SlideShare a Scribd company logo
Supply Chain Development
Management of Change Under the NEC 3
Stuart Brisbane(CFW Consultant)
21st Sept 2017
The Vale Hotel - Hensol
Agenda
1. Overview
2. Early Warnings
3. Compensation Events
• Clause 60 (Definition)
• Clause 61 ( Notification)
• Clause 62 (Quotation)
• Clauses 63 & 64 (Assessment)
• Clause 65 (implementation)
4. Some Points to Note
5. Recap
1. Overview
1. Overview
1. Overview
1. Overview
NEC3 Suite of Contracts
• Works
• Engineering and Construction Contract (ECC)
• Engineering and Construction Short Contract (ECSC)
• Engineering and Construction Subcontract (ECS)
• Engineering and Construction Short Subcontract (ECSS)
• Services
• Professional Services Contract (PSC) – Architecture, Engineering
• Term Service Contract (TSC) – Maintenance, Management
• Term Service Short Contract (TSSC)
• Supply
• Supply Contract (SC) – Goods, Products
• Supply Short Contract (SSC)
• Others
• Adjudicator’s Contract (AC), Framework Contract (FC)
1. Overview
NEC4 Suite of Contracts
1. Overview
NEC4 Suite of Contracts
1. Overview
The brand new NEC4 Design Build and
Operate Contract (DBO) allows Clients to
procure a more integrated whole-life
delivery solution. It reflects the increasing
demand for contracts extending into the
operational phase.
NEC4 Suite of Contracts
1. Overview
1. Overview
NEC3 Suite of Contracts
1. Overview
Core & Main Option Clauses
• The Core Clauses are set out in nine sections and apply in all
contracts. The clauses allow for a flexible amount of Contractor
design.
• Section 1: General
• Section 2: The Contractor’s Main Responsibilities
• Section 3: Time
• Section 4: Testing and Defects
• Section 5: Payment
• Section 6: Compensation Events
• Section 7: Title
• Section 8: Risk and Insurance
• Section 9: Dispute and Termination
• The Main Option Clauses provide two options for the dispute
resolution procedure.
• Option W1: Used unless the HGCRA 1996 applies.
• Option W2: Used in the UK when the HGCRA 1996 applies.
1. Overview
Cost Components & Contract Data
• The Cost Components are two schedules which contain cost information
supplied by the Contractor. They are used to assess payments to the
Contractor and the cost effect of Compensation Events. Costs are defined in
relation to people, equipment, plant and machinery, utility charges,
manufacture and fabrication, design and insurance.
• Known as the ‘Contract Particulars’ under JCT, the Contract Data provides
data required by the specific conditions of the contract. The section is split
into two parts
• Part 1 - Data provided by the Employer
• Part 2 – Data provided by the Contractor. Information includes...
• Name of Parties
• Insurance Details
• Start and Completion Dates
• Interest Rates
• Retention Percentage if applicable
• Rates for Delay Damages if applicable
1. Overview
Works and Site Information
• The Works Information specifies and describes the Works to be carried
out, including Contractor’s design responsibilities. Most information will be
given in a specification and on production drawings in the traditional
manner. However, it may also include…
• Statement of Constraints on how works are carried out
• Health and Safety
• Details of Contractor’s Design elements
• Information on Specialist Subcontractors
• Details of Tests
• Performance or Advance Payment Bonds
• The Site Information describes the site and its surroundings and is used
to assess compensation for site conditions. Information may include soil
investigations, contamination reports and details of below ground
services.
1. Overview
Managing Change
• NEC3 includes a clause which obliges the Contractor and
Project Manager to notify each other as soon as they become
aware of any matter which could increase the Prices or delay
Completion. This is called an Early Warning.
• Under the JCT Type, the procedure for managing change is
known as ‘Variations’. A Contractor’s Schedule 2 Quotation can
be used to obtain a fixed price quotation for a variation.
However, it is not mandatory and typically responsibility lies with
the QS to price variations. Disputes can arise and are often not
resolved quickly.
• Under the NEC3, the procedure is known as ‘Compensation
Events’ and an immediate assessment of the cost and time
implications are made. These are mandatory and binding, with
no provision for later review. They are events which do not
arise from the Contractor’s fault and entitle the Contractor to be
compensated for any effect the event has on the Prices and
Dates.
Compensation Events
are listed in the Core
Clauses and the
Options. The Contract
Data also has
provision for the
Employer to insert their
own additional
compensation events.
1. Overview
1. Overview
Terms in italics are project specific
Defined terms have capital initials
These drafting principles make it easier to understand the contract
These principles should be adhered to when drafting documents & communicating
Clause 11.1:
Terms identified in the Contract Data are in italics e.g.. Period for reply, boundaries of
the site
Defined terms have capital initials, e.g. Accepted Programme, Completion, Defect
The index is useful to refer to as it details the links within the contract – it helps
build the intellectual map
• There are 19 defined terms relevant to the core
clauses
• These are in alphabetic order
• Additional defined terms exist dependent upon the:
– Main Options
– Secondary Options
1. Overview
Clause Defined term & comment Linkage
11.2(1) Accepted Programme – latest Accepted Programme supersedes
previous. Vital to have an Accepted Programme in place for the good of
the project
31.3, 50.3
(remedy)
11.2(2) Completion – the second bullet serves as a basic filter, the first bullet
allows the Employer to be very precise
X7.1 (remedy)
11.2(9) Key Date – critical milestone from the Employer’s perspective, often
reflects interface between the Contractor and Others
14.3 (alter),
25.3 (remedy)
11.2(14) Risk Register – consists of risks identified as part of the tender process
plus early warnings
Contract
Data, 16.4
11.2(16) Site Information – factual information about the site 60.1(12),
60.2, 60.3
11.2(18) Working Areas – necessary for Providing the Works & used only for
work on this contract
15.1, SCC,
SSCC
11.2(19) Works Information – specifies and describes the works or any
constraints
14.3, 60.1(1)
Some Defined Terms and Basic Contract Linkages
1. Overview
Clause Defined term & comment
Main Option A,
11.2(20)
Activity Schedule (note the sequential clause numbering)
Main Option A,
11.2(27)
Price for Work Done to Date (PWDD) – completed activities
Main Option B,
11.2(28)
Price for Work Done to Date (PWDD) – bill items
Main Option C,
11.2(23)
Defined Cost – definition of what is paid for under Options C-F
Main Option C,
11.2(25)
Disallowed Cost – definition of what is not paid under Options C-F
X5.1 Sectional Completion – references equally apply to Sectional
Completion eg clause 16.1
1. Overview
Some Defined Terms and Basic Contract Linkages
Key People
• The ECC sets out the responsibilities and roles of the following key
people:
• Employer
Not involved in administrating the contract – no power to issue instructions.
• Project Manager
Known as the ‘Contract Administrator’ under the JCT, the Project Manager manages
procurement of the Works for the Employer. Contract contemplates appointment prior to
the Consultants so that they manage the design process.
• Supervisor
Known as the ‘Clerk of Works’ under the JCT, the Supervisor exercises certain
responsibilities on site for the Employer, including testing, monitoring quality and issuing
the Defects Certificate.
• Contractor
• Subcontractors
• Adjudicator
• Note, no references to an Architect or QS by profession.
Unless delegated the
role or responsibility, the
Architect who produced
the Works Information,
may not have a role in
the Contract and
therefore have no
responsibility to monitor
quality and compliance
with the Works
Information. The
Supervisor may have
limited knowledge of the
Works Information and
this may affect the
quality of the completed
building. Traditionally as
Contract Administration,
the Architect has a
responsibility to monitor
quality.
1. Overview
1. Overview
1. Overview
Communication protocol: Clause 13.1
• Clause 13.1 clearly states the methods of communication which the contract requires in a form that can be
read, copied and recorded
• The contract requires professional record keeping
• The Project Manager should discuss and agree with the Contractor which method(s) of communication
will be used at commencement of the contract
• The NEC published guidance on communication in April 2013
• Good examples and suggestions are contained within this guidance
1. Overview
• As a minimum, the ECC pro-forma’s are recommended as the means of communicating
• They state the relevant clause
• The communications are structured
• This is not being contractual – it’s following what the contract requires (‘acting as stated’)
Communication protocol: Clause 13.7
• ‘Notified’ matters need to be communicated separately!
• Each early warning should be notified separately
• Each defect should be notified separately
• Each compensation event should be notified separately
1. Overview
Full list of notifications under the ECC (clause 13.7)
Clause Issue
14.2 Delegation
14.4 Replacement of the PM or Supervisor
16.1 Early Warning
17.1 Ambiguities and inconsistencies
18.1 Illegal or impossible requirements
31.3 Programmes
40.3 Tests and inspections
42.2 Defects
61.1 Compensation Events
61.3 Compensation Events
61.4 Compensation Events
61.5 Decisions on Compensation Events
61.6 Assumptions on Compensation Events
62.6 Quotations for Compensation Events
64.3 Assessments of Compensation Events
64.4 Late assessment of Compensation Events
65.1 Implementation of Compensation Events
73.1 Discovery of objects of value etc
1. Overview
• The Contract Data ‘refers’ to the documents
which contain the Works Information.
– Contract Data Part 1 identifies the Employer’s
Works Information
– Contract Data Part 2 identifies the Contractor’s
Works Information for his design
1. Overview
• What happens if there are inconsistencies between
the Works Information provided by the Contractor
(for his design) and that provided by the Employer?
Clause 17.1
notify
Clause 14.3
Ability to
change
Clause
60.1(1),
Second bullet
Changing the Contractor’s WI to comply with the Employer’s is not a
compensation event. In that respect, the Employer’s WI is dominant
1. Overview
• What happens if the Employer’s WI contains
inconsistencies in drafting and/or is
ambiguous?
Clause 17.1,
Notify
Clause 14.3 –
ability to
change
Clause 63.8,
Employer
pays
The Employer compensates the Contractor for any inconsistency or ambiguity
1. Overview
TELEVISIONS – 42” or 24” – 63X £127.99 = £8063.37
• The Risk Register is a new feature under NEC3.
• It is a live document that is formed by the Project Team post-contract (i.e. not a
contract document) and will change as the work progresses.
• Risks can be added to the Register as part of the Early Warning process, or
removed because of actions taken by the parties (i.e. soil investigations).
• Risks are allocated a likelihood of occurrence and impact, along with an
approximate cost effect. Regular Risk Reduction Meetings should be held during
the Contract.
1. Overview
1. Overview
• Clause 80.1 defines the Employers Risks under the contract
• Clause 81.1 sets out that all other risks are carried by the Contractor.
• Clause 83 each party indemnifies the other against events which are at its risk
• Often ITT’s are including preliminary risk registers to help prospective contractors understand what
getting into.
• Risk Registers are a practical project management tool , time or cost consequences should fall
outside of clause 83 and be addressed through other mechanisms (CE’s) Parties need to be very
clear as to how any such risks are allocated.
• Recent difficulties around final entry clause 80.1 which allows additional Employers risks to be
specified in the Contract Data in order to include a preliminary risk register .
• Employer will often append or refer to the risk register in the contact data and if that register
assigns actions to the employer could be argued that they become part of 80.1
• Broad consensus that risk register operates at a practical level and not intended to alter 80.1 and
81.1 however still limited case law and remains uncertainty.
• Prudent for clarity to amend the contract that items in the risk register are not employers risks.
• Under the JCT Types, the Contractor is required to submit a Programme but
it is not a binding Contract Document and there is no requirement to keep it
up to date.
• In contrast, the Accepted Programme forms part of the Contract Data under
