SlideShare a Scribd company logo
1
REPORT
INDUSTRIAL TRAINING
Course number: ME 370
Name of the Project:
Study Steam Circuit across SPD, SFD & PP Department Explore all options, including
assessing right pipe size, to optimize Energy Consumption
Organization: Unilever Bangladesh Ltd
Prepared by:
NASHIYAT FYZA
Student Number: 1110061
GAZI SHEHZAD SHAHWANI
Student number: 1110066
DEPARTMENT OF MECHANICAL ENGINEERING
BANGLADESH UNIVERSITY OG ENGINEERING AND TECHNOLOGY
2
Table of Content:
Content Page
Introduction 03
Industrial Safety 03
Boiler Overview 04
Main Safety Devices of the Boiler 05
Efficiency of Boiler & Steam Distribution System 06
Boiler Steam Distribution Circuit 06
Recommended Velocity of Steam 12
Sample Calculation of Pipe Size 14
Calculated Pipe Size List 17
Thermal Insulation in Steam Line 19
Calculated Thickness of Insulation 21
Calculation of Steam Flow Rate 23
BOQ (Bill of Quantity) Calculation 24
Condensate Recovery 25
Calculation of % Flash Steam Generated 29
Calculation for Flash Gas 31
Types of Trap Used 32
Conclusion 39
Acknowledgement 39
3
Introduction:
This report include an overview of the steam circuit of Unilever Bangladesh Kalurghat
Factory. The Steam Circuit and the Boilers operating in the factory were installed years
ago. The steam pipe size was up to the requirement at that time. But recently the steam
requirement has decreased due to installment of improved technology. There are some
changes in the steam requirement plants, too. Therefore, the present steam distribution
line needs to be redesigned to improve efficiency and reduce thermal loss. This report
includes existing steam circuit, analysis the future requirement, redesign the steam line
and insulation up to that requirement and propose an efficient steam recovery system.
Industrial Safety:
Industrial safety is defined as policies and protections put in place to ensure plant and
factory worker protection from hazards that could cause injury. Safety policies put in
place by the Occupational Safety & Health Administration (OSHA) are examples
of industrial safety policies.
There are some basis safety rule in the factory:
• Gather to the assembly point in case of sudden emergency
• Safety shoe, Hair cap & Apron is needed in the factory premise
• Use pedestrian walkways & Zebra Crossing
• Switch off Phone at NG Substation & Perfume Storage
• Never browse phone while using staircase & always hold the hand rail
• In case of Medical Emergency, ambulance service is provided right to the assembly
point
4
• Never touch any chemical line, tank, steam pipe line etc.
• Smoking is prohibited inside the area
• PPE (Personal Protective Equipment) should be provided in the restricted area
• Loose Dress, watches & rings are not allowed
• Permission must be taken before taking any picture
• Proper use of dustbin/ Trash can
• Visitors’ card should always be displayed
• Put at least one leg on ground while sitting on a chair
• Never put bags/chairs in walkway
Boiler Overview:
There are three boilers working for the steam supply for the factory.
Cochran Thermax III & Thermax IV: Thermax III and Thermax IV use fuel the
produce necessary heat to produce steam. Both of them are Fire Tube Boiler. Wet back
system is introduced in both of the boilers to reduce thermal stress of the boiler main
body. The boilers can operate up to 12 bar pressure. But the operating pressure is
usually kept at 10 bar. The burner is rotary cap type which has a turndown ratio of
4:1.Turndown ratio is an important boiler parameter which is defined as the ratio of
maximum firing rate to the minimum controllable firing rate. Usually diesel is
preferred as fuel of the boiler burner, but gas can also be used as the burner fuel.
Thermax III has a capacity of 12 ton/hr and Thermax IV has a capacity of 11 ton/hr.
Exhaust Gas Boiler (EGB): The exhaust gas boiler uses the exhaust heat of the
generator to produce steam. This boiler works at a pressure of 8 bar and has a capacity
of producing 1.5 ton steam/hr
5
Main Safety Devices of the Boiler (Steam Line):
1. Pressure Safety Valve:
Releases steam to atm when steam pressure exceeds the limit. Two PSV operates.
One at 12.6 bar & other at 12.7 bar. If first one fails, the other starts working.
2. Steam High Pressure Switch: (Electrical device)
This switch triggers when the steam pressure inside the vessel reaches too high a
point (180psig) and triggers the burner to stop firing
3. Steam Excess Pressure Switch:
Same kind of electrical device which works when steam high pressure switch fails
(182 psig)
4. Burner Hinge Proving Switch:
If the burner door opens accidentally, it shuts the boiler down
5. Flame Detector:
Detects the flame color of the pilot burner through photocell and thereby determines
whether the air fuel mixture is in correct proportion or not.
6
6. First Low Water Cut Off:
When the water level in the boiler drops below the Permitted limit (-63mm), 1st
alarm
bells and stops firing
7. Second Water Cut Off:
If previous system fails and water level drops below the lower limit (-76mm), 1st &
2nd alarm bells simultaneously and stops firing automatically
8. Steam Pressure Regulator:
Keeps the steam Pressure at the Operating level (175psig)
Efficiency of Boiler & Steam Distribution System:
• Proper Boiler Design
(Material of Boiler, Type of Burner Used, Proper Boiler Insulation, Amount of scale & films
in the heat transfer surface, Type & quality of fuel, proper AF ratio, efficient steam
generation process)
• Heat Recovery devices used in the system ( i.e. Economizer, Air- preheater)
• Proper steam transmission process in the pipeline including proper insulation
(i.e. losses in the pipeline is low)
• 100% condensate recovery
• Type of condensation ( i.e. film condensation reduces the heat transfer rate, drop wise
condensation increases heat transfer)
Boiler Steam Distribution Circuit of the Factory:
The Steam from the main two boilers are distributed into three department of the factory: Soap
Processing Department (SPD), Soap Finishing Department (SFD) and PP ( Personal Product
Department). The steam is distributed into four header.
7
Fig: Steam Circuit from the main boiler to the Main Headers
Soap Processing Department (SPD) Steam Distribution:
As SPD requires more steam than the two other departments , two steam headers are installed
for this department. This headers are known as SPD header and Still header.
From the SPD six steam line go to the Pan Room, DPU, Evaporator, Jet, Meltout & Bleacher
Plant.
8
Fig: Existing Steam Line Distribution from the SPD header To the Processing Department
