SlideShare a Scribd company logo
Prepared by Rangarajan Ramaswamy, PMP, PMI-SP, PMI-RMP Page 1 of 5
RANGA’S 51 HOT TOPICS TO
REMEMBER FOR
RISK MANAGEMENT
PROFESSIONAL (RMP) EXAM
1. A contingency plan is a planned action to be taken if a threat or an opportunity happens. A fallback
plan is implemented if the contingency plan is not effective or fails. A secondary risk
is associated with risks pertaining to risk response. A workaround is an immediate fix needed if an
unidentified or unanticipated risk occurs during execution stage.
2. A Pre-mortem is the process of "evaluating" a project before it has actually been done, to identify
potential risks on the project.
3. Assumption testing is done during Perform Qualitative Risk Assessment process. In assumption
testing, the stability and consequence are rated from 1 to 10. A stability rating of 5 to 10 means the
assumption is valid and a consequence rating of 5 to 10 means the assumption could have large
impact on the project.
4. It is important to analyze assumptions made when determining risk to uncover the consequences if the
assumptions are false.
5. Mutual exclusivity in decision tree model - Two events are called mutually exclusive if both cannot
occur in a single trial. Example: Flipping a coin will always give only 1 result (Head or Tail).
6. FMEA (Failure Mode Effect Analysis) is used to identify potential causes of product failure,
determine the effects, and identify actions to mitigate the failures.
7. Risk rating is something between 1 – 10. Risk Score is calculated as P*I. Comparing the risk scores
of risks in the project results in the Risk Ranking within the project.
8. Residual risks are risks that have been passively accepted, or for which contingency plans have been
created. It is important that management be informed of risks that have been passively accepted, as
well as the risks for which contingency and fallback plans have been created.
9. Residual risks are those risks that remain after Plan Risk Response process.
10. Project Cost breakdown is as follows:-
a. Work package estimate = Summation of activity estimate
b. Control account estimate = Summation of work packages estimate
c. Project estimate = Summation of Control accounts estimate
d. Cost baseline = Project estimate + Contingency reserve
e. Cost budget = Cost baseline + Management reserve
11. Management reserve is usually a percentage of the total project cost. The contingency reserve is the
expected monetary value (EMV) of the risks.
RANGA’S 51 HOT TOPICS TO REMEMBER FOR
RISK MANAGEMENT PROFESSIONAL (RMP) EXAM
Prepared by Rangarajan Ramaswamy, PMP, PMI-SP, PMI-RMP Page 2 of 5
12. Monte Carlo simulation is used to determine time and cost based on probability distribution.
13. Project Manager holds the Primary responsibility of identifying risk.
14. All the Risks for which PM and team has no control over, management should be involved.
15. The team is more confident and optimistic about the project during the Plan Risk Response process.
16. Meetings should not be required before the approved fallback or contingency plan is implemented.
17. PM should spend most of the time preparing contingency plans.
18. The highest-risk path is the path through the network diagram that has the highest risk score. The
activities on this path may not immediately follow each other, as activities do on the critical path.
19. Exploiting an opportunity means increasing its probability. Enhancing an opportunity means
increasing its impact.
20. The ultimate outcome of the risk ranking process is that the non-top risks are separated from the top
risks, so that the top risks can be moved forward.
21. The risk reserve report keeps a running balance of the remaining reserve, and is used like a
checkbook.
22. Path convergence is best described as many activities leading into a central activity. This adds risk to
that central activity.
23. Perform qualitative risk analysis is subjective evaluation.
24. Perform quantitative risk analysis is objective evaluation.
25. The team needs to understand the risk tolerance areas for the project to know the acceptable level of
risk and, therefore, which risks need to be addressed.
26. Stakeholder risk tolerance is identified during the Plan Risk Management process.
27. When an identified risk arises, it is not necessary to hold a meeting, and the risk response plan does
not require review. Of course, since the risk has occurred, it was not avoided.
28. It is the responsibility of risk governance board to ensure the project is following the standard policies
during all processes.
29. Risk management "metrics" are used to measure how the project risk management team is performing
against the plan.
30. Purpose of risk audit is to determine the effectiveness of risk management team.
31. Project charter and WBS helps prevent re-work, wasted time & effort.
32. While calculating worst case scenarios simply neglect the probability and add the negative impacts.
Similarly, for calculating best case scenarios neglect the probability and add the positive impacts.
RANGA’S 51 HOT TOPICS TO REMEMBER FOR
RISK MANAGEMENT PROFESSIONAL (RMP) EXAM
Prepared by Rangarajan Ramaswamy, PMP, PMI-SP, PMI-RMP Page 3 of 5
33. Prompt lists are used to help ensure that all aspects are covered during risk identification. A prompt
list categorizes risks into types or areas and is usually specific to a project type and an organization’s
function (e.g. legal, commercial, technical, design, construction, testing etc.)
34. Many workarounds on a project indicate that there was a lack of adequate project planning and the
project is likely in trouble.
35. Work Performance Data is raw data such as physical progress, start finish dates. Work Performance
Information is analysis of performance data such as change requests, forecasted estimates. Work
Performance Report is physical or electronic representation of Work Performance Information such
as status reports, memos, notes, dashboards.
36. Contingency reserves are associated with the “known-unknowns,” which may be estimated to account
