SlideShare a Scribd company logo
Slide 1 -
PG
Understand Risk management to
Handle a Project
By Sameer Mitter
Slide 2 -
AGENDA
1. Introduction
2. Project Risk Management
3. Project Risk Register
4. Contingency Plan
Slide 3 -
Risk Management means
identification as early as
possible!
1. Introduction
Shark or Dolphin?
Risk = probability [%] * extent of damage [time, money]
Slide 4 -
►Risk Management is aiming at risk minimization and
mitigation
►Risk Analysis:
► Structured Process to identify possible hazards to the
project
► Integral part of any project planning and decision
process in the oil industry
►Risk Mitigation: avoid, insure, move (hand over), accept
►Risk Management provides for plans and resources in
case a project risk materializes
►Risk Assessment and mitigation (re-)planning is a
continuous, i.e. frequently repeated process
1. Introduction
Slide 5 -
Project Plan
Cost Risk Schedule Risk Content Risk
Preventive Planning Corrective Planning
1. Introduction
Slide 6 -
Preventive Action:
►is initiated before damage occurs or as preparation for
damage
►is immediately integrated into the plans
►reduces the probability that a damage will appear
Corrective Action:
►Is a planned solution which is available for
emergencies
►reduces the extent (cost) of damage
1. Introduction
Slide 7 -
Doesn’t matter:
Hope for Dolphin but be prepared for shark!!!
Advertisement of Ernst & Young, FAZ 4.11.1999
Again: Shark or Dolphin?
1. Introduction
Slide 8 -
Risk management is fundamental to project management
and has an impact on estimates of time and effort required for
the project. It is concerned with assessing the kinds of risk
associated with trying to make something happen, for
example the possibility of delays in the schedule caused
through staff sickness or materials not being available at the
appropriate time. Risks in a project can be both internal –
arising from within the project – and external – arising from
the context or environment of the project.
Project Risk Management, describes the processes
concerned with conducting risk management on a project. It
consists of the Risk Management Planning, Risk
Identification, Qualitative Risk Analysis, Quantitative Risk
Analysis, Risk Response Planning, and Risk Monitoring and
Control project management processes.
2. Project Risk Management
Slide 9 -
2. Project Risk Management
Slide 10 -
On some projects it may be appropriate to hold regular Risk
Management meetings.
The following are seen as the key stages:
►during feasibility studies,
►just before or at the early stages of FEED,
►just before or at the early stages of detailed engineering,
►just before or at the early stages of construction,
►few months prior to shut-downs,
►when setting business performance contracts,
►before partner or major project review meetings,
►as part of regular meetings with contractors/vendors,
►generally at the commencement of each major phase of a
project.
2. Project Risk Management
Slide 11 -
Risk Allocation
The primary principle is to allocate the risk to the people
best able to control the risk.
The major considerations being:
►ability to control, bear, or provide contingencies for the
risk when it occurs,
►ability to control the events leading to the risk,
►fit with corporate objectives, image, and risk taking
aversion levels,
►safety to environment life and health,
►exposure levels to profitability and loss,
►the timing of commitments,
2. Project Risk Management
Slide 12 -
2. Project Risk Management
►novelty or repeatability of the risks to be taken,
►the legal and moral position,
►the effects on the decision makers (authorities,
responsibilities, competencies, morale)
►the consent of the people to whom the risk applies.
To allocate a risk that cannot be controlled means that a
project has really retained the risk, but may have lost the
opportunity to control it. Risk and responsibility are inevitably
related.
Slide 13 -
Slide 14 -
The project will conduct a Risk Workshop that will identify
potential risk to delivering a successful project from all
aspects (technical, commercial, economic, operational or
political with HSEQ aspects as an integrated consideration
in each). Based on this, the project will determine potential
mitigation options and test the robustness of the project to
what is assessed to be the residual risk faced by the
project.
Based on the outcome of the Risk Workshop, the Project
Team will prepare a Project Risk Register.
3. Project Risk Register
Slide 15 -
The risk register will:
►categorise and list each identified risk
►assign a timing to describe which stage of the project
each risk will be active
►identify the actions by the Project Team to mitigate
each risk
►identify the project team member responsible for
managing each mitigation plan item
The Risk Register will be kept under regular (monthly)
review by the Project Team and updated to reflect the
changing circumstances either in the project or in the
environment within which the project is being developed.
Risks will be added or eliminated resulting from such
reviews and the risk mitigation plan will be updated to
respond to the currently and forecasted identified risk
picture.
3. Project Risk Register
Slide 16 -
The contents of a risk register can then be used to:
► identify and record risks,
►assess and quantify risks with regard to their consequence
(probability and severity) and manageability. Consequences
considered could cover cost, schedule, quality and technical
risks,
►identify ownership - or change of ownership,
►sort actions in risk priority order,
►identify mitigation actions and their timing,
►record what would constitute acceptable residual risk levels,
►provide a view of how risks could be subdivided into level 2 risk
registers,
►reference other studies needed e.g. cost benefit and risk
analysis studies,
►record actions taken,
►record the residual risks - after the risk reduction actions have
been taken.
