Project Scope Document
HRIS with ESS Project
GenRays
April Drake, Project Manager
2
Table of Contents
Project Scope Description........................................................................................................... 3
Customer Requirements.............................................................................................................. 3
Statement of Work........................................................................................................................ 4
Project Deliverables...................................................................................................................... 5
Acceptance Criteria...................................................................................................................... 5
Work Breakdown Structure ......................................................................................................... 6
Project Boundaries..................................................................................................................... 11
Budget.........................................................................................................................................11
Schedule ......................................................................................................................................11
Resources.....................................................................................................................................11
Project Staff Availability and Restrictions....................................................................................12
Project Assumptions.................................................................................................................. 12
Initial Defined Risks and Constraints....................................................................................... 13
Project Approval......................................................................................................................... 14
3
Project Scope Description
AfterrealizinggreaterthananticipatedROIwiththe rolloutof anew financial,logisticsandpurchasing
system,GenRaysdesirestofuel additional growthandexpansiontothe company.Withthe cost-savings
associatedwiththe automaticcalculationsexperiencedwiththe new technicallyadvanced system,they
are nowable to fundmore researchandprojectsto improve theirworkplace.
The HRIS and ESS projectwill attempttobringthe followingbenefitstoGenRays:
1) Furtherproductivity withEformsandautomaticcalculations
2) Addingandmaintainingthe talentpool withRecruitingandPerformance Review enhancements
3) Enable employeesabetterCareerPathmanagementandtrackingsystem
4) Decrease IT overhead,increase ReportingandAnalyticscapabilitieswithdatabase consolidation
5) Minimize riskinPayroll andEmployeeInformationtrackingandintegrate withLDAPdirectory
6) Increase Benefitsflexibilityandmanagementcapabilities
CustomerRequirements
AshleyBurrici
Benefits
Abilitytoacrue PTO basedonattendance insteadof yearsof service
Abilitytochange andapprove benefitsduringopenenrollment
Abilitytoviewbenefitcarrier'sinformationdirectlythroughGenRay'sOpenEnrollmentapplication
DB Consolidation
Abilitytoreport& manipulate datawithall recordsinthe same system
General Communications
Abilitytoemail employeesforgovernmentcompliance andcompanyinformation
Performance & Compensation
Abilitytodetermine amountof compensationincreasesawardedbasedonperformance
Brian Jenkins
DB Consolidation
Migrate old db'sintothe newsystem
Connie Barnett
DB Consolidation
Ensure HR and payroll data are in the same system
Payroll & Integrated ESS
Abilitytoaddmanagement-onlyinformation
Abilitytoentertime andattendance information
Abilitytoreview andapprove time andattendance informationbefore processing
Crystal Marshall
DB Consolidation
Ensure Directoryservice canintegrate withHRISdatabase
Eforms Capabilities
Abilitytocreate new Eforms
4
Eformshave "mail-merge"- like auto-populatecapability
Eformsscale to at least3700 per year
Employee InformationManagement(LDAP)
Abilitytoadd,change and quicklylocate the mostcurrentemployee info,incl.locations,phone,email
Darcy Martin
Performance & Compensation
Abilitytoanalyze actual costassociatedwithmanufacturingparticularcomponents
Abilitytoanalyze changesinemployeescompensationbyperformancedata
Abilitytoentergoalsatannual review
Abilitytoreconcile actual performance realized,toannual goals,atperiodicreviews
Abilitytosearchperformance review information
Jonathan Hartwig
DB Consolidation
Migrate current trainingrecordsdbintothe new HRIScentralizeddb
Training Records
Abilitytoanalyze whohastakentrainingandif resultwasmove togreaterauthorityposition
Abilitytomine performance review data
Rory Genhardt
SuccessionPlanning
Abilitytodefinecareerpathandtrack progressmeetingrequirements
Recruiting
Abilitytoanalyze whoismostinterestedandqualifiedfromcandidate pool
Abilitytoapplyforpositionsandmonitorprogressinhiringprogress
Performance & Compensation
Abilitytotrackanswersto performance reviews
Training Records
Abilitytoentercompletedcoursesandcertificates
Abilitytotracktrainingcoursesemployee completes
Rylee Anderson
PositionControl
Abilitytoanalyze employee compensationbyjobtitle andsalarygradesacrossmanufacturingsites
Tyler Guerts
Recruiting
Abilitytopushnotificationstoqualifiedcandidateswhenmatchingjobcriteriaidentified
Abilitytorecordandsearch forexternal resumesfromcollege campusvisits
Statement of Work
The projectteam will worktoinitiate,plan,execute,monitorandcontrol,andclose all phasesof the
HRIS withESS project,withinthe boundariesprescribedbyseniormanagement.The projectteamwill
reportto seniormanagementatkeymilestonesinthe projectandworkto mitigate anyrisksalongthe
way.Vendorswill be evaluatedtodeliverthe technologyandimplementationof the system,however
these costsshouldbe weighedagainstbuildingin-house asanoptionto vetthe decisiontobuy.The
5
workshouldinclude trainingof all GenRaysemployeesonthe new system.The new systemwill have
keyperformance indicatorswhichwill establishsuccesstowardsmeetingprojectobjectives,bothduring
and afterthe systemisimplemented,andlessonslearnedshouldbe archivedforfuture projectresearch
artifacts.
Project Deliverables
Project Phase Deliverable Timeframe
Initiation Develop ProjectCharter, ConductFeasibilityReport tovet
BuildvsBuy decision,Acquire ProjectApproval
Jan – Feb2015
Planning DevelopProjectManagementPlan& Sub-Plans, Assign
Team MemberstoWBS, Conduct SystemandVendor
Procurements, DesignSystem&Modulesincluding
interfaces,ApprovePrototype
March-May 2015
