictionary
  • 4. April 2015 Assessing Quantum in Construction Disputes Contractual Mechanisms and the Courts Definition of Quantum – Construction Context ‘The amount of money sought in respect of any matter which it is alleged gives rise to an entitlement to a payment (for whatever reason) which is additional to the initial contract sum or to the contract sum derived from the rates and prices in the contract’ i.e. not payment for work included in the contract in accordance with the corresponding rates and prices included in the contract.
  • 5. April 2015 Assessing Quantum in Construction Disputes Contractual Mechanisms and the Courts Calculating Quantum – Construction Context • Construction and change go hand in hand – hence the need to include express provisions dealing with change and it’s impacts • Standard forms recognise this and include express provisions to permit change under the contract and to manage that change within the contractual framework – these provisions allocate risk and should simplify dispute resolution • Calculating Quantum should not be a random process – can be governed by the provisions of the Contract and/or applicable Law -not just the applicable Law
  • 6. April 2015 Assessing Quantum in Construction Disputes Contractual Mechanisms and the Courts Calculating Quantum – Construction Context • Express Provisions typically address how change (e.g. additional work or breaches of contract) is to be valued – risk mitigation • Bespoke forms generally mimic the standard forms with risk transfer tailored to suit the bargaining position of the parties and their appetite for risk • Limitations on valuing change can be expressly stated – risk mitigation • How do we ascertain the required or allowed amount ?
  • 7. April 2015 Assessing Quantum in Construction Disputes Contractual Mechanisms and the Courts Quantum – Items to Consider Next Instalment….Part 2 • Damages • Interest and Finance Charges • Acceleration • Quantum Meruit • Causation • Duty to Mitigate • Irish Case Law Today…Part 1 • Valuation Rules • ‘Similar’ – Character and Conditions • BOQ rates as a basis • ‘Reasonable’ • Cost • Fair Valuation • Loss and/or Expense • Overheads and Profit • Substantiation • Limitations Clauses
  • 8. April 2015 Assessing Quantum in Construction Disputes Contractual Mechanisms and the Courts Public Works Contract* - Valuation Rules * Public Works Contract for Building Works Designed by the Employer Document Reference PW-CF1 v.1.10 27 June 2014
  • 9. April 2015 Assessing Quantum in Construction Disputes Contractual Mechanisms and the Courts Public Works Contract – Valuation Rules 10.6.1 Similar work under similar circumstances - use the rates in the pricing document 10.6.2 Not similar work and not under similar circumstances – use the rates in the pricing document as the basis where reasonable If the above rules do not apply…..then 10.6.3 Fair Valuation – to be based on rates for similar work in the locality, If available Or the ER may ‘conclusively direct’ that 10.6.4 Valuation is based on Schedule 2D rates and provisions Time and Materials/Dayworks
  • 10. April 2015 Assessing Quantum in Construction Disputes Contractual Mechanisms and the Courts Public Works Contract – Other Valuation Provisions 10.3.4 Contractor to keep records of ‘costs’ associated with claims 10.7.1 (2) Delay Costs – defined as ‘expenses [excluding profit and loss of profit]’ 10.7.4 Limits recovery for Delay, Disruption, Acceleration, Loss of Productivity, Knock On Effects Claimant must also inter alia…. 10.3.1 (1) Set out ‘relevant facts’ 10.3.1 (2) Provide a proposal ‘so far as is practicable’ and 10.3.3 (3) If ongoing, provide other information the ER ‘reasonably requires’
  • 11. April 2015 Assessing Quantum in Construction Disputes Contractual Mechanisms and the Courts FIDIC Red Book 1999* Clause 12.3 – Valuation Rules * FIDIC Conditions of Contract for Construction for Building and Engineering Works designed by the Contractor 1999 a) For each item of work, the appropriate rate or price specified in the contract shall apply b) If there is no such item in the contract, the rate or price specified in the contract for ‘similar’ work executed under similar conditions shall apply failing which… c) A new rate or price shall apply which shall be ‘derived from any relevant rates or prices in the contract, with reasonable adjustments and… d) If no rates or prices are relevant, new rates and prices shall be based on the reasonable cost of executing the work, together with reasonable profit Clause 13.6 - dayworks ‘for work of a minor or incidental basis’