3. Project Risk Register
Slide 17 -
Low Manageability High
LowImpact(likelihood&Probability)High
S
3. Project Risk Management
Slide 18 -
Probability Definition
Very High
>25% likely; greater than 1 chance in 4
Uncontrolled.
Will occur whenever circumstances are unfavorable.
Comparable events are frequent.
High
5 - 25% likely; between 1 chance in 20 and 1 chance in 4
Could results from the failure of a single system or control.
Could be expected to occur if this operation were repeated regularly.
Comparable events are within the team's direct experience.
Moderate
1 - 5% likely; between 1 chance in 100 and 1 chance in 20.
Could results from a plausible combination of system or control failures.
Would probably occur if the system were to be operated for long enough.
Comparable events are known to have occurred in the past.
Low
<1% likely; less than 1 chance in 100
Could only occur as the result of multiple, independent system or control failures.
Future occurrence is thought most unlikely.
No comparable occurrence is known.
Slide 19 -
Risk Matrix
Impact
Level
Very High Moderate High Very High Very High
High Low Moderate High Very High
Moderate Very Low Low Moderate High
Low Very Low Very Low Low Moderate
    < 1% 1 - 5% 5 - 25% > 25%
    Low Moderate High Very High
    Probability / Frequency
Slide 20 -
Manageability Definition
Low
Project Management Team can only influence impact.
Risk reduction measures are unlikely to be cost-effective.
Medium
Project Management Team can influence probability and / or impact.
Risk reduction measures will be roughly cost-neutral.
High
Project Management Team can control probability and / or impact.
Risk reduction measures will be highly cost-effective
Slide 21 -
General
Last
Update
Pre-mitigation Risk
Assessment
No
T/
O
Category
Threat/Opportunity
Name
Event
Description/Impact
Owner
Pr
ob
Conseque
nce
Risk
Pro
dn
Ca
pe
x
M's
ton
es
38 T Technical Technical
Management
Technical, planning and
constructability
deficiencies
Rework required and
delays to the overall
project schedule due
to project rephasing.
Interfaces increased
H M H H 483
11 T Manage-
. ment
Drilling Programme
Drilling programme
overrun; consumption of
offshore bedding and
deck space
Delays to subsequent
construction programs
through insufficient
POB and late
completion of offshore
works
VH L M VH 456
Slide 22 -
Ashtart Alignment Workshop Risked Schedule
Slide 23 -
One key process in risk management is to follow the 5 points
below:
1. Determine which are the key risks which have the potential
to occur and which would serious jeopardize the project.
2. Prioritize these risks in terms of magnitude
3. Determine which one's are under your control and which
one's are completely out of your control.
4. Immediately escalate the risks which are out of your control
upwards to your project board for their information and also
knowledge in how these could be mitigated.
5. Start contingency planning on those risks within your
control.
4. Contingency plan
Slide 24 -
4. Contingency plan
In business continuity and risk management, a contingency
plan is a process that prepares an organization to respond
coherently to an unplanned event. The contingency plan can
be also used as an alternative for action if expected results
fail to materialize. A contingency plan is sometimes referred
to as "Plan B”.
Contingency planning goes hand-in-hand with risk
management. Where a risk can be anticipated, contingency
plans can be implemented. If the risk materializes, thus
reducing its impact. Contingency planning can generate a
range of possible responses to potential crisis situations.
Slide 25 -
For residual risks that may occur, contingency plans should
be developed in case they do. Contingency plans should be
appropriate and commensurate to the impact of the original
risk. In many cases it is more cost effective to allocate a
certain amount of resources to mitigate a risk rather than
start by developing a contingency plan which, if necessary
to implement, is likely to be more expensive. The number
of scenarios likely to require a full contingency plan
depends upon the project. Contingency planning should not
be confused with the normal re-planning necessary to react
to minor changes in the developing project plan.
4. Contingency plan
Slide 26 -
.
The main categories of risks which require to develop a
contingency plan can be summarized as:
►physical – loss of, or damage to, information, equipment or
buildings as a result of an accident, fire or natural disaster
►technical – systems that do not work or do not work well
enough to deliver the anticipated benefits
►labour – key people unable to contribute to the project because
of, for example, illness, career change or industrial action
►political/social – for example, withdrawal of support for the
project as a result of change of government, a policy change by
senior management, or protests from the community, the
media, patients, service users or staff
►liability – legal action or the threat of it because some aspect
of the project is considered to be illegal or because there may
be compensation claims if something goes wrong.
4. Contingency plan
Slide 27 -
The importance of a project contingency plan is that it allows
the Project team to deal with known risks with more
confidence. Contingency planning prevents the "panic mode"
situation when we face risks, as it incorporates risks into the
schedule.
On our projects we must also be constantly thinking about
what could go wrong and make sure that we have thought
through contingency plans for them. No project ever goes as
planned and therefore we need to be deliberate and
thoughtful around what could go wrong so we know what to
do in case it happens (versus reacting at the time they
happen). Make sure you have risk and contingency planning
in your focus and revisit them on a regular basis to keep
them updated.
4. Contingency plan
Slide 28 -
Thank you for your attention

