SlideShare a Scribd company logo
1 of 9
cost-value reconciliation
(CVR)
group1
 Cost-value reconciliation (CVR) brings together the established totals for cost and
value to illustrate the profitability of a company
 The CVR serves two purposes
 it forms the basis of statutory accounts
 provides management information to assist in the identification of problems, the need
for reserves, the reasons for loss and information to prevent repetition of such losses
 At each interim valuation date, normally the end of each calendar month, the total
costs to date are compared with the total valuation.
 The cost-value comparison, or reconciliation, is usually completed by the
contractor’s QS
 starting point of any CVR must always be the gross certified value
 Adjustments
 adjustments for external preliminaries claimed in valuations against the internal
preliminary schedule;
 adjustments for elements included within costing but not in the external valuation, for
example, materials brought to site on the same day as the valuation but after materials
on site were recorded
 items of over measurement not picked up by the client’s QS
 any adjustments necessary to bring the cost cut-off date and the on-site valuation date
together
 variations which have not been agreed with the client’s QS
 contractual claims for loss and/or expense which have not been agreed by the client’s QS
 possibility of liquidated damages being charged by the employer
 provision should be made for future known losses
 Once the gross adjusted valuation has been assessed three further elements are
deducted from the figure to arrive at a final residual value or margin
 First, subcontract liabilities which should cover all disciplines of subcontractor,
 second, snagging and defects which can be subdivided into two sections
 Snagging required at the end of the project to achieve handover;
 A levy to be used to cover for costs that may be incurred in the making good of defects period
before the certificate of making good of defects is issued.
 The third and final element of deduction is that of the main contractor’s core costs, that
is, labour, material and plant and other associated costs. In general, these will be supplied to
the contractor’s QS by a separate cost department within the contractor’s company
 The residue is the profit generated from the main contractor’s works section of the
project. When added to the profit on other sections, that is, the subcontract liability
schedule, this indicates the profit to date for the project.
THANKS

More Related Content

What's hot

Quantity surveyor
Quantity surveyorQuantity surveyor
Quantity surveyorSyafiq Deen
 
Stages In Construction
Stages In ConstructionStages In Construction
Stages In ConstructionAB MAKASANA
 
Training fidic moustafa ismail 2017 _ lec 4
Training fidic moustafa ismail  2017 _  lec 4Training fidic moustafa ismail  2017 _  lec 4
Training fidic moustafa ismail 2017 _ lec 4Moustafa Ismail Abu Dief
 
PPT on Construction Costing
PPT on Construction CostingPPT on Construction Costing
PPT on Construction CostingManish Kandpal
 
Quantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficienciesQuantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficienciesMichael Pink
 
Procurement in construction
Procurement in constructionProcurement in construction
Procurement in constructionMahSobeh
 
QUANTITY SURVEYOR magazine
QUANTITY SURVEYOR magazineQUANTITY SURVEYOR magazine
QUANTITY SURVEYOR magazineChong Chin Pin
 
Quantity surveyor
Quantity surveyorQuantity surveyor
Quantity surveyorLY97
 
Common causes of cost overruns in construction projects
Common causes of cost overruns in construction projectsCommon causes of cost overruns in construction projects
Common causes of cost overruns in construction projectsSANJEEV Wazir
 
Ibe quantity surveyor 2013
Ibe quantity surveyor 2013Ibe quantity surveyor 2013
Ibe quantity surveyor 2013nurun2010
 
Civil Quantity Survey and Estimation
Civil Quantity Survey and EstimationCivil Quantity Survey and Estimation
Civil Quantity Survey and EstimationGide India
 
Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1Lee Pei Gie
 

What's hot (20)

Quantity surveyor
Quantity surveyorQuantity surveyor
Quantity surveyor
 
Stages In Construction
Stages In ConstructionStages In Construction
Stages In Construction
 
Construction contract
Construction contractConstruction contract
Construction contract
 
FIDIC variation, claim & dispute - CYLFEx workshop
FIDIC variation, claim & dispute - CYLFEx workshopFIDIC variation, claim & dispute - CYLFEx workshop
FIDIC variation, claim & dispute - CYLFEx workshop
 
Training fidic moustafa ismail 2017 _ lec 4
Training fidic moustafa ismail  2017 _  lec 4Training fidic moustafa ismail  2017 _  lec 4
Training fidic moustafa ismail 2017 _ lec 4
 