  • 12. April 2015 Assessing Quantum in Construction Disputes Contractual Mechanisms and the Courts FIDIC Red Book 1999 - Other Valuation Provisions 3.5 In the event that the parties fail to reach agreement on ‘any matter’, the Engineer shall make a ‘fair determination in accordance with the Contract, taking due regard of all relevant circumstances’ 20.1 Contractor to maintain records ‘as may be necessary to substantiate any claim’ and must submit ‘a fully detailed claim which includes full supporting particulars’ • Numerous provisions for recovery of ‘cost’ (e.g. 4.12) • Numerous provisions for ‘cost plus reasonable profit’ (e.g. 4.7)
  • 13. April 2015 Assessing Quantum in Construction Disputes Contractual Mechanisms and the Courts RIAI Contract* – Clause 13 Valuation Rules Valuation rules to apply when valuing variations : a) Bill rates if the additional work is similar in character and carried out under similar conditions, b) Bill rates shall form the basis of the valuation where work is not carried out under similar conditions, ‘so far as may be reasonable’ c) Where no appropriate Bill Rates exist, a ‘Fair Valuation’ shall be made based upon current rates for ‘similar work in the locality’. d) daywork as tendered or SCS/CIF agreement * RIAI Agreement and Schedule of Conditions of Building Contract 2002 (Rev 1 Print 4)
  • 14. April 2015 Assessing Quantum in Construction Disputes Contractual Mechanisms and the Courts RIAI Contract – Other Valuation Provisions Clause 2 Loss and Expense ‘beyond that provided for or reasonably contemplated by this contract’ – limitation (Balfour Beatty v Scottish Power 1994)
  • 15. April 2015 Assessing Quantum in Construction Disputes Contractual Mechanisms and the Courts Valuing Change – Consistency in the Approach across Forms a) Valuation Rules generally apply for valuing variations/compensation events b) Contract Rates and Prices to be utilised – similar works under similar conditions c) Contract Rates form the basis – where reasonable d) Fair Valuation variants – reasonable cost and/or market rates e) Actual Resources utilising defined rates and mark-ups Contracts also allow for recovery of: • Cost • Expense • Loss and Expense
  • 16. April 2015 Assessing Quantum in Construction Disputes Contractual Mechanisms and the Courts Why use the Rules ? • Parties must first look to the Contract to value additional work - If the work meets the definition of a variation or compensation event, the Valuation Rules apply (MT Hojgaard v E.ON 2013) • The rates and prices in the contract are the starting point for valuing additional work – ‘sacrosanct’ (Henry Boot v Alstom 2000; Maeda Corp v Hong Kong 2012) • To move away from the contract rates, establish that work is not similar or is not executed under similar conditions, or is outside the scope of the contract (Costain v Zanen 1996) - thus the application of contract rates would be unreasonable as a basis or in their entirety • Risk Transfer – within the scope of the contract
  • 17. April 2015 Assessing Quantum in Construction Disputes Contractual Mechanisms and the Courts Bill Rates as a Basis (Henry Boot v Alstom 2000 & Maeda Corp v Hong Kong 2011) • Rates are sacrosanct • Only insofar as they apply to similar works executed under similar circumstances • Rates can be opened up and relevant elements changed to produce a new rate based on the contract rates – a ‘star rate’ • Fair Valuation for relevant elements of a contract rate • Not an opportunity to right any wrongs/correct any errors
  • 18. April 2015 Assessing Quantum in Construction Disputes Contractual Mechanisms and the Courts Similar Character and Similar Conditions • The Contract is ‘the means of which the intention of the parties was expressed’. The ‘factual matrix’ within which consideration as to whether or not work was similar or undertaken under similar conditions must be based on the contract (Wates v Bredero Fleet 1993) • Thus the Contractor cannot rely upon information known to him when pricing the project but which is not incorporated into the contract (e.g. the information pack under the Public Works Contract and Clause 1.9.1 – the entire agreement clause) • An ‘ambiguity or peculiarity’ in the wording of the contract may render extrinsic information admissible but only where known to both parties
  • 19. April 2015 Assessing Quantum in Construction Disputes Contractual Mechanisms and the Courts Reasonable and Reasonableness – What is ‘Reasonable’ ? Chitty 31st Edn. 37-101 : ‘a question requiring consideration of all the factors in a particular case’ but ‘no rigid rules apply’ …… ‘cost plus a percentage for profit’ often equates to ’reasonable remuneration’ Keating 9th Edn. 4-001 : Is the reasonable remuneration to be calculated ‘within a contractual framework’ ? Keating 9th Edn. 20-183 : ‘In considering what is reasonable, the Court would have regard to all the circumstances including the terms of the Contract’ – in the context of issuing instructions – why not when calculating quantum ?