for the unknown amount of rework.
37. List of formulae to be remembered :-
a. No. of communication channels N = n(n-1)/2 (where n is no of stakeholders)
b. Duration or cost for triangular distribution E= (O + M + P)/3
c. Duration or cost for Beta distribution (traditional PERT) E= (O + 4M + P)/6
d. CV = EV - AC
e. SV = EV - PV
f. CPI = EV/AC
g. SPI = EV/PV
h. EAC forecast for work performed at the budgeted rate: EAC = AC + (BAC – EV)
i. EAC forecast for work performed at the present rate CPI : EAC = BAC / CPI
j. EAC forecast for ETC work considering both SPI and CPI factors:
EAC = AC + [(BAC – EV) / (CPI X SPI)]
k. TCPI based on the BAC: (BAC – EV) / (BAC – AC)
l. TCPI based on the EAC: (BAC – EV) / (EAC – AC).
m. In short TCPI = work remaining/funds remaining
n. Variance at completion VAC = BAC – EAC
o. Activity standard deviation is (P-O)/6
p. Activity variance is square of standard deviation = [(P-O)/6]2
38. Projects with TCPI > 1 is harder to complete and TCPI < 1 is easier to complete.
39. CPI>1(Under Budget) ,CPI=1(At budget) , CPI<1 (Over Budget)
40. SPI>1(Ahead of plan) , SPI=1(As planned) , SPI<1 (Behind Plan)
41. In repetitive processes, the control limits are generally set at ±3 sigma around a process mean that has
been set at 0 sigma. A process is considered out of control when: (1) a data point exceeds a control
limit; (2) seven consecutive plot points are above the mean; or (3) seven consecutive plot points are
below the mean.
42. Non-critical risks are maintained in Watchlist and revisited periodically (mostly during execution and
M&C).
43. Expectancy Theory - Employees who believe that their efforts will lead to effective performance
and who expect to be rewarded for their accomplishments will remain productive as rewards meet
their expectations.
RANGA’S 51 HOT TOPICS TO REMEMBER FOR
RISK MANAGEMENT PROFESSIONAL (RMP) EXAM
Prepared by Rangarajan Ramaswamy, PMP, PMI-SP, PMI-RMP Page 4 of 5
44. Perquisites (Perks) - Some employees receive special rewards, such as assigned parking
spaces, corner offices, and executive dining.
45. Fringe Benefits- These are the "standard" benefits formally given to all employees, such as education
benefits, insurance, profit sharing etc.
46. McGregor's Theory of X and Y–
a. Theory X- Managers who accept this theory believe that people need to be watched
every minute. They believe employees are incapable, avoid responsibility, and avoid
work whenever possible.
b. Theory Y- Managers who accept this theory believe that people are willing to work
without supervision, and want to achieve. They believe employees can direct their own
efforts.
47. Maslow's Hierarchy of Needs – represents a pyramid that shows how people are motivated and states
that one cannot ascend to the next top level until the levels below are fulfilled.
Top level: Self-actualization – Self-fulfillment, growth, learning
Esteem: - Accomplishment, respect, attention, appreciation
Social - Love, affection, approval, friends, association
Safety – Security, stability, freedom from harm
Base level: Physiological – Need for air, water, food, housing, clothing
48. David McClelland's Theory of Needs (or Acquired Needs Theory) states that a person falling into one
category would be managed differently than a person falling into another category. The categories
are:-
a. Achievement - These people should be given projects that are challenging but are
reachable. (Recognition)
b. Affiliation - These people work best when cooperating with others. They seek approval
rather than recognition.
c. Power - People whose need for power is socially oriented, these people like to organize
and influence others.
49. Herzberg's Theory deals with hygiene factors and motivating agents. Poor hygiene factors may
demotivate, but improving them, under most circumstances, will not improve motivation.
a. Examples of hygiene factors are:
i. Working conditions
ii. Salary
iii. Personal life
iv. Relationships at work
v. Security
vi. Status
b. Motivating Agents What motivates people is the work itself, including such things as:
i. Responsibility
ii. Self-actualization
iii. Professional growth
iv. Recognition
50. Neuro-linguistic programming (NLP) is an approach to communication, personal development, and
psychotherapy. The first stage being the act of establishing and maintaining rapport between the
practitioner and the client which is achieved through pacing and leading the verbal (e.g., sensory
RANGA’S 51 HOT TOPICS TO REMEMBER FOR
RISK MANAGEMENT PROFESSIONAL (RMP) EXAM
Prepared by Rangarajan Ramaswamy, PMP, PMI-SP, PMI-RMP Page 5 of 5
predicates and keywords) and non-verbal behavior (e.g., matching and mirroring non-verbal behavior,
or responding to eye movements) of the client.
51. Correlation coefficient is a measure that determines the degree to which two variable's movements are
associated, giving a value between +1 and −1 inclusive, where 1 is total positive correlation, 0 is no
correlation, and −1 is total negative correlation.
What to expect in the exam?
1. Around 30% of questions related to above mentioned points.
2. Around 50% of situation based questions (You are the Risk manager of a company etc.)
3. Around 10% of questions related to Monte Carlo simulation. Simulation result will be displayed
and asked to calculate project average budget, P50, P80 etc.
4. Around 5% of questions are like what to do if the risks are not identified in the risk register.
5. Remaining 5% of questions related to Probability, confidence and stability level. Questions based
on when to use contingency reserve and when to use management reserve. Questions on Risk
averse and Risk seeking managers. Questions on different types of simulations MCS and LHS
(Monte Carlo sampling and Latin hypercube sampling ) etc.
References:-
1. Rita Mulcahy’s Risk Management
2. Rita Mulcahy’s PMP Exam Prep
3. PMBOK 5th
Edition
4. Investopedia.com
5. Wikipedia.org
xxx---My wishes and good luck for your exam---xxx
I would love to receive your feedback and you can reach me through LinkedIn at
http://qa.linkedin.com/in/rangarajanramaswamy/