Development Develop Base SystemInfrastructure June-July2015
Develop&Integrate SystemModules,PlanTraining August-Sept2015
Implementation Acquire Acceptance, ConductTrainingof staff October2015
Closing Assessmentof ROI,Lesson’sLearned,Close
Procurements,Celebration
Nov-Jan2015
Acceptance Criteria
Acceptance of the systemto be achievedthroughthe followingkeystakeholders onthese requirements:
SystemComponent Requirement Stakeholder
Benefits Abilitytoaccrue PTO basedonattendance insteadof
yearsof service
AshleyBurrici
Abilitytochange andapprove benefitsduringopen
enrollment
AshleyBurrici
Databases Abilitytoreport& manipulate datawithall recordsin
the same system
AshleyBurrici
Ensure HR and payroll data are in the same system Connie Barnett
Migrate current trainingrecordsdbintothe new HRIS
centralizeddb
JonathanHartwig
Migrate old db'sintothe new system Brian Jenkins
Eforms Capabilities Abilitytocreate new Eforms Crystal Marshall
Eformshave "mail-merge"- like auto-populate
capability
Crystal Marshall
Employee
Information
Management
Abilitytoadd,change and quicklylocate the most
currentemployee info,incl.locations,phone,email
Crystal Marshall
Abilityforemployeestomaintaintheirown
information
Crystal Marshall
General
Communications
Abilitytoemail employeesforgovernmentcompliance
and companyinformation
AshleyBurrici
6
Payroll & Integrated
ESS
Abilitytoaddmanagement-onlyinformation Connie Barnett
Abilitytoentertime andattendance information Connie Barnett
Abilitytoreview andapprove time andattendance
informationbefore processing
Connie Barnett
Performance Review
& Compensation
Abilitytoanalyze actual costassociatedwith
manufacturingparticularcomponents
Darcy Martin
Abilitytoanalyze changesinemployeescompensation
by performance data
Darcy Martin
Abilitytodetermine amountof compensation
increasesawardedbasedonperformance
AshleyBurrici
Abilitytoentergoalsatannual review Darcy Martin
Abilitytoreconcile actual performance realized,to
annual goals,at periodicreviews
Darcy Martin
Abilitytosearchperformance review information Darcy Martin
PositionControl Abilitytoanalyze employee compensationbyjobtitle
and salarygradesacross manufacturingsites
Rylee Anderson
RecruitingDatabase
- Reporting&
Notifications
Abilitytopushnotificationstoqualifiedcandidates
whenmatchingjobcriteriaidentified
TylerGuerts
RecruitingEfforts Abilitytoanalyze whoismostinterestedandqualified
fromcandidate pool
Rory Genhardt
Abilitytoapplyforpositionsandmonitorprogressin
hiringprogress
Rory Genhardt
Abilitytorecordandsearch forexternal resumesfrom
college campusvisits
TylerGuerts
SuccessionPlanning Abilitytodefinecareerpathandtrack progress
meetingrequirements
Rory Genhardt
Abilitytoentercompletedcoursesandcertificates Rory Genhardt
Abilitytotrackanswersto performance reviews Rory Genhardt
Abilitytotracktrainingcoursesemployee completes Rory Genhardt
SystemIntegration Abilitytoviewbenefitcarrier'sinformationdirectly
throughGenRay'sOpenEnrollmentapplication
AshleyBurrici
Ensure Directoryservice canintegrate withHRIS
database
Crystal Marshall
Capacity
Requirement
Eformsscale to at least3700 per year Crystal Marshall
Training Records Abilitytoanalyze whohastakentrainingandif result
was move togreaterauthorityposition
JonathanHartwig
Abilitytomine performance review data JonathanHartwig
Work Breakdown Structure
WBS Name Resource Names Deliverable
7
1 Project InitiationPhase Project Manager,Sponsors
1.1 Develop ProjectCharter ProjectManager,Sponsors
1.1.1 RequirementsGathering ProjectManager
1.1.2 ProjectCharter ProjectManager ProjectCharter
1.1.3 ProjectCharterReview ProjectManager,Sponsors ProjectCharter
Approval
1.2 ConductFeasibilityStudy
1.2.1 FeasibilityReport ProjectManager FeasibilityReport
1.2.2 ResearchPhase Review &
Approval
ProjectManager,Sponsors BuildVs.BuyDecision
1.2.3 Team LeadsAssignment ProjectManager,Sponsors ProjectManagement
Team Assignments
2 Designing& PlanningPhase
2.1 Develop ProjectManagement
Plan
Team Leads, Project
Manager
2.1.1 PlanScope & Requirements
Management
2.1.1.1 Define Scope ProjectManager ProjectScope
Statement
2.1.1.2 Create WBS ProjectManager WBS
2.1.2 PlanSchedule Management Team Leads, Project
Manager
2.1.2.1 Define Activities
8
2.1.2.2 Sequence Activities
2.1.2.3 Estimate ActivityResources
2.1.2.4 Estimate ActivityDurations
2.1.2.5 DevelopSchedule ProjectManager ProjectSchedule
includingCritical Path
2.1.3 PlanCost Management ProjectManager, Team
Leads
2.1.3.1 Estimate Costs ProjectManager, Team
Leads
2.1.3.2 Determine Budget ProjectManager
2.1.4 PlanQualityManagement ProjectManager, Team
Leads
2.1.5 PlanHR Management ProjectManager, Team
Leads
2.1.6 PlanCommunication
Management
ProjectManager Project
CommunicationsPlan
2.1.7 PlanRiskManagement ProjectManager, Team
Leads
2.1.7.1 IdentifyRisks
2.1.7.2 PerformQualitativeRisk
Analysis
2.1.7.3 PerformQuantitativeRisk
Analysis
2.1.7.4 PlanRiskResponses
9
2.1.8 PlanProcurement
Management
ProjectManager, Team
Leads
2.1.9 PlanStakeholderManagement ProjectManager ProjectStakeholder
Register
2.2 ProjectPlan Review &
Approval
ProjectManager, Team
Leads,Sponsors
ProjectManagement
Plan and Approval
3 Carrying Out the Work Phase
3.1 ConductProcurements VendorSelected
3.1.1 Acquire ProjectTeam ProjectManager ProjectTeam
Assignments
3.1.2 DevelopProjectTeam ProjectManager Kickoff Meeting
3.2 Pilot Phase
3.2.1 Planning(System
Architecture)
Team Leads Architecture Diagrams
3.2.2 Developing(Prototype) ProjectManager, Team
Leads, Vendor, Team
Members
3.2.3 PilotReview &Signoff Team Leads Pilot
3.3 Production Phase
3.3.1 Determine FAQsforUI Team Leads, TeamMembers,
Vendor
3.3.2 Share FAQsfor UI Team Leads FAQsfor UI
3.3.3 PlatformDevelopment
10
3.3.3.1 Preparing Team Leads, TeamMembers,
Vendor
3.3.3.2 Developing Vendor, TeamLeads, Team
Members
3.3.3.3 PerformQualityAssurance Team Leads PlatformQA Checklist
3.3.4 ModulesDevelopment
3.3.4.1 Preparing Team Leads, TeamMembers,
Vendor
3.3.4.2 Developing Team Leads, TeamMembers,
Vendor
3.3.4.3 PerformQualityAssurance Team Leads ModulesQA Checklist
3.3.5 ProductionReview&Signoff ProjectManager Implementation
Signoff
3.4 DeploymentPhase
3.4.1 TrainingPlanning ProjectManager TrainingSchedule &
Artifacts
3.4.2 Training All Employees, Project
Manager, Sponsors, Team
Leads, TeamMembers,
Vendor
4 ClosingPhase
4.1 Close Procurements ProjectManager, Team
Leads
4.2 LessonsLearned ProjectManager LessonsLearned
11
4.3 SuccessMeasurements ProjectManager, Team
Leads, Team Members
KPIMeasurements
4.4 ArtifactsArchiving ProjectManager, Team
Leads
Project Boundaries
Budget
103K is allocatedforthe entire project.Itisassumedthisisforthe procurements,includingany