This steam lines are designed according to the past steam requirement. But, the future steam
requirement will change as there are some changes in the plant operation. The Pan Room plant
will require 2500 kg/hr of extra steam at 6 bar for Scrapping Operation (Manual Fitting- Prefit &
Fit Operation). 200 kg/hr extra flow at 4 bar for inline fitting will also be needed. The steam line
for inline fitting will also be drawn from the Pan Room line. As a huge amount of steam will be
needed in the pan room section, an individual pan room header is proposed in the project to
increase the dryness of the steam. The DPU and Jet steam requirement will also increase about
500 kg/hr and 200 kg/hr respectively. The bleacher plant will not be needing any steam. But the
Wheel Crutcher from SFD will be installed in the SPD. Which will need 200 kg/hr of steam of
about 4 bar. Therefore, the Wheel Crutcher steam line is drawn from the bleacher line. All the
changed pipe size are tabulated in following section.
9
Fig: Proposed Steam Line Distribution from the SPD header To the Processing Department
according to the Future requirement
Fig: Present Steam Distribution Line in the Still header of SPD
The steam requirement of the Still plant will not be needing any change. Therefore, the steam
line will remain same.
10
Soap Finishing Department (SFD):
The Wheel Crutcher plant from line 4 will be replace to the SPD bleacher department. Other
steam requirement will be the same.
Fig: Present Steam Distribution Line in SFD header
11
Personal Product Department:
Steam from main boiler as well as EGB are supplied to the PP department. There are three
header in the PP department:
1. PP header
2. High pressure header
3. Low pressure header
Fig: Present Steam Distribution Line in the PP department
The chiller line will be needing 2000 kg/hr extra steam supply and a new 5 ton mixer CIP will be
installed in the line.
12
Fig: Steam Distribution Line in the PP department according to the future requirement
Recommended velocity of steam in pipe:
13
Sample Calculation for Pipe size: (Source: Spirax Secro: Pipe Size.pdf )
14
Sample Calculation for Pipe Size:
Sample Calculation from Equation (For Prefit & Fit):
Input Parameter:
Pressure, P=6 bar g
Velocity, v=35 m/s (assuming)
Mass Flow Rate, m= 2500 kg/h
Calculated Parameter:
Specific Volume at 6 bar g=0.315 m3/kg
Volumetric Flow rate=0.21875 kg/s
Diameter= 89.21mm
Sample Calculation from Chart: (For Prefit & Fit Operation)
Input Parameter:
Pressure: 6 bar g
Velocity: 35 m/s (assuming)
Mass Flow Rate: 2500 kg/h
Output Result:
Calculated Pipe Size: 89 mm
Recommender Pipe Size: 100 mm
15
16
Sample Calculation from Spirax Sarco’s app:
( for Pre-fit & Fit Operation)
Input Parameter:
Pressure: 6 bar g
Velocity: 35 m/s (assuming)
Mass Flow Rate: 2500 kg/h
Output Result:
Calculated Pipe Size: 82.8942 mm
Recommender Pipe Size: 100 mm
17
Calculated Pipe Dia Chart:
18
= Pipe dia for new installed plant
= Pipe dia which have to be changed from existing
19
Thermal Insulation in a Steam Pipe:
1. Conserve energy by reducing heat loss
2. Control surface temperatures for personnel
protection and comfort
3. Facilitate temperature control of a process
20
21
Sample Calculation for thickness:
T1=20 deg C
T2=184 deg C
r1=6”=6×0.0254m= 0.1524m
k= 0.033
N=length of the cylinder
Q/N= Heat loss per unit length of pipe=80 W/m (assumed)
So,
80= 2π×0,033× (184-20)/ ln ((0.1524+t)/0.1524)
t = 80.72 mm
Calculated Thickness of Insulation:
Taking Rock Wool as the insulating Material, Heat loss per length as 80 W/m and
Operating temperature as 184 degree:
22
Insulation Calculation from Table:
To avoid heat loss and reduced efficiency pipe work in heating systems should always be
insulated. Very hot systems, like hot water and steam systems should also be insulated to avoid
potential personal injuries.
The table below indicates recommended insulation thickness.
based on insulation with thermal resistivity in the range 4 - 4.6 ft2
hr o
F/ Btu in
(typical for mineral wool at room temperature)
Source: http://www.engineeringtoolbox.com/pipes-insulation-thickness-d_16.html
23
Calculation of Flow rate in Universal Mixture 1 ( Due to absence of Flow
meter):
24
BOQ Calculation:
Requirement Size/Quantity
For Steam line:
Pipe 5m (65mm)
PRV 10 bar to 8 bar
Pressure Gauge Quantity: 2
Globe Valve Quantity: 2
Pipe 38m (80 mm)
Bend 5, L type
1, T type
25
For Condensate line:
Float type Trap Quantity: 2
Pipe 30m (25mm)
15m (15mm)
Bend 10, L type
5. T type
Globe Valve Quantity: 4
What is Condensate Recovery?
If 1 t/h of steam is supplied to equipment for a heating process, then the same amount of
condensate (1 t/h) needs to be discharged from the equipment. Condensate recovery is a process
to reuse the water and sensible heat contained in the discharged condensate. Recovering
condensate instead of throwing it away can lead to significant savings of energy, chemical
treatment and make-up water.
26
Condensate Recovery: Vented System
Steam trap inlet pressure or a condensate pump is used to return condensate to an open-to-
atmosphere.
The maximum recovery temperature of condensate is some value less than 100°C
Larger amount of energy is lost when condensate flashes to atmosphere
Formation of vapor clouds can also have a negative impact on a plant’s work environment
Configuration is much simpler, typically require a much lower initial investment
Piping can be sized like water piping once condensate and flash steam have been separated
Use: boiler make-up water, pre-heat, Water for cleaning or other hot water applications.
27
Condensate Recovery: Pressurized System
Recovered condensate is maintained above atmospheric pressure throughout the recovery
process
Condensate can be recovered at much higher temperatures. For example 184°C with steam at 10
barg.
A specialized valve must be installed to regulate the release of flash steam to atmosphere
Since flash steam is not vented to atmosphere, a greater amount of water can be recovered and
reused
Condensate transport piping must be sized for two-phase flow of steam and condensate
The absence of vapor clouds can also considerably improve a plant’s work environment
Use: direct feed to boiler, and Flash Steam Recovery Applications
28
Condensate can be reused in many different ways
As heated feedwater, by sending hot condensate back to the boiler’s deaerator
As pre-heat, for any applicable heating system
As steam, by reusing flash steam
As hot water, for cleaning equipment or other cleaning applications