the NEC3 and the Contractor is required to keep it up to date. Any changes
must be accepted by the Project Manager within 2 weeks. It is an important
document and is used to monitor/assess the time effects of Compensation
Events.
Programme should show…
• Start Date/Completion Date/Key Dates
• Planned Completion
• Order and Timing of Operations
• Time Risk Allowances
• Health and Safety Requirements
• Information from Required Others
• Float
1. Overview
• The programme is key – it’s the ‘beating heart’ of the NEC
• The NEC programme is a joint programme
• It provides critical management data
• If the programme is not compliant/accepted it becomes
very difficult to objectively assess compensation events
• In order to ensure acceptance it is worthwhile considering a
joint review before final submission/acceptance
1. Overview
1. Overview
2. Early Warning
• Early Warnings are very important part of NEC
• They are about identifying potential problems before they occur
with a view to avoidance or mitigation
• Designed to avoid waiting until they have happened and seeking to
apportion blame
• There is no entitlement under Early Warnings
• They should not be viewed as claims however if not given or given
and ignored have consequences
• Under Clause 16.1 Contractor or PM can issue
• Consequences if Contractor not issued when could have – under
options C-F could be disallowed costs
• Clause 16.2 gives rights to PM or Contractor to Instruct attendance
at risk reduction meeting.
• Issue of EW entails PM must add to the Risk Register
• All about encouraging proactive and collaborative working
2. Early Warning
Full list of notifications under the ECC (clause 13.7)
Clause Issue
14.2 Delegation
14.4 Replacement of the PM or Supervisor
16.1 Early Warning
17.1 Ambiguities and inconsistencies
18.1 Illegal or impossible requirements
31.3 Programmes
40.3 Tests and inspections
42.2 Defects
61.1 Compensation Events
61.3 Compensation Events
61.4 Compensation Events
61.5 Decisions on Compensation Events
61.6 Assumptions on Compensation Events
62.6 Quotations for Compensation Events
64.3 Assessments of Compensation Events
64.4 Late assessment of Compensation Events
65.1 Implementation of Compensation Events
73.1 Discovery of objects of value etc
1. Overview
The early warning process:
2. Early Warning
The early warning process
• The Project Manager should facilitate and
trouble shoot the process
• This is not about casting blame
• Its about mature project management –
recognising that both parties will encounter
problems
• Its about overcoming them collaboratively
3. Early Warning
The early warning process:
•‘Notify’ – separately
(13.7)
•4 reasons
•5th reason is
discretionary
•Protecting time,
quality and cost
16.1 Notify
•May instruct others
to attend
16.2 Instruct a
meeting
•How to avoid or
reduce
•Seek solutions
•Decide on actions
•Update
16.3 Mitigate
•Revise
•Issue to the
Contractor
16.4 Update
and issue
2. Early Warning
The early warning process:
2. Early Warning
The early warning process:
•‘Notify’ – separately
(13.7)
•4 reasons
•5th reason is
discretionary
•Protecting time,
quality and cost
16.1 Notify
•May instruct others
to attend
16.2 Instruct a
meeting
•How to avoid or
reduce
•Seek solutions
•Decide on actions
•Update
16.3 Mitigate
•Revise
•Issue to the
Contractor
16.4 Update
and issue
2. Early Warning
The early warning process:
2. Early Warning
Impact if we don’t manage Early Warnings:
Clause 16.1
Notify (separate
communication:
clause 13.7)
The Prices
Clause 63.5: “…event is
assessed as if the
Contractor had given
early warning”
Disallowed Cost
Clause 11.2 (25)*….was
incurred only because the
Contractor did not ….give
an early warning….
Options A-F
Options C-F
Under Options C-F failure to notify early warnings can have a detrimental effect on the Prices (value)
and Defined Cost (cost)
*11.2(26) under Option F
3. Early Warning
The early warning process:
2. Early Warning
Options A-F
The early warning process:
2. Early Warning
Options C-F
Core clauses General 11.2
2. Early Warning
Implementing the key
procedures: Early warnings
Procedures in contract
• Risk Register to be compiled by the
Project Manager
• Each early warning to be notified
and recorded in the Risk Register
• Mitigation & risk reduction to be
undertaken as per clause 16.3
Practical suggestions
• Ensure the ethos is right within the team
– early warnings are not a pre-empt to a
claim!
• Develop the Risk Register from the
tender process
• Consider a protocol of picking up the
phone and discussing initially. If both
parties agree/one feels strongly then
follow through with the paperwork?
• Ensure dialogue is maintained
• Consider a categorisation system eg. category 1 = critical (meet in the next 24 hours),
category 2 = non-critical (record and discuss at the next progress meeting)
2. Early Warning
2. Early Warning
HANDOUT 1
2. Early Warning
HANDOUT 2
2. Early Warning
HANDOUT 3
3. Compensation Events
4. Compensation Events
Compensation events are defined as events which if they do not arise from
Contractors fault, entitle Contractor to be compensated for effect on the
Prices, Key Dates and Completion Date
Therefore it is important to remember that compensation events deal with both time
and money
What is a compensation event?
• Events which entitle the Contractor to be compensated for
the effect on the Prices, Key Dates and Completion Date
• Both time & cost are assessed in a single quotation
• Some compensation events may be negative e.g. omit work
from the Works Information (this will have a negative impact
on the Prices but will not bring forward the Completion
Date)
• This section rewrites the traditional rule book in terms of
change management
 Clearly defined timescales are in place
 Failure to comply with these timescales can result in the
Contractor being time barred
The timescales are clearly defined with sanctions in place for those that do not
follow the process!
3. Compensation Events
What is a compensation event?
• Compensation Events are the ONLY way to
change price / and or Completion Date
• All in one place and treated in the same way
• Cost assessed at forecast change in cost
• Time forecast delay based on latest Accepted
Programme
• All to tight and defined timescale
3. Compensation Events
1. Overview
Core & Main Option Clauses
• The Core Clauses are set out in nine sections and apply in all
contracts. The clauses allow for a flexible amount of Contractor
design.
• Section 1: General
• Section 2: The Contractor’s Main Responsibilities
• Section 3: Time
• Section 4: Testing and Defects
• Section 5: Payment
• Section 6: Compensation Events
• Section 7: Title
• Section 8: Risk and Insurance
• Section 9: Dispute and Termination
• The Main Option Clauses provide two options for the dispute
resolution procedure.
• Option W1: Used unless the HGCRA 1996 applies.
• Option W2: Used in the UK when the HGCRA 1996 applies.
1. Overview
The compensation event process – Overview:
• The compensation event process is clearly defined
• Section 6 is divided into 5 main sections: Define,Notify,
Quote, Assess, Implement
• Timescales are in place with sanctions for either party
if they are not followed
• The timescales are about agreeing the impact not
when the work is done
• Both time and cost are assessed
• There is no separate prolongation/extension of time
4. Compensation Events
The compensation event process – Overview:
3. Compensation Events
• There is a defined process to agree (or impose)
the effects of a compensation event
• Within defined time limits
• Definition (60)
• Notification (61)
• Quotation (62)
• Assessment (63/64)
• Implementation (65)
• Either Party can make sure that process and time
scales are adhered to
What are the reasons for a compensation event?
• There are three main reasons:
• A change of mind/decision
• Failure to do something (a lot relate back to the programme)
• Something has happened that is beyond a reasonable risk
3. Compensation Events
Where are they listed?
• There are four sources of compensation events:
• Clause 60.1 (19 reasons)
• A further 3 stated in clauses 60.4, 60.5 & 60.6 (Options B & D)
• Also secondary Options X2, X12.3(6) & (7), X14.2, X15.2 &
Y2.4
• Potentially additional compensation events in Option Z
• NEC 4 also introducing a new category for introduction of
client specific CE’s
4. Compensation Events
Lots of Effort !!!
• Many find the Compensation Event process particularly
challenging.
• Need to consider that the conventional contracts have not
avoided the need to manage change, in fact most simply
push much of the work to the post completion phase
resulting in delays , debates, and extended payments.
• NEC3 requires contemporaneous change management and
the increased effort should be rewarded by the whole
project team having greater certainty of outcome and
avoidance of post – completion disputes.
4. Compensation Events
4. Compensation Events
3. Compensation Events
Definition of
Compensation events
Clause 60
3. Compensation Events
3. Compensation Events
60. Definition
Essentially is the list of items which are
compensation events under the contract.
The first step in administering the
Compensation Event process is a simple
initial check as to what is / has / could be
happening on the project against that list.
Summary of the compensation event clauses
Clause Description Relevant Clauses
60.1(1) Change to the Works Information 14.3, 27.3 & 44
60.1(2) Access and use of the site 33.1
60.1(3) Employer providing something 31.2
60.1(4) Stop or not start any work 34.1
60.1(5) Employer and Others working times and conditions 31.2
60.1(6) Replying to communications 13.3
60.1(7) Object of value 73.1
60.1(8) Changing decisions -
60.1(9) Withholding acceptance 13.8, 13.4, 24.1,31.3
60.1(10) Instructions to search 42.1
60.1(11) Test or inspection causing delay 40.5
60.1(12) Physical conditions 60.2 & 60.3
60.1(13) Weather -
60.1(14) Employer’s risk 80.1
60.1(15) Take over 35.2
60.1(16) Employer provides materials, facilities and samples 40.2
60.1(17) Correction to an assumption 61.6
60.1(18) Breach of contract -
60.1(19) Unforeseen events 19.1
3. Compensation Events
3. Compensation Events
3. Compensation Events
Compensation event clauses
3. Compensation Events
3. Compensation Events
Compensation event clauses
3. Compensation Events
Compensation event clauses
3. Compensation Events
Compensation event clauses
3. Compensation Events
Compensation event clauses
3. Compensation Events
Compensation event clauses
3. Compensation Events
3. Compensation Events
3. Compensation Events
3. Compensation Events
Compensation event clauses
3. Compensation Events
Compensation event clauses
3. Compensation Events
Compensation event clauses
3. Compensation Events
Compensation event clauses
3. Compensation Events
Compensation event clauses
3. Compensation Events
Compensation event clauses
3. Compensation Events
Compensation event clauses
NEC 4 – adding compensation Events
Compensation events - Additional compensation events
may now be added by the Client in the Contract Data Part
One.
Compensation events - A new compensation has also
been added, in the core clauses, entitling the Contractor to
claim for preparing quotations for a proposed instruction
which are not accepted by the Project Manager.
Notification of
Compensation events
Clause 61
3. Compensation Events
3. Compensation Events
61. Notification
There is a reciprocal duty for the Contractor
and the Project Manager to notify each
other of any Compensation Event they
become aware of.
The details of these obligations are set out
in core clause 61.
3. Compensation Events
3. Compensation Events
3. Compensation Events
3. Compensation Events
3. Compensation Events
3. Compensation Events
3. Compensation Events
Notification of Compensation Events
3. Compensation Events
3. Compensation Events
Both Parties have a responsibility to Inform and manage
Many PM’s and majority of contractors need to consider.
The 8 week time barring period does not apply to
compensation events that the project manager should
have notified , in which case the contractor has long as he
wishes to notify up to defects date.
For that reason it is in the Employers best interests for the
Project Manager to notify compensation events in order to start
the procedural clock ticking
Notification of Compensation Events
3. Compensation Events
3. Compensation Events
Notification of Compensation Events
Beware contract
amendments
and Z Clauses
Options A-F
3. Compensation Events
Notification of Compensation Events
3. Compensation Events
Notification of Compensation Events
Quotations for
Compensation Events
Clause 62
3. Compensation Events
3. Compensation Events
62. Quotations