More Related Content

What's hot

Risk 2 simplelearn-exam1-ans
Risk 2 simplelearn-exam1-ansRisk 2 simplelearn-exam1-ans
Risk 2 simplelearn-exam1-ans
Mohamed Saeed
 
Risk 0-risk-guide book for pmi-rmp by amer elbaz
Risk 0-risk-guide book for pmi-rmp by amer elbazRisk 0-risk-guide book for pmi-rmp by amer elbaz
Risk 0-risk-guide book for pmi-rmp by amer elbaz
Mohamed Saeed
 
Risk 6 questions - 170
Risk 6 questions - 170Risk 6 questions - 170
Risk 6 questions - 170
Mohamed Saeed
 
Episode 25 : Project Risk Management
Episode 25 :  Project Risk ManagementEpisode 25 :  Project Risk Management
Episode 25 : Project Risk Management
SAJJAD KHUDHUR ABBAS
 
PMP_Project Risk Management
PMP_Project Risk ManagementPMP_Project Risk Management
PMP_Project Risk Management
Hisham Haridy MBA, PMP®, RMP®, SP®
 
PMP PMBOK 5th Ch 11 Project Risk Management
PMP PMBOK 5th Ch 11 Project Risk ManagementPMP PMBOK 5th Ch 11 Project Risk Management
PMP PMBOK 5th Ch 11 Project Risk Management
Abdullah Ahmed, PMP, RMP
 
Quantitative Project Risk Analysis
Quantitative Project Risk AnalysisQuantitative Project Risk Analysis
Quantitative Project Risk Analysis
Intaver Insititute
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
Martin Sillaots
 
Risk Analysis : PMP- Project Risk Management
Risk Analysis : PMP- Project Risk ManagementRisk Analysis : PMP- Project Risk Management
Risk Analysis : PMP- Project Risk Management
Saket Bansal
 
Chapter 5 risk_
Chapter 5 risk_Chapter 5 risk_
Chapter 5 risk_
Rione Drevale
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
Oleksa Stelmakh
 
Risk strategies presentation
Risk strategies presentationRisk strategies presentation
Risk strategies presentation
Raven Morgan
 
Plan Risk responses
Plan Risk responsesPlan Risk responses
Plan Risk responses
Nam N.N Tran M.Eng, PMP
 
Pm study project risk management test
Pm study project  risk management testPm study project  risk management test
Pm study project risk management test
Abdullah Ahmed, PMP, RMP
 
Project Risk Management - PMBOK5
Project Risk Management - PMBOK5Project Risk Management - PMBOK5
Project Risk Management - PMBOK5
pankajsh10
 
Step by step guide on project risk management
Step by step guide on project risk managementStep by step guide on project risk management
Step by step guide on project risk management
PMC Mentor
 
Pmi sp questions with answers
Pmi sp questions with answersPmi sp questions with answers
Pmi sp questions with answers
Mohamed Saeed
 