The Benefits of Condensate Recovery
Reduced Fuel Costs
Lower Water-related Expenses
Positive Impact on Safety and the Environment
29
Calculating the % Flash Steam Generated
The % of flash steam generated (flash steam ratio) can be calculated from:
where:
• hf1 = Specific Enthalpy of Saturated Water at Inlet*
• hf2 = Specific Enthalpy of Saturated Water at Outlet
• hfg2 = Latent Heat of Saturated Steam at Outlet
What to Do With Flash Steam?
30
Method of using Flash Gas
A Flash steam vent condenser is incorporated in the system to recover the flash steam by using
an external heat exchanger.
The vent condenser (heat exchanger) will consume the flash steam by heating air, water or some
other process fluids.
Method of using Flash: Heating air is another application for a vent condenser:
31
Calculation for use of Flash Gas:
Example: Use of Flash Gas:
NEW CHILLER operates at 8 bar pressure with a steam flow rate of 2000kg/hr.
Flash Gas produced from Condensate of New Chiller can partially meet the demand of 5 Ton
Mixture & Inline Fitting.
5 Ton Mixture requires 800 kg/hr at a pressure of 2bar. When the condensate from NEW
CHILLER flows through steam trap & expands through pressure drop to 2 bar, 10% flash steam
if produced. That means we get steam of 200 kg/hr at 2 bar, which will meet the at least 25%
demand of 5ton mixture.
32
Inline Fitting requires 200kg/hr steam at a pressure of 4 bar. Flashing the NEW CHILLER
condensate at 4 bar would produce 130kg/hr ( 6% of 2200kg/hr) which will meet 65% demand of
Inline Fittings.
In the same way, demand of line 4 can be partially met by flash steam produced by line 1 & line
2.
Two Types of Thermodynamic Steam Trap
Operating Mechanism of Thermodynamic Disc Traps
Situation 1: From the Open to the Closed Position (Thermodynamic Explanation)
When in the open position, there are two main forces that act on the disc valve: steam in the
pressure chamber on top of the disc, and steam racing across the underside of the disc.
This steam acting to open and close the valve is known as Control Steam.
33
When steam rapidly flows under the valve disc, the pressure under the disc decreases. The valve
disc is then "pushed" onto the valve seat because of the greater pressure within the chamber. This
closes the valve
Situation 1: From the Open to the Closed Position (Thermodynamic Explanation)
Situation 2: From the Closed to the Open Position (Thermodynamic Explanation)
Radiant and other heat losses cause a decrease in the pressure within the chamber, which
eventually causes the disc to lift off its seat, discharging condensate
34
Balanced Pressure Thermostatic Steam Trap
The operating element is a capsule containing a
special liquid and water mixture with a boiling
point below that of water
In the cold conditions the capsule is relaxed, the
valve is off its seat and is wide open, allowing
unrestricted removal of air
As condensate passes through the balanced
pressure steam trap, heat is transferred to the liquid
in the capsule.
The liquid vaporizes before steam reaches the trap
35
The vapor pressure within the capsule causes it to expand and the valve shuts
Heat loss from the trap then cools the water surrounding the capsule, the vapor condenses and
the capsule contracts, opening the valve and releasing condensate until steam approaches again
and the cycle repeats
Bimetallic Thermostatic Steam Traps:
On start-up, the bimetallic element is relaxed and the valve is open. Cooled condensate, plus air,
is immediately discharged.
Hot condensate flowing through the trap heats the bimetallic element causing it to pull the valve
towards the seat.
As the hot condensate is discharged and approaches steam saturation temperature the bimetallic
element closes the valve.
36
Liquid expansion steam trap
It can be seen from Figure 11.2.2 that when the pressure is at pressure P1, condensate would
have to cool by only a small amount ( T1), and trapping would be acceptable
If pressure is increased to P2 then condensate has to cool more ( T2) to pass through the steam
trap
37
Ball float steam trap
Condensate reaching the trap will cause the ball float to rise, lifting the valve off its seat and
releasing condensate the valve is always flooded and neither steam nor air will pass through it.
The automatic air vent uses the same balanced pressure capsule element as a thermostatic steam
trap.
The Float and Thermostatic Steam Trap
38
Inverted bucket steam trap:
In (i) the bucket hangs down, pulling the valve off its seat. Condensate flows under the bottom of
the bucket filling the body and flowing away through the outlet
In (ii) the arrival of steam causes the bucket to become buoyant, it then rises and shuts the outlet
In (iii) the trap remains shut until the steam in the bucket has condensed or bubbled through the
vent hole to the top of the trap body.
39
Conclusion:
It can be concluded that all modern equipment and hi-tech machineries are available in Unilever.
It has been keeping up its position among the renowned companies for years. So, it was a great
opportunity to learn about machineries, production processes and supply chain in this training.
All the steam flowing through the pipelines are saturated steam. So, the property of saturated
steam was considered in the calculation. Though theoretically it was considered that steam
delivers only sensible heat by changing its phase from saturated vapor to saturated liquid, but
practically some degree of cooling takes place below saturation temperature.
The pressure drop in the pipe was considered due to frictional loss. But there may be some
pressure loss due to radiation heat transfer from pipe and hence comes the need for proper
insulation.
Pipes available in the market are of certain specific diameter. So, we cannot use pipe of any
diameter. Hence, pipe diameter chosen for steam circuit, is the next available size of the
calculated value. Again, due to the limitation of the project period, exact measurement of the
required pipe length was not possible for the future requirement. The required pipe size,
insulation, type of steam trap, condensate return piping has been designed, from which we can
easily calculate the BOQ, Bill of Quantity.
Acknowledgement:
The project required a huge amount of data from different departments of the factory. We would
like to thanks the Engineering Department & all the operators of the factory. This training
certainly add a great value to our career. We would like to thanks Unilever Bangladesh Ltd. &
Department of Mechanical Engineering (BUET) for creating such opportunity.