The Project Manager must instruct the contractor to prepare a quotation , or
alternative quotations when a Compensation Event is instigated on behalf of the
Employer.
A decision to instruct will depend on the outcome of the quotation.
The Project Manager must also instruct the contractor to prepare quotations for
any other Compensation Event.
The timeframe both for the contractor to submit a quotation and for the Project
Manager to reply are prescriptive.
Timescales can be altered by agreement between the Contractor and the Project
manager although such agreements should be based on genuine necessity.
Quotations for compensation Events
3. Compensation Events
3. Compensation Events
3. Compensation Events
3. Compensation Events
3. Compensation Events
3. Compensation Events
Assessing Compensation
Events
Clause 63
3. Compensation Events
3. Compensation Events
63 & 64 Assessing
Compensation Events are assessed relative to Defined Costs and accepted
Program.
Quotations deal with both Time & Money
The Project Manager must instruct the contractor to prepare a quotation , or
alternative quotations when a Compensation Event is instigated on behalf of the
Employer.
Core Clause 63 details the provisions that must be followed by the contractor.
There are circumstances in which the Project manager must assess a
compensation Event and these are governed by the detailed provisions set out in
Core Clause 64.
Assessing Compensation Events
3. Compensation Events
Assessing Compensation Events
3. Compensation Events
3. Compensation Events
3. Compensation Events
3. Compensation Events
3. Compensation Events
3. Compensation Events
3. Compensation Events
3. Compensation Events
Project Managers
Assessment of
Compensation Events
Clause 64
3. Compensation Events
3. Compensation Events
63 & 64 Assessing
Compensation Events are assessed relative to Defined Costs and accepted
Program.
Quotations deal with both Time & Money
The Project Manager must instruct the contractor to prepare a quotation , or
alternative quotations when a Compensation Event is instigated on behalf of the
Employer.
Core Clause 63 details the provisions that must be followed by the contractor.
There are circumstances in which the Project manager must assess a
compensation Event and these are governed by the detailed provisions set out
in Core Clause 64.
Project Managers Assessment of Compensation Events
3. Compensation Events
3. Compensation Events
3. Compensation Events
3. Compensation Events
3. Compensation Events
3. Compensation Events
3. Compensation Events
3. Compensation Events
3. Compensation Events
3. Compensation Events
Implementing
Compensation Events
Clause 65
3. Compensation Events
3. Compensation Events
65 Implementing
Compensation Events are implemented when their time and money are fixed.
These implications are fixed once and once only and not revisited even in the
context for a prediction subsequently not transpiring
Time and money are inextricably linked through the Programme and the Defined
Cost.
Implementing Compensation Events
3. Compensation Events
3. Compensation Events
Time Barring
3. Compensation Events
The compensation event procedure includes temporal obligations with respect to change
management that are both reciprocal and onerous.
The potential time and money rights of the parties in relation to change can be time-barred if the
contractual timescales are not followed. Specifically, if the following actions which confer those
time and money rights are not taken within the specified time periods, then those rights are
extinguished:
• The Contractor must notify a compensation event within eight weeks of becoming aware of it
– it is a large carrot to notify a compensation event on time if the right to it can be extinguished
after eight weeks.
• The Project Manager must notify the Contractor within two weeks of receipt if any event is
considered not to be a compensation event – it is an equally large carrot to check a compensation
event on time if it is deemed to be accepted after two weeks by default, i.e. if it is not proactively
rejected if it is considered accepted.
The purpose of such time-barring is to effectively incentivise the parties to perform efficiently and
deal with compensation events as they arise. This is a critically important objective of NEC3 in
dealing with change contemporaneously and not leaving it for a final account debate.
3. Compensation Events
HANDOUT 4
Agree to meet regularly & maintain dialogue
3. Compensation Events
Consider the contractual loop / Genuine need for Alterations to the periods –
And KEEP YOUR CLIENT INFORMED
Implementing the key procedures:
Compensation events
Procedures in contract
• Clear timescales and procedures
detailed in section 6
• Both parties may ultimately be time
barred if they fail to follow the
timescales
Practical suggestions
• Meet to discuss appropriate
compensation events before final
submission
• Discuss any issues – the aim is to
informally agree before formal
submission
Agree to meet regularly & maintain dialogue
3. Compensation Events
3. Compensation Events
HANDOUT 5
3. Compensation Events
HANDOUT 6
3. Compensation Events
HANDOUT 7
Some Points to Note
3. Compensation Events
• Clause 80.1 defines the Employers Risks under the contract
• Clause 81.1 sets out that all other risks are carried by the Contractor.
• Clause 83 each party indemnifies the other against events which are at its risk
• Often ITT’s are including preliminary risk registers to help prospective contractors understand what
getting into.
• Risk Registers are a practical project management tool , time or cost consequences should fall
outside of clause 83 and be addressed through other mechanisms (CE’s) Parties need to be very
clear as to how any such risks are allocated.
• Recent difficulties around the final entry clause 80.1 which allows additional Employers risks to be
specified in the Contract Data in order to include a preliminary risk register .
• Employer will often append or refer to the risk register in the contact data and if that register
assigns actions to the employer could be argued that they become part of 80.1
• Broad consensus that risk register operates at a practical level and not intended to alter 80.1 and
81.1 however still limited case law and remains uncertainty.
• Prudent for clarity to amend the contract that items in the risk register are not employers risks.
4. Points to Note
4. Points to Note
Key risks – physical conditions:
• Physical conditions (clause 60.1(12)) are a compensation event if they are over and
above the defined risk:
• …… an experienced Contractor ….. such a small chance of occurring
……unreasonable for him to have allowed for it
• When ‘judging’ if it is a compensation event – clause 60.2 lists what the Contractor
is deemed to have taken account of
The Contractor needs to take account of the risks which are within the parameters of this
definition
On most projects this represents a significant risk
Example: A new housing development on a disused hospital site: Discovery of a redundant
drain and telephone cables in different places to those shown on drawings is unlikely to be a
compensation event (?)
4. Points to Note
4. Points to Note
Check the Z clauses – Advice is to minimise however increasingly seen used
• Introduction of Provisional Sums
• Significantly altering of periods (4 weeks to become time barred)
Note that clause 26.3 sets out the reasons why the Project manager might reject
a subcontractor.
The use of any other reason would potentially trigger a compensation event as
clause 60.1(9)
So Project Managers must tread carefully when considering such matters.
And as later note that Welsh LA have added further reasons via the
amendment of a core clause rather than adding a Z clause.
4. Points to Note
Consider the final part of clause 26.2 the Contractor is prohibited from appointing a
proposed subcontractor until the Project Manager has accepted that subcontractor.
Contractor’s should be aware of this prohibition as at clause 91.2 the appointment
of a subcontractor for substantial work before the Project Manager has accepted the
subcontractor is Reason 13 of the reasons allowing the Employer to terminate the
Contract.
The only point for debate in respect of this reason is what is substantial work as
opposed to unsubstantial work.
4. Points to Note
4. Points to Note
Recommendations are to keep Z clauses to the minimum
Government and NEC Guidelines available which detail and
suggest reasonable and some of the more common uses of Z
clauses – such as compliance with Official Secrets act.
Review of this Contract discovered significant amendments to
and introduction of new core clauses (Just on compensation
events)adds to 60.1(10), removes 60.1(12),60.1(19), 60.2, 60.3
adds 60.4 (confirms contractors risks on risk register not CE’s) and
60.5 liability under common law relating to compensation events.
Recent works with Welsh Contractor reviewing NEC framework
Documents issued by Local Authority
4. Points to Note
Inclusion of 33 Z Clauses – covering such items as
Recent works with Welsh Contractor reviewing NEC framework
Documents issued by Local Authority
Contractors obligations for Security Waste Management & WRAP
Confidentiality and FOIA & EIR Quality and Quality plans
Publicity & Advertising Preliminaries and Value Engineering
Guarantees / Warranties / Insurances Provisional Sums
Community Benefits Welsh Language
BREEAM & EPC CDM
Discrimination Recycling
BIM & Soft Landings Considerate Constructors
Data Protection
Recent works with Welsh Contractor reviewing NEC framework
Documents issued by Local Authority
4. Points to Note
LA’s added and amended the core NEC 3 clauses – in this case adding Disallowed costs
into an Option A contract !!
Significant risks of introducing confusion – NEC3 is a set of standard procedures and
processes with supply chain contracts designed to be back to back.
Changes should be via Z clauses
4. Points to Note
Is it really the
LA’s intention
to pass
obligations
down the
entire supply
chain
Recent works with Welsh Contractor reviewing NEC framework
Documents issued by Local Authority
4. Points to Note
LA’s added reasons why the Project manager is able to reject a proposed sub contractor –
Again need to be commercially aware of potential ramifications
Recent works with Welsh Contractor reviewing NEC framework
Documents issued by Local Authority
4. Points to Note
Consider how you might need to add into supply chain agreements – use of vesting
certificates ? – Protect your liability?
Recent works with Welsh Contractor reviewing NEC framework
Documents issued by Local Authority
4. Points to Note
Consider how you might need to add into supply chain agreements – and manage the
payment process to protect cashflow
Recent works with Welsh Contractor reviewing NEC framework
Documents issued by Local Authority
4. Points to Note
Consider how you might need to add into supply chain agreements in relation to
Compensation Events.
Recent works with Welsh Contractor reviewing NEC framework
Documents issued by Local Authority
4. Points to Note
LA’s intention being to pass obligations down
the entire supply chain. Contractors involved
in such Frameworks need to consider the
practicalities of actually being able to pass
these onto their supply chain / or take an
informed commercial risk.
Recent works with Welsh Contractor reviewing NEC framework
Documents issued by Local Authority
Recap
1. Overview
2. Early Warnings
3. Compensation Events
• Clause 60 (Definition)
• Clause 61 ( Notification)
• Clause 62 (Quotation)
• Clauses 63 & 64 (Assessment)
• Clause 65 (implementation)
4. Some Points to Note
5. Recap
Planned CFW NEC Activities / Interventions
Workshop 2 – Tuesday 10th October 7.30am-11.00pm
Conway Business Centre, Junction Way, Conwy LL31 9XX
Importance of Program control and management under NEC 3
Program is often referred to as the beating heart of the NEC – but what should it
include, how often does it need to be updated? How does it relate to compensation
events? What is acceptance? We will also explore how the NEC3 deals with inclement
weather and acceleration.
Workshop 3 – Thursday 12th October 7.30am-11.00pm
National Botanic Garden of Wales, Middleton Hall, Llanarthne SA32 8HN
Understanding works information and contract data under NEC 3
In this workshop we will be delving a little deeper into the importance of the Works
information, Contract data parts 1 & 2 – Where is the key information? What is
included? What might you need to be aware of? We will look the functions of the risk
register, explore use of activity schedules and the concepts of allowed and disallowed
costs.
Management of Change Under
NEC3
Stuart Brisbane
Contact 07981 954 417
Thanks for Listening
21st Sept 2017