  • 20. April 2015 Assessing Quantum in Construction Disputes Contractual Mechanisms and the Courts Reasonable and Reasonableness – What is ‘Reasonable’ ? • Contract conditions should be construed so as to give them the meaning that ‘a reasonable person, having all the background knowledge which would have been available to the parties would have understood them to be using the language in the contract to mean’ (Chartbrook v Persimmon 2009) • What factors determine reasonableness ? • Consideration of relevant information • Within a contractual framework • Opinion is that of a ‘reasonable person’ suitably informed – legal standard • Offer Value for Money and address Obligation to Mitigate • If you want to be ‘unreasonable’, utilise express terms
  • 21. April 2015 Assessing Quantum in Construction Disputes Contractual Mechanisms and the Courts Cost ‘an amount that has to be paid or spent to buy or obtain something’* • Cost under the contract is not an estimate; a quotation; an allowance; an on account sum…..or an amount based on contract rates unless expressly described as such in the contract (selling price) • FIDIC 1.1.4.3 defines cost as ‘expenditure reasonably incurred’ and goes on to state that it includes ‘overheads and similar charges, but does not include profit’ (off site costs included) *Oxford Dictionary
  • 22. April 2015 Assessing Quantum in Construction Disputes Contractual Mechanisms and the Courts Fair Valuation • Where bill rates don’t apply, or it would be unreasonable to use them as a basis for a valuation, a Fair Valuation shall be made…..result is new rates and prices What is a Fair Valuation ? • A fair valuation will ‘ordinarily be based on the reasonable costs of carrying out the work, if reasonably and properly incurred’…thus there is no entitlement to payment for expenditure which ‘would not have been incurred by a reasonably competent Contractor in the same or similar circumstances’ (Weldon Plant v Commissioner for New Towns 2000)
  • 23. April 2015 Assessing Quantum in Construction Disputes Contractual Mechanisms and the Courts Fair Valuation • For a valuation to be ‘fair’, it must contain all the elements ‘ordinarily found in contract rate or price’ – labour/plant/materials/overheads/profit (Weldon Plant v Commissioner for New Towns 2000) • Profit is an integral element of the rates and prices included in the contract and a fair rate would include profit (Semco Salvage v Lancer 1997) • Clause 12.3 of FIDIC – a ‘new rate or price’….based on the ‘reasonable Cost of executing the work, together with reasonable profit, taking account of any other relevant matter’.
  • 24. April 2015 Assessing Quantum in Construction Disputes Contractual Mechanisms and the Courts Fair Valuation • Elements usually found in a contract rate • Can be cost based however….Cost must be reasonable costs – reasonably and properly incurred • PWC – ‘rates for similar work in the locality, if available’ • RIAI – based on current Market Rates but • FIDIC – Based on reasonable cost and reasonable profit • ‘ ”Fair Valuation” will normally mean cost plus a reasonable percentage for profit…with a deduction for any proven inefficiency….but if there is proof of general market rate for comparable work it may be taken into consideration or applied completely’* ….’reasonably and properly incurred cost’ *Max . W. Abrahamson; Engineering Law and the ICE Contracts, 4th Edn.
  • 25. April 2015 Assessing Quantum in Construction Disputes Contractual Mechanisms and the Courts Fair Valuation • Fair to who ? • Cost based – therefore includes risk NOT included for in Contract Rates however must be read in conjunction with the balance of the contract – are the limitations clauses relevant in this context ? • Cost Plus indicative of maximum entitlement…but Market Rate could produce a higher return (Laserbore v Morrison 1993)
  • 26. April 2015 Assessing Quantum in Construction Disputes Contractual Mechanisms and the Courts Loss and/or Expense • Loss and/or damage; Loss and/or Expense – equates to damages in a legal context (Wraight v OH&T Holdings 1968) • Direct loss and /or expense – ‘not merely consequential’ but resulted ‘directly and naturally’ from the breach (Crudace v Cawoods 1978) • In the context of damages, for costs to be recoverable, they must be ‘necessarily and reasonably incurred’ (Floods of Queensferry v Shand 1999) • The term ‘direct’ relates to ‘remoteness’ and not the type of damage (direct v indirect cost) • Limitations clause can provide same effect – FIDIC 17.6 ‘indirect consequential loss or damage’ is not recoverable • Loss of Profit is recoverable (Hotel Services v Hilton 2000; Deepak v ICI 1999)