More Related Content

What's hot

Heat exchanger: Shell And Tube Heat Exchanger
Heat exchanger: Shell And Tube Heat ExchangerHeat exchanger: Shell And Tube Heat Exchanger
Heat exchanger: Shell And Tube Heat Exchanger
Akshay Sarita
 
Process calculation condensation
Process calculation  condensationProcess calculation  condensation
Process calculation condensation
Chandran Udumbasseri
 
Fuel and combustion
Fuel and combustionFuel and combustion
Fuel and combustion
Raju Mirdha
 
Boiler efficiency by loss Method
Boiler efficiency by loss MethodBoiler efficiency by loss Method
Boiler efficiency by loss Method
Rajeev Saini
 
Feedstock Purfication in Hydrogen Plants
Feedstock Purfication in Hydrogen PlantsFeedstock Purfication in Hydrogen Plants
Feedstock Purfication in Hydrogen Plants
Gerard B. Hawkins
 
U#3 BOILER CHEMICAL CLEANING.
U#3 BOILER CHEMICAL CLEANING.U#3 BOILER CHEMICAL CLEANING.
U#3 BOILER CHEMICAL CLEANING.
Dilip Kumar
 
POWER PLANT CHEMISTRY
POWER PLANT CHEMISTRYPOWER PLANT CHEMISTRY
POWER PLANT CHEMISTRY
Dilip Kumar
 
Calculation of Turbine Efficiency
Calculation of Turbine EfficiencyCalculation of Turbine Efficiency
Calculation of Turbine Efficiency
Jahanzeb Khan
 
Calculation of an Ammonia Plant Energy Consumption:
Calculation of an Ammonia Plant Energy Consumption:  Calculation of an Ammonia Plant Energy Consumption:
Calculation of an Ammonia Plant Energy Consumption:
Gerard B. Hawkins
 
Boiler calculations
Boiler calculationsBoiler calculations
Boiler calculations
Usman Shahdin
 
Ammonia production from natural gas, haldor topsoe process
Ammonia production from natural gas, haldor topsoe processAmmonia production from natural gas, haldor topsoe process
Ammonia production from natural gas, haldor topsoe process
Gaurav Soni
 
Ammonia plant material balance
Ammonia plant material balanceAmmonia plant material balance
Ammonia plant material balance
Prem Baboo
 
Failure in synthesis converter
Failure in synthesis converterFailure in synthesis converter
Failure in synthesis converter
Prem Baboo
 
Pinch analysis technique to optimize heat exchanger
Pinch analysis technique to optimize heat exchangerPinch analysis technique to optimize heat exchanger
Pinch analysis technique to optimize heat exchanger
K Vivek Varkey
 
Boiler Operation
Boiler OperationBoiler Operation
Boiler Operation
Susovan Sensharma
 
Power Plant Water Treatment
 Power Plant Water Treatment Power Plant Water Treatment
Power Plant Water Treatment
Rama Chandra Reddy
 
Presentation on CFBC Boilers
Presentation on CFBC BoilersPresentation on CFBC Boilers
CONDENSATE RECOVERY SYSTEMS
CONDENSATE RECOVERY SYSTEMSCONDENSATE RECOVERY SYSTEMS
CONDENSATE RECOVERY SYSTEMS
Thermodyne Engineering systems
 
Ethylene Plant Design Considerations
Ethylene Plant Design ConsiderationsEthylene Plant Design Considerations
Ethylene Plant Design Considerations
Gerard B. Hawkins
 
Thermal properties of Petroleum Fractions
Thermal properties of Petroleum FractionsThermal properties of Petroleum Fractions
Thermal properties of Petroleum Fractions
Manikanta Sjs
 

What's hot (20)

Heat exchanger: Shell And Tube Heat Exchanger
Heat exchanger: Shell And Tube Heat ExchangerHeat exchanger: Shell And Tube Heat Exchanger
Heat exchanger: Shell And Tube Heat Exchanger
 
Process calculation condensation
Process calculation  condensationProcess calculation  condensation
Process calculation condensation
 
Fuel and combustion
Fuel and combustionFuel and combustion
Fuel and combustion
 
Boiler efficiency by loss Method
Boiler efficiency by loss MethodBoiler efficiency by loss Method
Boiler efficiency by loss Method
 
Feedstock Purfication in Hydrogen Plants
Feedstock Purfication in Hydrogen PlantsFeedstock Purfication in Hydrogen Plants
Feedstock Purfication in Hydrogen Plants
 
U#3 BOILER CHEMICAL CLEANING.
U#3 BOILER CHEMICAL CLEANING.U#3 BOILER CHEMICAL CLEANING.
U#3 BOILER CHEMICAL CLEANING.
 
POWER PLANT CHEMISTRY
POWER PLANT CHEMISTRYPOWER PLANT CHEMISTRY
POWER PLANT CHEMISTRY
 
Calculation of Turbine Efficiency
Calculation of Turbine EfficiencyCalculation of Turbine Efficiency
Calculation of Turbine Efficiency
 
Calculation of an Ammonia Plant Energy Consumption:
Calculation of an Ammonia Plant Energy Consumption:  Calculation of an Ammonia Plant Energy Consumption:
Calculation of an Ammonia Plant Energy Consumption:
 
Boiler calculations
Boiler calculationsBoiler calculations
Boiler calculations
 
Ammonia production from natural gas, haldor topsoe process
Ammonia production from natural gas, haldor topsoe processAmmonia production from natural gas, haldor topsoe process
Ammonia production from natural gas, haldor topsoe process
 
Ammonia plant material balance
Ammonia plant material balanceAmmonia plant material balance
Ammonia plant material balance
 
Failure in synthesis converter
Failure in synthesis converterFailure in synthesis converter
Failure in synthesis converter
 
Pinch analysis technique to optimize heat exchanger
Pinch analysis technique to optimize heat exchangerPinch analysis technique to optimize heat exchanger
Pinch analysis technique to optimize heat exchanger
 
Boiler Operation
Boiler OperationBoiler Operation
Boiler Operation
 
Power Plant Water Treatment
 Power Plant Water Treatment Power Plant Water Treatment
Power Plant Water Treatment
 
Presentation on CFBC Boilers
Presentation on CFBC BoilersPresentation on CFBC Boilers
Presentation on CFBC Boilers
 
CONDENSATE RECOVERY SYSTEMS
CONDENSATE RECOVERY SYSTEMSCONDENSATE RECOVERY SYSTEMS
CONDENSATE RECOVERY SYSTEMS
 
Ethylene Plant Design Considerations
Ethylene Plant Design ConsiderationsEthylene Plant Design Considerations
Ethylene Plant Design Considerations
 