PMI ACP Classroom Question Paper with Answers
PMI ACP Classroom Question Paper with AnswersPMI ACP Classroom Question Paper with Answers
PMI ACP Classroom Question Paper with Answers
Thanh Nguyen
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
Russell Taylor BEng CEng FAPM FIET
 

What's hot (20)

Risk 2 simplelearn-exam1-ans
Risk 2 simplelearn-exam1-ansRisk 2 simplelearn-exam1-ans
Risk 2 simplelearn-exam1-ans
 
Risk 0-risk-guide book for pmi-rmp by amer elbaz
Risk 0-risk-guide book for pmi-rmp by amer elbazRisk 0-risk-guide book for pmi-rmp by amer elbaz
Risk 0-risk-guide book for pmi-rmp by amer elbaz
 
Risk 6 questions - 170
Risk 6 questions - 170Risk 6 questions - 170
Risk 6 questions - 170
 
Episode 25 : Project Risk Management
Episode 25 :  Project Risk ManagementEpisode 25 :  Project Risk Management
Episode 25 : Project Risk Management
 
PMP_Project Risk Management
PMP_Project Risk ManagementPMP_Project Risk Management
PMP_Project Risk Management
 
PMP PMBOK 5th Ch 11 Project Risk Management
PMP PMBOK 5th Ch 11 Project Risk ManagementPMP PMBOK 5th Ch 11 Project Risk Management
PMP PMBOK 5th Ch 11 Project Risk Management
 
Quantitative Project Risk Analysis
Quantitative Project Risk AnalysisQuantitative Project Risk Analysis
Quantitative Project Risk Analysis
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
Risk Analysis : PMP- Project Risk Management
Risk Analysis : PMP- Project Risk ManagementRisk Analysis : PMP- Project Risk Management
Risk Analysis : PMP- Project Risk Management
 
Chapter 5 risk_
Chapter 5 risk_Chapter 5 risk_
Chapter 5 risk_
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
Risk strategies presentation
Risk strategies presentationRisk strategies presentation
Risk strategies presentation
 
Plan Risk responses
Plan Risk responsesPlan Risk responses
Plan Risk responses
 
Pm study project risk management test
Pm study project  risk management testPm study project  risk management test
Pm study project risk management test
 
Project Risk Management - PMBOK5
Project Risk Management - PMBOK5Project Risk Management - PMBOK5
Project Risk Management - PMBOK5
 
Step by step guide on project risk management
Step by step guide on project risk managementStep by step guide on project risk management
Step by step guide on project risk management
 
Pmi sp questions with answers
Pmi sp questions with answersPmi sp questions with answers
Pmi sp questions with answers
 
PMI ACP Classroom Question Paper with Answers
PMI ACP Classroom Question Paper with AnswersPMI ACP Classroom Question Paper with Answers
PMI ACP Classroom Question Paper with Answers
 
Pmp risk management
Pmp risk managementPmp risk management
Pmp risk management
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 

Similar to Ranga's 51 hot topics to remember for Risk Management Professional (RMP) exam

Sameer Mitter Bournemouth - What do understand by Risk management
Sameer Mitter Bournemouth - What do understand by Risk managementSameer Mitter Bournemouth - What do understand by Risk management
Sameer Mitter Bournemouth - What do understand by Risk management
Sameer Mitter
 
8. project risk management
8. project risk management8. project risk management
8. project risk management
Mohamed Salah Eldien Mohamed Ali
 
Managing risk as Opportunity
Managing risk as OpportunityManaging risk as Opportunity
Managing risk as Opportunity
Glen Alleman
 
MBA 6941, Managing Project Teams 1 Course Learning Ou.docx
 MBA 6941, Managing Project Teams 1 Course Learning Ou.docx MBA 6941, Managing Project Teams 1 Course Learning Ou.docx
MBA 6941, Managing Project Teams 1 Course Learning Ou.docx
aryan532920
 
Risk Management Best Practices
Risk Management Best PracticesRisk Management Best Practices
Risk Management Best Practices
PMILebanonChapter
 
Risk-Management-05012023-025512pm.ppt
Risk-Management-05012023-025512pm.pptRisk-Management-05012023-025512pm.ppt
Risk-Management-05012023-025512pm.ppt
YasirShaikh34
 
Ch_1_PRM.pdf
Ch_1_PRM.pdfCh_1_PRM.pdf
Ch_1_PRM.pdf
AronHailesellasieAbr
 
Managing Risk as Opportunity
Managing Risk as OpportunityManaging Risk as Opportunity
Managing Risk as Opportunity
Glen Alleman
 
Lecture 6 Managing risk.pptx
Lecture 6 Managing risk.pptxLecture 6 Managing risk.pptx
Lecture 6 Managing risk.pptx
MehediHasan636262
 