More Related Content

What's hot

Nec3 introduction
Nec3 introductionNec3 introduction
Nec3 introduction
Quigg Golden Limited
 
Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017
DarrenTofu
 
FIDIC variation, claim & dispute - CYLFEx workshop
FIDIC variation, claim & dispute - CYLFEx workshopFIDIC variation, claim & dispute - CYLFEx workshop
FIDIC variation, claim & dispute - CYLFEx workshop
M Maged Hegazy, LLM, MBA, CCP, P3O
 
Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)
mohamed Ismail
 
FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
FIDIC 2017 Yellow and Silver in EPC and PPP ContractsFIDIC 2017 Yellow and Silver in EPC and PPP Contracts
FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
Loay Ghazaleh MBA, BSc Civil Eng.
 
Assignment - FIDIC Contract
Assignment - FIDIC ContractAssignment - FIDIC Contract
Assignment - FIDIC Contract
Kai Yun Pang
 
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Rae Davies
 
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16Arvind Solanki
 
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias TanFIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias TanAdrias TAN
 
NEC Engineering and Construction Contract (ECC) - compensation events webinar
NEC Engineering and Construction Contract (ECC) -  compensation events webinarNEC Engineering and Construction Contract (ECC) -  compensation events webinar
NEC Engineering and Construction Contract (ECC) - compensation events webinar
Association for Project Management
 
NEC Contracts - Programmes under ECC and PSC webinar
NEC Contracts - Programmes under ECC and PSC webinarNEC Contracts - Programmes under ECC and PSC webinar
NEC Contracts - Programmes under ECC and PSC webinar
Association for Project Management
 
Suspension and Termination by Contractor Presentation.pptx
Suspension and Termination by Contractor Presentation.pptxSuspension and Termination by Contractor Presentation.pptx
Suspension and Termination by Contractor Presentation.pptx
NathannielGonzales1
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2
ahmong4
 
NEC Term Service Contract (TSC)
NEC Term Service Contract (TSC)NEC Term Service Contract (TSC)
NEC Term Service Contract (TSC)
Association for Project Management
 
PP2 Seminar - Determination of Contractor's Employment by Employer
PP2 Seminar - Determination of Contractor's Employment by EmployerPP2 Seminar - Determination of Contractor's Employment by Employer
PP2 Seminar - Determination of Contractor's Employment by Employer
Trace96
 
Payments in the construction industry
Payments in the construction industryPayments in the construction industry
Payments in the construction industry
Kheng Hoe Advocates
 
Building contracts and the JCT
Building contracts and the JCTBuilding contracts and the JCT
Building contracts and the JCTJulian Swindell
 
time bar clauses
time bar clausestime bar clauses
time bar clausesAMILA GAYAN
 
NEC Engineering and Construction Contract (ECC) -The Supervisor's roles and r...
NEC Engineering and Construction Contract (ECC) -The Supervisor's roles and r...NEC Engineering and Construction Contract (ECC) -The Supervisor's roles and r...
NEC Engineering and Construction Contract (ECC) -The Supervisor's roles and r...
Association for Project Management
 

What's hot (20)

Nec3 introduction
Nec3 introductionNec3 introduction
Nec3 introduction
 
Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017
 
FIDIC variation, claim & dispute - CYLFEx workshop
FIDIC variation, claim & dispute - CYLFEx workshopFIDIC variation, claim & dispute - CYLFEx workshop
FIDIC variation, claim & dispute - CYLFEx workshop
 
Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)
 
FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
FIDIC 2017 Yellow and Silver in EPC and PPP ContractsFIDIC 2017 Yellow and Silver in EPC and PPP Contracts
FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
 
Assignment - FIDIC Contract
Assignment - FIDIC ContractAssignment - FIDIC Contract
Assignment - FIDIC Contract
 
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
 
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
 
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias TanFIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
 
NEC Engineering and Construction Contract (ECC) - compensation events webinar
NEC Engineering and Construction Contract (ECC) -  compensation events webinarNEC Engineering and Construction Contract (ECC) -  compensation events webinar
NEC Engineering and Construction Contract (ECC) - compensation events webinar
 
NEC Contracts - Programmes under ECC and PSC webinar
NEC Contracts - Programmes under ECC and PSC webinarNEC Contracts - Programmes under ECC and PSC webinar
NEC Contracts - Programmes under ECC and PSC webinar
 
Suspension and Termination by Contractor Presentation.pptx
Suspension and Termination by Contractor Presentation.pptxSuspension and Termination by Contractor Presentation.pptx
Suspension and Termination by Contractor Presentation.pptx
 
Fidic law1
Fidic law1Fidic law1
Fidic law1
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2
 
NEC Term Service Contract (TSC)
NEC Term Service Contract (TSC)NEC Term Service Contract (TSC)
NEC Term Service Contract (TSC)
 
PP2 Seminar - Determination of Contractor's Employment by Employer
PP2 Seminar - Determination of Contractor's Employment by EmployerPP2 Seminar - Determination of Contractor's Employment by Employer
PP2 Seminar - Determination of Contractor's Employment by Employer
 
Payments in the construction industry
Payments in the construction industryPayments in the construction industry
Payments in the construction industry
 
Building contracts and the JCT
Building contracts and the JCTBuilding contracts and the JCT
Building contracts and the JCT
 
time bar clauses
time bar clausestime bar clauses
time bar clauses
 
NEC Engineering and Construction Contract (ECC) -The Supervisor's roles and r...
NEC Engineering and Construction Contract (ECC) -The Supervisor's roles and r...NEC Engineering and Construction Contract (ECC) -The Supervisor's roles and r...
NEC Engineering and Construction Contract (ECC) -The Supervisor's roles and r...
 

Similar to CFW NEC Management of change under the NEC3

NEC4 overview: key changes and impacts - Nottingham, September 2017
NEC4 overview: key changes and impacts - Nottingham, September 2017NEC4 overview: key changes and impacts - Nottingham, September 2017
NEC4 overview: key changes and impacts - Nottingham, September 2017
Browne Jacobson LLP
 
Planning and Project Controls under NEC4 – the choice isn’t yours! by "Glenn ...
Planning and Project Controls under NEC4 – the choice isn’t yours! by "Glenn ...Planning and Project Controls under NEC4 – the choice isn’t yours! by "Glenn ...
Planning and Project Controls under NEC4 – the choice isn’t yours! by "Glenn ...
Project Controls Expo
 
NEC4 overview: key changes and impacts - London, September 2017
NEC4 overview: key changes and impacts - London, September 2017NEC4 overview: key changes and impacts - London, September 2017
NEC4 overview: key changes and impacts - London, September 2017
Browne Jacobson LLP
 
contract_management.ppt
contract_management.pptcontract_management.ppt
contract_management.ppt
ssuser32da691
 
NCIT civil Syllabus 2013-2014
NCIT civil Syllabus 2013-2014NCIT civil Syllabus 2013-2014
NCIT civil Syllabus 2013-2014
LAKSHITHA RAJAPAKSHA
 
Cl presentation
Cl presentationCl presentation
Cl presentation
lucaschinsheng
 
Ak contract management
Ak contract managementAk contract management
Ak contract management
ManaliChitranshi
 
From NEC3 to NEC4 ECC
From NEC3 to NEC4 ECCFrom NEC3 to NEC4 ECC
From NEC3 to NEC4 ECC
Ir Albert YEU FCIArb MICE
 
Measuring tendering and estimating for CBE
Measuring tendering and estimating for CBEMeasuring tendering and estimating for CBE
Measuring tendering and estimating for CBE
Sahl Buhary
 
C. Site managment chapter 5.pptx
C. Site managment chapter 5.pptxC. Site managment chapter 5.pptx
C. Site managment chapter 5.pptx
EdenBekele5
 
Major Differences between (FIDIC-JCT-NEC).pdf
Major Differences between (FIDIC-JCT-NEC).pdfMajor Differences between (FIDIC-JCT-NEC).pdf
Major Differences between (FIDIC-JCT-NEC).pdf
ssuser6d14e4
 
Contract payment and variation
Contract payment and variationContract payment and variation
Contract payment and variation
Vj NiroSh
 
Assignment 1 Complete
Assignment 1 CompleteAssignment 1 Complete
Assignment 1 CompleteJohn Ashton
 
Lecture4construction contract.ppt
Lecture4construction contract.pptLecture4construction contract.ppt
Lecture4construction contract.ppt
IrynaRudnieva
 
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Antonio Coladarce
 
Effective contract administration may 2014
Effective contract administration may 2014Effective contract administration may 2014
Effective contract administration may 2014
SHKLaw
 
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...Praveen Premkumar
 
PP Seminar Tutorial 7
PP Seminar Tutorial 7PP Seminar Tutorial 7
PP Seminar Tutorial 7
Farah Sham
 
Seminar Presentation Slides (Chapter 2)
Seminar Presentation Slides (Chapter 2)Seminar Presentation Slides (Chapter 2)
Seminar Presentation Slides (Chapter 2)
Melvin Lim
 
Architectural Professional Practice - Construction Documents
Architectural Professional Practice - Construction DocumentsArchitectural Professional Practice - Construction Documents
Architectural Professional Practice - Construction DocumentsGalala University
 

Similar to CFW NEC Management of change under the NEC3 (20)

NEC4 overview: key changes and impacts - Nottingham, September 2017
NEC4 overview: key changes and impacts - Nottingham, September 2017NEC4 overview: key changes and impacts - Nottingham, September 2017
NEC4 overview: key changes and impacts - Nottingham, September 2017
 
Planning and Project Controls under NEC4 – the choice isn’t yours! by "Glenn ...
Planning and Project Controls under NEC4 – the choice isn’t yours! by "Glenn ...Planning and Project Controls under NEC4 – the choice isn’t yours! by "Glenn ...
Planning and Project Controls under NEC4 – the choice isn’t yours! by "Glenn ...
 
NEC4 overview: key changes and impacts - London, September 2017
NEC4 overview: key changes and impacts - London, September 2017NEC4 overview: key changes and impacts - London, September 2017
NEC4 overview: key changes and impacts - London, September 2017
 
contract_management.ppt
contract_management.pptcontract_management.ppt
contract_management.ppt
 
NCIT civil Syllabus 2013-2014
NCIT civil Syllabus 2013-2014NCIT civil Syllabus 2013-2014
NCIT civil Syllabus 2013-2014
 
Cl presentation
Cl presentationCl presentation
Cl presentation
 
Ak contract management
Ak contract managementAk contract management
Ak contract management
 
From NEC3 to NEC4 ECC
From NEC3 to NEC4 ECCFrom NEC3 to NEC4 ECC
From NEC3 to NEC4 ECC
 
Measuring tendering and estimating for CBE
Measuring tendering and estimating for CBEMeasuring tendering and estimating for CBE
Measuring tendering and estimating for CBE
 
C. Site managment chapter 5.pptx
C. Site managment chapter 5.pptxC. Site managment chapter 5.pptx
C. Site managment chapter 5.pptx
 
Major Differences between (FIDIC-JCT-NEC).pdf
Major Differences between (FIDIC-JCT-NEC).pdfMajor Differences between (FIDIC-JCT-NEC).pdf
Major Differences between (FIDIC-JCT-NEC).pdf
 
Contract payment and variation
Contract payment and variationContract payment and variation
Contract payment and variation
 
Assignment 1 Complete
Assignment 1 CompleteAssignment 1 Complete
Assignment 1 Complete
 
Lecture4construction contract.ppt
Lecture4construction contract.pptLecture4construction contract.ppt
Lecture4construction contract.ppt
 
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
 
Effective contract administration may 2014
Effective contract administration may 2014Effective contract administration may 2014
Effective contract administration may 2014
 
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
 
PP Seminar Tutorial 7
PP Seminar Tutorial 7PP Seminar Tutorial 7
PP Seminar Tutorial 7
 
Seminar Presentation Slides (Chapter 2)
Seminar Presentation Slides (Chapter 2)Seminar Presentation Slides (Chapter 2)
Seminar Presentation Slides (Chapter 2)
 
Architectural Professional Practice - Construction Documents
Architectural Professional Practice - Construction DocumentsArchitectural Professional Practice - Construction Documents
Architectural Professional Practice - Construction Documents
 

More from Rae Davies

Construction Futures Wales - Mental Health in Construction HHW
Construction Futures Wales - Mental Health in Construction HHWConstruction Futures Wales - Mental Health in Construction HHW
Construction Futures Wales - Mental Health in Construction HHW
Rae Davies
 
Construction Futures Wales - Project Bank Accounts
Construction Futures Wales - Project Bank AccountsConstruction Futures Wales - Project Bank Accounts
Construction Futures Wales - Project Bank Accounts
Rae Davies
 
Construction Futures Wales Project Bank Accounts - November 2018
Construction Futures Wales Project Bank Accounts  - November 2018Construction Futures Wales Project Bank Accounts  - November 2018
Construction Futures Wales Project Bank Accounts - November 2018
Rae Davies
 
Construction Futures Wales - Mental health in the Workplace
Construction Futures Wales - Mental health in the WorkplaceConstruction Futures Wales - Mental health in the Workplace
Construction Futures Wales - Mental health in the Workplace
Rae Davies
 
Construction Futures Wales & Wales Nuclear Forum - React to Nuclear Event
Construction Futures Wales & Wales Nuclear Forum - React to Nuclear EventConstruction Futures Wales & Wales Nuclear Forum - React to Nuclear Event
Construction Futures Wales & Wales Nuclear Forum - React to Nuclear Event
Rae Davies
 
Construction Futures Wales - Project Bank Accounts
Construction Futures Wales - Project Bank AccountsConstruction Futures Wales - Project Bank Accounts
Construction Futures Wales - Project Bank Accounts
Rae Davies
 
Construction Futures Wales - Digitalisation Workshop
Construction Futures Wales - Digitalisation WorkshopConstruction Futures Wales - Digitalisation Workshop
Construction Futures Wales - Digitalisation Workshop
Rae Davies
 
Construction Futures Wales - Succession Planning Workshop
Construction Futures Wales - Succession Planning WorkshopConstruction Futures Wales - Succession Planning Workshop
Construction Futures Wales - Succession Planning Workshop
Rae Davies
 
Construction Futures Wales - Supply Chain Development Workshop
Construction Futures Wales - Supply Chain Development WorkshopConstruction Futures Wales - Supply Chain Development Workshop
Construction Futures Wales - Supply Chain Development Workshop
Rae Davies
 