Thermal properties of Petroleum Fractions
Thermal properties of Petroleum FractionsThermal properties of Petroleum Fractions
Thermal properties of Petroleum Fractions
 

Similar to Report on Industrial Training

thermal power plant PTTP Parichha
thermal power plant PTTP Parichhathermal power plant PTTP Parichha
thermal power plant PTTP Parichha
Gagandeep Maan
 
ammonia&utility operator
ammonia&utility operatorammonia&utility operator
ammonia&utility operator
Veeru Golla Palli
 
ammoniautility operator
ammoniautility operatorammoniautility operator
ammoniautility operator
Veeru Golla Palli
 
Microsoft PowerPoint - DEV of Dual Filling
Microsoft PowerPoint - DEV of Dual FillingMicrosoft PowerPoint - DEV of Dual Filling
Microsoft PowerPoint - DEV of Dual Filling
PRAN-RFL Group
 
Aph operation and emergency handling
Aph operation and emergency handlingAph operation and emergency handling
Aph operation and emergency handling
Parag Agrawal
 
Bhel ppt
Bhel pptBhel ppt
Bhel ppt
S PARVEEN SINGH
 
Sabardairy Training Report
Sabardairy Training ReportSabardairy Training Report
Sabardairy Training Report
NiravDesai66
 
Inplant training report
Inplant training reportInplant training report
Inplant training report
applesam8
 
hindalco power
hindalco powerhindalco power
hindalco power
Archana Nayak
 
Thermal Power Plant
Thermal Power PlantThermal Power Plant
Thermal Power Plant
Manish Kumar
 
Ppt of internship at dccpp
Ppt of internship at dccppPpt of internship at dccpp
Ppt of internship at dccpp
DurgSingh
 
400 bpm dual filling sytem(completed)
400 bpm dual filling sytem(completed)400 bpm dual filling sytem(completed)
400 bpm dual filling sytem(completed)
PRAN-RFL Group
 
sugar mill ss.pptx
sugar mill ss.pptxsugar mill ss.pptx
sugar mill ss.pptx
TANISH SHARMA
 
Presentation On Boiler Analysis
Presentation On Boiler AnalysisPresentation On Boiler Analysis
Presentation On Boiler Analysis
Aditya Bhattacharjee
 
training report
training reporttraining report
training report
Ajay Chauhan
 
Inlet Air Cooling system from Ikeuchi Improve gas Turbine efficiency
Inlet Air Cooling system from Ikeuchi Improve gas Turbine efficiencyInlet Air Cooling system from Ikeuchi Improve gas Turbine efficiency
Inlet Air Cooling system from Ikeuchi Improve gas Turbine efficiency
H.Ikeuchi & Co.,Ltd
 
presentation report on steam boiler
presentation report on steam boilerpresentation report on steam boiler
presentation report on steam boiler
Mosuud jilani lipon
 
Husk based power plant 6 t 32 kg fbc with single stage turbine for finance,...
Husk based power plant 6 t 32 kg fbc with single stage turbine   for finance,...Husk based power plant 6 t 32 kg fbc with single stage turbine   for finance,...
Husk based power plant 6 t 32 kg fbc with single stage turbine for finance,...
Radha Krishna Sahoo
 
Industrial visit to BHEL, Ranipet
Industrial visit to BHEL, RanipetIndustrial visit to BHEL, Ranipet
Industrial visit to BHEL, Ranipet
PritishTayal
 
IRJET- Water Cooling With LPG as Refrigerant for Restaurants
IRJET- Water Cooling With LPG as Refrigerant for RestaurantsIRJET- Water Cooling With LPG as Refrigerant for Restaurants
IRJET- Water Cooling With LPG as Refrigerant for Restaurants
IRJET Journal
 

Similar to Report on Industrial Training (20)

thermal power plant PTTP Parichha
thermal power plant PTTP Parichhathermal power plant PTTP Parichha
thermal power plant PTTP Parichha
 
ammonia&utility operator
ammonia&utility operatorammonia&utility operator
ammonia&utility operator
 
ammoniautility operator
ammoniautility operatorammoniautility operator
ammoniautility operator
 
Microsoft PowerPoint - DEV of Dual Filling
Microsoft PowerPoint - DEV of Dual FillingMicrosoft PowerPoint - DEV of Dual Filling
Microsoft PowerPoint - DEV of Dual Filling
 
Aph operation and emergency handling
Aph operation and emergency handlingAph operation and emergency handling
Aph operation and emergency handling
 
Bhel ppt
Bhel pptBhel ppt
Bhel ppt
 
Sabardairy Training Report
Sabardairy Training ReportSabardairy Training Report
Sabardairy Training Report
 
Inplant training report
Inplant training reportInplant training report
Inplant training report
 
hindalco power
hindalco powerhindalco power
hindalco power
 
Thermal Power Plant
Thermal Power PlantThermal Power Plant
Thermal Power Plant
 
Ppt of internship at dccpp
Ppt of internship at dccppPpt of internship at dccpp
Ppt of internship at dccpp
 
400 bpm dual filling sytem(completed)
400 bpm dual filling sytem(completed)400 bpm dual filling sytem(completed)
400 bpm dual filling sytem(completed)
 
sugar mill ss.pptx
sugar mill ss.pptxsugar mill ss.pptx
sugar mill ss.pptx
 
Presentation On Boiler Analysis
Presentation On Boiler AnalysisPresentation On Boiler Analysis
Presentation On Boiler Analysis
 
training report
training reporttraining report
training report
 
Inlet Air Cooling system from Ikeuchi Improve gas Turbine efficiency
Inlet Air Cooling system from Ikeuchi Improve gas Turbine efficiencyInlet Air Cooling system from Ikeuchi Improve gas Turbine efficiency
Inlet Air Cooling system from Ikeuchi Improve gas Turbine efficiency
 
presentation report on steam boiler
presentation report on steam boilerpresentation report on steam boiler
presentation report on steam boiler
 
Husk based power plant 6 t 32 kg fbc with single stage turbine for finance,...
Husk based power plant 6 t 32 kg fbc with single stage turbine   for finance,...Husk based power plant 6 t 32 kg fbc with single stage turbine   for finance,...
Husk based power plant 6 t 32 kg fbc with single stage turbine for finance,...
 