More Related Content

What's hot

Chapter 1 risk management (3)
Chapter 1  risk management (3)Chapter 1  risk management (3)
Chapter 1 risk management (3)
rafeeqameen
 
Plan Risk responses
Plan Risk responsesPlan Risk responses
Plan Risk responses
Nam N.N Tran M.Eng, PMP
 
Proactive vs. Reactive Approaches to Software Security Strategy
Proactive vs. Reactive Approaches to Software Security StrategyProactive vs. Reactive Approaches to Software Security Strategy
Proactive vs. Reactive Approaches to Software Security StrategyLindsey Landolfi
 
Risk management in software engineering
Risk management in software engineeringRisk management in software engineering
Risk management in software engineering
deep sharma
 
The Art and Science Behind Successful Risk Workshops
The Art and Science Behind Successful Risk WorkshopsThe Art and Science Behind Successful Risk Workshops
The Art and Science Behind Successful Risk Workshops
Acumen
 
Risk Management
Risk ManagementRisk Management
Risk Management
Saqib Raza
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
Oleksa Stelmakh
 
Risk management case study
Risk management case studyRisk management case study
Risk management case study
Eng.Ahmed Said Mohamed Refaei
 
Technical Risk Management
Technical Risk ManagementTechnical Risk Management
Technical Risk Management
Glen Alleman
 
risk management
risk managementrisk management
risk management
Arti Maggo
 
Project Risk
Project RiskProject Risk
Project Risk
Rohit Kumar
 
Episode 25 : Project Risk Management
Episode 25 :  Project Risk ManagementEpisode 25 :  Project Risk Management
Episode 25 : Project Risk Management
SAJJAD KHUDHUR ABBAS
 
Risk management
Risk managementRisk management
Risk management
bipulpwc
 
Risk Mitigation, Monitoring and Management Plan (RMMM)
Risk Mitigation, Monitoring and Management Plan (RMMM)Risk Mitigation, Monitoring and Management Plan (RMMM)
Risk Mitigation, Monitoring and Management Plan (RMMM)
Navjyotsinh Jadeja
 
Project Management C7 -risk_management
Project Management C7  -risk_managementProject Management C7  -risk_management
Project Management C7 -risk_managementIzah Asmadi
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project Success
Glen Alleman
 
Project risk analysis
Project risk analysisProject risk analysis
Project risk analysis
Nur E Alam Siddike
 
Project risk management
Project risk managementProject risk management
Project risk management
Aswin prakash i , Xantus Technologies
 

What's hot (20)

Chapter 1 risk management (3)
Chapter 1  risk management (3)Chapter 1  risk management (3)
Chapter 1 risk management (3)
 
Plan Risk responses
Plan Risk responsesPlan Risk responses
Plan Risk responses
 
Proactive vs. Reactive Approaches to Software Security Strategy
Proactive vs. Reactive Approaches to Software Security StrategyProactive vs. Reactive Approaches to Software Security Strategy
Proactive vs. Reactive Approaches to Software Security Strategy
 
Risk management in software engineering
Risk management in software engineeringRisk management in software engineering
Risk management in software engineering
 
Risk analysis
Risk analysisRisk analysis
Risk analysis
 
The Art and Science Behind Successful Risk Workshops
The Art and Science Behind Successful Risk WorkshopsThe Art and Science Behind Successful Risk Workshops
The Art and Science Behind Successful Risk Workshops
 
Risk Management
Risk ManagementRisk Management
Risk Management
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
Risk management case study
Risk management case studyRisk management case study
Risk management case study
 
Technical Risk Management
Technical Risk ManagementTechnical Risk Management
Technical Risk Management
 
risk management
risk managementrisk management
risk management
 
Project Risk
Project RiskProject Risk
Project Risk
 
Episode 25 : Project Risk Management
Episode 25 :  Project Risk ManagementEpisode 25 :  Project Risk Management
Episode 25 : Project Risk Management
 
Risk Analysis
Risk AnalysisRisk Analysis
Risk Analysis
 
Risk management
Risk managementRisk management
Risk management
 
Risk Mitigation, Monitoring and Management Plan (RMMM)
Risk Mitigation, Monitoring and Management Plan (RMMM)Risk Mitigation, Monitoring and Management Plan (RMMM)
Risk Mitigation, Monitoring and Management Plan (RMMM)
 
Project Management C7 -risk_management
Project Management C7  -risk_managementProject Management C7  -risk_management
Project Management C7 -risk_management
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project Success
 
Project risk analysis
Project risk analysisProject risk analysis
Project risk analysis
 
Project risk management
Project risk managementProject risk management
Project risk management
 

Similar to Sameer Mitter Bournemouth - What do understand by Risk management

8. project risk management
8. project risk management8. project risk management
8. project risk management
Mohamed Salah Eldien Mohamed Ali
 
Ranga's 51 hot topics to remember for Risk Management Professional (RMP) exam
Ranga's 51 hot topics to remember for Risk Management Professional (RMP) examRanga's 51 hot topics to remember for Risk Management Professional (RMP) exam
Ranga's 51 hot topics to remember for Risk Management Professional (RMP) exam
rrangraj
 