CFW Managing your Cash-flow
CFW Managing your Cash-flowCFW Managing your Cash-flow
CFW Managing your Cash-flow
Rae Davies
 
CFW An Introduction to Building Information Modelling
CFW An Introduction to Building Information Modelling CFW An Introduction to Building Information Modelling
CFW An Introduction to Building Information Modelling
Rae Davies
 
Construction Futures Wales Workplace Health Workshop - Case Studies - Public ...
Construction Futures Wales Workplace Health Workshop - Case Studies - Public ...Construction Futures Wales Workplace Health Workshop - Case Studies - Public ...
Construction Futures Wales Workplace Health Workshop - Case Studies - Public ...
Rae Davies
 
Construction Futures Wales Workplace Health Workshop - Fit For Work - Paul Kirk
Construction Futures Wales Workplace Health Workshop - Fit For Work - Paul KirkConstruction Futures Wales Workplace Health Workshop - Fit For Work - Paul Kirk
Construction Futures Wales Workplace Health Workshop - Fit For Work - Paul Kirk
Rae Davies
 
CFW Workplace Health Workshop North & South Wales Oct 2016 - Morgan Sindall, ...
CFW Workplace Health Workshop North & South Wales Oct 2016 - Morgan Sindall, ...CFW Workplace Health Workshop North & South Wales Oct 2016 - Morgan Sindall, ...
CFW Workplace Health Workshop North & South Wales Oct 2016 - Morgan Sindall, ...
Rae Davies
 
CFW Procurement Workshop October 2016
CFW Procurement Workshop October 2016CFW Procurement Workshop October 2016
CFW Procurement Workshop October 2016
Rae Davies
 
RWE Mynydd y Gwair Supply Chain Event - Construction Futures Wales / Paul Wintle
RWE Mynydd y Gwair Supply Chain Event - Construction Futures Wales / Paul WintleRWE Mynydd y Gwair Supply Chain Event - Construction Futures Wales / Paul Wintle
RWE Mynydd y Gwair Supply Chain Event - Construction Futures Wales / Paul Wintle
Rae Davies
 
RWE Mynydd y Gwair Supply Chain Event - Jones Bros / Paul Thorburn
RWE Mynydd y Gwair Supply Chain Event - Jones Bros / Paul ThorburnRWE Mynydd y Gwair Supply Chain Event - Jones Bros / Paul Thorburn
RWE Mynydd y Gwair Supply Chain Event - Jones Bros / Paul Thorburn
Rae Davies
 
RWE Mynydd y Gwair Supply Chain Event - Dawnus / Matthew Morgan
RWE Mynydd y Gwair Supply Chain Event - Dawnus / Matthew MorganRWE Mynydd y Gwair Supply Chain Event - Dawnus / Matthew Morgan
RWE Mynydd y Gwair Supply Chain Event - Dawnus / Matthew Morgan
Rae Davies
 
RWE Mynydd y Gwair Supply Chain Event - Bricks & Mortar / Sue Woodward
RWE Mynydd y Gwair Supply Chain Event - Bricks & Mortar / Sue WoodwardRWE Mynydd y Gwair Supply Chain Event - Bricks & Mortar / Sue Woodward
RWE Mynydd y Gwair Supply Chain Event - Bricks & Mortar / Sue Woodward
Rae Davies
 
RWE Mynydd y Gwair Supply Chain Event - Tim James / Kirsty Curry
RWE Mynydd y Gwair Supply Chain Event - Tim James / Kirsty CurryRWE Mynydd y Gwair Supply Chain Event - Tim James / Kirsty Curry
RWE Mynydd y Gwair Supply Chain Event - Tim James / Kirsty Curry
Rae Davies
 

More from Rae Davies (20)

Construction Futures Wales - Mental Health in Construction HHW
Construction Futures Wales - Mental Health in Construction HHWConstruction Futures Wales - Mental Health in Construction HHW
Construction Futures Wales - Mental Health in Construction HHW
 
Construction Futures Wales - Project Bank Accounts
Construction Futures Wales - Project Bank AccountsConstruction Futures Wales - Project Bank Accounts
Construction Futures Wales - Project Bank Accounts
 
Construction Futures Wales Project Bank Accounts - November 2018
Construction Futures Wales Project Bank Accounts  - November 2018Construction Futures Wales Project Bank Accounts  - November 2018
Construction Futures Wales Project Bank Accounts - November 2018
 
Construction Futures Wales - Mental health in the Workplace
Construction Futures Wales - Mental health in the WorkplaceConstruction Futures Wales - Mental health in the Workplace
Construction Futures Wales - Mental health in the Workplace
 
Construction Futures Wales & Wales Nuclear Forum - React to Nuclear Event
Construction Futures Wales & Wales Nuclear Forum - React to Nuclear EventConstruction Futures Wales & Wales Nuclear Forum - React to Nuclear Event
Construction Futures Wales & Wales Nuclear Forum - React to Nuclear Event
 
Construction Futures Wales - Project Bank Accounts
Construction Futures Wales - Project Bank AccountsConstruction Futures Wales - Project Bank Accounts
Construction Futures Wales - Project Bank Accounts
 
Construction Futures Wales - Digitalisation Workshop
Construction Futures Wales - Digitalisation WorkshopConstruction Futures Wales - Digitalisation Workshop
Construction Futures Wales - Digitalisation Workshop
 
Construction Futures Wales - Succession Planning Workshop
Construction Futures Wales - Succession Planning WorkshopConstruction Futures Wales - Succession Planning Workshop
Construction Futures Wales - Succession Planning Workshop
 
Construction Futures Wales - Supply Chain Development Workshop
Construction Futures Wales - Supply Chain Development WorkshopConstruction Futures Wales - Supply Chain Development Workshop
Construction Futures Wales - Supply Chain Development Workshop
 
CFW Managing your Cash-flow
CFW Managing your Cash-flowCFW Managing your Cash-flow
CFW Managing your Cash-flow
 
CFW An Introduction to Building Information Modelling
CFW An Introduction to Building Information Modelling CFW An Introduction to Building Information Modelling
CFW An Introduction to Building Information Modelling
 
Construction Futures Wales Workplace Health Workshop - Case Studies - Public ...
Construction Futures Wales Workplace Health Workshop - Case Studies - Public ...Construction Futures Wales Workplace Health Workshop - Case Studies - Public ...
Construction Futures Wales Workplace Health Workshop - Case Studies - Public ...
 
Construction Futures Wales Workplace Health Workshop - Fit For Work - Paul Kirk
Construction Futures Wales Workplace Health Workshop - Fit For Work - Paul KirkConstruction Futures Wales Workplace Health Workshop - Fit For Work - Paul Kirk
Construction Futures Wales Workplace Health Workshop - Fit For Work - Paul Kirk
 
CFW Workplace Health Workshop North & South Wales Oct 2016 - Morgan Sindall, ...
CFW Workplace Health Workshop North & South Wales Oct 2016 - Morgan Sindall, ...CFW Workplace Health Workshop North & South Wales Oct 2016 - Morgan Sindall, ...
CFW Workplace Health Workshop North & South Wales Oct 2016 - Morgan Sindall, ...
 
CFW Procurement Workshop October 2016
CFW Procurement Workshop October 2016CFW Procurement Workshop October 2016
CFW Procurement Workshop October 2016
 
RWE Mynydd y Gwair Supply Chain Event - Construction Futures Wales / Paul Wintle
RWE Mynydd y Gwair Supply Chain Event - Construction Futures Wales / Paul WintleRWE Mynydd y Gwair Supply Chain Event - Construction Futures Wales / Paul Wintle
RWE Mynydd y Gwair Supply Chain Event - Construction Futures Wales / Paul Wintle
 
RWE Mynydd y Gwair Supply Chain Event - Jones Bros / Paul Thorburn
RWE Mynydd y Gwair Supply Chain Event - Jones Bros / Paul ThorburnRWE Mynydd y Gwair Supply Chain Event - Jones Bros / Paul Thorburn
RWE Mynydd y Gwair Supply Chain Event - Jones Bros / Paul Thorburn
 
RWE Mynydd y Gwair Supply Chain Event - Dawnus / Matthew Morgan
RWE Mynydd y Gwair Supply Chain Event - Dawnus / Matthew MorganRWE Mynydd y Gwair Supply Chain Event - Dawnus / Matthew Morgan
RWE Mynydd y Gwair Supply Chain Event - Dawnus / Matthew Morgan
 
RWE Mynydd y Gwair Supply Chain Event - Bricks & Mortar / Sue Woodward
RWE Mynydd y Gwair Supply Chain Event - Bricks & Mortar / Sue WoodwardRWE Mynydd y Gwair Supply Chain Event - Bricks & Mortar / Sue Woodward
RWE Mynydd y Gwair Supply Chain Event - Bricks & Mortar / Sue Woodward
 
RWE Mynydd y Gwair Supply Chain Event - Tim James / Kirsty Curry
RWE Mynydd y Gwair Supply Chain Event - Tim James / Kirsty CurryRWE Mynydd y Gwair Supply Chain Event - Tim James / Kirsty Curry
RWE Mynydd y Gwair Supply Chain Event - Tim James / Kirsty Curry
 

Recently uploaded

The Parable of the Pipeline a book every new businessman or business student ...
The Parable of the Pipeline a book every new businessman or business student ...The Parable of the Pipeline a book every new businessman or business student ...
The Parable of the Pipeline a book every new businessman or business student ...
awaisafdar
 
What is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdfWhat is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdf
seoforlegalpillers
 
LA HUG - Video Testimonials with Chynna Morgan - June 2024
LA HUG - Video Testimonials with Chynna Morgan - June 2024LA HUG - Video Testimonials with Chynna Morgan - June 2024
LA HUG - Video Testimonials with Chynna Morgan - June 2024
Lital Barkan
 
Affordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n PrintAffordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n Print
Navpack & Print
 
CADAVER AS OUR FIRST TEACHER anatomt in your.pptx
CADAVER AS OUR FIRST TEACHER anatomt in your.pptxCADAVER AS OUR FIRST TEACHER anatomt in your.pptx
CADAVER AS OUR FIRST TEACHER anatomt in your.pptx
fakeloginn69
 
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBdCree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
creerey
 
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdfSearch Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Arihant Webtech Pvt. Ltd
 
Buy Verified PayPal Account | Buy Google 5 Star Reviews
Buy Verified PayPal Account | Buy Google 5 Star ReviewsBuy Verified PayPal Account | Buy Google 5 Star Reviews
Buy Verified PayPal Account | Buy Google 5 Star Reviews
usawebmarket
 
anas about venice for grade 6f about venice
anas about venice for grade 6f about veniceanas about venice for grade 6f about venice
anas about venice for grade 6f about venice
anasabutalha2013
 
Attending a job Interview for B1 and B2 Englsih learners
Attending a job Interview for B1 and B2 Englsih learnersAttending a job Interview for B1 and B2 Englsih learners
Attending a job Interview for B1 and B2 Englsih learners
Erika906060
 
The effects of customers service quality and online reviews on customer loyal...
The effects of customers service quality and online reviews on customer loyal...The effects of customers service quality and online reviews on customer loyal...
The effects of customers service quality and online reviews on customer loyal...
balatucanapplelovely
 
BeMetals Presentation_May_22_2024 .pdf
BeMetals Presentation_May_22_2024   .pdfBeMetals Presentation_May_22_2024   .pdf
BeMetals Presentation_May_22_2024 .pdf
DerekIwanaka1
 
Kseniya Leshchenko: Shared development support service model as the way to ma...
Kseniya Leshchenko: Shared development support service model as the way to ma...Kseniya Leshchenko: Shared development support service model as the way to ma...
Kseniya Leshchenko: Shared development support service model as the way to ma...
Lviv Startup Club
 
Brand Analysis for an artist named Struan
Brand Analysis for an artist named StruanBrand Analysis for an artist named Struan
Brand Analysis for an artist named Struan
sarahvanessa51503
 
ikea_woodgreen_petscharity_dog-alogue_digital.pdf
ikea_woodgreen_petscharity_dog-alogue_digital.pdfikea_woodgreen_petscharity_dog-alogue_digital.pdf
ikea_woodgreen_petscharity_dog-alogue_digital.pdf
agatadrynko
 
Project File Report BBA 6th semester.pdf
Project File Report BBA 6th semester.pdfProject File Report BBA 6th semester.pdf
Project File Report BBA 6th semester.pdf
RajPriye
 
The-McKinsey-7S-Framework. strategic management
The-McKinsey-7S-Framework. strategic managementThe-McKinsey-7S-Framework. strategic management
The-McKinsey-7S-Framework. strategic management
Bojamma2
 
What are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdfWhat are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdf
HumanResourceDimensi1
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptx
Cynthia Clay
 
ikea_woodgreen_petscharity_cat-alogue_digital.pdf
ikea_woodgreen_petscharity_cat-alogue_digital.pdfikea_woodgreen_petscharity_cat-alogue_digital.pdf
ikea_woodgreen_petscharity_cat-alogue_digital.pdf
agatadrynko
 

Recently uploaded (20)

The Parable of the Pipeline a book every new businessman or business student ...
The Parable of the Pipeline a book every new businessman or business student ...The Parable of the Pipeline a book every new businessman or business student ...
The Parable of the Pipeline a book every new businessman or business student ...
 