Industrial visit to BHEL, Ranipet
Industrial visit to BHEL, RanipetIndustrial visit to BHEL, Ranipet
Industrial visit to BHEL, Ranipet
 
IRJET- Water Cooling With LPG as Refrigerant for Restaurants
IRJET- Water Cooling With LPG as Refrigerant for RestaurantsIRJET- Water Cooling With LPG as Refrigerant for Restaurants
IRJET- Water Cooling With LPG as Refrigerant for Restaurants
 

Report on Industrial Training

  • 1. 1 REPORT INDUSTRIAL TRAINING Course number: ME 370 Name of the Project: Study Steam Circuit across SPD, SFD & PP Department Explore all options, including assessing right pipe size, to optimize Energy Consumption Organization: Unilever Bangladesh Ltd Prepared by: NASHIYAT FYZA Student Number: 1110061 GAZI SHEHZAD SHAHWANI Student number: 1110066 DEPARTMENT OF MECHANICAL ENGINEERING BANGLADESH UNIVERSITY OG ENGINEERING AND TECHNOLOGY
  • 2. 2 Table of Content: Content Page Introduction 03 Industrial Safety 03 Boiler Overview 04 Main Safety Devices of the Boiler 05 Efficiency of Boiler & Steam Distribution System 06 Boiler Steam Distribution Circuit 06 Recommended Velocity of Steam 12 Sample Calculation of Pipe Size 14 Calculated Pipe Size List 17 Thermal Insulation in Steam Line 19 Calculated Thickness of Insulation 21 Calculation of Steam Flow Rate 23 BOQ (Bill of Quantity) Calculation 24 Condensate Recovery 25 Calculation of % Flash Steam Generated 29 Calculation for Flash Gas 31 Types of Trap Used 32 Conclusion 39 Acknowledgement 39
  • 3. 3 Introduction: This report include an overview of the steam circuit of Unilever Bangladesh Kalurghat Factory. The Steam Circuit and the Boilers operating in the factory were installed years ago. The steam pipe size was up to the requirement at that time. But recently the steam requirement has decreased due to installment of improved technology. There are some changes in the steam requirement plants, too. Therefore, the present steam distribution line needs to be redesigned to improve efficiency and reduce thermal loss. This report includes existing steam circuit, analysis the future requirement, redesign the steam line and insulation up to that requirement and propose an efficient steam recovery system. Industrial Safety: Industrial safety is defined as policies and protections put in place to ensure plant and factory worker protection from hazards that could cause injury. Safety policies put in place by the Occupational Safety & Health Administration (OSHA) are examples of industrial safety policies. There are some basis safety rule in the factory: • Gather to the assembly point in case of sudden emergency • Safety shoe, Hair cap & Apron is needed in the factory premise • Use pedestrian walkways & Zebra Crossing • Switch off Phone at NG Substation & Perfume Storage • Never browse phone while using staircase & always hold the hand rail • In case of Medical Emergency, ambulance service is provided right to the assembly point
  • 4. 4 • Never touch any chemical line, tank, steam pipe line etc. • Smoking is prohibited inside the area • PPE (Personal Protective Equipment) should be provided in the restricted area • Loose Dress, watches & rings are not allowed • Permission must be taken before taking any picture • Proper use of dustbin/ Trash can • Visitors’ card should always be displayed • Put at least one leg on ground while sitting on a chair • Never put bags/chairs in walkway Boiler Overview: There are three boilers working for the steam supply for the factory. Cochran Thermax III & Thermax IV: Thermax III and Thermax IV use fuel the produce necessary heat to produce steam. Both of them are Fire Tube Boiler. Wet back system is introduced in both of the boilers to reduce thermal stress of the boiler main body. The boilers can operate up to 12 bar pressure. But the operating pressure is usually kept at 10 bar. The burner is rotary cap type which has a turndown ratio of 4:1.Turndown ratio is an important boiler parameter which is defined as the ratio of maximum firing rate to the minimum controllable firing rate. Usually diesel is preferred as fuel of the boiler burner, but gas can also be used as the burner fuel. Thermax III has a capacity of 12 ton/hr and Thermax IV has a capacity of 11 ton/hr. Exhaust Gas Boiler (EGB): The exhaust gas boiler uses the exhaust heat of the generator to produce steam. This boiler works at a pressure of 8 bar and has a capacity of producing 1.5 ton steam/hr
  • 5. 5 Main Safety Devices of the Boiler (Steam Line): 1. Pressure Safety Valve: Releases steam to atm when steam pressure exceeds the limit. Two PSV operates. One at 12.6 bar & other at 12.7 bar. If first one fails, the other starts working. 2. Steam High Pressure Switch: (Electrical device) This switch triggers when the steam pressure inside the vessel reaches too high a point (180psig) and triggers the burner to stop firing 3. Steam Excess Pressure Switch: Same kind of electrical device which works when steam high pressure switch fails (182 psig) 4. Burner Hinge Proving Switch: If the burner door opens accidentally, it shuts the boiler down 5. Flame Detector: Detects the flame color of the pilot burner through photocell and thereby determines whether the air fuel mixture is in correct proportion or not.
  • 6. 6 6. First Low Water Cut Off: When the water level in the boiler drops below the Permitted limit (-63mm), 1st alarm bells and stops firing 7. Second Water Cut Off: If previous system fails and water level drops below the lower limit (-76mm), 1st & 2nd alarm bells simultaneously and stops firing automatically 8. Steam Pressure Regulator: Keeps the steam Pressure at the Operating level (175psig) Efficiency of Boiler & Steam Distribution System: • Proper Boiler Design (Material of Boiler, Type of Burner Used, Proper Boiler Insulation, Amount of scale & films in the heat transfer surface, Type & quality of fuel, proper AF ratio, efficient steam generation process) • Heat Recovery devices used in the system ( i.e. Economizer, Air- preheater) • Proper steam transmission process in the pipeline including proper insulation (i.e. losses in the pipeline is low) • 100% condensate recovery • Type of condensation ( i.e. film condensation reduces the heat transfer rate, drop wise condensation increases heat transfer) Boiler Steam Distribution Circuit of the Factory: The Steam from the main two boilers are distributed into three department of the factory: Soap Processing Department (SPD), Soap Finishing Department (SFD) and PP ( Personal Product Department). The steam is distributed into four header.
  • 7. 7 Fig: Steam Circuit from the main boiler to the Main Headers Soap Processing Department (SPD) Steam Distribution: As SPD requires more steam than the two other departments , two steam headers are installed for this department. This headers are known as SPD header and Still header. From the SPD six steam line go to the Pan Room, DPU, Evaporator, Jet, Meltout & Bleacher Plant.