  • 27. April 2015 Assessing Quantum in Construction Disputes Contractual Mechanisms and the Courts Direct Loss and/or Expense (Robertson v Amey 2005) • Cost and Expense are synonymous • Loss and Losses are synonymous • Direct = Remoteness not causation • ‘Direct’ and ‘Directly Incurred’ = Arising Naturally (must flow naturally from the event) • Direct Loss and/or Expense – Indirect Loss and/or Expense is not recoverable (2nd limb of Hadley v Baxendale) • Failure to make a profit due to an entitlement event = a loss
  • 28. April 2015 Assessing Quantum in Construction Disputes Contractual Mechanisms and the Courts Overheads and Profit (Lilly v Mackay 2012) • Judge considered previous case law and ruled : ‘A contractor can recover head office overheads and profit lost as a result of delay on a construction project caused by factors which entitle it to loss and expense’ ‘It is necessary for the contractor to prove on a balance of probabilities that if the delay had not occurred, it would have secured work on projects which would have produced a return (over and above costs) representing a profit and/or contribution to head office overheads’ ‘The use of a formula, such as Emden or Hudson, is a legitimate and indeed helpful way of ascertaining, on a balance of probabilities, what that return can be calculated to be’
  • 29. April 2015 Assessing Quantum in Construction Disputes Contractual Mechanisms and the Courts Substantiation • Obligation to prove to the Court that the amount being claimed is appropriate • Plaintiff obliged to provide ‘such particularity’ as required to inform the Respondent of the case being made (Wharf Properties v Cumine 1991) • ‘Strict Proof’ not required in construction litigation – Court recognises that there is an ‘acceptable margin of error’ and that the use of resources to enhance detail to a negligible degree is unnecessary as it is ‘misleading as to an exactitude’ which is not attainable in construction litigation (Ascon v McAlpine 1999) • In the ‘absence of detailed evidence’, the Court will seek to assess the appropriate quantum ‘on the balance of probabilities’….’albeit based on the minimum probability so attributable’ (CBUK v SRS 2012; also Robertson v Amey 2005)
  • 30. April 2015 Assessing Quantum in Construction Disputes Contractual Mechanisms and the Courts Substantiation • Where loss is proved to have occurred, and the Claimant has used his best endeavours to assist the Court, quantum assessment will not be denied ‘for want of fine detail’* • However the Court may dismiss the Claim where the Claimant has not helped himself or the Court – the Court will not make the Claimant’s case and if the case is not pleaded on the available information, the case may be dismissed • Causation is a pre-requisite to entitlement – link the impact to the cause (Holland v Kvaerner 1996) *Ennis & Breyer; SCL Paper D162 Para 4.19
  • 31. April 2015 Assessing Quantum in Construction Disputes Contractual Mechanisms and the Courts Substantiation • Under Clause 4.23 of the JCT, the Contractor is obliged to submit such information ‘as should reasonably enable the Architect/Contract Administrator to form an opinion’ and ‘details of such loss and/or expense as are reasonably necessary for such ascertainment’ • ‘the Architect and the Quantity Surveyor are not strangers to the project in considering what needs to be provided to them’ (Lilly v Mackay 2012) • Even if Contract Terms are perceived as being more onerous, it is likely the Courts will follow CBUK v SRS 2012 & Lilly Mackay 2012 • Front Line Factual Information produces the most compelling case
  • 32. April 2015 Assessing Quantum in Construction Disputes Contractual Mechanisms and the Courts LIMITATIONS CLAUSES – Impact on Quantum • PWC Compensation Events Definition – Disruption Excluded • FIDIC Clause 17.6 excludes entitlement to consequential or indirect loss or damage (Hedley v Baxendale 1854 – first limb) • RIAI Clause 2 – Loss and Expense…within reasonable contemplation (Balfour Beatty v Scottish Power 1994)
  • 33. April 2015 Assessing Quantum in Construction Disputes Contractual Mechanisms and the Courts Context of legal interpretations – when should we concern ourselves with such matters ? • Preparation of Tender/Contract Documents Drafting Contract Conditions & BOQ Prep • Contract Administration • Risk Assessment/Claims Risk Assessment • Disputes ….all the time ! GCCC Review – BOQ Status ; Single Person DAB €10m+
  • 34. April 2015 Assessing Quantum in Construction Disputes Contractual Mechanisms and the Courts Whilst general principles/legal doctrine exists which may provide guidance, every case must be considered on it’s own merits and particular circumstances If in doubt and stakes are high…consult your Lawyer….. and your QS
  • 35. Assessing Quantum in Construction Disputes Contractual Mechanisms and the Courts Thank You For Case Law….go to http://www.bailii.org/ http://www.irlii.org Mark Wearen MSCSI MRICS MCInstCES MSc October 2015 April 2015