TENDER DOCUMENT
TENDER DOCUMENTTENDER DOCUMENT
TENDER DOCUMENT
 
Preparation of boq
Preparation of boqPreparation of boq
Preparation of boq
 
PPT on Construction Costing
PPT on Construction CostingPPT on Construction Costing
PPT on Construction Costing
 
Project cost control
Project cost controlProject cost control
Project cost control
 
Quantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficienciesQuantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficiencies
 
Procurement in construction
Procurement in constructionProcurement in construction
Procurement in construction
 
Construction tender process
Construction tender processConstruction tender process
Construction tender process
 
QUANTITY SURVEYOR magazine
QUANTITY SURVEYOR magazineQUANTITY SURVEYOR magazine
QUANTITY SURVEYOR magazine
 
Quantity surveyor
Quantity surveyorQuantity surveyor
Quantity surveyor
 
Common causes of cost overruns in construction projects
Common causes of cost overruns in construction projectsCommon causes of cost overruns in construction projects
Common causes of cost overruns in construction projects
 
Quantity take off
Quantity take offQuantity take off
Quantity take off
 
Ibe quantity surveyor 2013
Ibe quantity surveyor 2013Ibe quantity surveyor 2013
Ibe quantity surveyor 2013
 
Civil Quantity Survey and Estimation
Civil Quantity Survey and EstimationCivil Quantity Survey and Estimation
Civil Quantity Survey and Estimation
 
Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1
 
Extension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed IbarhimExtension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed Ibarhim
 

Similar to Cost value reconciliation (cvr)

The Scoop on the Incurred Cost Submission
The Scoop on the Incurred Cost SubmissionThe Scoop on the Incurred Cost Submission
The Scoop on the Incurred Cost SubmissionUnanet
 
afar-04-construction-accounting-advanced-financial-accounting-reporting.pdf
afar-04-construction-accounting-advanced-financial-accounting-reporting.pdfafar-04-construction-accounting-advanced-financial-accounting-reporting.pdf
afar-04-construction-accounting-advanced-financial-accounting-reporting.pdfGiovanniperez59
 
DIRECTED READING THREE PERCEPTIONS OF PROJECT COST D.H. Hamburg.docx
DIRECTED READING THREE PERCEPTIONS OF PROJECT COST D.H. Hamburg.docxDIRECTED READING THREE PERCEPTIONS OF PROJECT COST D.H. Hamburg.docx
DIRECTED READING THREE PERCEPTIONS OF PROJECT COST D.H. Hamburg.docxduketjoy27252
 
AS-7 Construction Contracts and AS-18 Related Party Transactions
AS-7 Construction Contracts and AS-18 Related Party TransactionsAS-7 Construction Contracts and AS-18 Related Party Transactions
AS-7 Construction Contracts and AS-18 Related Party TransactionsPrakhar Jain
 
Govology Webinar: GovCon Accounting Policies & Procedures
Govology Webinar: GovCon Accounting Policies & ProceduresGovology Webinar: GovCon Accounting Policies & Procedures
Govology Webinar: GovCon Accounting Policies & ProceduresRobert E Jones
 
Contract Costing NOtes.docx
Contract Costing NOtes.docxContract Costing NOtes.docx
Contract Costing NOtes.docxSreedeviPMenon
 
Bba ii cost and management accounting u 3.3 contract costing
Bba ii cost and management accounting u 3.3 contract costingBba ii cost and management accounting u 3.3 contract costing
Bba ii cost and management accounting u 3.3 contract costingRai University
 
Revenue Recognition Serial Part 6: Step 5 - Recognizing Revenue as or When Pe...
Revenue Recognition Serial Part 6: Step 5 - Recognizing Revenue as or When Pe...Revenue Recognition Serial Part 6: Step 5 - Recognizing Revenue as or When Pe...
Revenue Recognition Serial Part 6: Step 5 - Recognizing Revenue as or When Pe...MHM (Mayer Hoffman McCann P.C.)
 