  • 8. 8 Fig: Existing Steam Line Distribution from the SPD header To the Processing Department This steam lines are designed according to the past steam requirement. But, the future steam requirement will change as there are some changes in the plant operation. The Pan Room plant will require 2500 kg/hr of extra steam at 6 bar for Scrapping Operation (Manual Fitting- Prefit & Fit Operation). 200 kg/hr extra flow at 4 bar for inline fitting will also be needed. The steam line for inline fitting will also be drawn from the Pan Room line. As a huge amount of steam will be needed in the pan room section, an individual pan room header is proposed in the project to increase the dryness of the steam. The DPU and Jet steam requirement will also increase about 500 kg/hr and 200 kg/hr respectively. The bleacher plant will not be needing any steam. But the Wheel Crutcher from SFD will be installed in the SPD. Which will need 200 kg/hr of steam of about 4 bar. Therefore, the Wheel Crutcher steam line is drawn from the bleacher line. All the changed pipe size are tabulated in following section.
  • 9. 9 Fig: Proposed Steam Line Distribution from the SPD header To the Processing Department according to the Future requirement Fig: Present Steam Distribution Line in the Still header of SPD The steam requirement of the Still plant will not be needing any change. Therefore, the steam line will remain same.
  • 10. 10 Soap Finishing Department (SFD): The Wheel Crutcher plant from line 4 will be replace to the SPD bleacher department. Other steam requirement will be the same. Fig: Present Steam Distribution Line in SFD header
  • 11. 11 Personal Product Department: Steam from main boiler as well as EGB are supplied to the PP department. There are three header in the PP department: 1. PP header 2. High pressure header 3. Low pressure header Fig: Present Steam Distribution Line in the PP department The chiller line will be needing 2000 kg/hr extra steam supply and a new 5 ton mixer CIP will be installed in the line.
  • 12. 12 Fig: Steam Distribution Line in the PP department according to the future requirement Recommended velocity of steam in pipe:
  • 13. 13 Sample Calculation for Pipe size: (Source: Spirax Secro: Pipe Size.pdf )
  • 14. 14 Sample Calculation for Pipe Size: Sample Calculation from Equation (For Prefit & Fit): Input Parameter: Pressure, P=6 bar g Velocity, v=35 m/s (assuming) Mass Flow Rate, m= 2500 kg/h Calculated Parameter: Specific Volume at 6 bar g=0.315 m3/kg Volumetric Flow rate=0.21875 kg/s Diameter= 89.21mm Sample Calculation from Chart: (For Prefit & Fit Operation) Input Parameter: Pressure: 6 bar g Velocity: 35 m/s (assuming) Mass Flow Rate: 2500 kg/h Output Result: Calculated Pipe Size: 89 mm Recommender Pipe Size: 100 mm
  • 15. 15
  • 16. 16 Sample Calculation from Spirax Sarco’s app: ( for Pre-fit & Fit Operation) Input Parameter: Pressure: 6 bar g Velocity: 35 m/s (assuming) Mass Flow Rate: 2500 kg/h Output Result: Calculated Pipe Size: 82.8942 mm Recommender Pipe Size: 100 mm
  • 18. 18 = Pipe dia for new installed plant = Pipe dia which have to be changed from existing
  • 19. 19 Thermal Insulation in a Steam Pipe: 1. Conserve energy by reducing heat loss 2. Control surface temperatures for personnel protection and comfort 3. Facilitate temperature control of a process
  • 20. 20
  • 21. 21 Sample Calculation for thickness: T1=20 deg C T2=184 deg C r1=6”=6×0.0254m= 0.1524m k= 0.033 N=length of the cylinder Q/N= Heat loss per unit length of pipe=80 W/m (assumed) So, 80= 2π×0,033× (184-20)/ ln ((0.1524+t)/0.1524) t = 80.72 mm Calculated Thickness of Insulation: Taking Rock Wool as the insulating Material, Heat loss per length as 80 W/m and Operating temperature as 184 degree:
  • 22. 22 Insulation Calculation from Table: To avoid heat loss and reduced efficiency pipe work in heating systems should always be insulated. Very hot systems, like hot water and steam systems should also be insulated to avoid potential personal injuries. The table below indicates recommended insulation thickness. based on insulation with thermal resistivity in the range 4 - 4.6 ft2 hr o F/ Btu in (typical for mineral wool at room temperature) Source: http://www.engineeringtoolbox.com/pipes-insulation-thickness-d_16.html
  • 23. 23 Calculation of Flow rate in Universal Mixture 1 ( Due to absence of Flow meter):
  • 24. 24 BOQ Calculation: Requirement Size/Quantity For Steam line: Pipe 5m (65mm) PRV 10 bar to 8 bar Pressure Gauge Quantity: 2 Globe Valve Quantity: 2 Pipe 38m (80 mm) Bend 5, L type 1, T type
  • 25. 25 For Condensate line: Float type Trap Quantity: 2 Pipe 30m (25mm) 15m (15mm) Bend 10, L type 5. T type Globe Valve Quantity: 4 What is Condensate Recovery? If 1 t/h of steam is supplied to equipment for a heating process, then the same amount of condensate (1 t/h) needs to be discharged from the equipment. Condensate recovery is a process to reuse the water and sensible heat contained in the discharged condensate. Recovering condensate instead of throwing it away can lead to significant savings of energy, chemical treatment and make-up water.
  • 26. 26 Condensate Recovery: Vented System Steam trap inlet pressure or a condensate pump is used to return condensate to an open-to- atmosphere. The maximum recovery temperature of condensate is some value less than 100°C Larger amount of energy is lost when condensate flashes to atmosphere Formation of vapor clouds can also have a negative impact on a plant’s work environment Configuration is much simpler, typically require a much lower initial investment Piping can be sized like water piping once condensate and flash steam have been separated Use: boiler make-up water, pre-heat, Water for cleaning or other hot water applications.
  • 27. 27 Condensate Recovery: Pressurized System Recovered condensate is maintained above atmospheric pressure throughout the recovery process Condensate can be recovered at much higher temperatures. For example 184°C with steam at 10 barg. A specialized valve must be installed to regulate the release of flash steam to atmosphere Since flash steam is not vented to atmosphere, a greater amount of water can be recovered and reused Condensate transport piping must be sized for two-phase flow of steam and condensate The absence of vapor clouds can also considerably improve a plant’s work environment Use: direct feed to boiler, and Flash Steam Recovery Applications