hardware and software licensed,anyvendorshired,andinternal staff time allocatedtocomplete
projecttasks.
Schedule
As perinternal HRmemo,workmay start afterW2s are issued,but thatprojectmust be complete with
all systemelementsfunctional before year-endclosing.
Resources
Sponsorshave indicatedthatthe ProjectManagershouldcoordinate withteamleadspriortoassigning
projectsupportstaff,inorderto ensure manageable levelsof conflictsothatit doesn’tovershadowthe
successof the progressforthe week.
In orderto observe thisrequest,the resourceswill be assignedinthe ProjectManagementPlanwhich
will be approvedbythe teamleads,and the PMP will reference how change control willbe managedif
any reschedulingorresource conflictsarise,inordertoobserve the request.
The financial systemsoverhaul usedcompanyresourcesthatprovedtobe effectiveinaccomplishingthe
objectives forthe projectandshouldbe leveragedagain if possible,withrespectforthe considerations
on theirtime andotherrestrictions outlinedinthe HRmemorandums.
Resourcesallocatedmustnotviolate the HRpolicyorindividualconstraintsof 8hour workdays,5 days
perweek.
12
ProjectStaffAvailabilityandRestrictions
Project Assumptions
A Buildvs.Buyanalysiswill be performed duringthe feasibilitystudy inordertoassessviabilityof
solutionsbuiltin-house tothose offeredbyvendor.
BestPracticesand Organizational Factorswill influence the nature of the projectactivities.
It isassumedthat the projectcostsinclude forall personnel man-hoursdevotedtoprojecttasks
includingprojectmanagement.
Name Avail for projects?Other Current ProjectsHours avail each weekRestrictions Compatible Incompatible
April Drake yes 40
Rory Genhardt no
Crystal Marshall no
Connie Barnett no
Darcy Martin no
Ashley Burrici no
Jonathan Hartwigyes
Rylee Anderson yes Management 5 Devon
Tyler Guerts yes Management 5
Cameron yes Audits 35 Madison
Madison yes none 40 Cameron
Chase yes Inventory 40 Unavailable last 2 weeks of June and December. Carson
Carson yes Maintenance 35 none Chase
Shea yes Product Evaluation 30 none Jessie
Jessie yes Data Analysis 30 none Shea
Shannon yes Market Research 40 Unavailable the last week of each quarter.
Bailey yes Marketing Communications20 none
Jamie yes Recruiting 40 Unavailable in April and May.
Logan yes Recruiting 40 Unavailable in July and August
Chris yes Sales Forecasts 30 none
Ryan yes Sales Forecasts 30 none Alex
Amari yes Inspections 35 none
Alex yes Data Analysis 40 none Ryan
Devon yes Training 30 Unavailable 1 week in April, June and November.Rylee Anderson
Harly yes Benefits Analysis 40 Unavailable 4 weeks in June
Kasey yes none 40 none
Kendall yes Programming 40 Unavailable in January and February
Drew yes Contracting 40 Unavailable in July
Morgan yes Product Evaluation 35
Ashton yes Design 30
Jordan yes Inventory 40 Unavailable last 2 weeks June and December
Dakota yes Materials Analysis 40 Unavailable 3 weeks in August
Jayden yes Materials Analysis 40 Unavailable 3 weeks in August
13
Initial DefinedRisks and Constraints
Risk Impact
Likelihood
of
Occurrence
(L,M,H)
Degree
of
Impact
(L,M,H) Action Trigger Responsibility Response Plan
Stakeholders in the
project teams
categorized as
Resistor may
interfere with
project objectives
and success
Medium M M
Progress towards
deliverables isn’t
as forecast
Project Manager
Do not staff possible
Resistor resources on
project unless
absolutely necessary,
use relationships and
management influence
and buy-in tactics to
gain acceptance from
resistors into project
goals (Surveys, input
into plans, etc.)
Project team
members not
getting along
interfere with team
ability to make
progress on project
objectives
Medium M M
Complaints within
the team
regarding other
team-members
attitudes or
performance
Team Lead
Attempt to mitigate with
functional manager
intervention, as with
lesson’s learned from
financial system project
this worked. If cannot
be mitigated, seek to
move scheduled tasks,
or remove one member
from the project.
Development cost
overruns due to
unforeseen
technical
challenges
High L H
Critical Path
analysis shows
behind schedule
on meeting Pilot
or Development
deliverables
Project Manager
First, if outsourcing, seek
to work with same or
similar vendor used in
financial project as they
experienced great
success and their systems
are already known to work
with ours. If building in-
house, assess if new
development staff need to
be added to project.
Second, if unrelated to
resources, seek to either
increase budget or time
constraints if necessary to
meet scope, or present
option to management to
cut scope.
14
Sensitive employee
data leaks to either
internal or external
sources during
migration or
implementation
High L H
Any employee or
other resource
observing
sensitive
employee data
leaking to any
inappropriate
resources
Team Members,
Leads, Project
Managers
First, seek to avoid
incident by having
highly technical staff
review the system
design and quality
assurance plans. If
incident occurs,
immediately secure the
data and seek to
remove from all
inappropriate sources.
Notify employee of
incident and extent of
PII leaked.
Troubleshoot issue and
have IT staff resolve.
System complexity
too great and too
many integration
issues uncovered,
resources not fully
utilized due to
dependencies
High M H
Team Members,
Vendors
Modulate the deployment
such that system is
done first, and then
each component
module is done after
System is stabilized.
Each module broken
down by area of
expertise so can be run
in parallel.
System downtime due
to unforeseen events
(power outages,
natural disasters,
security patching,
troubleshooting critical
issues)
High L H
Any critical system
impacted such
that it is
offline/unusable
for a moderate
to substantial
time during
project execution
Team Members,
Vendors
Useindustry Best
Practices for security,
fault tolerance and
redundancy such that
development isn’t
impacted. Havebackup
plan for all critical
systems including
options such as off-
prem resources as
options (cloud).
Project Team
members availability
impacted adversely by
unforeseen events or
priority conflicts
High M H
Any project
milestone begins
to slip due to
availability, team
meetings and
status
milestones
Team Members,
Vendors,
Project
Management
Staff backups/teams of
people instead of just
single resources, to as
many areas of the
project as possible,
without overstaffing
which would adversely
impact budget.
Key: L = low, M= medium, H = high
Project Approval
Approved by the Project Sponsor:
__________________________________________ Date: ___________________
15
<Project Sponsor> <Project Sponsor Title>