Contract Costing.pptx
Contract Costing.pptxContract Costing.pptx
Contract Costing.pptxVasuV18
 
151 Section B—Conforming Amendments Related to Revenue f.docx
151 Section B—Conforming Amendments Related to Revenue f.docx151 Section B—Conforming Amendments Related to Revenue f.docx
151 Section B—Conforming Amendments Related to Revenue f.docxjesusamckone
 
CPM lecture note 4,5,6&7.pdf
CPM lecture note 4,5,6&7.pdfCPM lecture note 4,5,6&7.pdf
CPM lecture note 4,5,6&7.pdfDejeneTsegaye6
 
CPM lecture note 4,5,6&7.pdf
CPM lecture note 4,5,6&7.pdfCPM lecture note 4,5,6&7.pdf
CPM lecture note 4,5,6&7.pdfDejeneTsegaye6
 
Construction contract_Existing and Proposed Accounting Standards
Construction contract_Existing and Proposed Accounting StandardsConstruction contract_Existing and Proposed Accounting Standards
Construction contract_Existing and Proposed Accounting StandardsAdi Iskandar Iliyas
 
Prolongation cost calculation
Prolongation cost  calculation Prolongation cost  calculation
Prolongation cost calculation R.R.G.S Bandara
 

Similar to Cost value reconciliation (cvr) (20)

The Scoop on the Incurred Cost Submission
The Scoop on the Incurred Cost SubmissionThe Scoop on the Incurred Cost Submission
The Scoop on the Incurred Cost Submission
 
afar-04-construction-accounting-advanced-financial-accounting-reporting.pdf
afar-04-construction-accounting-advanced-financial-accounting-reporting.pdfafar-04-construction-accounting-advanced-financial-accounting-reporting.pdf
afar-04-construction-accounting-advanced-financial-accounting-reporting.pdf
 
DIRECTED READING THREE PERCEPTIONS OF PROJECT COST D.H. Hamburg.docx
DIRECTED READING THREE PERCEPTIONS OF PROJECT COST D.H. Hamburg.docxDIRECTED READING THREE PERCEPTIONS OF PROJECT COST D.H. Hamburg.docx
DIRECTED READING THREE PERCEPTIONS OF PROJECT COST D.H. Hamburg.docx
 
AS-7 Construction Contracts and AS-18 Related Party Transactions
AS-7 Construction Contracts and AS-18 Related Party TransactionsAS-7 Construction Contracts and AS-18 Related Party Transactions
AS-7 Construction Contracts and AS-18 Related Party Transactions
 
Govology Webinar: GovCon Accounting Policies & Procedures
Govology Webinar: GovCon Accounting Policies & ProceduresGovology Webinar: GovCon Accounting Policies & Procedures
Govology Webinar: GovCon Accounting Policies & Procedures
 
Joint costing
Joint costingJoint costing
Joint costing
 
Management Reserve
Management ReserveManagement Reserve
Management Reserve
 
Contract Costing NOtes.docx
Contract Costing NOtes.docxContract Costing NOtes.docx
Contract Costing NOtes.docx
 
Bba ii cost and management accounting u 3.3 contract costing
Bba ii cost and management accounting u 3.3 contract costingBba ii cost and management accounting u 3.3 contract costing
Bba ii cost and management accounting u 3.3 contract costing
 
Audit of contracts version 2
Audit of contracts version 2Audit of contracts version 2
Audit of contracts version 2
 
MODULE 5.pptx
MODULE 5.pptxMODULE 5.pptx
MODULE 5.pptx
 
Revenue Recognition Serial Part 6: Step 5 - Recognizing Revenue as or When Pe...
Revenue Recognition Serial Part 6: Step 5 - Recognizing Revenue as or When Pe...Revenue Recognition Serial Part 6: Step 5 - Recognizing Revenue as or When Pe...
Revenue Recognition Serial Part 6: Step 5 - Recognizing Revenue as or When Pe...
 
Contract Costing.pptx
Contract Costing.pptxContract Costing.pptx
Contract Costing.pptx
 
151 Section B—Conforming Amendments Related to Revenue f.docx
151 Section B—Conforming Amendments Related to Revenue f.docx151 Section B—Conforming Amendments Related to Revenue f.docx
151 Section B—Conforming Amendments Related to Revenue f.docx
 
CPM lecture note 4,5,6&7.pdf
CPM lecture note 4,5,6&7.pdfCPM lecture note 4,5,6&7.pdf
CPM lecture note 4,5,6&7.pdf
 