  • 28. 28 Condensate can be reused in many different ways As heated feedwater, by sending hot condensate back to the boiler’s deaerator As pre-heat, for any applicable heating system As steam, by reusing flash steam As hot water, for cleaning equipment or other cleaning applications The Benefits of Condensate Recovery Reduced Fuel Costs Lower Water-related Expenses Positive Impact on Safety and the Environment
  • 29. 29 Calculating the % Flash Steam Generated The % of flash steam generated (flash steam ratio) can be calculated from: where: • hf1 = Specific Enthalpy of Saturated Water at Inlet* • hf2 = Specific Enthalpy of Saturated Water at Outlet • hfg2 = Latent Heat of Saturated Steam at Outlet What to Do With Flash Steam?
  • 30. 30 Method of using Flash Gas A Flash steam vent condenser is incorporated in the system to recover the flash steam by using an external heat exchanger. The vent condenser (heat exchanger) will consume the flash steam by heating air, water or some other process fluids. Method of using Flash: Heating air is another application for a vent condenser:
  • 31. 31 Calculation for use of Flash Gas: Example: Use of Flash Gas: NEW CHILLER operates at 8 bar pressure with a steam flow rate of 2000kg/hr. Flash Gas produced from Condensate of New Chiller can partially meet the demand of 5 Ton Mixture & Inline Fitting. 5 Ton Mixture requires 800 kg/hr at a pressure of 2bar. When the condensate from NEW CHILLER flows through steam trap & expands through pressure drop to 2 bar, 10% flash steam if produced. That means we get steam of 200 kg/hr at 2 bar, which will meet the at least 25% demand of 5ton mixture.
  • 32. 32 Inline Fitting requires 200kg/hr steam at a pressure of 4 bar. Flashing the NEW CHILLER condensate at 4 bar would produce 130kg/hr ( 6% of 2200kg/hr) which will meet 65% demand of Inline Fittings. In the same way, demand of line 4 can be partially met by flash steam produced by line 1 & line 2. Two Types of Thermodynamic Steam Trap Operating Mechanism of Thermodynamic Disc Traps Situation 1: From the Open to the Closed Position (Thermodynamic Explanation) When in the open position, there are two main forces that act on the disc valve: steam in the pressure chamber on top of the disc, and steam racing across the underside of the disc. This steam acting to open and close the valve is known as Control Steam.
  • 33. 33 When steam rapidly flows under the valve disc, the pressure under the disc decreases. The valve disc is then "pushed" onto the valve seat because of the greater pressure within the chamber. This closes the valve Situation 1: From the Open to the Closed Position (Thermodynamic Explanation) Situation 2: From the Closed to the Open Position (Thermodynamic Explanation) Radiant and other heat losses cause a decrease in the pressure within the chamber, which eventually causes the disc to lift off its seat, discharging condensate
  • 34. 34 Balanced Pressure Thermostatic Steam Trap The operating element is a capsule containing a special liquid and water mixture with a boiling point below that of water In the cold conditions the capsule is relaxed, the valve is off its seat and is wide open, allowing unrestricted removal of air As condensate passes through the balanced pressure steam trap, heat is transferred to the liquid in the capsule. The liquid vaporizes before steam reaches the trap
  • 35. 35 The vapor pressure within the capsule causes it to expand and the valve shuts Heat loss from the trap then cools the water surrounding the capsule, the vapor condenses and the capsule contracts, opening the valve and releasing condensate until steam approaches again and the cycle repeats Bimetallic Thermostatic Steam Traps: On start-up, the bimetallic element is relaxed and the valve is open. Cooled condensate, plus air, is immediately discharged. Hot condensate flowing through the trap heats the bimetallic element causing it to pull the valve towards the seat. As the hot condensate is discharged and approaches steam saturation temperature the bimetallic element closes the valve.
  • 36. 36 Liquid expansion steam trap It can be seen from Figure 11.2.2 that when the pressure is at pressure P1, condensate would have to cool by only a small amount ( T1), and trapping would be acceptable If pressure is increased to P2 then condensate has to cool more ( T2) to pass through the steam trap
  • 37. 37 Ball float steam trap Condensate reaching the trap will cause the ball float to rise, lifting the valve off its seat and releasing condensate the valve is always flooded and neither steam nor air will pass through it. The automatic air vent uses the same balanced pressure capsule element as a thermostatic steam trap. The Float and Thermostatic Steam Trap
  • 38. 38 Inverted bucket steam trap: In (i) the bucket hangs down, pulling the valve off its seat. Condensate flows under the bottom of the bucket filling the body and flowing away through the outlet In (ii) the arrival of steam causes the bucket to become buoyant, it then rises and shuts the outlet In (iii) the trap remains shut until the steam in the bucket has condensed or bubbled through the vent hole to the top of the trap body.
  • 39. 39 Conclusion: It can be concluded that all modern equipment and hi-tech machineries are available in Unilever. It has been keeping up its position among the renowned companies for years. So, it was a great opportunity to learn about machineries, production processes and supply chain in this training. All the steam flowing through the pipelines are saturated steam. So, the property of saturated steam was considered in the calculation. Though theoretically it was considered that steam delivers only sensible heat by changing its phase from saturated vapor to saturated liquid, but practically some degree of cooling takes place below saturation temperature. The pressure drop in the pipe was considered due to frictional loss. But there may be some pressure loss due to radiation heat transfer from pipe and hence comes the need for proper insulation. Pipes available in the market are of certain specific diameter. So, we cannot use pipe of any diameter. Hence, pipe diameter chosen for steam circuit, is the next available size of the calculated value. Again, due to the limitation of the project period, exact measurement of the required pipe length was not possible for the future requirement. The required pipe size, insulation, type of steam trap, condensate return piping has been designed, from which we can easily calculate the BOQ, Bill of Quantity. Acknowledgement: The project required a huge amount of data from different departments of the factory. We would like to thanks the Engineering Department & all the operators of the factory. This training certainly add a great value to our career. We would like to thanks Unilever Bangladesh Ltd. & Department of Mechanical Engineering (BUET) for creating such opportunity.