What is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdfWhat is the TDS Return Filing Due Date for FY 2024-25.pdf
What is the TDS Return Filing Due Date for FY 2024-25.pdf
 
LA HUG - Video Testimonials with Chynna Morgan - June 2024
LA HUG - Video Testimonials with Chynna Morgan - June 2024LA HUG - Video Testimonials with Chynna Morgan - June 2024
LA HUG - Video Testimonials with Chynna Morgan - June 2024
 
Affordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n PrintAffordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n Print
 
CADAVER AS OUR FIRST TEACHER anatomt in your.pptx
CADAVER AS OUR FIRST TEACHER anatomt in your.pptxCADAVER AS OUR FIRST TEACHER anatomt in your.pptx
CADAVER AS OUR FIRST TEACHER anatomt in your.pptx
 
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBdCree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
 
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdfSearch Disrupted Google’s Leaked Documents Rock the SEO World.pdf
Search Disrupted Google’s Leaked Documents Rock the SEO World.pdf
 
Buy Verified PayPal Account | Buy Google 5 Star Reviews
Buy Verified PayPal Account | Buy Google 5 Star ReviewsBuy Verified PayPal Account | Buy Google 5 Star Reviews
Buy Verified PayPal Account | Buy Google 5 Star Reviews
 
anas about venice for grade 6f about venice
anas about venice for grade 6f about veniceanas about venice for grade 6f about venice
anas about venice for grade 6f about venice
 
Attending a job Interview for B1 and B2 Englsih learners
Attending a job Interview for B1 and B2 Englsih learnersAttending a job Interview for B1 and B2 Englsih learners
Attending a job Interview for B1 and B2 Englsih learners
 
The effects of customers service quality and online reviews on customer loyal...
The effects of customers service quality and online reviews on customer loyal...The effects of customers service quality and online reviews on customer loyal...
The effects of customers service quality and online reviews on customer loyal...
 
BeMetals Presentation_May_22_2024 .pdf
BeMetals Presentation_May_22_2024   .pdfBeMetals Presentation_May_22_2024   .pdf
BeMetals Presentation_May_22_2024 .pdf
 
Kseniya Leshchenko: Shared development support service model as the way to ma...
Kseniya Leshchenko: Shared development support service model as the way to ma...Kseniya Leshchenko: Shared development support service model as the way to ma...
Kseniya Leshchenko: Shared development support service model as the way to ma...
 
Brand Analysis for an artist named Struan
Brand Analysis for an artist named StruanBrand Analysis for an artist named Struan
Brand Analysis for an artist named Struan
 
ikea_woodgreen_petscharity_dog-alogue_digital.pdf
ikea_woodgreen_petscharity_dog-alogue_digital.pdfikea_woodgreen_petscharity_dog-alogue_digital.pdf
ikea_woodgreen_petscharity_dog-alogue_digital.pdf
 
Project File Report BBA 6th semester.pdf
Project File Report BBA 6th semester.pdfProject File Report BBA 6th semester.pdf
Project File Report BBA 6th semester.pdf
 
The-McKinsey-7S-Framework. strategic management
The-McKinsey-7S-Framework. strategic managementThe-McKinsey-7S-Framework. strategic management
The-McKinsey-7S-Framework. strategic management
 
What are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdfWhat are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdf
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptx
 
ikea_woodgreen_petscharity_cat-alogue_digital.pdf
ikea_woodgreen_petscharity_cat-alogue_digital.pdfikea_woodgreen_petscharity_cat-alogue_digital.pdf
ikea_woodgreen_petscharity_cat-alogue_digital.pdf
 