CPM lecture note 4,5,6&7.pdf
CPM lecture note 4,5,6&7.pdfCPM lecture note 4,5,6&7.pdf
CPM lecture note 4,5,6&7.pdf
 
Prolongation and HOOH Costs
Prolongation and HOOH CostsProlongation and HOOH Costs
Prolongation and HOOH Costs
 
Construction contract_Existing and Proposed Accounting Standards
Construction contract_Existing and Proposed Accounting StandardsConstruction contract_Existing and Proposed Accounting Standards
Construction contract_Existing and Proposed Accounting Standards
 
Ias11
Ias11Ias11
Ias11
 
Prolongation cost calculation
Prolongation cost  calculation Prolongation cost  calculation
Prolongation cost calculation
 

More from EVERSENDAI ENGINEERING (L.L.C.) (20)

Supply chain management
Supply chain managementSupply chain management
Supply chain management
 
Laws company act
Laws company actLaws company act
Laws company act
 
Hrm
HrmHrm
Hrm
 
construction planning
construction planningconstruction planning
construction planning
 
Bim notes
Bim notesBim notes
Bim notes
 
basic qs notes
basic qs notesbasic qs notes
basic qs notes
 
statistics basic
statistics basicstatistics basic
statistics basic
 
Sustainability
Sustainability Sustainability
Sustainability
 
Stratergy notes 2
Stratergy notes 2Stratergy notes 2
Stratergy notes 2
 
Strategy note 1
Strategy note 1Strategy note 1
Strategy note 1
 
Qhsem
Qhsem Qhsem
Qhsem
 
Project planning notes
Project planning notesProject planning notes
Project planning notes
 
Quantity surveying notes......
Quantity surveying notes......  Quantity surveying notes......
Quantity surveying notes......
 
stakeholder management
stakeholder managementstakeholder management
stakeholder management
 
Finance
FinanceFinance
Finance
 
construction Contracts
construction Contractsconstruction Contracts
construction Contracts
 
Bim notes
Bim notesBim notes
Bim notes
 
Basic civil notes
Basic civil notesBasic civil notes
Basic civil notes
 
Reinforcement theory of motivation -proposed by bf skinner
Reinforcement theory of motivation -proposed by bf skinnerReinforcement theory of motivation -proposed by bf skinner
Reinforcement theory of motivation -proposed by bf skinner
 
Measurements in construction
Measurements in constructionMeasurements in construction
Measurements in construction
 

Recently uploaded

(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxhumanexperienceaaa
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 

Recently uploaded (20)

(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 

Cost value reconciliation (cvr)

  • 2.  Cost-value reconciliation (CVR) brings together the established totals for cost and value to illustrate the profitability of a company  The CVR serves two purposes  it forms the basis of statutory accounts  provides management information to assist in the identification of problems, the need for reserves, the reasons for loss and information to prevent repetition of such losses  At each interim valuation date, normally the end of each calendar month, the total costs to date are compared with the total valuation.
  • 3.  The cost-value comparison, or reconciliation, is usually completed by the contractor’s QS  starting point of any CVR must always be the gross certified value  Adjustments  adjustments for external preliminaries claimed in valuations against the internal preliminary schedule;  adjustments for elements included within costing but not in the external valuation, for example, materials brought to site on the same day as the valuation but after materials on site were recorded  items of over measurement not picked up by the client’s QS  any adjustments necessary to bring the cost cut-off date and the on-site valuation date together  variations which have not been agreed with the client’s QS  contractual claims for loss and/or expense which have not been agreed by the client’s QS  possibility of liquidated damages being charged by the employer  provision should be made for future known losses
  • 4.  Once the gross adjusted valuation has been assessed three further elements are deducted from the figure to arrive at a final residual value or margin  First, subcontract liabilities which should cover all disciplines of subcontractor,  second, snagging and defects which can be subdivided into two sections  Snagging required at the end of the project to achieve handover;  A levy to be used to cover for costs that may be incurred in the making good of defects period before the certificate of making good of defects is issued.  The third and final element of deduction is that of the main contractor’s core costs, that is, labour, material and plant and other associated costs. In general, these will be supplied to the contractor’s QS by a separate cost department within the contractor’s company  The residue is the profit generated from the main contractor’s works section of the project. When added to the profit on other sections, that is, the subcontract liability schedule, this indicates the profit to date for the project.
  • 5.
  • 6.
  • 7.
  • 8.