Lecture 6 Managing risk.pptx
Lecture 6 Managing risk.pptxLecture 6 Managing risk.pptx
Lecture 6 Managing risk.pptx
MehediHasan636262
 
Ch_1_PRM.pdf
Ch_1_PRM.pdfCh_1_PRM.pdf
Ch_1_PRM.pdf
AronHailesellasieAbr
 
SPM RISK PLANNING.pdfddddddddddddddddddddddddddddddddddddddddddddddd
SPM RISK PLANNING.pdfdddddddddddddddddddddddddddddddddddddddddddddddSPM RISK PLANNING.pdfddddddddddddddddddddddddddddddddddddddddddddddd
SPM RISK PLANNING.pdfddddddddddddddddddddddddddddddddddddddddddddddd
ShepherdChidambaeh
 
Managing Risk as Opportunity
Managing Risk as OpportunityManaging Risk as Opportunity
Managing Risk as Opportunity
Glen Alleman
 
11 risk management
11 risk management11 risk management
11 risk management
Waseem Siddique
 
Construction project management &amp; risk mitigation
Construction project management &amp; risk mitigationConstruction project management &amp; risk mitigation
Construction project management &amp; risk mitigation
rajlaxmipardeshi
 
Risk Management Methodologies in Construction Industries
Risk Management Methodologies in Construction IndustriesRisk Management Methodologies in Construction Industries
Risk Management Methodologies in Construction Industries
IRJET Journal
 
UCISA Toolkit - Effective Risk Management for Business Change and IT Projects
UCISA Toolkit - Effective Risk Management for Business Change and IT Projects UCISA Toolkit - Effective Risk Management for Business Change and IT Projects
UCISA Toolkit - Effective Risk Management for Business Change and IT Projects
Mark Ritchie
 
Project of entrepreneurship
Project of entrepreneurship Project of entrepreneurship
Project of entrepreneurship
AliAbbas390458
 
MBA 6941, Managing Project Teams 1 Course Learning Ou.docx
 MBA 6941, Managing Project Teams 1 Course Learning Ou.docx MBA 6941, Managing Project Teams 1 Course Learning Ou.docx
MBA 6941, Managing Project Teams 1 Course Learning Ou.docx
aryan532920
 
Project risk management
Project risk managementProject risk management
Project risk management
Er Swati Nagal
 
Risk Management
Risk ManagementRisk Management
Risk Management
Ibrahem Soltan
 
Managing risk as Opportunity
Managing risk as OpportunityManaging risk as Opportunity
Managing risk as Opportunity
Glen Alleman
 
Webinar - Building Team Efficiency and Effectiveness
Webinar - Building Team Efficiency and EffectivenessWebinar - Building Team Efficiency and Effectiveness
Webinar - Building Team Efficiency and Effectiveness
Invensis Learning
 
2.11 risk management 1
2.11 risk management 12.11 risk management 1
2.11 risk management 1reddvise
 
PROJECT RISK MANAGEMENT ... complete training materials and others at www.ga...
PROJECT RISK MANAGEMENT ...  complete training materials and others at www.ga...PROJECT RISK MANAGEMENT ...  complete training materials and others at www.ga...
PROJECT RISK MANAGEMENT ... complete training materials and others at www.ga...
GAFM Academy of Project Management ® - ISO 29990 Certified International Board of Standards
 
Risk based thinking
Risk based thinkingRisk based thinking
Risk based thinking
Ranjeet Singh
 
Project risk management
Project risk managementProject risk management
Project risk management
BarnatuCoffee
 

Similar to Sameer Mitter Bournemouth - What do understand by Risk management (20)

8. project risk management
8. project risk management8. project risk management
8. project risk management
 
Ranga's 51 hot topics to remember for Risk Management Professional (RMP) exam
Ranga's 51 hot topics to remember for Risk Management Professional (RMP) examRanga's 51 hot topics to remember for Risk Management Professional (RMP) exam
Ranga's 51 hot topics to remember for Risk Management Professional (RMP) exam
 
Lecture 6 Managing risk.pptx
Lecture 6 Managing risk.pptxLecture 6 Managing risk.pptx
Lecture 6 Managing risk.pptx
 
Ch_1_PRM.pdf
Ch_1_PRM.pdfCh_1_PRM.pdf
Ch_1_PRM.pdf
 
SPM RISK PLANNING.pdfddddddddddddddddddddddddddddddddddddddddddddddd
SPM RISK PLANNING.pdfdddddddddddddddddddddddddddddddddddddddddddddddSPM RISK PLANNING.pdfddddddddddddddddddddddddddddddddddddddddddddddd
SPM RISK PLANNING.pdfddddddddddddddddddddddddddddddddddddddddddddddd
 
Managing Risk as Opportunity
Managing Risk as OpportunityManaging Risk as Opportunity
Managing Risk as Opportunity
 
11 risk management
11 risk management11 risk management
11 risk management
 
Construction project management &amp; risk mitigation
Construction project management &amp; risk mitigationConstruction project management &amp; risk mitigation
Construction project management &amp; risk mitigation
 