Risk Management
Risk ManagementRisk Management
Risk Management
Hinal Lunagariya
 
Project of entrepreneurship
Project of entrepreneurship Project of entrepreneurship
Project of entrepreneurship
AliAbbas390458
 
Bertrand's Individual Essay
Bertrand's Individual EssayBertrand's Individual Essay
Bertrand's Individual EssayPrince Bertrand
 
Project risk management
Project risk managementProject risk management
Project risk management
Karishma Chaudhary
 
11 risk management
11 risk management11 risk management
11 risk management
Waseem Siddique
 
Risk management overview
Risk management overviewRisk management overview
Risk management overview
Hossam Maghrabi
 
Webinar - Building Team Efficiency and Effectiveness
Webinar - Building Team Efficiency and EffectivenessWebinar - Building Team Efficiency and Effectiveness
Webinar - Building Team Efficiency and Effectiveness
Invensis Learning
 
Building a risk tolerant integrated master schedule
Building a risk tolerant integrated master scheduleBuilding a risk tolerant integrated master schedule
Building a risk tolerant integrated master schedule
Glen Alleman
 
Project risk management
Project risk managementProject risk management
Project risk management
BarnatuCoffee
 
Riskmanagement software Engineering1.ppt
Riskmanagement software Engineering1.pptRiskmanagement software Engineering1.ppt
Riskmanagement software Engineering1.ppt
sirishaYerraboina1
 

Similar to Ranga's 51 hot topics to remember for Risk Management Professional (RMP) exam (20)

Sameer Mitter Bournemouth - What do understand by Risk management
Sameer Mitter Bournemouth - What do understand by Risk managementSameer Mitter Bournemouth - What do understand by Risk management
Sameer Mitter Bournemouth - What do understand by Risk management
 
8. project risk management
8. project risk management8. project risk management
8. project risk management
 
Managing risk as Opportunity
Managing risk as OpportunityManaging risk as Opportunity
Managing risk as Opportunity
 
MBA 6941, Managing Project Teams 1 Course Learning Ou.docx
 MBA 6941, Managing Project Teams 1 Course Learning Ou.docx MBA 6941, Managing Project Teams 1 Course Learning Ou.docx
MBA 6941, Managing Project Teams 1 Course Learning Ou.docx
 
Risk analysis
Risk analysisRisk analysis
Risk analysis
 
Risk Management Best Practices
Risk Management Best PracticesRisk Management Best Practices
Risk Management Best Practices
 
Risk-Management-05012023-025512pm.ppt
Risk-Management-05012023-025512pm.pptRisk-Management-05012023-025512pm.ppt
Risk-Management-05012023-025512pm.ppt
 
Ch_1_PRM.pdf
Ch_1_PRM.pdfCh_1_PRM.pdf
Ch_1_PRM.pdf
 
Managing Risk as Opportunity
Managing Risk as OpportunityManaging Risk as Opportunity
Managing Risk as Opportunity
 
Lecture 6 Managing risk.pptx
Lecture 6 Managing risk.pptxLecture 6 Managing risk.pptx
Lecture 6 Managing risk.pptx
 
Risk Management
Risk ManagementRisk Management
Risk Management
 
Project of entrepreneurship
Project of entrepreneurship Project of entrepreneurship
Project of entrepreneurship
 
Bertrand's Individual Essay
Bertrand's Individual EssayBertrand's Individual Essay
Bertrand's Individual Essay
 
Project risk management
Project risk managementProject risk management
Project risk management
 
11 risk management
11 risk management11 risk management
11 risk management
 
Risk management overview
Risk management overviewRisk management overview
Risk management overview
 
Webinar - Building Team Efficiency and Effectiveness
Webinar - Building Team Efficiency and EffectivenessWebinar - Building Team Efficiency and Effectiveness
Webinar - Building Team Efficiency and Effectiveness
 
Building a risk tolerant integrated master schedule
Building a risk tolerant integrated master scheduleBuilding a risk tolerant integrated master schedule
Building a risk tolerant integrated master schedule
 
Project risk management
Project risk managementProject risk management
Project risk management
 
Riskmanagement software Engineering1.ppt
Riskmanagement software Engineering1.pptRiskmanagement software Engineering1.ppt
Riskmanagement software Engineering1.ppt
 

Recently uploaded

BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...
BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...
BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...
Nguyen Thanh Tu Collection
 
Synthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptxSynthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptx
Pavel ( NSTU)
 
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
MysoreMuleSoftMeetup
 
Palestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptxPalestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptx
RaedMohamed3
 
How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...
Jisc
 
The Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official PublicationThe Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official Publication
Delapenabediema
 
Polish students' mobility in the Czech Republic
Polish students' mobility in the Czech RepublicPolish students' mobility in the Czech Republic
Polish students' mobility in the Czech Republic
Anna Sz.
 