More Related Content

Similar to GenRays Project Scope Document

A guide for automated testing
A guide for automated testingA guide for automated testing
A guide for automated testingMoataz Nabil
 
Sabiron PLM Project Methodology.pdf
Sabiron PLM Project Methodology.pdfSabiron PLM Project Methodology.pdf
Sabiron PLM Project Methodology.pdfBrion Carroll (II)
 
El valor de la migración y Modernizacion a Microsoft azure
El valor de la migración y Modernizacion a Microsoft azureEl valor de la migración y Modernizacion a Microsoft azure
El valor de la migración y Modernizacion a Microsoft azureCade Soluciones
 
CPIN 269 Final Documentation
CPIN 269 Final DocumentationCPIN 269 Final Documentation
CPIN 269 Final DocumentationJennifer Cordes
 
Using ADO.NET Entity Framework in Domain Driven Design: A Pattern Approach
Using ADO.NET Entity Framework in Domain Driven Design: A Pattern ApproachUsing ADO.NET Entity Framework in Domain Driven Design: A Pattern Approach
Using ADO.NET Entity Framework in Domain Driven Design: A Pattern ApproachHoan Phuc
 
PMI-ACP Case Study
PMI-ACP Case StudyPMI-ACP Case Study
PMI-ACP Case StudyThanh Nguyen
 
Digital Content Retrieval Final Report
Digital Content Retrieval Final ReportDigital Content Retrieval Final Report
Digital Content Retrieval Final ReportKourosh Sajjadi
 
Project Handover Document Template
Project Handover Document TemplateProject Handover Document Template
Project Handover Document TemplateBody of Knowledge
 
TaskYou are required to prepare for this Assessment Item by1..docx
TaskYou are required to prepare for this Assessment Item by1..docxTaskYou are required to prepare for this Assessment Item by1..docx
TaskYou are required to prepare for this Assessment Item by1..docxbradburgess22840
 
TaskYou are required to prepare for this Assessment Item by1..docx
TaskYou are required to prepare for this Assessment Item by1..docxTaskYou are required to prepare for this Assessment Item by1..docx
TaskYou are required to prepare for this Assessment Item by1..docxdeanmtaylor1545
 
Accenture Case Study Solution by Amit Bhardwaj
Accenture Case Study Solution by Amit BhardwajAccenture Case Study Solution by Amit Bhardwaj
Accenture Case Study Solution by Amit BhardwajAmit Bhardwaj
 
Info461ProjectCharterEskridgeAs08
Info461ProjectCharterEskridgeAs08Info461ProjectCharterEskridgeAs08
Info461ProjectCharterEskridgeAs08Greg Eskridge
 
Running Head Project Overview Statement1Project Overview Stat.docx
Running Head Project Overview Statement1Project Overview Stat.docxRunning Head Project Overview Statement1Project Overview Stat.docx
Running Head Project Overview Statement1Project Overview Stat.docxtodd581
 