Risk Management Methodologies in Construction Industries
Risk Management Methodologies in Construction IndustriesRisk Management Methodologies in Construction Industries
Risk Management Methodologies in Construction Industries
 
UCISA Toolkit - Effective Risk Management for Business Change and IT Projects
UCISA Toolkit - Effective Risk Management for Business Change and IT Projects UCISA Toolkit - Effective Risk Management for Business Change and IT Projects
UCISA Toolkit - Effective Risk Management for Business Change and IT Projects
 
Project of entrepreneurship
Project of entrepreneurship Project of entrepreneurship
Project of entrepreneurship
 
MBA 6941, Managing Project Teams 1 Course Learning Ou.docx
 MBA 6941, Managing Project Teams 1 Course Learning Ou.docx MBA 6941, Managing Project Teams 1 Course Learning Ou.docx
MBA 6941, Managing Project Teams 1 Course Learning Ou.docx
 
Project risk management
Project risk managementProject risk management
Project risk management
 
Risk Management
Risk ManagementRisk Management
Risk Management
 
Managing risk as Opportunity
Managing risk as OpportunityManaging risk as Opportunity
Managing risk as Opportunity
 
Webinar - Building Team Efficiency and Effectiveness
Webinar - Building Team Efficiency and EffectivenessWebinar - Building Team Efficiency and Effectiveness
Webinar - Building Team Efficiency and Effectiveness
 
2.11 risk management 1
2.11 risk management 12.11 risk management 1
2.11 risk management 1
 
PROJECT RISK MANAGEMENT ... complete training materials and others at www.ga...
PROJECT RISK MANAGEMENT ...  complete training materials and others at www.ga...PROJECT RISK MANAGEMENT ...  complete training materials and others at www.ga...
PROJECT RISK MANAGEMENT ... complete training materials and others at www.ga...
 
Risk based thinking
Risk based thinkingRisk based thinking
Risk based thinking
 
Project risk management
Project risk managementProject risk management
Project risk management
 

More from Sameer Mitter

Sameer Mitter - An Introduction to Supply Chain Management and Financial Perf...
Sameer Mitter - An Introduction to Supply Chain Management and Financial Perf...Sameer Mitter - An Introduction to Supply Chain Management and Financial Perf...
Sameer Mitter - An Introduction to Supply Chain Management and Financial Perf...
Sameer Mitter
 
How to make a plan to work in a Project team - Sameer Mitter
How to make a plan to work in a Project team - Sameer MitterHow to make a plan to work in a Project team - Sameer Mitter
How to make a plan to work in a Project team - Sameer Mitter
Sameer Mitter
 
Sameer Mitter | Difference between Technology and Information Technology & Sc...
Sameer Mitter | Difference between Technology and Information Technology & Sc...Sameer Mitter | Difference between Technology and Information Technology & Sc...
Sameer Mitter | Difference between Technology and Information Technology & Sc...
Sameer Mitter
 
How to do Project Work and Administration Process correctly - Sameer Mitter
How to do Project Work and Administration Process correctly - Sameer MitterHow to do Project Work and Administration Process correctly - Sameer Mitter
How to do Project Work and Administration Process correctly - Sameer Mitter
Sameer Mitter
 
What is Modern Project Management And Why it is Important - Sameer Mitter
What is Modern Project Management And Why it is Important - Sameer MitterWhat is Modern Project Management And Why it is Important - Sameer Mitter
What is Modern Project Management And Why it is Important - Sameer Mitter
Sameer Mitter
 
Sameer Mitter - What is Project Management and How to Handle it
Sameer Mitter - What is Project Management and How to Handle itSameer Mitter - What is Project Management and How to Handle it
Sameer Mitter - What is Project Management and How to Handle it
Sameer Mitter
 
Sameer Mitter - Advantage and Disadvantage of Information Technology Project ...
Sameer Mitter - Advantage and Disadvantage of Information Technology Project ...Sameer Mitter - Advantage and Disadvantage of Information Technology Project ...
Sameer Mitter - Advantage and Disadvantage of Information Technology Project ...
Sameer Mitter
 
Sameer Mitter | Introduction to Information technology Project Management
Sameer Mitter | Introduction to Information technology Project ManagementSameer Mitter | Introduction to Information technology Project Management
Sameer Mitter | Introduction to Information technology Project Management
Sameer Mitter
 

More from Sameer Mitter (8)

Sameer Mitter - An Introduction to Supply Chain Management and Financial Perf...
Sameer Mitter - An Introduction to Supply Chain Management and Financial Perf...Sameer Mitter - An Introduction to Supply Chain Management and Financial Perf...
Sameer Mitter - An Introduction to Supply Chain Management and Financial Perf...
 
How to make a plan to work in a Project team - Sameer Mitter
How to make a plan to work in a Project team - Sameer MitterHow to make a plan to work in a Project team - Sameer Mitter
How to make a plan to work in a Project team - Sameer Mitter
 
Sameer Mitter | Difference between Technology and Information Technology & Sc...
Sameer Mitter | Difference between Technology and Information Technology & Sc...Sameer Mitter | Difference between Technology and Information Technology & Sc...
Sameer Mitter | Difference between Technology and Information Technology & Sc...
 