The basics of sentences session 5pptx.pptx
The basics of sentences session 5pptx.pptxThe basics of sentences session 5pptx.pptx
The basics of sentences session 5pptx.pptx
heathfieldcps1
 
Model Attribute Check Company Auto Property
Model Attribute  Check Company Auto PropertyModel Attribute  Check Company Auto Property
Model Attribute Check Company Auto Property
Celine George
 
2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...
Sandy Millin
 
Language Across the Curriculm LAC B.Ed.
Language Across the  Curriculm LAC B.Ed.Language Across the  Curriculm LAC B.Ed.
Language Across the Curriculm LAC B.Ed.
Atul Kumar Singh
 
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXXPhrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
MIRIAMSALINAS13
 
special B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdfspecial B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdf
Special education needs
 
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCECLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
BhavyaRajput3
 
How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17
Celine George
 
CACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdfCACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdf
camakaiclarkmusic
 
The approach at University of Liverpool.pptx
The approach at University of Liverpool.pptxThe approach at University of Liverpool.pptx
The approach at University of Liverpool.pptx
Jisc
 
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
EugeneSaldivar
 
Home assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdfHome assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdf
Tamralipta Mahavidyalaya
 
Lapbook sobre os Regimes Totalitários.pdf
Lapbook sobre os Regimes Totalitários.pdfLapbook sobre os Regimes Totalitários.pdf
Lapbook sobre os Regimes Totalitários.pdf
Jean Carlos Nunes Paixão
 

Recently uploaded (20)

BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...
BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...
BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...
 
Synthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptxSynthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptx
 
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
 
Palestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptxPalestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptx
 
How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...
 
The Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official PublicationThe Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official Publication
 
Polish students' mobility in the Czech Republic
Polish students' mobility in the Czech RepublicPolish students' mobility in the Czech Republic
Polish students' mobility in the Czech Republic
 
The basics of sentences session 5pptx.pptx
The basics of sentences session 5pptx.pptxThe basics of sentences session 5pptx.pptx
The basics of sentences session 5pptx.pptx
 
Model Attribute Check Company Auto Property
Model Attribute  Check Company Auto PropertyModel Attribute  Check Company Auto Property
Model Attribute Check Company Auto Property
 
2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...
 
Language Across the Curriculm LAC B.Ed.
Language Across the  Curriculm LAC B.Ed.Language Across the  Curriculm LAC B.Ed.
Language Across the Curriculm LAC B.Ed.
 
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXXPhrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
 
special B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdfspecial B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdf
 
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCECLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
 
How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17
 
CACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdfCACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdf
 
The approach at University of Liverpool.pptx
The approach at University of Liverpool.pptxThe approach at University of Liverpool.pptx
The approach at University of Liverpool.pptx
 
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
 
Home assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdfHome assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdf
 
Lapbook sobre os Regimes Totalitários.pdf
Lapbook sobre os Regimes Totalitários.pdfLapbook sobre os Regimes Totalitários.pdf
Lapbook sobre os Regimes Totalitários.pdf
 