Project Management Report - 2Assignment 2Project Managemen.docx
Project Management Report - 2Assignment 2Project Managemen.docxProject Management Report - 2Assignment 2Project Managemen.docx
Project Management Report - 2Assignment 2Project Managemen.docxwkyra78
 
Project management-plan
Project management-planProject management-plan
Project management-planTran Tien
 

Similar to GenRays Project Scope Document (20)

SDM Term Project (DWMT Consulting)
SDM Term Project (DWMT Consulting)SDM Term Project (DWMT Consulting)
SDM Term Project (DWMT Consulting)
 
A guide for automated testing
A guide for automated testingA guide for automated testing
A guide for automated testing
 
Sabiron PLM Project Methodology.pdf
Sabiron PLM Project Methodology.pdfSabiron PLM Project Methodology.pdf
Sabiron PLM Project Methodology.pdf
 
El valor de la migración y Modernizacion a Microsoft azure
El valor de la migración y Modernizacion a Microsoft azureEl valor de la migración y Modernizacion a Microsoft azure
El valor de la migración y Modernizacion a Microsoft azure
 
CPIN 269 Final Documentation
CPIN 269 Final DocumentationCPIN 269 Final Documentation
CPIN 269 Final Documentation
 
Using ADO.NET Entity Framework in Domain Driven Design: A Pattern Approach
Using ADO.NET Entity Framework in Domain Driven Design: A Pattern ApproachUsing ADO.NET Entity Framework in Domain Driven Design: A Pattern Approach
Using ADO.NET Entity Framework in Domain Driven Design: A Pattern Approach
 
PMI-ACP Case Study
PMI-ACP Case StudyPMI-ACP Case Study
PMI-ACP Case Study
 
Digital Content Retrieval Final Report
Digital Content Retrieval Final ReportDigital Content Retrieval Final Report
Digital Content Retrieval Final Report
 
Project Handover Document Template
Project Handover Document TemplateProject Handover Document Template
Project Handover Document Template
 
TaskYou are required to prepare for this Assessment Item by1..docx
TaskYou are required to prepare for this Assessment Item by1..docxTaskYou are required to prepare for this Assessment Item by1..docx
TaskYou are required to prepare for this Assessment Item by1..docx
 
TaskYou are required to prepare for this Assessment Item by1..docx
TaskYou are required to prepare for this Assessment Item by1..docxTaskYou are required to prepare for this Assessment Item by1..docx
TaskYou are required to prepare for this Assessment Item by1..docx
 
0.3 aim phases_and_documentations
0.3 aim phases_and_documentations0.3 aim phases_and_documentations
0.3 aim phases_and_documentations
 
Accenture Case Study Solution by Amit Bhardwaj
Accenture Case Study Solution by Amit BhardwajAccenture Case Study Solution by Amit Bhardwaj
Accenture Case Study Solution by Amit Bhardwaj
 
Evolve methodology
Evolve methodologyEvolve methodology
Evolve methodology
 
Info461ProjectCharterEskridgeAs08
Info461ProjectCharterEskridgeAs08Info461ProjectCharterEskridgeAs08
Info461ProjectCharterEskridgeAs08
 
Running Head Project Overview Statement1Project Overview Stat.docx
Running Head Project Overview Statement1Project Overview Stat.docxRunning Head Project Overview Statement1Project Overview Stat.docx
Running Head Project Overview Statement1Project Overview Stat.docx
 
Project Management Report - 2Assignment 2Project Managemen.docx
Project Management Report - 2Assignment 2Project Managemen.docxProject Management Report - 2Assignment 2Project Managemen.docx
Project Management Report - 2Assignment 2Project Managemen.docx
 
Montero thesis-project
Montero thesis-projectMontero thesis-project
Montero thesis-project
 
Dimensions iom training
Dimensions iom trainingDimensions iom training
Dimensions iom training
 
Project management-plan
Project management-planProject management-plan
Project management-plan
 