How to do Project Work and Administration Process correctly - Sameer Mitter
How to do Project Work and Administration Process correctly - Sameer MitterHow to do Project Work and Administration Process correctly - Sameer Mitter
How to do Project Work and Administration Process correctly - Sameer Mitter
 
What is Modern Project Management And Why it is Important - Sameer Mitter
What is Modern Project Management And Why it is Important - Sameer MitterWhat is Modern Project Management And Why it is Important - Sameer Mitter
What is Modern Project Management And Why it is Important - Sameer Mitter
 
Sameer Mitter - What is Project Management and How to Handle it
Sameer Mitter - What is Project Management and How to Handle itSameer Mitter - What is Project Management and How to Handle it
Sameer Mitter - What is Project Management and How to Handle it
 
Sameer Mitter - Advantage and Disadvantage of Information Technology Project ...
Sameer Mitter - Advantage and Disadvantage of Information Technology Project ...Sameer Mitter - Advantage and Disadvantage of Information Technology Project ...
Sameer Mitter - Advantage and Disadvantage of Information Technology Project ...
 
Sameer Mitter | Introduction to Information technology Project Management
Sameer Mitter | Introduction to Information technology Project ManagementSameer Mitter | Introduction to Information technology Project Management
Sameer Mitter | Introduction to Information technology Project Management
 

Recently uploaded

Program Your Destiny eBook - Destiny University.pdf
Program Your Destiny eBook - Destiny University.pdfProgram Your Destiny eBook - Destiny University.pdf
Program Your Destiny eBook - Destiny University.pdf
Michael Herlache, MBA
 
Ethical_dilemmas_MDI_Gurgaon-Business Ethics Case 1.pptx
Ethical_dilemmas_MDI_Gurgaon-Business Ethics Case 1.pptxEthical_dilemmas_MDI_Gurgaon-Business Ethics Case 1.pptx
Ethical_dilemmas_MDI_Gurgaon-Business Ethics Case 1.pptx
TANMAYJAIN511570
 
SOCIOLOGY PPT. SOCIAL SECURITY POWER POINT
SOCIOLOGY PPT. SOCIAL SECURITY POWER POINTSOCIOLOGY PPT. SOCIAL SECURITY POWER POINT
SOCIOLOGY PPT. SOCIAL SECURITY POWER POINT
ssuser8d5e2d1
 
Collocation thường gặp trong đề thi THPT Quốc gia.pdf
Collocation thường gặp trong đề thi THPT Quốc gia.pdfCollocation thường gặp trong đề thi THPT Quốc gia.pdf
Collocation thường gặp trong đề thi THPT Quốc gia.pdf
ngochaavk33a
 
What Is The Psychology Behind Reborn Dolls_.pptx
What Is The Psychology Behind Reborn Dolls_.pptxWhat Is The Psychology Behind Reborn Dolls_.pptx
What Is The Psychology Behind Reborn Dolls_.pptx
Lloyd Dobson Artist
 
UNIVERSAL HUMAN VALUES- Harmony in the Nature
UNIVERSAL HUMAN VALUES- Harmony in the NatureUNIVERSAL HUMAN VALUES- Harmony in the Nature
UNIVERSAL HUMAN VALUES- Harmony in the Nature
Chandrakant Divate
 

Recently uploaded (6)

Program Your Destiny eBook - Destiny University.pdf
Program Your Destiny eBook - Destiny University.pdfProgram Your Destiny eBook - Destiny University.pdf
Program Your Destiny eBook - Destiny University.pdf
 
Ethical_dilemmas_MDI_Gurgaon-Business Ethics Case 1.pptx
Ethical_dilemmas_MDI_Gurgaon-Business Ethics Case 1.pptxEthical_dilemmas_MDI_Gurgaon-Business Ethics Case 1.pptx
Ethical_dilemmas_MDI_Gurgaon-Business Ethics Case 1.pptx
 
SOCIOLOGY PPT. SOCIAL SECURITY POWER POINT
SOCIOLOGY PPT. SOCIAL SECURITY POWER POINTSOCIOLOGY PPT. SOCIAL SECURITY POWER POINT
SOCIOLOGY PPT. SOCIAL SECURITY POWER POINT
 
Collocation thường gặp trong đề thi THPT Quốc gia.pdf
Collocation thường gặp trong đề thi THPT Quốc gia.pdfCollocation thường gặp trong đề thi THPT Quốc gia.pdf
Collocation thường gặp trong đề thi THPT Quốc gia.pdf
 
What Is The Psychology Behind Reborn Dolls_.pptx
What Is The Psychology Behind Reborn Dolls_.pptxWhat Is The Psychology Behind Reborn Dolls_.pptx
What Is The Psychology Behind Reborn Dolls_.pptx
 
UNIVERSAL HUMAN VALUES- Harmony in the Nature
UNIVERSAL HUMAN VALUES- Harmony in the NatureUNIVERSAL HUMAN VALUES- Harmony in the Nature
UNIVERSAL HUMAN VALUES- Harmony in the Nature
 