CFW NEC Management of change under the NEC3

  • 1. Supply Chain Development Management of Change Under the NEC 3 Stuart Brisbane(CFW Consultant) 21st Sept 2017 The Vale Hotel - Hensol
  • 2. Agenda 1. Overview 2. Early Warnings 3. Compensation Events • Clause 60 (Definition) • Clause 61 ( Notification) • Clause 62 (Quotation) • Clauses 63 & 64 (Assessment) • Clause 65 (implementation) 4. Some Points to Note 5. Recap
  • 7. NEC3 Suite of Contracts • Works • Engineering and Construction Contract (ECC) • Engineering and Construction Short Contract (ECSC) • Engineering and Construction Subcontract (ECS) • Engineering and Construction Short Subcontract (ECSS) • Services • Professional Services Contract (PSC) – Architecture, Engineering • Term Service Contract (TSC) – Maintenance, Management • Term Service Short Contract (TSSC) • Supply • Supply Contract (SC) – Goods, Products • Supply Short Contract (SSC) • Others • Adjudicator’s Contract (AC), Framework Contract (FC) 1. Overview
  • 8. NEC4 Suite of Contracts 1. Overview
  • 9. NEC4 Suite of Contracts 1. Overview The brand new NEC4 Design Build and Operate Contract (DBO) allows Clients to procure a more integrated whole-life delivery solution. It reflects the increasing demand for contracts extending into the operational phase.
  • 10. NEC4 Suite of Contracts 1. Overview
  • 11. 1. Overview NEC3 Suite of Contracts
  • 13. Core & Main Option Clauses • The Core Clauses are set out in nine sections and apply in all contracts. The clauses allow for a flexible amount of Contractor design. • Section 1: General • Section 2: The Contractor’s Main Responsibilities • Section 3: Time • Section 4: Testing and Defects • Section 5: Payment • Section 6: Compensation Events • Section 7: Title • Section 8: Risk and Insurance • Section 9: Dispute and Termination • The Main Option Clauses provide two options for the dispute resolution procedure. • Option W1: Used unless the HGCRA 1996 applies. • Option W2: Used in the UK when the HGCRA 1996 applies. 1. Overview
  • 14. Cost Components & Contract Data • The Cost Components are two schedules which contain cost information supplied by the Contractor. They are used to assess payments to the Contractor and the cost effect of Compensation Events. Costs are defined in relation to people, equipment, plant and machinery, utility charges, manufacture and fabrication, design and insurance. • Known as the ‘Contract Particulars’ under JCT, the Contract Data provides data required by the specific conditions of the contract. The section is split into two parts • Part 1 - Data provided by the Employer • Part 2 – Data provided by the Contractor. Information includes... • Name of Parties • Insurance Details • Start and Completion Dates • Interest Rates • Retention Percentage if applicable • Rates for Delay Damages if applicable 1. Overview
  • 15. Works and Site Information • The Works Information specifies and describes the Works to be carried out, including Contractor’s design responsibilities. Most information will be given in a specification and on production drawings in the traditional manner. However, it may also include… • Statement of Constraints on how works are carried out • Health and Safety • Details of Contractor’s Design elements • Information on Specialist Subcontractors • Details of Tests • Performance or Advance Payment Bonds • The Site Information describes the site and its surroundings and is used to assess compensation for site conditions. Information may include soil investigations, contamination reports and details of below ground services. 1. Overview
  • 16. Managing Change • NEC3 includes a clause which obliges the Contractor and Project Manager to notify each other as soon as they become aware of any matter which could increase the Prices or delay Completion. This is called an Early Warning. • Under the JCT Type, the procedure for managing change is known as ‘Variations’. A Contractor’s Schedule 2 Quotation can be used to obtain a fixed price quotation for a variation. However, it is not mandatory and typically responsibility lies with the QS to price variations. Disputes can arise and are often not resolved quickly. • Under the NEC3, the procedure is known as ‘Compensation Events’ and an immediate assessment of the cost and time implications are made. These are mandatory and binding, with no provision for later review. They are events which do not arise from the Contractor’s fault and entitle the Contractor to be compensated for any effect the event has on the Prices and Dates. Compensation Events are listed in the Core Clauses and the Options. The Contract Data also has provision for the Employer to insert their own additional compensation events. 1. Overview
  • 17. 1. Overview Terms in italics are project specific Defined terms have capital initials These drafting principles make it easier to understand the contract These principles should be adhered to when drafting documents & communicating Clause 11.1: Terms identified in the Contract Data are in italics e.g.. Period for reply, boundaries of the site Defined terms have capital initials, e.g. Accepted Programme, Completion, Defect The index is useful to refer to as it details the links within the contract – it helps build the intellectual map
  • 18. • There are 19 defined terms relevant to the core clauses • These are in alphabetic order • Additional defined terms exist dependent upon the: – Main Options – Secondary Options 1. Overview
  • 19. Clause Defined term & comment Linkage 11.2(1) Accepted Programme – latest Accepted Programme supersedes previous. Vital to have an Accepted Programme in place for the good of the project 31.3, 50.3 (remedy) 11.2(2) Completion – the second bullet serves as a basic filter, the first bullet allows the Employer to be very precise X7.1 (remedy) 11.2(9) Key Date – critical milestone from the Employer’s perspective, often reflects interface between the Contractor and Others 14.3 (alter), 25.3 (remedy) 11.2(14) Risk Register – consists of risks identified as part of the tender process plus early warnings Contract Data, 16.4 11.2(16) Site Information – factual information about the site 60.1(12), 60.2, 60.3 11.2(18) Working Areas – necessary for Providing the Works & used only for work on this contract 15.1, SCC, SSCC 11.2(19) Works Information – specifies and describes the works or any constraints 14.3, 60.1(1) Some Defined Terms and Basic Contract Linkages 1. Overview
  • 20. Clause Defined term & comment Main Option A, 11.2(20) Activity Schedule (note the sequential clause numbering) Main Option A, 11.2(27) Price for Work Done to Date (PWDD) – completed activities Main Option B, 11.2(28) Price for Work Done to Date (PWDD) – bill items Main Option C, 11.2(23) Defined Cost – definition of what is paid for under Options C-F Main Option C, 11.2(25) Disallowed Cost – definition of what is not paid under Options C-F X5.1 Sectional Completion – references equally apply to Sectional Completion eg clause 16.1 1. Overview Some Defined Terms and Basic Contract Linkages
  • 21. Key People • The ECC sets out the responsibilities and roles of the following key people: • Employer Not involved in administrating the contract – no power to issue instructions. • Project Manager Known as the ‘Contract Administrator’ under the JCT, the Project Manager manages procurement of the Works for the Employer. Contract contemplates appointment prior to the Consultants so that they manage the design process. • Supervisor Known as the ‘Clerk of Works’ under the JCT, the Supervisor exercises certain responsibilities on site for the Employer, including testing, monitoring quality and issuing the Defects Certificate. • Contractor • Subcontractors • Adjudicator • Note, no references to an Architect or QS by profession. Unless delegated the role or responsibility, the Architect who produced the Works Information, may not have a role in the Contract and therefore have no responsibility to monitor quality and compliance with the Works Information. The Supervisor may have limited knowledge of the Works Information and this may affect the quality of the completed building. Traditionally as Contract Administration, the Architect has a responsibility to monitor quality. 1. Overview
  • 24. Communication protocol: Clause 13.1 • Clause 13.1 clearly states the methods of communication which the contract requires in a form that can be read, copied and recorded • The contract requires professional record keeping • The Project Manager should discuss and agree with the Contractor which method(s) of communication will be used at commencement of the contract • The NEC published guidance on communication in April 2013 • Good examples and suggestions are contained within this guidance 1. Overview • As a minimum, the ECC pro-forma’s are recommended as the means of communicating • They state the relevant clause • The communications are structured • This is not being contractual – it’s following what the contract requires (‘acting as stated’)
  • 25. Communication protocol: Clause 13.7 • ‘Notified’ matters need to be communicated separately! • Each early warning should be notified separately • Each defect should be notified separately • Each compensation event should be notified separately 1. Overview
  • 26. Full list of notifications under the ECC (clause 13.7) Clause Issue 14.2 Delegation 14.4 Replacement of the PM or Supervisor 16.1 Early Warning 17.1 Ambiguities and inconsistencies 18.1 Illegal or impossible requirements 31.3 Programmes 40.3 Tests and inspections 42.2 Defects 61.1 Compensation Events 61.3 Compensation Events 61.4 Compensation Events 61.5 Decisions on Compensation Events 61.6 Assumptions on Compensation Events 62.6 Quotations for Compensation Events 64.3 Assessments of Compensation Events 64.4 Late assessment of Compensation Events 65.1 Implementation of Compensation Events 73.1 Discovery of objects of value etc 1. Overview
  • 27. • The Contract Data ‘refers’ to the documents which contain the Works Information. – Contract Data Part 1 identifies the Employer’s Works Information – Contract Data Part 2 identifies the Contractor’s Works Information for his design 1. Overview
  • 28. • What happens if there are inconsistencies between the Works Information provided by the Contractor (for his design) and that provided by the Employer? Clause 17.1 notify Clause 14.3 Ability to change Clause 60.1(1), Second bullet Changing the Contractor’s WI to comply with the Employer’s is not a compensation event. In that respect, the Employer’s WI is dominant 1. Overview
  • 29. • What happens if the Employer’s WI contains inconsistencies in drafting and/or is ambiguous? Clause 17.1, Notify Clause 14.3 – ability to change Clause 63.8, Employer pays The Employer compensates the Contractor for any inconsistency or ambiguity 1. Overview TELEVISIONS – 42” or 24” – 63X £127.99 = £8063.37
  • 30. • The Risk Register is a new feature under NEC3. • It is a live document that is formed by the Project Team post-contract (i.e. not a contract document) and will change as the work progresses. • Risks can be added to the Register as part of the Early Warning process, or removed because of actions taken by the parties (i.e. soil investigations). • Risks are allocated a likelihood of occurrence and impact, along with an approximate cost effect. Regular Risk Reduction Meetings should be held during the Contract. 1. Overview
  • 31. 1. Overview • Clause 80.1 defines the Employers Risks under the contract • Clause 81.1 sets out that all other risks are carried by the Contractor. • Clause 83 each party indemnifies the other against events which are at its risk • Often ITT’s are including preliminary risk registers to help prospective contractors understand what getting into. • Risk Registers are a practical project management tool , time or cost consequences should fall outside of clause 83 and be addressed through other mechanisms (CE’s) Parties need to be very clear as to how any such risks are allocated. • Recent difficulties around final entry clause 80.1 which allows additional Employers risks to be specified in the Contract Data in order to include a preliminary risk register . • Employer will often append or refer to the risk register in the contact data and if that register assigns actions to the employer could be argued that they become part of 80.1 • Broad consensus that risk register operates at a practical level and not intended to alter 80.1 and 81.1 however still limited case law and remains uncertainty. • Prudent for clarity to amend the contract that items in the risk register are not employers risks.
  • 32. • Under the JCT Types, the Contractor is required to submit a Programme but it is not a binding Contract Document and there is no requirement to keep it up to date. • In contrast, the Accepted Programme forms part of the Contract Data under the NEC3 and the Contractor is required to keep it up to date. Any changes must be accepted by the Project Manager within 2 weeks. It is an important document and is used to monitor/assess the time effects of Compensation Events. Programme should show… • Start Date/Completion Date/Key Dates • Planned Completion • Order and Timing of Operations • Time Risk Allowances • Health and Safety Requirements • Information from Required Others • Float 1. Overview
  • 33. • The programme is key – it’s the ‘beating heart’ of the NEC • The NEC programme is a joint programme • It provides critical management data • If the programme is not compliant/accepted it becomes very difficult to objectively assess compensation events • In order to ensure acceptance it is worthwhile considering a joint review before final submission/acceptance 1. Overview
  • 36. • Early Warnings are very important part of NEC • They are about identifying potential problems before they occur with a view to avoidance or mitigation • Designed to avoid waiting until they have happened and seeking to apportion blame • There is no entitlement under Early Warnings • They should not be viewed as claims however if not given or given and ignored have consequences • Under Clause 16.1 Contractor or PM can issue • Consequences if Contractor not issued when could have – under options C-F could be disallowed costs • Clause 16.2 gives rights to PM or Contractor to Instruct attendance at risk reduction meeting. • Issue of EW entails PM must add to the Risk Register • All about encouraging proactive and collaborative working 2. Early Warning
  • 37. Full list of notifications under the ECC (clause 13.7) Clause Issue 14.2 Delegation 14.4 Replacement of the PM or Supervisor 16.1 Early Warning 17.1 Ambiguities and inconsistencies 18.1 Illegal or impossible requirements 31.3 Programmes 40.3 Tests and inspections 42.2 Defects 61.1 Compensation Events 61.3 Compensation Events 61.4 Compensation Events 61.5 Decisions on Compensation Events 61.6 Assumptions on Compensation Events 62.6 Quotations for Compensation Events 64.3 Assessments of Compensation Events 64.4 Late assessment of Compensation Events 65.1 Implementation of Compensation Events 73.1 Discovery of objects of value etc 1. Overview
  • 38. The early warning process: 2. Early Warning
  • 39. The early warning process • The Project Manager should facilitate and trouble shoot the process • This is not about casting blame • Its about mature project management – recognising that both parties will encounter problems • Its about overcoming them collaboratively 3. Early Warning
  • 40. The early warning process: •‘Notify’ – separately (13.7) •4 reasons •5th reason is discretionary •Protecting time, quality and cost 16.1 Notify •May instruct others to attend 16.2 Instruct a meeting •How to avoid or reduce •Seek solutions •Decide on actions •Update 16.3 Mitigate •Revise •Issue to the Contractor 16.4 Update and issue 2. Early Warning
  • 41. The early warning process: 2. Early Warning
  • 42. The early warning process: •‘Notify’ – separately (13.7) •4 reasons •5th reason is discretionary •Protecting time, quality and cost 16.1 Notify •May instruct others to attend 16.2 Instruct a meeting •How to avoid or reduce •Seek solutions •Decide on actions •Update 16.3 Mitigate •Revise •Issue to the Contractor 16.4 Update and issue 2. Early Warning
  • 43. The early warning process: 2. Early Warning
  • 44. Impact if we don’t manage Early Warnings: Clause 16.1 Notify (separate communication: clause 13.7) The Prices Clause 63.5: “…event is assessed as if the Contractor had given early warning” Disallowed Cost Clause 11.2 (25)*….was incurred only because the Contractor did not ….give an early warning…. Options A-F Options C-F Under Options C-F failure to notify early warnings can have a detrimental effect on the Prices (value) and Defined Cost (cost) *11.2(26) under Option F 3. Early Warning
  • 45. The early warning process: 2. Early Warning Options A-F
  • 46. The early warning process: 2. Early Warning Options C-F Core clauses General 11.2
  • 48. Implementing the key procedures: Early warnings Procedures in contract • Risk Register to be compiled by the Project Manager • Each early warning to be notified and recorded in the Risk Register • Mitigation & risk reduction to be undertaken as per clause 16.3 Practical suggestions • Ensure the ethos is right within the team – early warnings are not a pre-empt to a claim! • Develop the Risk Register from the tender process • Consider a protocol of picking up the phone and discussing initially. If both parties agree/one feels strongly then follow through with the paperwork? • Ensure dialogue is maintained • Consider a categorisation system eg. category 1 = critical (meet in the next 24 hours), category 2 = non-critical (record and discuss at the next progress meeting) 2. Early Warning
  • 53. 4. Compensation Events Compensation events are defined as events which if they do not arise from Contractors fault, entitle Contractor to be compensated for effect on the Prices, Key Dates and Completion Date Therefore it is important to remember that compensation events deal with both time and money
  • 54. What is a compensation event? • Events which entitle the Contractor to be compensated for the effect on the Prices, Key Dates and Completion Date • Both time & cost are assessed in a single quotation • Some compensation events may be negative e.g. omit work from the Works Information (this will have a negative impact on the Prices but will not bring forward the Completion Date) • This section rewrites the traditional rule book in terms of change management  Clearly defined timescales are in place  Failure to comply with these timescales can result in the Contractor being time barred The timescales are clearly defined with sanctions in place for those that do not follow the process! 3. Compensation Events