Ranga's 51 hot topics to remember for Risk Management Professional (RMP) exam

  • 1. Prepared by Rangarajan Ramaswamy, PMP, PMI-SP, PMI-RMP Page 1 of 5 RANGA’S 51 HOT TOPICS TO REMEMBER FOR RISK MANAGEMENT PROFESSIONAL (RMP) EXAM 1. A contingency plan is a planned action to be taken if a threat or an opportunity happens. A fallback plan is implemented if the contingency plan is not effective or fails. A secondary risk is associated with risks pertaining to risk response. A workaround is an immediate fix needed if an unidentified or unanticipated risk occurs during execution stage. 2. A Pre-mortem is the process of "evaluating" a project before it has actually been done, to identify potential risks on the project. 3. Assumption testing is done during Perform Qualitative Risk Assessment process. In assumption testing, the stability and consequence are rated from 1 to 10. A stability rating of 5 to 10 means the assumption is valid and a consequence rating of 5 to 10 means the assumption could have large impact on the project. 4. It is important to analyze assumptions made when determining risk to uncover the consequences if the assumptions are false. 5. Mutual exclusivity in decision tree model - Two events are called mutually exclusive if both cannot occur in a single trial. Example: Flipping a coin will always give only 1 result (Head or Tail). 6. FMEA (Failure Mode Effect Analysis) is used to identify potential causes of product failure, determine the effects, and identify actions to mitigate the failures. 7. Risk rating is something between 1 – 10. Risk Score is calculated as P*I. Comparing the risk scores of risks in the project results in the Risk Ranking within the project. 8. Residual risks are risks that have been passively accepted, or for which contingency plans have been created. It is important that management be informed of risks that have been passively accepted, as well as the risks for which contingency and fallback plans have been created. 9. Residual risks are those risks that remain after Plan Risk Response process. 10. Project Cost breakdown is as follows:- a. Work package estimate = Summation of activity estimate b. Control account estimate = Summation of work packages estimate c. Project estimate = Summation of Control accounts estimate d. Cost baseline = Project estimate + Contingency reserve e. Cost budget = Cost baseline + Management reserve 11. Management reserve is usually a percentage of the total project cost. The contingency reserve is the expected monetary value (EMV) of the risks.
  • 2. RANGA’S 51 HOT TOPICS TO REMEMBER FOR RISK MANAGEMENT PROFESSIONAL (RMP) EXAM Prepared by Rangarajan Ramaswamy, PMP, PMI-SP, PMI-RMP Page 2 of 5 12. Monte Carlo simulation is used to determine time and cost based on probability distribution. 13. Project Manager holds the Primary responsibility of identifying risk. 14. All the Risks for which PM and team has no control over, management should be involved. 15. The team is more confident and optimistic about the project during the Plan Risk Response process. 16. Meetings should not be required before the approved fallback or contingency plan is implemented. 17. PM should spend most of the time preparing contingency plans. 18. The highest-risk path is the path through the network diagram that has the highest risk score. The activities on this path may not immediately follow each other, as activities do on the critical path. 19. Exploiting an opportunity means increasing its probability. Enhancing an opportunity means increasing its impact. 20. The ultimate outcome of the risk ranking process is that the non-top risks are separated from the top risks, so that the top risks can be moved forward. 21. The risk reserve report keeps a running balance of the remaining reserve, and is used like a checkbook. 22. Path convergence is best described as many activities leading into a central activity. This adds risk to that central activity. 23. Perform qualitative risk analysis is subjective evaluation. 24. Perform quantitative risk analysis is objective evaluation. 25. The team needs to understand the risk tolerance areas for the project to know the acceptable level of risk and, therefore, which risks need to be addressed. 26. Stakeholder risk tolerance is identified during the Plan Risk Management process. 27. When an identified risk arises, it is not necessary to hold a meeting, and the risk response plan does not require review. Of course, since the risk has occurred, it was not avoided. 28. It is the responsibility of risk governance board to ensure the project is following the standard policies during all processes. 29. Risk management "metrics" are used to measure how the project risk management team is performing against the plan. 30. Purpose of risk audit is to determine the effectiveness of risk management team. 31. Project charter and WBS helps prevent re-work, wasted time & effort. 32. While calculating worst case scenarios simply neglect the probability and add the negative impacts. Similarly, for calculating best case scenarios neglect the probability and add the positive impacts.
  • 3. RANGA’S 51 HOT TOPICS TO REMEMBER FOR RISK MANAGEMENT PROFESSIONAL (RMP) EXAM Prepared by Rangarajan Ramaswamy, PMP, PMI-SP, PMI-RMP Page 3 of 5 33. Prompt lists are used to help ensure that all aspects are covered during risk identification. A prompt list categorizes risks into types or areas and is usually specific to a project type and an organization’s function (e.g. legal, commercial, technical, design, construction, testing etc.) 34. Many workarounds on a project indicate that there was a lack of adequate project planning and the project is likely in trouble. 35. Work Performance Data is raw data such as physical progress, start finish dates. Work Performance Information is analysis of performance data such as change requests, forecasted estimates. Work Performance Report is physical or electronic representation of Work Performance Information such as status reports, memos, notes, dashboards. 36. Contingency reserves are associated with the “known-unknowns,” which may be estimated to account for the unknown amount of rework. 