Sameer Mitter Bournemouth - What do understand by Risk management

  • 1. Slide 1 - PG Understand Risk management to Handle a Project By Sameer Mitter
  • 2. Slide 2 - AGENDA 1. Introduction 2. Project Risk Management 3. Project Risk Register 4. Contingency Plan
  • 3. Slide 3 - Risk Management means identification as early as possible! 1. Introduction Shark or Dolphin? Risk = probability [%] * extent of damage [time, money]
  • 4. Slide 4 - ►Risk Management is aiming at risk minimization and mitigation ►Risk Analysis: ► Structured Process to identify possible hazards to the project ► Integral part of any project planning and decision process in the oil industry ►Risk Mitigation: avoid, insure, move (hand over), accept ►Risk Management provides for plans and resources in case a project risk materializes ►Risk Assessment and mitigation (re-)planning is a continuous, i.e. frequently repeated process 1. Introduction
  • 5. Slide 5 - Project Plan Cost Risk Schedule Risk Content Risk Preventive Planning Corrective Planning 1. Introduction
  • 6. Slide 6 - Preventive Action: ►is initiated before damage occurs or as preparation for damage ►is immediately integrated into the plans ►reduces the probability that a damage will appear Corrective Action: ►Is a planned solution which is available for emergencies ►reduces the extent (cost) of damage 1. Introduction
  • 7. Slide 7 - Doesn’t matter: Hope for Dolphin but be prepared for shark!!! Advertisement of Ernst & Young, FAZ 4.11.1999 Again: Shark or Dolphin? 1. Introduction
  • 8. Slide 8 - Risk management is fundamental to project management and has an impact on estimates of time and effort required for the project. It is concerned with assessing the kinds of risk associated with trying to make something happen, for example the possibility of delays in the schedule caused through staff sickness or materials not being available at the appropriate time. Risks in a project can be both internal – arising from within the project – and external – arising from the context or environment of the project. Project Risk Management, describes the processes concerned with conducting risk management on a project. It consists of the Risk Management Planning, Risk Identification, Qualitative Risk Analysis, Quantitative Risk Analysis, Risk Response Planning, and Risk Monitoring and Control project management processes. 2. Project Risk Management
  • 9. Slide 9 - 2. Project Risk Management
  • 10. Slide 10 - On some projects it may be appropriate to hold regular Risk Management meetings. The following are seen as the key stages: ►during feasibility studies, ►just before or at the early stages of FEED, ►just before or at the early stages of detailed engineering, ►just before or at the early stages of construction, ►few months prior to shut-downs, ►when setting business performance contracts, ►before partner or major project review meetings, ►as part of regular meetings with contractors/vendors, ►generally at the commencement of each major phase of a project. 2. Project Risk Management
  • 11. Slide 11 - Risk Allocation The primary principle is to allocate the risk to the people best able to control the risk. The major considerations being: ►ability to control, bear, or provide contingencies for the risk when it occurs, ►ability to control the events leading to the risk, ►fit with corporate objectives, image, and risk taking aversion levels, ►safety to environment life and health, ►exposure levels to profitability and loss, ►the timing of commitments, 2. Project Risk Management
  • 12. Slide 12 - 2. Project Risk Management ►novelty or repeatability of the risks to be taken, ►the legal and moral position, ►the effects on the decision makers (authorities, responsibilities, competencies, morale) ►the consent of the people to whom the risk applies. To allocate a risk that cannot be controlled means that a project has really retained the risk, but may have lost the opportunity to control it. Risk and responsibility are inevitably related.
  • 14. Slide 14 - The project will conduct a Risk Workshop that will identify potential risk to delivering a successful project from all aspects (technical, commercial, economic, operational or political with HSEQ aspects as an integrated consideration in each). Based on this, the project will determine potential mitigation options and test the robustness of the project to what is assessed to be the residual risk faced by the project. Based on the outcome of the Risk Workshop, the Project Team will prepare a Project Risk Register. 3. Project Risk Register
  • 15. Slide 15 - The risk register will: ►categorise and list each identified risk ►assign a timing to describe which stage of the project each risk will be active ►identify the actions by the Project Team to mitigate each risk ►identify the project team member responsible for managing each mitigation plan item The Risk Register will be kept under regular (monthly) review by the Project Team and updated to reflect the changing circumstances either in the project or in the environment within which the project is being developed. Risks will be added or eliminated resulting from such reviews and the risk mitigation plan will be updated to respond to the currently and forecasted identified risk picture. 3. Project Risk Register
  • 16. Slide 16 - The contents of a risk register can then be used to: ► identify and record risks, ►assess and quantify risks with regard to their consequence (probability and severity) and manageability. Consequences considered could cover cost, schedule, quality and technical risks, ►identify ownership - or change of ownership, ►sort actions in risk priority order, ►identify mitigation actions and their timing, ►record what would constitute acceptable residual risk levels, ►provide a view of how risks could be subdivided into level 2 risk registers, ►reference other studies needed e.g. cost benefit and risk analysis studies, ►record actions taken, ►record the residual risks - after the risk reduction actions have been taken. 3. Project Risk Register
  • 17. Slide 17 - Low Manageability High LowImpact(likelihood&Probability)High S 3. Project Risk Management