GenRays Project Scope Document

  • 1. Page 1 Project Scope Document HRIS with ESS Project GenRays April Drake, Project Manager
  • 2. 2 Table of Contents Project Scope Description........................................................................................................... 3 Customer Requirements.............................................................................................................. 3 Statement of Work........................................................................................................................ 4 Project Deliverables...................................................................................................................... 5 Acceptance Criteria...................................................................................................................... 5 Work Breakdown Structure ......................................................................................................... 6 Project Boundaries..................................................................................................................... 11 Budget.........................................................................................................................................11 Schedule ......................................................................................................................................11 Resources.....................................................................................................................................11 Project Staff Availability and Restrictions....................................................................................12 Project Assumptions.................................................................................................................. 12 Initial Defined Risks and Constraints....................................................................................... 13 Project Approval......................................................................................................................... 14
  • 3. 3 Project Scope Description AfterrealizinggreaterthananticipatedROIwiththe rolloutof anew financial,logisticsandpurchasing system,GenRaysdesirestofuel additional growthandexpansiontothe company.Withthe cost-savings associatedwiththe automaticcalculationsexperiencedwiththe new technicallyadvanced system,they are nowable to fundmore researchandprojectsto improve theirworkplace. The HRIS and ESS projectwill attempttobringthe followingbenefitstoGenRays: 1) Furtherproductivity withEformsandautomaticcalculations 2) Addingandmaintainingthe talentpool withRecruitingandPerformance Review enhancements 3) Enable employeesabetterCareerPathmanagementandtrackingsystem 4) Decrease IT overhead,increase ReportingandAnalyticscapabilitieswithdatabase consolidation 5) Minimize riskinPayroll andEmployeeInformationtrackingandintegrate withLDAPdirectory 6) Increase Benefitsflexibilityandmanagementcapabilities CustomerRequirements AshleyBurrici Benefits Abilitytoacrue PTO basedonattendance insteadof yearsof service Abilitytochange andapprove benefitsduringopenenrollment Abilitytoviewbenefitcarrier'sinformationdirectlythroughGenRay'sOpenEnrollmentapplication DB Consolidation Abilitytoreport& manipulate datawithall recordsinthe same system General Communications Abilitytoemail employeesforgovernmentcompliance andcompanyinformation Performance & Compensation Abilitytodetermine amountof compensationincreasesawardedbasedonperformance Brian Jenkins DB Consolidation Migrate old db'sintothe newsystem Connie Barnett DB Consolidation Ensure HR and payroll data are in the same system Payroll & Integrated ESS Abilitytoaddmanagement-onlyinformation Abilitytoentertime andattendance information Abilitytoreview andapprove time andattendance informationbefore processing Crystal Marshall DB Consolidation Ensure Directoryservice canintegrate withHRISdatabase Eforms Capabilities Abilitytocreate new Eforms
  • 4. 4 Eformshave "mail-merge"- like auto-populatecapability Eformsscale to at least3700 per year Employee InformationManagement(LDAP) Abilitytoadd,change and quicklylocate the mostcurrentemployee info,incl.locations,phone,email Darcy Martin Performance & Compensation Abilitytoanalyze actual costassociatedwithmanufacturingparticularcomponents Abilitytoanalyze changesinemployeescompensationbyperformancedata Abilitytoentergoalsatannual review Abilitytoreconcile actual performance realized,toannual goals,atperiodicreviews Abilitytosearchperformance review information Jonathan Hartwig DB Consolidation Migrate current trainingrecordsdbintothe new HRIScentralizeddb Training Records Abilitytoanalyze whohastakentrainingandif resultwasmove togreaterauthorityposition Abilitytomine performance review data Rory Genhardt SuccessionPlanning Abilitytodefinecareerpathandtrack progressmeetingrequirements Recruiting Abilitytoanalyze whoismostinterestedandqualifiedfromcandidate pool Abilitytoapplyforpositionsandmonitorprogressinhiringprogress Performance & Compensation Abilitytotrackanswersto performance reviews Training Records Abilitytoentercompletedcoursesandcertificates Abilitytotracktrainingcoursesemployee completes Rylee Anderson PositionControl Abilitytoanalyze employee compensationbyjobtitle andsalarygradesacrossmanufacturingsites Tyler Guerts Recruiting Abilitytopushnotificationstoqualifiedcandidateswhenmatchingjobcriteriaidentified Abilitytorecordandsearch forexternal resumesfromcollege campusvisits Statement of Work The projectteam will worktoinitiate,plan,execute,monitorandcontrol,andclose all phasesof the HRIS withESS project,withinthe boundariesprescribedbyseniormanagement.The projectteamwill reportto seniormanagementatkeymilestonesinthe projectandworkto mitigate anyrisksalongthe way.Vendorswill be evaluatedtodeliverthe technologyandimplementationof the system,however these costsshouldbe weighedagainstbuildingin-house asanoptionto vetthe decisiontobuy.The