  • 55. What is a compensation event? • Compensation Events are the ONLY way to change price / and or Completion Date • All in one place and treated in the same way • Cost assessed at forecast change in cost • Time forecast delay based on latest Accepted Programme • All to tight and defined timescale 3. Compensation Events
  • 57. Core & Main Option Clauses • The Core Clauses are set out in nine sections and apply in all contracts. The clauses allow for a flexible amount of Contractor design. • Section 1: General • Section 2: The Contractor’s Main Responsibilities • Section 3: Time • Section 4: Testing and Defects • Section 5: Payment • Section 6: Compensation Events • Section 7: Title • Section 8: Risk and Insurance • Section 9: Dispute and Termination • The Main Option Clauses provide two options for the dispute resolution procedure. • Option W1: Used unless the HGCRA 1996 applies. • Option W2: Used in the UK when the HGCRA 1996 applies. 1. Overview
  • 58. The compensation event process – Overview: • The compensation event process is clearly defined • Section 6 is divided into 5 main sections: Define,Notify, Quote, Assess, Implement • Timescales are in place with sanctions for either party if they are not followed • The timescales are about agreeing the impact not when the work is done • Both time and cost are assessed • There is no separate prolongation/extension of time 4. Compensation Events
  • 59. The compensation event process – Overview: 3. Compensation Events • There is a defined process to agree (or impose) the effects of a compensation event • Within defined time limits • Definition (60) • Notification (61) • Quotation (62) • Assessment (63/64) • Implementation (65) • Either Party can make sure that process and time scales are adhered to
  • 60. What are the reasons for a compensation event? • There are three main reasons: • A change of mind/decision • Failure to do something (a lot relate back to the programme) • Something has happened that is beyond a reasonable risk 3. Compensation Events
  • 61. Where are they listed? • There are four sources of compensation events: • Clause 60.1 (19 reasons) • A further 3 stated in clauses 60.4, 60.5 & 60.6 (Options B & D) • Also secondary Options X2, X12.3(6) & (7), X14.2, X15.2 & Y2.4 • Potentially additional compensation events in Option Z • NEC 4 also introducing a new category for introduction of client specific CE’s 4. Compensation Events
  • 62. Lots of Effort !!! • Many find the Compensation Event process particularly challenging. • Need to consider that the conventional contracts have not avoided the need to manage change, in fact most simply push much of the work to the post completion phase resulting in delays , debates, and extended payments. • NEC3 requires contemporaneous change management and the increased effort should be rewarded by the whole project team having greater certainty of outcome and avoidance of post – completion disputes. 4. Compensation Events
  • 65. Definition of Compensation events Clause 60 3. Compensation Events
  • 66. 3. Compensation Events 60. Definition Essentially is the list of items which are compensation events under the contract. The first step in administering the Compensation Event process is a simple initial check as to what is / has / could be happening on the project against that list.
  • 67. Summary of the compensation event clauses Clause Description Relevant Clauses 60.1(1) Change to the Works Information 14.3, 27.3 & 44 60.1(2) Access and use of the site 33.1 60.1(3) Employer providing something 31.2 60.1(4) Stop or not start any work 34.1 60.1(5) Employer and Others working times and conditions 31.2 60.1(6) Replying to communications 13.3 60.1(7) Object of value 73.1 60.1(8) Changing decisions - 60.1(9) Withholding acceptance 13.8, 13.4, 24.1,31.3 60.1(10) Instructions to search 42.1 60.1(11) Test or inspection causing delay 40.5 60.1(12) Physical conditions 60.2 & 60.3 60.1(13) Weather - 60.1(14) Employer’s risk 80.1 60.1(15) Take over 35.2 60.1(16) Employer provides materials, facilities and samples 40.2 60.1(17) Correction to an assumption 61.6 60.1(18) Breach of contract - 60.1(19) Unforeseen events 19.1 3. Compensation Events
  • 70. Compensation event clauses 3. Compensation Events
  • 71.
  • 86. 3. Compensation Events Compensation event clauses NEC 4 – adding compensation Events Compensation events - Additional compensation events may now be added by the Client in the Contract Data Part One. Compensation events - A new compensation has also been added, in the core clauses, entitling the Contractor to claim for preparing quotations for a proposed instruction which are not accepted by the Project Manager.
  • 87. Notification of Compensation events Clause 61 3. Compensation Events
  • 88. 3. Compensation Events 61. Notification There is a reciprocal duty for the Contractor and the Project Manager to notify each other of any Compensation Event they become aware of. The details of these obligations are set out in core clause 61.
  • 96. Notification of Compensation Events 3. Compensation Events
  • 97. 3. Compensation Events Both Parties have a responsibility to Inform and manage Many PM’s and majority of contractors need to consider. The 8 week time barring period does not apply to compensation events that the project manager should have notified , in which case the contractor has long as he wishes to notify up to defects date. For that reason it is in the Employers best interests for the Project Manager to notify compensation events in order to start the procedural clock ticking Notification of Compensation Events
  • 99. 3. Compensation Events Notification of Compensation Events Beware contract amendments and Z Clauses Options A-F
  • 100. 3. Compensation Events Notification of Compensation Events
  • 101. 3. Compensation Events Notification of Compensation Events
  • 102. Quotations for Compensation Events Clause 62 3. Compensation Events
  • 103. 3. Compensation Events 62. Quotations The Project Manager must instruct the contractor to prepare a quotation , or alternative quotations when a Compensation Event is instigated on behalf of the Employer. A decision to instruct will depend on the outcome of the quotation. The Project Manager must also instruct the contractor to prepare quotations for any other Compensation Event. The timeframe both for the contractor to submit a quotation and for the Project Manager to reply are prescriptive. Timescales can be altered by agreement between the Contractor and the Project manager although such agreements should be based on genuine necessity.
  • 104. Quotations for compensation Events 3. Compensation Events
  • 111. 3. Compensation Events 63 & 64 Assessing Compensation Events are assessed relative to Defined Costs and accepted Program. Quotations deal with both Time & Money The Project Manager must instruct the contractor to prepare a quotation , or alternative quotations when a Compensation Event is instigated on behalf of the Employer. Core Clause 63 details the provisions that must be followed by the contractor. There are circumstances in which the Project manager must assess a compensation Event and these are governed by the detailed provisions set out in Core Clause 64.
  • 112. Assessing Compensation Events 3. Compensation Events
  • 113. Assessing Compensation Events 3. Compensation Events
  • 121. Project Managers Assessment of Compensation Events Clause 64 3. Compensation Events
  • 122. 3. Compensation Events 63 & 64 Assessing Compensation Events are assessed relative to Defined Costs and accepted Program. Quotations deal with both Time & Money The Project Manager must instruct the contractor to prepare a quotation , or alternative quotations when a Compensation Event is instigated on behalf of the Employer. Core Clause 63 details the provisions that must be followed by the contractor. There are circumstances in which the Project manager must assess a compensation Event and these are governed by the detailed provisions set out in Core Clause 64.
  • 123. Project Managers Assessment of Compensation Events 3. Compensation Events
  • 134. 3. Compensation Events 65 Implementing Compensation Events are implemented when their time and money are fixed. These implications are fixed once and once only and not revisited even in the context for a prediction subsequently not transpiring Time and money are inextricably linked through the Programme and the Defined Cost.
  • 135. Implementing Compensation Events 3. Compensation Events
  • 137. Time Barring 3. Compensation Events The compensation event procedure includes temporal obligations with respect to change management that are both reciprocal and onerous. The potential time and money rights of the parties in relation to change can be time-barred if the contractual timescales are not followed. Specifically, if the following actions which confer those time and money rights are not taken within the specified time periods, then those rights are extinguished: • The Contractor must notify a compensation event within eight weeks of becoming aware of it – it is a large carrot to notify a compensation event on time if the right to it can be extinguished after eight weeks. • The Project Manager must notify the Contractor within two weeks of receipt if any event is considered not to be a compensation event – it is an equally large carrot to check a compensation event on time if it is deemed to be accepted after two weeks by default, i.e. if it is not proactively rejected if it is considered accepted. The purpose of such time-barring is to effectively incentivise the parties to perform efficiently and deal with compensation events as they arise. This is a critically important objective of NEC3 in dealing with change contemporaneously and not leaving it for a final account debate.
  • 139. Agree to meet regularly & maintain dialogue 3. Compensation Events Consider the contractual loop / Genuine need for Alterations to the periods – And KEEP YOUR CLIENT INFORMED
  • 140. Implementing the key procedures: Compensation events Procedures in contract • Clear timescales and procedures detailed in section 6 • Both parties may ultimately be time barred if they fail to follow the timescales Practical suggestions • Meet to discuss appropriate compensation events before final submission • Discuss any issues – the aim is to informally agree before formal submission Agree to meet regularly & maintain dialogue 3. Compensation Events
  • 144. Some Points to Note 3. Compensation Events
  • 145. • Clause 80.1 defines the Employers Risks under the contract • Clause 81.1 sets out that all other risks are carried by the Contractor. • Clause 83 each party indemnifies the other against events which are at its risk • Often ITT’s are including preliminary risk registers to help prospective contractors understand what getting into. • Risk Registers are a practical project management tool , time or cost consequences should fall outside of clause 83 and be addressed through other mechanisms (CE’s) Parties need to be very clear as to how any such risks are allocated. • Recent difficulties around the final entry clause 80.1 which allows additional Employers risks to be specified in the Contract Data in order to include a preliminary risk register . • Employer will often append or refer to the risk register in the contact data and if that register assigns actions to the employer could be argued that they become part of 80.1 • Broad consensus that risk register operates at a practical level and not intended to alter 80.1 and 81.1 however still limited case law and remains uncertainty. • Prudent for clarity to amend the contract that items in the risk register are not employers risks. 4. Points to Note
  • 146. 4. Points to Note
  • 147. Key risks – physical conditions: • Physical conditions (clause 60.1(12)) are a compensation event if they are over and above the defined risk: • …… an experienced Contractor ….. such a small chance of occurring ……unreasonable for him to have allowed for it • When ‘judging’ if it is a compensation event – clause 60.2 lists what the Contractor is deemed to have taken account of The Contractor needs to take account of the risks which are within the parameters of this definition On most projects this represents a significant risk Example: A new housing development on a disused hospital site: Discovery of a redundant drain and telephone cables in different places to those shown on drawings is unlikely to be a compensation event (?) 4. Points to Note
  • 148. 4. Points to Note Check the Z clauses – Advice is to minimise however increasingly seen used • Introduction of Provisional Sums • Significantly altering of periods (4 weeks to become time barred)
  • 149. Note that clause 26.3 sets out the reasons why the Project manager might reject a subcontractor. The use of any other reason would potentially trigger a compensation event as clause 60.1(9) So Project Managers must tread carefully when considering such matters. And as later note that Welsh LA have added further reasons via the amendment of a core clause rather than adding a Z clause. 4. Points to Note
  • 150. Consider the final part of clause 26.2 the Contractor is prohibited from appointing a proposed subcontractor until the Project Manager has accepted that subcontractor. Contractor’s should be aware of this prohibition as at clause 91.2 the appointment of a subcontractor for substantial work before the Project Manager has accepted the subcontractor is Reason 13 of the reasons allowing the Employer to terminate the Contract. The only point for debate in respect of this reason is what is substantial work as opposed to unsubstantial work. 4. Points to Note
  • 151. 4. Points to Note Recommendations are to keep Z clauses to the minimum Government and NEC Guidelines available which detail and suggest reasonable and some of the more common uses of Z clauses – such as compliance with Official Secrets act. Review of this Contract discovered significant amendments to and introduction of new core clauses (Just on compensation events)adds to 60.1(10), removes 60.1(12),60.1(19), 60.2, 60.3 adds 60.4 (confirms contractors risks on risk register not CE’s) and 60.5 liability under common law relating to compensation events. Recent works with Welsh Contractor reviewing NEC framework Documents issued by Local Authority
  • 152. 4. Points to Note Inclusion of 33 Z Clauses – covering such items as Recent works with Welsh Contractor reviewing NEC framework Documents issued by Local Authority Contractors obligations for Security Waste Management & WRAP Confidentiality and FOIA & EIR Quality and Quality plans Publicity & Advertising Preliminaries and Value Engineering Guarantees / Warranties / Insurances Provisional Sums Community Benefits Welsh Language BREEAM & EPC CDM Discrimination Recycling BIM & Soft Landings Considerate Constructors Data Protection
  • 153. Recent works with Welsh Contractor reviewing NEC framework Documents issued by Local Authority 4. Points to Note LA’s added and amended the core NEC 3 clauses – in this case adding Disallowed costs into an Option A contract !! Significant risks of introducing confusion – NEC3 is a set of standard procedures and processes with supply chain contracts designed to be back to back. Changes should be via Z clauses
  • 154. 4. Points to Note Is it really the LA’s intention to pass obligations down the entire supply chain Recent works with Welsh Contractor reviewing NEC framework Documents issued by Local Authority
  • 155. 4. Points to Note LA’s added reasons why the Project manager is able to reject a proposed sub contractor – Again need to be commercially aware of potential ramifications Recent works with Welsh Contractor reviewing NEC framework Documents issued by Local Authority
  • 156. 4. Points to Note Consider how you might need to add into supply chain agreements – use of vesting certificates ? – Protect your liability? Recent works with Welsh Contractor reviewing NEC framework Documents issued by Local Authority
  • 157. 4. Points to Note Consider how you might need to add into supply chain agreements – and manage the payment process to protect cashflow Recent works with Welsh Contractor reviewing NEC framework Documents issued by Local Authority
  • 158. 4. Points to Note Consider how you might need to add into supply chain agreements in relation to Compensation Events. Recent works with Welsh Contractor reviewing NEC framework Documents issued by Local Authority
  • 159. 4. Points to Note LA’s intention being to pass obligations down the entire supply chain. Contractors involved in such Frameworks need to consider the practicalities of actually being able to pass these onto their supply chain / or take an informed commercial risk. Recent works with Welsh Contractor reviewing NEC framework Documents issued by Local Authority
  • 160.
  • 161.
  • 162. Recap 1. Overview 2. Early Warnings 3. Compensation Events • Clause 60 (Definition) • Clause 61 ( Notification) • Clause 62 (Quotation) • Clauses 63 & 64 (Assessment) • Clause 65 (implementation) 4. Some Points to Note 5. Recap
  • 163. Planned CFW NEC Activities / Interventions Workshop 2 – Tuesday 10th October 7.30am-11.00pm Conway Business Centre, Junction Way, Conwy LL31 9XX Importance of Program control and management under NEC 3 Program is often referred to as the beating heart of the NEC – but what should it include, how often does it need to be updated? How does it relate to compensation events? What is acceptance? We will also explore how the NEC3 deals with inclement weather and acceleration. Workshop 3 – Thursday 12th October 7.30am-11.00pm National Botanic Garden of Wales, Middleton Hall, Llanarthne SA32 8HN Understanding works information and contract data under NEC 3 In this workshop we will be delving a little deeper into the importance of the Works information, Contract data parts 1 & 2 – Where is the key information? What is included? What might you need to be aware of? We will look the functions of the risk register, explore use of activity schedules and the concepts of allowed and disallowed costs.
  • 164. Management of Change Under NEC3 Stuart Brisbane Contact 07981 954 417 Thanks for Listening 21st Sept 2017