  • 18. Slide 18 - Probability Definition Very High >25% likely; greater than 1 chance in 4 Uncontrolled. Will occur whenever circumstances are unfavorable. Comparable events are frequent. High 5 - 25% likely; between 1 chance in 20 and 1 chance in 4 Could results from the failure of a single system or control. Could be expected to occur if this operation were repeated regularly. Comparable events are within the team's direct experience. Moderate 1 - 5% likely; between 1 chance in 100 and 1 chance in 20. Could results from a plausible combination of system or control failures. Would probably occur if the system were to be operated for long enough. Comparable events are known to have occurred in the past. Low <1% likely; less than 1 chance in 100 Could only occur as the result of multiple, independent system or control failures. Future occurrence is thought most unlikely. No comparable occurrence is known.
  • 19. Slide 19 - Risk Matrix Impact Level Very High Moderate High Very High Very High High Low Moderate High Very High Moderate Very Low Low Moderate High Low Very Low Very Low Low Moderate     < 1% 1 - 5% 5 - 25% > 25%     Low Moderate High Very High     Probability / Frequency
  • 20. Slide 20 - Manageability Definition Low Project Management Team can only influence impact. Risk reduction measures are unlikely to be cost-effective. Medium Project Management Team can influence probability and / or impact. Risk reduction measures will be roughly cost-neutral. High Project Management Team can control probability and / or impact. Risk reduction measures will be highly cost-effective
  • 21. Slide 21 - General Last Update Pre-mitigation Risk Assessment No T/ O Category Threat/Opportunity Name Event Description/Impact Owner Pr ob Conseque nce Risk Pro dn Ca pe x M's ton es 38 T Technical Technical Management Technical, planning and constructability deficiencies Rework required and delays to the overall project schedule due to project rephasing. Interfaces increased H M H H 483 11 T Manage- . ment Drilling Programme Drilling programme overrun; consumption of offshore bedding and deck space Delays to subsequent construction programs through insufficient POB and late completion of offshore works VH L M VH 456
  • 22. Slide 22 - Ashtart Alignment Workshop Risked Schedule
  • 23. Slide 23 - One key process in risk management is to follow the 5 points below: 1. Determine which are the key risks which have the potential to occur and which would serious jeopardize the project. 2. Prioritize these risks in terms of magnitude 3. Determine which one's are under your control and which one's are completely out of your control. 4. Immediately escalate the risks which are out of your control upwards to your project board for their information and also knowledge in how these could be mitigated. 5. Start contingency planning on those risks within your control. 4. Contingency plan
  • 24. Slide 24 - 4. Contingency plan In business continuity and risk management, a contingency plan is a process that prepares an organization to respond coherently to an unplanned event. The contingency plan can be also used as an alternative for action if expected results fail to materialize. A contingency plan is sometimes referred to as "Plan B”. Contingency planning goes hand-in-hand with risk management. Where a risk can be anticipated, contingency plans can be implemented. If the risk materializes, thus reducing its impact. Contingency planning can generate a range of possible responses to potential crisis situations.
  • 25. Slide 25 - For residual risks that may occur, contingency plans should be developed in case they do. Contingency plans should be appropriate and commensurate to the impact of the original risk. In many cases it is more cost effective to allocate a certain amount of resources to mitigate a risk rather than start by developing a contingency plan which, if necessary to implement, is likely to be more expensive. The number of scenarios likely to require a full contingency plan depends upon the project. Contingency planning should not be confused with the normal re-planning necessary to react to minor changes in the developing project plan. 4. Contingency plan
  • 26. Slide 26 - . The main categories of risks which require to develop a contingency plan can be summarized as: ►physical – loss of, or damage to, information, equipment or buildings as a result of an accident, fire or natural disaster ►technical – systems that do not work or do not work well enough to deliver the anticipated benefits ►labour – key people unable to contribute to the project because of, for example, illness, career change or industrial action ►political/social – for example, withdrawal of support for the project as a result of change of government, a policy change by senior management, or protests from the community, the media, patients, service users or staff ►liability – legal action or the threat of it because some aspect of the project is considered to be illegal or because there may be compensation claims if something goes wrong. 4. Contingency plan
  • 27. Slide 27 - The importance of a project contingency plan is that it allows the Project team to deal with known risks with more confidence. Contingency planning prevents the "panic mode" situation when we face risks, as it incorporates risks into the schedule. On our projects we must also be constantly thinking about what could go wrong and make sure that we have thought through contingency plans for them. No project ever goes as planned and therefore we need to be deliberate and thoughtful around what could go wrong so we know what to do in case it happens (versus reacting at the time they happen). Make sure you have risk and contingency planning in your focus and revisit them on a regular basis to keep them updated. 4. Contingency plan
  • 28. Slide 28 - Thank you for your attention

Editor's Notes

  1. &amp;lt;number&amp;gt;
  2. 7/19/19
  3. 7/19/19
  4. 7/19/19
  5. 7/19/19
  6. 7/19/19
  7. 7/19/19
  8. 7/19/19
  9. 7/19/19
  10. 7/19/19
  11. 7/19/19
  12. 7/19/19
  13. 7/19/19
  14. 7/19/19