  • 5. 5 workshouldinclude trainingof all GenRaysemployeesonthe new system.The new systemwill have keyperformance indicatorswhichwill establishsuccesstowardsmeetingprojectobjectives,bothduring and afterthe systemisimplemented,andlessonslearnedshouldbe archivedforfuture projectresearch artifacts. Project Deliverables Project Phase Deliverable Timeframe Initiation Develop ProjectCharter, ConductFeasibilityReport tovet BuildvsBuy decision,Acquire ProjectApproval Jan – Feb2015 Planning DevelopProjectManagementPlan& Sub-Plans, Assign Team MemberstoWBS, Conduct SystemandVendor Procurements, DesignSystem&Modulesincluding interfaces,ApprovePrototype March-May 2015 Development Develop Base SystemInfrastructure June-July2015 Develop&Integrate SystemModules,PlanTraining August-Sept2015 Implementation Acquire Acceptance, ConductTrainingof staff October2015 Closing Assessmentof ROI,Lesson’sLearned,Close Procurements,Celebration Nov-Jan2015 Acceptance Criteria Acceptance of the systemto be achievedthroughthe followingkeystakeholders onthese requirements: SystemComponent Requirement Stakeholder Benefits Abilitytoaccrue PTO basedonattendance insteadof yearsof service AshleyBurrici Abilitytochange andapprove benefitsduringopen enrollment AshleyBurrici Databases Abilitytoreport& manipulate datawithall recordsin the same system AshleyBurrici Ensure HR and payroll data are in the same system Connie Barnett Migrate current trainingrecordsdbintothe new HRIS centralizeddb JonathanHartwig Migrate old db'sintothe new system Brian Jenkins Eforms Capabilities Abilitytocreate new Eforms Crystal Marshall Eformshave "mail-merge"- like auto-populate capability Crystal Marshall Employee Information Management Abilitytoadd,change and quicklylocate the most currentemployee info,incl.locations,phone,email Crystal Marshall Abilityforemployeestomaintaintheirown information Crystal Marshall General Communications Abilitytoemail employeesforgovernmentcompliance and companyinformation AshleyBurrici
  • 6. 6 Payroll & Integrated ESS Abilitytoaddmanagement-onlyinformation Connie Barnett Abilitytoentertime andattendance information Connie Barnett Abilitytoreview andapprove time andattendance informationbefore processing Connie Barnett Performance Review & Compensation Abilitytoanalyze actual costassociatedwith manufacturingparticularcomponents Darcy Martin Abilitytoanalyze changesinemployeescompensation by performance data Darcy Martin Abilitytodetermine amountof compensation increasesawardedbasedonperformance AshleyBurrici Abilitytoentergoalsatannual review Darcy Martin Abilitytoreconcile actual performance realized,to annual goals,at periodicreviews Darcy Martin Abilitytosearchperformance review information Darcy Martin PositionControl Abilitytoanalyze employee compensationbyjobtitle and salarygradesacross manufacturingsites Rylee Anderson RecruitingDatabase - Reporting& Notifications Abilitytopushnotificationstoqualifiedcandidates whenmatchingjobcriteriaidentified TylerGuerts RecruitingEfforts Abilitytoanalyze whoismostinterestedandqualified fromcandidate pool Rory Genhardt Abilitytoapplyforpositionsandmonitorprogressin hiringprogress Rory Genhardt Abilitytorecordandsearch forexternal resumesfrom college campusvisits TylerGuerts SuccessionPlanning Abilitytodefinecareerpathandtrack progress meetingrequirements Rory Genhardt Abilitytoentercompletedcoursesandcertificates Rory Genhardt Abilitytotrackanswersto performance reviews Rory Genhardt Abilitytotracktrainingcoursesemployee completes Rory Genhardt SystemIntegration Abilitytoviewbenefitcarrier'sinformationdirectly throughGenRay'sOpenEnrollmentapplication AshleyBurrici Ensure Directoryservice canintegrate withHRIS database Crystal Marshall Capacity Requirement Eformsscale to at least3700 per year Crystal Marshall Training Records Abilitytoanalyze whohastakentrainingandif result was move togreaterauthorityposition JonathanHartwig Abilitytomine performance review data JonathanHartwig Work Breakdown Structure WBS Name Resource Names Deliverable
  • 7. 7 1 Project InitiationPhase Project Manager,Sponsors 1.1 Develop ProjectCharter ProjectManager,Sponsors 1.1.1 RequirementsGathering ProjectManager 1.1.2 ProjectCharter ProjectManager ProjectCharter 1.1.3 ProjectCharterReview ProjectManager,Sponsors ProjectCharter Approval 1.2 ConductFeasibilityStudy 1.2.1 FeasibilityReport ProjectManager FeasibilityReport 1.2.2 ResearchPhase Review & Approval ProjectManager,Sponsors BuildVs.BuyDecision 1.2.3 Team LeadsAssignment ProjectManager,Sponsors ProjectManagement Team Assignments 2 Designing& PlanningPhase 2.1 Develop ProjectManagement Plan Team Leads, Project Manager 2.1.1 PlanScope & Requirements Management 2.1.1.1 Define Scope ProjectManager ProjectScope Statement 2.1.1.2 Create WBS ProjectManager WBS 2.1.2 PlanSchedule Management Team Leads, Project Manager 2.1.2.1 Define Activities
  • 8. 8 2.1.2.2 Sequence Activities 2.1.2.3 Estimate ActivityResources 2.1.2.4 Estimate ActivityDurations 2.1.2.5 DevelopSchedule ProjectManager ProjectSchedule includingCritical Path 2.1.3 PlanCost Management ProjectManager, Team Leads 2.1.3.1 Estimate Costs ProjectManager, Team Leads 2.1.3.2 Determine Budget ProjectManager 2.1.4 PlanQualityManagement ProjectManager, Team Leads 2.1.5 PlanHR Management ProjectManager, Team Leads 2.1.6 PlanCommunication Management ProjectManager Project CommunicationsPlan 2.1.7 PlanRiskManagement ProjectManager, Team Leads 2.1.7.1 IdentifyRisks 2.1.7.2 PerformQualitativeRisk Analysis 2.1.7.3 PerformQuantitativeRisk Analysis 2.1.7.4 PlanRiskResponses
  • 9. 9 2.1.8 PlanProcurement Management ProjectManager, Team Leads 2.1.9 PlanStakeholderManagement ProjectManager ProjectStakeholder Register 2.2 ProjectPlan Review & Approval ProjectManager, Team Leads,Sponsors ProjectManagement Plan and Approval 3 Carrying Out the Work Phase 3.1 ConductProcurements VendorSelected 3.1.1 Acquire ProjectTeam ProjectManager ProjectTeam Assignments 3.1.2 DevelopProjectTeam ProjectManager Kickoff Meeting 3.2 Pilot Phase 3.2.1 Planning(System Architecture) Team Leads Architecture Diagrams 3.2.2 Developing(Prototype) ProjectManager, Team Leads, Vendor, Team Members 3.2.3 PilotReview &Signoff Team Leads Pilot 3.3 Production Phase 3.3.1 Determine FAQsforUI Team Leads, TeamMembers, Vendor 3.3.2 Share FAQsfor UI Team Leads FAQsfor UI 3.3.3 PlatformDevelopment
  • 10. 10 3.3.3.1 Preparing Team Leads, TeamMembers, Vendor 3.3.3.2 Developing Vendor, TeamLeads, Team Members 3.3.3.3 PerformQualityAssurance Team Leads PlatformQA Checklist 3.3.4 ModulesDevelopment 3.3.4.1 Preparing Team Leads, TeamMembers, Vendor 3.3.4.2 Developing Team Leads, TeamMembers, Vendor 3.3.4.3 PerformQualityAssurance Team Leads ModulesQA Checklist 3.3.5 ProductionReview&Signoff ProjectManager Implementation Signoff 3.4 DeploymentPhase 3.4.1 TrainingPlanning ProjectManager TrainingSchedule & Artifacts 3.4.2 Training All Employees, Project Manager, Sponsors, Team Leads, TeamMembers, Vendor 4 ClosingPhase 4.1 Close Procurements ProjectManager, Team Leads 4.2 LessonsLearned ProjectManager LessonsLearned