37. List of formulae to be remembered :- a. No. of communication channels N = n(n-1)/2 (where n is no of stakeholders) b. Duration or cost for triangular distribution E= (O + M + P)/3 c. Duration or cost for Beta distribution (traditional PERT) E= (O + 4M + P)/6 d. CV = EV - AC e. SV = EV - PV f. CPI = EV/AC g. SPI = EV/PV h. EAC forecast for work performed at the budgeted rate: EAC = AC + (BAC – EV) i. EAC forecast for work performed at the present rate CPI : EAC = BAC / CPI j. EAC forecast for ETC work considering both SPI and CPI factors: EAC = AC + [(BAC – EV) / (CPI X SPI)] k. TCPI based on the BAC: (BAC – EV) / (BAC – AC) l. TCPI based on the EAC: (BAC – EV) / (EAC – AC). m. In short TCPI = work remaining/funds remaining n. Variance at completion VAC = BAC – EAC o. Activity standard deviation is (P-O)/6 p. Activity variance is square of standard deviation = [(P-O)/6]2 38. Projects with TCPI > 1 is harder to complete and TCPI < 1 is easier to complete. 39. CPI>1(Under Budget) ,CPI=1(At budget) , CPI<1 (Over Budget) 40. SPI>1(Ahead of plan) , SPI=1(As planned) , SPI<1 (Behind Plan) 41. In repetitive processes, the control limits are generally set at ±3 sigma around a process mean that has been set at 0 sigma. A process is considered out of control when: (1) a data point exceeds a control limit; (2) seven consecutive plot points are above the mean; or (3) seven consecutive plot points are below the mean. 42. Non-critical risks are maintained in Watchlist and revisited periodically (mostly during execution and M&C). 43. Expectancy Theory - Employees who believe that their efforts will lead to effective performance and who expect to be rewarded for their accomplishments will remain productive as rewards meet their expectations.
  • 4. RANGA’S 51 HOT TOPICS TO REMEMBER FOR RISK MANAGEMENT PROFESSIONAL (RMP) EXAM Prepared by Rangarajan Ramaswamy, PMP, PMI-SP, PMI-RMP Page 4 of 5 44. Perquisites (Perks) - Some employees receive special rewards, such as assigned parking spaces, corner offices, and executive dining. 45. Fringe Benefits- These are the "standard" benefits formally given to all employees, such as education benefits, insurance, profit sharing etc. 46. McGregor's Theory of X and Y– a. Theory X- Managers who accept this theory believe that people need to be watched every minute. They believe employees are incapable, avoid responsibility, and avoid work whenever possible. b. Theory Y- Managers who accept this theory believe that people are willing to work without supervision, and want to achieve. They believe employees can direct their own efforts. 47. Maslow's Hierarchy of Needs – represents a pyramid that shows how people are motivated and states that one cannot ascend to the next top level until the levels below are fulfilled. Top level: Self-actualization – Self-fulfillment, growth, learning Esteem: - Accomplishment, respect, attention, appreciation Social - Love, affection, approval, friends, association Safety – Security, stability, freedom from harm Base level: Physiological – Need for air, water, food, housing, clothing 48. David McClelland's Theory of Needs (or Acquired Needs Theory) states that a person falling into one category would be managed differently than a person falling into another category. The categories are:- a. Achievement - These people should be given projects that are challenging but are reachable. (Recognition) b. Affiliation - These people work best when cooperating with others. They seek approval rather than recognition. c. Power - People whose need for power is socially oriented, these people like to organize and influence others. 49. Herzberg's Theory deals with hygiene factors and motivating agents. Poor hygiene factors may demotivate, but improving them, under most circumstances, will not improve motivation. a. Examples of hygiene factors are: i. Working conditions ii. Salary iii. Personal life iv. Relationships at work v. Security vi. Status b. Motivating Agents What motivates people is the work itself, including such things as: i. Responsibility ii. Self-actualization iii. Professional growth iv. Recognition 50. Neuro-linguistic programming (NLP) is an approach to communication, personal development, and psychotherapy. The first stage being the act of establishing and maintaining rapport between the practitioner and the client which is achieved through pacing and leading the verbal (e.g., sensory
  • 5. RANGA’S 51 HOT TOPICS TO REMEMBER FOR RISK MANAGEMENT PROFESSIONAL (RMP) EXAM Prepared by Rangarajan Ramaswamy, PMP, PMI-SP, PMI-RMP Page 5 of 5 predicates and keywords) and non-verbal behavior (e.g., matching and mirroring non-verbal behavior, or responding to eye movements) of the client. 51. Correlation coefficient is a measure that determines the degree to which two variable's movements are associated, giving a value between +1 and −1 inclusive, where 1 is total positive correlation, 0 is no correlation, and −1 is total negative correlation. What to expect in the exam? 1. Around 30% of questions related to above mentioned points. 2. Around 50% of situation based questions (You are the Risk manager of a company etc.) 3. Around 10% of questions related to Monte Carlo simulation. Simulation result will be displayed and asked to calculate project average budget, P50, P80 etc. 4. Around 5% of questions are like what to do if the risks are not identified in the risk register. 5. Remaining 5% of questions related to Probability, confidence and stability level. Questions based on when to use contingency reserve and when to use management reserve. Questions on Risk averse and Risk seeking managers. Questions on different types of simulations MCS and LHS (Monte Carlo sampling and Latin hypercube sampling ) etc. References:- 1. Rita Mulcahy’s Risk Management 2. Rita Mulcahy’s PMP Exam Prep 3. PMBOK 5th Edition 4. Investopedia.com 5. Wikipedia.org xxx---My wishes and good luck for your exam---xxx I would love to receive your feedback and you can reach me through LinkedIn at http://qa.linkedin.com/in/rangarajanramaswamy/