  • 11. 11 4.3 SuccessMeasurements ProjectManager, Team Leads, Team Members KPIMeasurements 4.4 ArtifactsArchiving ProjectManager, Team Leads Project Boundaries Budget 103K is allocatedforthe entire project.Itisassumedthisisforthe procurements,includingany hardware and software licensed,anyvendorshired,andinternal staff time allocatedtocomplete projecttasks. Schedule As perinternal HRmemo,workmay start afterW2s are issued,but thatprojectmust be complete with all systemelementsfunctional before year-endclosing. Resources Sponsorshave indicatedthatthe ProjectManagershouldcoordinate withteamleadspriortoassigning projectsupportstaff,inorderto ensure manageable levelsof conflictsothatit doesn’tovershadowthe successof the progressforthe week. In orderto observe thisrequest,the resourceswill be assignedinthe ProjectManagementPlanwhich will be approvedbythe teamleads,and the PMP will reference how change control willbe managedif any reschedulingorresource conflictsarise,inordertoobserve the request. The financial systemsoverhaul usedcompanyresourcesthatprovedtobe effectiveinaccomplishingthe objectives forthe projectandshouldbe leveragedagain if possible,withrespectforthe considerations on theirtime andotherrestrictions outlinedinthe HRmemorandums. Resourcesallocatedmustnotviolate the HRpolicyorindividualconstraintsof 8hour workdays,5 days perweek.
  • 12. 12 ProjectStaffAvailabilityandRestrictions Project Assumptions A Buildvs.Buyanalysiswill be performed duringthe feasibilitystudy inordertoassessviabilityof solutionsbuiltin-house tothose offeredbyvendor. BestPracticesand Organizational Factorswill influence the nature of the projectactivities. It isassumedthat the projectcostsinclude forall personnel man-hoursdevotedtoprojecttasks includingprojectmanagement. Name Avail for projects?Other Current ProjectsHours avail each weekRestrictions Compatible Incompatible April Drake yes 40 Rory Genhardt no Crystal Marshall no Connie Barnett no Darcy Martin no Ashley Burrici no Jonathan Hartwigyes Rylee Anderson yes Management 5 Devon Tyler Guerts yes Management 5 Cameron yes Audits 35 Madison Madison yes none 40 Cameron Chase yes Inventory 40 Unavailable last 2 weeks of June and December. Carson Carson yes Maintenance 35 none Chase Shea yes Product Evaluation 30 none Jessie Jessie yes Data Analysis 30 none Shea Shannon yes Market Research 40 Unavailable the last week of each quarter. Bailey yes Marketing Communications20 none Jamie yes Recruiting 40 Unavailable in April and May. Logan yes Recruiting 40 Unavailable in July and August Chris yes Sales Forecasts 30 none Ryan yes Sales Forecasts 30 none Alex Amari yes Inspections 35 none Alex yes Data Analysis 40 none Ryan Devon yes Training 30 Unavailable 1 week in April, June and November.Rylee Anderson Harly yes Benefits Analysis 40 Unavailable 4 weeks in June Kasey yes none 40 none Kendall yes Programming 40 Unavailable in January and February Drew yes Contracting 40 Unavailable in July Morgan yes Product Evaluation 35 Ashton yes Design 30 Jordan yes Inventory 40 Unavailable last 2 weeks June and December Dakota yes Materials Analysis 40 Unavailable 3 weeks in August Jayden yes Materials Analysis 40 Unavailable 3 weeks in August
  • 13. 13 Initial DefinedRisks and Constraints Risk Impact Likelihood of Occurrence (L,M,H) Degree of Impact (L,M,H) Action Trigger Responsibility Response Plan Stakeholders in the project teams categorized as Resistor may interfere with project objectives and success Medium M M Progress towards deliverables isn’t as forecast Project Manager Do not staff possible Resistor resources on project unless absolutely necessary, use relationships and management influence and buy-in tactics to gain acceptance from resistors into project goals (Surveys, input into plans, etc.) Project team members not getting along interfere with team ability to make progress on project objectives Medium M M Complaints within the team regarding other team-members attitudes or performance Team Lead Attempt to mitigate with functional manager intervention, as with lesson’s learned from financial system project this worked. If cannot be mitigated, seek to move scheduled tasks, or remove one member from the project. Development cost overruns due to unforeseen technical challenges High L H Critical Path analysis shows behind schedule on meeting Pilot or Development deliverables Project Manager First, if outsourcing, seek to work with same or similar vendor used in financial project as they experienced great success and their systems are already known to work with ours. If building in- house, assess if new development staff need to be added to project. Second, if unrelated to resources, seek to either increase budget or time constraints if necessary to meet scope, or present option to management to cut scope.
  • 14. 14 Sensitive employee data leaks to either internal or external sources during migration or implementation High L H Any employee or other resource observing sensitive employee data leaking to any inappropriate resources Team Members, Leads, Project Managers First, seek to avoid incident by having highly technical staff review the system design and quality assurance plans. If incident occurs, immediately secure the data and seek to remove from all inappropriate sources. Notify employee of incident and extent of PII leaked. Troubleshoot issue and have IT staff resolve. System complexity too great and too many integration issues uncovered, resources not fully utilized due to dependencies High M H Team Members, Vendors Modulate the deployment such that system is done first, and then each component module is done after System is stabilized. Each module broken down by area of expertise so can be run in parallel. System downtime due to unforeseen events (power outages, natural disasters, security patching, troubleshooting critical issues) High L H Any critical system impacted such that it is offline/unusable for a moderate to substantial time during project execution Team Members, Vendors Useindustry Best Practices for security, fault tolerance and redundancy such that development isn’t impacted. Havebackup plan for all critical systems including options such as off- prem resources as options (cloud). Project Team members availability impacted adversely by unforeseen events or priority conflicts High M H Any project milestone begins to slip due to availability, team meetings and status milestones Team Members, Vendors, Project Management Staff backups/teams of people instead of just single resources, to as many areas of the project as possible, without overstaffing which would adversely impact budget. Key: L = low, M= medium, H = high Project Approval Approved by the Project Sponsor: __________________________________________ Date: ___________________